Closed Repair Requests: December 2004

See Also: All Closed Repair Requests at Stuart-Hobson Middle School

December 2004 Summary

  • Urgent Requests
    1
    Average Time Elapsed: 8 Days
  • Routine Requests
    5
    Average Time Elapsed: 57 Days
  • Total Requests
    6

Detailed Reports

Urgent Repair Requests Completed in December 2004 (1)
Description Open Date Close Date Time Elapsed
FM-200458776 /04 12/7/04 Stuart- Hobson Boiler Room Boiler #2 need safety valve . November 29, 2004 December 7, 2004 8 days

Routine Repair Requests Completed in December 2004 (5)
Description Open Date Close Date Time Elapsed
FM-200459282 04 12/7/04 Stuart- Hobson Boiler Room Replace modulator on boiler #2 December 7, 2004 December 7, 2004 0 days
FM-200454140 04 12/8/04 Stuart-Hobson Courtyard 1) Change hardware on door from Courtyard to Cafeteria so door will not lock students out. Area cleared on FM-200450997. Poc - Susan Chapin - 202-365-0803 September 9, 2004 December 8, 2004 90 days
FM-200454081 04 12/8/04 Stuart-Hopson Boiler room tunnel Asbestos assesment required. Repair leaking steam supply line in the tunnel.(2") September 9, 2004 December 8, 2004 90 days
FM-200453952 04 12/10/04 Stuart-Hopson Boiler room Repair or replace two(2) leaking tubes in # 1 boiler September 6, 2004 December 10, 2004 95 days
FM-200459554 /04 12/23/04 Stuart- Hobson Boiler Room Repair or replace modutrol motor on Boiler #3. Will not go in highfire. December 13, 2004 December 23, 2004 10 days