| Description | Open Date |
|---|---|
| FM-200455634 9/24/04 Simon Urgent !!!! Basement 1) Lights out in (3) classrooms. | |
| FM-200515656 11/21/05 Asbestos Assessment Required. First floor, Auditorium. Repair peeling ceiling plaster. Note: Currently the plaster is falling, this is health/safety concern. The roof may also need to be inspected. Lead & Asbestos Code A - Clear for repairs on 11/28/05. Tidewater - Roger Small/Philp Connolly (RG 11/30/05) | |
| FM-200515657 11/21/05 Asbestos Assessment Required. First floor, Cafeteria Area. Repair peeling ceiling plaster. Note: Currently the plaster is hanging from walls, this is a health/safety concern. This problem was cited by the Health Inspector. Lead & Asbestos Code A - Clear for repairs on 11/28/05. Tidewater - Roger Small/Philp Connolly (RG 11/30/05) | |
| FM-200515841 11/28/05 Exterior, Large Playground Area "Urgent" Repair or Replace metal railing to playground, it has been pulled away from concrete base and is now parallelwiththe groung. Note: This is a serious safety concern. | |
| FM-200515842 11/28/05 Exterior, Large Playground Area "Urgent" Repair or Replace cracked and damaged asphalt. The playground area has cracked, causing chunks of pavement to come up forming several potholes. Note: This is a safety hazard for students and faculty. | |
| FM-200621445 4/18/06 Asbestos Assessment Required. Ground floor, Girls' Restroom. Repair large hole in wall underneath the hand basin. This restroom is frequented by Pre-K and Kindergarden student. Note: This is a entry way for rodents and other pests causing this to be a safety hazard. Asbestos Code A - Clear for repairs on 04/19/06. Tidewater - Shamika Parker (RG 04/20/06) |