Closed Repair Requests: January 2005

See Also: All Closed Repair Requests at Kramer Middle School

January 2005 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    2
    Average Time Elapsed: 84 Days
  • Total Requests
    2

Detailed Reports

Routine Repair Requests Completed in January 2005 (2)
Description Open Date Close Date Time Elapsed
FM-200456505 04 1/4/05 Kramer Basement room 21 Office suite doors need to be rekeyed, ASAP. October 5, 2004 January 4, 2005 91 days
FM-200457217 /04 1/6/05 Kramer First floor boys restroom 115 Commode stall 4 leaking water at base. Commode stall 7 need spud replacement. October 21, 2004 January 6, 2005 77 days

© The Washington Post Company