FM-200117468 01 8/29/01 (HARRIS, C.W.) FIRE CODE VIOLATION: F-110.1 PAGE (2 OF 2) 1. ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR/ROOM #236 (TIME OUT ROOM) HOLES NEED PATCHING IN ROOM #236. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 08/15/01. RONALD EDWARD - SAFETY (202)576-6693 August 14, 2001 August 29, 2001 15 days
FM-200117470 01 8/29/01 (HARRIS, C.W.) FIRE CODE VIOLATION: F-110.1 PAGE (2 OF 2) 1. ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR/TIME OUT ROOM: CEILING TILE MISSING. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 08/15/01. RONALD EDWARD - SAFETY (202)576-6693 August 14, 2001 August 29, 2001 15 days
FM-200119011 01 9/7/01 (HARRIS, C.W. ) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ 34 WING FLOOD ON 2ND FLOOR. URINAL WONT STOP RUNNING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/04/01. LEROY MINTON - SAFETY (202)576-6691 (RG) September 4, 2001 September 7, 2001 3 days
FM-200117478 01 9/25/01 (HARRIS, C.W.) FIRE CODE VIOLATION: F-303.4 PAGE (2 OF 2) 1. ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR/ROOM #241: DOOR NEEDS ADJUSTING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/10/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/23/01 HORNE ENGINEER : SHARON VOSS August 15, 2001 September 25, 2001 41 days
FM-200119747 01 10/9/01 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. PRE-K K WING/ GIRL BATHROOM THIRD STALL NEEDS A NEW FLUSH VALVE ASSEMBLY WATER CONSTANTLY RUNNING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/17/01. LEROY MINTON - SAFETY (202)576-6691 September 13, 2001 October 9, 2001 26 days
FM-200118545 01 10/22/01 HARRIS, C.W. ASBESTOS ASSESSMENT REQ. MAIN OFFICE 1) REPLACE STAIN CELING TILE IN THE MAIN OFFICE. (FIFTY PIECES) ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. SYLIVA GRIMES - SAFETY (202)576-5583 August 27, 2001 October 22, 2001 56 days
FM-200117441 01 10/22/01 (HARRIS, C.W.) FIRE CODE VIOLATION: F-110.1 PAGE (1 OF 2) HOLE IN CEILING IN THE MULTIPURPOSE ROOM AND MAIN OFFICE. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 08/15/01. RONALD EDWARD - SAFETY (202)576-6693 August 14, 2001 October 22, 2001 69 days
FM-200122188 /01 11/14/01 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. PRE-K WING/ 1ST FLOOR GIRLS BATHROOM 3RD STALL WATER PRESSURE WILL NOT CUT OFF. ASBESTOS CODE A - CLEARED FOR REPAIRS 10-24-01. (LM) SAFETY OFFICE 202-576-8962. October 23, 2001 November 14, 2001 22 days
FM-200122788 01 11/29/01 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM 2ND STALL STOP VALVE WATER IS LEAKING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. LEROY MINTON - SAFETY (202)576-6691(RG) November 1, 2001 November 29, 2001 28 days
FM-200120944 01 12/11/01 C. W. HARRIS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE (1) 1" NIPPLE ON BOILER #2 FEED WATER LINE. NIPPLE IS BROKEN OFF IN TEE 1-1/4 X 1-1/4 X 1. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/03/01. LEROY MINTON - SAFETY (202)576-6691 (RG) October 3, 2001 December 11, 2001 69 days
FM-200127235 02 1/23/02 (HARRIS, C.W.) 1ST FLOOR/ INTERIOR DOORS STAIRWAY #3 (2) TWO PLEXIGLASS PIECES ARE OUT OF THE DOOR. NEEDS TO BE REPAIRED OR REPLACED BEFORE SOMEONE GETS HURT. January 10, 2002 January 23, 2002 13 days
FM-200201896 02 1/28/02 (HARRIS,C.W.) ***EMERGENCY*** 1ST FLOOR LOBBY/FRONT ENTRANCE 1) WIRE MESH GLASS IN FRONT ENTRANCE DOOR WAS SHATTERED OVER THE WEEKEND & HAS A LARGE HOLE IN IT (POSES A SAFETY HAZARD TO STUDENTS) January 28, 2002 January 28, 2002 0 days
FM-200111474 01 2/4/02 HARRIS, C.W. FIRST FLOOR GIRLS RESTROOM PRE-KINDERGARTEN AND KINDERGARTEN WING 1) REPLACE SINK ON BRACKET ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/21/01. LEROY MINTON - SAFETY (202)576-6691 May 29, 2001 February 4, 2002 251 days
FM-200204889 02 3/27/02 (Harris, C.W.) **Urgent** 1. Asbestos assessment required. 1st Floor/Health suite: Unable to secure medications; locks need to be changed on medicine cabinet. Asbestos Code A - Clear For Repairs On 03/25/02. DCPS Safety - Richard Gibson (RG 03/25/02) March 25, 2002 March 27, 2002 2 days
FM-200204948 02 5/3/02 (Harris, C.W.) 1. Asbestos assessment required. 2nd floor/wing boys bathroom #5 & 6: Urinals (back-up in trap) Asbestos Code A - Clear For Repairs On 03/27/02. DCPS Safety - Leroy Minton Jr. (RG 03/27/02) March 26, 2002 May 3, 2002 38 days
FM-200204947 02 5/3/02 (Harris, C.W.) 1. Asbestos assessment required. 1st floor/boys bathroom: Urinals backed up in trap. Asbestos Code A - Clear For Repairs On 03/27/02. DCPS Safety - Leroy Minton Jr (RG 03/27/02) It was discovered on 04-25-02 that this job would need O&M (clean-up) before the plumbing work could proceed. The O&M was conducted and cleared by Leroy Minton Jr. of DCPS Safety on 04-25-02. (LMJ) March 26, 2002 May 3, 2002 38 days
FM-200208135 02 6/3/02 Harris,C.W. ****Urgent**** 2nd Floor Boys' Restroom The pipe running under the floor has a hole in it and the water leaking out of it is going down into the 1st floor restroom. May 21, 2002 June 3, 2002 13 days
FM-200209289 02 6/17/02 Harris,C.W. ****Urgent**** 1st Floor Teachers' Restroom The door is locked and can not be opened. June 11, 2002 June 17, 2002 6 days
FM-200210782 02 7/10/02 (Harris, C.W.) **Urgent** 1st Floor/Lobby: Glass broke in window next to exit door near asst. principal's office. Asbestos Code A - Cleared for repairs on 07-05-02 (LM) Leroy Minton Safety Office 202-576-8962. July 8, 2002 July 10, 2002 2 days
FM-200205882 02 8/20/02 Harris, C.W. Second (2nd) Floor - Boys Restroom Urinal next to partition needs a new wax rings, water running onto the floor. Safety Hazard. April 16, 2002 August 20, 2002 126 days
FM-200215103 02 8/21/02 Harris,C.W. ****Urgent/BREAK-IN**** Asst. Principal's Office 2. Replace lock damaged during an attempted break-in. August 20, 2002 August 21, 2002 1 day
FM-200215099 02 8/21/02 Harris,C.W. 1st Floor Room 109 Replace wire-mesh safety glass--broken out. August 20, 2002 August 21, 2002 1 day
FM-200215555 02 8/27/02 Harris,C.W. ****Urgent/BREAK-IN**** 1st Floor Room 142 Weld the window guard back that was pulled away during a break-in at room 142. August 26, 2002 August 27, 2002 1 day
FM-200215556 02 9/10/02 Harris,C.W. ****Urgent/BREAK-IN**** 1st Floor Rooms 143, 145 & 153 Long side windows broken out in all three areas during a break-in need replacement. August 26, 2002 September 10, 2002 15 days
FM-200103351 2/8/01 9/16/02 HARRIS, CW CW HARRIS PRE -K PLAYGROUND NEED THE CHAR SCRAPE UP FROM OLD BURNED PADING. SO THEY CAN START PLACING NEW PADING DOWN. PER SH....WILL HAVE CXB CHANGE TO ALLOW PERMIT CREATION. CODE A-CLAER FOR REPAIR BY DCPS SHEILA HOWARD SAFETY February 8, 2001 September 16, 2002 585 days
FM-200219387 /02 10/23/02 C.W. Harris first floor hallway near Pre-k "URGENT" 1. Asbestos assestment may be required. 2. Repair leak on 6" heating hot water supply line at valve flange. Asbestos Code C on 10/16/02 DCPS Charles E. Buchanan October 15, 2002 October 23, 2002 8 days
FM-200110504 01 3/14/03 C.W. HARRIS ROOF 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE A 2" SHUT OFF VALVE ON THE COOLING TOWER (DRAIN). (NO INSULATION ON VALVE) ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/21/01. MR. LEROY MINTON - SAFETY (202)576-6691 May 17, 2001 March 14, 2003 666 days
FM-200225940 03 3/26/03 C.W.Harris Boiler room Repair # 3 boiler it off on safety (P3 open) February 20, 2003 March 26, 2003 34 days
FM-200228418 03 4/22/03 (Harris, C.W.) !!!URGENT!!! Asbestos Assessment Required. 1st Floor/Cafeteria: Broken window April 7, 2003 April 22, 2003 15 days
FM-200202358 02 4/29/03 HARRIS, C.W. REQUEST ASBESTOS ASSESSMENT OF SCOPE OF WORK ATTACHED. SCHOOL GROUNDS - EXTERIOR WORK ONLY 1) REPLACE CHAINLINK FENCE,REPLACE CONCRETE/MASONARY RETAINING WALL WITH CAPSTONE, REPAIR OR REPLACE ASPHALT PAVING AND OR CONCRETE PAVING /STAIRS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/04/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG) February 4, 2002 April 29, 2003 449 days
FM-200118364 01 4/29/03 (HARRIS C.W.) ASBESTOS ASSESSMENT REQ. NEED FENCE LINE REPAIR ALL THE WAY AROUND THE GROUNDS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/03/01. RICHARD GIBSON- SAFETY (202)576-5584(RG) August 24, 2001 April 29, 2003 613 days
FM-200226936 03 5/2/03 (Harris, C.W.) !!!URGENT!!! 1st Floor/Stairwell #1: Very difficult to open, and close exit door. Asbestos Code A - Clear for repairs on 03/24/03. Horne Engineering - Sheryll James (RG 03/25/03) March 12, 2003 May 2, 2003 51 days
FM-200329302 03 5/15/03 (Harris) !!!URGENT!!! C.W. Harris Second Floor 5/6 Wing Boy's Restroom: Unstop 2 urinals; Girl's Restroom: Unstop 3 water closets (all will be marked with grey tape) Asbestos Code A - Cleared for repairs on 04-30-03 by Leroy Minton Jr. (LM/04-08-03) the Safety Office 202-576-8962. April 30, 2003 May 15, 2003 15 days
FM-200332702 03 7/2/03 (Harris) !!!VERY URGENT!!! 1st Floor/Room #143: Due to break-in, two (2) windows were broken. June 30, 2003 July 2, 2003 2 days
FM-200218371 02 7/24/03 Harris,C.W. ****Very Urgent/BREAK-IN**** 1st Floor Restroom/Primary Wing Replace broken window pane. September 26, 2002 July 24, 2003 301 days
FM-200340888 03 12/1/03 (Harris) !!!VERY URGENT!!! 2nd Floor/Boys Restroom: Leak in cold water supply line on sink; unable to shut water off. December 1, 2003 December 1, 2003 0 days
FM-200445201 04 3/11/04 Harris, C.W. Urgent !!! Front Of Building 1) Repair uneven pavement in front of the school. Teachers has fallen down. March 11, 2004 March 11, 2004 0 days
FM-200454427 04 11/30/04 Harris C.W. Room 149 Fabricate drip pan for the univent in room 149 Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Leroy Minton Jr. (RG 09/13/04) September 13, 2004 November 30, 2004 78 days
FM-200227872 03 3/7/05 (Harris, C.W.) !!!VERY URGENT!!! 1st Floor/Outside window: Window at the end of the hallway, has been vandalized; grates torn from the window. March 28, 2003 March 7, 2005 710 days
FM-200501897 05 3/24/05 Harris, C.W. Stairwell 1 Hand rail broken. Asbestos Code A - Clear for repairs on 02/23/05. DCPS Safety - Richard Gibson (RG) February 23, 2005 March 24, 2005 29 days
FM-200126471 /01 6/2/05 (HARRIS,C.W.) LOBBY/PARENT CENTER ROOM UNIVENT IS LEAKING THROUGH THE CEILING CAUSING THE PLASTER CEILING TO PEEL. WATER IS DRIPPING & POOLING IN DIFFERENT AREAS OF THE CEILING. POC: Mr. Thornton 202-645-3188 building based staff. (same as FM-200204887) Asbestos Code A - Clear for repairs. Abated on 05/29/02 per Leroy Minton confirmation. Safety Office 202-576-8962. December 31, 2001 June 2, 2005 1,249 days
FM-200505152 05 6/14/05 ( HARRIS, C.W. ) First Floor - Stairwell 1 1) Repair doors, will not open or close properly. Asbestos Code A - Clear for repairs on 05/05/05. DCPS Safety - Richard Gibson (RG) May 5, 2005 June 14, 2005 40 days
FM-200456924 /04 8/1/05 Harris, C.W. Exterior Grounds 1) Repair or replace playground tiles and change safety rails. Poc - Oscar Mebane - 202-345-0688 October 18, 2004 August 1, 2005 287 days
FM-200457867 04 8/30/05 Harris, C.W. First floor nurse suite Ceiling tile need to be replace. Asbestos Code A - Clear for repairs on 11/03/04. DCPS Safety - Richard Gibson (RG) November 3, 2004 August 30, 2005 300 days
FM-200508226 05 9/7/05 Harris, C.W. "Fire Code Violation" Second floor Fallen ceiling tile in teachers lounge (IFC 703.1) Asbestos Code A - Clear for repairs on 07/21/05. DCPS Safety - Richard Gibson (RG) July 20, 2005 September 7, 2005 49 days
FM-200508224 05 9/7/05 Harris, C.W. "Fire Code Violation" Second floor Missing ceiling tile in hallway (IFC 703.1) Asbestos Code A - Clear for repairs on 07/21/05. DCPS Safety - Richard Gibson (RG) July 20, 2005 September 7, 2005 49 days
FM-200216908 02 11/18/05 Harris,C.W. ****Urgent**** Exterior of Building Install exterior lights on rear of building and D-Street side. September 6, 2002 November 18, 2005 1,169 days
FM-200222414 /02 11/18/05 (Harris, C.W.) !!!VERY URGENT!!! 2nd Floor Hallway: Water leaking from roof down in-to 2nd floor hallway. At the time of the snow and ice this week, the area was leaking profusely. December 12, 2002 November 18, 2005 1,072 days
FM-200222438 /02 11/18/05 (Harris, C.W.) !!!VERY URGENT!!! First floor - custodial office Roof is leaking. December 12, 2002 November 18, 2005 1,072 days
FM-200335092 03 11/18/05 Harris,C.W. Room #109, #144, #145, #212 & #217 Safety Insulated pipes in rooms #109, #144, #145, #212 and #217, condensation leaks from univents. Asbestos Code A - Clear for repairs on 08/14/03. Horne Engineering - Philp Connolly ( RG 08/18/03 ) August 13, 2003 November 18, 2005 828 days
FM-200204887 02 11/18/05 (Harris,C.W.) ****Urgent**** Asbestos Assessment Required 1st Floor Lobby Parents Center Room Parents Center had a ceiling leak causing the ceiling plaster to crumble and fall. Plastering and painting can now be done. Asbestos Code A - Clear for repairs.(LM) Abated on 05/29/02 per Leroy Minton confirmation. Safety Office 202-576-8962. March 25, 2002 November 18, 2005 1,334 days
FM-200505979 05 11/18/05 (Harris, C.W.) "Urgent" Asbestos Assessment Required. Second floor, Room 216. Replace wiremesh in light kit. Asbestos Code A - Clear for repairs on 05/27/05. Tidewater - Tony Marcolin (RG 06/02/05) May 25, 2005 November 18, 2005 177 days
FM-200507359 05 11/18/05 "Urgent" Outside Building. Repair or Replace exterior lights, currently they are out. June 30, 2005 November 18, 2005 141 days
FM-200342193 04 11/21/05 Harris, C.W. Safety Room #232 1) Fabricate and install protective covering over exterior of univent cabinet, Univent fan blades are exposed to students creating - A Severe Safety Hazard. Code A -claer for repair by DCPS Charles E Buchanan on 01/05/04 January 4, 2004 November 21, 2005 687 days
FM-200501099 05 11/21/05 Harris, C.W. Second floor room 206 Door check broken off from the door. The wooden door is assume to be asbestos door. The wooden door is in good condition have no sign on asbestos expose. Recommend that wooden door be remove in store in a secured places. if the is in the problem call Safety Office 202-576-8964 HA 097 fire door pain ted 3' X 7" (ACM) Code A-clear for repair by DCPS Charles Buchanan on 2/04/05 February 1, 2005 November 21, 2005 293 days
FM-200222519 /02 11/21/05 (Harris) !!!URGENT!!! 1st Floor/Main office: Malfunction panel box. Breaker tripping, interferring with fax machine and copy machine. December 13, 2002 November 21, 2005 1,074 days
FM-200209874 02 11/21/05 Harris,C.W. 1. Asbestos Assessment Reqd. 2nd Floor Stairwell #3 2. The door closer is broken off the the wood on the door is damaged. Repair or replace. Special Note: Confirmed by Leroy Minton, Jr. Of DCPS Safety 06-27-02 the doors are ACM and will be required to be removed by the asbestos abatement contractor. The work order did not go to Horne Eng. Sheila R. Howard-DCPS Safety 07-01-02 June 20, 2002 November 21, 2005 1,250 days
FM-200502501 05 11/21/05 (Harris, C.W.) !!!VERY URGENT!!! Asbestos Assessment Required. 2nd Floor/Room #206: Repair or replace pivot on door. Please repair as soon as possible, as the door was taken down for fear it would fall on students/staff. Classroom is without door. March 10, 2005 November 21, 2005 256 days
FM-200202103 02 11/21/05 (HARRIS,C.W.) ASBESTOS ASSESSMENT REQUIRED 2ND FLOOR BREAKER BOX SWITCH IN BOX IS NOT RESETTING TO "ON" POSITION (POWER TO A/C) IN ROOM 246. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/30/02 RICHARD GIBSON - SAFETY (202)576-5584 (RG)-01/30/02 January 30, 2002 November 21, 2005 1,391 days
FM-200214892 02 11/21/05 Harris,C.W. 1. Asbestos Assessment Reqd. 2nd Floor Teachers' Lounge 2. Install 240v outlet for new copier machines. Asbestos code A-clear for repair by DCPS SAfety Charles E Bichananon 8/20/02 Charles E. Buchanan August 16, 2002 November 21, 2005 1,193 days
FM-200218261 02 11/21/05 Harris,C.W. ****Urgent**** 1. Asbestos Assessment Reqd. 2nd Floor Hallway Floor tile is coming up in the hallway. September 25, 2002 November 21, 2005 1,153 days
FM-200508987 05 11/21/05 Harris, C. W. Boiler Room Thread bottom of 1 1/2" blow down line and add 45 degree eelbow for safety (pressure) relief valves on Boilers #1,#2 and #3 to comply with ASME Code for Annual Boiler Inspection. July 28, 2005 November 21, 2005 116 days
FM-200502777 05 11/21/05 (C.W. Harris) Asbestos Assessment Required Second floor/Room 206 Repair or Replace door, it is broken off hinges. Asbestos Code A - clear for repairs on 04/07/05. DCPS Safety - Richard Gibson (RG) March 16, 2005 November 21, 2005 250 days
FM-200209875 02 11/21/05 Harris,C.W. 1. Asbestos Assessment Reqd. 1st Floor Stairwell #3 2. The frame around the door on the outside was set on fire and needs to be replaced or repaired. Special Note: The doors were confirmed by Leroy Minton, Jr. of DCPS Safety 06-27-02 to be ACM. The doors must be removed by the asbestos abatement team. The work order did not go to Horne Eng. Sheila Howard-DCPS Safety 07-01-02. June 20, 2002 November 21, 2005 1,250 days
FM-200617460 06 1/19/06 Urgent: Cafeteria-Need a ladder so the bulbs can be changed; lights are out. January 17, 2006 January 19, 2006 2 days
FM-200122596 /01 4/14/06 (HARRIS, C.W.) ( MASONRY EXTERIOR ) A SMALL AREA ON THE BRICK WALL IN THE FRONT OF THE SCHOOL BUILDING IS CRACKING. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/01/01 DCPS SAFETY : CEB October 30, 2001 April 14, 2006 1,627 days
FM-200508242 05 4/19/06 Harris, C.W. "Fire Code Violation" First Floor Missing ceiling tile from leaking pipe (IFC 703.1) Asbestos Code A - Clear for repairs on 07/21/05. DCPS Safety - Richard Gibson (RG) July 20, 2005 April 19, 2006 273 days
FM-200625529 06 9/5/06 Exterior of Building/Playground Area. Install trim around safety turf. July 11, 2006 September 5, 2006 56 days
FM-200630367 10/3/06 10/11/06 Room 239. Repair or Replace door knob lock, the current knob lock is malfunctioning causing the door to jam. Note: This is a safety hazard! October 3, 2006 October 11, 2006 8 days
FM-200516803 /05 2/27/07 Urgent; Replace the lock on the custodial office door on the first floor December 20, 2005 February 27, 2007 434 days
FM-200625810 06 2/27/07 Second Floor/Ceiling tile missing, hallway near 218 Asbestos Code A - Clear for repairs on 07/18/06 DCPS Safety - Richard Gibson (RG) July 18, 2006 February 27, 2007 224 days
FM-200516804 /05 2/28/07 Urgent: Install a window guard on the outside of the boiler room on the first floor. December 20, 2005 February 28, 2007 435 days