Closed Repair Requests: October 2001

See Also: All Closed Repair Requests at Ballou Senior High School

October 2001 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    22
    Average Time Elapsed: 30.5 Days
  • Total Requests
    22

Detailed Reports

Routine Repair Requests Completed in October 2001 (22)
Description Open Date Close Date Time Elapsed
FM-200120755 01 10/3/01 BALLOU MARKING OF FOOTBALL FIELD October 1, 2001 October 3, 2001 2 days
FM-200120733 01 10/3/01 BALLOU MARKING OF FOOTBALL FIELD October 1, 2001 October 3, 2001 2 days
FM-200120734 01 10/3/01 BALLOU MARKING OF FOOTBALL FIELD 7:30 GAME October 1, 2001 October 3, 2001 2 days
FM-200109824 01 10/9/01 BALLOU SUBLEVEL BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. BUSTED 2" FWS LINE (PIPE). REPLACE 10 FT. 2" OF BLACK PIPING ON THE FEEDWATER SUPPLY LINE THAT CONNECTS TO THE AIR-SEPERATOR AND THE EXPANSION- TANK. NOTE: THIS BUSTED SUPPLY LINE WILL EFFECT THE COOLING PUMPS AND CENTRAVAC CHILLER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/26/01. HORNE ENG. - SAM EBRAHIM May 9, 2001 October 9, 2001 153 days
FM-200121087 01 10/9/01 BALLOU MARKING OF FOOTBALL FIELD October 5, 2001 October 9, 2001 4 days
FM-200118507 01 10/10/01 BALLOU OUTSIDE - GROUNDS RESTROOM REMOVE SPIKES IN FACADE NEAR TOILETS, PATCH HOLES & PAINT POC: RICARDO WELCH (202)438-7469 ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER BILL CAMPION DO NOT SCRAPE ANY OF THIS PAINT SURFACE RE-PAINT OVER ONLY. August 27, 2001 October 10, 2001 44 days
FM-200121105 01 10/11/01 BALLOU MARKING OF FOOTBALL FIELD October 5, 2001 October 11, 2001 6 days
FM-200121103 01 10/11/01 BALLOU MARKING OF FOOTBALL FIELD October 5, 2001 October 11, 2001 6 days
FM-200121108 01 10/12/01 BALLOU MARKING OF FOOTBALL FIELD October 5, 2001 October 12, 2001 7 days
FM-200117602 01 10/12/01 BALLOU FOOTBALL STADIUM & EAST OF EXISTING SCOREBOARD ASBESTOS ASSESSMENT REQUIRED INSTALL GLAZING IN PRESS BOX WINDOW ON FOOTBALL STADIUM AND REPAIR BROKEN WINDOW EAST OF EXISTING SCOREBOARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/27/01. HORNE ENGINEERS - SAM EBRAHIM (RG) August 16, 2001 October 12, 2001 57 days
FM-200121541 /01 10/16/01 MARKING OF FOOTBALL FIELD 7:30 GAME October 12, 2001 October 16, 2001 4 days
FM-200115294 01 10/16/01 BALLOU BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE FRONT MORRISON TUBER BURNER HUB ON #4 BOILER. CLEAVER BROOKS PACKAGED BOILER. BOILER INFO: CLEAVER BROOKS MOD. #760-125A, SER. #L47171. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/27/01 BY HORNE ENGINEER: EDWARD RODRIGUEZ July 16, 2001 October 16, 2001 92 days
FM-200121540 /01 10/16/01 BALLOU MARKING OF FOOTBALL FIELD 5:30 GAME October 12, 2001 October 16, 2001 4 days
FM-200113649 01 10/17/01 BALLOU BASEMENT LEVEL INSTALL ELECTRICAL CIRCUIT FROM TELEPHONE CLOSET TO OUTLETS IN HALLWAY. E.L.S. CONTRACTORS DANNY HUDSON (202) 576-8045 June 19, 2001 October 17, 2001 120 days
FM-200121546 /01 10/18/01 BALLOU MARKING OF FOOTBALL FIELD 3:00 GAME October 12, 2001 October 18, 2001 6 days
FM-200121547 /01 10/18/01 BALLOU MARKING OF FOOTBALL FIELD 5:30 GAME October 12, 2001 October 18, 2001 6 days
FM-200121557 /01 10/19/01 BALLOU MARKING OF FOOTBALL FIELD October 12, 2001 October 19, 2001 7 days
FM-200121969 /01 10/24/01 BALLOU MARKING OF FOOTBALL FIELD October 19, 2001 October 24, 2001 5 days
FM-200121876 /01 10/26/01 (BALLOU) 1ST FLOOR/ GIRLS BATHROON BY GYM !!! EMERGENCY !!! CRACK IN 4 OR 5 INCH WASTE LINE. October 18, 2001 October 26, 2001 8 days
FM-200121970 /01 10/26/01 BALLOU MARKING OF FOOTBALL FIELD October 19, 2001 October 26, 2001 7 days
FM-200119046 01 10/30/01 (BALLOU) 1. ASBESTOS ASSESSMENT REQUIRED. ALLOU 1ST FL. NORTH HALLWAY PANEL H1 REPLACE (1) BROKEN 20 AMP. CIRCUIT BREAKER AND INCREASE THE REPLACMENT BREAKER WITH (1) ONE 40 AMP. NOTE: THIS BREAKER CONTROLS THE BOILER ROOM LIGHTING #12. INFO: PANEL H-1 FEDERAL PACIFIC MOD. 881185, VOL. 265/460, TYPE-NHDP PH. 3. Requester Phone: 645-3385 Requestor Phone: 645-3385 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/01/01. HORNE ENGINEERING - ROGER KAGER (RG) August 23, 2001 October 30, 2001 68 days
FM-200118841 01 10/31/01 (BALLOU) 1ST FLOOR/ ATENDANCE OFFICE-107 !!!!!! EMERGENCY !!!!!! SPARKS COMING FROM PLUG OUTLETS. CHECK ELECTRICAL SERVICE AND INSTALL NEW OUTLETS. August 30, 2001 October 31, 2001 62 days

© The Washington Post Company