Description Open Date
FM-200225978 2/21/03 Payne !! URGENT !!! All Floors 1) Replace fuse electrical panel (guts) with circuit breaker panels . February 21, 2003
FM-200448693 6/2/04 Payne Boiler Room Boiler #1 and #2 install pull chain on safety valve. Safety hazard. June 2, 2004
FM-200506805 6/15/05 Payne Urgent !! Playground 1) There is a big hole in the ground on the playground. The hole looks like it is sinking. It has gotten larger than it was yesterday. June 15, 2005
FM-200516161 12/8/05 A fiber release episode was identified in room 19 at the door entrance above demo'd ceiling. There is a large fitting dislodged from the pipe, fitting is laying on the side of demo'd ceiling, (approx. <10LF) ceiling is open in the storage closet. Design required for abatement. Asbestos Code C - on 12/12/05. Tidewater - Roger Small (RG 12/13/05) Asbestos Code A - Abated and cleared fpr repairs on 10/23/06 per Goel confirmation (LM/10-23-06) Safety Office. 202-576-8962. December 8, 2005