Closed Repair Requests: October 2003

See Also: All Closed Repair Requests at Kramer Middle School

October 2003 Summary

  • Urgent Requests
    1
    Average Time Elapsed: 0 Days
  • Routine Requests
    4
    Average Time Elapsed: 48 Days
  • Total Requests
    5

Detailed Reports

Urgent Repair Requests Completed in October 2003 (1)
Description Open Date Close Date Time Elapsed
FM-200339198 /03 10/21/03 (Kramer) !!EMERGENCY!! 2nd Floor/Room #210: Locksmith needed; chemical cabinets need to be open. (Safety Hazard) October 21, 2003 October 21, 2003 0 days

Routine Repair Requests Completed in October 2003 (4)
Description Open Date Close Date Time Elapsed
FM-200338354 03 10/2/03 Kramer Kitchen Sink leaking. October 1, 2003 October 2, 2003 1 day
FM-200228192 03 10/3/03 Kramer Second floor room 205 Art room sink fixtures need repair or replacing. No water running. ASAP April 3, 2003 October 3, 2003 183 days
FM-200338525 03 10/10/03 (Kramer) Basement/Room #21: Re-Key room rooms, #E & D, two keys each, and one (1) master key. October 6, 2003 October 10, 2003 4 days
FM-200339387 /03 10/28/03 (Kramer) !!EMERGENCY!! Basement rear exit entrance door Cannot open door to enter building, the cylinder does not turn. October 24, 2003 October 28, 2003 4 days