Closed Repair Requests: March 2004

See Also: All Closed Repair Requests at Ballou Senior High School

March 2004 Summary

  • Urgent Requests
    1
    Average Time Elapsed: 244 Days
  • Routine Requests
    5
    Average Time Elapsed: 75.4 Days
  • Total Requests
    6

Detailed Reports

Urgent Repair Requests Completed in March 2004 (1)
Description Open Date Close Date Time Elapsed
FM-200333593 03 3/22/04 (Ballou) FIRE CODE VIOLATION: 2nd Floor: Safety glass in center stairwell #2. July 22, 2003 March 22, 2004 244 days

Routine Repair Requests Completed in March 2004 (5)
Description Open Date Close Date Time Elapsed
FM-200339669 /03 3/1/04 Ballou Health Suite -Ceiling Repair heating unit (split system) Information : Nordyne Carrier Unit ; Mod.#T3BA-048K sER#T3B970209-693 Note: No heat in this area. October 29, 2003 March 1, 2004 124 days
FM-200444454 04 3/4/04 (Ballou) Asbestos Assessment Required. 2nd. floor #207 r/r recess door hinge,unable to secure also a safty hazard. Code A-clear for repair by DCPS Charles Buchanan on 2/27/04 classroom has solid wooding door. February 25, 2004 March 4, 2004 8 days
FM-200445366 04 3/15/04 Backus Room 105 Pipe is leaking through the ceiling. March 15, 2004 March 15, 2004 0 days
FM-200333614 03 3/22/04 (Ballou) FIRE CODE VIOLATION: 1st Floor: Water leaking in electrical appliance, hallway, and main (lobby.) July 22, 2003 March 22, 2004 244 days
FM-200445653 04 3/23/04 Ballou Need to have two (2) master keys, attached is a copy of approval from Mrs. White. March 22, 2004 March 23, 2004 1 day