Closed Repair Requests: December 2005

See Also: All Closed Repair Requests at Stuart-Hobson Middle School

December 2005 Summary

  • Urgent Requests
    3
    Average Time Elapsed: 461 Days
  • Routine Requests
    6
    Average Time Elapsed: 393.5 Days
  • Total Requests
    9

Detailed Reports

Urgent Repair Requests Completed in December 2005 (3)
Description Open Date Close Date Time Elapsed
FM-200453479 04 12/1/05 Stuart-Hobson Fire Code Violation First floor Panic hardware broken. Asbestos Code A - Clear for repairs on 08/30/04. DCPS Safety - Richard Gibson (RG 08/31/04) August 27, 2004 December 1, 2005 461 days
FM-200453471 04 12/1/05 Stuart-Hobson Fire Code Violation Room 216 Hardware on the door broken. Asbestos Code A - Clear for repairs on 08/30/04. DCPS Safety - Richard Gibson (RG 08/31/04) August 27, 2004 December 1, 2005 461 days
FM-200453465 04 12/1/05 Stuart-Hobson Fire Code Violation Third floor Pentrating opening in the wall. Asbestos Code A - Clear for repairs on 08/30/04. DCPS Safety - Richard Gibson (RG 08/31/04) August 27, 2004 December 1, 2005 461 days

Routine Repair Requests Completed in December 2005 (6)
Description Open Date Close Date Time Elapsed
FM-200340762 /03 12/1/05 Stuart-Hobson Boiler room Unstop all floor drains in the boiler room, November 26, 2003 December 1, 2005 736 days
FM-200453513 04 12/1/05 Stuart-Hobson Fire Code Violation Basement Boiler room area electrical wires exposed. August 27, 2004 December 1, 2005 461 days
FM-200452759 04 12/1/05 Stuart-Hobson Boiler Room Unclog drain in Boiler Room. Drain is causing Boiler Room to have water on floor. August 17, 2004 December 1, 2005 471 days
FM-200447676 04 12/1/05 Stuart-Hobson Second Floor - Girls Lavatory 1) Water leaking from 2nd floor girls bathroom down through the ceiling into the First Floor Bathroom. Asbestos Code A - Clear for repairs on 05/10/04. Horne Engineering - Bipin Nanavaty (RG 05/10/04) May 10, 2004 December 1, 2005 570 days
FM-200515922 05 12/20/05 Stairwell (3) - Lights are out, can not get them to come on. December 1, 2005 December 20, 2005 19 days
FM-200512643 05 12/28/05 Stuart-Hobson Main Office Repair Leaking A/C Unit September 15, 2005 December 28, 2005 104 days