Urgent Repair Requests Closed in February 2003 (77) | School | Description | Open Date | Close Date | Time Elapsed |
| Smothers ES | FM-200222102 02 2/4/03 (Smothers) !!!VERY URGENT!!! First floor - room 106 and second floor Please remove and cap wall hung drinking fountain in room 106. It does not work and have no need for it. Drinking fountain stopped up on second floor, in hallway. | December 4, 2002 | February 4, 2003 | 62 days |
| Smothers ES | FM-200216307 02 2/4/03 Smothers ****Urgent**** 1st Floor Kitchen Office Area Repair ceiling leak [3/4" pipe] over the desk in the kitchen office area. Area previously abated [Ref: 200203981]. | September 3, 2002 | February 4, 2003 | 154 days |
| Green Elementary School | FM-200225130 03 2/4/03 GREEN boiler room "URGENT" BOILER ROOM WILL FLOOD Repair/replace ruptured (2) two inch nipple on discharge line from sump pump. Replace (2) two cracked floor plugs to drains that are no longer used due to boiler room reconstruction. Plugs needed to prevent boiler room from flooding. | February 4, 2003 | February 4, 2003 | 0 days |
| Garfield ES | FM-200215450 02 2/4/03 Garfield F-608.1 Fire Code Violation 1. Asbestos Assessment Reqd. 2nd Floor Room 200B/New Wing 2. Need door adjustment. Asbestos Code A - Clear for repairs on 08/26/02. DCPS Safety - Leroy Minton Jr. (RG 08/27/02) | August 23, 2002 | February 4, 2003 | 165 days |
| Bunker Hill Elementary School | FM-200203909 02 2/5/03 (Bunker Hill) Asbestos assessment req. 1st floor/ Room 128 Please repair hump in wooden floor in room 128. Hump in floor is a safety hazard. Code-A clear for repiar by Horne Engineer ( Roger Kager ) 3/08/02 CEB | March 5, 2002 | February 5, 2003 | 337 days |
| Patricia R Harris Ed Center | FM-200225244 03 2/5/03 Harris, P.R. Second floor - room 229 URGENT Breaker needs replacing, that controls lights in room 229. Lights are unable to come on. Teacher can not have class. No other rooms are available. | February 5, 2003 | February 5, 2003 | 0 days |
| Davis Elementary School | FM-200225182 03 2/5/03 "URGENT" Davis Room 218 Univent leak at union on return line Asbestos Code A - Clear for repairs on 02/06/03. Horne Engineering - Troy Wilcome (RG 02/11/03) | February 4, 2003 | February 5, 2003 | 1 day |
| Merritt Middle School | FM-200222724 /02 2/5/03 (Merritt) !!!URGENT!!! 3rd Floor/Gym office restroom: Hot water running very hard, making it uncomfortable for staff to perform with the steamed heat coming from that area. | December 17, 2002 | February 5, 2003 | 50 days |
| Park View ES | FM-200225146 03 2/6/03 "URGENT" Parkview Boiler Room Pump out flooded boilerroom | February 4, 2003 | February 6, 2003 | 2 days |
| Sousa Middle School | FM-200225285 03 2/6/03 SOUSA JHS boiler room " URGENT URGENT NO HEAT TO BUILDING" Correct problem with boiler # 3 out on flame failure. One of three boiler operate. | February 6, 2003 | February 6, 2003 | 0 days |
| Watkins Elementary School | FM-200223787 03 2/6/03 Watkins !!!VERY URGENT!!! Fourth floor boy bathroom Last stall toilet is busted need new toilet. | January 13, 2003 | February 6, 2003 | 24 days |
| Eliot Junior High School | FM-200206983 02 2/6/03 Roof-top: Hole in skylight, piece of plexi-glass broken off. Rain is coming in room #200 on the 2nd floor. Asbestos Code A - Clear for repairs on 05/02/02. DCPS Safety - Richard Gibson (RG 05/02/02) | May 2, 2002 | February 6, 2003 | 280 days |
| Garnet-Patterson MS | FM-200201701 02 2/6/03 GARNET- PATTERSON AUDITORIUM RESTROOM, CAFETERIA STORAGE AREA 1. ASBESTOS ASSESSMENT REQUIRED. 2. DEMO THE FLOOR OF THE AUDITORIUM RESTROOM AND REMOVAL THE PIPE INSULATION OFF OF THE SPRAY PAINTED AREAS OF THE CAFETERIA STORAGE AREA AND REPAIR THE FLOOR. ED RODRIDUEZ-HORNE ENGINEERING OF HORNE HAS ALREADY WALKED THE SCOPE OF WORK WITH SHEILA HOWARD OF DCPS SAFETY AND CARNAL BRADLEY OF DCPS MECH. MAIN (01-24-02) TSI REMOVAL IN RESTROOM DCB (IT GROUP)/703-461-6848 CODE A - ASBESTOS ABATED ON 01/31/02 PER SHEILA R. HOWARD CONFIRMATION. (RG 02/27/02) No Permit was issued on 3/14/02. J. Eggleston | January 24, 2002 | February 6, 2003 | 378 days |
| Eastern High School | FM-200214217 02 2/6/03 (Eastern) Fire code violation: Page 3 of 5 Room #150: Replace safety glass. Asbestos Code A - Clear for repairs on 08/13/02 . Leroy Minton / Safety Office 202-576-8962. | August 13, 2002 | February 6, 2003 | 177 days |
| Macfarland Middle School | FM-200224156 03 2/7/03 MacFarland Urgent!! First and Third Floor - Girls Lavatory 1) First Floor - Replace commode back in 3rd stall. Was removed to unstop. 2) Third Floor - Furnish and install broken sink in lavatory. | January 17, 2003 | February 7, 2003 | 21 days |
| Hendley Elementary School | FM-200225261 03 2/10/03 (Hendley) !!!URGENT!!! Annex/1st Floor Custodian closet: Lock is hard to open with key, need thumb replacement. | February 5, 2003 | February 10, 2003 | 5 days |
| Plummer Elementary School | FM-200213492 02 2/10/03 (Plummer) Fire code violation: Page 1 of 1 1. Asbestos assessment required. 2nd Floor/Room #124: Replace light kit in door. Asbestos Code A - Clear for repairs on 08/05/02. DCPS Safety - Leroy Minton Jr. (RG 08/06/02) | August 2, 2002 | February 10, 2003 | 192 days |
| Aiton Elementary School | FM-200225270 03 2/10/03 (Aiton) !!!URGENT!!! 1st Floor/Custodian office: Key will not turn in lock. | February 5, 2003 | February 10, 2003 | 5 days |
| Smothers ES | FM-200223655 03 2/10/03 SMOTHERS pipe tunnel Replace (2 ) two inoperable sump pumps to prevent tunnel and boiler room from flooding. URGENT URGENT - boiler room will flood 2/10/03 - boiler room sump pump non-operable | January 9, 2003 | February 10, 2003 | 32 days |
| Brookland Elementary | FM-200210645 02 2/10/03 (Brookland) Fire code violation: Page 1 of 1 1. Asbestos assessment required. 3rd Floor/6th Gr: Water leaking near light. # Ceiling tile and duct sealant removal AMP Room 176. Code A Clear for Repair-Asbestos Abatement Date 07-26-02 confirmed by Leroy Minton, Jr. DCPS Safety-Sheila R. Howard 07-26-02. | July 1, 2002 | February 10, 2003 | 224 days |
| Payne Elementary School | FM-200225204 03 2/10/03 (Payne) !!!VERY URGENT!!! New wing/2nd Floor: Key will not turn in lock; unable to unlock door. | February 5, 2003 | February 10, 2003 | 5 days |
| Truesdell Elementary | FM-200206210 02 2/10/03 Truesdell !!! Urgent !!! Third (3rd) Floor - Stairway Landing Fabricate and Install guard over window that is accessible from the roof. These was an attempted break-in over the past weekend. | April 22, 2002 | February 10, 2003 | 294 days |
| Horace Mann Elementary School | FM-200224116 03 2/11/03 Mann Comm. center - cafeteria Unclog service sink, backs up are causing overflow problems. URGENT | January 16, 2003 | February 11, 2003 | 26 days |
| Hine JHS | FM-200118023 01 2/11/03 Hine Floor tile mastic removal Main Office. Library and Main office Carpet flooded and main office. Carpet can not be cleaned any more. Bad smell and mildew remove, health hazard LIBRARY ABATED FRIDAY 12/7/01 AND WORK ORDER WILL NOT BE CLOSED OUT UNTIL THE MAIN OFFICE HAS BEEN ABATED. Asbestos Code A - Clear for repairs. Abated on 07-30-02 (LM) per Leroy Minton confirmation. Safety Office 202-576-8962. | August 21, 2001 | February 11, 2003 | 539 days |
| Garnet-Patterson MS | FM-200207504 02 2/11/03 (Garnett-Patterson) Fire code violation: 1st Floor storage room: Ceiling tile missing due to water leak. This is a multi-trade the lead trade is Plumbing(200207506). I am closing this Service Order to avoid duplication. 5-14-02 SKPjr. Asbestos Code A - Clear for repairs on 05/10/02. DCPS Safety - Leroy Minton Jr.(RG 05/10/02) | May 9, 2002 | February 11, 2003 | 278 days |
| Malcolm X ES | FM-200225441 03 2/11/03 (Malcolm X) !!!URGENT!!! We need a lock repaired on the outside shed that houses the water hose. We need this repaired as soon as possible. in that there is no way for us to cut off the hot water in the shed. Vandals have access to the water if the shed cannot be locked. | February 7, 2003 | February 11, 2003 | 4 days |
| Clark Elementary School | FM-200209391 02 2/11/03 (Clark) Fire code violation: Page 1 of 2 1. Asbestos assessment required. 2nd Floor/Room #202: Ceiling tile missing. Asbestos code A - clear for repairs, on 6/19/02 DCPS Safety - R. Edwards (RE - 6/19/02) | June 12, 2002 | February 11, 2003 | 244 days |
| Bell High School | FM-200221700 /02 2/11/03 (Bell) !!!VERY URGENT!!! Through-out building: No electrical power. | November 26, 2002 | February 11, 2003 | 77 days |
| Bruce-Monroe Elementary School | FM-200224230 03 2/11/03 (Bruce-Monroe) 1. Asbestos Assessment Required. 1st Floor/South Stairway: Repair stairwell nosing through-out the building. Asbestos Code A - Clear for repairs on 01/23/03. Horne Engineering - Troy Wilcome (RG 01/24/03) (If Tiles Are Damaged Stop And Call DCPS- Safety For Instructions ) | January 21, 2003 | February 11, 2003 | 21 days |
| Shaed Elementary School | FM-200203408 02 2/12/03 Shaed School (Boiler Room ) 1. Asbestos assestment required 2. Replace 4" Multi gate valves on chill water condenser line. Valve is not holding causing hot water to be carried over to chiller. EEC/Envirobate/301-742-0330 Code A Clear for Repair asbestos abatement date was 06-26-02 confirmed by Leroy Minton DCPS Safety Sheila R. Howard DCPS Safety 06-28-02. | February 25, 2002 | February 12, 2003 | 352 days |
| Stanton Elementary School | FM-200209296 02 2/12/03 Stanton Annex ## Leak has been fixed, but there is a hole in the ceiling inside the Principal's Office that needs to be plastered and painted. The water leak caused the damage. 1. Asbestos Assessment Reqd. 1st Floor [Principal's Office] 2. Water has been leaking from the ceiling for 2 days in the principal's office---possibly from a ruptured pipe. IT Group Vincent Reed - 202-437-5638 Code A Clear for Repair asbestos abatement date was 06-28-02 confirmed by Leroy Minton DCPS Safety Sheila R. Howard DCPS Safety 06-28-02. | June 11, 2002 | February 12, 2003 | 246 days |
| Spingarn High School | FM-200212543 02 2/12/03 (Spingarn) Fire code violation: Page 1 of 3 Room #306: Broken safety glass. | July 22, 2002 | February 12, 2003 | 205 days |
| Seaton Elementary School | FM-200122299 /01 2/12/03 (SEATON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ SPEECH, ASST. PRINCIPAL OFFICE KEY MADE FOR THE CLOSET DOOR AND INNER OFFICE DOOR. ASBESTOA CODE A-CLEAR FOR REPAIR BY 11-14-01 DCPS SAFETY (REWARD) | October 24, 2001 | February 12, 2003 | 476 days |
| Turner Elementary School | FM-200224777 03 2/12/03 (Turner) 2nd Floor/Room #201, &213: Replace broken windows in both classroom doors. (Safety hazard) | January 29, 2003 | February 12, 2003 | 14 days |
| Beers Elementary School | FM-200224545 03 2/12/03 Beers Cafeteria/kitchen In the kitchen a plug needs to be replace it has loose wires. Urgent | January 24, 2003 | February 12, 2003 | 19 days |
| Turner Elementary School | FM-200225602 03 2/12/03 (Turner) Third floor - room 302 Replace missing window. Safety and security hazard. 15 10/16x37 5/16 URGENT | February 11, 2003 | February 12, 2003 | 1 day |
| Merritt Middle School | FM-200220069 /02 2/12/03 (Merritt) Health Code Violation: !!VERY URGENT!! 1st Floor/Cafeteria staff restroom: Faucets needs to be replaced, hot water continues to run. Water is 150 degree of temperature, and running very hard. | October 25, 2002 | February 12, 2003 | 110 days |
| Amidon Elementary School | FM-200221482 /02 2/12/03 Amidon First and second floors Porvide and install rubber padding around outside edges of all surface mounted panel boxes (6) total. The sharp edges of the panel boxes are very dangerous and could cause serious injury to students. Please expedite. Asbestos Code A-clear for repair by DCPS Safety Charles E. Buchanan on 11/25/02 | November 21, 2002 | February 12, 2003 | 83 days |
| Johnson JHS | FM-200221391 /02 2/12/03 Johnson First floor room 106 Request additional wall plug in room 106 for the use of computer. Asbestos Code A - Clear for repairs on 11/20/02. DCPS Safety - Leroy Minton Jr. (RG 12/02/02) | November 20, 2002 | February 12, 2003 | 84 days |
| Houston Elementary School | FM-200225772 03 2/13/03 (Houston) !!!VERY URGENT!!! Emergeny Request!!!! Front door will not lock anyone can walk in at anytime. | February 12, 2003 | February 13, 2003 | 1 day |
| Tubman Elementary School | FM-200225732 03 2/13/03 Tubman Boiler room "URGENT" Repair burner #1 , cuts off on flame failure, one boiler will not carry the building on cold days. Repair boiler burner # 2 continuously going out on flame failure. | February 13, 2003 | February 13, 2003 | 0 days |
| Bowen Elementary School | FM-200225775 03 2/13/03 (Bowen) !!!VERY URGENT!!! Basement/Tunnel Bomb shelter: Electrical power failure in this area after contractors completed their work. Please restore electrical power. (Unable to see without lights) | February 13, 2003 | February 13, 2003 | 0 days |
| Payne Elementary School | FM-200225548 03 2/13/03 (Payne) !!!VERY URGENT!!! Old wing/2nd Floor/room 207 Key broken off in door need locksmith to remove broken keys and replace it with new keys. | February 11, 2003 | February 13, 2003 | 2 days |
| Cooke H.D. Elementary School | FM-200203349 02 2/14/03 (Cooke, H.D.) Asbestos assessment req. 2nd floor/ Northside stairwell Remove and replace wooden hand rail. Hand rail coming apart and injuring hands. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/25/02. HORNE ENGINEERIN - SHARON VOSS (RG 02/26/02) | February 22, 2002 | February 14, 2003 | 357 days |
| King M L ES | FM-200225834 03 2/14/03 Paul !!! URGENT !!! FIRST FLOOR - BOYS RESTROOM 1) Repair or replace urinal traps and pipes . ( very bad smell - Health Hazard ) | February 14, 2003 | February 14, 2003 | 0 days |
| Ronald H. Brown MS | FM-200222705 /02 2/14/03 Brown, Ron Third floor boys lavatory near stairwell # 10 Expose wires in bathroom. Students removed lightswitch plate, pulled out wires, remove caps so lights will not come on. Urgent Plear repair. | December 17, 2002 | February 14, 2003 | 59 days |
| Ross Elementary School | FM-200224247 03 2/14/03 (Ross) !!!URGENT!!! Basement/Boys restroom: 1st urinal leaking from the bottom flooding the floors. Custodian shut down until repair personnel arrives. | January 21, 2003 | February 14, 2003 | 24 days |
| Malcolm X ES | FM-200216263 02 2/14/03 (Malcolm X) Fire code violation: 1. Asbestos assessment required: Exit #6: Door won't open in the kindergarten area. Asbestos Code A - Cleared for repairs on 03-18903 by Leroy Minton Jr. (LM/03-18-03) Safety Office 202-576-8962. | August 30, 2002 | February 14, 2003 | 168 days |
| Winston EC | FM-200225783 03 2/14/03 Winston !!! URGENT !!! First Floor - Kitchen 1) Unstop drain or drains in the kitchen . | February 13, 2003 | February 14, 2003 | 1 day |
| Kramer Middle School | FM-200205026 02 2/14/03 KRAMER Asbestos Assessment Required 2nd Floor Library Remove and replace the wooden floor tiles which has rotted out [safety hazard]. Code A-clear for repair by Horne Engineer ( Sam Ebrahim ) on 3/28/02 (CEB) | March 28, 2002 | February 14, 2003 | 323 days |
| Reed LC | FM-200201398 02 2/14/03 (REED) ASBESTOS ASSESSMENT REQUIRED GROUND FLOOR LIFE GUARDS ROOM SPARKS ARE COMING FROM THE BREAKER BOX THAT PROVIDES POWER TO THE POOL PUMP ROOM & THERE IS NO ELECTRICITY (CANNOT SEE TO ADD CHLORINE TO THE POOL WATER) ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/24/02 RICHARD GIBSON - SAFETY (202)576-5584 (RG)-01/24/02 | January 22, 2002 | February 14, 2003 | 388 days |
| Woodson High School | FM-200225715 03 2/14/03 (Woodson, H.D.) !!!URGENT!!! 4th Floor/Boys restroom: Toilet is backing up, please unstop. | February 12, 2003 | February 14, 2003 | 2 days |
| Stevens Elementary School | FM-200225917 03 2/18/03 STEVENS URGENT!!!! BOILERROOM 1) THE SKY LIGHT GLASS IS BROKEN, AND GLASS IS HANGING ON THE PIPE AND FROM THE SKYLIGHT. PLEASE REPAIR. | February 18, 2003 | February 18, 2003 | 0 days |
| Payne Elementary School | FM-200225372 03 2/19/03 Payne Second floor - health suite Replace shorted incondecent bulb with lay-in (recessed) four (4) tube fluorescent (tube) light fixture (2). Urgent As of now ther is no light in the health suite. | February 6, 2003 | February 19, 2003 | 13 days |
| Woodson High School | FM-200220927 /02 2/19/03 (Woodson, H.D.) !!!URGENT!!! 1. Asbestos assessment required. 7th Floor/Stairwell #3 & 4 : Request welders to spot weld latch guard, surrounding steps to cage. Asbestos Code A-clear for repair by charles E. Buchanan on 11/14/02 DCPS Charles E. Buchanan | November 13, 2002 | February 19, 2003 | 98 days |
| Whittier Elementary School | FM-200209989 02 2/21/03 (Whittier) Fire code violation: Page 1 of 1 1. Asbestos assessment required. 1st Floor/Room #103: Door hardware missing. Asbestos Code A - Clear for repairs on 6/24/02 DCPS Safety - R. Edwards, (RE-6/24/02) | June 21, 2002 | February 21, 2003 | 245 days |
| Beers Elementary School | FM-200217598 02 2/21/03 (Beers) !!!URGENT!!! Rear of Kitchen/Cafeteria outside closet: Due to break-in, vandals broke lock off door also, broke glass out of glass door. | September 16, 2002 | February 21, 2003 | 158 days |
| Montgomery ES | FM-200212251 02 2/21/03 Montgomery ****Urgent**** 1st Floor Room 108 near Entrance Straighten and reattach the security grate that was pulled away from the window. | July 16, 2002 | February 21, 2003 | 220 days |
| Ferebee-Hope Elementary School | FM-200214618 02 2/21/03 Ferebee-Hope F-110.2(1) Fire Code Violation Swimming Pool Level Men's Restroom There is a hole in the wall. Asbestos Code A - Clear for repairs on 08/19/02. DCPS Safety - Leroy Minton Jr (RG 08/20/02) | August 15, 2002 | February 21, 2003 | 190 days |
| Whittier Elementary School | FM-200209987 02 2/21/03 (Whittier) Fire code violation: Page 1 of 1 1. Asbestos assessment required. New Wing: Ceiling tile missing across from Room #17: Asbestos Code A - Clear for repairs on 6/24/02 DCPS Safety - R. Edwards, (RE-6/24/02) | June 21, 2002 | February 21, 2003 | 245 days |
| Shaed Elementary School | FM-200219618 /02 2/24/03 (Shaed) Health Code violation: Loading Dock: Repair drain. Asbestos Code A - Cleared for repairs on 10-23-02 (LM 10/24/02) Leroy Minton Jr. Safety Office 202-576-8962. | October 17, 2002 | February 24, 2003 | 130 days |
| Cooke H.D. Elementary School | FM-200120403 01 2/24/03 (COOKE, H.D.) ASBESTOS ASSESSMENT REQ. HAND-RAIL COMING FROM WALL: RAIL NEEDS TO BE BOLT TO WALL. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/24/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 24, 2001 | February 24, 2003 | 518 days |
| Winston EC | FM-200215626 02 2/24/03 Winston F-608.1 Fire Code Violation Asbestos Assessment Reqd. 4th Floor Next to Special Ed Room Door not aligned and not closing properly. Asbestos Code A - Clear for repairs on 02-13-03 by Leroy Minton Jr. (LM/02-13-03) Safety Office (202) 576-8962. | August 26, 2002 | February 24, 2003 | 182 days |
| Cardozo High School | FM-200211137 02 2/24/03 Cardozo 1. Asbestos Assessment Reqd. Basement Tunnel 2. Repair or replace leaking 3" galvanized, insultated, domestic cold-water pipe. Asbestos Code A - Clear for repairs. (LM) Abated on 08/13/02 per Leroy Minton confirmation. Safety Office 202-576-8962. | July 12, 2002 | February 24, 2003 | 227 days |
| Woodson High School | FM-200226116 03 2/24/03 (Woodson, H.D.) !!!VERY URGENT!!! 3rd Floor/Boys & Girls restroom: When commode is flushed in these restrooms, all other toilets back up, and run over from the 7th floor to the basement. (Appears to be a major back-up) | February 24, 2003 | February 24, 2003 | 0 days |
| Whittier Elementary School | FM-200225781 03 2/24/03 (Whittier) !!!VERY URGENT!!! 1st Floor/Girls restroom: Total of two (2) commodes overflowing with water, spilling over, flooding the floor (Unable to locate shut off valves) | February 13, 2003 | February 24, 2003 | 11 days |
| Thomas Elementary School | FM-200220363 /02 2/25/03 Thomas First floor - Kitchen restroom Survey restroom door and shave the bottom or top of the door, so that it may close and open for privacy. Asbestos Code B- by Horne Engineer Sheryll Jones on 11/12/02 DCPS Charles E Buchanan DCPS Follow up investigation found that the damage door was a wooden door therefore a code A-clear for repair was giving by DCPS Safety Charles E. Buchanan on 11/12/02 | October 31, 2002 | February 25, 2003 | 117 days |
| Emery Elementary School | FM-200212295 02 2/25/03 (Emery) Fire code violation: Page 2 of 2 Parking lot exit: Missing door return. Please Note ! This job can only be conducted with the assistance of Safety Office personnel. Please ! do not attemp this job without our assistance. (Leroy Minton Jr. / 01-14-03) Safety Office 202-576-8962. | July 16, 2002 | February 25, 2003 | 224 days |
| Coolidge High School | FM-200210247 02 2/25/03 (Coolidge) Fire code violation: Page 3 of 4 1. Asbestos assessment required. Basement storage room: Breach in ceiling, room #177 laundry room. Asbsetos Code A - Clear for repairs on 6/27/02 DCPS Safety, L. Minton (RE - 6/27/02 | June 25, 2002 | February 25, 2003 | 245 days |
| Macfarland Middle School | FM-200224077 03 2/26/03 McFarland Urgent !!! Kitchen 1) Unstop grease trap, backing up. Trap is clean. | January 16, 2003 | February 26, 2003 | 41 days |
| Bell High School | FM-200226113 03 2/26/03 (Bell) !!!URGENT!!! Front entrance doors: Panic bar jammed on doors. | February 24, 2003 | February 26, 2003 | 2 days |
| Gage-Eckington ES | FM-200226230 03 2/26/03 GAGE-ECKINGTON URGENT DOOR DOSEN'T LOCK. SECURITYY BREACH. | February 25, 2003 | February 26, 2003 | 1 day |
| Macfarland Middle School | FM-200224154 03 2/26/03 MacFarland Urgent!! Basement - Kitchen 1) Unstop grease trap that is backing up on floor. | January 17, 2003 | February 26, 2003 | 40 days |
| Patricia R Harris Ed Center | FM-200121723 /01 2/26/03 (HARRIS, P.R.) ASBESTOS ASSESSMENT REQ. GROUND FLOOR/ BIG GYM THE GYM FLOOR IS ALL BEAT UP BECAUSE OF TERMITES AND THE BLEACHERS ARE BROKEN WITH METAL STICKING OUT IS SUCH AWAY AS TO HURT A CHILD TAKING GYM IN THIS AREA. ASBESTOS CODE-A CLEAR FOR REPAIR BY HORNE ENGINEER : EDWARD RODRIGUEZ 10/24/01 (CEB) | October 16, 2001 | February 26, 2003 | 498 days |
| Ronald H. Brown MS | FM-200205522 02 2/27/03 (Brown, Ron) **Very Urgent** 1. Asbestos assessment required. 1st floor/library: Busted pipe in the ceiling; at this time there is no flooding however, constant dripping, and tile is wet. DCB (IT Group)/703-461-6848 Code A Clear For Repair- Asbestos Abatement Date - April 9, 2002 Sheila R. Howard confirmation with Vincent Reed of IT Group April 10, 2002. | April 5, 2002 | February 27, 2003 | 328 days |
| Ronald H. Brown MS | FM-200226405 03 2/28/03 Brown, Ron First floor - Cafeteria Replace small steam table glass 4"x30" to prevent students from sticking hands in food. Safety / Health issue | February 28, 2003 | February 28, 2003 | 0 days |
| Kramer Middle School | FM-200225033 03 2/28/03 Kramer First floor - room 102 principal office Lights need repair. Urgent | January 31, 2003 | February 28, 2003 | 28 days |
Routine Repair Requests Closed in February 2003 (409) | School | Description | Open Date | Close Date | Time Elapsed |
| Roosevelt High School | FM-200224935 03 2/1/03 Roosevelt Boiler Room Flooded Boiler Room Flooded Pit | January 30, 2003 | February 1, 2003 | 2 days |
| Eliot Junior High School | FM-200224977 03 2/2/03 Eliot Stairwell ,Mechanical room Replace 2" valve in stairwell mechanical room. | January 31, 2003 | February 2, 2003 | 2 days |
| Lafayette Elementary School | FM-200224974 03 2/2/03 Lafayette Throughout Building Retrap and add control valves throughout building. | January 31, 2003 | February 2, 2003 | 2 days |
| Orr Elementary School | FM-200224946 03 2/2/03 Repair explosion doors on boilers Hinges are broken and need to be repair. | January 31, 2003 | February 2, 2003 | 2 days |
| Sousa Middle School | FM-200225014 03 2/2/03 Sousa Classroom 321 Repair/Replace 1'' valve on supply line. | January 31, 2003 | February 2, 2003 | 2 days |
| Harris, C.W. ES | FM-200224126 03 2/3/03 (Harris, C.W.) 1st Floor/Room #114: Classroom door glass and window panes broken, please replace. (Wire mesh glass) in door) | January 16, 2003 | February 3, 2003 | 18 days |
| Brent Elementary School | FM-200219905 /02 2/3/03 Brent Boiler Room P.M Chiller | October 23, 2002 | February 3, 2003 | 103 days |
| Patricia R Harris Ed Center | FM-200225060 03 2/3/03 Harris, P.R. Main floor - restroom the one next to #1 stairs Toilet needs to be pulled up from the floor because of blockage in the line. | February 3, 2003 | February 3, 2003 | 0 days |
| Jefferson JHS | FM-200224926 03 2/3/03 Jefferson Hand basin in two classrooms are stopped up. | January 30, 2003 | February 3, 2003 | 4 days |
| Truesdell Elementary | FM-200223972 03 2/3/03 Truesdell Boiler Room Basement Repair leaking return line size 3/4" in front of boilers and leaking 2" nipple at condensation tank. Asbestos Code A - Clear for repairs on 01/15/03. Horne Engineering - Tony Marcolin (RG 01/17/03) | January 14, 2003 | February 3, 2003 | 20 days |
| Brookland Elementary | FM-200225048 03 2/3/03 Brookland Boiler room Check low gas pressure condition to boilers # 2. the flame is not burning correct. | February 3, 2003 | February 3, 2003 | 0 days |
| Hine JHS | FM-200224513 03 2/3/03 (Hine) Door will not lock properly | January 16, 2003 | February 3, 2003 | 18 days |
| Moten Elementary School | FM-200225114 03 2/3/03 (Moten) Emergency !!! Ground Floor/Near stairwell -C: Water leaking from water fountain; water is not coming from the spout of the water fountain, it appears to be coming from behind a wall. The floors are flooded; a teachers slipped and fell on the floor today. Asbestos Code A - Clear for repairs on 02/04/03. Horne Engineering - Troy Wilcome (RG 02/04/03) | February 3, 2003 | February 3, 2003 | 0 days |
| Plummer Elementary School | FM-200225064 03 2/3/03 Plummer Third Floor - Girls Bathroom and Auditorium 1) Unstop (2) toilets in girls bathroom . 2) Unstop (1) toilet in auditorium girls room. Note - These toilets are stopping up on a re-occurring basis . | February 3, 2003 | February 3, 2003 | 0 days |
| Tyler Elementary School | FM-200220177 /02 2/3/03 Asbestos assessment maybe required Repair or replace leaking convertor for hot water side of the building , unit is constantly flooded each day and must be blown down . Asbestos Code A-clear for repair by Horne Engineer Donald Magleinti on 10/30/02 DCPS Charles E. Buchanan | October 29, 2002 | February 3, 2003 | 97 days |
| Kramer Middle School | FM-200224614 03 2/3/03 Kramer room 319 Door lock hardware need to be replace or repair, vandalism. | January 27, 2003 | February 3, 2003 | 7 days |
| Kramer Middle School | FM-200224427 03 2/3/03 Kramer First and third floor Room 101 needs to be rekeyed. Room 308 needs to be keyed. | January 23, 2003 | February 3, 2003 | 11 days |
| Wilkinson ES | FM-200216012 02 2/4/03 Wilkinson F-303.4 Fire code violation: Second floor - Room 259 Storage room missing hardware. | August 28, 2002 | February 4, 2003 | 160 days |
| Smothers ES | FM-200214495 02 2/4/03 Smothers F-303.4 Fire Code Violation 1st Floor Custodian's Room Custodian's room and office doors are not latching. | August 14, 2002 | February 4, 2003 | 174 days |
| Shepherd ES | FM-200221491 /02 2/4/03 Shepherd Second Floor - Girls Toilet - Old Wing 1) Repair or replace (2) leaking toilets. | November 21, 2002 | February 4, 2003 | 75 days |
| Raymond Elementary School | FM-200224544 03 2/4/03 (Raymond) New wing/1st Floor: Girls and boys bathroom: Sink leaking profusely. | January 24, 2003 | February 4, 2003 | 11 days |
| Brightwood Elementary School | FM-200224715 03 2/4/03 (Brightwood) Old Annex side/Boys restroom 1st floor: Ruptured copper pipe, leaking very badly, replace valves over hot water tank. | January 28, 2003 | February 4, 2003 | 7 days |
| Winston EC | FM-200216010 02 2/4/03 Winston F-303.4 Fire Code Violation 1st Floor Corridor Doors not latching. | August 28, 2002 | February 4, 2003 | 160 days |
| Winston EC | FM-200215980 02 2/4/03 Winston F-303.4 Fire Code Violation 2nd Floor Room 241 No key for door, can't get out.. | August 28, 2002 | February 4, 2003 | 160 days |
| Winston EC | FM-200215977 02 2/4/03 Winston F-303.4 Fire Code Violation 2nd Floor Corridor Doors not latching in elevator area. | August 28, 2002 | February 4, 2003 | 160 days |
| Winston EC | FM-200215619 02 2/4/03 Winston F-303.4 Fire Code Violation 4th Floor Chiller Room Missing door hardware. | August 26, 2002 | February 4, 2003 | 162 days |
| Burrville Elementary School | FM-200224193 03 2/4/03 Burrville School Replace burned out decks | January 21, 2003 | February 4, 2003 | 14 days |
| Cardozo High School | FM-200224547 03 2/4/03 Cardozo) 1. Asbestos Assessment Required. Laundry Room: Gas leak investigated by the gas company, discovered leaking from pipe under floor, Engineer indicated, the floor has to be removed to get to the corroded pipe, as need to be capped off. Asbestos Code A - Clear for repairs on 01/24/03. Horne Engineering - Troy Wilcome (RG 01/27/03) | January 24, 2003 | February 4, 2003 | 11 days |
| Wilson High School | FM-200218319 02 2/4/03 Wilson,W. 1st Floor Boys' Locker Room 1. Replace cracked toilet in the restroom; and 2. Repair urinal in the team room that does not flush properly. | September 25, 2002 | February 4, 2003 | 132 days |
| West Elementary School | FM-200220935 /02 2/4/03 West Mech.Room #8 Repair or replace inline circulator pump. Name-General Electric; Volts-115; AMP-4.60; Frame-48Y; HP- 1/2; RPM-1725; HZ-60; PH-1; SF-1.35. Pump is leaking before water enter the coil. Inoperable (No heat in Learning Center) | November 14, 2002 | February 4, 2003 | 82 days |
| Webb Elementary School | FM-200224489 03 2/4/03 Webb Cafeteria and Room #139 Replace double shift motor in cafeteria (3 motors )and room #139 (1 motor) area are cold. | January 24, 2003 | February 4, 2003 | 11 days |
| Harris, C.W. ES | FM-200224900 03 2/4/03 Harris, C.W. Second floor - room 234 Replace broken wire glass in light kit next to classroom door. | January 30, 2003 | February 4, 2003 | 5 days |
| Hine JHS | FM-200213939 02 2/4/03 (Hine) Fire code violation: Page 2 of 6 1. Asbestos assessment requied. Room #304: Door hardware defective. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 9, 2002 | February 4, 2003 | 179 days |
| Hine JHS | FM-200214012 02 2/4/03 (Hine) Fire code violation Page 4 of 6 Building D: Corridor door not latching. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 4, 2003 | 176 days |
| Hine JHS | FM-200214013 02 2/4/03 (Hine) Fire code violation Page 4 of 6 Building D-8th Street side: Corridor door not latching by boys locker room. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 4, 2003 | 176 days |
| Hine JHS | FM-200214015 02 2/4/03 (Hine) Fire code violation Page 4 of 6 1. Asbestos assessment required. 2nd Floor: Door not latching to music room. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 4, 2003 | 176 days |
| Hine JHS | FM-200214025 02 2/4/03 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. 2nd Floor: Girls bathroom not latching. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 4, 2003 | 176 days |
| Jefferson JHS | FM-200224033 03 2/4/03 Jefferson First floor - boys lavatory Replace broken faucet. | January 15, 2003 | February 4, 2003 | 20 days |
| Malcolm X ES | FM-200216220 02 2/4/03 (Malcolm X) Fire code violation: 3rd Floor: Storage room #7, latch broken. | August 30, 2002 | February 4, 2003 | 158 days |
| Malcolm X ES | FM-200216269 02 2/4/03 (Malcolm X) Fire code violation: 1. Asbestos assessment required: Exit door/Penthouse side: Door not latching. Asbestos Code A-clear for repair On 9/03/02 DCPS Charles E. Buchanan | August 30, 2002 | February 4, 2003 | 158 days |
| Spingarn High School | FM-200127303 02 2/4/03 SPINGARN ROOM 317 REPAIR LEAKING COIL IN ROOM 317 ASSESSMENT DOES NOT APPLY, ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/18/02 BY HORNE ENGINEER: ROGER KAGER | January 11, 2002 | February 4, 2003 | 389 days |
| Spingarn High School | FM-200127300 02 2/4/03 SPINGARN PARENT CENTER REPLACE HEAT COIL IN PARENT CENTER. (NEW COIL IS ON HAND BUT NEEDS ADJUSTMENT TO FIT HEATING UNIT.) ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/18/02 BY HORNE ENGINEER: ROGER KAGER | January 11, 2002 | February 4, 2003 | 389 days |
| Smothers ES | FM-200225056 03 2/4/03 Smothers Emergency !! First Floor - Kitchen 1) Ceiling pipe leaking over oven.. Asbestos Code A - Clear for repairs on 02/04/03. Horne Engineering - Troy Wilcome (RG 02/04/03) | February 3, 2003 | February 4, 2003 | 1 day |
| Smothers ES | FM-200224849 03 2/4/03 Smothers First floor - boys lavatory Battery pack, auto flush valve is broken on one toilet. | January 29, 2003 | February 4, 2003 | 6 days |
| Smothers ES | FM-200222539 /02 2/4/03 (Smothers) "AS SOON AS POSSIBLE" 2nd Floor/Teachers lounge: Sink stopped up, needs to be snaked out. | December 13, 2002 | February 4, 2003 | 53 days |
| Smothers ES | FM-200219698 /02 2/4/03 Smothers First Floor - Boys Bathroom 1) Repair leak that occurs when the recently installed urinals are used . Note - 5 out of 6 urinals had to be shut off to stop the water from leaking while they are on, which leaves an odor when the students use them. | October 18, 2002 | February 4, 2003 | 109 days |
| Orr Elementary School | FM-200214642 02 2/4/03 Orr F-303.4 Fire Code Violation 2nd Floor by Rooms 208-210 Corridor doors need knobs. | August 15, 2002 | February 4, 2003 | 173 days |
| Orr Elementary School | FM-200214652 02 2/4/03 Orr F-303.4 Fire Code Violation 1st Floor Blue Stairwell Corridor Corridor doors not latching in the blue stairwell by the conference and special education rooms. | August 15, 2002 | February 4, 2003 | 173 days |
| Smothers ES | FM-200218710 02 2/4/03 Smothers 1st Floor - Room 106 Please remove and cap wall hung drinking fountain in room 106, it does not work and have no need for it. Asbestos Code A-clear for repair by Horne Engineer Edward Rodriguez on 10/07/02 DCPS Charles E. Buchanan | October 2, 2002 | February 4, 2003 | 125 days |
| Orr Elementary School | FM-200214668 02 2/4/03 Orr F-303.4 Fire Code Violation 1st Floor Level Missing hardware on outside door on Minnesota Avenue side. | August 15, 2002 | February 4, 2003 | 173 days |
| Wilson High School | FM-200218393 02 2/5/03 Wilson,W. 1st Floor Boys' Restroom Repair toilet & urinal that do not flush properly. Replace urinal that was removed. | September 26, 2002 | February 5, 2003 | 132 days |
| Clark Elementary School | FM-200223588 03 2/5/03 (Clark) 1st Floor: Stopped up sink in K-1: Sink will get worse with students washing their hands. When sink fills up, in over-flows. (Instructed to route students to another sink for washing hands, until the help arrives. | January 7, 2003 | February 5, 2003 | 29 days |
| Barnard Elementary School | FM-200224420 03 2/5/03 Barnard Boiler Room-Pump Room R/R faculity float on condensate return. Float is stick, either in open or close position. This float operaties the solenoid valve of the city water make up to tank | January 23, 2003 | February 5, 2003 | 13 days |
| Payne Elementary School | FM-200225180 03 2/5/03 Payne Boiler Room Boilers off line -lock out status | February 4, 2003 | February 5, 2003 | 1 day |
| Clark Elementary School | FM-200203382 02 2/5/03 Clark Cafeteria, First Floor (1) Asbestos Assessment Required (2) Repair leaking supply line in ceiling of cafeteria area on the first floor to air handler unit. Line can not be isolated. POC: CARNAL BRADLEY 202 438-7437 | February 25, 2002 | February 5, 2003 | 345 days |
| Merritt Middle School | FM-200221176 /02 2/5/03 Merritt First floor - Kitchen Screen door in rear (exit door) of kitchen is in dare need of repair. Screen and plexex glass need to be replaced or repaired.. This need to be done as soon as possible. | November 18, 2002 | February 5, 2003 | 79 days |
| Whittier Elementary School | FM-200223549 03 2/5/03 Whittier Boiler Room Exterior Unstop drains outside boiler room back door. Approx (2) 3" Engineer attempted t unstop with negative results. Note: Flooding boiler room | January 6, 2003 | February 5, 2003 | 30 days |
| Raymond Elementary School | FM-200220109 /02 2/5/03 Raymond Boiler Room P.M Chiller | October 28, 2002 | February 5, 2003 | 100 days |
| Ronald H. Brown MS | FM-200126874 02 2/5/03 BROWN RON BOILER ROOM TSI, Exploratory Demolition. 1. ASBESTOS ASSESTMENT REQUIRED 2. REPAIR LEAKING 3/4 INCH SUPPLY LINE FOR ENGINEERS OFFICE UNIVENT. DCB (IT Group) / 703-461-6848 CODE A - ASBESTOS ABATED ON 02/18/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/20/02) | January 7, 2002 | February 5, 2003 | 394 days |
| Tyler Elementary School | FM-200224878 03 2/5/03 Tyler 1) Front Door - Door is leaning , lock wont catch, hinges pulled away from frame. | January 30, 2003 | February 5, 2003 | 6 days |
| Ronald H. Brown MS | FM-200221106 /02 2/5/03 Brown, Ron 3rd floor - Room 329 - Broken large window pane. 3rd floor - Room 325 - Classroom entry door glass broken. Student broke glass in classroom door 325. Week of 11/4 - /11/8 FM-200220899 Asbestos Code A-clear for repair by Horne Engineer Philip Connolly on 11/19/02 DCPS Charles E. Buchanan | November 15, 2002 | February 5, 2003 | 82 days |
| Thomas Elementary School | FM-200221128 /02 2/5/03 THOMAS SCHOOL BOILER ROOM Replace leaking mechanical seals on condensate return pump # 3. NOTE: THIS IS THE ONLY OPERABLE CONDENSATE RETURN PUMP | November 18, 2002 | February 5, 2003 | 79 days |
| Ronald H. Brown MS | FM-200224615 03 2/5/03 (Brown, Ron (Roper) 1st Floor/Principal's office: Need safe opened, new principal on board. | January 27, 2003 | February 5, 2003 | 9 days |
| Ronald H. Brown MS | FM-200225093 03 2/5/03 Brown, Ron (Roper) Male PE Office, Room 227 Near custidial closet Near stairwell #8 Replace large wire mesh glass in above area. Large hole present need replacing to prevent student from breaking more and secure teachers property. | February 3, 2003 | February 5, 2003 | 2 days |
| Spingarn High School | FM-200224791 03 2/5/03 Spingarn Second floor - Auditorium Requesting an glaze man to come out and measure and replace glass with mess glass. | January 29, 2003 | February 5, 2003 | 7 days |
| Eaton Elementary School | FM-200224855 03 2/5/03 Eaton E.S Boiler Room Basement Replace burn out motor on air handler unit B-1 Trane Unit, Motor Century Type 5C Volt 200-208, FR-M145T HP-1.5, AMP 6.0, PH-3, RPM-1745 | January 29, 2003 | February 5, 2003 | 7 days |
| Bruce-Monroe Elementary School | FM-200117755 01 2/5/03 (BRUCE-MONROE) FRONT HALL 1. ASBESTOS ASSESSMENT 2. TSI, PLASTER-REMOVE, FLOOR TILES AND REPAIR REPLACE CEILING TILE IN THE FRONT HALL DO TO SMOKE DAMAGE. DCB (IT GROUP)/703-461-6848 CODE A - ASBESTOS ABATED ON 01/29/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/05/02) | August 17, 2001 | February 5, 2003 | 537 days |
| Bunker Hill Elementary School | FM-200202563 02 2/5/03 (BUNKER HILL) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/ROOM #111: PLEASE REMOVE CARPET FROM THE AREA. THE ENTIRE CARPET WAS DAMAGED BY WATER LEAKING FROM A UNIVENT APPROXIMATELY THREE (3) WEEKS AND THE SMELL OF MOLD AND FUNGUS IS GETTING PROGRESSIVELY WORSE. THIS CARPET IS LESS THAN A YEAR OLD, AND WAS INSTALLED ON TOP OF 1 X 1 TILE. CODE A - ASBESTOS ABATED ON 02/16/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/20/02) | February 6, 2002 | February 5, 2003 | 364 days |
| King M L ES | FM-200224886 03 2/5/03 King, M. L. Jr. First floor Need keys made for rooms 117 and 118 - Teachers bathroom in the lobby. | January 30, 2003 | February 5, 2003 | 6 days |
| Bruce-Monroe Elementary School | FM-200224408 03 2/5/03 Bruce-Monroe Boiler Room Boiler Room Boiler #1 won't restart after shuting down it goes out on flame failure burner needs to be adjusted | January 23, 2003 | February 5, 2003 | 13 days |
| Ronald H. Brown MS | FM-200225098 03 2/5/03 Brown, Ron (Roper) Basement - second and third floor Replace broken wire mesh glass in the following areas: Stairwell # 8 Boys lockerroom office Classroom # 325 and 213 | February 3, 2003 | February 5, 2003 | 2 days |
| Davis Elementary School | FM-200106476 01 2/5/03 DAVIS BASEMENT ART ROOM 16 REPAIR WASTE LINE AND UNSTOP SINK WITH K50. THE PLUMBERS ARE HAVING A HARD TIME FIXING THIS SINK. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/21/01. HORNE ENGINEERS - R AGNANT | March 22, 2001 | February 5, 2003 | 685 days |
| Raymond Elementary School | FM-200225121 03 2/5/03 Raymond See Locations Attached Replace inoperable electronic sensor control valves on heating univents that will not response to water flow temepertures | February 3, 2003 | February 5, 2003 | 2 days |
| Duke Ellington School | FM-200225123 03 2/5/03 (Ellington) Ground Floor: Three toilets down, these toilets are stopped up. (There are no other toilets on that floor) | February 3, 2003 | February 5, 2003 | 2 days |
| Spingarn High School | FM-200127301 02 2/5/03 SPINGARN ROOM 314 REPAIR LEAKING COIL IN ROOM 314. ROOM HAS NO HEAT. ASSESSMENT DOES NOT APPLY. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/18/02 BY HORNE ENGINEER: ROGER KAGER | January 11, 2002 | February 5, 2003 | 390 days |
| Orr Elementary School | FM-200225047 03 2/5/03 ORR boiler room Check operation of boiler # 2 continuously going out in flame failure. | February 2, 2003 | February 5, 2003 | 3 days |
| Orr Elementary School | FM-200225376 03 2/6/03 ORR BOILER ROOM Thomas/Wilson responded to call, the building was cold. Boiler #2 was off on flame failure, reset boiler #2 it ran for five minutes then went back out on flame failure. | February 6, 2003 | February 6, 2003 | 0 days |
| Tubman Elementary School | FM-200207633 02 2/6/03 (Tubman) Fire code violation: Page 1 of 1 1. Asbestos assessment required. 1st floor/Next to room #134: Defective glass in door. Code A-clear for repair by Horne Engineer ( Sheryll James ) on 05/15/02 | May 13, 2002 | February 6, 2003 | 269 days |
| Kimball Elementary School | FM-200207231 02 2/6/03 Kimball Drains @ The Rear of the Cafeteria Unstop drains in the rear of the cafeteria below the stairway-- above the driveway. | May 6, 2002 | February 6, 2003 | 276 days |
| Bell High School | FM-200207193 02 2/6/03 (Bell) Fire Code Violation: Page 1 of 1 1st floor/Room #150-A: Extension cords used as permanent wiring. | May 6, 2002 | February 6, 2003 | 276 days |
| Eliot Junior High School | FM-200225230 03 2/6/03 Eliot Boiler room Asbestos assessment required Repair or replace 2 1/2" blow down lines and or valve ,front and back of # 1 boiler , lines and or valves appears to have a restriction in them, can not blow boiler down. | February 5, 2003 | February 6, 2003 | 1 day |
| Birney Elementary School | FM-200101247 01 2/6/03 BIRNEY Throughout building Retrap and add control valves throughout building. | January 13, 2001 | February 6, 2003 | 754 days |
| Garnet-Patterson MS | FM-200224106 03 2/6/03 (Garnet-Patterson) Kitchen Faucet in kitchen is running. EMERGENCY | January 16, 2003 | February 6, 2003 | 21 days |
| Kimball Elementary School | FM-200224138 03 2/6/03 KIMBALL room 202 1. Asbestos assessment may be required. Mr. C. Bradley @ 202-438-7437 2. Repair/repalce leaking heat coil (isolated) in univent. Room will only have partical heat from radiator. Asbestos Code A - Clear for repairs on 01/28/03. Horne Engineering - Philp Connolly (RG 01/30/03) | January 17, 2003 | February 6, 2003 | 20 days |
| Garnet-Patterson MS | FM-200225254 03 2/6/03 (Garnet-Patterson) Asbestos assessment required. 1st Floor/North end of hallway: Leak in steam pipe. | February 5, 2003 | February 6, 2003 | 1 day |
| Bowen Elementary School | FM-200220733 /02 2/6/03 (Bowen) 3rd Floor: Need lock change for room #302, also, need keys made to the nurses suite; teacher was locked in and the door had to be broken. | November 12, 2002 | February 6, 2003 | 86 days |
| Jessie LaSalle Elementary | FM-200223679 03 2/6/03 LaSalle Room 305 Repair or replace shaft and bearing on the univent in room 305 | January 10, 2003 | February 6, 2003 | 27 days |
| Leckie Elementary School | FM-200214723 02 2/6/03 (Leckie) Fire code violation: Page 3 of 3 Across from Mech. room: Exit light out. | August 16, 2002 | February 6, 2003 | 174 days |
| Eastern High School | FM-200214283 02 2/6/03 (Eastern) Fire code violation: Page 5 of 5 1. Asbestos assessment required. Next to armory: Exit light out. | August 13, 2002 | February 6, 2003 | 177 days |
| Ludlow-Taylor ES | FM-200110307 01 2/6/03 LUDLOW-TAYLOR FIRST (1ST) FLOOR TSI, PLASTER - REMOVE, FLOOR TILES AND REPAIR. 1) ASBESTOS ASSESSMENT REQUIRED 2) REPLACE MISSING, BROKEN AND STAINED CEILING TILES. 1ST FLOOR THE ROOM ARE MULTIPURPOSE ROOM; EXITING HALLWAYS FROM MULTI- PURPOSE ROOM, COUNSELOR OFFICES 1 AND 2; MAIN HALLWAY, ROOM #113, CUSTODIAN OFFICE, LIBRARY, MAIN OFFICE, ROOM #105, 102, 100 AND 101 CEILING TILES IS 2 INCH X 4 INCH DROP-IN. ENVIROBATE (IT GROUP) 703-461-6848 CODE A - ASBESTOS ABATED ON 10/24/01 (SG) PER LEROY MINTONS CONFIRMATION. | May 15, 2001 | February 6, 2003 | 632 days |
| Garrison ES | FM-200207755 02 2/6/03 (Garrison) Fire code violation: 1st Floor: Fire extinguisher cabinet needs to be fixed. | May 15, 2002 | February 6, 2003 | 267 days |
| Hine JHS | FM-200218609 02 2/6/03 Repair or replace univent motor ,motor will not start | October 1, 2002 | February 6, 2003 | 128 days |
| Watkins Elementary School | FM-200219962 /02 2/6/03 Watkins Fourth floor - boys Boys bathroom last stall toilet, is busted, need new toilet. Asbestos Code A - Clear for repairs on 10/25/02. Horne Engineering - Philp Connolly (RG 10/28/02) | October 24, 2002 | February 6, 2003 | 105 days |
| Peabody Elementary School | FM-200224689 03 2/6/03 Peabody Room #10 Repair or replace leaking coventor, has a hold in it. Asbestos Code A - Clear for repairs on 01/29/03. Horne Engineering - Bipin Nanavaty (RG 01/30/03) | January 28, 2003 | February 6, 2003 | 9 days |
| Nalle Elementary School | FM-200225344 03 2/6/03 NALLE J.C. boiler room Correct problem with down boiler # 2, burner continuously goes out on flame failure. 1 of 2 boiler operates | February 6, 2003 | February 6, 2003 | 0 days |
| Savoy Elementary School | FM-200214050 02 2/6/03 Savoy F-303.4 Fire Code Violation First Floor - Hall door next to 117 C 1) Broken door return. | August 12, 2002 | February 6, 2003 | 178 days |
| West Elementary School | FM-200225276 03 2/6/03 West School Remove acess growth on fence line | February 5, 2003 | February 6, 2003 | 1 day |
| West Elementary School | FM-200219912 /02 2/6/03 West Boiler Room P.M Chiller | October 23, 2002 | February 6, 2003 | 106 days |
| Anacostia Senior High School | FM-200224752 03 2/7/03 Anacostia Room #208, #222 and #231 Replace bearing and shaft in univents in ceiling. Shaft size is 1 1/4". | January 29, 2003 | February 7, 2003 | 9 days |
| Woodson High School | FM-200225220 03 2/7/03 Woodson, H.D. Room #210 Repair leaking heating unit. EMERGENCY!!!!!!! | February 5, 2003 | February 7, 2003 | 2 days |
| Wilson High School | FM-200225187 03 2/7/03 Woodrow Wilson Pool Pump Room First Floor 1. Added chemical to water 2. Back wash filter 3. Provide heat to water | February 5, 2003 | February 7, 2003 | 2 days |
| Payne Elementary School | FM-200223774 03 2/7/03 Payne Incinerator Room Asbestos assessment required Repair or replace 2" return steam line, leak very badly. Valve will not hold. No insulation on line. Asbestos Code A - Clear for repairs on 01/15/03. Horne Engineering - Philp Connolly (RG 01/17/03) | January 13, 2003 | February 7, 2003 | 25 days |
| Ferebee-Hope Elementary School | FM-200225185 03 2/7/03 Ferebee-Hope Pool Pump Room First Floor 1. Disassemble strainers and clean them 2. Added chemicals 3. Added water to bring up water level 4. Work on heat exchange | February 5, 2003 | February 7, 2003 | 2 days |
| Hine JHS | FM-200225303 03 2/7/03 Hine Rooms 203A, 305, and 307 Repair new univents in the following rooms: 203A, 305, and 307 ,units do not respond to thermostat or controls,(no heat) | February 6, 2003 | February 7, 2003 | 1 day |
| Hine JHS | FM-200225327 03 2/7/03 Hine Room 400, and 201 Replace shaft bearings on univent in 400 ,201, also replace blower fan in room 201. | February 6, 2003 | February 7, 2003 | 1 day |
| Raymond Elementary School | FM-200220506 02 2/7/03 Raymond Room #35 Repair or replace electronic control valve to heating unit in room #35, control valve will not open to let the water circulate through the coil. EMERGENCY !!!!! | November 1, 2002 | February 7, 2003 | 98 days |
| Ferebee-Hope Elementary School | FM-200225301 03 2/8/03 Ferebee Hope Pool Area First Floor 1. Work on heat for pool 2. Add water to pool 3. Adjust chemical levels | February 6, 2003 | February 8, 2003 | 2 days |
| Nalle Elementary School | FM-200225352 03 2/8/03 (Nalle) !!!EMERGENCY!!! Cafeteria: Room behind rear door of cafeteria: Steam line broken in that area; tremendous amount of steam discharging. Problem is so bad, cafeteria might have to close down before lunch time. | February 6, 2003 | February 8, 2003 | 2 days |
| Janney Elementary School | FM-200224885 03 2/8/03 Janney Teachers Lounge First Floor Replace burn out motor for HVAC Air Handler Unit Model #FBAANFO48000ADAA Serial # 3594A03018 Volts 208/230 HP=3/4 FLA=5.5 Phase Hz 1/6 No Heat In The Principal Office Asst. Principal Office, Main Office and Conferance Room | January 30, 2003 | February 8, 2003 | 9 days |
| Woodson High School | FM-200225313 03 2/8/03 H.D Woodson Pool Pump Room First Floor 1. Back wash filters 2. Add chemicals to pool 3. Adjust water level 4. Put lights in pump room | February 6, 2003 | February 8, 2003 | 2 days |
| Eastern High School | FM-200225339 03 2/8/03 Eastern Room 159A Replace leaking trap and replace radiator valve in room 159 A | February 6, 2003 | February 8, 2003 | 2 days |
| Roosevelt High School | FM-200103380 01 2/9/03 ROOSEVELT BOILER ROOM PROVIDE (9) NINE 1/2" BRONZE HAND WHEEL TRY COCKS WITH STAINLESS STEEL BALL TO REPLACE LEAKING TRY COCKS ON HIGH PRESS. BOILERS TRY COCKS MUST BE RATE FOR PRESSURES UP TO 250 PSI. | February 9, 2001 | February 9, 2003 | 730 days |
| Ballou Senior High School | FM-200114424 01 2/10/03 BALLOU FIRST (1ST), SECOND (2ND) AND THIRD (3RD) FLOORS TSI, PLASTER-REMOVAL, FLOOR TILING AND REPAIR. 1) ASBESTOS ASSESSMENT REQUIRED. 2) ELECTRICAL CONTRACTOR WILL BE DRILLING 4" HOLES IN THE FLOORS NEXT TO THE STAIRWAY. THE FLOOR TILES MUST BE REMOVED BEFORE THIS WORK CAN BE DONE. PLEASE HAVE FLOOR TILES ABATED. RE-ASSIGNED TO HORNE ENG. ON 11/30/01 (SG). CAPE (IT GROUP)/703-461-6848 CODE A - ASBESTOS ABATED ON 02/14/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/20/02) | June 29, 2001 | February 10, 2003 | 591 days |
| Spingarn High School | FM-200225331 03 2/10/03 (Spingarn) !!!EMERGENCY!!! 1st Floor/Boys bathroom: All urinals stopped up. (Continues to back up in other area's) | February 6, 2003 | February 10, 2003 | 4 days |
| Woodson High School | FM-200216668 02 2/10/03 (Woodson, H.D.) Fire code violation: Room #302: Exposed wiring, also need electrical switch plate. | September 5, 2002 | February 10, 2003 | 158 days |
| Roosevelt High School | FM-200217357 02 2/10/03 Roosevelt B15 Mechanical room Replace leaking centrifugal pumps (D1 and D2). Pumps used to circulate heating hot water throughout building. Unable to operate pumps in current condition. | September 12, 2002 | February 10, 2003 | 151 days |
| Coolidge High School | FM-200209240 02 2/10/03 (Coolidge) !!!!Emergency!!!! Roof: Asbestos Assessment Required Rains from 3rd floor to 1st floor; water coming through lockers on 1st floor. POC: ALFRED COLEMAN 202-439-8276 CELL PHONE GARY RUCKER 202-945-9367 PAGER EC & D/301-742-0330 Code A - Asbestos abated on 06/11/02 PER Leroy Minton confirmation.(RG 06/18/02) | June 7, 2002 | February 10, 2003 | 248 days |
| Gage-Eckington ES | FM-200225201 03 2/10/03 Gage-Eckington Second floor girls restroom main lobby There are six (6) stalls, two (2) of them need handles replaced, water will not stop running or dripping causing floods all day. | February 5, 2003 | February 10, 2003 | 5 days |
| Bowen Elementary School | FM-200225502 03 2/10/03 (Bowen) 1st Floor/Boys restroom: Toilet in last stall backing up, and spilling over. (No success with plunger) | February 10, 2003 | February 10, 2003 | 0 days |
| Spingarn High School | FM-200224182 03 2/10/03 Spingarn Boiler Room Asbestos assessment required Replace 1/2" stud to refractory door to Boiler #4 Asbestos Code A - Clear for repairs on 01/22/03. Horne Engineering - Troy Wilcome (RG 01/23/03) | January 21, 2003 | February 10, 2003 | 20 days |
| Woodson High School | FM-200225425 03 2/10/03 Woodson, H.D. Boiler room Repair # 1 and # 2 Burners ,they cut in flame failure and be reset | February 10, 2003 | February 10, 2003 | 0 days |
| Roosevelt High School | FM-200201774 02 2/10/03 ROOSEVELT B-55 MECHANICAL ROOM REPLACE BURNED UP AIR COMPRESSOR MOTOR ON AIR COMPRESSOR IN B-55 MECH. ROOM. LINCOLN ELECTRIC ODP AC MOTOR, VOLTS 230/460/208, AMPS: 13.5/6.7/14.4, RPM: 1745/1725, S.F. 1.15/1.15, NEMA: J/G TEMP. RISE: B/F, BEARINGS DRIVE/OPP: 207/205, SERIAL: U1921209068 | January 25, 2002 | February 10, 2003 | 381 days |
| Gibbs Elementary School | FM-200219966 /02 2/10/03 (Gibbs) First floor - Asst. Principal office Commode needs r/r cracked, water is running onto floor. | October 24, 2002 | February 10, 2003 | 109 days |
| Nalle Elementary School | FM-200225431 03 2/10/03 Nalle Boiler Room Boiler #2 down on lock out | February 10, 2003 | February 10, 2003 | 0 days |
| Truesdell Elementary | FM-200225299 03 2/10/03 Truesdell First floor room 112 Lock needs repairing. Tumble pin is broken. Teacher can not secure her belongings. | February 6, 2003 | February 10, 2003 | 4 days |
| Raymond Elementary School | FM-200224742 03 2/10/03 Raymond E.S Third Floor Room 35 First and Third First Floor Room 18 Abestos Assestment Required Remove (2) bad electronic valve on (2) univent and pipe straight | January 28, 2003 | February 10, 2003 | 13 days |
| Nalle Elementary School | FM-200206829 02 2/10/03 Nalle 1. Asbestos assessment required: The thunderstorm today has blown out two windows. One window is located in the cafeteria which located in the basement.The other window is located in room 212-A (old wing). EEC/301-742-0330 Code A - Asbestos abated on 06/13/02 PER Leroy Minton confirmation.(RG 06/18/02) | April 19, 2002 | February 10, 2003 | 297 days |
| Gibbs Elementary School | FM-200224102 03 2/10/03 Gibbs Second Floor - Across fron teachers lounge Replace fixx stand water cooler, compressor not working. | January 16, 2003 | February 10, 2003 | 25 days |
| Merritt Middle School | FM-200224921 03 2/10/03 Merritt !!!EMERGENCY!!! Back door is coming off. please respond February 03, 2003: Principal states, door has come off completely, please send someone to repair this door, we are unable to secure it. Asbestos Code A - Clear for repairs on 02/04/03. Horne Engineering - Rayomd Agnant (RG 02/04/03) | January 30, 2003 | February 10, 2003 | 11 days |
| Payne Elementary School | FM-200202544 02 2/11/03 Payne Tunnel 1) TSI, Removal in Tunnel Exploratory Demo in 2nd floor Boys Room. 2) Fiber Release Clean-up in AMP #129. 1. Asbestos assessment required on restricted tunnel. 2. Makea all necessary repairs on steam and return lines in tunnel area. Emergency. POC: HAWKINS, CLARENCE 202- 4387367 DCB (IT Group)/ 703-461-6848 CODE A - ASBESTOS ABATED ON 02/16/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/20/02) | February 6, 2002 | February 11, 2003 | 370 days |
| Macfarland Middle School | FM-200127241 02 2/11/03 (MACFARLAND) (EMERGENCY) 1. ASBESTOS ASSESSMENT REQUIRED. TSI, PLASTER-REMOVE, FLOOR TILES AND REPAIR 2ND FLOOR/ROOM #200: RADIATOR IN ROOM #300 LEAKING DOWN IN-TO THE ABOVE ROOM #200. ALSO, PIPE LEAKING FROM CEILING OF ROOM #259. POC: CARNAL BRADLEY 202 438-7437 DCB (IT GROUP)/703-461-6848 CODE A - ASBESTOS ABATED ON 02/04/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/12/02) | January 10, 2002 | February 11, 2003 | 397 days |
| Ballou Senior High School | FM-200225511 03 2/11/03 Ballou Health Suite Replace wall multistage heat pump thermostat. Info: Honeywell Y594R1243; 24 V Control Heating and Cooling Sub base package T874R1152/Q674L1207 0.1A TO 1.2A. | February 11, 2003 | February 11, 2003 | 0 days |
| Adams Elementary | FM-200201272 02 2/11/03 ADAMS MAIN OFFICE SUPPLY CLOSET TSI, REMOVAL IN AMP #122A 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE AND REPAIR A LEAKING LINE IN THE CEILING. DCB (IT GROUP)/ 703-461-6848 CODE A - ASBESTOS ABATED ON 02/13/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/19/02) | January 17, 2002 | February 11, 2003 | 390 days |
| Bruce-Monroe Elementary School | FM-200220676 /02 2/11/03 Bruce-Monroe Stairway (North, east, south and west) Repair / replace step plates on stairs. East - 3 West - 4 North - 4 South - 2 | November 12, 2002 | February 11, 2003 | 91 days |
| Ferebee-Hope Elementary School | FM-200225631 03 2/11/03 Ferebee-Hope Pool Area/ Pool Pump Room First Floor Provide chemical and heat to pool water | February 11, 2003 | February 11, 2003 | 0 days |
| Dunbar High School | FM-200225627 03 2/11/03 Dunbar Check on contractor work for Mr. Tony Law | February 11, 2003 | February 11, 2003 | 0 days |
| Hart Middle School | FM-200223603 03 2/11/03 HART boiler room Check boiler burners # 2 will not start this is the only operating boiler. | January 7, 2003 | February 11, 2003 | 35 days |
| Hart Middle School | FM-200225510 03 2/11/03 Hart Boiler Room Replace inoperable High/Low limit control and operator limit control on Boiler #1 and #2. Note: Amount two (2) High / Low Limit and two (2) Operator Limit | February 11, 2003 | February 11, 2003 | 0 days |
| Gibbs Elementary School | FM-200214585 02 2/11/03 Gibbs - F-303.4 First floor - room 123 Defective door hardware door knob3, Extinguishers has outdated tag. | August 15, 2002 | February 11, 2003 | 180 days |
| Winston EC | FM-200225466 03 2/11/03 (Winston) 1st Floor/Open space: Wire mesh glass broken in the entrance door in the 3/4 center. | February 10, 2003 | February 11, 2003 | 1 day |
| Marshall Educational Center | FM-200224965 03 2/11/03 Thurgood Marshall School Remove bridge and parts on playground equipment | January 31, 2003 | February 11, 2003 | 11 days |
| Simon Elementary School | FM-200225020 03 2/11/03 Simon First floor - Girls bathroom You have to flush the toilet many times in order for it to flush all the way. | January 31, 2003 | February 11, 2003 | 11 days |
| Woodson High School | FM-200225592 03 2/11/03 H.D. Woodson Room 312 ceiling Abestos assessment required on pipes in the ceilng Repair or replace ruptured heat pipes in the ceiling of room 312 Asbestos Code A - Clear for repairs on 02/11/03. Horne Engineering - Edward Rodriguez (RG 02/11/03) | February 11, 2003 | February 11, 2003 | 0 days |
| Woodson High School | FM-200225629 03 2/11/03 H.D Woodson Pool Pump Room First Floor 1. Back wash filters 2. Added chemicals 3. Added water | February 11, 2003 | February 11, 2003 | 0 days |
| Ballou Senior High School | FM-200108406 01 2/11/03 BALLOU BOILER ROOM SUB-BASEMENT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. CLEAVERY BROOKS PACKAGED BOILER #4. REFACTORY ENTIRE INTERIOR OF THE BOILER INCLUDING THE MORRISON TUBE AREA. BOILER INFO: MOD #760-125A SER#L47171 Tracking #10087 EEC (Envirobate)/301-436-1150 Code A - Asbestos abated on 06/07/02 PER Leroy Minton confirmation.(RG 06/18/02) | April 13, 2001 | February 11, 2003 | 669 days |
| Hine JHS | FM-200219904 /02 2/11/03 Hine Boiler Room P.M Chiller | October 23, 2002 | February 11, 2003 | 111 days |
| Hine JHS | FM-200224493 03 2/11/03 HINE room 205 "No Heat in room" Repair/replace univent motor line has a short tripping circuit breaker out on overload. | January 24, 2003 | February 11, 2003 | 18 days |
| Hine JHS | FM-200224498 03 2/11/03 HINE room 106 "No Heat in room" 1. Asbestos assessment may be required. per Mr. Bradley @ 438-7437. 2. Remove univent coil to be cleaned by engineer. 3. Reinstall univent coil upon completion of engineer cleaning coil. Asbestos Code A - Clear for repairs on 01/27/03. Horne Engineering - Tony Marcolin (RG 01/28/03) | January 24, 2003 | February 11, 2003 | 18 days |
| Meyer Elementary School | FM-200225371 03 2/11/03 Meyers First floor - Library 1) walls needs painting. Lead & Asbestos Code A - Clear for repairs on 02/10/03. Horne Engineering - Edward Rodriguez (RG 02/11/03) | February 6, 2003 | February 11, 2003 | 5 days |
| Hine JHS | FM-200224519 03 2/11/03 (Hine) Repair or replace light dimmer panel board on stage | January 16, 2003 | February 11, 2003 | 26 days |
| Hine JHS | FM-200224874 03 2/11/03 Repair or replace electrical short in the univent in room 205,unit kicks circuit breaker out | January 30, 2003 | February 11, 2003 | 12 days |
| Woodson High School | FM-200225626 03 2/11/03 H.D Woodson Check on contractor work for Mr. Tony Law | February 11, 2003 | February 11, 2003 | 0 days |
| Reed LC | FM-200225625 03 2/11/03 Marie Reed Check on contractor work for Mr. Tony Law | February 11, 2003 | February 11, 2003 | 0 days |
| Woodson High School | FM-200216589 02 2/11/03 (Woodson, H.D.) Fire code violation: 6th Floor/Stairway #4: Door missing hardware. | September 5, 2002 | February 11, 2003 | 159 days |
| Shaed Elementary School | FM-200219909 /02 2/11/03 Shaed Boiler Room P.M Chiller | October 23, 2002 | February 11, 2003 | 111 days |
| Stuart-Hobson Middle School | FM-200225312 03 2/11/03 Stuart-Hobson Basement girls gym Locl on door is very hard to get into and key s get stuck and hard to get the key back out. | February 6, 2003 | February 11, 2003 | 5 days |
| Ballou Senior High School | FM-200224679 03 2/11/03 (Ballou) 1st Floor water coolers: 1. Fountain near boys restroom - Replace push plate. 2. Water fountain outside maint. office - Re-anchor to wall, replace filter, and cooler. (Wall hung) 3. Water cooler near room #111 - replace. (No filter) 4. Water cooler near room #115 - re-anchor, (No filter) Replace Bubbler. 5, Water cooler near gym - replace 2nd cooler, remove stoppage, no filter, (Wall hung) 6. Water cooler near library - water line outside jacket replace. Asbestos Code A - Clear for repairs on 02/10/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | January 28, 2003 | February 11, 2003 | 14 days |
| Duke Ellington School | FM-200224911 03 2/12/03 Ellington, Duke First floor - Front office The light switch is broken and need repair. | January 30, 2003 | February 12, 2003 | 13 days |
| Backus Middle School | FM-200225134 03 2/12/03 Backus Second Floor 1) Can not turn on (3) switches in the panel box. The panel box has shifted. | February 4, 2003 | February 12, 2003 | 8 days |
| Cleveland Elementary School | FM-200225696 03 2/12/03 Cleveland First floor auditorium / all purpose room Repair breaker to auditorium stage lights. They will not come on. | February 12, 2003 | February 12, 2003 | 0 days |
| Cleveland Elementary School | FM-200224432 03 2/12/03 Cleveland/KC Lewis First floor - Room 101 Install exit sign over exit door. There is no exit sign present. | January 23, 2003 | February 12, 2003 | 20 days |
| Ferebee-Hope Elementary School | FM-200225725 03 2/12/03 Ferebee Hope Pool Pump Room First Floor 1. Adjust bypass on heating valve,for convector 2. Check chemical level 3. Adjust water feed valve 4. Check air temp | February 12, 2003 | February 12, 2003 | 0 days |
| Garfield ES | FM-200204058 02 2/12/03 (Garfield) Asbestos Assessment Required 1st Floor Area 60 [Corridor] Replace 9x9-inch floor tiles in area 60 where they are breaking up. Code A-clear for repair asbestos abatement on 06/20/02 confirmed by R Edwards. CE Buchanan 06/25/02 | March 7, 2002 | February 12, 2003 | 342 days |
| Amidon Elementary School | FM-200224053 03 2/12/03 Amidon School Repair playground equipment (preventive maintenance) | January 15, 2003 | February 12, 2003 | 28 days |
| Cardozo High School | FM-200225536 03 2/12/03 Cardozo S.H.S. Cafeteria Brick work is needed for a hole. Asbestos Code A - Clear for repairs on 12/20/02. Horne Engineering - Troy Wilcome (RG 12/23/02) | February 11, 2003 | February 12, 2003 | 1 day |
| Cardozo High School | FM-200207072 02 2/12/03 (Cardozo) Fire Code Violation: 3rd floor/Room #314: Leak in the ceiling, electrical hazard. Code A-clear for repair by Horne Engineer ( Bipin Nanavaty ) on 05/07/02 | May 3, 2002 | February 12, 2003 | 285 days |
| Wilson High School | FM-200225724 03 2/12/03 Woodrow Wilson Pool Pump Room First Floor 1. Added water to pool 2. Added chemical 3. Back wash filter | February 12, 2003 | February 12, 2003 | 0 days |
| Bunker Hill Elementary School | FM-200222133 02 2/12/03 Bunker Hill Nurse's Restroom Asbestos assessment required Boiler #1 repair and replace crack section. Asbestos Code A - Clear for repairs on 12/09/02. Horne Engineering - Sheryll James (RG 12/12/02) | December 6, 2002 | February 12, 2003 | 68 days |
| Hardy Middle School | FM-200208095 02 2/12/03 (Hardy) Fire code violation: 1. Asbestos assessment required. 2nd Floor/Through-out: Door hardware (locks) need to be checked through-out. Asbestos Code A - Clear for repairs on 05/21/02. Horne Engineering - Bipin Nanavaty (RG 05/22/02) | May 21, 2002 | February 12, 2003 | 267 days |
| Harris, C.W. ES | FM-200224441 03 2/12/03 Harris, C.W. Second floor - room 222 Door knob broken. | January 23, 2003 | February 12, 2003 | 20 days |
| Harris, C.W. ES | FM-200224548 03 2/12/03 (C.W. Harris) 1st Floor/Lobby: Panic bar broken. | January 24, 2003 | February 12, 2003 | 19 days |
| Patricia R Harris Ed Center | FM-200225297 03 2/12/03 P.R. Harris mechanical room (stairwell # 4) Replace return fan motor (bad bearing) on A.H.U. # 2 . Serving kitchen area and lunchroom area on first floor Motor = General electric Serial # = 5K145AL247 model # = GKF, HP =2, PH = 3 , RPM = 1725, volts = 230/460, amps = 6.2 /3.1 fram = 145T HZ = 60 | February 6, 2003 | February 12, 2003 | 6 days |
| Terrell Mc ES | FM-200225455 03 2/12/03 (Terrell, M.C.) Exit door lock needs repairing; door slams exceedingly hard and loosens lock. Door check is also broken. | February 5, 2003 | February 12, 2003 | 7 days |
| Hine JHS | FM-200224991 03 2/12/03 (Hine) B - Wing - Stairwells and Muliti-Purpose Area Exit lights will not come on... | January 31, 2003 | February 12, 2003 | 12 days |
| Brookland Elementary | FM-200222276 /02 2/12/03 Brookland First floor - Kindergaten Repair broken window. | December 10, 2002 | February 12, 2003 | 64 days |
| Ballou Senior High School | FM-200203048 02 2/12/03 (BALLOU) 1) FT/Mastic removal within AMP room 28. ASBESTOS ASSESSMENT REQ. BASEMENT/ A-6 NEED TO HAVE THE ELECTRICAL OUTLETS ON THE FLOOR REMOVED AND MOVED TO THE WALL. Envirobate - Charles Crenshaw - 571-436-1150 | February 15, 2002 | February 12, 2003 | 362 days |
| Stoddert ES | FM-200225356 03 2/12/03 (Stoddert) Through-out building: Lost of electrical power. | February 6, 2003 | February 12, 2003 | 6 days |
| Johnson JHS | FM-200214225 02 2/12/03 Johnson 1st and 2nd Floors [B-wing Area] Change 240-type receptacles to 20 amp-125v receptacles in the main office and room 104-A and rooms 200 through 204. | August 13, 2002 | February 12, 2003 | 183 days |
| Johnson JHS | FM-200219229 /02 2/12/03 (Johnson Exterior Reset timer for exterior lights. No lights will come on. | October 10, 2002 | February 12, 2003 | 125 days |
| Stanton Elementary School | FM-200213305 02 2/12/03 Stanton School Cutting of grass with big tractor | July 29, 2002 | February 12, 2003 | 198 days |
| Johnson JHS | FM-200222124 02 2/12/03 Johnson First Floor - Classroom 106 1) Principal request (2) additional wall plugs in room 106 for the use of computers. | December 5, 2002 | February 12, 2003 | 69 days |
| Johnson JHS | FM-200224687 03 2/12/03 Johnson Kitchen 1) Exposed live wires in steam table. Please cover | January 28, 2003 | February 12, 2003 | 15 days |
| Kimball Elementary School | FM-200210185 02 2/12/03 Kimball Main Office 1) Install electrical outlets for new copying machine. # ( 6-20r) Contact - Rosie Henry - 645-3150 Asbestos Code A - Clear for repairs, 6/27/02 Horne Engineering - Bipin Nanavaty, (RE- 6/28/02) | June 25, 2002 | February 12, 2003 | 232 days |
| Woodson High School | FM-200225109 03 2/12/03 (Woodson, H.D.) Plaza level/Main office: Loose electrical plug under employee's desk. | February 3, 2003 | February 12, 2003 | 9 days |
| Amidon Elementary School | FM-200201801 02 2/12/03 AMIDON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 3/4 BYPASS VALVE ON #1 BOILER. | January 25, 2002 | February 12, 2003 | 383 days |
| Ballou Senior High School | FM-200224613 03 2/12/03 Ballou Health Suite No heat due to burnt up electric fuse holder. | January 27, 2003 | February 12, 2003 | 16 days |
| Kramer Middle School | FM-200224030 03 2/12/03 Kramer Kitchen Sink is leaking water onto floor from pipe underneath. Please repair or replace. | January 15, 2003 | February 12, 2003 | 28 days |
| Beers Elementary School | FM-200224683 03 2/12/03 (Beers) Building #1/Nurse office: Electrical fixture hanging from wall. | January 28, 2003 | February 12, 2003 | 15 days |
| Ludlow-Taylor ES | FM-200225179 03 2/12/03 Ludlow-Taylor Boiler Room Boilers off line-lock out status | February 4, 2003 | February 12, 2003 | 8 days |
| Malcolm X ES | FM-200224876 03 2/12/03 Malcolm X 1) 4th floor 6 grade classroom - circuit breaker is gone. 2) 4th floor Boys and Girls bathroom - no lights. | January 30, 2003 | February 12, 2003 | 13 days |
| Maury Elementary School | FM-200225385 03 2/12/03 Maury First Floor P.E. Room and First Floor Boys Room East Building. 1) Replace leaking wax ring in P.E. Room. 2) Replace leaking wax ring in Boys Room. March 26, 2003 Corected copy: 1st Floor/East building, P.E. room: Unstop 4" inch wastline on toilets in the boys restroom. | February 7, 2003 | February 12, 2003 | 5 days |
| Park View ES | FM-200224438 03 2/12/03 Parkview First and Second Floor - Boys and Girls Bathroom 1) Make repairs to exposed sanitary piping at ceiling from above urinals. Poc - Preston McCrary - 240-832-7573 Asbestos Code A - Clear for repairs on 01/28/03. Horne Engineering - Sharon Voss ( RG 01/30/03) | January 23, 2003 | February 12, 2003 | 20 days |
| Amidon Elementary School | FM-200209702 02 2/12/03 Amidon 1) Floor tile/mastic, TSI removal and repair within AMP rooms 124a,130,139, 142,147,152,230a,corridor,150 and 209. Envirobate - Charles Crenshaw - 571-436-1150 Code A-clear for repair asbestos abatement on 06/24/02 confirmed by R Edwards. CE Buchanan 06/25/02 | June 18, 2002 | February 12, 2003 | 239 days |
| Ballou Senior High School | FM-200224743 03 2/12/03 (Ballou) 3rd Floor - water coolers: 1. Water cooler by 307 has improper anchor support for bracket. ( no filter) 2. Water cooler near 315 ( no filter) reanchor bracket. Asbestos Code A - Clear for repairs on 02/10/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | January 28, 2003 | February 12, 2003 | 15 days |
| Seaton Elementary School | FM-200222353 /02 2/12/03 (Seaton) 1st Floor/Gym Teachers office, and Main office: 1) Power failure in these rooms. | December 10, 2002 | February 12, 2003 | 64 days |
| Wilson J. O. ES | FM-200225649 03 2/12/03 Wilson, J.O. Boiler Room Repair domestic hot water circulating pump has broken coupling | February 12, 2003 | February 12, 2003 | 0 days |
| Wilson J. O. ES | FM-200214984 02 2/12/03 Wilson J.O. F-504.1 Fire code violation: Second floor Glass missing from extinguisher cabinet (201). | August 19, 2002 | February 12, 2003 | 177 days |
| Coolidge High School | FM-200202631 02 2/12/03 Coolidge Tunnel & Cafeteria Exploratory Demolition in Cafeteria 1. Asbestos exploratory need on cafeteria floor due to demolition. 2. Repair steam leak in tunnel and cafeteria floor (demolition work to concrete floor). DCB (IT GROUP)/703-461-6848 | February 7, 2002 | February 12, 2003 | 370 days |
| Duke Ellington School | FM-200217859 02 2/12/03 Ellington Basement Gym Locker Room & Storage #13 Lights in storage area do not work---need repair. | September 18, 2002 | February 12, 2003 | 147 days |
| Anacostia Senior High School | FM-200224496 03 2/12/03 (Anacostia) Ground Floor/Kitchen: Breaker for walk-in box and freezer continues to kick out. | January 24, 2003 | February 12, 2003 | 19 days |
| Backus Middle School | FM-200203197 02 2/12/03 (Backus) Asbestos Assessment Required Exploratory Demolition - Third (3rd) Floor Gym Locker Room Furnish & install 2 water coolers in the boys and girls locker rooms. EEC / 301-742-0330 Code A - Asbestos abated on 06/10/02 PER Leroy Minton confirmation.(RG 06/18/02) | February 21, 2002 | February 12, 2003 | 356 days |
| Duke Ellington School | FM-200223861 03 2/12/03 Ellington, Duke Second floor - Library Has a electrical socket in floor that need to be removed. | January 13, 2003 | February 12, 2003 | 30 days |
| Duke Ellington School | FM-200224414 03 2/12/03 Ellington, Duke Second floor - Library Need a electrical outlet for the air conditioner. | January 23, 2003 | February 12, 2003 | 20 days |
| Duke Ellington School | FM-200224889 03 2/12/03 Ellington, Duke Second floor - Library Has a electrical socket in floor that need to be remove. | January 30, 2003 | February 12, 2003 | 13 days |
| Kimball Elementary School | FM-200225333 03 2/13/03 KIMBALL room 106 1. Asbestos assessment may be required per C. Bradley @ 202-438-7437. 2. Remove and repair rupture on heating coil in classroom 106 leak has been isolated by valving unit, left room with only on radiator. Asbestos Code A - Clear for repairs on 02/07/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | February 6, 2003 | February 13, 2003 | 7 days |
| Kimball Elementary School | FM-200219710 /02 2/13/03 Kimball Second Floor - Auditorium 1) Replace broken window glass. | October 21, 2002 | February 13, 2003 | 115 days |
| Johnson JHS | FM-200225543 03 2/13/03 Johnson Boiler Room P.M Chiller | February 11, 2003 | February 13, 2003 | 2 days |
| Johnson JHS | FM-200214373 02 2/13/03 Johnson - F519.3 First floor - gym 1. Fire extinguisher cabinets x 4 missing glass / door x 4. | August 14, 2002 | February 13, 2003 | 183 days |
| Macfarland Middle School | FM-200225278 03 2/13/03 Macfarland School Remove access growth on fence line | February 5, 2003 | February 13, 2003 | 8 days |
| Raymond Elementary School | FM-200225552 03 2/13/03 Raymond Boiler Room P.M Chiller | February 11, 2003 | February 13, 2003 | 2 days |
| Brightwood Elementary School | FM-200203776 02 2/13/03 BRIGHTWOOD BOILER ROOM REPAIR BOILER #3. BOILER IN LOCK OUT, STAND BY MODE. (CONTRACTOR) | March 4, 2002 | February 13, 2003 | 346 days |
| Orr Elementary School | FM-200224879 03 2/13/03 Orr 1) Remove all locks on stairwell doors. | January 30, 2003 | February 13, 2003 | 14 days |
| Hine JHS | FM-200225546 03 2/13/03 Hines Boiler Room P.M Chiller | February 11, 2003 | February 13, 2003 | 2 days |
| Winston EC | FM-200225535 03 2/13/03 Winston Boiler Room P.M Chiller | February 11, 2003 | February 13, 2003 | 2 days |
| Terrell Mc ES | FM-200223314 /02 2/13/03 Terrell, M.C. Boiler Room Replace relief valve: model #M, serial # 740, size 1 1/2, set 40-LBS, vavle keep popping> | December 30, 2002 | February 13, 2003 | 45 days |
| Ronald H. Brown MS | FM-200225542 03 2/13/03 Ron Brown Boiler Room P.M Chiller | February 11, 2003 | February 13, 2003 | 2 days |
| Gibbs Elementary School | FM-200225545 03 2/13/03 Gibbs Boiler Room P.M Chiller | February 11, 2003 | February 13, 2003 | 2 days |
| Payne Elementary School | FM-200223778 03 2/13/03 Payne Kitchen Exit Corridor Room Asbestos assessment required Repair or replace 1" return line on the convector in air way of the kitchen steam is coming out very badly. Asbestos Code A - Clear for repairs on 01/15/03. Horne Engineering - Philp Connolly (RG 01/17/03) | January 13, 2003 | February 13, 2003 | 31 days |
| Gibbs Elementary School | FM-200222753 /02 2/13/03 Gibbs School Repair brick work due to plumbing repairs. | December 18, 2002 | February 13, 2003 | 57 days |
| Ferebee-Hope Elementary School | FM-200225645 03 2/13/03 Ferebee Hope Pool and Pump Room First Floor 1. Provide heat to pool water 2. Added chemical to pool water 3. Adjusted air temp. 4. Provide information for abestos request | February 11, 2003 | February 13, 2003 | 2 days |
| Ferebee-Hope Elementary School | FM-200225636 03 2/13/03 Ferebee Hope Pool and Pump Room First Floor 1. Back wash pool and drop water level 2. Check chemical and ph level 3. Open steam stop valve, to heat pool | February 11, 2003 | February 13, 2003 | 2 days |
| West Elementary School | FM-200224690 03 2/13/03 West Boiler Room Basement Asbestos Assestment Required Replace 1 1/2" gate valve on back of #1 and #2 boilers blow down lines. Valves will not hold (leaking) Asbestos Code A - Clear for repairs on 01/29/03. Horne Engineering - Sharon Voss ( RG 01/30/03) | January 28, 2003 | February 13, 2003 | 16 days |
| Clark Elementary School | FM-200224993 03 2/13/03 Clark Boiler Room Asbestos assessment required Replace leaking tubes in Boiler #1. Asbestos Code A - Clear for repairs on 02/03/03. Horne Engineering - Troy Wilcome (RG 02/04/03) | January 31, 2003 | February 13, 2003 | 13 days |
| Cleveland Elementary School | FM-200225699 03 2/13/03 Cleveland First floor cafeteria managers office Need locksmith to come and cut new key to the cafeteria managers office. | February 12, 2003 | February 13, 2003 | 1 day |
| Eastern High School | FM-200225782 03 2/13/03 (Eastern) Outside/Football shed: Replace locks on doors to shed, locks damaged due to vandalism. (Equipment stored in the shed) | February 13, 2003 | February 13, 2003 | 0 days |
| Woodson High School | FM-200225635 03 2/13/03 H.D Woodson Pool Pump Room First Floor 1. Some open return system line, which released large amount of steam 2. Inform contractor, that pool needs vacuum 3. Check chemical level | February 11, 2003 | February 13, 2003 | 2 days |
| Benjamin Banneker Academic HS | FM-200225737 03 2/13/03 Banneker Boiler room Repair or replace sump pumps # 1 and # 2, boiler room is flooded,problem appears to be with the pumps and not the motors | February 13, 2003 | February 13, 2003 | 0 days |
| Meyer Elementary School | FM-200207401 02 2/13/03 (Meyer) Fire code violation: 1. Asbestos assessment required. 1st Floor/Room #13: Defective Door missing glass. Code A-clear for repair by Horne Engineer ( Bipin Nanavaty ) on 05/15/02 | May 8, 2002 | February 13, 2003 | 281 days |
| Woodson High School | FM-200225538 03 2/13/03 H. D Woodson Boiler Room P.M Chiller | February 11, 2003 | February 13, 2003 | 2 days |
| Ludlow-Taylor ES | FM-200225207 03 2/13/03 Ludlow-Taylor First floor recreation office and custodian room Unstop sink in bathroom. | February 5, 2003 | February 13, 2003 | 8 days |
| Emery Elementary School | FM-200212290 02 2/13/03 (Emery) Fire code violation: Exit #2: Exit light out. | July 16, 2002 | February 13, 2003 | 212 days |
| Lincoln Middle School | FM-200224778 03 2/13/03 Lincoln / Taft Second floor - Office off from gym EMERGENCY Restroom - toilet needs to repaired, sink no water supply to both toilet and sink. Shower not working, no water supply replace fixtures thru out. | January 29, 2003 | February 13, 2003 | 15 days |
| Emery Elementary School | FM-200212264 02 2/13/03 (Emery) Fire code violation: Page 1 of 2 Next to room #319: Exit light. tracking # 14593 # 14606 | July 16, 2002 | February 13, 2003 | 212 days |
| Woodson High School | FM-200225646 03 2/13/03 H.D Woodson Pool Pump Room First Floor 1. Put swimming pool back on line 2. Added chemicals to water 3. Back wash filter system | February 11, 2003 | February 13, 2003 | 2 days |
| Woodson High School | FM-200225447 03 2/13/03 Woodson, H.D. Room 411 Asbestos assessment required Repair or replace ruptured heating coil in unit heater in room 411, there no isolation valves Asbestos Code A - Clear for repairs on 02/10/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | February 10, 2003 | February 13, 2003 | 3 days |
| Roosevelt High School | FM-200225461 03 2/13/03 (Roosevelt) Boiler room: Repairs on Thursday: Supply materials to make necessary repairs to cables, to supply power to boiler room. | February 10, 2003 | February 13, 2003 | 3 days |
| Kimball Elementary School | FM-200225792 03 2/13/03 Kimball Classroom 104 Repair/Replace leaking steam trap. | February 13, 2003 | February 13, 2003 | 0 days |
| Emery Elementary School | FM-200212289 02 2/13/03 (Emery) Fire code violation: Playground Exit: Exit light out. tracking # 14604 # 14596 | July 16, 2002 | February 13, 2003 | 212 days |
| Murch Elementary School | FM-200222602 /02 2/13/03 Murch Water fountains are leaking through out bldg. | December 16, 2002 | February 13, 2003 | 59 days |
| Kramer Middle School | FM-200214818 02 2/14/03 Kramer F-303.4 Fire Code Violation 2nd Floor Stairwell B Door has missing latch. | August 16, 2002 | February 14, 2003 | 182 days |
| Ballou Senior High School | FM-200216979 02 2/14/03 Ballou F- 110.1(7) Fire Code Violation 1st Floor Auditorium Defective electrical wiring. | September 9, 2002 | February 14, 2003 | 158 days |
| Ballou Senior High School | FM-200216982 02 2/14/03 Ballou F- 608.1 Fire Code Violation 1st Floor Auditorium Exit doors in rear of auditorium need adjustment. | September 9, 2002 | February 14, 2003 | 158 days |
| Ballou Senior High School | FM-200224740 03 2/14/03 (Ballou) 2nd Floor - water coolers: 1. Water cooler near elevator reanchor to wall ( no filter). 2. Water cooler near 209 ( no filter) reanchor bracket. 3 Water cooler near 215 ( no filter) reanchor bracket. Asbestos Code A - Clear for repairs on 02/10/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | January 28, 2003 | February 14, 2003 | 17 days |
| Cardozo High School | FM-200223587 03 2/14/03 (Cardozo) 1st Floor/Boys restroom: A total of three (3) urinals needs snaking out. | January 7, 2003 | February 14, 2003 | 38 days |
| Cardozo High School | FM-200225850 03 2/14/03 (Cardozo) 1st & 3rd Floors/Boys bathrooms: Unstop urinals in 1st and 3rd floor boys bathrooms. Urinals are backing up, flooding the floors when flushed. Water supply turned off to stop flooding; restore water supply to sink. | February 14, 2003 | February 14, 2003 | 0 days |
| Clark Elementary School | FM-200222112 02 2/14/03 (Clark) 1st Floor/Storeroom: Make necessary repairs to restore lights which will not come on. Staff is unable to find the circuit breaker that controls the storeroom. | December 4, 2002 | February 14, 2003 | 72 days |
| Cleveland Elementary School | FM-200225701 03 2/14/03 Cleveland First floor Room 103 headstart Repair lock on the door. Having problem with master key locking and unlocking. | February 12, 2003 | February 14, 2003 | 2 days |
| Deal Junior High School | FM-200224351 03 2/14/03 Deal Second floor - room 220 Replace lock cylinder, unable to secure science lab. | January 22, 2003 | February 14, 2003 | 23 days |
| Eastern High School | FM-200225058 03 2/14/03 repair hole in wall left due to plumbing repair | February 3, 2003 | February 14, 2003 | 11 days |
| Duke Ellington School | FM-200218789 02 2/14/03 Ellington Ground floor - Cafeteria manager"s office Install two outlets inside cafeteria office, so that extension cord can be removed. | October 3, 2002 | February 14, 2003 | 134 days |
| Duke Ellington School | FM-200221438 /02 2/14/03 Ellington, Duke Basement - cafeteria storage room Light fixture in the storage room will not work, need electrical repair. | November 20, 2002 | February 14, 2003 | 86 days |
| Emery Elementary School | FM-200212265 02 2/14/03 (Emery) Fire code violation: Page 1 of 2 Next to room #200: Exit light out. | July 16, 2002 | February 14, 2003 | 213 days |
| Ferebee-Hope Elementary School | FM-200214579 02 2/14/03 Ferebee-Hope F-110.1(1) Fire Code Violation 1. Asbestos Assessment Reqd. Cafeteria Level Recreation Game Room 2. Replacement of ceiling tiles. AsbestosCode A-clear for repair by Horne Engineer ( Troy Welcome ) Charles Buchanan on 8/19/02 | August 15, 2002 | February 14, 2003 | 183 days |
| Hine JHS | FM-200214028 02 2/14/03 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. Corridor door near room #233: Door not latching. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 14, 2003 | 186 days |
| Hine JHS | FM-200214029 02 2/14/03 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. Stairwell door by room #233: Door closer and latch broken also needs alignment. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 14, 2003 | 186 days |
| Janney Elementary School | FM-200225596 03 2/14/03 Janney Boiler Room Exterior R/R exterior lock on boiler room door key will not fully engage in key way to enable or disable lock | February 11, 2003 | February 14, 2003 | 3 days |
| Ketcham Elementary School | FM-200217917 02 2/14/03 (Ketcham) Fire code violation: 1 of 2 Basement/Kitchen: Door hardware (knob) missing in kitchen exit door, exit doors in the cafeteria. | September 19, 2002 | February 14, 2003 | 148 days |
| Kramer Middle School | FM-200214813 02 2/14/03 Kramer F-303.4 Fire Code Violation 3rd Floor Room 315 Defective hardware. | August 16, 2002 | February 14, 2003 | 182 days |
| Kramer Middle School | FM-200214845 02 2/14/03 Kramer F-303.4 Fire Code Violation 1st Floor Boys' Side Coach's Office Door not latching. Routed to Locksmith on 1/15/03 per Structural Maintenance. | August 16, 2002 | February 14, 2003 | 182 days |
| Moten Elementary School | FM-200216883 02 2/14/03 Moten F-303.4 Fire Code Violation 2nd Floor Corridor Doors missing latch. | September 6, 2002 | February 14, 2003 | 161 days |
| Moten Elementary School | FM-200216893 02 2/14/03 Moten F-303.4 Fire Code Violation 2nd Floor Auditorium Stage right exit door in corridor is not latching. | September 6, 2002 | February 14, 2003 | 161 days |
| Moten Elementary School | FM-200216895 02 2/14/03 Moten F-303.4 Fire Code Violation Asbestos Assessment Reqd. 2nd Floor Auditorium Exit door in corridor has defective latch/stage left. | September 6, 2002 | February 14, 2003 | 161 days |
| Moten Elementary School | FM-200216896 02 2/14/03 Moten F-303.4 Fire Code Violation Asbestos Assessment Reqd. 2nd Floor Hallway Corridor latch is missing. | September 6, 2002 | February 14, 2003 | 161 days |
| Orr Elementary School | FM-200214669 02 2/14/03 Orr F-303.4 Fire Code Violation 1st Floor Level Recreation Area Recreation side door is defective. | August 15, 2002 | February 14, 2003 | 183 days |
| Roosevelt High School | FM-200225135 03 2/14/03 Roosevelt Ground Floor - Outside of Room (4) 1) Needs new breaker, breaker keeps kicking off. | February 4, 2003 | February 14, 2003 | 10 days |
| School WW High School | FM-200225831 03 2/14/03 School W/O Walls Boiler room Repair or replace leaking pilot line and or valve on the # 1 boiler ,line has a tag on it, also cover exposed wires on the boiler. | February 14, 2003 | February 14, 2003 | 0 days |
| Sousa Middle School | FM-200217764 02 2/14/03 (Sousa) Fire code violation: Page 2 of 6 1st Floor/Room #116: Door leading to playground need 116 not operating properly, needs adjusting. | September 18, 2002 | February 14, 2003 | 149 days |
| Sousa Middle School | FM-200217862 02 2/14/03 (Sousa) Fire code violation: Page 5 of 6 Room #303: Door latch missing. 09/18/2002 17:03 EJ - | September 18, 2002 | February 14, 2003 | 149 days |
| Sousa Middle School | FM-200217863 02 2/14/03 (Sousa) Fire code violation: Page 5 of 6 3rd Floor/Corridor: Door not latching next to room #301. 09/18/2002 17:03 EJ - | September 18, 2002 | February 14, 2003 | 149 days |
| Sousa Middle School | FM-200217864 02 2/14/03 (Sousa) Fire code violation: Page 6 of 6 Room #301: Door hardware not working (Both doors) 09/18/2002 17:03 EJ - | September 18, 2002 | February 14, 2003 | 149 days |
| Spingarn High School | FM-200225868 03 2/14/03 Spingarn Boiler Room Boiler #4 Replace refractory to door. | February 14, 2003 | February 14, 2003 | 0 days |
| Turner Elementary School | FM-200215236 02 2/14/03 Turner Fire code violation Second floor - Center hallway Exit light not illuminated. | August 21, 2002 | February 14, 2003 | 177 days |
| Walker-Jones EC | FM-200225533 03 2/14/03 Walker Jones Boiler Room P.M Chiller | February 11, 2003 | February 14, 2003 | 3 days |
| West Elementary School | FM-200220800 /02 2/14/03 (West) Health Code Violation: Kitchen/Cafeteria: Increase temperature of hot water on the premises for proper hand washing, cleaning, sanitizing trays and equipment. | November 13, 2002 | February 14, 2003 | 93 days |
| Wilkinson ES | FM-200215983 02 2/14/03 Wilkinson Fire code violation: First floor - Teacher's storage room Need keys. | August 28, 2002 | February 14, 2003 | 170 days |
| Wilson J. O. ES | FM-200222595 /02 2/14/03 J.O Wilson 1st stair way Asbestos assesment required on ceiling Repair or replace ruptured supply in ceiling of stairway. Asbestos Code A - Clear for repairs on 12/16/02. Horne Engineering - Bipin Nanavaty (RG 12/18/02) | December 16, 2002 | February 14, 2003 | 60 days |
| Wilson High School | FM-200224845 03 2/14/03 (Wilson, W.) 1st Floor Auditorium: Replace electrical conduit and wiring to univent. | January 29, 2003 | February 14, 2003 | 16 days |
| Woodson High School | FM-200216580 02 2/14/03 (Woodson, H.D.) Fire code violation: 7th Floor Stairwell #1: Hardware defective, and not latching hall. | September 5, 2002 | February 14, 2003 | 162 days |
| Woodson High School | FM-200216622 02 2/14/03 (Woodson, H.D.) Fire code violation: 4th floor/Stairway#1: Door hardware missing. | September 5, 2002 | February 14, 2003 | 162 days |
| Woodson High School | FM-200216674 02 2/14/03 (Woodson, H.D.) Fire code violation: 3rd Floor/Stairwell #2: Missing hardware. Issue to locksmith per - R. Welch 9/27/02 | September 5, 2002 | February 14, 2003 | 162 days |
| Woodson High School | FM-200216735 02 2/14/03 (Woodson, H.D.) Fire code violation; 2nd Floor/Stairway #1: Latch missing. Issue to locksmith per - R. Welch 9/27/02 | September 6, 2002 | February 14, 2003 | 161 days |
| Woodson High School | FM-200216737 02 2/14/03 (Woodson, H.D.) Fire code violation; 2nd Floor/Stairway #3: Missing latch. Issue to loksmith per - R. Welch 9/27/02 | September 6, 2002 | February 14, 2003 | 161 days |
| Woodson High School | FM-200225329 03 2/14/03 Woodson, H.D. Ground floor room G 75 There is five electrical outlet on the floor that fire is shooting from them. | February 6, 2003 | February 14, 2003 | 8 days |
| Woodson High School | FM-200205588 02 2/15/03 H. D. Woodson 1st fl. mech room over pool Replace dehumidifier computer control panel. Kids broke in area and destroyed controls, possibly more damage. System is not working now, air is getting stuffy, walls beginning to sweat. | April 8, 2002 | February 15, 2003 | 313 days |
| Emery Elementary School | FM-200218751 02 2/15/03 Emery Boiler Room 1. Boiler# 2 - Down on flame failure | October 3, 2002 | February 15, 2003 | 135 days |
| Emery Elementary School | FM-200219596 /02 2/15/03 Emery Boiler Room Send burner technician with calibration instruments to properly claibrate burners at all modulation levels on boiler #1 and #2. When burners are calibrated properly they burnt more efficiently and cleaner * Alot of soot in boilers during cleaning. | October 17, 2002 | February 15, 2003 | 121 days |
| Ballou Senior High School | FM-200225558 03 2/18/03 Ballou Boiler Room P.M Chiller | February 11, 2003 | February 18, 2003 | 7 days |
| Young Elementary School | FM-200225916 03 2/18/03 Charles Young !!! EMERGENCY !!!! Outside Court Yard 1) The gutters are hanging from the building and need to be reattached . | February 18, 2003 | February 18, 2003 | 0 days |
| Woodson High School | FM-200225426 03 2/19/03 Woodson, H.D. Cafeteria Asbestos assessment required Repair or rplace ruputured 1 1/2 return line on heating unit in the cafeteria. Asbestos Code A - Clear for repairs on 02/10/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | February 10, 2003 | February 19, 2003 | 9 days |
| Duke Ellington School | FM-200218790 02 2/19/03 Ellington Room 314 Electrical outlet hanging off of the wall (no cover). | October 3, 2002 | February 19, 2003 | 139 days |
| Duke Ellington School | FM-200218541 02 2/19/03 Ellington Ground Floor - Outside Cafeteria 1) Re-anchor brackets supporting electrical pipes. | September 30, 2002 | February 19, 2003 | 142 days |
| Reed LC | FM-200224276 03 2/19/03 (Reed) Ground floor - Pool deck area An electrician is needed to find out why four (4) wall mounted lights will not come on. | January 21, 2003 | February 19, 2003 | 29 days |
| Reed LC | FM-200225777 03 2/19/03 REED !!! EMERGENCY !!! First Floor - Cafeteria 1) Circuit went out and the oven and the refrigerator is not working. | February 13, 2003 | February 19, 2003 | 6 days |
| Anacostia Senior High School | FM-200225925 03 2/19/03 Anacostia Boiler Room Busted 2" black nipple on supply line feeding all boilers. Continuously loosing water. NO HEAT | February 19, 2003 | February 19, 2003 | 0 days |
| Brookland Elementary | FM-200225922 03 2/19/03 Brookland 2nd floor level ,area that over looks the trash dumpster Asbestos assessment requierd of the wall Locate and make repairs to ruptured line in the wall of the the 2nd floor area that over looks the dumpster. Principle Office No heat in principle office neumatic control valve was clogged up Ground Dept. Patch up 6" inch. diameter hole Asbestos Code A - Clear for repairs on 02/19/03. Horne engineering - Bipin Nanavaty (RG 02/20/03) | February 19, 2003 | February 19, 2003 | 0 days |
| Moten Elementary School | FM-200203434 02 2/20/03 (Moten) Health code violation: Kitchen: Hot water tank; leaks from the bottom. | February 25, 2002 | February 20, 2003 | 360 days |
| Smothers ES | FM-200225485 03 2/20/03 Smothers Custodian Closet First Floor Replace 3" inch. discharge line to sump pump | February 10, 2003 | February 20, 2003 | 10 days |
| Hart Middle School | FM-200220465 /02 2/20/03 (Hart) Health Code Violation: Kitchen: Repair or replace garbage disposal on sink; gargage disposal leaks at the bottom. | October 31, 2002 | February 20, 2003 | 112 days |
| Hart Middle School | FM-200220464 /02 2/20/03 (Hart) Health Code Violation: Kitchen: Provide hot and cold water knobs at two (2) compartment sink, near cooking facility area. | October 31, 2002 | February 20, 2003 | 112 days |
| Green Elementary School | FM-200219956 /02 2/20/03 Green First floor - Cafeteria Installation of one water cooler in all purpose room. Asbestos Code A - Clear for repairs on 02/13/03. Horne Engineering - Sharon Voss (RG 02/14/03) | October 24, 2002 | February 20, 2003 | 119 days |
| Roosevelt High School | FM-200220252 /02 2/20/03 Roosevelt Kitchen Replace two faucets in service sink. NOTE: (Chicago faucet) (W/Vaccum breaker CHF 897) | October 29, 2002 | February 20, 2003 | 114 days |
| Raymond Elementary School | FM-200225119 03 2/20/03 Raymond See Locations Attached Reprogram computerized schedule for univents unit are shutting off about 5:00 p.m | February 3, 2003 | February 20, 2003 | 17 days |
| Sousa Middle School | FM-200217856 02 2/21/03 (Sousa) Fire code violation: Page 5 of 6 Stairwell near room #216: Hole in ceiling. 09/18/2002 17:03 EJ - Asbesstos Code A-clear for repair by Horne Engineer Sharon Voss DCPS Charles E. Buchanan on 9/20/02 | September 18, 2002 | February 21, 2003 | 156 days |
| Sousa Middle School | FM-200217843 02 2/21/03 (Sousa) Fire code violation: Page 4 of 6 2nd Floor: Exit door leading toward library missing latch. | September 18, 2002 | February 21, 2003 | 156 days |
| Wilkinson ES | FM-200215978 02 2/21/03 Wilkinson F110.3 Fire code violation: First floor - Girls restroom Need drain cover. | August 28, 2002 | February 21, 2003 | 177 days |
| Sousa Middle School | FM-200217834 02 2/21/03 (Sousa) Fire code violation: Page 3 of 6 1st Floor/Room #120: Hole in ceiling. Asbesstos Code A-clear for repair by Horne Engineer Sharon Voss DCPS Charles E. Buchanan on 9/20/02 | September 18, 2002 | February 21, 2003 | 156 days |
| Ketcham Elementary School | FM-200225879 03 2/21/03 Ketcham Front entrance Requesting that front door lock be fixed. It is not catching, so front door can not be secured properly. | February 14, 2003 | February 21, 2003 | 7 days |
| Bruce-Monroe Elementary School | FM-200225946 03 2/21/03 Bruce-Monroe Boiler Room Repair/Replace rupture 1" domestic hot water line in the boiler room. | February 20, 2003 | February 21, 2003 | 1 day |
| Hine JHS | FM-200213929 02 2/21/03 (Hine) Fire code violation: Page 1 of 6 1. Asbestos assessment required. Room #307: Door needs adjusting. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 9, 2002 | February 21, 2003 | 196 days |
| Plummer Elementary School | FM-200225927 03 2/21/03 Plummer Boiler Room Replace a leaking 3" inch. circulating line and replace the blow down on the storage tank | February 19, 2003 | February 21, 2003 | 2 days |
| Hart Middle School | FM-200220463 /02 2/21/03 (Hart) Health Code Violation: Kitchen: Repair two (2) compartment sink near serving line with continued running cold water. | October 31, 2002 | February 21, 2003 | 113 days |
| Ketcham Elementary School | FM-200225785 03 2/21/03 Ketcham Requesting that the locks be changed on the principal and assistant principals offices. Also a lock be put on the principals security closet. | February 13, 2003 | February 21, 2003 | 8 days |
| Turner Elementary School | FM-200215244 02 2/21/03 Turner Fire code violation Second floor - Room 204 Door hardware missing. | August 21, 2002 | February 21, 2003 | 184 days |
| Roosevelt High School | FM-200225156 03 2/21/03 (Roosevelt) 2nd Floor/Boys bathroom: Due to vandalism, replace sink inside this boys restroom. | February 4, 2003 | February 21, 2003 | 17 days |
| Green Elementary School | FM-200225846 03 2/21/03 Green First floor girls toilet and room 131 Unstop commode in girls toilet in main lobby and room 131. Plunging will not open line. | February 14, 2003 | February 21, 2003 | 7 days |
| Beers Elementary School | FM-200225495 03 2/21/03 Beers Auditorium Asbestos assessment required Check insulation on pipes and coil unit. Repair/Replace leaking coil in air handle unit. Asbestos Code A - Clear for repairs on 02/14/03. Horne Engineering - Philp Connolly (RG 02/19/03) | February 10, 2003 | February 21, 2003 | 11 days |
| Marshall Educational Center | FM-200225293 03 2/21/03 Marshall Kitchen Asbestos assessment required Repair leaking coil in kitchen. Asbestos Code A - Clear for repairs on 02/07/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | February 6, 2003 | February 21, 2003 | 15 days |
| Beers Elementary School | FM-200122717 /01 2/21/03 (BEERS) ASBESTOS ASSESSMENT REQ. BLDG. #1, 2, AND 3 ALL BATHROOMS THROUGH OUT THE BUILDING NEED LOCKS ON DOORS. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-07-01 HORNE ENGINEER : SHARON VOSS | October 31, 2001 | February 21, 2003 | 478 days |
| Sousa Middle School | FM-200217717 02 2/21/03 (Sousa) Fire code violation: Page 1 of 6 Room #12: Hole in ceiling Asbestos Code A - Clear for repairs on 02/13/03. Horne Engineering - Tony Marcolin (RG 02/14/03) | September 17, 2002 | February 21, 2003 | 157 days |
| Brookland Elementary | FM-200225926 03 2/21/03 Brookland Exterior entrance door by the dumpster Make adjustments on the outside cylinder of the exterior door by thew dumpster, the key binds very hard to turn . Asbestos Code A - Clear for repairs on 02/19/03. Horne Engineering - Bipin Nanavaty (RG 02/20/03) | February 19, 2003 | February 21, 2003 | 2 days |
| Ronald H. Brown MS | FM-200218227 02 2/21/03 (Brown, Ron (Roper) Fire code violation: Page 2 of 3 Library: Missing ceiling tile (Hole in the ceiling. Asbestos Code A - Clear for repairs on 09/25/02. Horne Engineering - Philp Connolly (RG 09/26/02) | September 24, 2002 | February 21, 2003 | 150 days |
| Ferebee-Hope Elementary School | FM-200214602 02 2/21/03 Ferebee-Hope F-608.1 Fire Code Violation 2nd Floor D Building UDC Rm. 207A Door needs adjustment. | August 15, 2002 | February 21, 2003 | 190 days |
| Kimball Elementary School | FM-200215007 02 2/21/03 Kimball F110.1 Fire code violation Room 105 Ceiling tile missing. Asbestos Code A - Clear for repairs on 01/24/03. Horne Engineering - Troy Wilcome ( RG 01/30/03) | August 19, 2002 | February 21, 2003 | 186 days |
| Bunker Hill Elementary School | FM-200225947 03 2/22/03 Bunker Hill Boiler Room Made necessary repairs to back flow preventor valve | February 20, 2003 | February 22, 2003 | 2 days |
| Meyer Elementary School | FM-200225343 03 2/22/03 Meyer Boiler room floor Unstop floor drains between Boilers #1 and #2 . | February 6, 2003 | February 22, 2003 | 16 days |
| Payne Elementary School | FM-200226011 03 2/23/03 PAYNE BOILER ROOM Repair/Replace rupture line in the boiler room. | February 21, 2003 | February 23, 2003 | 2 days |
| Raymond Elementary School | FM-200226013 03 2/23/03 (Raymond) EMERGENCY New wing/1st Floor: Hot water running very hard in the custodian closet; unable to find shut-off valve. | February 21, 2003 | February 23, 2003 | 2 days |
| Johnson JHS | FM-200219406 /02 2/24/03 Johnson Fourth floor room 423 Wall outlet not working, Teacher need it for her computer. Asbestos code A-clear for repair on 10/23/02 DCPS Charles E. Buchanan | October 15, 2002 | February 24, 2003 | 132 days |
| Whittier Elementary School | FM-200224339 03 2/24/03 Whittier Second floor - Hallway Repair or replace water fountain knob broken off. A child got his finger stuck in the hole were the knob goes. | January 22, 2003 | February 24, 2003 | 33 days |
| Meyer Elementary School | FM-200202917 02 2/24/03 (MEYER) BASEMENT/ ROOM 27 ONE ROW OF LIGHTS WENT OUT IN THE TEACHERS STORAGE ROOM. WE PUT BULBS IN THE LIGHTS THEY WILL NOT COME ON. NEEDS ATTENTION A.S.A.P. | February 12, 2002 | February 24, 2003 | 377 days |
| Wilkinson ES | FM-200215951 02 2/24/03 Wilkinson F-110.1(1) & F303.4 D.C. Supp 1999 Fire code violation: Second floor - Room 216 Need TV off of floor and door missing hardware. | August 28, 2002 | February 24, 2003 | 180 days |
| Janney Elementary School | FM-200226071 03 2/24/03 Janney Locksmith emergency Dead bolt lock on door room 300 will turn but will not unlock. Cannot get into room. | February 24, 2003 | February 24, 2003 | 0 days |
| Ferebee-Hope Elementary School | FM-200224916 03 2/24/03 Ferebee-Hope First floor - D-Building Replace two (2) knob locks on key and knob door.have key. Furnish key.Replace door closer, bent and broken. | January 30, 2003 | February 24, 2003 | 25 days |
| Wilkinson ES | FM-200216004 02 2/24/03 Wilkinson F-608.1 Fire code violation: First floor - Hall 207 Exit door in hall #207 next to gym need adjustment. | August 28, 2002 | February 24, 2003 | 180 days |
| Wilkinson ES | FM-200216005 02 2/24/03 Wilkinson F-608.1 Fire code violation: First floor - Exit door in stairwell next to gym in hall need adjustment. | August 28, 2002 | February 24, 2003 | 180 days |
| Payne Elementary School | FM-200225160 03 2/24/03 Payne Health suite old building Replace both outside locks on doors. We do have keys to the doors. | February 4, 2003 | February 24, 2003 | 20 days |
| Nalle Elementary School | FM-200214965 02 2/24/03 Nalle F-110.1 Fire code violation: Room-118 Hole in wall. Asbestos Code A - Clear for repairs on 02/13/03. Horne Engineering - Tony Marcolin (RG 02/14/03) | August 19, 2002 | February 24, 2003 | 189 days |
| Winston EC | FM-200215683 02 2/24/03 Winston F-303.4 Fire Code Violation 3rd Floor Exit Door Exit door to gym not closing properly. | August 27, 2002 | February 24, 2003 | 181 days |
| Emery Elementary School | FM-200223754 /02 2/24/03 (Emery) Principal office bathroom toilet is clog water is coming out of bathroom in to office floor !!!EMERGENCY!!! | November 12, 2002 | February 24, 2003 | 104 days |
| Burrville Elementary School | FM-200224500 03 2/24/03 Burrville Second Floor - Gym Area 1) Replace lock on Gym Door. | January 24, 2003 | February 24, 2003 | 31 days |
| Wilson High School | FM-200224515 03 2/24/03 Wilson,W Collage Bureau-room 104A Asbestos assessment required Replace leaking return line 1/2" black iron pipe, to radiator. Leak is inside of wall next to radiator. Asbestos Code A - Clear for repairs on 01/27/03. Horne Engineering - Tony Marcolin (RG 01/28/03) | January 24, 2003 | February 24, 2003 | 31 days |
| Jefferson JHS | FM-200225924 03 2/24/03 Jefferson Boiler Room Replace 1 1/2" black pipe (approx 8" long) at the top of Hartford Loop. Pipe leaking is the supply line from the condensate pump. Boiler is now inoperable. No insulation on pipe. | February 19, 2003 | February 24, 2003 | 5 days |
| Ferebee-Hope Elementary School | FM-200224915 03 2/24/03 Ferebee-Hope First floor - B-Building weight room Change lock do not have key. Furnish key.Replace door closer, bent and broken. | January 30, 2003 | February 24, 2003 | 25 days |
| Orr Elementary School | FM-200214659 02 2/24/03 Orr F-303.4 Fire Code Violation 1st Floor Girls' Bathroom Missing hardware on bathroom door. | August 15, 2002 | February 24, 2003 | 193 days |
| Nalle Elementary School | FM-200214973 02 2/24/03 Nalle F-110.1 Fire code violation: Second floor - Library Hole in walls. | August 19, 2002 | February 24, 2003 | 189 days |
| Woodson High School | FM-200226094 03 2/24/03 (Woodson, H.D.) 5th Floor/Boys bathroom: Flush valve leaking profusely; running out in the hallway. Unit broke on flush valve; need a complete flush valve unit. (Unable to shut off water) | February 24, 2003 | February 24, 2003 | 0 days |
| Nalle Elementary School | FM-200214956 02 2/24/03 Nalle F-110.1 Fire code violation: Room 217 Hole in wall above sink. Asbestos Code A - Clear for repairs on 02/13/03. Horne Engineering - Tony Marcolin (RG 02/14/03) | August 19, 2002 | February 24, 2003 | 189 days |
| Patricia R Harris Ed Center | FM-200214456 02 2/24/03 Harris,P.R. F-608.5 Fire Code Violation 1st Floor Next to Room 119 Door is inoperable. | August 14, 2002 | February 24, 2003 | 194 days |
| Roosevelt High School | FM-200223608 03 2/24/03 (Roosevelt) !!!EMERGENCY!!! Through-Out building: Spot electrical power outage. | January 7, 2003 | February 24, 2003 | 48 days |
| Kimball Elementary School | FM-200226081 03 2/25/03 Old Boiler Room in flooded north wing. | February 24, 2003 | February 25, 2003 | 1 day |
| Beers Elementary School | FM-200223931 03 2/25/03 Beers Second floor - bldg. #3 teacher's lounge Principal is requesting keys to be made for teacher's lounge door for all teachers and staff. Custodian staff need four (4) keys made do to the different kinds of pad lock door lock. | January 14, 2003 | February 25, 2003 | 42 days |
| Spingarn High School | FM-200228809 03 2/25/03 (Spingarn) KITCHEN IS EXTREMELY DARK. LIGHTING IS NOT ADEQUATE FOR OPERATION. HEALTH CODE VIOLATION. | February 25, 2003 | February 25, 2003 | 0 days |
| Jefferson JHS | FM-200202793 02 2/25/03 Jefferson Auditorium stage mech. room Replace two (2) three phase 12 hp motors for air handler units in auditorium. | February 11, 2002 | February 25, 2003 | 379 days |
| Montgomery ES | FM-200226126 03 2/25/03 Scott Montgomery Auditorium, left side facing stage Replace motor magnetek in Air Handler Unit Volts: 230/460 HP: 1.5 RPM: 1725 FRAME: NA56Y PART 10-168273 AMP: 4.8/2.4 SF 120 INSUL CLASS B, TIME: CONT, PHASE: 3 TYPE: SC, HZ: 60 , CODE M, SERIAL B82-03 | February 24, 2003 | February 25, 2003 | 1 day |
| Takoma Educational Center | FM-200119916 01 2/25/03 (TAKOMA) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ PASSAGE 84 REPAIR CEILING (SHEET ROCK). DAMAGED FROM PREVIOUS PIPE LEAK. ASBESTOS CODE A-CLEAR FOR REPAIR NO 9/21/01 BY HORNE ENGINEER ROGER KAGER | September 17, 2001 | February 25, 2003 | 526 days |
| Beers Elementary School | FM-200222313 /02 2/25/03 (Beers) Building #3/2nd Floor-Teachers lounge: Principal is requesting keys to be made for all teachers and staff. Custodian staff needs four (4) keys made due to the different kinds of padlock door lock. | December 10, 2002 | February 25, 2003 | 77 days |
| Turner Elementary School | FM-200215239 02 2/25/03 Turner Fire code violation Second floor - Room 204 Light kit missing from door. Asbestos/Lead Code A-clear for repair by Horne Engineer Sheryll James/ Edward Rodriguez on 8/26/02 DCPS Charles E. Buchanan | August 21, 2002 | February 25, 2003 | 188 days |
| Gibbs Elementary School | FM-200214581 02 2/25/03 Gibbs - f-110.1(1) Second floor - Girls restroom Hole in ceiling "unsafe conditions". | August 15, 2002 | February 25, 2003 | 194 days |
| Gibbs Elementary School | FM-200214578 02 2/25/03 Gibbs - f-110.1(1) Third floor - room 305 Hole in ceiling (storage room), hole in wall at bottom "unsafe conditions". | August 15, 2002 | February 25, 2003 | 194 days |
| Garfield ES | FM-200226232 03 2/25/03 Garfield Frist Floor - Enterance Door 1. Replace glass in the enterance door on the left side ,unable to secure building . | February 25, 2003 | February 25, 2003 | 0 days |
| Ferebee-Hope Elementary School | FM-200214620 02 2/25/03 Ferebee-Hope F-110.3 Fire Code Violation 1. Asbestos Assessment Reqd. Swimming Pool Level Boys' Shower Room 2. Water leaking from ceiling. Asbestos Code A - Clear for repairs on 08/20/02. Horne Engineering - Troy Wilcome (RG 08/21/02) | August 15, 2002 | February 25, 2003 | 194 days |
| Beers Elementary School | FM-200223935 03 2/25/03 Beers Auditorium P.E. teache's key broke and auditorium office door. Two keys need to be make for door. | January 14, 2003 | February 25, 2003 | 42 days |
| Beers Elementary School | FM-200223936 03 2/25/03 Beers Second floor - bldg # 1 Counselor's room Counselor's door lock is jammed - something is broken inside the knob lock. Counselor can not get into the room. | January 14, 2003 | February 25, 2003 | 42 days |
| Eliot Junior High School | FM-200218250 02 2/25/03 (Eliot) Fire code violation: Page 2 of 2 1st Floor/Boys gym: Missing glass in exit door | September 24, 2002 | February 25, 2003 | 154 days |
| Amidon Elementary School | FM-200226076 03 2/25/03 Amidon First Floor - Kitchen 1. The sprout broke off of kitchen sink , please repair or replace faucet . | February 24, 2003 | February 25, 2003 | 1 day |
| Savoy Elementary School | FM-200224423 03 2/25/03 Savoy Kitchen Air Handler First Floor Motor will not run (Power coming to main breaker but not leaving to supply the circuit) | January 23, 2003 | February 25, 2003 | 33 days |
| Beers Elementary School | FM-200225266 03 2/25/03 Beers Auditorium Auditorium hallway stairway door lock is jamming. Kids are bumping to the doors. | February 5, 2003 | February 25, 2003 | 20 days |
| Seaton Elementary School | FM-200225550 03 2/25/03 Seaton Boiler Room P.M Chiller | February 11, 2003 | February 25, 2003 | 14 days |
| Brent Elementary School | FM-200217277 02 2/26/03 Brent Asbestos Assessment Reqd. 1st, 2nd & 3rd Floor Stairwells Install lower handrails for handicapped child on both stairwell sides. [Use ADA requirements and guidelines.] Asbestos Code A - Clear for repairs on 01/16/03. Horne Engineering - Tony Marcolin (RG 01/17/03) | September 11, 2002 | February 26, 2003 | 168 days |
| Patterson ES | FM-200224903 03 2/26/03 Patterson Third floor - custodian closet stairwell 6 Repair or replace closet faucet. Hot water running shut off valve will not hold. | January 30, 2003 | February 26, 2003 | 27 days |
| Moten Elementary School | FM-200216975 02 2/26/03 Moten F- 303.4 Fire Code Violation 1st Floor Cafeteria Kitchen exit [rear] door not aligned. | September 9, 2002 | February 26, 2003 | 170 days |
| Moten Elementary School | FM-200216973 02 2/26/03 Moten F-303.4 Fire Code Violation 1st Floor Corridor Door closer missing next to incinerator room. | September 9, 2002 | February 26, 2003 | 170 days |
| Ferebee-Hope Elementary School | FM-200214636 02 2/26/03 Ferebee-Hope F-303.4/608.5 Fire Code Violation Auditorium Exit door needs adjustment near stage. | August 15, 2002 | February 26, 2003 | 195 days |
| Gibbs Elementary School | FM-200214593 02 2/26/03 Gibbs - f-303.4 First floor - Kitchen Side exit door in kitchen need adjustment. | August 15, 2002 | February 26, 2003 | 195 days |
| Montgomery ES | FM-200226240 03 2/26/03 S.Montgomery Auditorium Heating coil on air handler Asbestos assessment required Repair or replace leaking heat coil on the air handler in the auditorium, there is no heat heat in this area. Asbestos Code A - Clear for repairs on 02/26/03. Horne Engineering - Edward Rodriguez (RG 02/27/03 | February 26, 2003 | February 26, 2003 | 0 days |
| Winston EC | FM-200216049 02 2/26/03 Winston F-303.4 Fire Code Violation 1st Floor Corridor Door hardware missing. | August 28, 2002 | February 26, 2003 | 182 days |
| Sousa Middle School | FM-200205865 02 2/26/03 Sousa Gym Office Restroom & Boys & Girls Restrooms 1) The gym office toilet needs a wax ring the toilet will not flush properly. 2) In the boys restroom toilet will not flush properly. 3) The last toilet in the girls restroom will not flush properly and the frist toilet is stopped up. | April 16, 2002 | February 26, 2003 | 316 days |
| Woodson High School | FM-200216411 02 2/26/03 (Woodson, H.D.) Fire code violation: Basement/Music hallway auditorium: Exit door closer broken. Issue to locksmiths per - R. Welch 9/27/02 | September 4, 2002 | February 26, 2003 | 175 days |
| Smothers ES | FM-200225974 03 2/26/03 Smothers Third Floor - Roof Leak 1) Please check and repair roof leak on the west side of the building. Asbestos Code A - Clear for repairs on 02/25/03. Horne Engineering - Philp Connolly (RG 02/26/03) | February 21, 2003 | February 26, 2003 | 5 days |
| Clark Elementary School | FM-200225117 03 2/26/03 Clark Basement/Boiler Room Repair/Repair boiler #1 has leaking tubes. Note: One tube, 2 1/2 " Only (2) boilers in plant Asbestos Code A - Clear for repairs on 02/14/03. Horne Engineering - Sharon Voss (RG 02/19/03) | February 3, 2003 | February 26, 2003 | 23 days |
| Wilson High School | FM-200224403 03 2/26/03 (Wilson, W.) First floor - hallway room 123 Repair leaking water cooler. | January 23, 2003 | February 26, 2003 | 34 days |
| Reed LC | FM-200224274 03 2/26/03 (Reed) Ground floor - Boys lavatory in rec area Replace a cracked urinal in the above area. Wall mounted, urinal is cut off so it will not leak an flood the floor. | January 21, 2003 | February 26, 2003 | 36 days |
| Shaw JHS | FM-200226293 03 2/26/03 Shaw Second floor - Seventh grade section The electric is out. | February 26, 2003 | February 26, 2003 | 0 days |
| Thomas Elementary School | FM-200214660 02 2/26/03 (Neval Thomas) 1. Asbestos assessment required. 1st Floor: Defective door. Asbestos Code A Clear for repair by DCPS Charles E Buchanan | August 15, 2002 | February 26, 2003 | 195 days |
| Woodson High School | FM-200216629 02 2/26/03 (Woodson, H.D.) Fire code violation: 3rd Floor/Stairway #4: Door needs adjusting. | September 5, 2002 | February 26, 2003 | 174 days |
| Woodson High School | FM-200225856 03 2/27/03 Woodson,H.D Boiler room Asbestos assessment required Repair or replace 1 1/2" leaking return condensate return line on #2 boiler Asbestos Code A - Clear for repairs on 02/19/03. Horne Engineering - Bipin Nanavaty (RG 02/20/03) | February 14, 2003 | February 27, 2003 | 13 days |
| Bunker Hill Elementary School | FM-200206620 02 2/27/03 Bunker Hill Asbestos Assessment Reqd. 1st Floor Room 122W Install a security mirror in the technology center. The mirror is on-site. Code A-clear for repair by Horne Engineer by (Sam Ebrahim ) on 4/26/02 ( CEB ) | April 25, 2002 | February 27, 2003 | 308 days |
| Backus Middle School | FM-200226209 03 2/27/03 Backus Room 304 Asbestos assessment maybe required Repair or replace coil in univent in room 304 , coil was disconnected ,and the dose not have any heat. Asbestos Code A - Clear for repairs on 02/26/03. Horne Engineering - Troy Wilcome (RG 02/27/03) | February 25, 2003 | February 27, 2003 | 2 days |
| Bruce-Monroe Elementary School | FM-200225878 03 2/27/03 Bruce-Monroe Second floor Learning center # 204 Boys lavatory, bradley basin water is leaking from water. Domestic supply line under fixture. Bradley basin causing a lot of water damage to school bldg. | February 14, 2003 | February 27, 2003 | 13 days |
| Bruce-Monroe Elementary School | FM-200123116 01 2/27/03 (BRUCE-MONROE) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ LEARNING CENTER 204 COUNTER TOP/ CABINET NEEDS TO BE REPLACED. SINK REMOVAL IN AMP #324. Cape (IT Group) /703-461-6848 CODE A - Asbestos abated on 04/09/02 PER Leroy Minton Confirmation. (RG-04/12/02) | November 8, 2001 | February 27, 2003 | 476 days |
| Brookland Elementary | FM-200226286 03 2/27/03 Brookland Gym Gym teachers key is broken off in door. | February 26, 2003 | February 27, 2003 | 1 day |
| Benjamin Banneker Academic HS | FM-200224410 03 2/27/03 Banneker Basement / custodial office Plumber is needed in custodial office service, sink is backed up and closed. | January 23, 2003 | February 27, 2003 | 35 days |
| Webb Elementary School | FM-200224898 03 2/27/03 Webb First floor - health suite Lock need to be repaired or replace. It do not lock and it need to be locked at all times. | January 30, 2003 | February 27, 2003 | 28 days |
| Brightwood Elementary School | FM-200225960 03 2/27/03 Brightwood Second Floor - Computer lab 1) Replace window pane in computer lab. | February 20, 2003 | February 27, 2003 | 7 days |
| Bell High School | FM-200224834 03 2/27/03 Bell M.C Mechanical Room Seond Floor Repair or replace busted coil in air handler unit Asbestos Code A - Clear for repairs on 01/28/03. Horne Engineering - Edward Rodriguez ( RG 01/30/03) | January 29, 2003 | February 27, 2003 | 29 days |
| Spingarn High School | FM-200225416 03 2/27/03 Spingarn Room#115 Asbestos assessment required Repair leaking univent coil in room #115 Asbestos Code A - Clear for repairs on 02/11/03. Horne Engineering - Philp Connolly (RG 02/12/03) | February 10, 2003 | February 27, 2003 | 17 days |
| Hardy Middle School | FM-200118223 01 2/27/03 (HARDY) 1. ASBESTOS ASSESSMENT REQUIRED. BOYS GYM: WOOD FLOOR, BUCKLING IN BOYS GYM. ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/23/01 HORNE ENGINEER : SHERYLL JAMES Duplicate Permit/orig. issued 10/25/01. | August 23, 2001 | February 27, 2003 | 553 days |
| Harris, C.W. ES | FM-200205467 02 2/27/03 Harris, C.W. AMP #128 1. Asbestos Assessment Required. 2. Exploratory Demolition 3.Insulated 8' of 1/2" return line in ceiling of parent teacher room. 4.Plaster ceiling in parent teacher room. DCB (IT Group) / 703-461-6848 Code A - Asbestos abated on 04/05/02 PER Sheila R Howard confirmation.( 04/08/02 RG) | April 4, 2002 | February 27, 2003 | 329 days |
| Jessie LaSalle Elementary | FM-200226316 03 2/27/03 LaSalle Boiler room Repair modulating control on # 1 boiler boiler only runs in low fire ,#2 boiler down also Flame failure,FM-200221236 | February 27, 2003 | February 27, 2003 | 0 days |
| Patricia R Harris Ed Center | FM-200220217 /02 2/27/03 Harris, P.R. _ Health Code First floor Kitchen Repair or replace leaking twist turn on two (2) compartment pot and pans tubs. | October 29, 2002 | February 27, 2003 | 121 days |
| Hart Middle School | FM-200202217 02 2/27/03 HART BASEMENT CORRIDOR 1. ASBESTOS ASSESSMENT REQUIRED 2. BASEMENT CORRIDOR ACROSS FROM ROOM B26. 3. REPAIR LEAKING PIPE IN BASEMENT CORRIDOR ACROSS FROM ROOM B26, PIPE IS LEAKING IN CEILING. INVESTIGATE AND EXPLORE LEAK FROM CONCRETE WALL. POC CARNAL BRADLEY 202-438-7437 MUST CALL FOR AN ESCORT. DCB (IT GROUP) / 703-461-6848 Code A - Asbestos Abated On 03/01/02 Per Ronald Edwards Confirmation. (RG 03/13/02) | January 31, 2002 | February 27, 2003 | 392 days |
| Backus Middle School | FM-200201920 02 2/27/03 (BACKUS) THROUGHOUT ENTIRE BUILDING. TSI, PLASTER-REMOVAL, FLOOR TILES AND REPAIR. EXPLORATORY DEMOLITION IN AMP #395. ASBESTOS ASSESSMENT REQUIRED 3RD FLOOR HALLWAY BY CLASSROOM 306 REPLACE WALL-MOUNTED WATER FOUNTAIN WITH DOUBLE-SPIGGOT WATER COOLER. DCB (IT GROUP) / 703-461-6848 Code A - Asbestos Abated On 03/05/02 Per Ronald Edwards Confirmation. (RG 03/13/02) | January 28, 2002 | February 27, 2003 | 395 days |
| Hine JHS | FM-200214022 02 2/28/03 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. Recreation office: Bathroom door sticks. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 28, 2003 | 200 days |
| Hyde Elementary School | FM-200226365 03 2/28/03 Hyde Boys Toilet - Basement Repair leaking radiator in basement boys restroom. | February 27, 2003 | February 28, 2003 | 1 day |
| Woodson High School | FM-200226134 03 2/28/03 Woodson Escalator 1. Repair light s on path of escalator - seems to be electrical. | February 25, 2003 | February 28, 2003 | 3 days |
| Wilson High School | FM-200225975 03 2/28/03 Wilson W. First Floor - Aditorium 1) Install portable heaters inside air handler ducks . | February 21, 2003 | February 28, 2003 | 7 days |
| Coolidge High School | FM-200220735 /02 2/28/03 Coolidge Roof Leak 1) Roof leaking from third floor to ground floor in stairwell and hallways. | November 12, 2002 | February 28, 2003 | 108 days |
| Eastern High School | FM-200225762 03 2/28/03 (Eastern) Cafeteria/Kitchen storeroom: Furnish and install two (2) lense in cafeteria storerooms reported by the health inspector for violation. (Re-inspection coming up soon) | February 13, 2003 | February 28, 2003 | 15 days |
| Plummer Elementary School | FM-200218226 02 2/28/03 Plummer Main office Install female plug for newly installed cann. copier. | September 24, 2002 | February 28, 2003 | 157 days |