| FM-200109783 01 9/21/01 BOWEN GYMNASIUM - OUTSIDE DOORS #6, #8 AND #9,# 10. THESE DOORS NEED COMPLETE ALTERATION TO LOWER END. THE DOORS AND PLATES WERE CUT TOO SHORT ALLOWING RATS, RODENTS AND OTHER ANIMALS ENTRANCE TO THE BUILDING (GYM). THESE ALTERATIONS WILL END THE ENTRANCE OF RATS INTO THE BUILDING. HEALTH AND SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/18/01. | |||
| FM-200105762 01 9/26/01 (BOWEN) TEACHERS LOUNGE: IMPROPER LOCK IN TEACHERS LOUNGE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/02/01. MR. LEROY MINTON - SAFETY (202)576-6691 | |||
| FM-200120194 01 10/22/01 (BOWEN) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ LEARNING CTR. #1, BOYS BATHROOM WATER COMING FROM BEHIND THE URINE BOWL. IN NEED OF A PLUMMER. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | |||
| FM-200111874 01 11/27/01 (BOWEN) "VERY URGENT" PLAYGROUND: FILL IN HOLES WITH ASPHALT, HOLE VERY DANGEROUS TO STUDENTS AND OTHERS ON THE PLAYGROUND. SIZE OF HOLE: WIDTH, 10 FEET. LENGTH, 10 FEET. THIS HOLE IS (3) FEET DEEP, OR MORE. | |||
| FM-200107168 01 1/8/02 BOWEN 3RD FLOOR WASH SINK REPLACE WASH SINK. THIS SINK LEAKS WATER INTO CLASSROOMS AND DOWN THE OFFICE FLOOR. RAPAIRS HAVE BEEN MADE BUT THE LEAKS CONTINUES. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/30/01. RONALD EDWARDS - SAFETY (202)576-6693 | |||
| FM-200107002 01 1/9/02 BOWEN ALL RESTROOM - THRU OUT BUILDING BOYS AND GIRLS WATER FAUCET FIXTURES ARE BROKEN NEEDS REPLACE ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/30/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | |||
| FM-200126980 02 2/20/02 (BOWEN) 2ND FLOOR/ LEARNING CENTER #3 !!! URGENT!!! WATER FOUNTAIN NEEDS TO BE REPAIRED OR REPLACED DUE TO THE BLDG. BEING SO HOT THEY NEED THE WATER FOUNTAIN. | |||
| FM-200204498 02 3/15/02 (Bowen) "Urgent" 1. Asbestos assessment required. 3rd Floor/Through-out: Install glass in doors in the following rooms: #302, 304, 306, & 308. Asbestos Code A - Clear For Repairs On 03/15/02. Sheila R Howard - DCPS - Safety (RG 03/15/02) | |||
| FM-200204502 02 3/28/02 (Bowen) "Urgent" 1. Asbestos assessment required. 3rd Floor/Through-out: Install locks on doors in the following rooms: #302, 304, 306, & 308. Asbestos Code A - Clear For Repairs On 03/15/02. Sheila R Howard - DCPS - Safety (RG 03/15/02) | |||
| FM-200206357 02 4/29/02 Bowen ****Urgent**** 1st Floor Girl's Restroom There is no water coming into the toilet bowls for flushing--they are not working properly in the 1st floor girl's restroom. | |||
| FM-200207809 02 5/24/02 Bowen ****Urgent**** 3rd Floor Hallway Slop Sink Clear clogged slop sink in the 3rd-floor hallway and replace missing faucet [students manage to keep the water running out onto the floor]. Asbestos Code A - Clear for repair on 05/15/02. DCPS Safety - Richard Gibson (RG 05/15/02) | |||
| FM-200208622 02 6/4/02 Bowen ****Very Urgent*** 1. Asbestos Assessment Reqd. 1st Floor Learning Centers 1 & 3 2. There is water coming down through the ceiling and flooding the floors in Learning Centers 1 & 3. The reason/source of the leaking is not clear. Asbestos Code A - Clear for repairs on 05/29/02. Horne Engineering - Bipin Nanavaty (RG 05/30/02) | |||
| FM-200208279 02 6/12/02 (Bowen) Fire code violation: Page 2 of 4 M Street stairwell: Broken door return Asbestos Code A - Clear for repairs on 05/24/02. DCPS Safety - Leroy Minton Jr. (RG 05/29/02) | |||
| FM-200208278 02 6/12/02 (Bowen) Fire code violation: Page 2 of 4 Room #311: Broken door return Asbestos Code A - Clear for repairs on 05/24/02. DCPS Safety - Leroy Minton Jr. (RG 05/29/02) | |||
| FM-200209354 02 6/13/02 Bowen ****Urgent**** Learing Center #1 Storage Vault 1. The key to the storage vault in learning center #1 has been lost----need replacement key to gain access to supplies needed before summer session starts. 2. Supply master key/keys to Mr. Hawkins for emergency access to all locked areas. | |||
| FM-200204777 02 7/3/02 (Bowen) ****Urgent**** 3rd Floor Windows At The Landing Weld bars/protective cage on the outside of the windows---students are opening and hanging out of the windows [serious safety hazard]. | |||
| FM-200212153 02 7/18/02 (Bowen) **Very Very Urgent** 3rd Floor: Water coolers are flooding the floors in the following rooms: #302, 303, & 304. | |||
| FM-200209383 02 8/20/02 Bowen Exterior Grounds Remove bulk trash left on the ground beside the dumpster [combustibles--safety & fire hazard]. | |||
| FM-200216124 02 8/30/02 Bowen First Floor - Hallway Urgent !! 1) Slop sink stopped up . When you pour water on 3rd floor ,sink floods on first floor. Floor is constantly flooding. !! | |||
| FM-200216322 02 11/1/02 Bowen ****Urgent**** Learning Centers 1 & 2 There is a strong smell of burning rubber, areas have been isolated and fire dept. was called in. Problem could be electrical---will be checked by electrical shop. | |||
| FM-200219813 /02 11/4/02 (Bowen) !!!VERY URGENT!!! 3rd Floor/Slop sink: Water flooding the floors; there is no cut-off valve present. | |||
| FM-200219819 /02 11/4/02 (Bowen) !!!VERY URGENT!!! 3rd Floor/Slop sink: Install cut-off valves to slop sink on the 3rd floor. | |||
| FM-200223425 03 1/23/03 (Bowen) !!!VERY URGENT!!! Cafeteria/Workers restroom: Toilet backing up through floor drains in the cafeteria/kitchen, given off an un-pleasant odor. | |||
| FM-200225775 03 2/13/03 (Bowen) !!!VERY URGENT!!! Basement/Tunnel Bomb shelter: Electrical power failure in this area after contractors completed their work. Please restore electrical power. (Unable to see without lights) | |||
| FM-200209334 02 3/13/03 Bowen ****Very Urgent**** 1st Floor Lobby/Main Entrance The automatic lock is malfuntioning, not catching. This is a potential safety & security problem. | |||
| FM-200221094 /02 3/15/03 (Bowen) 2nd & 3rd floor: Repair water fountains on the above floors; fountains were vandalized and pulled away from the walls. Remount to floor. away from the walls Asbestos Code A-clear for repair by Horne Engineer Sheryll James DCPS Safety on 11/21/02 Charles E. Buchanan | |||
| FM-200227234 03 3/19/03 (Bowen) !!!VERY URGENT!!! Learning center #1: Toilet will not flush, and sink is stopped up. (Plunging did not work) Also, leaking under sink in the Principal's office. | |||
| FM-200111169 01 3/19/03 BOWEN PLAYGROUND AREA 1) CHECK CEMENTED HOLE ON PLAYGROUND HOLE HAS CREATED A SAFETY HAZARD | |||
| FM-200205925 02 3/19/03 Bowen Outside - Front Entrance Entrance of Building sidewalk cement is pucking. Safety Hazard. | |||
| FM-200207637 02 3/21/03 Bowen ****Urgent**** 3rd Floor Hallway/Water Fountain A water fountain has been pulled away from the pipes and water is pooling across the floor. | |||
| FM-200228499 03 4/24/03 Bowen Chiller Room Replace 2" leaking steam line in chiller room over top of chiller next to electric panel box. URGENT!!!! | |||
| FM-200336251 03 9/10/03 (Bowen) !!!URGENT!!! 2nd Floor/Nurse's Suite:l Hot water will not come the faucett when turning on. (Unable to get any hot water to come through the faucett. | |||
| FM-200339310 /03 1/5/04 (Bowen) !!!URGENT!!! 3rd Floor: Need two (2) keys for Learning Center #2. Need two (2) keys for room #301. Keys to the vault was stolen, need keys also. | |||
| FM-200445107 04 3/25/04 (Bowen) !!!VERY URGENT!!!+ Asbestos Assessment Required. 1st Floor/Girls Restroom: Door broken by student vandals. 3rd Floor/Room #300: Repair or replace door; hinges have come away from door. Code A - clear for repairs as of 3/10/04 by Ed Rodriguez. Per Mr. Clarence Coleman, locks are damaged and needs to be replaced , Room 301 and also Girls restroom. | |||
| FM-200210723 02 6/26/04 Bowen 1. Asbestos Assessment Reqd. 1st-floor Room 105 [Special Ed. Office] 2. Install a bracket in the window of room 105 to hold the window a/c unit; 3. Install a dedicated electrical outlet to support the a/c unit; and 4. Install the window a/c unit [unit is on-site]. Asbestos Code A clear for repairs, on 7/03/02 DCPS Safety, R. Edwards (RE - 7/11/02) | |||
| FM-200210122 02 7/22/04 Bowen 1. Asbestos Assessment Reqd. 1st Floor Rooms 101, 1055, Main Office & Health Suite 2. Install an electrical outlet to support new window a/c unit in room 105. 3. Install new electrical outlet to support existing window a/c unit in room 101. 4. Redo electrical outlet in the main office where the outlet put in was the wrong type----prongs on window a/c unit will not fit the outlet. 5. Install an electrical outlet for the existing window a/c unit in the health suite. Code A-clear for repair by DCPS Safety ( Leroy Minton ) on 06/25/02 | |||
| FM-200210121 02 7/27/04 Bowen ****Urgent**** 1. Asbestos Assessment Reqd. 1st Floor Room 105 2. Install new on-site window a/c unit. Code A-clear for repair by Horne Engineer ( Bipin Nanaavaty ) on 06/26/02 | |||
| FM-200452950 04 8/25/04 Bowen URGENT First floor hall Repair toilet in nurses office. | |||
| FM-200456892 /04 10/20/04 Bowen Urgent !!! Gym 1) Repair busted water line on the water fountain. | |||
| FM-200454475 04 11/30/04 (Bowen) !!!URGENT!!! 3rd Floor: Copper pipe leaking from water fountain; large amount of water on floor. | |||
| FM-200454476 04 11/30/04 (Bowen) !!!URGENT!!! 2nd Floor/Counselor's Office: Leaking water from pipe that was previously capped off. | |||
| FM-200451190 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. 3rd Floor/Next to Room #311: Missing closer on stairwell door. Code A - clear for repairs as of 8/24/04 safety Sylvia. | |||
| FM-200451188 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. 3rd Floor/Next to Room #301: No door hardware stairwell. Code A - clear for repairs as of 8/24/04 safety Sylvia. | |||
| FM-200451189 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. 3rd Floor/Room #303: Door hardware missing. Code A - clear for repairs as of 8/24/04 safety Sylvia. | |||
| FM-200451196 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. Ms. Lichabs-Missing ceiling tile. Code A- clear for repairs as 8/19/04 safety Sylvia. Replace ceiling tile only. | |||
| FM-200451197 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. Storage Area/Learning Center #3: Missing ceiling tile. Code A - clear for repairs as of 8/19/04 safety Sylvia. Replace tile only. | |||
| FM-200451198 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. 1st Floor/Learning Center #3: Missing ceiling tile. Code A - clear for repairs as of 8/19/04 safety Sylvia. Replace tile only. | |||
| FM-200451199 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. Gym: Missing ceiling tile. Code A - clear for repairs as of 8/19/04 safety Sylvia. Replace tile only. | |||
| FM-200451203 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Asbestos Assessment Required. Main Entrance Doors: Defective door closer. Code A - clear for repairs as of 8/24/04 safety Sylvia. | |||
| FM-200451799 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Boys Club Storage: Door 11 in kindergarten, improper hardware. Code A- clear for repairs as of 8/19/04 safety Sylvia. | |||
| FM-200451808 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Kitchen in Pre-K: Improper hardware on door. Code A - clear for repairs as of 8/19/04 safety Sylvia. | |||
| FM-200451809 04 1/6/05 (Bowen) FIRE CODE VIOLATION: Kitchen in Pre-K: Missing ceiling tile. Asbestos Code A - Clear for repairs on 08/11/04. DCPS Safety - Richard Gibson (RG) | |||
| FM-200500797 05 1/26/05 Bowen Boiler Room Repair 1 1/2" return line in meter room. Urgent !!!!! | |||
| FM-200503824 05 4/12/05 (Bowen) "Emergency" Building Exterior/Playground. Remove and replace broken plexiglass on playground equipment it poses a safety hazzard. | |||
| FM-200504359 05 4/20/05 (Bowen) " Urgent" Ground level/Cafeteria Repair or Replace drinking fountain, existing fountain is leaking and flooding area. | |||
| FM-200505046 05 5/3/05 (Bowen) !!!VERY URGENT!!! 1st Floor/Storage Room: Unable to get access to room, keys lost. | |||
| FM-200505424 05 5/12/05 (Bowen) URGENT!!! Third Floor - Hallway 1) Repair lighting, no lighting. | |||
| FM-200504690 05 5/23/05 ( BOWEN ) URGENT!!!!! First Floor - Girls Restroom 1) Repair door, it's broken and about to fall off. | |||
| FM-200224692 03 10/25/05 (Bowen) Cafeteria office ceiling: Provide safety assessment for clearing chipped paint from the ceiling in the cafeteria office. Lead & Asbestos Code A - Clear for repairs on 01/28/03. Horne Engineering - Edward Rodriguez ( RG 01/30/03) | |||
| FM-200449625 04 10/25/05 (Bowen) Asbestos Assessment Required. 1st Floor/Boys Gym: Repair flooring, broken tile. Code A - clear for repairs as of 7/7/04 by safety office Sylvia Grimes. | |||
| FM-200336693 03 10/25/05 (Bowen) !!!VERY URGENT!!! Learning Center 1: Lighrs are out in both kindergarten area's; when lights are turned on, a booming sound is heard, and they go off again. | |||
| FM-200337861 03 10/25/05 (Bowen) !!!VERY URGENT!!! 1st Floor Kitchen/Cafeteria: Floor drains stopped up; sewage backing up in drains. | |||
| FM-200227821 03 10/25/05 (Bowen) Playground: Remove bricks from playground area; injuries could be sustained. | |||
| FM-200447904 04 10/25/05 (Bowen) !!!URGENT!!! Lead Assessment: 1st Floor/Room #103: In order to scrape ceiling, need lead assessment. Lead & Asbestos Code A - Clear for repairs on 05/14/04. Horne Engineering - Edward Rodriguez (RG 05/18/04) | |||
| FM-200226795 03 10/26/05 (Bowen) !!!VERY URGENT!!! Learning Center #1: Stopped up sink in the teachers lounge. 11/12/2003, staff called in to make inquiry as to when repairs will be made, as conditions are worse. | |||
| FM-200122460 /01 12/14/05 (BOWEN) 1. ASBESTOS ASSESSMENT REQUIRED. Fence need to be install on the side of the kitchen separating the field area from the playground. Requester Phone: 724-4871 Requestor Phone: 724-4871 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/26/01. RICHARD E GIBSON - SAFETY (202)576-5584 (RG) | |||
| FM-200330982 03 12/14/05 Bowen Make the following repairs: Component - K K 72 - 62 1) The double wide double long slide has only four feet of rubber pad on exit end. Component - K K 72 - 44 2) The safety rails have to wide of a gap, this is not safe. Component - K K 72 - 101 3) The attached To/Fro swing were taken down, they should be replaced. Component - K K 72 - 55 4) The safety panel is missing its steering wheel. Component - K K 72 - 49 5) The suspension bridge was taken down , it should be replaced. Component - K K 72 - 21 6) The chain is broken on the vinyl clad chain net climber. Component - K K 72 - 15 7) One of the curly climbers were taken down,it should be replaced. Component - K K 72 - 25 8) Some of the safety loops are missing on the three rung ladders. | |||
| FM-200515930 05 1/6/06 Urgent: Repair the outside lights around the building and on the playground area. | |||
| FM-200122318 /01 2/3/06 (BOWEN) 1. ASBESTOS ASSESSMENT REQUIRED. K27 is no longer the Custodians Office it is now the Counselors Office locate on the first floor. The wall is very badly damage. It has a very large split and material are falling out. Not sure if the materials falling out is of a dangerous nature. Also the base boards ar coming away from the wall. Requester Phone: 202 724-4871 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/26/01. HORNE ENGINEERING - SHERYLL JAMES (RG) | |||
| FM-200126888 02 2/3/06 (BOWEN) OUTSIDE/PLAYGROUND THE LIGHTS ON THE BLDG LIGHTING THE PLAYGROUND ARE CONSISTENTLY BEING BROKEN BY CHILDREN THROWING BRICKS. REPLACE ALL BROKEN LIGHTS (WHICH ARE NOW BROKEN SHARDS HANGING OVER PLAYGROUND & COULD FALL ONTO THE CHILDREN CAUSING SERIOUS INJURY) & INSTALL PROTECTIVE CAGES OVER THE REPLACEMENT LIGHTS & ALL OTHER REMAINING LIGHTS (PREVENTING BREAKAGE) ON THE OUTSIDE OF THE BLDG & THE PLAYGROUND. | |||
| FM-200117746 01 2/3/06 (BOWEN) 1. ASBESTOS ASSESSMENT REQUIRED. OUTSIDE/BUILDING FLOOD LIGHTS: FLOOD LIGHTS WERE DAMAGED BY VANDALS; REPLACE LIGHTS WITH PROTECTIVE SHIELDS. (LIGHTS HAVE BEEN OUT FOR A WEEK) CODE A-CLEAR FOR REPAIR BY DCPS SAFETY RONALD EDWARD. CEB | |||
| FM-200112459 01 2/3/06 BOWEN THIRD FLOOR HALLWAY 1) REPLACE WASH SINK ON THIRD FLOOR HALLWAY SINK LEAKS WATER INTO CLASSROOMS AND ONTO OFFICE FLOOR ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/30/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | |||
| FM-200124473 01 2/3/06 (BOWEN) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ CAFETERIA REPAIR PLASTER CEILING-DAMAGE FROM OLD ROOF. PIECES ARE FALLING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/06/01. HORNE ENGINEERING - SHERYLL JAMES (RG) NOTE: This plastering/painting job can not proceed until the roofing problem causing the falling plaster is resolved [Ref: FM-200208742]. At that time, please update this to a very urgent status, as the plaster is falling in ever larger pieces. | |||
| FM-200508969 05 2/3/06 Bowen Fire Code Violation - 2003 D.C. Supp IFC - 110.1.1 Second Floor - Storage Room 1) Vertical Penetration. Code A - clear for repairs as of 8/3/05 by Tidewater. Sylvia Grimes safety office. | |||
| FM-200514763 /05 2/16/06 (Bowen) "Emergency" Asbestos Assessment Required. Second floor, Hallway. Repair Fire doors that are hanging of hinges. Note: There is danger of the doors falling. Asbestos Code A - Clear for repairs on 11/02/05. Tidewater - Thomas Johnson (RG 11/03/05) | |||
| FM-200515093 05 2/16/06 First floor, Learning Center I & Kitchen Area. "Urgent" Boys' & Girls' Restroom 1.) Replace all faucet knobs on sinks because the existing knobs are just turning. 2.) Kitchen Area, replace faucet on sink. | |||
| FM-200502113 05 3/3/06 Bowen Main lobby first floor girls bathroom Door coming off hinges, same one that was just fixed. Asbestos Code A - Clear for repairs on 03/02/05. DCPS Safety - Richard Gibson (RG) | |||
| FM-200508977 05 3/30/06 Bowen Fire Code Violation - 2003 D.C. Supp IFC - 110.1.1 Gym 1) Vertical Penetration. Code A -clear for repairs as of 8/3/05 by Tidewater. Sylvia Grimes safety office. | |||
| FM-200204828 02 4/17/06 (Bowen) ****Urgent**** Window at The 3rd Floor Landing Weld protective bars or a protective cage over the outside of the window in the 3rd floor landing, where one student was about to push another out the open window. The absence of protective bars or cage allows a potential safety hazard. | |||
| FM-200335061 03 8/25/06 Bowen Boiler Room Boilers #1 and #2 has two (2) check valve each, that needs to be remove. Size of valves are 1" and 1/2". Code A- clear for repairs as of 9/9/03. by safety Sylvia Grimes. | |||
| FM-200629183 06 12/1/06 2nd Floor- Learning Center 3 Repair ceiling; ceiling tile just fell on a child. Asbestos Code A - Clear for repairs on 09/12/06. DCPS Safety - Richard Gibson (RG ) | |||
| FM-200223008 /02 1/11/07 (Bowen) !!!VERY URGENT!!! 1. Asbestos assessment required. Through-out the building: Check all exit doors, leading to hallways and classrooms. Student injured by door. Asbestos Code A - Clear for repairs on 12/23/02. Horne Engineering - Bipin Nanavaty (RG 12/24/02) | |||
| FM-200509657 05 1/11/07 Bowen Boiler Room Repair or replace Boiler room back door. Door has came from frame. Urgent !!!!! Asbestos Code A - Clear for repairs on 08/09/05 by Leroy Minton Jr. (LM/08*09-05) Safety Office 202-576-8962. | |||
| FM-200333361 03 1/11/07 Anthony Bowen - Learning Center # 1 & 2 1. Install 2 spot coolers in the open space areas Asbestos Code A - Cleared for repairs on 07-17-03 by Leroy Minton Jr (LM/07-17-03) Safety Office 202-576-8962. | |||
| FM-200620402 06 1/22/07 Exterior Cafeteria Door. "Urgent" Repair or replace 4th metal exit door frame. Note:The frame was damaged during an attempted break-in. 04/05/2006 14:49 TH - This is now an emergency-Mr. Hawkins said that the door can't be secured. The panic bar will lock but all youhave to do is push or pull the door and it's not very hard to open. | |||
| FM-200450683 04 1/22/07 (Bowen) Main Entrance Door: Plate on door coming up on Delaware avenue side. Code A - clear for repairs as of 8/19/04 safety Sylvia | |||
| FM-200224697 03 1/22/07 (Bowen) 1. Asbestos Assessment Required. Learning centers #1, 2, & 3/Gymnasium: 1. Replace missing & damaged ceiling tiles in gymnasium, approx. six (6) pieces. (Scaffoling is needed due to the ceiling height. (2' X 4') 2. Replace missing and damaged 12" X 12" spline ceiling tiles as needed in the learning centers #1, 2, & 3. Asbestos Code A - Clear for repairs on 03/12/03. DCPS-Safety - Richard Gibson (RG 03/12/03) | |||
| FM-200224694 03 1/22/07 (Bowen) 1. Asbestos Assessment Required. Replace torn and ripped carpeting in the following: Learning center #1, 2, and 3. The carpeting in these area's are old and is a safety hazard. Asbestos Code A - Clear for repairs on 01/29/03. Horne Engineering - Tony Marcolin (RG 01/31/03) | |||
| FM-200503774 05 1/23/07 (Bowen) !!!VERY URGENT!!! 2nd Floor/Hallway: Door is broken, close to fast before students are able to get through. Student sustained injury today from the fast closing door. Code A-clear for repair by DCPS Charles Buchanan on 4/12/05 Repair was completed on 4/11/05 | |||
| FM-200206084 02 1/23/07 (Bowen) 1. Asbestos assessment required. 1st floor/Learning center #2: Need screens for windows; bugs flies and bees are entering the building. Asbestos Code A - Clear for repairs on 04/30/02. DCPS Safety - Ronald Edwards (RG 04/30/02) | |||
| FM-200204114 02 1/23/07 (Bowen) Asbestos Assessment Reqd. 1st floor/door #6 by gym Replace panic bar which is now off. (panic bar on site but may need longer bolts); replace door closures 1st floor learning ctr. #1, 2nd floor learning ctr. #3; 3rd floor room 311, and 2nd hallway exit door. Asbestos Code A - Clear for repairs on 6/06/02 DCPS Safety - R. Edwards, (RE - 6/06/02) | |||
| FM-200216937 02 1/27/07 (Bowen) ***Urgent*** 3rd Floor: Replace broken lock in room #303 and 304. Need master key for classroom #301. Asbestos Code A - Clear for repairs on 09/10/02. DCPS Safety - Leroy Minton Jr. (RG 09/11/02) | |||
| FM-200215544 02 1/27/07 (Bowen) !!!VERY URGENT!!! Main hallway: Slop sink is running over flooding the floors. | |||
| FM-200517277 06 1/29/07 First floor, Learning Center. "Urgent" Repair or Replace lock on office door there is no way to secure room. Note: Cameras and additional items of value are stored in this office, some items are already missing. | |||
| FM-200514433 /05 2/8/07 Bowen Boiler Room Repair or replace burners #1 (burnt smell) and #2 (lock out mode) Building only have two (2) Boilers for heat. Urgent !!!! |