Closed Repair Requests: November 2003

See Also: All Closed Repair Requests at Ballou Senior High School

November 2003 Summary

  • Urgent Requests
    1
    Average Time Elapsed: 0 Days
  • Routine Requests
    3
    Average Time Elapsed: 4 Days
  • Total Requests
    4

Detailed Reports

Urgent Repair Requests Completed in November 2003 (1)
Description Open Date Close Date Time Elapsed
FM-200339884 03 11/4/03 Ballou Second Floor Nerw Building. - Space - 122 1) Install plywood bracket to cinder block wall. Asbestos Code A - Clear for repairs on 11/04/03. DCPS Safety - Richard Gibson (RG) November 4, 2003 November 4, 2003 0 days

Routine Repair Requests Completed in November 2003 (3)
Description Open Date Close Date Time Elapsed
FM-200339738 /03 11/3/03 Ballou Kitchen 1) Repair or replace block above electrical panel. October 31, 2003 November 3, 2003 3 days
FM-200340023 03 11/6/03 Ballou Second floor teachers room Install new flush valve. November 6, 2003 November 6, 2003 0 days
FM-200339857 03 11/12/03 Ballou School Repair hole in wall -cement buildup by cafateria door November 3, 2003 November 12, 2003 9 days