FM-200118861 01 9/5/01 MARSHALL THROUGHOUT BLDG. EMERGENCY INSTALL (30) SPOT COOLERS THROUGHOUT BLDG. POC RICARDO WELCH 202 438-7469 STRUCTURAL MAIN. SITE VISIT ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/31/01. LEROY MINTON - SAFETY (202)576-6691 August 30, 2001 September 5, 2001 6 days
FM-200109540 01 9/26/01 MARSHALL PENTHOUSE NEAR COOLING TOWER 1. ASBESTOS ASSESSMENT REQUIRED. 2. FABRICATE SHEET METAL COVER FOR 1 EA. MAIN A.H.U THAT SERVES OPEN SPACE AREA. COVERING WAS REMOVED TO REPAIR HEATING AND COOLING COIL. POC: A. ANDREWS ENGINNER RADIO CODE #379 ASBESTOS CODE A - CLEAR FOR REPAIRS 0N 05/03/01. MR. RICHARD GIBSON - SAFETY (202)576-5584 May 3, 2001 September 26, 2001 146 days
FM-200122292 /01 10/26/01 (MARSHALL) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ STAGE #3, CENTER #3 URINALS ARE STOPPED UP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/24/01. SYLVIA GRIMES - SAFETY (202)576-5583 (RG) October 24, 2001 October 26, 2001 2 days
FM-200122293 /01 10/26/01 (MARSHALL) ASBESTOS ASSESSMENT REQ. 2RD FLOOR/ GIRLS RESTROOM TWO COMMODE ARE LEAKING AND NEEDS TO BE REPAIRED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/24/01. SYLVIA GRIMES - SAFETY (202)576-5583 (RG) October 24, 2001 October 26, 2001 2 days
FM-200122295 /01 10/26/01 (MARSHALL) !!!EMERGENCY!!! 1ST FLOOR BOYS RESTROOM/HANDICAP: SINK IS FALLING OFF THE WALL; NEEDS TO BE REPAIRED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/24/01. SYLVIA GRIMES - SAFETY (202)576-5583 (RG) October 24, 2001 October 26, 2001 2 days
FM-200117794 01 10/30/01 (MARSHALL) FIRE CODE VIOLATION:110. PAGE (1 OF 1) 1. ASBESTOS ASSESSMENT REQUIRED. REPAIR CEILING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/19/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/25/01BY HORNE ENGINEER: STEPHEN CALDWELL August 17, 2001 October 30, 2001 74 days
FM-200122296 /01 10/30/01 (MARSHALL) !!!EMERGENCY!!! 1ST FLOOR/AUDITORIUM: NEED ELECTRICIAN TO INSTALL 2 TEMPORARY 220 LINES SO THEY WILL BE ABLE TO HOOK UP SPEAKERS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/24/01. SYLVIA GRIMES - SAFETY (202)576-5583 (RG) October 24, 2001 October 30, 2001 6 days
FM-200123862 /01 1/8/02 (MARSHALL) POOL AREA ASBESTOS ASSESSMENT REQUIRED FLOOR DRAIN IN LADY SHOWER ROOM IN POOL AREA IS STOPPED UP. SENIOR CITIZENS CAN NOT TAKE SHOWER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/27/01 CHARLES BUCHANAN - SAFETY (202)576-5582 (RG) November 27, 2001 January 8, 2002 42 days
FM-200115636 01 1/24/02 (MARSHALL) "EMERGENCY" 1. ASBESTOS ASSESSMENT REQUIRED. POOL AREA: DUE TO ATTEMPTED BREAK-IN, REPAIR OR REPLACE WINDOW ON THE BASEMENT LEVEL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/31/01. LEROY MINTON - SAFETY (202)576-6691 July 23, 2001 January 24, 2002 185 days
FM-200124515 01 3/13/03 MARSHALL PARKING LOT - !!!! EMERGENCY !!!! NEED A FOUR (4) FOOT FENCE IN FRONT OF A BRICK WALL. SO THE STUDENT WANT BE PLAY AROUND AND PUSH EACH OTHER INTO THE WALL. SAFETY AND HEALTH HAZARD. December 4, 2001 March 13, 2003 464 days
FM-200223422 03 6/10/03 (Marshall) !!!VERY URGENT!!! 2nd Floor/Open space: Partial electrical power through-out this area, also, the office and classroom area's. January 2, 2003 June 10, 2003 159 days
FM-200212301 02 6/17/03 Marshall ****Urgent**** Pool Area 7 smoked-glass windows have been broken out and need to be replaced [check with custodian/foreman for size-- Walker Harris]. July 16, 2002 June 17, 2003 336 days
FM-200336699 03 9/3/03 (Marshall) !!!URGENT!!! 1st Floor/Counselors Office; Need new lock on door; staff unable to find keys. September 2, 2003 September 3, 2003 1 day
FM-200450579 04 8/19/04 Marshall main office Install electrical plug or outlet for a xerox machine. ASAP Asbestos Code A - Clear for repairs on 07/21/04. DCPS Safety - Richard Gibson (RG) July 21, 2004 August 19, 2004 29 days
FM-200456658 04 11/8/04 Marshall Stage 1 Electric panel came off the wall and wires are exposed. Could not get the panel back on the wall. Asbestos Code A - Clear for repairs on 10/08/04. DCPS Safety - Richard Gibson (RG) October 8, 2004 November 8, 2004 31 days
FM-200454065 04 12/8/04 Marshall Replace missin ceiling tile throughout facility. Stage 1, 2, 3, bathrooms and gym. Asbestos Code A - Clear for repairs on 09/09/04. DCPS Safety - Richard Gibson (RG) September 8, 2004 December 8, 2004 91 days
FM-200455123 04 12/10/04 Marshall, Thurgood Fire Code Violation First floor Inside playground expose electrical wires in ceiling. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 December 10, 2004 81 days
FM-200500165 05 1/27/05 Marshall. Thurgood Second floor First floor boys bathroom has a leak in the ceiling. Steam pipe. Asbestos Code A - Clear for repairs on 01/07/05. DCPS Safety - Charles Buchanan (RG 01/07/05) January 5, 2005 January 27, 2005 22 days
FM-200455112 04 3/20/05 Marshall, Thurgood Fire Code Violation Second floor Stairs # 3 at exit door, breach in wall. Asbestos Code A - Clear for repairs on 09/22/04. DCPS Safety - Leroy Minton Jr. (RG 09/22/04) September 20, 2004 March 20, 2005 181 days
FM-200455158 04 3/31/05 Marshall, Thurgood Fire Code Violation Gym Missing ceiling tiles thru out. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 March 31, 2005 192 days
FM-200455157 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Upper level storage room missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455132 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Bathroom near nurse office missing ceiling tile girls. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455128 04 4/5/05 Marshall, Thurgood Fire Code Violation Lobby Storage room missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455126 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Stage # 1 exit hallway missing ceiling tile. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455125 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Staff bathroom missing ceiling tile stage 1. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455124 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Stage rear right closet missing ceiling tile around sprinkler head. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455122 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Stage # 1 girls bathroom missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455182 04 4/5/05 Marshall, Thurgood Fire Code Violation Basement Kitchen area exit, missing ceiling tile. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455120 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Stage # 1 Door # 2 missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 April 5, 2005 197 days
FM-200455113 04 4/5/05 Marshall, Thurgood Fire Code Violation Second floor Stairs # 2 book room missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) UPDATE: As up 5-12-05 this FCV continue to leak. Mr Coleman has been informed of this task. I will wait for you and then when you tell me leak has been repaired, Then we will install tiles and close-out this { FCV }. September 20, 2004 April 5, 2005 197 days
FM-200505365 05 5/17/05 (Marshall) "Urgent) First floor, Boys' restroom. Unclog fixtures in boys' restroom. May 11, 2005 May 17, 2005 6 days
FM-200455121 04 7/11/05 Marshall, Thurgood Fire Code Violation First floor Stage # 1 boys bathroom missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 July 11, 2005 294 days
FM-200504204 05 10/6/05 ( MARSHALL ) Second Floor - Stage 2 Girls Bathroom 1) Repair fourth toilet, leaks from the stop control valve when flushed. Asbestos Code A - Clear for repairs on 04/18/05. DCPS Safety - Richard Gibson (RG) April 18, 2005 October 6, 2005 171 days
FM-200504194 05 11/28/05 ( MARSHALL ) URGENT!!!!!! First Floor - Handicapp Girls Restroom, and Gym Restroom 1) Repair toilets, Handicapp Girls: last toilet leaks at bottom, Gym: second from last leaks from bottom. April 18, 2005 November 28, 2005 224 days
FM-200502276 05 11/28/05 Marshall First floor bathroom Handicap boys bathroom has 4x4 feet hole on ceiling where facilities fixed a pipe. Asbestos Code A - Clear for repairs on 03/14/05. DCPS Safety - Leroy Minton Jr. (RG 03/14/05) March 7, 2005 November 28, 2005 266 days
FM-200513020 05 11/28/05 Marshall Urgent First Floor-Stage 1 Playground on stage 1 window has a hole in it, repair/replace the window September 22, 2005 November 28, 2005 67 days
FM-200216467 02 11/28/05 Marshall Asbestos Assessment Reqd. All Throughout Building, Including the Gym Restrooms & Stages 1, 2 & 3 Replace missing ceiling tiles throughout the facility. Asbestos Code A - Clear for repairs on 09/06/02. DCPS Safety - Leroy Minton Jr. (RG 09/09/02) September 4, 2002 November 28, 2005 1,181 days
FM-200202712 02 11/28/05 (MARSHALL) ***URGENT*** POOL AREA LOCKER ROOM REPLACE BROKEN COMMODE IN BOYS LOCKER ROOM, IN THE POOL AREA, WHICH IS LEAKING WITH WATER RUNNING OVER THE FLOOR. February 8, 2002 November 28, 2005 1,389 days
FM-200332686 03 12/14/05 Marshall Urgent!!! 1) Install fence around playground equipment. June 30, 2003 December 14, 2005 898 days
FM-200510560 05 1/30/06 Thurgood Marshall Education Center Fire Code Violation Gym-Breach in the ceiling tiles.(violation of IFC 110.1.1/2000) Asbestos Code A - Clear for repairs on 08/17/05. DCPS Safety - Richard Gibson (RG) August 17, 2005 January 30, 2006 166 days
FM-200618961 06 2/23/06 Urgent Basement-Boys & Girls Restroom Unstop two toilets in each restroom. February 22, 2006 February 23, 2006 1 day
FM-200510572 05 3/31/06 Thurgood Marshall Education Center Fire Code Violation Common Area-Pillar bulging:next to the day care center.(violation of 2003, 12H DCMR 110.1.1) [Failure to remave or remedy a dangerous condition] Asbestos Code A - Clear for repairs on 08/17/05. Tidewater - Rodney Distance (RG 08/24/05) August 17, 2005 March 31, 2006 226 days
FM-200100132 01 4/14/06 BRIDGE HALLWAY EIGHT (8) SECURE LOOSE CINDER BLOCKS ABOVE NEW DOOR INSTALLATION FORMERLY GR-20000316 ASBESTOS CODE A-CLEAR FOR REPAIR ON11/28/01 BY DCPS SAFETY R. EDWARD January 6, 2001 April 14, 2006 1,924 days
FM-200517232 06 4/19/06 Second floor, Stage 2/Computer room. "Urgent" Repair or Replace knob lock on door of computer room. Note: The door will not lock. January 7, 2006 April 19, 2006 102 days
FM-200623226 06 8/21/06 Marshall Boiler Room Repair or replace 1-1/2" or 2" nipple on bottom of circulating pump strainer. No A/C in Building Urgent !!!!! May 24, 2006 August 21, 2006 89 days
FM-200624762 06 10/4/06 Basement/Safety Glass Missing - Door not Closing Properly In Gym Asbestos Code A - Clear for repairs on 06/27/06. Tidewater - Shamika Parker (RG 07/03/06) June 26, 2006 October 4, 2006 100 days
FM-200624771 06 11/2/06 Basement/Safety Rail Missing In Boiler Rm. Asbestos Code A - Clear for repairs on 06/27/06. Tidewater - Shamika Parker (RG 07/03/06) June 26, 2006 November 2, 2006 129 days
FM-200512403 05 12/15/06 Peabody Very Urgent Back of School-A tree is blocking the walkway. September 12, 2005 December 15, 2006 459 days
FM-200225246 03 2/27/07 Marshall, Thurgood Gym, swimming pool, stage 1, 2 and 3 Furnish and install ceiling tile in the following areas: Gym - 10 Swimming pool - 6 Stage #1 6 Stage # 2 10 Stage # 3 6 Asbestos Code A - Cleared for repairs on 01-13-04 by Leroy Minton Jr (LM/01-13-04) Safety Office 202-576-8962. February 5, 2003 February 27, 2007 1,483 days
FM-200631443 /06 2/27/07 Third Floor/Ceiling tile missing Asbestos Code A - Clear for repairs on 11/30/06. DCPS Safety - Richard Gibson (RG) October 26, 2006 February 27, 2007 124 days
FM-200621778 06 2/27/07 Replace missing brick in front of main entrance and recreation entrance side of building. Note: The brick walkways are dangerous, a students fell down when her foot fell in where a brick is missing in space of walkway. April 25, 2006 February 27, 2007 308 days
FM-200513018 05 2/27/07 Marshall Urgent Basement-Air Handler Room Replace the lights that is over ten feet high, so the water meter can be replaced September 22, 2005 February 27, 2007 523 days