Closed Repair Requests: March 2004

See Also: All Closed Repair Requests at Stuart-Hobson Middle School

March 2004 Summary

  • Urgent Requests
    10
    Average Time Elapsed: 489.2 Days
  • Routine Requests
    17
    Average Time Elapsed: 542 Days
  • Total Requests
    27

Detailed Reports

Urgent Repair Requests Completed in March 2004 (10)
Description Open Date Close Date Time Elapsed
FM-200114490 01 3/17/04 STUART-HOBSON (1) SURVEY ELECTRICAL CAPACITY TO DETERMINE WHETHER THE ROOMS WILL HANDLE THE LOAD. (2) INSTALL NEW WINDOW A/C UNITS IN THE FOLLOWING LOCATIONS.: AUDITORIUM - (4) 28,000 BTU ROOM 201 - (1) 28,000 BTU ROOM 200 - (1) 25,000 BTU ROOM 204 - (1) 25,000 BTU ROOM 205 - (1) 25,000 BTU ROOM 207 - (1) 25,000 BTU TEACHERS LOUNGE (1) 25,000 BTU AUDITORIUM - (6) 28,000 BTU Code A Clear for repair by Leroy Minton, Jr. DCPS Safety 07-31-02 DCPS Safety-Sheila R. Howard 07-31-02 July 2, 2001 March 17, 2004 989 days
FM-200338409 03 3/17/04 Stuart-Hobson First floor Room 105, 106 and 207 Window fell down from top, the window back up it will not stay up. This is consider a safety hazard for the students, also cold coming into room. October 2, 2003 March 17, 2004 167 days
FM-200227460 03 3/17/04 Stuart-Hobson First floor room 102 Hinge that holds door together has been off also door is very hard to close. This is consider an fire code violation. and safety hazard. Asbestos Code A-clear for repair by DCPS on 04/07/03 Charles Buchanan March 21, 2003 March 17, 2004 362 days
FM-200222311 /02 3/17/04 Stuart-Hobson Third floor - room 305 Doors is pulled from the hinges and locked is hard to lock. Considered an safety and fire code violation. Asbestos Code A - Clear for repairs on 12/12/02. Horne Engineering - Bipin Nanavaty (RG 12/13/02) December 10, 2002 March 17, 2004 463 days
FM-200222310 /02 3/17/04 Stuart-Hobson First floor - exit door Screws and brackets off in the door hinges, top of door hinges are hanging down. Considered an safety and fire code violation. Asbestos Code A - Clear for repairs on 12/12/02. Horne Engineering - Bipin Nanavaty (RG 12/13/02) December 10, 2002 March 17, 2004 463 days
FM-200222308 /02 3/17/04 Stuart-Hobson Second floor - room 201 Door is pulled from hinges and hard to close to lock the door. Considered an safety and fire code violation. Asbestos Code A - Clear for repairs on 12/12/02. Horne Engineering - Bipin Nanavaty (RG 12/13/02) December 10, 2002 March 17, 2004 463 days
FM-200218492 02 3/17/04 (Stuart-Hobson) ***Urgent*** Basement Custodian's Office Restroom Replace faulty flush valve. When flushed, the water will not go down and the custodian's need to be able to use this restroom. September 27, 2002 March 17, 2004 537 days
FM-200206493 02 3/17/04 (Stuart-Hobson) 1. Asbestos assessment required. Basement/court yard cafeteria: Drain stopped up and backing up. When it rains court yard floods; as of this date, court yard is still flooded. Asbestos Code A - Clear for repairs on 04/24/02. DCPS Safety - Richard Gibson (04/24/02) April 24, 2002 March 17, 2004 693 days
FM-200203264 02 3/17/04 (Stuart-Hobson) ***Urgent*** First Floor Main Office Repair or replace bad ballast which is causing the light not to function. This light is over the top of the secretarys desk making it hard for her to see. February 21, 2002 March 17, 2004 755 days
FM-200445964 04 3/29/04 Stuart-Hobson Boiler Room URGENT URGENT URGENT!!!!!!!!!! Boiler #1 Replace safety valve, Valve keep popping. School will be without heat if repairs are not made today 3/29/04. boilers 2 and 3 are down March 29, 2004 March 29, 2004 0 days

Routine Repair Requests Completed in March 2004 (17)
Description Open Date Close Date Time Elapsed
FM-200444832 04 3/9/04 (Stuart-Hobson) Playground: Repair or replace chains, and bridge, equipment vandalized. March 4, 2004 March 9, 2004 5 days
FM-200126755 02 3/17/04 (STUART-HOBSON) ***EMERGENCY*** EXTERIOR DOOR/5TH STREET ENTRANCE REAR EXIT DOOR LEADING TO PLAYGROUND--CENTER BAR FELL OUT & DOOR CANNOT BE SECURED. January 4, 2002 March 17, 2004 803 days
FM-200222021 02 3/17/04 Stuart-Hobson 3rd Floor and Lunchroom Check heating units on 3rd floor and lunchroom. The whole 3rd floor is cold and lunchroom. December 4, 2002 March 17, 2004 469 days
FM-200125683 /01 3/17/04 (STUART-HOBSON) OUTSIDE/4TH STREET SIDE OF PLAYGROUND 2 DRAINS STOP UP ON PLAYGROUND WHEN IT RAINS December 18, 2001 March 17, 2004 820 days
FM-200218019 02 3/17/04 Stuart-Hobson Fiber release clean up AMP room 34. Asbestos Assessment Reqd. Basement Room 31 [Book Storage] During a periodic surveillance inspection by EA, a fiber release episode was discovered in room 31. The debris is located under the north radiator beneath damaged pipe insulation. POC: Brian McLaughlin (443)463-6348 Horne Tracking #16093 Asbesstos Code B- Troy Wilcome September 20, 2002 March 17, 2004 544 days
FM-200208745 02 3/17/04 Stuart-Hobson Second (2nd) Floor - Boys' Restroom Sinks in Restroom all three supply lines are cut. Had to cut the cut off valve off due to they are leaking. Asbestos Code A - Clear For repairs on 05/05/03. Horne Engineering - Philp Connolly (RG 05/07/03) May 31, 2002 March 17, 2004 656 days
FM-200206948 02 3/17/04 3rd floor/Roof top entrance: 1. Asbestos assessment required. Entrance to roof needs a trap door replaced; when it rains water falls down on the landing. Asbestos Code A - Clear for repairs on 05/01/02. Horne Engineering - Sheryll James (RG 05/02/02) May 1, 2002 March 17, 2004 686 days
FM-200114791 01 3/17/04 STUART-HOBSON KITCHEN 1) REPAIR ALL GAS APPLIANCES IN KITCHEN,DEFECTIVE POLIT LEAKING GAS.. RED TAGED BY WASHINGTON GAS...!! July 6, 2001 March 17, 2004 985 days
FM-200205462 02 3/17/04 Stuart-Hobson !!! EMERGENCY !!! Second (2nd) Floor - Boys Restroom Back-ups and the valves have been cut off. April 4, 2002 March 17, 2004 713 days
FM-200442848 04 3/17/04 Stuart-Hobson Emergency First floor room 102, 104 and 106 Close and repair windows in the above rooms. Rooms are very cold. January 16, 2004 March 17, 2004 61 days
FM-200203477 02 3/17/04 (Stuart-Hobson) ***Emergency*** 2nd Floor Boys Lavatory Urinal drains are backing up and emitting a very bad odor. February 26, 2002 March 17, 2004 750 days
FM-200336567 03 3/17/04 Stuart-Hobson Kitchen - Disconnect Utilities on Kitchen Equipment 1) Deep Fryer and Confection Oven. August 29, 2003 March 17, 2004 201 days
FM-200333804 03 3/17/04 (Stuart-Hobson) Kitchen/Cafeteria: Pilot is not lighting on the bottom deck oven; gas smell present. Repairmen arrived, however, they did not service the right oven. (Deborah Davis/07/29/2003) July 25, 2003 March 17, 2004 236 days
FM-200329886 03 3/17/04 Stuart-Hobson 1) In accordance with the grass cutting contract for the summer of 2003 to include grass cutting and edging. May 9, 2003 March 17, 2004 313 days
FM-200203327 02 3/17/04 STUART-HOBSON BASEMENT, F IRST (1ST) AND THIRD (3RD) FLOOR. 1. ASBESTOS ASSESSMENT REQUIRED. 2. ATTACH ARE THE (SCOPE OF WORK) - SURVEY THIS AREA VERIZON CSI WILL EXTEND TWO (2) ISDN MULTI-POINT CIRCUITS AND SPID FOUR (4) ISDN TELEPHONE. INSTALL ADN PROVIDE 400" CAT 5C FOR THREE (3) WORKSTATIONS. JACKS FOR VOICE ONLY, CSI MATERIAL AND LABOR. VERIZON, INC./ KEVIN HANCOCK-703-741-1433 TRACKING #194935 CODE A-CLEAR FOR REPAIR BYB HORRNE ENGINEER ( STEPHEN CALDWELL ) ON 2/04/02 (CEB) February 22, 2002 March 17, 2004 754 days
FM-200224377 03 3/17/04 Stuart-Hobson Basement hall Over top of lockers side of wall plaster is peeling and falling off, please plaster and paint it. Lead & Asbestos Code A - Clear For Repairs On 01/23/03. Horne Engineering - Edward Rodriguez (RG 01/24/03) January 22, 2003 March 17, 2004 420 days
FM-200127105 02 3/17/04 (STUART-HOBSON) ***EMERGENCY*** BASEMENT KITCHEN CONVECTION OVEN NEEDS TO HAVE PILOT LIGHT LIT--LIGHT WENT OUT AND WHEN LIT DOES NOT STAY LIT. January 9, 2002 March 17, 2004 798 days