Closed Repair Requests: August 2001

See Also: All Closed Repair Requests at Ballou Senior High School

August 2001 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    1
    Average Time Elapsed: 72 Days
  • Total Requests
    1

Detailed Reports

Routine Repair Requests Completed in August 2001 (1)
Description Open Date Close Date Time Elapsed
FM-200113192 01 8/24/01 BALLOU OUTSIDE COOLING TOWER FURNISH ENGINEER WITH 2" FLOAT BALL FOR COOLING TOWER. FLOAT FW ASSEMBLY. INFO. COOLING TOWER GOOD FELLOW CB350 SER. 25405. WP-200108521 June 13, 2001 August 24, 2001 72 days