FM-200115811 01 9/20/01 HEARST REPAIR PLAYGROUND EQUIPMENT DUE TO SAFETY INSPECTION July 25, 2001 September 20, 2001 57 days
FM-200122707 /01 12/15/01 HEARST PRINCIPALS OFFICE REPLACE A/C UNIT. (UNIT IS ON SITE) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/06/01 LEROY MINTON - SAFETY (202)576-6691(RG) October 31, 2001 December 15, 2001 45 days
FM-200205703 02 4/16/02 Hearst ***Urgent**** 1st & 2nd Floor Boys & Girls Restrooms 1) The 1st floor boys restroom has two toilets that are continuously flushing. 2) The 2nd floor girls restroom has one toilet that is overflowing onto the floor. April 11, 2002 April 16, 2002 5 days
FM-200213542 02 8/9/02 Hearst ****Urgent**** 2nd Floor Girls' Lavatory Repair continuously running toilet. August 5, 2002 August 9, 2002 4 days
FM-200109621 01 4/30/03 HEARST PLEASE NOTE THE ATTACHED COMMENTS FROM INSPECTOR JULIUS DANCY AND MAKE APPROPRIATE REPAIRS: KK 72-44 SAFETY RAIL - GAP IS TOO WIDE 75-10-1 WAVE SLIDE - RUBBER PAD TOO SHORT 78-23-1 STEEL SUSPENSION BRIDGE MISSING HEALTH AND SAFETY HAZARD. May 7, 2001 April 30, 2003 723 days
FM-200221190 /02 4/30/03 Hearst Outside Remove and/or replace the chain link on play area on playground equipment. Safety Hazard Rusted through with sharp edges exposed. November 18, 2002 April 30, 2003 163 days
FM-200118882 01 5/20/03 (HEARST) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR RESTROOM: TOILETS OVERFLOWED ON THE FIRST FLOOR NEAR MAIN OFFICE, SPILLING, AND SOAKING CARPET IN CORRIDOR; RAW SEWAGE IS PRESENT. ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 August 30, 2001 May 20, 2003 628 days
FM-200330917 03 6/20/03 Hearst Filling of sink hole next to the rear exterior steps. Safety issue - Recommended by Ronald Edwards. May 30, 2003 June 20, 2003 21 days
FM-200334978 03 9/3/03 Hearst Boiler Room Boiler, replace safety valve. Boiler failed D.C. Inspection. August 13, 2003 September 3, 2003 21 days
FM-200454343 04 12/8/04 (Hearst) !!!URGENT!!! 2nd Floor/Room #202: Sparks coming from lights when switch is turned on. September 10, 2004 December 8, 2004 89 days
FM-200453895 04 12/10/04 Hearst Second floor boys restroom Has hazard plaster on walls is chipping. Asbestos Code A - Clear for repairs on 10/25/04. DCPS Safety - Leroy Minton Jr. (RG 10/25/04) September 3, 2004 December 10, 2004 98 days
FM-200456652 04 8/1/05 (Hearst) !!!VERY URGENT!!! 1st Floor/Room #104: Ruptured pipe under sink, staff using mops to dry up the water that has flooded the floors. October 8, 2004 August 1, 2005 297 days
FM-200513410 05 10/6/05 (Hearst) "Urgent" Second floors, Boys' restroom. Urinals are leaking behind wall. October 3, 2005 October 6, 2005 3 days
FM-200338600 03 10/28/05 (Hearst) Asbestos Assessment Required. Broken toilets need to be replaced in boys lavatories first floor and second floor Health and safety issue-urgent August 8, 2003 October 28, 2005 812 days
FM-200329436 03 10/28/05 (Hearst) !!!EMERGENCY!!! 1st Floor/Boys Bathroom: Leaking urinal; health and safety issue, please expedite repair May 2, 2003 October 28, 2005 910 days
FM-200204024 02 10/28/05 (Hearst) Exterior of Bldg. Repair exterior lighting on playground side and increase exterior lighting on the parking lot side. Because areas are poorly lit, there is insufficient lighting for the after-school program and evidence of loitering on the playground & parking lot after regular school hours. Asbestos Code A - Clear For Repairs On 03/12/02. Ronald Edwards - Safety (202)576-6693 (RG 03/13/02) March 7, 2002 October 28, 2005 1,331 days
FM-200511265 05 10/28/05 Hearst Boiler Room Repair or replace domestic hot water heater. Heater will not come on. Urgent !!!! August 25, 2005 October 28, 2005 64 days
FM-200502585 05 10/28/05 (Hearst) Asbestos Assessment Required. Second floor/Boys' restroom Replace cracked commode. Asbestos Code A - Clear for repairs on 03/11/05. DCPS Safety - Richard Gibson (RG) March 11, 2005 October 28, 2005 231 days
FM-200331991 03 10/28/05 (Hearst) !!!VERY URGENT!!! 2nd Floor/Boys restroom: Toilet leaking down in-to the 1st floor, boys restroom, damaging ceiling. Students are using this restroom as the water is dripping on them. (Safety hazard) June 17, 2003 October 28, 2005 864 days
FM-200332967 03 11/2/05 (Hearst) Asbestos Assessment Required. Through-Out the Building: Ballast needed in the following area's: 1st Floor hall, girls lavatory, room #100, room #208-B, room #206, girls lavatory, room #200, and room #201. (We have no budget for pruchasing ballast) Asbestos Code A - Cleared for repairs on 07-07-03 by Leroy Minton Jr. (LM/07-07-03) Safety Office 202-576-8962. July 7, 2003 November 2, 2005 849 days
FM-200618592 06 2/16/06 Asbestos Assessment Required. Exterior of Building. "Emergency" Repair or Replace smoke stack (metal), it's corroded and causing a safety hsnzard. Asbestos Code A - Clear for repairs on 02/15/06. Tidewater - Tony Marcolin (RG 02/16/06) SEE ASSESSMENTS February 13, 2006 February 16, 2006 3 days
FM-200328957 03 2/24/06 Hearst Replacement of screened window. Boys lavatory first floor. We have the screen and tubing. We need a person who is skilled to repair a window. Urgent this is a safety issue. A child could fall from the window. April 22, 2003 February 24, 2006 1,039 days
FM-200508799 05 2/24/06 Hearst Boiler Room Replace leaking hartford loop and place safety valve in vertical position. Per Boiler Inspector. July 27, 2005 February 24, 2006 212 days
FM-200513099 05 2/24/06 Hearst Emergency First Floor-Boys Restroom The ceiling has collapsed. Need repair/replacement. Code A-clear for repairs as of 9/23/05 by Tidewater Thomas Johnson. Sylvia Grimes Safety. September 23, 2005 February 24, 2006 154 days
FM-200513411 05 2/24/06 (Hearst) "Urgent" First floors, Boys' restroom. Repair hole in ceiling fom leaking urinals on second floor. HA 008 Plater White No Asbestos HA 708 Brown coat With HA 008 Code A-clear for repair by DCPS Charles Buchanan on 10/4/05 October 3, 2005 February 24, 2006 144 days