Open Repair Requests: August 2003

See Also: All Open Repair Requests at Woodson High School

August 2003 Summary

  • Urgent Requests
    0
  • Routine Requests
    5
  • Total Requests
    5

Detailed Reports

Routine Repair Requests Opened in August 2003 (5)
Description Open Date
FM-200334223 8/4/03 Woodson Boiler Room Boiler room drain stop up, water on floor. Please unstop drain. August 4, 2003
FM-200334225 8/4/03 Woodson Elevator Room / Penthouse Replace (1) window A/C unit in the Penthouse Elevator Room, unit not working properly. A/C window unit is needed to cool all senors for properly operation of #1 and #2 elevator. August 4, 2003
FM-200334229 8/4/03 Woodson Physical Heating Plant Repair #1 and #2 air compressor and air check compressor are not able to reach desired 60 pounds for the operation of pneumatic zones. Only 30 pounds can be maintained these are alternating air compressors this is not efficient to operation of compressors. August 4, 2003
FM-200334434 8/5/03 Woodson, H.D. Plaza Paint main office, rooms 1, 2, 3 and 4, work room, corridor hall, teachers resource room center and conference room.Repair or replace lights ballasts inthe following Areas: Lead & Asbestos Code A - Clear for repairs on 08/06/03. Horne Engineering - Edward Rodriguez (RG 08/07/03) August 5, 2003
FM-200336188 8/25/03 Woodson Boiler Room Repair or replace Hot/Cold dual circulating pump, pump #15 need motor replace and pump #14 has leaking seal. Both pumps are needed for the heating and cooloing of the center core of the facility. August 25, 2003