Closed Repair Requests: March 2007

See Also: All Closed Repair Requests at Kramer Middle School

March 2007 Summary

  • Urgent Requests
    1
    Average Time Elapsed: 712 Days
  • Routine Requests
    4
    Average Time Elapsed: 26 Days
  • Total Requests
    5

Detailed Reports

Urgent Repair Requests Completed in March 2007 (1)
Description Open Date Close Date Time Elapsed
FM-200503758 05 3/21/07 ( KRAMER ) !!!VERY URGENT!!! Second Floor - Room 203 1) Repair/Replace sink fixtures Classroom sink is running hot water, no cut-off valve . Asbestos Code A - Clear for repairs on 04/08/05. DCPS Safety - Richard Gibson (RG) April 8, 2005 March 21, 2007 712 days

Routine Repair Requests Completed in March 2007 (4)
Description Open Date Close Date Time Elapsed
FM-200701456 /9/07 3/9/07 Back entrance door off hinges, can't secure. March 9, 2007 March 9, 2007 0 days
FM-200700587 17/07 3/21/07 BOILER ROOM - Repair Boiler # 1 flame failure caused by low gas pressure February 17, 2007 March 21, 2007 32 days
FM-200634001 16/07 3/21/07 Boiler room - Restore service to domestic hot water heater, heater went out when boiler room flooded January 16, 2007 March 21, 2007 64 days
FM-200702353 21/07 3/29/07 Health Suite Office. Repair or replace locks on all health suite entrance doors. Health suite must be secured prior to arrival of new medical equipment. March 21, 2007 March 29, 2007 8 days