September 2004 Summary

  • Urgent Requests
    1
    Average Time Elapsed: 22 Days
  • Routine Requests
    1
    Average Time Elapsed: 8 Days
  • Total Requests
    2

Detailed Reports

Urgent Repair Requests Completed in September 2004 (1)
Description Open Date Close Date Time Elapsed
FM-200452776 04 9/8/04 (Kramer) !!!URGENT!!! 1st Floor/Across from Library: Staff without key to open door to room #218, and the shed on the 17th & Que Street side of the building; please re-key both area's. (Need access to equipment) August 17, 2004 September 8, 2004 22 days

Routine Repair Requests Completed in September 2004 (1)
Description Open Date Close Date Time Elapsed
FM-200454092 04 9/17/04 Kramer Boiler Room Check and repair Boiler #3, out on P3. Will not come on. Need to boil out boiler for reinspection. September 9, 2004 September 17, 2004 8 days