Closed Repair Requests: August 2002

See Also: All Closed Repair Requests at Woodson High School

August 2002 Summary

  • Urgent Requests
    3
    Average Time Elapsed: 11 Days
  • Routine Requests
    14
    Average Time Elapsed: 14.9 Days
  • Total Requests
    17

Detailed Reports

Urgent Repair Requests Completed in August 2002 (3)
Description Open Date Close Date Time Elapsed
FM-200214278 02 8/20/02 Woodson,H.D. ****Urgent**** 5th Floor Room 511 Replace existing flush valve that is leaking in the restroom. August 13, 2002 August 20, 2002 7 days
FM-200213758 02 8/20/02 Woodson,H.D. ****Urgent**** Ground Floor Kitchen Drains in the kitchen are backing up--these lines need to be jetted out. August 7, 2002 August 20, 2002 13 days
FM-200214304 02 8/27/02 Woodson,H.D. ****Urgent**** Ground Floor Kitchen 1. Repair broken line on steamer; and 2. Unstop clogged kitchen drains--water is flooding across the kitchen floor. August 14, 2002 August 27, 2002 13 days

Routine Repair Requests Completed in August 2002 (14)
Description Open Date Close Date Time Elapsed
FM-200213252 02 8/2/02 Woodson,H.D. ****Emergency**** 7th Floor Room 701 Repair busted line inside classroom. No penetration! July 29, 2002 August 2, 2002 4 days
FM-200213074 02 8/5/02 Woodson 701- Math Classroom Remove (1) copper cooling and heating coil from the unit vent and acid flush. Supply water is not circulating through-out the coil causing a restriction for cooling and heating this room or replace pneumatic valve. Asbestos assessment already performed on this unit from prior repairs by the steamfitters. (7-24-02) July 26, 2002 August 5, 2002 10 days
FM-200213436 02 8/9/02 Emergency Woodson,H.D. Need Doors Painted for Superintendent Conference. 1) 55 th Street Side - Double Doors. ( Exterior) 2) 55 th Street Side - Cafeteria Doors ( Interior) 6 Doors (Interior) 2 Single ,3 Double Doors 3) Art Room - 4 (Interior) Doors 4) 10 Doors ( Interior) by elevator. 5) Snack Hall - 4 Double Doors ,3 Single Doors. 6) Hospitality Room - 2 Double Doors ( Interior) . 7) Lobby Area 4 (Interior) Doors, 7 Single Doors ( Interior), 4 ( Exterior ) Lobby Doors. 8) Behind Stage - 1 Double Door, 5 Single ( Interior) and 2 Double Doors. 9) Music Hall - 2 ( Exterior ) Doors and 5 Single Doors. Lead code A-clear for repair by Horne Engineer ( Edward Rodriguez ) on 8/02/02 DCPS Charles Buchanan Asbestos Code A-clear for repair by Horne Engineer Stephen C aldwell on 8/26/02 DCPS Charles E. Buchanan August 1, 2002 August 9, 2002 8 days
FM-200205170 02 8/9/02 Woodson Between floors 601-701 1.Asbestos assessment required 2.Make the necessary repairs to leaking return line in room #601 and #701between floors, Both rooms are isolated, no heat supplied to this area at this time. EMERGENCY!!! Code A-clear for repair by Horne Engineer ( Troy Wilcome ) on 4/03/02 (CEB) April 1, 2002 August 9, 2002 130 days
FM-200214726 02 8/16/02 Woodson, H.D. 1) Install (2) light fixtures in Cafeteria. Light fixtures are on site. 2) Repair outlet in Kitchen ( sparks coming from) August 16, 2002 August 16, 2002 0 days
FM-200214293 02 8/16/02 Woodson, H.D. Ground Floor - Auditorium 1) E;ectrician needed to stand by for support with superintendents conference 8/14/02. August 14, 2002 August 16, 2002 2 days
FM-200214300 02 8/20/02 Woodson,H.D. 1st Floor Teachers' Cafeteria & Hospitality Room 2. Replace missing floor tiles and fill hole in floor in the teachers' cafeteria; 3. Replace missing floor tiles in the hospitality room; and 4. Outside room G76, replace missing floor tiles. August 14, 2002 August 20, 2002 6 days
FM-200213898 02 8/20/02 Woodson,H.D. Ground-Floor Kitchen/Hospitality Suite Repair or replace leaking faucets inside kitchen and hospitality suite. August 8, 2002 August 20, 2002 12 days
FM-200214606 02 8/20/02 Woodson,H.D. Ground Floor Level/Kitchen Unstop toilet in kitchen area. August 15, 2002 August 20, 2002 5 days
FM-200215324 02 8/23/02 Woodson,H.D. Plaza/Principal's Office Replace windows that sustained bullet holes. August 22, 2002 August 23, 2002 1 day
FM-200214168 02 8/23/02 H.D. Woodson School 1) Removal of bulk trash August 13, 2002 August 23, 2002 10 days
FM-200215375 02 8/24/02 H.D. Woodson School Marking of football field August 22, 2002 August 24, 2002 2 days
FM-200214279 02 8/26/02 Woodson, H.D. Exterior 1) Welder needed to cut up metal so that grounds department can easily dispose of it. August 13, 2002 August 26, 2002 13 days
FM-200215345 02 8/27/02 Woodson,H.D. ****Emergency**** Kitchen Unstop floor drains in the kitchen area. August 22, 2002 August 27, 2002 5 days