Closed Repair Requests: January 2005

See Also: All Closed Repair Requests at Woodson High School

January 2005 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    5
    Average Time Elapsed: 39.2 Days
  • Total Requests
    5

Detailed Reports

Routine Repair Requests Completed in January 2005 (5)
Description Open Date Close Date Time Elapsed
FM-200500006 05 1/3/05 Woodson, H.D. Boiler room Replace leaking tubes in # 1 boiler . January 3, 2005 January 3, 2005 0 days
FM-200456570 04 1/4/05 Woodson Boiler Room Remove blower from burner motor from Boiler #1 and #2 October 7, 2004 January 4, 2005 89 days
FM-200456515 04 1/4/05 (Woodson, H.D.) !!!EMERGENCY!!! Outside Plaza: Welder needed to weld loose grate that a child has fallen through. October 5, 2004 January 4, 2005 91 days
FM-200459852 /04 1/5/05 Woodson, HD Emergency Ground floor kitchen The sink is stopped-up. December 20, 2004 January 5, 2005 16 days
FM-200500707 05 1/24/05 Woodson Room #601 Repair or replace busted line on heating unit and room #601. January 24, 2005 January 24, 2005 0 days