Closed Repair Requests: July 2004

See Also: All Closed Repair Requests at Stuart-Hobson Middle School

July 2004 Summary

  • Urgent Requests
    1
    Average Time Elapsed: 109 Days
  • Routine Requests
    2
    Average Time Elapsed: 87.5 Days
  • Total Requests
    3

Detailed Reports

Urgent Repair Requests Completed in July 2004 (1)
Description Open Date Close Date Time Elapsed
FM-200445489 04 7/4/04 Stuart-Hobson URGENT Basement kitchen Compact sink has an crack on side of sink. Water leaks down on the floor a lot. Cafeteria worker almost slipped up due to water being all over the floor. This needs immediate attention. March 17, 2004 July 4, 2004 109 days

Routine Repair Requests Completed in July 2004 (2)
Description Open Date Close Date Time Elapsed
FM-200447550 04 7/7/04 Stuart-Hobson Third floor boys bathroom Two (2) commodes need flush valves due to they will not flush at all. These need immediate attention because students have to use the restroom. May 5, 2004 July 7, 2004 63 days
FM-200445487 04 7/7/04 Stuart-Hobson Second floor girls bathroom (7) Commodes do not work, they need flushs, they leak and drip down thru ceiling on first floor bathroom ceiling. We have only three commodes working. Also have blind teacher that have to use the bathroom. This considered an health hazard. We had to cut all commdoes off. March 17, 2004 July 7, 2004 112 days