Closed Repair Requests: September 2001

See Also: All Closed Repair Requests at Ballou Senior High School

September 2001 Summary

  • Urgent Requests
    2
    Average Time Elapsed: 89 Days
  • Routine Requests
    17
    Average Time Elapsed: 89.5 Days
  • Total Requests
    19

Detailed Reports

Urgent Repair Requests Completed in September 2001 (2)
Description Open Date Close Date Time Elapsed
FM-200115156 01 9/17/01 BALLOU BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. INSULATE ALL BOILER DOORS. REFRACTORY IN BOILER DOORS #1, 2, 3 AND 4. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY SG 8/10/01. July 12, 2001 September 17, 2001 67 days
FM-200112901 01 9/27/01 (BALLOU) FIRE CODE VIOLATION: F-110.1 1. ASBESTOS ASSESSMENT REQUIRED. BASEMENT/BOYS & GIRLS CLUB: CEILING IN ASSEMBLY HALL HAS EXPOSED WIRES. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/18/01. LEROY MINTON - SAFETY (202)576-6691 June 8, 2001 September 27, 2001 111 days

Routine Repair Requests Completed in September 2001 (17)
Description Open Date Close Date Time Elapsed
FM-200119385 01 9/12/01 BALLOU REMOVE GRAFFITI FROM STADIUM September 7, 2001 September 12, 2001 5 days
FM-200100135 01 9/13/01 BALLOU GIRLS LOCKER ROOM AREA: REPAIR LEAK IN BLACK IRON PIPE 3" IN CEILING. HC-20000657 January 7, 2001 September 13, 2001 249 days
FM-200119123 01 9/13/01 BALLOU REPAIR FENCE ON FOOTBALL STADIUM September 5, 2001 September 13, 2001 8 days
FM-200112300 01 9/15/01 BALLOU BASEMENT BOYS RESTROOM REPLACE ONE BROKEN AND LEAKING PNEUMATIC VALVE ON HW & CW FEEDWATER SUPPLY LINE. NOTE: LEAKING PNEUMATIC VALVE IS DAMAGING CEILING AREA. WP-200108521 June 4, 2001 September 15, 2001 103 days
FM-200100934 01 9/15/01 BALLOU BOILER ROOM FURNISH AC SHOP WITH (3) 10" 12 BOLT GATE VALVES AND (1) 2" VALVE FOR CHILL WATER LINE THIT IS NOT HOLDING AND IS LETTING HOT WATER GO INTO CHILLER. January 11, 2001 September 15, 2001 247 days
FM-200118280 01 9/15/01 BALLOU BOILER ROOM REPLACE (2) FLOW SWITCHES ON THE CHILL-WATER AND CONDENSOR SW-LINES. INFO: MCDONNELL & MILLER FLOW SWITCH, FS 82. WP-200108521 August 23, 2001 September 15, 2001 23 days
FM-200116922 01 9/15/01 BALLOU BOILER ROOM (1) ASBESTOS ASSESSMENT REQUIRED (2) DISASSEMBLE END BELLS ON CENTRIFUGAL A/C CHILLER. CODE A-CLEAR FOR REPAIR BY HORNE ENG. 8/12/01. (CEB) August 8, 2001 September 15, 2001 38 days
FM-200102666 01 9/15/01 BALLOU 1ST FL. ROOM 105 GREENHOUSE REPAIR OR REPLACE INTERNAL ELECTRICAL COMPONENT ON #5 BOILER. NOTE: BOILER WILL NOT IGNITE. INFO: GAMA FURNACE (GAS) #5 BOILER. MOD. # GMP150-5, SER. #5808604994, PART IGNITION IGNITER - NORTON 982, B1401015, MOD # 27 1 NW (SOLENOID & ELECRODE TEXAS INST. INT 21GL-2670, L220F30. B13709-14). February 1, 2001 September 15, 2001 226 days
FM-200107263 01 9/15/01 BALLOU COOLING TOWER 1) REPAIR LINES CONNECTED TO CHILLER AND COOLING TOWER. 2) TAKE WATER SAMPLES FROM COOLING TOWER AND CONDENSER ( CHILLERS) 3) CHECK PERTINENT OPERATING EQUIPMENT. April 3, 2001 September 15, 2001 165 days
FM-200119730 01 9/17/01 BALLOU REMOVE SOCCER POLE September 13, 2001 September 17, 2001 4 days
FM-200120129 01 9/19/01 BALLOU REMOVE TREE FROM AROUND STADIUM FIELD AT BALLOU September 19, 2001 September 19, 2001 0 days
FM-200118506 01 9/20/01 BALLOU OUTSIDE - GROUNDS INSTALL DOOR HARDWARE ON STORAGE ROOM AND EXTERIOR TILET DOORS August 27, 2001 September 20, 2001 24 days
FM-200119909 01 9/21/01 BALLOU MARKING OF FOOTBALL FIELD September 17, 2001 September 21, 2001 4 days
FM-200120004 01 9/24/01 BALLOU MARKING OF FOOTBALL FIELD September 17, 2001 September 24, 2001 7 days
FM-200100428 01 9/24/01 BOYS SHOWER ROOM: REPAIR BRICK AND BLOCK IN THE BOYS SHOWER ROOM GR-20000076 January 9, 2001 September 24, 2001 258 days
FM-200112940 01 9/26/01 (BALLOU) FIRE CODE VIOLATION: F-608.5 1. ASBESTOS ASSESSMENT REQUIRED. DOOR ON RIGHT SIDE NEAR STAGE, PANIC BAR BROKEN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/19/01. September 24, 2001 September 26, 2001 2 days
FM-200108898 01 9/26/01 BALLOU 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days