Urgent Open Repair Requests
See Also: All Open Repair Requests at Green Elementary School
Detailed Reports
| Description | Open Date |
|---|---|
| FM-200213993 8/9/02 Green ****Urgent**** Room 109 [St. John] Replace steady, continuously leaking faucet in the above room. Asbestos Code A - Clear for repairs on 08/09/02. DCPS-Safety - Richard Gibson (RG 08/09/02) | |
| FM-200219954 10/24/02 Green Urgent!!! Repair and replace handrail on the third floor steps way. Asbestos Code A-clear for repair by DCPS on DCPSS Charles Buchanan | |
| FM-200340626 11/21/03 (Green) Exterior of Building: Repair concrete walk-way near main entrance Asbestos Code A - Clear for repairs on 11/21/03. DCPS Safety - Richard Gibson (RG) | |
| FM-200450519 7/20/04 Green First floor All - purpose room Replace missing ceiling tiles in all purpose room six (6) pieces. Asbestos Code A - Clear for repairs on 07/20/04. DCPS Safety - Richard Gibson (RG) | |
| FM-200503401 3/30/05 (Green) Asbestos Assessment Required. Second floor, Hallway. Repair or Replace drinking fountain. Asbestos Code A - Clear for repairs on 03/30/05. DCPS Safety - Richard Gibson (RG) | |
| FM-200503425 3/30/05 (Green) Asbestos Assessment Required. Exterior of building/Near Parking Lot Repair structural damage on corner of building near parking lot. Asbestos Code A - Clear for repairs on 03/30/05. DCPS Safety - Richard Gibson (RG 03/30/05) | |
| FM-200505311 5/10/05 ( GREEN ) URGENT!!!!! First Floor - Room130 (Computer Lab) 1) Repair ceiling, (it's falling due to over head bathroom leak). Note: (refer to FM-200505310) | |
| FM-200622771 5/16/06 Green Boiler Room Repair or replace sump pump in Boiler Room. Boiler Room is flooded. Urgent !!!!! | |
| FM-200634140 1/19/07 Nurse Office - Asbestos assessment may be required for ceiling materials and pipe insulation. Repair leaking pipe in ceiling of nurse's offices. Asbestos Code C on 01/24/07. Tidewater - Roger Small (RG 01/24/07) Asbestos Code A - Abated and cleared for repairs on 01/31/07 by Goel Construction (LM/02-08-07) Safety Office 202-576-8962 | |
| FM-200701662 62 3/13/07 Boiler room - URGENT!!!! Complete installation of sump pumps, contractor started on repairs several months ago and has not return to complet repairs. |