Urgent Requests
0 -
Routine Requests
5 -
Total Requests
5
Detailed Reports
| Description | Open Date |
|---|---|
| FM-200625168 7/3/06 Principal's Office/Back Exit Door - Change Lock | |
| FM-200625699 7/14/06 Woodson Boiler Room Open boiler drain with a new access hole for cleaning scale. | |
| FM-200625700 7/14/06 Woodson Boiler Room Repair refractory on Boiler #1 | |
| FM-200626193 7/24/06 Woodson Boiler Room Repair or replace chill water circulating pump #10 and #11. These pumps serve the auditorium and Gym area. | |
| FM-200626286 7/24/06 Plaza Area- Exit Door Repair/replace lock; the building was broken into yesterday. Note: The building cannot be secured. |