Closed Repair Requests: May 2006

See Also: All Closed Repair Requests at Woodson High School

May 2006 Summary

  • Urgent Requests
    7
    Average Time Elapsed: 342.4 Days
  • Routine Requests
    11
    Average Time Elapsed: 223.3 Days
  • Total Requests
    18

Detailed Reports

Urgent Repair Requests Completed in May 2006 (7)
Description Open Date Close Date Time Elapsed
FM-200621405 06 5/4/06 Woodson ROTC/Computer Lab Asbestos assessment required Repair or replace rupture line in ROTC/Computer Lab Line can not be isolated Urgent !!!!! Asbestos Code A - Clear for repairs on 04/18/06. Tidewater - Tony Marcolin (RG 04/18/06) April 18, 2006 May 4, 2006 16 days
FM-200620726 06 5/12/06 Woodson Room #305 Asbestos assessment required on line Repair leak in ceiling of room #305, ceiling tile has fallen in this classroom. Urgent !!!! Asbestos Code B on 04/06/06. Tidewater - Shamika Parker (RG) Asbestos abated on 04/21/06 by Goel Contractors per Ricardo Eley comfirmed.(RG 04/26/06) April 3, 2006 May 12, 2006 39 days
FM-200459763 /04 5/19/06 Woodson, HD Ground floor Custodian office ceiling need plastering and painting due to pipe busting need soon. Asbestos Code A - Clear for repairs on 12/17/04. DCPS Safety - Richard Gibson (RG) December 17, 2004 May 19, 2006 518 days
FM-200501794 05 5/19/06 Woodson, H.D. ( High School Bathroom Survey Report ) Seventh Floor Boys Bathroom - Needs Painting Sixth Floor Boys Restroom - Touch Up Ceiling Paint Second Floor Boys - Touch Up Wall Paint First Floor Teachers Restroom - Repair Ceiling First Floor Female Staff - Touch Up Painting Asbestos Code A - Clear for repairs on 02/22/05. DCPS Safety - Richard Gibson (RG) February 20, 2005 May 19, 2006 453 days
FM-200506513 05 5/19/06 (Woodson, H.D.) "Urgent" Asbestos Assessment Required. Auditorium. Scrape and paint the ceiling, the paint is constantly falling in the auditorium. Also repair lighting. Note: This work was suppose to be completed last month. Lead & Asbestos Code A - Clear for repairs on 06/09/05. Tidewater - Sheryll James (RG 06/27/05) June 8, 2005 May 19, 2006 345 days
FM-200623034 06 5/19/06 Woodson Chiller Check voltage to line to chiller. Urgent !!!! May 19, 2006 May 19, 2006 0 days
FM-200333885 03 5/19/06 (Woodson) !!!VERY URGENT!!! Asbestos Assessment Required. 4th Floor/Girls restroom: Repair or replace ceiling, plaster falling on the floor in large pieces. Code A-clear for repair by Safety Office on 7/29/03 Charles Buchanan July 28, 2003 May 19, 2006 1,026 days

Routine Repair Requests Completed in May 2006 (11)
Description Open Date Close Date Time Elapsed
FM-200622174 06 5/4/06 Basement- Gym Area (lobby door leading to the parking lot) Door lock is broken; they are able to secure the building, but it needs to be repaired as soon as possible. May 3, 2006 May 4, 2006 1 day
FM-200622213 06 5/6/06 1st Floor- Wellness Center Light fixture is broken; there is no light. May 4, 2006 May 6, 2006 2 days
FM-200511677 05 5/9/06 Woodson Boiler Room Check domestic hot water in boiler room. Boiler Room floor flooded August 31, 2005 May 9, 2006 251 days
FM-200621115 06 5/9/06 Woodson Boiler room Replace domestic hot waer heater #1, short cycling on fuse system. No hot water in Building. April 7, 2006 May 9, 2006 32 days
FM-200621116 06 5/9/06 Woodson Boiler room Repair or replace circulating pump on domestic hot waer heater #2 No hot water in Building. April 7, 2006 May 9, 2006 32 days
FM-200332611 03 5/9/06 H.D.Woodson Boilerroom R/R leaking DHW circulating pump for the # 2 DHW heater June 27, 2003 May 9, 2006 1,047 days
FM-200450360 04 5/9/06 Woodson Boiler Room Repair or replace busted domestic hot water heater line in Boiler room, Pipe is approx. 1 3/4" July 16, 2004 May 9, 2006 662 days
FM-200515592 /05 5/9/06 Woodson Boiler room Replace 1-1/4" ruptured line on the domestic hot water line in the boiler room. November 18, 2005 May 9, 2006 172 days
FM-200621166 06 5/12/06 Woodson Boiler Room Basement - Boiler Room - Repair or replace 8 bolt butterly valves ( 6") with blank cover to prevent water leaks in boiler room. April 11, 2006 May 12, 2006 31 days
FM-200622601 06 5/12/06 Woodson Roof Repair or replace 1" valve and 1" copper pipe to cooling tower May 12, 2006 May 12, 2006 0 days
FM-200513320 05 5/15/06 Woodson Boiler Room Boiler #1 and #2 Retubes October 1, 2005 May 15, 2006 226 days