Description Open Date Close Date Time Elapsed
FM-200119692 01 10/9/01 (CLEVELAND) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ KITCHEN THE KITCHEN SINK IS LEAKING WATER FROM UNDER THE SINK. THE TRAP NEEDS TO BE REPLACED. THE SIZE LOOKS TO BE 1" IN SIZE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/17/01. LEROY MINTON - SAFETY (202)576-6691 September 13, 2001 October 9, 2001 26 days
FM-200121174 /01 10/26/01 (CLEVELAND) PLAYGROUND !!! URGENT !!! PROVIDE SECURITY CHAIN & LOCK ON THE EAST SIDE GATE (ALLEY SIDE). TO SECURITY SITE AT CLEVELAND E.S. GIVE KEYS TO MS. V. WATKINS. October 24, 2001 October 26, 2001 2 days
FM-200119688 01 11/13/01 (CLEVELAND) ASBESTOS ASSESSMENT REQ. THE BACK DOOR OF THE BUILDING NEEDS A NEW PANIC BAR REPLACEMENT. IT KEEPS GETTING HUNG. THE CENTER BAR ALSO NEEDS REPAIR OR WELDING BEFORE IT FALLS AGAIN AND HIT SOMEONE IN THE HEAD. IT IS A SAFETY HAZARD WAITING TO HAPPEN. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/14/01 BILL CAMPION OF HORNE ENGINEER September 13, 2001 November 13, 2001 61 days
FM-200123290 /01 11/19/01 (CLEVELAND @ K.C. LEWIS) OUTSIDE/ FRONT ENTRANCE OF BUILDING REPAIR CONCRETE BLOCKS. BLOCKS ARE UNEVEN AND HAS BECOME A SAFETY HAZARD. ONE CHILD HAD TO BE TAKEN TO HOSPITAL DO TO TRIP HAZARD. November 14, 2001 November 19, 2001 5 days
FM-200122432 /01 11/19/01 (CLEVELAND) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ NURSES OFFICE RESTROOM TOILET IS STOPPED UP AND OVERFLOWS ONTO FLOOR. WE NEED TO HAVE IT UNCLOGGED. NO ONE CAN USE IT AT ALL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. LEROY MINTON - SAFETY (202)576-6691(RG) October 26, 2001 November 19, 2001 24 days
FM-200123098 01 12/10/01 (CLEVELAND) (3) OUTSIDE LIGHTS ARE OUT IN (3) NEW LIGHT FIXTURES MAY NEED BULBS OR SENSORS CHECKED ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/08/01 RICHARD GIBSON - SAFETY (202)576-5584(RG) November 8, 2001 December 10, 2001 32 days
FM-200123399 /01 1/18/02 CLEVELAND THIRD FLOOR CORRIDORS. WATER FOUNTAIN LEVEL NEEDS TO BE ADJUSTED. WATER LEVEL IS SO LOW THAT WATER FOUNTAIN CANNOT BE USED BY STUDENTS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/16/01. LEROY MINTON - SAFETY (202)576-6691 (RG) November 15, 2001 January 18, 2002 64 days
FM-200123546 02 2/1/02 (CLEVELAND) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR @ ROOM 103 NEED A PANIC BAR ON RECENTLY INSTALLED ON NEW DOOR. ABSENCE OF PANIC BAR CREATES A SAFETY AND SECURITY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/26/01 LEROY MINTON - SAFETY (202) 576-6691 (RG) January 30, 2002 February 1, 2002 2 days
FM-200123291 02 2/1/02 (CLEVELAND) ASBESTOS ASSESSMENT REQ. NEW DOOR HAS BEEN INSTALLED. BUT IT HAS NO PANIC BAR. WE NEED A PANIC BAR INSTALLED, THIS IS A SAFETY HAZARD. ONE OF OUR KIDS MAY PUSH IT IOPEN AND KEEP GOING. CODE A - CLEAR FOR REPAIRS AS OF 11/20/01 (SG). January 30, 2002 February 1, 2002 2 days
FM-200204030 02 3/11/02 (Cleveland) ****Urgent**** Basement Boiler Room Exit Door Boiler room exit door needs a panic bar installed on it. A padlock now used cannot be left off because the door can be pulled open from the outside and this poses a safety hazard to both students and staff. March 7, 2002 March 11, 2002 4 days
FM-200203908 02 3/19/02 (Cleveland) ****Urgent**** 1st Floor by Boys Restroom Water fountain needs repair work done because it is very unstable . The water continues to leak from the trap onto the floor and the trap nut, which is split in half, should be replaced. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/06/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG 03/06/02) March 5, 2002 March 19, 2002 14 days
FM-200203905 02 3/19/02 (Cleveland) Asbestos asseeement req. 1st floor/ Corridor Repair water fountain. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/06/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG 03/06/02) March 5, 2002 March 19, 2002 14 days
FM-200204690 02 3/25/02 (Cleveland) ****Urgent**** Asbestos Assessment Required 2nd Floor Room 209 Install a new lock on the door to the counselors office wehre confidential student records must be kept under lock & key. Code A-clear for repair by Horne Engineer ( Sharon Voss ) 0n 3/20/02 (CEB) March 19, 2002 March 25, 2002 6 days
FM-200116369 01 4/15/02 (CLEVELAND) 1. ASBESTOS ASSESSMENT REQUIRED. Work permit is needed to allow the removal of TV wall mounts and TV sets from the building. Only Rooms with wall mounts will neccesitate wall disturbance. Classroom Nos. with wall mounts: 100, 103, 104A, 105A, 200, 203A, 204, 300, 302, 304, Requester Phone: 576-7272 ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. CHARLES BUCHANAN - SAFETY (202)576-5582 July 30, 2001 April 15, 2002 259 days
FM-200108465 16/01 4/15/02 CLEVELAND THIRD (3RD) FLOOR - BOYS RESTROOM FILL IN HOLE AROUND HEAT RISER (ON FLOOR). HOLE HAS NOT BEEN FILL IN WITH CEMENT. THE KIDS ARE DROPPING TRASH INSIDE THAT HOLE. HEALTH AND SAFETY HAZARD. April 16, 2001 April 15, 2002 364 days
FM-200203401 02 5/14/02 (Cleveland) Basement Boiler Room Exit Door Need a panic bar installed on the basement boiler room exit door. Unable to leave padlock off because the door can be pulled open from the outside. This situation poses a safety hazzard for both staff and students. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/26/02 HORNE ENGINEER: STEPHEN CALDWELL February 25, 2002 May 14, 2002 78 days
FM-200202752 02 5/24/02 (CLEVELAND) 3RD FLOOR/LANDING: WE NEED TO HAVE EIGHT PIECES OF FLOOR TILE REPLACED ON STAIRWELL LANDING. THE ASBESTOS ASSESSMENT HAS BEEN COMPLETED, AND (16) PIECES OF TILE SHOULD BE REPLACED IN THE STAIRWELL LANDING. (THIS IS A SAFETY HAZARD, THE STUDENTS ARE TRIPPING ON THE STAIRWELL) ASBESTOS CODE A-CLEAR FOR REPAIR ON 02/11/02 HORNE ENGINEER: SHARON VOSS February 11, 2002 May 24, 2002 102 days
FM-200203574 02 6/5/02 (Cleveland) ***Urgent*** 1st Floor Boys Restroom Sink Repair Bradley basin or install a new drain. The basin leaks from the bottom when water runs into the drain and spills onto the floor. February 27, 2002 June 5, 2002 98 days
FM-200204032 02 7/2/02 (Cleveland) ****Urgent**** Asbestos Assessment Reqd. 3rd Floor Landing Landing door on the 3rd floor, leading into the hallway has a broken door closure which needs replacement. [Fire Inspector Tillman was at the chool on Jan. 3, 2002 and said the closure had to be replaced--possible fire-code violation.] Horne assessment and design required; damage door integument exposing insulation within. DCPS Safety R. Edwards 5/17/02 Code A-clear for repair by Horne Engineer ( Stephen Caldwell ) on 5/16/02 March 7, 2002 July 2, 2002 117 days
FM-200225044 03 6/23/03 Cleveland Third floor - boy's restroom Bradley basin is leaking water onto the floor. The kids are slipping and falling in the water. This is a safety hazard for us. January 31, 2003 June 23, 2003 143 days
FM-200220097 /02 8/23/04 Lewis, K.C. / Cleveland Hot method floor tile removal SE stairwell. Second floor - Stairwell Steps Replace loose 9x9 floor tile on stairwell steps. Located between second floor landing and next set of steps downward. Asbestos Code A - Abated and cleared for repairs on 11-14-02 (LM/11-19-02) per Leroy Minton confirmation. Safety Office 202-576-8962. October 28, 2002 August 23, 2004 665 days
FM-200224551 03 8/23/04 Cleveland/ KC Lewis Fisrt floor - all purpose room Install missing ceiling tile in all purpose room. Some tiles are loose and just hanging. We do not have a ladder to do the job. Safety hazard. Asbestos Code A - Clear for repairs on 01/28/03. Horne Engineering - Sharon Voss ( RG 01/30/03) January 24, 2003 August 23, 2004 577 days
FM-200218697 02 8/23/04 Cleveland First floor - all purpose room Have loose and missing ceiling tile in the all purpose room. Our ladders are unsafe to go up and make the replacement ourself. Asbestos Code A - Clear for repairs on 10/09/02. DCPS Safety - Leroy Minton Jr. (RG 10/10/02) October 2, 2002 August 23, 2004 691 days
FM-200228166 03 8/23/04 Cleveland Third floor room 309 and 308 The rod that runs through the body of door is broken. Both doors have splits. Door may fall on someone. This is a safety hazard. Repair or replace doors. Asbestos Code A-clear for repair by Horne Engineering Sharon Voss on 04/07/03 Charles Buchanan April 2, 2003 August 23, 2004 509 days
FM-200124627 01 8/23/04 (CLEVELAND) ASBESTOS ASSESSMENT REQ. GROUNDS/ SCHOOL PARKING LOT AT THE REAR ENTRANCE OF THE BUILDING. THE HANDRAIL FELL DOWN. WE NEED TO HAVE THE HAND RAIL PUT BACK UP. HAND RAIL HAS TO SET UP WITH CONCRETE ON CONCRETE BLOCK. HAND RAIL IS ON THE NORTH SIDE OF THE BUILDING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/13/01. RONALD EDWARD - SAFETY (202)576-6693 December 6, 2001 August 23, 2004 991 days
FM-200508885 05 9/20/05 Cleveland Fire Code Violation - IFC - 1008.1.2 First Floor - Front Entrance 1) Front entrance exit door difficult to open. Asbestos Code A - Clear for repairs on 07/28/05. DCPS Safety - Richard Gibson (RG) July 28, 2005 September 20, 2005 54 days
FM-200515036 05 11/4/05 Urgent: Repair lock on door to rm. 302 on the third floor and room 115. The cylinder keeps turning. November 3, 2005 November 4, 2005 1 day
FM-200454982 04 3/8/06 (Cleveland) !!!URGENT!!! 1st Floor/Teachers Lounge: Install outlet for copier. September 17, 2004 March 8, 2006 537 days
FM-200459141 04 3/8/06 Cleveland To have marquee school sign set up. Have the bolt kit from vendor. Asbestos Code A - Clear for repairs on 12/03/04. DCPS Safety -Richard Gibson (RG 12/03/04) December 3, 2004 March 8, 2006 460 days
FM-200517380 06 3/8/06 Cleveland Boiler Room Correct problems with gaskets leaking again in front section of boilers #1 and #2 Urgent !!!! January 12, 2006 March 8, 2006 55 days
FM-200619875 06 3/17/06 Cleveland Boiler Room Repair or replace Boiler #2. Boiler will not lite off. Both boilers are down at present (No heat). Urgent !!!! March 14, 2006 March 17, 2006 3 days
FM-200515355 /05 6/6/06 Cleveland Boiler Room Repair or replace burner on Boiler #1. will not lite off. Only (2) Boiler on site and the other did not pass inspection. Urgent !!!!! November 10, 2005 June 6, 2006 208 days
FM-200628940 06 10/24/06 Cleveland Rooftop Unit Check and repair cooling tower on roof.Cooling tower is overflowing down the wall and damaging the walls in room #308. Bad solenoid valve. Urgent !!!!! September 7, 2006 October 24, 2006 47 days
FM-200628191 06 12/21/06 2nd Floor- Room 201 Repair broken window. Asbestos Code A - Clear for repairs on 08/24/06. DCPS Safety - Richard Gibson (RG) August 23, 2006 December 21, 2006 120 days
FM-200505421 05 1/11/07 (Cleveland) Emergency First floor, Main Office. Install aluminum transition strip. (Threshold Plate) Note: tripping hazard Asbestos Code A - Clear for repairs on 05/17/05. DCPS Safety - Richard Gibson (RG) May 12, 2005 January 11, 2007 609 days
FM-200513290 05 3/30/07 (Cleveland) "Emergency" First floor, Pre-K classroom. Need carpenters to secure sound proof ceiling tile it is currently hanging. School staff did not have the appropriate tool to perform task. Note: This is a safety hazard. Asbestos Code A - Clear for repairs on 09/29/05. Tidewater - Philp Connolly (RG 09/30/05) September 29, 2005 March 30, 2007 547 days
FM-200505981 05 3/30/07 Cleveland Main Office Floor Install Alluminum Thress Hold Asbestos Code A - Clear for repairs on 05/25/05. DCPS Safety - Richard Gibson (RG) May 25, 2005 March 30, 2007 674 days