Closed Repair Requests: April 2004

See Also: All Closed Repair Requests at Ballou Senior High School

April 2004 Summary

  • Urgent Requests
    9
    Average Time Elapsed: 272 Days
  • Routine Requests
    5
    Average Time Elapsed: 24.4 Days
  • Total Requests
    14

Detailed Reports

Urgent Repair Requests Completed in April 2004 (9)
Description Open Date Close Date Time Elapsed
FM-200333595 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 3rd Floor: Safety glass in center stairwell #3. July 22, 2003 April 19, 2004 272 days
FM-200333613 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 1st Floor/Room #116: Safety glass. Asbestos Code A - Clear for repairs on 07/23/03. Horne Engineering - Sheryll James Voss (RG 07/24/03) July 22, 2003 April 19, 2004 272 days
FM-200333611 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 1st Floor/Near Auditorium: Safety glass in doorway #1. July 22, 2003 April 19, 2004 272 days
FM-200333605 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 1st Floor/Doorway #5: Safety glass. July 22, 2003 April 19, 2004 272 days
FM-200333603 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 1st Floor/Room #115: Safety glass. July 22, 2003 April 19, 2004 272 days
FM-200333600 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 1st Floor/Gym: Safety glass. July 22, 2003 April 19, 2004 272 days
FM-200333599 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 1st Floor/Main Entrance: Safety glass. July 22, 2003 April 19, 2004 272 days
FM-200333597 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 2nd Floor: Safety glass in center/Room #210 Rear. July 22, 2003 April 19, 2004 272 days
FM-200333596 03 4/19/04 (Ballou) FIRE CODE VIOLATION: 2nd Floor: Safety glass in center/Room #210 Front. July 22, 2003 April 19, 2004 272 days

Routine Repair Requests Completed in April 2004 (5)
Description Open Date Close Date Time Elapsed
FM-200443265 04 4/5/04 (Ballou) HEALTH CODE VIOLATION: 30 Day Notice. Kitchen: Stop kettle pit to drainage site too eliminate observed pooling, and standing water, and organic waste from cleaning process. Per. Mr. Anderson, work in progress. January 27, 2004 April 5, 2004 69 days
FM-200446475 04 4/9/04 (Ballou) 1st Floor/Office of the Registrar: Repair or replace vandalized lock in office at south end of the building. April 7, 2004 April 9, 2004 2 days
FM-200444824 04 4/22/04 (Ballou) ground floor/armory-replace one rim cylinder to computer lab.keyed to bldg.master with three pass keys. March 3, 2004 April 22, 2004 50 days
FM-200447155 04 4/26/04 Ballou First Floor - Girls Bathroom 1) Unstop (2) toilets. April 26, 2004 April 26, 2004 0 days
FM-200447316 04 4/30/04 Ballou First floor In staff restroom repair flush valve and toilet . April 29, 2004 April 30, 2004 1 day