This database contains records of each project of the Commander's Emergency Response Program recorded in the Iraq Reconstruction Management System, obtained through Army Corps of Engineers in response to a Freedom of Information Act request. The records are presented in their raw form, with no changes made by The Washington Post. Read additional information about the database here.
Results:
Now showing 50 of 26,204 results, totaling $3.0 billion
| Start Date | Cost | Title | Fund Source | City | Province | Subsector |
|---|---|---|---|---|---|---|
| March 28, 2008 | $152,900 | SONS OF IRAQ MANSURIYAH AL JABEL CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | MANSURIYAT AL JABAL | DIYALA | Protective Measures |
| March 28, 2008 | $92,550 | ZONE SIERRA CRITICAL INFRASTRUCTURE SECURITY SERVICE RENEWAL #1 (PARENT URI: 56321) | U.S. | UMM ASH SHUWAYS | DIYALA | Protective Measures |
| March 28, 2008 | $204,750 | ZONE UNIFORM CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | TALL TAMDAR | DIYALA | Protective Measures |
| March 28, 2008 | $270,600 | ZONE WHISKEY CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | TALL TAMDAR | DIYALA | Protective Measures |
| March 27, 2008 | $20,000 | 4 HUSAYNIYAH AND KARBALA MICRO GRANTS | U.S. | `UTAYJ | BABIL | Econ. & Related Initiatives |
| March 27, 2008 | $23,000 | AL NU'AMIYAH WATER STATION REPAIR | U.S. | AL `AMIRIYAH | BAGHDAD | Water & Sanitation |
| March 27, 2008 | $48,000 | AL ZA'ANTI CANAL PROJECT | U.S. | AL `AMIRIYAH | BAGHDAD | Irrigation |
| March 27, 2008 | $48,000 | AL ZA'ANTI DRAIN CLARIFICATION PROJECT | U.S. | RAZAZA | KARBALA | Irrigation |
| March 27, 2008 | $29,400 | BRIDGE REPAIR DISTRICT 2 | U.S. | AL `AMIRIYAH | BAGHDAD | Transportation |
| March 27, 2008 | $50,000 | BULK FUNDS | U.S. | `ABBAS AL MAHDI | BAGHDAD | Econ. & Related Initiatives |
| March 27, 2008 | $50,000 | BULK FUNDS | U.S. | QAL`AT `ABD AL JASADI | BAGHDAD | Civil Clean-Up |
| March 27, 2008 | $28,000 | BULK FUNDS | U.S. | SHAYKH MUHAMMED | SALAH AD DIN | Econ. & Related Initiatives |
| March 27, 2008 | $8,526 | CLEANING IRIGATION CANNAL | U.S. | `ABBAS AL MAHDI | BAGHDAD | Civil Clean-Up |
| March 27, 2008 | $247,408 | HIT TEACHER'S INSTITUTE RENOVATION | U.S. | HIT | AL ANBAR | Education |
| March 27, 2008 | $48,000 | HITAWEEN CANAL PROJECT | U.S. | AL `AMIRIYAH | BAGHDAD | Irrigation |
| March 27, 2008 | $40,000 | HITAWEEN SUB DRAINAGE CANAL | U.S. | MUHAMMAD AL `ABBAS1 | AL ANBAR | Water & Sanitation |
| March 27, 2008 | $182,900 | JAMILLA SECURITY GAURDS | U.S. | MURADIYAH | BAGHDAD | Protective Measures |
| March 27, 2008 | $50,000 | MICROGRANTS | U.S. | QAL`AT `ABD AL JASADI | BAGHDAD | Civil Clean-Up |
| March 27, 2008 | $49,499 | PROVIDE 10 INDUSTRIAL TRASH DUMPSTER IN SOUTH SINA'EE | U.S. | AL FALLUJAH | AL ANBAR | Water & Sanitation |
| March 27, 2008 | $42,500 | REPAIR OF TWO TEREX CRANES FOR DIYALA ELCTRICAL INDUSTRIES | U.S. | QATUN | DIYALA | Electricity |
| March 27, 2008 | $89,850 | RUBBLE AND DEBRI REMOVAL | U.S. | QAL`AT `ABD AL JASADI | BAGHDAD | Civil Clean-Up |
| March 27, 2008 | $47,000 | ZOBA/AL SHETI BRIDGE RENOVATION | U.S. | AL `AMIRIYAH | BAGHDAD | Transportation |
| March 26, 2008 | $50,000 | 2-237 IN, 1-101 COMMUNITY RECONSTRUCTION | U.S. | SALMAN AL KHALAF | AL ANBAR | Civic Infrastructure Repair |
| March 26, 2008 | $50,000 | 214 BULK CERP 1 | U.S. | ABU `URUQ | DIYALA | Misc. Humanitarian & Recon. |
| March 26, 2008 | $27,600 | AL ABARRA MAYORS OFFICE CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | QARYAT ZUHRAH | DIYALA | Protective Measures |
| March 26, 2008 | $14,200 | AL ABBAS CULVERT REPAIR | U.S. | AL KHITHIR | AL MUTHANNA | Irrigation |
| March 26, 2008 | $50,000 | BULK FUNDS | U.S. | `ABBAS AL MAHDI | BAGHDAD | Econ. & Related Initiatives |
| March 26, 2008 | $5,000 | BULK FUNDS | U.S. | QAL`AT `ABD AL JASADI | BAGHDAD | Econ. & Related Initiatives |
| March 26, 2008 | $15,200 | CLEANING IRIGATION CANNAL | U.S. | `ABBAS AL MAHDI | BAGHDAD | Civil Clean-Up |
| March 26, 2008 | $25,000 | COMPANY LEVEL BULK CONDOLENCE PAYMENT AUTHORITY | U.S. | AL FALLUJAH | AL ANBAR | Condolence Payments |
| March 26, 2008 | $5,000 | DETAINEE PAYMENT AUTHORITY | U.S. | AL FALLUJAH | AL ANBAR | Detainee Payments |
| March 26, 2008 | $47,993 | FALLUJAH JAIL FOOD DELIVERY | U.S. | AL FALLUJAH | AL ANBAR | Law & Governance |
| March 26, 2008 | $68,145 | KHAMASIYAH WATER TOWER RENOVATION | U.S. | JASIM AL `UDWAN | BAGHDAD | Misc. Humanitarian & Recon. |
| March 26, 2008 | $32,850 | OLD NAHER SHAYK SCHOOL CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | AS SADAH | DIYALA | Protective Measures |
| March 26, 2008 | $230,400 | SONS OF IRAQ SPENCER'S CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | ZORBIBANI | AL TAMIM | Protective Measures |
| March 26, 2008 | $23,500 | TAL'AFAR WATER POINT PROJECT ACCESS ROAD PAVING | U.S. | TALAFAR CITY | NINAWA | Transportation |
| March 25, 2008 | $27,900 | ABU FAYAD CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | BUHRIZ | DIYALA | Protective Measures |
| March 25, 2008 | $49,100 | AGRICULTURAL ASSISTANCE FOR CROP DEVELOPMENT - HA | U.S. | AZ ZUBAYR | AL BASRAH | Agriculture |
| March 25, 2008 | $46,150 | AL ALI CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | ABBAS | DIYALA | Protective Measures |
| March 25, 2008 | $58,250 | AL AMIA WATER PURIFICATION STATION | U.S. | MUHAMMAD SALTH | BAGHDAD | Water & Sanitation |
| March 25, 2008 | $71,000 | AL HATAMA RTE GARDEN T59 CRITICAL INFRASTRUCTURE SECURITY SERVICE RENEWAL #2 (PARENT URI 49934) | U.S. | SHAYKH `ABBAS | SALAH AD DIN | Protective Measures |
| March 25, 2008 | $166,950 | AL INTESAR CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | BANI SA`D | DIYALA | Protective Measures |
| March 25, 2008 | $84,000 | AL RABIA WATER PURIFICATION STATION | U.S. | MUHAMMAD SALTH | BAGHDAD | Water & Sanitation |
| March 25, 2008 | $166,950 | AL RASOUL VILLAGE ZONE ROMEO CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | BANI SA`D | DIYALA | Protective Measures |
| March 25, 2008 | $321,949 | ARAB JABAR CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | TALL TAMDAR | DIYALA | Protective Measures |
| March 25, 2008 | $20,000 | BAHBAHANI CANAL CLEANING | U.S. | SUNAYDIQ | BABIL | Misc. Humanitarian & Recon. |
| March 25, 2008 | $184,800 | BAZUL AHMED CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | AMIRIYAH | DIYALA | Protective Measures |
| March 25, 2008 | $78,300 | DUKUYLA CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | JAWAD AL KAZIM | DIYALA | Protective Measures |
| March 25, 2008 | $69,150 | DULIM CRITICAL INFRASTRUCTURE SECURITY SERVICE | U.S. | TALL TAMDAR | DIYALA | Protective Measures |
| March 25, 2008 | $35,750 | DUR AL THUBA SCHOOL ROAD CRITICAL INFRASTRUCTURE SECURITY SERVICE RENEWAL #1 PARENT URI 54166 | U.S. | MIQDADIYA | DIYALA | Protective Measures |
© The Washington Post Company