Closed Repair Requests: December 2006

See Also: All Closed Repair Requests at Ballou Senior High School

December 2006 Summary

  • Urgent Requests
    5
    Average Time Elapsed: 433.4 Days
  • Routine Requests
    9
    Average Time Elapsed: 858.3 Days
  • Total Requests
    14

Detailed Reports

Urgent Repair Requests Completed in December 2006 (5)
Description Open Date Close Date Time Elapsed
FM-200510507 05 12/11/06 (Ballou/Stay High School) "Urgent" Sub basement level/Rooms A4 and A6. Need masons to survey and repair exterior breaches in building causing leaks in the above classroom area. August 16, 2005 December 11, 2006 482 days
FM-200506283 05 12/11/06 (BALLOU) Front entrance 1) Resurface walkways (safety factor fourth request) Mr. Willie Hill has knowledge of the situation. May 31, 2005 December 11, 2006 559 days
FM-200622779 06 12/11/06 Survey: rm.#126, a hole in cinder block wall for internet wiring for # A127 to A126 the size of a quarter. Asbestos Code A - Clear for repairs on 05/17/06. DCPS Safety - Richard Gibson (RG) May 15, 2006 December 11, 2006 210 days
FM-200453733 04 12/11/06 (Ballou) URGENT-THE REPAVING OF PARKING LOT-NORTH-SAFTY HAZARD REQUEST FROM DR.HUDSON-PRICIPAL August 31, 2004 December 11, 2006 832 days
FM-200630085 06 12/14/06 Survey 110 outlet for 210 copier special ed.URGENT!! September 21, 2006 December 14, 2006 84 days

Routine Repair Requests Completed in December 2006 (9)
Description Open Date Close Date Time Elapsed
FM-200459710 /04 12/11/06 Ballou South-Parking Lot Area-ROTC Stabilize (3) heat pump units to foundation, also fence in area around the heat pumps. Note: Units are exposed, possible theft of these units. December 16, 2004 December 11, 2006 725 days
FM-200458340 /04 12/11/06 Ballou Main entrance Foundation for marquee with photo cell. November 16, 2004 December 11, 2006 755 days
FM-200446827 04 12/11/06 Ballou Grounds Around Cooling Tower 1). Pour a contrete slab aroung and graded away from cooling tower structure. 2). Install drainage pipeing around the outer edge of contrete slab to capture and redirect rain and ground water away from cooling tower structure. April 19, 2004 December 11, 2006 966 days
FM-200446086 04 12/11/06 Ballou Grounds Around Cooling Tower Clean area around cooling tower. Remove debris and cut down trees. March 30, 2004 December 11, 2006 986 days
FM-200514468 05 12/11/06 Ballou Furnish rope and hooks for hanging of U.S and district flags. September 23, 2005 December 11, 2006 444 days
FM-200442468 04 12/11/06 Ballou Please evaluate driveway and parking lot to determine if repaving is needed. If needed please pave. January 9, 2004 December 11, 2006 1,067 days
FM-200442466 04 12/11/06 Ballou Please evaluate driveway and parking lot to determine if repaving is needed. If needed please pave. January 9, 2004 December 11, 2006 1,067 days
FM-200206578 02 12/11/06 1) In accordance with grass cutting contract for the summer of 2002 to include grass cutting and edging. April 25, 2002 December 11, 2006 1,691 days
FM-200632316 20/06 12/14/06 Restore Power - Gym - Score Board + Clock System. November 20, 2006 December 14, 2006 24 days