January 2005 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    4
    Average Time Elapsed: 3.5 Days
  • Total Requests
    4

Detailed Reports

Routine Repair Requests Completed in January 2005 (4)
Description Open Date Close Date Time Elapsed
FM-200500281 05 1/11/05 Ballou Auto shop Replacement of exterior glass. January 10, 2005 January 11, 2005 1 day
FM-200500320 05 1/12/05 Ballou Art room unstop sink. January 11, 2005 January 12, 2005 1 day
FM-200500468 05 1/18/05 (Ballou) locksmith nd.to rekey rooms on the 2nd.floor,keys were lost by employee(contractors) nd.access. January 6, 2005 January 18, 2005 12 days
FM-200500790 05 1/25/05 BALLOU HEALTH SUITE REPLACE LIGHT BALLAST . January 25, 2005 January 25, 2005 0 days