November 2006 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    6
    Average Time Elapsed: 64.3 Days
  • Total Requests
    6

Detailed Reports

Routine Repair Requests Completed in November 2006 (6)
Description Open Date Close Date Time Elapsed
FM-200631413 /26/06 11/9/06 KRAMER boiler room Need help to rehang boiler # 2 door can not align with pins. October 26, 2006 November 9, 2006 14 days
FM-200630025 26/06 11/9/06 Kramer M.S. Boiler room Repair refractory on front door of boiler # 3 . PER BOILER INSPECTOR"S REQUEST,KEITH JONES September 26, 2006 November 9, 2006 44 days
FM-200630207 28/06 11/16/06 Grounds - 18th St. side fence is down, repair or replace. September 28, 2006 November 16, 2006 49 days
FM-200629289 13/06 11/16/06 Grounds - Repair or replace the fence at the front and facing 18th street. September 13, 2006 November 16, 2006 64 days
FM-200628279 06 11/16/06 18th St. Side Fence Is In Need Of Repairs, Fence is down and pole is Bent August 25, 2006 November 16, 2006 83 days
FM-200625426 06 11/16/06 Outside The grass cutters (contractors) tore down the fence. July 7, 2006 November 16, 2006 132 days