Closed Repair Requests: August 2001

See Also: All Closed Repair Requests at Woodson High School

August 2001 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    6
    Average Time Elapsed: 4.7 Days
  • Total Requests
    6

Detailed Reports

Routine Repair Requests Completed in August 2001 (6)
Description Open Date Close Date Time Elapsed
FM-200118056 01 8/24/01 WOODSON, H.D. PARKING LOT - EXTERIOR OF BUILDING OUTSIDE DRAIN NEEDS TO BE SNAKED OUT - FOR TEACHERS CONFERENCE. ISOLATE EMERGENCY!!! August 21, 2001 August 24, 2001 3 days
FM-200118043 01 8/24/01 WOODSON, H.D. KITCHEN DRAINS CLOGGED, GARBAGE DISPOSAL CLOGGED. NEED IMMEDICATE ATTENTION. ISOLATE EMERGENCY!!! August 21, 2001 August 24, 2001 3 days
FM-200117940 01 8/24/01 WOODSON SHS KITCHEN 1) DRAIN STOPPED UP IN KITCHEN BY GREASE TRAP. August 21, 2001 August 24, 2001 3 days
FM-200118206 01 8/29/01 (WOODSON, H.D.) !!!!EMERGENCY!!!! GROUND FLOOR/WELLNESS CENTER CLINIC: COMMODE STOPPED UP. THIS IS AN EMERGENCY, AS THE ORIENTATION FOR THE NEW TEACHERS IS IN SESSION TODAY. PENETRATIONS !! August 23, 2001 August 29, 2001 6 days
FM-200118316 01 8/30/01 WOODSON SHS KITCHEN 1) DRAIN STOPPED UP IN KITCHEN BY GREASE TRAP. August 24, 2001 August 30, 2001 6 days
FM-200118204 01 8/30/01 (WOODSON, H.D.) !!!!EMERGENCY!!!! GROUND FLOOR/KITCHEN: BUSTED PIPE UNDER KITCHEN SINK, FLOODING THE KITCHEN. SHUT-OFF VALVES ARE FROZEN; UNABLE TO SHUT WATER OFF. (ORIENTATION IS IN SESSION TODAY FOR THE NEW TEACHERS) August 23, 2001 August 30, 2001 7 days