Closed Repair Requests: February 2006

See Also: All Closed Repair Requests at Kramer Middle School

February 2006 Summary

  • Urgent Requests
    0
    Average Time Elapsed: 0 Days
  • Routine Requests
    13
    Average Time Elapsed: 1,004.6 Days
  • Total Requests
    13

Detailed Reports

Routine Repair Requests Completed in February 2006 (13)
Description Open Date Close Date Time Elapsed
FM-200119862 01 2/3/06 (KRAMER) ASBESTOS ASSESSMENT REQ. STAIRWELLS PANEL BOXES NEED REPAIR/ REPLACE. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/18/01 BY HORNE ENGINEER TROY WILCOME September 14, 2001 February 3, 2006 1,603 days
FM-200125330 /01 2/3/06 KRAMER MECH. ROOM 2ND FL. REPAIR OR REPLACE HERMAN NELSON MOTOR IN AIR HANDLER UNIT FOR AUDITORIUM. ONLY ONE UNIT WORKING. IT WILL NOT HEAT AREA PROPERLY. December 14, 2001 February 3, 2006 1,512 days
FM-200125326 /01 2/3/06 KRAMER BASEMENT BOYS GYM REPLACE BEARINGS TO HERMAN NELSON AIR HANDLER UNIT FOR BOYS SIDE OF GYM. December 14, 2001 February 3, 2006 1,512 days
FM-200124993 /01 2/3/06 KRAMER ROOM#206 1. ASBESTOS ASSESSMENT REQUIRED 2. REPAIR OR REPLACE HEATING COIL IN UNIVENT IN ROOM#206. COIL IS BUSTED AND LEAKING WATER ALL OVER CLASS ROOM FLOOR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/12/01. HORNE ENGINEERING - TROY WILCOME December 12, 2001 February 3, 2006 1,514 days
FM-200124001 /01 2/3/06 (KRAMER) 1. ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR/ROOM #203: FLOOR BUCKLING, TILE CRACKING AND COMING AWAY FROM THE FLOOR. ASBESTOS CODE A-CLAER FOR REPAIR 11/30/01 BY HORNE ENGINEER: TROY WILCOME November 29, 2001 February 3, 2006 1,527 days
FM-200123745 /01 2/3/06 KRAMER BOILER ROOM REPAIR OR REPLACE LEAKING FLOAT SWITCHES ON VACUUM RETURN TANK. RETURNS ARE LEAKING ALL OVER BOILER ROOM FLOOR. TANK LOCATED SOUTH WEST SIDE OF BOILER ROOM. November 23, 2001 February 3, 2006 1,533 days
FM-200123391 /01 2/3/06 (KRAMER) 1ST FLOOR/ AUDITORIUM REPAIR STAGE LIGHTS. BULBS ARE BROKEN OFF INTO FIXTURES. November 15, 2001 February 3, 2006 1,541 days
FM-200510004 05 2/8/06 Kramer Jr. High Fire Code Violation 2000 IFC 703.2.2 Second Floor - Stairwell next to Room 201 1) The VP stair case door will not close properly. ( broken hardware) Asbestos Code A - Clear for repairs on 08/11/05. Tidewater - Paul Berman (RG 08/15/05) (SEE ASSESSMENTS) August 10, 2005 February 8, 2006 182 days
FM-200510003 05 2/8/06 Kramer Jr. High Fire Code Violation 2000 IFC 703.2.2 Second Floor - Room 209 1) Self closing mechanism is broken. ( Door ) Asbestos Code A - Clear for repairs on 08/11/05. (SEE ASSESSMENTS) Tidewater - Paul Berman (RG 08/15/05) August 10, 2005 February 8, 2006 182 days
FM-200510029 05 2/8/06 Kramer Jr. High Fire Code Violation 2000 IFC 703.2.2 First , Second and Third Floors - Through-out 1) Classroom fire doors need to be adjusted. Asbestos Code A - Clear for repairs on 08/11/05. Tidewater - Henry Addison (RG 08/15/05) (SEE ASSESSMENTS) August 10, 2005 February 8, 2006 182 days
FM-200507682 05 2/10/06 Kramer MS Rooms# 101 - 104 - 205 - 208 - 308 - 315 & Audiitorium 1. Replace window a/c units in the rooms listed. July 12, 2005 February 10, 2006 213 days
FM-200455932 04 2/16/06 Kramer Front Entrance 1) Fabricate and install handrails at the front entrance steps. Place handrails at the center of the steps in line with the center doors. Paint handrails to match color of existing handrails at side entrances. Poc - Richard E. Smith - 202-576-3300 September 28, 2004 February 16, 2006 506 days
FM-200228677 03 2/27/06 Kramer First floor 115 boys restroom Ceiling has fallen above urinals evidence of leaking to restroom in basement. Health Hazard. Asbestos Code A - Clear for repairs on 04/14/03. Horne Engineering - Troy Wilcome (RG 04/16/03) April 11, 2003 February 27, 2006 1,053 days