Closed Repair Requests: September 2005

See Also: All Closed Repair Requests at Woodson High School

September 2005 Summary

  • Urgent Requests
    15
    Average Time Elapsed: 830.7 Days
  • Routine Requests
    96
    Average Time Elapsed: 691.2 Days
  • Total Requests
    111

Detailed Reports

Urgent Repair Requests Completed in September 2005 (15)
Description Open Date Close Date Time Elapsed
FM-200445177 04 9/2/05 (Woodson, H.D.) !!!VERY URGENT!!! Asbestos Assessment Required. Ground Floor/Girls Restroom: Toilet commode broken in pieces, and part has been removed; the other part is bolted down with sharpe edges exposed. Asbestos Code A - Clear for repairs on 03/12/04. Horne Engineering - Sheryll James (RG 03/15/04) March 10, 2004 September 2, 2005 541 days
FM-200216514 02 9/26/05 (Woodson, H.D.) !!!Very Very Urgent!!! Ground Floor: Repair or replace plate guard sticking up from steps. A parent tripped and fell this morning. September 4, 2002 September 26, 2005 1,118 days
FM-200506793 05 9/26/05 (Woodson, H.D.) "Urgent" Fourth floor, Room 406. Need carpenter to secure room where plywood panel was kicked out (beneath window) June 14, 2005 September 26, 2005 104 days
FM-200445844 04 9/26/05 Woodson, H.D. Ground floor and outside Repair or replace all hand rails back to brick wall and ground also need welder for four (4) sets of steps. ASAP Asbestos Code A - Clear for repairs on 03/25/04. DCPS Safety - Richard Gibson (RG) March 25, 2004 September 26, 2005 550 days
FM-200500192 05 9/26/05 WOODSON H. D. FRONT DOORS TO PARKING AREA UNABLE TO SECURE DOORS URGENT URGENT January 6, 2005 September 26, 2005 263 days
FM-200216332 02 9/27/05 (Woodson, H.D.) !!Urgent!! 3rd Floor: Slop sink stopped up. September 3, 2002 September 27, 2005 1,120 days
FM-200340113 03 9/27/05 (Woodson, H.D.) !!!VERY URGENT!!! Ground Floor/Custodian Office: Commode leaking from the shut off, and on valve. November 7, 2003 September 27, 2005 690 days
FM-200217981 02 9/27/05 Woodson,H.D. Pool Area Lights out in pool around 32 neded. Cherry picker ceiling very high. A 32 lights out safety hazard. September 20, 2002 September 27, 2005 1,103 days
FM-200221030 /02 9/27/05 (Woodson, H.D.) !!!VERY URGENT!!! Plaza: Exterior lights are out surrounding the building. (Safety hazard) November 14, 2002 September 27, 2005 1,048 days
FM-200213895 02 9/27/05 Woodson,H.D. 1. Asbestos Assessment Reqd. Ground Floor Girls' Restroom 2. Repair sink that is falling off its braces; and 3. Install a partition. Asbestos Code A - Clear for repairs on 08/12/02. DCPS Safety - Charles Buchanan (RG 08/12/02) August 8, 2002 September 27, 2005 1,146 days
FM-200213897 02 9/27/05 Woodson,H.D. 1. Asbestos Assessment Reqd. 5th Floor Room 511 2. Repair badly leaking pipe inside classroom 511 Asbestos Code A - Clear for repairs on 08/12/02. DCPS Safety - Charles Buchanan (RG 08/12/02) August 8, 2002 September 27, 2005 1,146 days
FM-200213996 02 9/27/05 Woodson,H.D. 1. Asbestos Assessment Reqd. Teachers Lounge & Area Outisde G76 2. Replace missing floor tiles in these two areas---the areas will be used during the superintendent's conference next week. Asbestos Code A - Clear for repairs on 08/12/02. DCPS Safety - Charles Buchanan (RG 08/12/02) August 9, 2002 September 27, 2005 1,145 days
FM-200443983 04 9/27/05 (Woodson, H.D.) !!!VERY URGENT!!! 3rd Floor/Boys Restroom: Commode stopped up, and running over. Water and feces are running out in the hallway, and classrooms. February 11, 2004 September 27, 2005 594 days
FM-200337707 03 9/27/05 (Woodson, H.D.) !!!VERY URGENT!!! Outside Grounds/Perimeter of Building: All drains are stopped up; very bad storm approaching the area, please respond as soon as possible. September 17, 2003 September 27, 2005 741 days
FM-200213450 02 9/27/05 Woodson,H.D. 1. Asbestos Assessment Reqd. Ground Floor Level Vending Room 2. Replace missing and damaged floor tiles inside the vending room [would help support the superintendent's conference]. Asbestos Code A - Clear for repairs on 12-13-02 by Leroy Minton Jr. Safety Office (202) 576-8962. (LM/12-13-02) August 2, 2002 September 27, 2005 1,152 days

Routine Repair Requests Completed in September 2005 (96)
Description Open Date Close Date Time Elapsed
FM-200511134 05 9/6/05 Woodson H D Music HallwayClassroom/ Classroom G-76 Repair Door locks Code A-clear for repair by DCPS Charles Buchanan on 8/26/05 August 24, 2005 September 6, 2005 13 days
FM-200506338 05 9/13/05 Woodson HD Stairway # 1 Light Fixture Damaged .Wires Exposed . June 6, 2005 September 13, 2005 99 days
FM-200512319 05 9/14/05 Woodson H D Ground fl. near Elevators Repair Lights September 12, 2005 September 14, 2005 2 days
FM-200445753 04 9/26/05 Woodson Room #201 Repair or replace leaking Tee on heating unit in room #201, union is leaking from hot water return line. March 24, 2004 September 26, 2005 551 days
FM-200445055 04 9/26/05 Woodson SHS ( Maintenance T School Blitz ) Exterior 1) Repair exterior lights / Replace bulbs. March 9, 2004 September 26, 2005 566 days
FM-200444948 04 9/26/05 Woodson Boiler Room Repair or replace leaking B&G pump in Boiler Room. March 8, 2004 September 26, 2005 567 days
FM-200444346 04 9/26/05 Woodson Main Lobby Repair or replace 4" flange leaking on city water supply line in main lobby. February 23, 2004 September 26, 2005 581 days
FM-200444310 04 9/26/05 Woodson Boiler Room Repair or replace domestic hot water heater 1 1/4" leaking supply line. February 22, 2004 September 26, 2005 582 days
FM-200443069 04 9/26/05 Woodson Boiler Room Repair duel water circulating pump #8. No Electrical power to pump. Emergency!!!! January 21, 2004 September 26, 2005 614 days
FM-200341156 03 9/26/05 Woodson Boiler Room Check switch to float on sump pumps, not working. Contractor Allen Mitchel work on pumps. December 7, 2003 September 26, 2005 659 days
FM-200339864 03 9/26/05 Woodson H.D. Boiler room Repair or replace ruptured 2" domestic hot water line on storage tank. November 4, 2003 September 26, 2005 692 days
FM-200338703 03 9/26/05 Woodson, H.D. Fourth floor room 401 Remove locks off of chemical labs, cabinets to remove chemicals from lab. October 9, 2003 September 26, 2005 718 days
FM-200338660 03 9/26/05 Woodson Mechanical Room Over Auditorium Repair or replace burned out motor on air handle unit blow fan motor. October 8, 2003 September 26, 2005 719 days
FM-200338028 03 9/26/05 Woodson, H.D. Boiler Room Check and or repair sump pumps in the Boiler Room, Boiler Room is flooded. September 25, 2003 September 26, 2005 732 days
FM-200337320 03 9/26/05 Woodson, H.D. Boiler Room Replace B&G pump to gas hot water heater. Pump burned up. Emergency!!!!! September 11, 2003 September 26, 2005 746 days
FM-200336307 03 9/26/05 H.D.Woodson School removal of bulk trash from dumpster August 26, 2003 September 26, 2005 762 days
FM-200334230 03 9/26/05 Woodson Physical Heating Plant Repair hot water circulating pump for the #2 gas hot water heater this pump is leaking badly and needs to be replaced. #1 and #2 gas hot water heaters are needed to supply domestic hot water while boilers and not in operation during the Summer for summer programs. August 4, 2003 September 26, 2005 784 days
FM-200506820 05 9/26/05 Woodson Boiler Room Chill water pump Repair or replace (2) C Primary chill water pumps need to cool building. One pump is leaking, one pump need bearing. June 15, 2005 September 26, 2005 103 days
FM-200506576 05 9/26/05 WOODSON, H.D. Troubleshoot chiller will not start. June 9, 2005 September 26, 2005 109 days
FM-200503809 05 9/26/05 Woodson, HD Boiler Room Repair or replace domestic hot water heater in Boiler Room. No hot water in Building. April 11, 2005 September 26, 2005 168 days
FM-200502395 05 9/26/05 Woodson Custodian's supply Room Repair or replace pneumatic control valve on heating unit in the custodian supply room (steam side) Islolation valves will not holding water leaking from valve. March 9, 2005 September 26, 2005 201 days
FM-200502317 05 9/26/05 Woodson Football Equipment Room Make necessary repair to air handle unit coil which has been isolated off. March 8, 2005 September 26, 2005 202 days
FM-200453568 04 9/26/05 Woodson Boiler Room Check chiller, chiller down. No run on print out. August 30, 2004 September 26, 2005 392 days
FM-200450789 04 9/26/05 Woodson, H.D. First floor business managers office Need to have file cabinets re-keyed. July 26, 2004 September 26, 2005 427 days
FM-200450783 04 9/26/05 Woodson ,H.D. Principal Office Cloeset Repair or replace leaking univent in principal office closet. July 26, 2004 September 26, 2005 427 days
FM-200449212 04 9/26/05 Woodson Boiler Room Emergency Make the necessary repairs to (2) perimeter pumps for/zone 7 the cool all classroom : #8 and #9 Pumps,no power. June 10, 2004 September 26, 2005 473 days
FM-200449197 04 9/26/05 Woodson Auditorium Repair or replace cutler hammer motor starter coil 110 Volt 60 Cycle No: 1318-1 June 10, 2004 September 26, 2005 473 days
FM-200449143 04 9/26/05 Woodson Auditorium Repair or replace starter control to air handler unit that coil auditorium. Start will not pull in. June 9, 2004 September 26, 2005 474 days
FM-200447130 04 9/26/05 Woodson Room #407 Asbestos assessment required on pipe in room #407 Replace leaking pipe in over head unit in room #407. Asbestos Code A - Clear for repairs on 04/26/04. Horne Engineering - Philp Connolly (RG 04/27/04) April 26, 2004 September 26, 2005 518 days
FM-200447050 04 9/26/05 Woodson Penhouse and Auditorium Repair or replace(2) two rupture coils. One (1) in Penhouse and one (1) over Auditorium. April 23, 2004 September 26, 2005 521 days
FM-200446814 04 9/26/05 Woodson Cooling tower Repair or replace cooling tower. Need parts and service. April 19, 2004 September 26, 2005 525 days
FM-200446551 04 9/26/05 Woodson Boiler Room Check pumps in Boiler Room, pumps making loud noise. There are no fitting to grease pumps. April 9, 2004 September 26, 2005 535 days
FM-200446132 04 9/26/05 Woodson,H.D. !!!VANDALISM!!! Rekey and change locks to new master Plaza: Main office front door office # 1 Two (2), three (3) teachers resource center front and back doors Stairway # 2 Ground floor: Doors around escalators # 1 and 2 Stairway # 1 hospitality suite storeroom door Pool office door room # G75, G76 and G79 Security office, girls lockerroom office door First floor library work and library classroom doors March 30, 2004 September 26, 2005 545 days
FM-200446131 04 9/26/05 Woodson,H.D. !!!VANDALISM!!! Rekey and change locks to new master Seventh floor - Asst. principal office Sixth floor Asst. principal office Fifth floor Asst. principal office and 501 computer room Third floor 301 computer room Fourth floor 409 computer room Plaza bank hall door March 30, 2004 September 26, 2005 545 days
FM-200225898 03 9/26/05 Woodson, H.D. Replace / install latch guard on restroom ladies, male and custodian closet. twenty four (24) latch guards: Floors 7, 6, 5, 4, 3, 2,1, plaza and ground. To prevent fire and unlawful entry. February 14, 2003 September 26, 2005 955 days
FM-200225414 03 9/26/05 Woodson Sr.High Cafeteria Asbestos assessment required Repair or replace ruptured 1 1/4" heating supply line in the cafeteria there are no isolation valves before the rupture. Asbestos Code A - Clear for repairs on 04/25/03. Horne Engineering - Philp connolly (RG 04/29/03) February 9, 2003 September 26, 2005 960 days
FM-200224178 03 9/26/05 Woodson Boiler Room Boiler #1 Replace leaking tubes. January 19, 2003 September 26, 2005 981 days
FM-200222315 /02 9/26/05 (Woodson, H.D.) Plaza/Main office & Conference room: Replace locks on file cabinets. December 10, 2002 September 26, 2005 1,021 days
FM-200221907 02 9/26/05 Woodson, H.D. Seventh floor - room 709 Replace door knob lock on door. Door can not lock room is unsecure, computer area in room. December 3, 2002 September 26, 2005 1,028 days
FM-200220953 /02 9/26/05 Woodson,H.D. 602 Science Room Repair the electrical switch or replace electrical controls to the over -head cab heating unit. Can not heat room due to defective control switch. November 14, 2002 September 26, 2005 1,047 days
FM-200500413 05 9/26/05 Woodson Boiler Room Repair or replace B&G pump for hot water tank, no hot water in building. January 13, 2005 September 26, 2005 256 days
FM-200458278 /04 9/26/05 Woodson Boiler Room Replace leaking tubes in Boiler #1. Building has no heat. November 10, 2004 September 26, 2005 320 days
FM-200457417 /04 9/26/05 Woodson, H.D. Boiler Room Repair or replace 1 1/2" supply line for domestic hot water. October 26, 2004 September 26, 2005 335 days
FM-200455951 04 9/26/05 Woodson Boiler Room Replace #9 sure flex couplin for condenser pump for cooling system. September 28, 2004 September 26, 2005 363 days
FM-200455527 04 9/26/05 Woodson, H.D. Boiler Room Repair or replace duel water circulation pump #12 motor is bad, September 23, 2004 September 26, 2005 368 days
FM-200214006 02 9/26/05 Woodson,H.D. Grounds/Building Exterior Repair or replace exterior lights damaged by vandalism. This effort will help support the superintendent's conference on 8/14/02. August 12, 2002 September 26, 2005 1,141 days
FM-200208590 02 9/26/05 Woodson,H.D. 1. Asbestos Assessment Reqd. Floors 1, 2, 3, 4, 5 & 6 Custodian Closets Install latch guards on the custodian closets, restrooms, & book rooms & plaza [15 guards]. Asbestos Code A - Clear for repairs on 05/29/02. Horne Engineering - Troy Wilcome (RG 05/30/02) May 29, 2002 September 26, 2005 1,216 days
FM-200207757 02 9/26/05 Woodson, H.D. Plaza A key is broken off in the padlock. May 15, 2002 September 26, 2005 1,230 days
FM-200201145 02 9/26/05 (WOODSON,H.D.) ***EMERGENCY*** GROUND LEVEL HALLWAY BY ROOM G-64; 4TH FLOOR GIRLS RESTROOM & TEACHERS RESTROOM IN STAIRWELL #4 1) GROUND LEVEL, BY ROOM G64, GASES FROM RAW SEWAGE IS LEAKING THRU THE SUPPLY LINE INTO THE BLDG & NEEDS TO BE CAPPED OFF; 2) 4TH FLOOR GIRLS RESTROOM HAS A SINK PULLED AWAY FROM THE WALL--THE SUPPLY LINE IS RUPTURED & WATER IS SEEPING THROUGH; 3) 4TH FLOOR TEACHERS RESTROOM (STAIARWELL #4) HAS A SINK WHICH IS CONSTANTLY RUNNING--CANNOT TURN OFF (NO SHUT-OFF VALVE) January 16, 2002 September 26, 2005 1,349 days
FM-200124525 01 9/26/05 WOODSON HD BOILER ROOM REPAIR SUMP PUMP. THERE IS A HOLE IN THE LINE COMING FROM THE PIT CAUSING WATER TO RUN BACK INTO THE PIT AND NOT EMPTY INTO THE DRAIN. December 5, 2001 September 26, 2005 1,391 days
FM-200333906 03 9/26/05 H.D. Woodson School; Cut grass with big tractor July 29, 2003 September 26, 2005 790 days
FM-200331607 03 9/26/05 Woodson Boiler Room Furnish control fuses for sump pumps #1,#2,#3, and #4. June 11, 2003 September 26, 2005 838 days
FM-200331602 03 9/26/05 Woodson Boiler Room Replace leaking 4" and 5" leaking discharge lines for sump pumps with copper lines . June 11, 2003 September 26, 2005 838 days
FM-200330815 03 9/26/05 Woodson, H.D. Outside plaza Send cherry picker / fork lift to clean roof tops and drains no entry way (pick up bottles, rocks trash etc.....) from roof outside. May 28, 2003 September 26, 2005 852 days
FM-200329339 03 9/26/05 (Woodson, H.D.) COVER ALL DRAINS/HOLES IN KITCHEN ORDER TO PREVENT RODENT ENTRY.HEALTH CODE VIOLATION. May 1, 2003 September 26, 2005 879 days
FM-200329320 03 9/26/05 Woodson Physcial Heating Plant, B/R Please make the necessary repairs to 2 Gas hot water heater for domestic hot water for main kitchen samitation, heater leaking at aquastat . Alsocheck # (1) and #2 gas hot water heaters electrical controls for flame to both heaters. May 1, 2003 September 26, 2005 879 days
FM-200228598 03 9/26/05 (Woodson) Ground and first floor Fix or replace locks, Activity room girls coach of file, pool and library on first floor stairway # 2 men restroom. April 10, 2003 September 26, 2005 900 days
FM-200227854 03 9/26/05 H.D Woodson Cafe. Mech. Room Basement Repair rupture 4" city water line connected to booster punp and install 4" isolation valve March 28, 2003 September 26, 2005 913 days
FM-200458524 /04 9/27/05 Woodson, HD Emergency Third floor boys bathroom The commode is overflowing, the cut off valve will not cut off and the water is running all over the floor. November 19, 2004 September 27, 2005 312 days
FM-200117045 01 9/27/05 (WOODSON, H.D.) 1. ASBESTOS ASSESSMENT REQUIRED. 7TH FLOOR/CORRIDOR: REPAIR BREECH IN WALL OUTSIDE ROOM #201. Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Tony Marcolin (RG 03/11/03) August 9, 2001 September 27, 2005 1,510 days
FM-200329392 03 9/27/05 Woodson, H.D. Ground floor kitchen Replace drain cover / hole in cover. May 2, 2003 September 27, 2005 879 days
FM-200203900 02 9/27/05 (Woodson,H.D.) Asbestos Assessment Required 7th Floor Escalator Well Repair large hole in the plaster wall. CODE A-CLEAR FOR REPAIR BY HORRNE ENGINEER ( PHILIP CONNOLLY ) ON 3/06/02 March 5, 2002 September 27, 2005 1,302 days
FM-200219018 02 9/27/05 Woodson, H.D. Fourth floor - Room 408 Replace wood door 81 1/2x36 3/4 Asbestos Code A-clear for repair by Charles E. Buchanan on 10/08/02 DCPS Charles E. Buchanan October 8, 2002 September 27, 2005 1,085 days
FM-200218805 02 9/27/05 (Woodson, H.D.) 1. Asbestos assessment required. Ground Floor/Locker room, team room #1: Replace crack urinal leaking. October 3, 2002 September 27, 2005 1,090 days
FM-200218778 02 9/27/05 Woodson, H.D. Ground Cracked urinal and it is leaking. October 3, 2002 September 27, 2005 1,090 days
FM-200502596 05 9/27/05 (Woodson) "Emergency" Third floor restroom. Unclogged fixture, overflowing into corridor. March 11, 2005 September 27, 2005 200 days
FM-200502657 05 9/27/05 Woodson H D Third fl Boys Restroom Toilet leaking arround the base line March 14, 2005 September 27, 2005 197 days
FM-200502865 05 9/27/05 Woodson, H.D. Ground plase 1 through 7 Water coolers are off walls and some are leaking water and can not cut off.Phone room need new lock. Kids are useing room to call fire department and anyone else. March 17, 2005 September 27, 2005 194 days
FM-200117010 01 9/27/05 WOODSON GROUND FLOOR, LOBBY BOYS, AND GIRLS BATHROOMS. 1) COMMODE AND SINKS ARE NOT WORKING. SINKS ALSO NEED KNOBS. August 9, 2001 September 27, 2005 1,510 days
FM-200503555 05 9/27/05 Woodson SHS Boys Locker Room 1) Pipe Busted. ( Athletic Training Area ). April 5, 2005 September 27, 2005 175 days
FM-200503654 05 9/27/05 (Woodson, H.D.) Science Labs. Need water supply to labs, currently there is no running water in science labs. April 6, 2005 September 27, 2005 174 days
FM-200504692 05 9/27/05 ( HD WOODSON ) "Emergency" Third Floor - Boys Restroom 1) Water running all over the floor. April 25, 2005 September 27, 2005 155 days
FM-200226555 03 9/27/05 Woodson Third floor - room 302 Need at least six (6) new outlets for the cosmotology lab. March 5, 2003 September 27, 2005 937 days
FM-200213518 02 9/27/05 Woodson,H.D. 1. Asbestos Assessment Reqd. Ground Floor Cafeteria/Hospitality Suite 2. Replace stained and missing ceiling tiles---this effort will support the superintendent's conference set for 8/12/02. A-Code Clear for repair by DCPS Charles Buchanan on 8/05/02 August 5, 2002 September 27, 2005 1,149 days
FM-200505778 05 9/27/05 Power issues identified associated with Homeland Security Lighting installation. Vendor - Jones Electric has provided details on specific power problems impacting function of Security Lights and photocell. Until resolved lights remain uncontrolled and burn constantly. Request site visit by Danny Hudson to survey problem and determine if DCPS can fix or should vendor fix. The vendor has provided a quote of 20K to resolve problem. See Renard Alexander (202) 409-0653 for details and to schedule survey. May 19, 2005 September 27, 2005 131 days
FM-200225284 03 9/27/05 (Woodson, H.D.) Asbestos assessment required. 3rd Floor/Teachers Lounge: Due to fire set by students, this teachers lounge has floor tile, and smoke damage. Asbestos Code A - Clear for repair on02/05/03. Horne Engineering - Troy Wilcome (RG 02/06/03) February 5, 2003 September 27, 2005 965 days
FM-200212707 02 9/27/05 Woodson,H.D. Ground, 4th, 5th & 6th Floors 2. Replace door closers in following areas: Ground floor, back of gym, cafeteria, by escalators, boys, locker room by room G-64, music room & main lobby; 4th floor moving stair & girls' restroom; 5th floor stairway #2, and 6th floor stairway #2. July 23, 2002 September 27, 2005 1,162 days
FM-200223592 03 9/27/05 (Woodson, H.D.) Cafeteria/Kitchen: Repair or replace water fountain in the cafeteria. January 7, 2003 September 27, 2005 994 days
FM-200212655 02 9/27/05 (Woodson, H.D.) 1. Asbestos assessment required. 4th Floor/Girls restroom: Paint entire restroom. Asbestos - Code A, clear for repairs on 7/30/02 Horne Engineering - Sharon Voss (RE - 7/31/02) Lead based paint - Code A, clear for repairs on 7/31/02 Horne Engineering - Edward Rodriguez (RE - 7/31/02) July 23, 2002 September 27, 2005 1,162 days
FM-200221910 02 9/27/05 Woodson, H.D. Ground floor - by room G-75 Exterior door need sleeve down the bottom of door. Trash and rain blows under door. December 3, 2002 September 27, 2005 1,029 days
FM-200227423 03 9/27/05 Woodson, H.D. Senevth, fifth and fourth floor Exit doors 1, 4 and 3 Knobs are missing on stairway doors. March 21, 2003 September 27, 2005 921 days
FM-200221633 /02 9/27/05 (Woodson, H.D.) Team locker room: Paint locker room; paint is badly needed. (Girls and boys) Lead & Asbestos Code A - Clear for repairs on 03/13/03. Horne Engineering - Edward Rodriguez (RG 03/14/03) November 25, 2002 September 27, 2005 1,037 days
FM-200336257 03 9/27/05 Woodson, H.D. Fifth floor room 506 cooking room Install gas stove. August 26, 2003 September 27, 2005 763 days
FM-200228866 03 9/27/05 (Woodson, H.D.) Through-Out Building/Ground Plaza: Replace drinking fountains with water coolers in the following locations: Bank, hall, and health suite. April 17, 2003 September 27, 2005 894 days
FM-200220346 /02 9/27/05 (Woodson, H.D.) Ground; 1st; & 2nd Floor: Water coolers leaking and running; needs to be remounted. Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Tony Marcolin (RG 03/11/03) October 30, 2002 September 27, 2005 1,063 days
FM-200220193 /02 9/27/05 (Woodson, H.D.) 1. Asbestos assessment required. Ground Floor/Kitchen: Repair hole in kitchen floor where pest control was needed. Asbestos Code A-clear for repair by Horne Engineer Edward Rodriguez on 10/30/02 DCPS Charles E. Buchanan October 29, 2002 September 27, 2005 1,064 days
FM-200219865 /02 9/27/05 Woodson H.D. Ground floor - receiving hallway Replace double metal doors aith light. Door size 82x35 3/4 Very,very sharp edge. October 23, 2002 September 27, 2005 1,070 days
FM-200219864 /02 9/27/05 Wioodson, H.D. Fourth, fifth and ground floor Rooms 507, 407, office and girls lockerroom Replace kick out panels (3). October 23, 2002 September 27, 2005 1,070 days
FM-200219671 /02 9/27/05 Woodson, H.D. Third floor - boys bathroom Due to fire damage this restroom needs to be painted. Asbestos code A-clear for repair by Horne Engineer Edward Rodriguez on 10/21/02 DCPS Charles E. Buchanan October 18, 2002 September 27, 2005 1,075 days
FM-200501793 05 9/27/05 Woodson H.D. ( High School Bathroom Survey Report ) Seventh Floor Girls Restroom - Replace Faucets Seventh Floor Boys Restroom - Repair Toilet Fifth Floor Boys Restroom - Repair Toilet Fourth Floor Restroom - Repair Sink Second Floor Boys - Repair Faucet First Floor Boys Restroom - Replace Faucet First Floor Health Suite - Repair Toilet, Sink and Urinal First Floor Male Staff - Repair Sink Ground Floor Armory - Replace Water Closets Grounds Floor Girls - Replace Water Closets,Repair Sinks and Repair Toilet Ground Floor Boys Restroom - Repair Sink and Water Closets Custodial Office - Repair Faucets February 20, 2005 September 27, 2005 219 days
FM-200205043 02 9/27/05 (Woodson,H.D.) Asbestos Assessment Required Plaza, 1st, 6th & 7th Floors Painting of the interior walls, ceiling & doors of the plaza, 1st, 6th and 7th floor areas by in-house school staff. Asbestos/Lead Code A-clear for repair by Horne Engineer (Edward Rodriguez) on 4/01/02 (CEB) March 28, 2002 September 27, 2005 1,279 days
FM-200500280 05 9/27/05 Woodson, HD EMERGENCY First and ground floor Two bathroom the shut off valves are no good. The plummer (Mr. Butler) said they would come back but did not. The water can not be shut off until after 3:30 PM because of the schhol in section. January 10, 2005 September 27, 2005 260 days
FM-200338630 03 9/27/05 (Woodson, H.D.) !!!EMERGENCY!!! 3rd Floor/Girls Restroom: Commode backing up, running out in the hallway, flooding the floors in-to the classrooms. Plaza/Ladies Restroom: Leaking commode, flooding the plaza. October 7, 2003 September 27, 2005 721 days
FM-200458532 /04 9/27/05 Woodson, HD 4th, 5th and 7th floor Teacher restroom 4th floor need toilet fix. 5th floor boys restroom need fix. Teacher restroom on 7th floor men and women. November 19, 2004 September 27, 2005 312 days
FM-200458531 /04 9/27/05 Woodson, HD Ground floor Girls restroom need to be fix, lockroom. 5th floor washer and dryer holes that let water out is stopped up. Crown D floor G 06 room sink is stopped up. November 19, 2004 September 27, 2005 312 days
FM-200512139 05 9/30/05 Woodson H.D. Emergency Kitchen-Grease trap is clogged up, water is backing up and flooding the floor. September 9, 2005 September 30, 2005 21 days