Closed Repair Requests in July 2005

Closed Repairs Summary

  • Urgent Requests
    82
  • Routine Requests
    357
  • Total Requests
    439

Detailed Reports

Urgent Repair Requests Closed in July 2005 (82)
School Description Open Date Close Date Time Elapsed
Shaw JHS FM-200507426 05 7/5/05 Shaw Boiler Room Repair or replace enterior door lock to boiler room. Door will not operate, entering or exit. Latch will not slide in or out. Urgent !!!! July 5, 2005 July 5, 2005 0 days
Dunbar High School FM-200507413 05 7/5/05 Dunbar Business Suite Repair or replace lock on classroom vault. Lock inoperation and vault has Education materials ard in vault. Summer school suite. Urgent !!!! July 5, 2005 July 5, 2005 0 days
Reed LC FM-200506896 05 7/6/05 (REED) Ground Floor - Pool-Male Locker Room 1) Repair or Replace the lock on the door. Note: Due to the safety of the public and students (This door will not lock) June 17, 2005 July 6, 2005 19 days
Randle-Highlands ES FM-200507218 05 7/7/05 !!!!!VERY URGENT!!!!! Ground Floor - Custodian Closet in the Gym Repair or Replace lock on the door, the lock was tamperd with over the weekend June 27, 2005 July 7, 2005 10 days
Barnard Elementary School FM-200507425 05 7/7/05 !!!!URGENT!!!! First Floor Main Office "Welcoming Center" The rear exit door located in the main office is not locking properly. The lock is sticking or not properly alligned this is a security issue. July 5, 2005 July 7, 2005 2 days
Moten Elementary School FM-200506949 05 7/7/05 Moten URGENT!!!! Ground, First, Second, Third, and Fourth Floors 1) Water fountains are in need of repairs. June 20, 2005 July 7, 2005 17 days
Woodson High School FM-200507307 05 7/8/05 URGENT!!!! Rm 312 Repair Door Lock June 30, 2005 July 8, 2005 8 days
Burrville Elementary School FM-200505378 05 7/8/05 (BURRVILLE) URGENT!!! Second Floor - Multi-Purpose Room 1) Replace bulbs because ceilings are too high May 11, 2005 July 8, 2005 58 days
Shaw JHS FM-200452414 04 7/11/05 Shaw Fire Code Violation Stairwell 6 Deffective hardware exit door. Asbestos Code A - Clear for repairs on 08/17/04. DCPS Safety - Leroy Minton Jr. (RG 08/18/04) August 12, 2004 July 11, 2005 333 days
Shaw JHS FM-200452413 04 7/11/05 Shaw Fire Code Violation Gym lobby Door not closing properly. Asbestos Code A - Clear for repairs on 08/17/04. DCPS Safety - Leroy Minton Jr. (RG 08/18/04) August 12, 2004 July 11, 2005 333 days
Shaw JHS FM-200452405 04 7/11/05 Shaw Fire Code Violation Second floor 9th grade teachers lounge door closer missing. Asbestos Code A - Clear for repairs on 08/17/04. DCPS Safety - Leroy Minton Jr. (RG 08/18/04) August 12, 2004 July 11, 2005 333 days
Marshall Educational Center FM-200455121 04 7/11/05 Marshall, Thurgood Fire Code Violation First floor Stage # 1 boys bathroom missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) September 20, 2004 July 11, 2005 294 days
Payne Elementary School FM-200507449 05 7/12/05 Second floor, New Wing/Teachers' restroom. Replace flush valve on commode it constantly runs. Note: The custodian on site attempted to replace flush valve but he was unsuccessful. Asbestos Code A - Clear for repairs on 07/06/05. DCPS Safety - Richard Gibson (RG) July 5, 2005 July 12, 2005 7 days
Gibbs Elementary School FM-200453256 04 7/13/05 Gibbs First floor cafeteria Ceiling tile is wet from roof leak, need to be replaced or repair.Front door needs repairing. Asbestos Code A - Clear for repairs on 08/26/04. DCPS Safety - Richard Gibson (RG 08/27/04) August 24, 2004 July 13, 2005 323 days
Hardy Middle School FM-200507207 05 7/15/05 "Urgent" First and Second floor. Unstop (4) slop sinks on both floors also unstop (3) urinals on second floor in boys' restroom. June 27, 2005 July 15, 2005 18 days
Payne Elementary School FM-200508079 05 7/19/05 (Payne) "Urgent" Old Building, Third floor/Custodian closet. Unclog slop sink. Note: Custodian foreman was unable to unclog sink he requested for the plumbers to bring a K-50. July 19, 2005 July 19, 2005 0 days
Cardozo High School FM-200102379 /01 7/22/05 (CARDOZO) BOYS BATHROOM GYM: MAKE REPAIRS TO VANDALIZED BATHROOM. REPLACE URINALS AND FACE BOWLS. Asbsetos Code A - Clear for repairs 02/25/02 DCPS Safety - Ronald Edwards (RE January 29, 2001 July 22, 2005 1,635 days
Eliot Junior High School FM-200102386 01 7/22/05 (ELIOT) BASEMENT LEVEL/STORAGE ROOM: 1) ASBESTOS ASSESSMENT REQUIRED. 2) REMOVE ALL MATERIAL FROM FLAMABLE STORAGE AREA, OUTSIDE INCINERATOR ROOM. REQUEST SAFETY INSPECTION OF MATERIAL. REQUEST SENT TO SAFETY. Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Philp Connolly (RG 03/11/03) January 29, 2001 July 22, 2005 1,635 days
Eastern High School FM-200100625 01 7/22/05 EASTERN BOILER ROOM SURVEY & REPLACE METAL LOUVERS IN BACK OF BOILER ROOM WITH METAL OR WOODEN LOUVERS THAT WILL BE ABLE TO CLOSE. BY THE LOUVERS NOT BEING ABLE TO CLOSE, PIPES MAY BUSTED DURING FREEZING WEATHER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/16/01. LEROY MINTON - SAFETY (202)576-6691 (RG) January 9, 2001 July 22, 2005 1,655 days
Wilson J. O. ES FM-200107943 01 7/22/05 WILSON, J.O. SECOND (2ND) AND THIRD (3RD) FLOOR 1) ASBESTOS ASSESSMENT REQUIRED. 2) REMOVE AND CAP OFF FLOOR MOUNTED ELECTRICAL OUTLETS TO THE FOLLOWING CLASSROOMS: #217, 203, 204, 205, 206, 207, 209, 317, 316, 315, 304, 305, 306, 308 AND 310. NOTE: OUTLETS ARE TRIPPING HAZARDS. Asbestos Code A - Abated and cleared for repairs on 02-26-03 by Leroy Minton Jr (LN/03-30-04) Safety Office. 202-576-6691. April 9, 2001 July 22, 2005 1,565 days
Thomas Elementary School FM-200104496 01 7/22/05 N. THOMAS 2ND FLOOR ROOM 211 ASBESTOS ASSESSMENT REPLACE FLOOR TILE. TILE IS 9 x 9, AND IT IS BEING BROKEN BY STUDENTS DAILY. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02-25-03 BY LEROY MINTON JR. (LM/02-25-03) SAFETY OFFICE. 202-576-8962. NOTE: THIS WORK IS COMPLETE WITH NEW FLOOR TILE / ACKNOWLEDGED BY LEROY MINTON JR. 02-24-03. February 28, 2001 July 22, 2005 1,605 days
Eastern High School FM-200100530 01 7/22/05 EASTERN SCHOOL PARKING LOT GATE - 17TH STREET ENTRANCE INSTALL NEW GATE TO PARKING LOT ENTRANCE ON 17TH STREET SIDE FOR SECURITY REASON TO PREVENT CAR THEFT. TWO CARS WERE STOLEN AND ONE CAR WAS VANDALIZED. PROPERTY DAMAGE ADN THEFT. URGENT. January 9, 2001 July 22, 2005 1,655 days
Stevens Elementary School FM-200104771 /01 7/22/05 STEVENS WINDOW REPLACEMENT NEED COMPLETE. REPLACE MGJO OF ALL WINDOWS SECURITY & SAFETY. MOST ARE ORIGINAL WINDOWA WITH ROTTEN FRAMES. March 2, 2001 July 22, 2005 1,603 days
Macfarland Middle School FM-200101965 1/23/01 7/22/05 MACFARLAND FIRST (1ST) AND SECOND (2ND) FLOOR - ROOF ROOF IS LEAKING WATER IS RUNNING INSIDE THE BUILDING SOME CHILD OR CHILDREN CAN SLIP. THIS A SAFETY CONCERN. January 23, 2001 July 22, 2005 1,641 days
Macfarland Middle School FM-200102125 1/25/01 7/22/05 (MACFARLAND) TUNNEL AND CRAWL SPACE: INSTALL SAFETY LIGHT COVERS TO LIGHTS IN THE TUNNELL AND CRAWL SPACE. MT-20001435 January 25, 2001 July 22, 2005 1,639 days
Deal Junior High School FM-200101183 01 7/22/05 DEAL NEW WING GYMNASIUM - SECOND (2ND) FLOOR BOYS AND GIRLS REPLACE CEILING TILES. TILES ARE OLD AND FALLING. (GLUED TO CONCRETE). SAFETY HAZARD. ASBESTOS ASSESSMENT REQUIRED January 12, 2001 July 22, 2005 1,652 days
Deal Junior High School FM-200101176 01 7/22/05 DEAL GYMNASIUM - SECOND (2ND) FLOOR REPAIR OR REPLACE LIGHT FIXTURES IN BOTH GYMNASIUM, BOYS AND GIRLS. THE LIGHTING IS VERY DARK. GYMNASIUMS FOR BOYS AND GIRLS LIGHTING IS A SAFETY HAZARD. ASBESTOS ASSESSMENT REQUIRED. January 9, 2001 July 22, 2005 1,655 days
Davis Elementary School FM-200101416 01 7/22/05 DAVIS FIRST (1ST) AND SECOND (2ND) FLOOR OLD WING BOYS RESTROOM BESIDE - 102 ROOM - 100, TEACHERS LOUNGE BESIDE ASST. PRINCIPAL OFFICE, BOTTOM STAIRWAY BY ROOM - 104 AND GIRLS RESTROOM ACROSS - 204. SAFETY TEST FOR OLD PEELING PAINT. ASBESTOS ASSESSMENT REQUIRED. MT-2001036 Hc-20000343 tracking # 109 January 16, 2001 July 22, 2005 1,648 days
Sousa Middle School FM-200104658 01 7/22/05 SOUSA SECOND (2ND) FLOOR - ROOM 220/CLOSET 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR OF REPLACE CLOSET HAS LARGE BREACH IN CEILING. SAFETY HAZARD. Asbestos Code A - Clear for Repair March 1, 2001 July 22, 2005 1,604 days
Park View ES FM-200108091 01 7/22/05 PARKVIEW 1) TSI REMOVAL TUNNEL AREAS. # IT CORP. Code A - There was some materials removed during summer of 2002. This work order does not identify any specifics in any of the tunnels, so this work order will be cleared for confussion sake. (LM/01-13-04) Leroy Minton Jr, Safety Office. 202-576-8962. Note; Please ! Approasch any new work with extreme caution, notify Safety Office if there are any suspect materials observed. April 11, 2001 July 22, 2005 1,563 days
Cardozo High School FM-200104225 01 7/22/05 CARDOZO NORTH & NORTHWEST ASBESTOS ASSESSMENT ASSESS PIPE WRAP MATERIAL FOR REMOVAL FOR PIPE STEAM LEAK REPAIR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/27/02. DCPS- SAFETY RONALD EDWARDS (202)576-6693 (RG 03/0102) February 23, 2001 July 22, 2005 1,610 days
Shaed Elementary School FM-200103681 01 7/22/05 SHAED ROOM - 1F 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR OR REPLACE CEILING PIPE, STEAM IS SEEKING THROUGH THE CEILING. 3) RE-INSULATE PIPE IN ROOM 121 AND CEILING OF CAFETERIA. 4) REPAIR PLASTER CEILING IN CAFETERIA. EMERGENCY HEALTH AND SAFETY HAZ Asbestos Code A - Clear for Repair February 14, 2001 July 22, 2005 1,619 days
Randle-Highlands ES FM-200508158 05 7/25/05 (Randle-Highlands) "Urgent" Ground floor, Principal office. Replace lock on principal's office door. Note: This lock change is for security reasons. July 20, 2005 July 25, 2005 5 days
Backus Middle School FM-200108471 01 7/25/05 BACKUS FIRST (1ST) AND SECOND (2ND) FLOOR CLASSROOMS FURNISH AND INSTALL SIXTY-FOUR (64) ELECTROIC INSTANT START 120 VOLTS 60 HZ BALLAST IN THE FOLLOWING LOCATION CLASSROOM. 102 - 2 202 - 12 208 - 4 105 - 4 204 - 10 210 - 8 106 - 12 206 - 8 212 - 4 SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/02/01. April 16, 2001 July 25, 2005 1,561 days
Garrison ES FM-200213904 02 7/25/05 Garrison 1. Asbestos Assessment Reqd. 1st-Floor Main Office/West Wing 2. Install a high-power electrical outlet. Asbestos Code A - Clear for repairs on 08/19/02. DCPS Safety - Leroy Minton Jr (RG 08/20/02) August 8, 2002 July 25, 2005 1,082 days
Ronald H. Brown MS FM-200109879 01 7/25/05 BROWN, RON EXTERIOR - PARKING LOT REPLACE LIGHTS ON REAR PARKING LOT. CARS HAVE BEEN BROKEN INTO, STOLEN AND AREA IS TOO DARK. EMERGENCY! SAFETY AND SECURITY HAZARD. May 9, 2001 July 25, 2005 1,538 days
Backus Middle School FM-200108277 01 7/25/05 BACKUS SECOND (2ND) FLOOR CLASSROOM 212 AND ASST. PRINCIPAL OFFICE 1) A/C UNIT IS TRIPPING THE BRAKER SYSTEM THIRD (3RD) FLOOR CLASSROOM 307 - SPOT COOLER AND CLASSROOM 316 - WINDOW A/C UNIT 1) ASBESTOS ASSESSMENT REQUIRED 2) REPLACE PLUGS, NEEDS MORE UPGRADE ELECTRICAL OUTLETS. URGENT! ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/23/01. April 12, 2001 July 25, 2005 1,565 days
Langdon Elementary School FM-200102685 01 7/25/05 LANGDON BOILER ROOM WATER METER AREA SURVEY AND MAKE REPAIRS TO PREVENT WATER FROM FILLING UP IN AREA. WATER IS IN AREA ABOUT 6" OR MORE AND WHEN IT PASSES THE THRESHOLD, WATER RUNS ON BOILER ROOM FLOOR CAUSING SERIOUS SAFETY HAZARD IN AREA. February 1, 2001 July 25, 2005 1,635 days
Malcolm X ES FM-200109766 01 7/25/05 MALCOLM X SECOND (2ND) FLOOR 1. BALLASTS IN CUSTODIAN CLOSET IS OUT. 2. BALLASTS OUT ON BACK STEP AREA. SAFETY HAZARD. May 8, 2001 July 25, 2005 1,539 days
Whittier Elementary School FM-200103613 3/01 7/25/05 WHITTIER OUTSIDE SECURITY LIGHTS AROUND ENTIRE BUILDING (BACK & FRONT) ARE OUT. NEED REPAIRING OR REPLACING. SECURITY HAZARD, COMPLETE PARKING IN ALL AREAS OF EXITS. SAFETY HAZARD NOT SAFE FOR CHILDREN & PARENTS. February 13, 2001 July 25, 2005 1,623 days
Bruce-Monroe Elementary School FM-200110707 01 7/25/05 BRUCE-MONROE 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR WALL IN PARENT CENTER WALL IS A POTENTIAL SAFETY HAZARD COULD FALL ON SOMEONE ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/21/01. (THE CEILING TILE HAS ASBESTOS IN IT, SO NO WORK CAN BE DONE ABOVE THE CEILING WITH OUT AN ABATEMENT DONE FIRST) May 21, 2001 July 25, 2005 1,526 days
Whittier Elementary School FM-200109546 01 7/25/05 (WHITTIER) 1. ASBESTOS ASSESSMENT REQUIRED. SEVERE LEAKING COMING FROM THROUGH HOLE IN WALL. FALLING PAINT AND PLASTER PRESENT. EXISTING CONDITION WARRANT HEALTH AND SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 6/11/01 May 3, 2001 July 25, 2005 1,544 days
Bunker Hill Elementary School FM-200108875 01 7/25/05 BUNKER HILL RM. 111, 115 AND 216 INSTALL AIR CONDITIONING UNITS 23,000 BUTS (OUTLETS ALREADY INSTALLED)IN THE AREAS INDICATED. Requester Phone: 576-6095 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/02/01. MR. CHARLES BUCHANAN - SAFETY (202)439-7840 April 6, 2001 July 25, 2005 1,571 days
Young Elementary School FM-200103274 01 7/25/05 YOUNG KINDERGARTEN 1ST FLOOR INSPECT BRICK WORK (POSSIBLE FUNGUS). BLACK SPOTS ARE PROTRUDING THROUGHOUT THE WALL. Code A - NO ACM IMPACT PER LEROY MINTON OF DCPS SAFETY 04-05-01 (DCPS SAFETY SHEILA R. HOWARD 11-29-01) February 8, 2001 July 25, 2005 1,628 days
Garrison ES FM-200217462 02 7/25/05 Garrison Asbestos Assessment Reqd. West Wing Rooms. 106, 107 & 108; Library/East Wing & 2nd Floor Install 220v circuits to support air conditioners in the above areas. A/C units are on site. Asbestos Code A - Cleared for repairs 09-17-02 by Leroy Minton Jr. (LM / 09-19-02) Safety Office 202-576-8962. September 13, 2002 July 25, 2005 1,046 days
Garrison ES FM-200110485 01 7/25/05 GARRISON FIRST FLOOR - BACK HALLWAY 1) REPLACE EXIT DOORS ,EAST WING UNDER STAIRCASE,VERMONT AVE BACK PLAYGROUND SIDE. DOOR IS DETERORATED. (METAL DOORS). Asbestos Code A - Clear for repairs on 04/30/02. DCPS Safety - Leroy Minton Jr. (RG 04/30/02) May 17, 2001 July 25, 2005 1,530 days
Garrison ES FM-200218111 02 7/25/05 Garrison Asbestos Assessment Reqd. 1st Floor East Wing Teachers' Lounge Repair/replace burned out electrical outlet. Asbestos Code A - Cleared for repairs on 10-17-02 (LM / 10-18-02) Leroy Minton Jr. Safety Office 202-576-8962. September 23, 2002 July 25, 2005 1,036 days
Garrison ES FM-200214256 02 7/25/05 Garrison 1. Asbestos Assessment Reqd. 1st Floor Main Office 2. Install an electrical outlets for new copiers (1) 220 or 240v and one 250v. Asbestos Code A - Clear for repairs on 08/19/02. DCPS Safety - Leroy Minton Jr (RG 08/19/02) August 13, 2002 July 25, 2005 1,077 days
Nalle Elementary School FM-200108265 01 7/25/05 NALLE THIRD (3RD) FLOOR - TEACHER BATHROOM NEED TO HAVE TRAP DOOR SECURED AS SOON AS POSSIBLE. OPEN AREA IS EXPOSED TO THE PUBLIC. SAFETY HAZARD. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-16-01 HORNE ENGINEER: SHERYLL JAMES April 12, 2001 July 25, 2005 1,565 days
Garrison ES FM-200217293 02 7/25/05 (Garrison) "URGENT" Teachers Parking Lot: Repair broken light in parking lot; light hanging by wire. September 11, 2002 July 25, 2005 1,048 days
West Elementary School FM-200504485 05 7/25/05 ( WEST ) First Floor - Boys Bathroom on Left Side of the Learning Center 1) Repair urinal, it's leaking from the wall onto the floor. Asbestos Code A - Clear for repairs on 05/25/05. DCPS Safety - Leroy Minton Jr. (RG 05/25/05) April 21, 2005 July 25, 2005 95 days
Duke Ellington School FM-200102723 01 7/25/05 ELLINGTON SUB-BASEMENT - DANCE STUDIO REPAIR OR REPLACE METAL BARS PULLING FROM THE WALLS. SAFETY HAZARD. Asbestos Code A - Clear for Repair ON 03/13/01. Horne Engineering - Dan Will February 1, 2001 July 25, 2005 1,635 days
Nalle Elementary School FM-200110101 01 7/25/05 NALLE FIRST (1ST) FLOOR - NEW WING 1) ASBESTOS ASSESSMENT REQUIRED 2) PIECES OF THE CEILING ARE FALLING IN THE BOYS BATHROOM ON THE FIRST FLOOR. A WATER PIPE HAD BURST IN THE BOYS BATHROOM ON SECOND FLOOR OF THE NEW WING CAUSING WATER TO LEAK THROUGH THE FLOOR TO THE CEILING. THIS SITUATION IS A HEALTH HAZARD AND A DAMAGE PROPERTY. ALSO DANGER TO THE CHILDREN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/14/01. May 11, 2001 July 25, 2005 1,536 days
Hyde Elementary School FM-200109622 01 7/25/05 HYDE CLASSROOM - 103 1) ASBESTOS ASSESSMENT REQUIRED. 2) AIR CONDITIONER IS BROKEN. REPLACE A NEW ONE. AIR CONDITIONER IS ON SITE (NEW ONE). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/05/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) May 7, 2001 July 25, 2005 1,540 days
Eastern High School FM-200456633 04 7/25/05 Eastern URGENT Sub-basement armory Repair hole in ceiling cause by roof leak- ceiling need to be repaired and painted. Asbestos Code A - Clear for repairs on 10/12/04. DCPS Safety -Leroy Minton Jr.(RG 10/12/04) October 8, 2004 July 25, 2005 290 days
Eastern High School FM-200456632 04 7/25/05 Eastern URGENT B-77 Furnish and install electrical receptables in science labs-outlets and install missing covers over receptables. Power cut off to tables. Asbestos Code A - Clear for repairs on 10/12/04. DCPS Safety -Leroy Minton Jr.(RG 10/12/04) October 8, 2004 July 25, 2005 290 days
Peabody Elementary School FM-200105908 01 7/26/05 PEABODY BASEMENT - CAFETERIA NEED TO UP-GRADE ELECTRICAL CIRCUIT BOX. REFRIGERATOR CONTINUES TO TRIP OUT. FOOD SPOILED TWO WEEK-ENDS STRAIGHT. NEED PROBLEM RESOLVED IMMEDIATELY. Asbestos Code A - Cleared for repairs on 03-18-03 by Leroy Minton Jr. (LM/03-18-03) Safety Office 202-576-8962. March 15, 2001 July 26, 2005 1,594 days
Cardozo High School FM-200453776 04 7/26/05 Cardozo Ground floor kitchen Replace broken floor tiles. 32 avanti 7x7". Assbestos Code A - Clear for refpairs on 01/18/05. DCPS Safety - Leroy Minton JR (RG 01/31/05) September 1, 2004 July 26, 2005 328 days
Macfarland Middle School FM-200453744 04 7/26/05 MacFarland Second floor room 213 Replace closet door in room 213. Asbestos Code A - Clear for repairs on 01/18/05. DCPS Safety - Leroy Minton (RG 01/31/05) September 1, 2004 July 26, 2005 328 days
Coolidge High School FM-200105885 01 7/26/05 COOLIDGE 5TH ST. TUNNEL REPLACE TWO EXPANSION JOINTS LOCATED IN TUNNEL ON 5TH STREET SIDE OF BLDG. BOTH ARE LEAKING AND HAVE PACKING BOLTS THAT ARE FIXED TO HOUSING. 4 BOLT FLANGED. Asbestos Code A - Cleared for repairs on 03-18-03 by Leroy Minton Jr. (LM/03-18-03) Safety Office 202-576-8962. March 15, 2001 July 26, 2005 1,594 days
Merritt Middle School FM-200501093 05 7/26/05 Merritt Throughout building Replace ceiling tile (2x4). Asbestos Code A - Clear for repairs on 02/01/05. DCPS Safety - Richard Gibson (RG 02/01/05) February 1, 2005 July 26, 2005 175 days
Eastern High School FM-200106483 01 7/26/05 EASTERN BASEMENT - #96 FURNISH AND INSTALL A/C UNIT - 23,000 BTU IN B-96 OFFICE; NEEDS TO KEEP COMPUTER FROM OVER HEATING. SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/28/01. March 22, 2001 July 26, 2005 1,587 days
Nalle Elementary School FM-200107483 01 7/27/05 NALLE ASBESTOS ASSESSMENT REQUIRED REPAIR OR REPLACE 1) AUDITORIUM - FIRST FLOOR IF YOU CLOSE THE DOOR , YOU CANT OPEN IT WITH OUT A CLOTHES HANGER. ONCE YOU GET IN YOU CANT GET OUT. 2) BASEMENT LEVEL-OLD WING,LEADS OUT ONTO C. STREET WHEN THE CHILDREN GO OUT THE DOOR IT STAYS AJAR. IT IS HARD TO CLOSE AND WONT OPEN WHEN YOU HIT THE PANIC BAR. 2) NEW WING - FIRST FLOOR: LEADS TO 50TH STREET. WHEN THE CHILDREN GO OUT THE DOOR IT STAYS AJAR. IT IS HARD TO CLOSE AND WONT OPEN WHEN YOU HIT THE PANIC BAR. Asbestos Code A - Cleared for repairs on 05-13-03 by Leroy Minton Jr. (LM/05-08-03) Safety Office 202-576-8962. April 5, 2001 July 27, 2005 1,574 days
Ballou Senior High School FM-200107175 01 7/27/05 BALLOU FIRST (1ST) FLOOR - CLASSROOMS 1) ASBESTOS ASSESSMENT REQUIRED 2) REPLACE LIGHT BALLASTS THROUGH OUT BUILDING. SAFETY HAZARD. ASBESTOS COBE A - CLEAR REPAIRS April 2, 2001 July 27, 2005 1,577 days
Ballou Senior High School FM-200107176 01 7/27/05 BALLOU FIRST (1ST) FLOOR - HALLWAY 1) ASBESTOS ASSESSMENT REQUIRED 2) REPLACE ERISTINS ELECTRICAL PANEL. BREAKER AND BUS WITH NEW. 1 - 277/480V PANEL 1 - 120/208V PANEL SAFETY HAZARD. Asbestos Code A - Clear for Repair April 2, 2001 July 27, 2005 1,577 days
Thomas Elementary School FM-200107133 01 7/27/05 THOMAS ROOMS 101, 102, 100 MAIN & PRINCIPALS OFFICE REPLACE AND INSTALL CARPET IN THE ABOVE ROOMS. CARPET IN SOME OF THE ROOMS ARE A SAFETY HAZARD. Asbestos Code A - Cleared for repairs on 04-01-03 by Leroy Minton Jr. (LM/04-01-03) Safety Office 202-576-8962. Note: Please be advised that this work order was cleared for the purpose of moving the work along when becomes a reality. At time of assessment the inspector could not determine the condition of the flooring under the carpet nor the impact it would have once removal of the carpet began. As a pre-cautionary measure we request that no carpet is to be taken up without contacting the Safety Office (202-576-8962) Repeat! No carpet is to removed by anyone! without first contacting the Safety Office. April 2, 2001 July 27, 2005 1,577 days
Takoma Educational Center FM-200106957 01 7/27/05 TAKOMA SECOND (2ND) FLOOR - ROOM 166 - CLOSET 1) ASBESTOS ASSESSMENT REQUIRED 2) INSTALL OR REPAIR BILFOLD BRACKET HINGES ON DOORS. DOORS ARE OFF TRACK. 3) PROVIDE LOCKS ON DOORS SO STUDENTS CAN BE PREVENTED FROM TAMPERING WITH TELEPHONE LINE EQUIPMENT. SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/11/01. March 29, 2001 July 27, 2005 1,581 days
Browne Junior High School FM-200455699 04 7/27/05 Browne First floor old wing Back hall by room 112 door hinges need to be replaced. Asbestos Code A - Clear for repairs on 09/27/04. DCPS Safety Leroy Minton Jr. (RG 09/28/04) September 24, 2004 July 27, 2005 306 days
Browne Junior High School FM-200458803 /04 7/27/05 BROWNE First floor (old wing) Stairwell 5 exit door need to be fixed, need door hinges. Asbestos Code A - Clear for repairs on 12/02/04. DCPS Safety - Leroy Minton Jr. (RG 12/02/04) November 30, 2004 July 27, 2005 239 days
Shaw JHS FM-200107745 01 7/27/05 SHAW SITE LIBRARY UP DATE SITE LIGHTING IN AREAS LISTED. BELOW: 1. BASKETBALL AREA - POLE LIGHT 2. TENNIS COURT - POLE LIGHT 3. MULTI-PURPOSE - POLE LIGHT 4. FOOTBALL FIELD - POLE LIGHT (ELS) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/28/02. DCPS- SAFETY RONALD EDWARDS (202)576-6693 (RG 03/0102) April 7, 2001 July 27, 2005 1,572 days
Roosevelt High School FM-200454052 04 7/27/05 ROOSEVELT SHS Bilingual Dept Rooms 5 & 10 Do asbestos assessment on damaged and falling wall plaster in rooms # 10 (director's office) and room # 5 on the third floor. Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Ronald Edwards (RG 09/15/04) September 8, 2004 July 27, 2005 322 days
Park View ES FM-200106571 26/01 7/27/05 PARKVIEW TUNNEL AREA UNDER HALLWAY BY CAFETERIA 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE 16 FT. OF 3/4 RUPTURED STEAM LINE IN TUNNEL AREA UNDER HALLWAY BY CAFETERIA. TUNNEL IS RESTRICTED. Asbestos Code A - Cleared for repairs and abated on 11-03-02 by Leroy Minton Jr (LM/01-13-04) Safety Office 202-576-8962. March 26, 2001 July 27, 2005 1,584 days
Deal Junior High School FM-200106628 01 7/27/05 DEAL EAST TUNNEL 1) ASBESTOS ASSESSMENT REQUIRED 2) SURVEY LEAK IN TUNNEL. POSSIBLY CAUSING WATER SEEPAGE IN CAFETERIA STORAGE AREA. Asbestos Code A - Cleared for repairs on 03-18-03 by Leroy Minton Jr. (LM/03-18-03) Safety Office 202-576-8962. March 26, 2001 July 27, 2005 1,584 days
Reed LC FM-200106930 0 3/29/01 7/27/05 REED AUDITORIUM, GYM & STAIRWAY BASEMENT AN ELECTRICIAN IS NEEDED TO COME AND COMPLETE WORK ON LIGHTS. THIS WORK ORDER IS BEING RESUBMITTED. Asbestos Code A - Clear for repairs on 04/16/02. DCPS Safety - Richard Gibson March 29, 2001 July 27, 2005 1,581 days
Draper Elementary School FM-200107138 01 7/27/05 DRAPER ENCLOSER EXISTING ELECTRIC PANELS BOXES ON FIRST FLOOR (4), SECOND FLOOR (2) AND THIRD FLOOR (2) PRIORITY (1) - URGENT ELS - CONTRACTOR ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/30/01. April 2, 2001 July 27, 2005 1,577 days
Kimball Elementary School FM-200107163 /01 7/27/05 KIMBALL BASEMENT TUNNEL REPAIR OR REPLACE INLET AND OUTLET BY-PASS VALVE ON WATER METER. CITED BY WASA 3/29/01. ORIGINALLY CITED 9/12/00. URGENT CODE A - CLEAR FOR REPAIR AS OF 4/16/01. April 2, 2001 July 27, 2005 1,577 days
Browne Junior High School FM-200501769 05 7/28/05 Browne First floor 112 Door knobs need to be replace aon both wood doors and fix locks and door hinges. Asbestos Code A - Clear for repairs on 02/18/05. DCPS Safety - Richard Gibson (RG) February 18, 2005 July 28, 2005 160 days
Browne Junior High School FM-200453747 04 7/29/05 Browne Second floor room 204 Room door need door handle. Asbestos Code A - Clear for repairs on 09/01/04. DCPS Safety - Richard Gibson ( 09/01/04 ) September 1, 2004 July 29, 2005 331 days
Hendley Elementary School FM-200509071 05 7/29/05 Hendley Play Grounds Replace Safety Turf due to fire July 29, 2005 July 29, 2005 0 days
Hendley Elementary School FM-200508813 05 7/29/05 (HENDLEY) URGENT!!!! First Floor - Lobby Area. 1) Replace exterior doors panic bar it will not stay shut, hard to secure. Code A-clear for repair by DCPS Charles Buchanan on 6/23/05 July 27, 2005 July 29, 2005 2 days
Browne Junior High School FM-200455693 04 7/29/05 Browne First floor rooms 109, 112, 115, 123, 124 and 132 Door hinges need to be fixed or replaced on the above rooms listed. Asbestos Code A - Clear for repairs on 09/27/04. DCPS Safety - Ricardo Eley (RG 09/27/04) September 24, 2004 July 29, 2005 308 days
Browne Junior High School FM-200501697 05 7/29/05 Browne EMERGENCY Second floor 212 Need door handles. Asbestos Code A - Clear for repairs on 02/17/05. DCPS Safety - Leroy Minton Jr. (RG 02/18/05) February 16, 2005 July 29, 2005 163 days

Routine Repair Requests Closed in July 2005 (357)
School Description Open Date Close Date Time Elapsed
Birney Elementary School FM-200507348 05 7/1/05 First Floor - Restrooms (Boys restroom) pipe inside wall need to be repaired and sink needs to be installed (Girls restroom) old side, sink need to be installed on wall . (First floor mop closet) old side, drain need to be unclogged June 30, 2005 July 1, 2005 1 day
Aiton Elementary School FM-200507326 05 7/1/05 Fourth fl. Custodian closet Repair Stopped-up Sink June 30, 2005 July 1, 2005 1 day
Amidon Elementary School FM-200507362 05 7/1/05 (AMIDON) First Floor Near Main Office Water pressure is low in fountains. 1) Replace water cooler filter. 2) Replace defective water cooler in the Gym July 1, 2005 July 1, 2005 0 days
Reed LC FM-200223621 03 7/1/05 (Reed) Grounds/Exterior walls: Please remove graffito from walls of school. January 7, 2003 July 1, 2005 906 days
Birney Elementary School FM-200506773 05 7/1/05 (BIRNEY) Repair or Replace water coolers throughout (water cooler project summer school) June 14, 2005 July 1, 2005 17 days
Garnet-Patterson MS FM-200507309 05 7/2/05 Garent-Patterson Boiler Room Unstop drain in boiler room. Will cause boiler room to be flooded, if not unclog. June 30, 2005 July 2, 2005 2 days
Moten Elementary School FM-200505347 05 7/5/05 ( MOTEN ) EMERGENCY!!! First Floor - Kitchen 1) Flood in the kitchen. Floor drain stopped up. May 11, 2005 July 5, 2005 55 days
Wilkinson ES FM-200507410 05 7/5/05 Wilkinson Second Floor - Boys Bathroom 1) Repair leaking sink. July 5, 2005 July 5, 2005 0 days
Savoy Elementary School FM-200506244 05 7/5/05 ( SAVOY ) First Floor - Teachers Restroom 1) Needs new flush kit. (sloan royal flushometer) June 2, 2005 July 5, 2005 33 days
Harris, C.W. ES FM-200507243 05 7/5/05 "Break In" First floor, Asst. Principal's Office. Lock is damaged on door due to break in. Note: Door cannot be secure. June 28, 2005 July 5, 2005 7 days
Burrville Elementary School FM-200507235 05 7/5/05 Playground Area. Install locks and chains to prevent entry to playground. June 28, 2005 July 5, 2005 7 days
Merritt Middle School FM-200506959 05 7/5/05 Merritt Generator Room Repair or replace exterior door. Lock on emergency generator room. Can not unlock door to operate emergency generator. June 20, 2005 July 5, 2005 15 days
John Burroughs ES FM-200507116 05 7/6/05 First Floor - Mr. Taylor Room 7 Repair lock on the door it's broken. June 23, 2005 July 6, 2005 13 days
Macfarland Middle School FM-200507488 05 7/6/05 MacFarland Room #208 1. Install new 208/230 volt line for Custodian Office on 2nd floor room #208. July 6, 2005 July 6, 2005 0 days
Seaton Elementary School FM-200507105 05 7/6/05 Frist Second and Third floors/Rms. 101- 111- 103- 209-210-305-304 Repair or Replace Door Locks June 22, 2005 July 6, 2005 14 days
Moten Elementary School FM-200505321 05 7/7/05 ( MOTEN ) EMERGENCY!!! First Floor - Kitchen 1) Flood in the kitchen, (Plumbers came out to fix the grease trap on 5/9/05) May 10, 2005 July 7, 2005 58 days
Whittier Elementary School FM-200339114 /03 7/7/05 Whittier Lower level back of bldg. Unstop clogged drain outside the boiler room (back). Water goes to the boiler room everytime it rains. October 17, 2003 July 7, 2005 629 days
Shepherd ES FM-200500158 05 7/7/05 Shepherd Library Remove sink cabinet, but keep small sink. January 5, 2005 July 7, 2005 183 days
Green Elementary School FM-200507370 05 7/7/05 Rm 134 Repair door lock July 1, 2005 July 7, 2005 6 days
Sousa Middle School FM-200507534 05 7/7/05 (Summer School Project) Repair or Replace all water coolers, and check all bathrooms in the building. July 7, 2005 July 7, 2005 0 days
Whittier Elementary School FM-200341086 03 7/7/05 (Whittier) 1st Hallway/New Wing Repair or replace water fountain; the supply line is broken. December 4, 2003 July 7, 2005 581 days
Randle-Highlands ES FM-200507409 05 7/7/05 Randle-Highland Fan Room Check and make repairs to air handler unit for gym. July 5, 2005 July 7, 2005 2 days
Stanton Elementary School FM-200507521 05 7/7/05 Annex Classrooms Restore Electrical Service to (2) A/C Units July 7, 2005 July 7, 2005 0 days
Moten Elementary School FM-200506953 05 7/7/05 Moten Second Floor - Custodian Closet 1) A 8" wall mount slop sink faucet need to be replaced June 20, 2005 July 7, 2005 17 days
Harris, C.W. ES FM-200507338 05 7/7/05 First Floor - Room 146 Second Floor - Room 243 Classrooms door lock damaged. Repair or Replace the locks. June 30, 2005 July 7, 2005 7 days
Houston Elementary School FM-200505706 05 7/8/05 Huston Auditoruim Relamp Entire Area May 19, 2005 July 8, 2005 50 days
Tubman Elementary School FM-200506906 05 7/8/05 Tubman Boiler Room Repair or replace air compressor in boiler room. June 17, 2005 July 8, 2005 21 days
Webb Elementary School FM-200505790 05 7/8/05 ( WEBB ) Unstop outside drain near Dom. May 20, 2005 July 8, 2005 49 days
Spingarn High School FM-200505807 05 7/8/05 ( SPINGARN ) EMERGENCY!!! Basement 1) Unstop outside drain. water is flooding into the basement May 20, 2005 July 8, 2005 49 days
Macfarland Middle School FM-200507557 05 7/8/05 By The Guidance Office Cap off line. July 7, 2005 July 8, 2005 1 day
Randle-Highlands ES FM-200507407 05 7/8/05 Randle-Highland Room #2201 Check and make repairs to air handler unit for classroom #2201. July 5, 2005 July 8, 2005 3 days
King M L ES FM-200507419 05 7/8/05 First Floor - Main Office Repair or Replace the loose lock on Main Office door. Code A-clear for repair by DCPS charles Buchanan on 7/05/05 July 5, 2005 July 8, 2005 3 days
Webb Elementary School FM-200507551 05 7/8/05 Second fl. Custodian Closet Unstop the Sink July 7, 2005 July 8, 2005 1 day
Savoy Elementary School FM-200506248 05 7/10/05 ( SAVOY ) Second Floor - Teachers Restroom (North End) 1) Needs new flush kit. June 2, 2005 July 10, 2005 38 days
Ballou Senior High School FM-200455958 04 7/11/05 (Ballou) FIRE CODE VIOLATION: 1st Floor/Through-Out Hallways: Ceiling tile missing. HA 032 Ceiling Tile 1' X 1' with gouge and Pinholes NAD Code A-clear for repair by DCPS Charles Buchanan on 10/14/04 September 28, 2004 July 11, 2005 286 days
Sousa Middle School FM-200454713 04 7/11/05 Sousa FIRE CODE VIOLATION Third floor Broken door closer on door, room 301. Code A-clear for repair by DCPS Charles Buchanan on 9/15/04 September 14, 2004 July 11, 2005 300 days
Sousa Middle School FM-200454699 04 7/11/05 Sousa FIRE CODE VIOLATION Third floor Threshold plate missing at bottom of fire door 316. Code A-clear for repair by DCPS Charles Buchanan on 9/15/04 September 14, 2004 July 11, 2005 300 days
School WW High School FM-200507637 05 7/11/05 (School Without Walls) EMERGENCY!!! Main entrance door can't be secured, center pice on panic bar is broken and need to be repaired. July 11, 2005 July 11, 2005 0 days
River Terrace ES FM-200454583 04 7/11/05 River Terrace FIRE CODE VIOLATION: First floor Exit door will not close properly (by stage in multi purpose room). Code A-clear for repair by DCPS Charles Buchanan on 9/16/04 September 14, 2004 July 11, 2005 300 days
Sousa Middle School FM-200454698 04 7/11/05 Sousa FIRE CODE VIOLATION Third floor Damaged fire door at stairwell 316. Code A-clear for repair by DCPS Charles Buchanan on 9/15/04 September 14, 2004 July 11, 2005 300 days
Kimball Elementary School FM-200500446 05 7/11/05 Kimball Boiler Room Repair or replace automatic water feeder to boiler #4. Not getting proper amount of water back into boiler. January 14, 2005 July 11, 2005 178 days
Deal Junior High School FM-200507451 05 7/12/05 First, Second, Third and Basement floors. Repair following restrooms, Boys' 1st fl., (1) commode (by 108) Girls' 1st fl., (3) flush valve assembly, bradley basin (repaired) (new wing) Boys' 2nd fl. (2) vacuum breakers, (1) flush valve assembly (new wing) Boys' 2nd fl. (1) flush valve kit (water closet), (1) spud washer (by 205) Girls' 2nd fl. (1) spud washer, (2) flush valve kits (water closet) (by 208) July 5, 2005 July 12, 2005 7 days
Cardozo High School FM-200505383 05 7/12/05 (Cardozo) First, Second and Third floor. Repair or Replace Portable A/C units in the following areas: Rooms- 113, 117, 119, 121, 123, 125. Rooms- 201, 203, 205. Rooms- 306, 310, 312, 315. May 11, 2005 July 12, 2005 62 days
Cardozo High School FM-200505384 05 7/12/05 (Cardozo) First, Second and Third floor. Replace Portable A/C units in the following areas: Rooms- 109, 113. Rooms- 206, 208, 210, 212, 222, 224, 220. Rooms- 318, 320, 316, 314. Note: Total 13 new units. May 11, 2005 July 12, 2005 62 days
Cardozo High School FM-200506279 05 7/12/05 (CARGOZO) First Floor-Room 120(Biology lab) 1) Survey and install new electrical service for new air conditioner. 2) Install new air conditioner,classroom lab is connected to green house, temperatures of green house and classroom amke it very hard to efficiently maintain proper cooling of classroom. May 26, 2005 July 12, 2005 47 days
Payne Elementary School FM-200455640 04 7/12/05 Payne Second floor old and new building Repair or replace urinal. (boys) flush valves. Attempt to unstop did not work. September 24, 2004 July 12, 2005 291 days
Reed LC FM-200507591 05 7/12/05 First Floor - Exterior Front Entrance Door The cylinder is loose and it makes the door hard to open July 8, 2005 July 12, 2005 4 days
Deal Junior High School FM-200507467 05 7/12/05 Second, Third and Basement floors. Girls' restroom 2nd floor (1) flush valve kit (water closet) (by 111) Girls' restroom 3rd floor (1) vacuum breaker, (1) spud washer (new wing) Bradley Basin Repair. Girls' restroom 3rd floor (1) flush valve kit (water closet), (1) spud washer (by 306) Boys' restroom 3rd floor (4) flush valve assembly (w/c) (BY 305) Basement Boys restroom (1) commode. July 6, 2005 July 12, 2005 6 days
Ballou Senior High School FM-200501336 05 7/12/05 (Ballou) please sandblast/power-wash writing on north-west wall of small lot-see Atkinson. February 7, 2005 July 12, 2005 155 days
Ballou Senior High School FM-200505020 05 7/13/05 (Ballou) locksmith nd.for restroom 2nd floor of a-wing students denied access. May 2, 2005 July 13, 2005 72 days
Browne Junior High School FM-200507749 05 7/13/05 Brown Entrance Door to the Third fl. Repair Hinges and closers July 13, 2005 July 13, 2005 0 days
Hendley Elementary School FM-200507412 05 7/13/05 Exterior Grounds Vandalism !!! 1) Remove playground equipment that was burnt up over the week end. July 5, 2005 July 13, 2005 8 days
Hendley Elementary School FM-200507174 05 7/13/05 "Emergency" Outside Wash Room/Rear of building. Repair leaking faucet pipe, water is spraying everywhere. June 24, 2005 July 13, 2005 19 days
Payne Elementary School FM-200455637 04 7/13/05 Payne First floor new wing boys restroom Commode need repairing or replacing. Attempt to unstop did not work. September 24, 2004 July 13, 2005 292 days
Payne Elementary School FM-200455639 04 7/13/05 Payne New wing St. John Repair or replace flush valves and commode dose not want .Attempt to unstop. September 24, 2004 July 13, 2005 292 days
Cardozo High School FM-200507558 05 7/13/05 Fan Rm Repair or Unstop Drain Line July 7, 2005 July 13, 2005 6 days
Ronald H. Brown MS FM-200504830 05 7/14/05 Brown, Ron Cafeteria Rear Door Replace Door and install new Lock Code A-clear for repair by DSCPS Charles Buchanan on 5/10/05 April 27, 2005 July 14, 2005 78 days
Green Elementary School FM-200507477 05 7/14/05 Third fl. Teachers Restroom Repair Spud and Stop Valve on the Commode July 6, 2005 July 14, 2005 8 days
Garnet-Patterson MS FM-200505034 05 7/14/05 ( GARNET-PATTERSON ) Second Floor - Landing 1) Attach panic bar to door. May 2, 2005 July 14, 2005 73 days
Beers Elementary School FM-200340404 /03 7/14/05 (Beers) Building #2 and #3: Hallway in bldg. 2 light fixture is not working, also bldg. 3 back stairs is dark-lights are not working. Also light fixture outside of Auditorium in hallway . Code A-clear for repair by DCPS Charles Buchanan on 11-20-03 November 18, 2003 July 14, 2005 604 days
Cardozo High School FM-200506280 05 7/14/05 (CARDOZO) First Floor-Girls Gym 1) furnish and install new door lock. May 26, 2005 July 14, 2005 49 days
Deal Junior High School FM-200507826 05 7/15/05 Deal School Repair Fence July 13, 2005 July 15, 2005 2 days
Stanton Elementary School FM-200507825 05 7/15/05 Stanton School Repair Fence July 13, 2005 July 15, 2005 2 days
Beers Elementary School FM-200443163 04 7/15/05 Beers Second floor bldg. 3 Electrical backstairs are dark. Please install flourescent lights. I have parts in house. Asbestos Code A - Clear for repairs on 02/02/04. Horne Engineering - Troy Wilcome (RG 02/03/04) January 23, 2004 July 15, 2005 539 days
Shepherd ES FM-200507840 05 7/16/05 Shepherd School Repair Fence July 14, 2005 July 16, 2005 2 days
Deal Junior High School FM-200507839 05 7/16/05 Deal School Repair Fence July 14, 2005 July 16, 2005 2 days
Jefferson JHS FM-200507049 05 7/18/05 (Jefferson) Outside Gate, Rear of building. Gate is currently off of track, it needs to be put back on. June 21, 2005 July 18, 2005 27 days
Watkins Elementary School FM-200341499 /03 7/18/05 Watkins First Floor - Teachers Restroom, Second and Fourth Floor - Male Restrooms 1) The last toilets in all restrooms need a flush valve kit. Teachers restroom sink needs a new faucet set for hot water. December 12, 2003 July 18, 2005 584 days
Watkins Elementary School FM-200507324 05 7/18/05 Fourth floor, Teachers' restroom. No Hot Water. June 30, 2005 July 18, 2005 18 days
Langdon Elementary School FM-200507912 05 7/18/05 Langdon Second fl Boys Restroom Repair Partition that is Hanging loose from wall Hanging July 15, 2005 July 18, 2005 3 days
Bowen Elementary School FM-200451859 04 7/18/05 (Bowen) Kitchen: Install appropriate electrical plug for a/c unit. August 9, 2004 July 18, 2005 343 days
Webb Elementary School FM-200507945 05 7/18/05 Webb First Floor - Boys Bathroom 1) Four urinals need to be unstopped. July 18, 2005 July 18, 2005 0 days
Watkins Elementary School FM-200507292 05 7/18/05 Ground floor. Repair or Replace wall hung water cooler by recreation center. June 30, 2005 July 18, 2005 18 days
Watkins Elementary School FM-200341500 /03 7/18/05 Watkins Kitchen Sink not working, faucets decayed and need replacing. December 12, 2003 July 18, 2005 584 days
Malcolm X ES FM-200508037 05 7/18/05 Malcolm X Multi-purpose Room Repair or replace parts or service rooftop unit #2. * Unit continuously trips out. July 18, 2005 July 18, 2005 0 days
Watkins Elementary School FM-200507321 05 7/18/05 Second floor, Teachers' restroom. Unclog sink. June 30, 2005 July 18, 2005 18 days
Savoy Elementary School FM-200507986 05 7/19/05 Savoy Second fl Area Repair Leaking Fixture July 18, 2005 July 19, 2005 1 day
Deal Junior High School FM-200507921 05 7/19/05 (Deal) Exterior, front of building. Remove dead tree from in front of the building. July 15, 2005 July 19, 2005 4 days
Kramer Middle School FM-200454891 04 7/20/05 Kramer First floor porch light front Lights on front of building out. Please replace or repair. September 16, 2004 July 20, 2005 307 days
Bancroft Elementary School FM-200508043 05 7/20/05 Bancroft First Floor - By Main Office 1) Repair Bradley Basin. July 19, 2005 July 20, 2005 1 day
Miner Elementary FM-200508192 05 7/20/05 Miner School Repair rolling gate on 16th Street side July 20, 2005 July 20, 2005 0 days
Bowen Elementary School FM-200459173 04 7/21/05 Bowen Two learning center on first floor There is no lights. December 6, 2004 July 21, 2005 227 days
Young Elementary School FM-200104584 01 7/22/05 YOUNG FRONT ENTRANCE ROOF AROUND BUILDING REPLACE MISSING DOWN SPOUT ON ROOF BY KINDERGARDEN AND CLEAN OUT GUTTERS. March 1, 2001 July 22, 2005 1,604 days
Garfield ES FM-200104318 01 7/22/05 GARFIELD OUTSIDE ALL CATCH BASIN NEED TO BE CLEANED AND SNAKED OUT, THERE ARE THREE IN ALL. 1 IN FRONT OF TEACHERS LOUNGE, 1 BEHIND THE DEMAMABLES & 1 BEHING THE CAFETERIA. February 26, 2001 July 22, 2005 1,607 days
Garfield ES FM-200101622 9/01 7/22/05 (Garfield) CAFETERIA AND TWO ROOMS WATER MAY BE COMING FROM ROOF DRAIN. WATER IS COMING OUT OF THE ROOM WALL. POC: GARY RUCKER (202) 438-9018 CODE A - ASBESTOS ABATED ON 11/01/01 PER SHEILA R. HOWARD CONFIRMED 02/26/02.(RG02/26/02) January 19, 2001 July 22, 2005 1,645 days
Francis Junior High School FM-200100570 01 7/22/05 FRANCIS, THIRD (3RD) FLOOR HALLWAY, OUTSIDE OF ROOM 310 SECURE LOCKERS TO WALL GR-20000041 January 9, 2001 July 22, 2005 1,655 days
Ferebee-Hope Elementary School FM-200105282 01 7/22/05 FEREBEE HOPE BOILER ROOM REPAIR INOPERABLE SUMP PUMP. March 8, 2001 July 22, 2005 1,597 days
Gibbs Elementary School FM-200103661 01 7/22/05 GIBBS CORRIDOR REMOVE & REPLACE BROKEN FLOOR TILE IN FRONT OF ROOM 130. Code A-clear for repair by Horne Engineer ( Philip Connolly) on 3/25/02 (CEB) February 14, 2001 July 22, 2005 1,619 days
Ferebee-Hope Elementary School FM-200105267 01 7/22/05 FEREBEE-HOPE 4TH FL. R/R COIL IN CEILING HEAT UP UNIVENT. March 8, 2001 July 22, 2005 1,597 days
Green Elementary School FM-200104833 01 7/22/05 GREEN 1ST, 2ND & 3RD FLOOR ROOMS 102, 128, 130, 201, 202, 208, 209, 215, 219, 303 & 304 REPLACE (12) TWELVE MOTION DETECTOR LIGHT SWITCHES IN THE THE ROOM ABOVE. March 2, 2001 July 22, 2005 1,603 days
Emery Elementary School FM-200105374 01 7/22/05 EMERY MAIN OFFICE FURNISH MATERIAL TO REPAIR MAIN OFFICE AREAS AND REWIRE AS NECESSARY. March 9, 2001 July 22, 2005 1,596 days
Hardy Middle School FM-200102367 01 7/22/05 (HARDY) 2ND FLOOR GYM: REPAIR BREECH IN WALLS IN GYM AREA AFTER ROOF LEAK. DRAIN WAS REPAIRED. (FIRE CODE VIOLATION) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/23/01. January 29, 2001 July 22, 2005 1,635 days
Hardy Middle School FM-200105524 01 7/22/05 HARDY FIRST FLOOR - ROOM 101 1) INSTALL (4) BALLASTS IN CLASSROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/21/01. HORNE ENGINEERING - BILL CAMPION (RG) March 12, 2001 July 22, 2005 1,593 days
Emery Elementary School FM-200100431 01 7/22/05 OUTSIDE OF CAFETERIA ON EAST SIDE OF BUILDING INSTALL FENCE ADJACENT TO HOMELESS SHELTER NOTE: FENCE SIZE APPROXIMATELY 8 FEET FORMERLY GR-20000110 January 9, 2001 July 22, 2005 1,655 days
Duke Ellington School FM-200101841 01 7/22/05 (ELLINGTON) COMPUTER ROOM #24: PIECES OF CEILING FALLING FROM ABOVE AND CHIPPED PAINT FALLING FROM WALL IMPROPERLY WRAPPED PIPE EXPOSED IN CEILING. MT-20001325 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/02/01. January 22, 2001 July 22, 2005 1,642 days
Patricia R Harris Ed Center FM-200100082 01 7/22/05 HARRIS, P.R. MECHANICAL ROOM, STAIR #5: REPLACE LEAKING MECHANICAL WATER SEAL ON TACO HOT WATER CIRCULATION PUMP. TACO MOD. #A5B2C2T,SER. #BB3006-5-6, RPM 1750, GPM 130, FRAM A5, N.O. FT 25, HP 1-1/2 , MGG. DATE 7.74. (PUMP IS LEAKING AN EXCESSIVE AMOUNT OF WATER ON FLOOR. HC-20000678 January 7, 2001 July 22, 2005 1,657 days
Patricia R Harris Ed Center FM-200102289 01 7/22/05 HARRIS, P.R. ROOMS 219-220 FIRST (1ST) FLOOR NEED A 3/4 INCH HOLE DRILLED INTO WALL FOR BELL ATLANTIC PHONE COMPANY TO INSTALL PHONE WIRES AND NEW PHONES. (NOTE: PLEASE CONTACT MR. JAMES TAYLOR FOR WORK REQUEST NUMBER AT 442-5533) MT-20001338 January 26, 2001 July 22, 2005 1,638 days
Patricia R Harris Ed Center FM-200126736 02 7/22/05 (HARRIS, P.R.) !!! EMERGENCY !!! EXTERIOR LIGHTS ALL EXTERIOR LIGHTING BLDG. BUILDING LIGHTS DONT COME ON. TO DARK IN AREA. REPAIR OR REPLACE EXTERIOR LIGHTING. January 4, 2002 July 22, 2005 1,295 days
Hart Middle School FM-200100225 01 7/22/05 (hart) REMOVE DRINKING FOUNTAIN AND REPLACE WITH A NEW WATER COOLER IN BASEMENT CAFETERIA. January 8, 2001 July 22, 2005 1,656 days
Hearst Elementary School FM-200103772 01 7/22/05 HEARST 1ST & 2ND FLOOR ROOMS 099, 102, 104, 106, 108, 110, 112, 200, 201, 204, 206, 208 (A&B), 210 & 212 REPLACEMENT OF CARPETING AS NEEDED. PLEASE START WITH ROOM 210 - LIBRARY. INSTALL CARPETING IN MAIN OFFICE (ROOM 110). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/28/01. HORNE ENGINEERING - BILL CAMPION (RE) February 16, 2001 July 22, 2005 1,617 days
Hearst Elementary School FM-200103775 01 7/22/05 HEARST 1ST & 2ND FLOOR, ROOF, GUTTERS & WALLS THE ROOF LEAKS INTO ROOM 201 & 099. THERE IS ALSO DAMAGE TO THE WALLS IN THE PRINCIPALS OFFICE (112) AND THE MAIN OFFICE (110). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/28/01. HORNE ENGINEERING - BILL CAMPION (RE) February 16, 2001 July 22, 2005 1,617 days
Hearst Elementary School FM-200103776 01 7/22/05 HEARST 1ST & 2ND FLOOR ROOMS 099, 102, 104, 106, 108, 110, 112, 200, 201, 204, 206, 208 (A&B), 210 & 212, HALLWAYS & FOYERS LEAD ASSESSMENT REQUIRED THE PAINT IS DULL AND PEELING. THE P.T.A. IS PROVIDING NEW SHELVING FOR THE LIBRARY. PAINTING IS NEEDED I Lead Code A - Clear to paint surface with a non-license personnel, but their can absolutely be no scraping, sanding, or abraiding any of these surfaces. Asbestos Code A - Clear For Repairs On 04/01/02. Horne Engineering - Edward Rodriguez (RG 04/02/02) February 16, 2001 July 22, 2005 1,617 days
Hendley Elementary School FM-200104000 01 7/22/05 HENDLEY KITCHEN AREA 1) ASBESTOS ASSESSMENT REQUIRED 2) CEILING NEEDS PLASTERING 2ND AND FINAL NOTICE FOR COMPLIANCE AS REQUESTED BY DEPT. OF HEALTH AND AS LISTED ON FOOD INSPECTION REPORT EMERGENCY Asbestos Code A - Clear for Repair February 21, 2001 July 22, 2005 1,612 days
Duke Ellington School FM-200101821 01 7/22/05 GROUND FLOOR AREA ROOM #24 FORMERLY - MT-20001449 PLASTER CEILING AND WALL IN ROOM #24. Lead & Asbestos Code A - Clear for repairs on 02/20/03. Horne Engineering - Edward Rodriguez (RG 02/20/03) January 22, 2001 July 22, 2005 1,642 days
Duke Ellington School FM-200100930 01 7/22/05 ELLINGTON TEACHERS LOUNGE NEED ASBESTOS ABATEMENT. BEFORE WORKING PLASTERS CAN START. MT-20000733 Asbestos Code A - Clear for Repair. Tracking No. 3251 January 11, 2001 July 22, 2005 1,653 days
Eliot Junior High School FM-200102416 01 7/22/05 (ELIOT) 1ST FLOOR, NEAR ROOM #108: REPAIR STUDENT LOCKERS IN HALLWAY OUTSIDE ROOM #108, AND SOME LOCKERS HAVE BEEN PULLED FROM WALL. January 29, 2001 July 22, 2005 1,635 days
Eliot Junior High School FM-200102090 01 7/22/05 (ELIOT) 2ND FLOOR, ROOM #204: REPAIR PLASTER CEILING IN ROOM #204, PLASTER HAS FALLEN DUE TO RADIATOR FROM THE CLASSROOM ABOVE. MT-20001320 Asbestos/Lead Code A-clear for repair by Horne Engineer ( Bipin Nanavaty ) on 4/17/02 (CEB) January 25, 2001 July 22, 2005 1,639 days
Eliot Junior High School FM-200100999 01 7/22/05 ROOM 104 SPECIAL EDUCATION CENTER - REPAIR LARG BREACH IN WALL ON LEFT SIDE OF DOOR UPON ENTRANCE. FORMERLY -MT-20001627 - SENT TO MS. SHEILA HOWARD 01/11/00 FOR ASSESSMENT. Code A-clear for repair by Horne Engineer (Bipin Nanavaty) 0n 3/22/02 (CEB) January 11, 2001 July 22, 2005 1,653 days
Jefferson JHS FM-200104057 01 7/22/05 JEFFERSON BASEMENT WEST TUNNE - MAIN BLDG. 1. ASBESTOS ASSESSMENT REQUIRED - ACCESS INSULATING MATERIAL ON STEAM SUPPLY LINE, 3 PCS. - 1 - 6" STRAIGHT SECTION, 1 - 4" STRAIGHT SECTION, 1 ELBOW ON 2" PIPE. 2. REPLACE LEAKING 2" STEAM SUPPLY LINE (BLACK PIPE). February 21, 2001 July 22, 2005 1,612 days
Jefferson JHS FM-200104344 01 7/22/05 JEFFERSON SECOND (2ND) FLOOR - CLASSROOM 209 1) ASBESTOS ASSESSMENT REQUIRED. 2) REPAIR OR REPLACE BREACH IN CEILING. ASBESTOS ASSESSMENT COMPLETED 02-27-01 Asbestos Code A - Clear for Repair February 26, 2001 July 22, 2005 1,607 days
Jefferson JHS FM-200104778 01 7/22/05 Jefferson 1) Replace outside security lights . There are no lights!!! Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Troy Wilcome (RG 03/11/03) March 2, 2001 July 22, 2005 1,603 days
Jefferson JHS FM-200104780 01 7/22/05 JEFFERSON 1ST FLOOR AUDITORIUM REPLACE 12 BREAKERS FOR HOUSE LIGHTS, FOOT LIGHTS AND STAGE LIGHTS. March 2, 2001 July 22, 2005 1,603 days
Eliot Junior High School FM-200100977 01 7/22/05 ->Consolidated task items: EHS03 - ASBESTOS ASSESSMENT REQUIRED SMI03 - PLASTERING - <- ELIOT ROOM 104 REPAIR LARGE BREACH IN WALL ON LEFT SIDE OF DOOR, UNPON ENTRANCE. MT-20001627 January 11, 2001 July 22, 2005 1,653 days
Johnson JHS FM-200108000 01 7/22/05 JOHNSON 1) INSTALL LIGHTS ACCORDING TO SCOPE. # ELS CONTRACTING , INC. code A-clear for repair by DCPS Charles Buchanan on 4/02/03 April 10, 2001 July 22, 2005 1,564 days
Kenilworth ES FM-200103850 /20/01 7/22/05 Kenilworth Mechanical Room (auditorium) Replace defective air handler shaft and bearings. February 20, 2001 July 22, 2005 1,613 days
Kenilworth ES FM-200103854 /20/01 7/22/05 Kenilworth Boiler Room Replace missing sump pump and motor. February 20, 2001 July 22, 2005 1,613 days
Kenilworth ES FM-200104255 /23/01 7/22/05 KENILWORTH LISTED BELOW REPLACE BALLASTS & TIPS IN THE FOLLOWING LOCATIONS. NOTE THAT ROOM 108 IS BEING LIT BY LAMPS. TIPS - ROOMS 108, 106, 223, 218, 219, 216, & 214. BALLASTS - ROOMS 313, 302, 303, 310, 3RD FLOOR HALLWAY, 202, 212, 147, 100 Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Sharon Voss (RG 03/11/03) February 23, 2001 July 22, 2005 1,610 days
Key Elementary School FM-200104238 01 7/22/05 KEY OUTSIDE BUSTED DRAIN LINE (PIPES) TWO (2) DOMESTIC WATER IS FLUSHING OUT. EMERGENCY. February 23, 2001 July 22, 2005 1,610 days
Kimball Elementary School FM-200100885 /01 7/22/05 KIMBALL ROOMS 001, 004, 005, 101, 104, 109, 112, 200, 203, 210, AND 212 REPLACE WINDOW PANES. MT 20001609 January 11, 2001 July 22, 2005 1,653 days
Eliot Junior High School FM-200100936 01 7/22/05 ELIOT ROOM 105 MISSING SQUIRREL CAGE AND BLOWER FAN. REPAIR OR REPLACE. NO HEAT. January 11, 2001 July 22, 2005 1,653 days
Eaton Elementary School FM-200104878 01 7/22/05 Eaton Boiler Room Repair heating/cooling circulating pump #3. Bearings appear to be going bad. Armstrong pump, model #4030, size: 4, Motor: Marathon, model #KVJ215TTDR7359BBW, Type: TDR, V-200, Fr: 215T, HP: -10, A: 30.6, Cyc: 60, Ph: 3, RPM: 1745, Design B-Code H, Shaft end, Bearing 207, 207, Opp.End Bearing 205. March 5, 2001 July 22, 2005 1,600 days
Lafayette Elementary School FM-200103794 01 7/22/05 LAFAYETTE 1ST FLOOR EARLY CHILDHOOD PLAY AREA REPLACE SKYLIGHT COVER (PLEXY) IN PLAYGROUND PLAY AREA. February 16, 2001 July 22, 2005 1,617 days
Eastern High School FM-200108005 01 7/22/05 EASTERN 1) INSTALL LIGHTS ACCORDING TO SCOPE. # ELS CONTRACTING , INC. April 10, 2001 July 22, 2005 1,564 days
Langdon Elementary School FM-200104189 01 7/22/05 LANGDON LEARNING CENTER INSTALL NEW OUTLETS IN CLASSROOM February 22, 2001 July 22, 2005 1,611 days
Leckie Elementary School FM-200103985 01 7/22/05 LECKIE MAIN ROOF TOP R/R EXHAUST FAN MOTOR FOR HALLWAYS AND STORGE ROOMS MOTOR LOCK UP. MOTOR = G.E. AC MOTOR, HP 1-1/2, FRAM 145T, PH 3, AMP 5.8/5.6/2.8, VOLT 208/230/460, MODEL #5K45P68004, RPM 1725. ODOR (ENVIRONMENT HEALTH) & FIRE CODE (SMOKE). February 21, 2001 July 22, 2005 1,612 days
Leckie Elementary School FM-200103986 01 7/22/05 LECKIE ROOF EXHAUST FOR RESTROOM #2 R/R BAD SHAFT BEARING AND LOCK UP MOTOR TO ALL RESTROOMS ON ROOF. G.E. MOTOR, MODE #5K45P68004, PH 3, AMP 5.8/5.6/2.8, HP 1-1/2, FRAM 145T, RPM 1725, VOLT 208/230/460. ODOR COMPLAINT AND FIRE CODE. February 21, 2001 July 22, 2005 1,612 days
Ludlow-Taylor ES FM-200101356 1/16/01 7/22/05 LUDLOW-TAYLOR RESTROOMS ASBESTOS ASSESSMENT REQUIRED. MT-20001785 ORIGINAL REQUEST DATE 01-16-01 (FJ) Code A - Same as WO MT-20001785 Horne Engineering - Roger Kager (RG 02/11/03) January 16, 2001 July 22, 2005 1,648 days
Horace Mann Elementary School FM-200101440 01 7/22/05 MANN 2ND FLOOR PLASTER & PAINT PEELING CEILING ABOVE PANEL BOX MT-20001810 Asbestos/Lead Code A-clear for repair by Horne Engineer (Stephen Caldwell) on 4/01/02 (CEB) January 17, 2001 July 22, 2005 1,647 days
Horace Mann Elementary School FM-200102366 01 7/22/05 MANN EXTERIOR SERAPE AND PAINT WOOD TRIM AROUND ENTIRE BUILDING. (MAIN) AT ROOF AND BELOW. PEELING AND CRACKING PAINT IS EXPOSING THE WOOD BENEATH TO THE ELEMENTA. Lead Code B Asbestos Code A - Clear for repairs on 03/07/03. Horne Engineering - Edward Rodriguez (RG 03/10/03) January 29, 2001 July 22, 2005 1,635 days
Horace Mann Elementary School FM-200102368 01 7/22/05 MANN 1ST FLOOR = ROOM 11 PAINT NEW DOOR & FRAMES. DOORS INSTALLED AUGUST 2000. NEW METAL DOOR WILL NEED TO BE PRIMED PRIOR TO PAINTING. LEAD BASED PAINT ASSESSMENT ON 02-15-01 PER SHEILA R. HOWARD SEND TO HORNE ENG. January 29, 2001 July 22, 2005 1,635 days
Horace Mann Elementary School FM-200104334 01 7/22/05 MANN SECOND (2ND) FLOOR - MAIN BUILDING STORAGE ROOM 1) ASBESTOS ASSESSMENT REQUIRED 2) CHECK FOR PEEL AND PAINTING CEILING ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/26/01. February 26, 2001 July 22, 2005 1,607 days
Horace Mann Elementary School FM-200104913 01 7/22/05 MANN FIRST (1ST) FLOOR - CORRIDOR #25 #23, 24, 25, 26 AND 27 INCLUSIVE 1) ASBESTOS ASSESSMENT REQUIRD 2) PAINT WALLS ON FIRST (1ST) FLOOR CORRIDOR AND STAIRWELL AND VESTIBULES. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/26/01. March 4, 2001 July 22, 2005 1,601 days
Maury Elementary School FM-200103705 01 7/22/05 MAURY (ROOF OVER KITCHEN) 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR/REPLACE BURNED OUT MOTOR (NO INFORMATIOON IS ON DATA TAG) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/01/01. HORNE ENGINEERING - BILL CAMPION (RG) February 15, 2001 July 22, 2005 1,618 days
Merritt Middle School FM-200100919 /01 7/22/05 MERRITT EAST LOCKER CORRIDOR BOYS RESTROOM REPAIR LEAK IN URINAL NEXT TO STALLS DUE TO CRACK BESIDE WALL MOUNTING BOLT ON RIGHT SIDE. REPLACE URINAL. MT-20001599 January 11, 2001 July 22, 2005 1,653 days
Eastern High School FM-200102372 01 7/22/05 EASTERN BASEMENT - BAND ROOM SURVEY & INSTALL TWO (2) UNIVENT HEATERS TO PROVIDE HEAT TI THIS AREA. THE TWO (2) EXISTING UNITS ARE TO SMALL TO PROVIDE ADEQUATE HEATING FOR THE ROOM. January 29, 2001 July 22, 2005 1,635 days
Eastern High School FM-200100425 01 7/22/05 EASTERN GYMNASIUM #1 REHANG BASKETBALL GOAL #2 REPAIR/REPLACE ROUET WHEELS ON ONE SECTION OF BLEACHERS--SCARRING FLOOR EVERYTIME USED #3 REPLACE LIGHTS IN CEILING OF GYMNASIUM FORMERLY GR-20000113 January 9, 2001 July 22, 2005 1,655 days
Moten Elementary School FM-200101040 01 7/22/05 MOTEN SECOND (2ND) AND THIRD (3RD) FLOOR BOYS AND GIRLS RESTROOMS RESTORE CEILING AND LIGHTS. January 11, 2001 July 22, 2005 1,653 days
Moten Elementary School FM-200105435 01 7/22/05 MOTEN FIRST,SECOND,THIRD,FORTH FLOORS. 1) ASBESTOS ASSESSMENT REQUIRED 2) MAKE REPAIRS TO CORRECT DEFICIENCIES. 3) DUE: MONDAY, MARCH 26, 2001. POINT OF CONTACT DCPS: GREGORY BRYANT (202)438-2829 AND GOERGE MOODY (202) 4398272. March 9, 2001 July 22, 2005 1,596 days
Eastern High School FM-200100145 /01 7/22/05 EASTERN TUNNEL FAN ROOM: REMOUNT MOTOR TO CONDENSATE TANK IN ORDER TO OPERATE. MOTOR ON-SITE. HC-20000667 January 7, 2001 July 22, 2005 1,657 days
Eastern High School FM-200100073 /01 7/22/05 EASTERN AUDITORIUM REPACE TWELVE (12) EACH 150 WATT SPOTLIGHTS IN CEILING OF AUDITORIUM NOTE: CEILING IS AT LEAST FORTY (40) FEET UP---CHERRY PICKER IS NECESSARY TO REPLACE LIGHT BULBS FORMERLY GR-20000009 January 6, 2001 July 22, 2005 1,658 days
Dunbar High School FM-200105115 01 7/22/05 DUNBAR A-BLDG. - MECHANICAL ROOM PLEASE SURVEY & REPAIR ROOF LEAK WHEN IT RAINS., WATER WILL DAMAGE MOTOR FOR AIR HANDLER A-2. THE CEILING HAS SPRAYED ON INSULATION. March 6, 2001 July 22, 2005 1,599 days
Dunbar High School FM-200104510 01 7/22/05 DUNBAR BOILER ROOM REPAIR LEAKING SEALS FOR HEATING CIRC. PUMPS, # 6, 7, 8 AND 9. February 28, 2001 July 22, 2005 1,605 days
Macfarland Middle School FM-200100523 1/9/01 7/22/05 MACFARLAND, FRONT STEPS REPAIR CENTER RAILING ON STEPS NOTE: RAILING IS LOOSE AROUND CONCRETE AT BASE OF STEPS AND TOPS OF STEPS GR-20000015 January 9, 2001 July 22, 2005 1,655 days
Drew Elementary School FM-200100124 01 7/22/05 DREW STATIONERY PLATFORM REPAIR/REPLACE BOARD ON STATIONERY PLATFORM--WOODEN BOARD APROXIMATELY 6" X 36" FORMERLY GR-20000298 January 6, 2001 July 22, 2005 1,658 days
Draper Elementary School FM-200101836 01 7/22/05 DRAPER BASEMENT TUNNEL FALL OUT SHELTER REPAIR OR REPLACE BAD WATER METER VALVE. OUTLET VALVE. January 22, 2001 July 22, 2005 1,642 days
Draper Elementary School FM-200100985 01 7/22/05 DRAPER BASEMENT CLOSET BY BOYS, REPAIR OR REPLACE CAFE DOOR, 100, 103, 204, 205, 206, 207, 308, CLOSET BY 304 AND 317. January 11, 2001 July 22, 2005 1,653 days
Deal Junior High School FM-200107831 01 7/22/05 DEAL AUDITORIUM 1) ALTER DRAPES SO A/C CAN BE INSTALLED. April 9, 2001 July 22, 2005 1,565 days
Deal Junior High School FM-200100491 01 7/22/05 DEAL FIRST (1ST), SECOND (2ND), THIRD (3RD) AND BASEMENT HALLWAYS SCRAPE, PLASTER AND PAINTING HALLWAYS WALLS. DEAL SCHOOL PAINT ASSESSMENT REQUIRED AND ASBESTOS ASSESSMENT PER SHEILA R. HOWARD ASBESTOS CODE A - CLEAR FOR REPAIR SEE ATTACHED ASBESTOS COD January 9, 2001 July 22, 2005 1,655 days
Orr Elementary School FM-200102069 01 7/22/05 ORR 1ST FL. KITCHEN REPLACE 2 UNIT HEATER MOTORS OR FANS IN KITCHEN. TRANE UNIT HEATER, MODEL S-CU TYPE AND SIZE 20WF - MOTOR UNIVERSAL ELECTRIC CO., SER. 9GF 78676, MOD. C A3D003, 115V, 60 HZ, .78A, 1050. January 25, 2001 July 22, 2005 1,639 days
Coolidge High School FM-200104373 01 7/22/05 COOLIDGE OUTSIDE FRONT SIDE OF BLDG. FABRICATE NEW FRAME AND INSTALL NEW DOOR. OLD WOODEN DOOR WONT CLOSE PROPERLY. February 27, 2001 July 22, 2005 1,606 days
Coolidge High School FM-200101269 01 7/22/05 COOLIDGE 1ST FL. BOYS & GIRLS GYM (1) ASBESTOS ASSESSMENT REQUIRED (2) INSTALL 4 CEILING MOUNTED, ELECTRIC RESISTANCE HEATERS WITH DEDICATED 30 AMP CIRCUITS IN EACH GYM. THIS WOULD SUPPLEMENT THE EXISTING HEATING EQUIPMENT DURING DOWN TIME AND/OR EXTREMELY COLD DAYS. ASBESTOS CODE A-CLEAR FOR REPAIR ASSESSED BY HORNE ENG ON 7/24/01. January 13, 2001 July 22, 2005 1,651 days
Payne Elementary School FM-200108113 01 7/22/05 (PAYNE) 1ST FLOOR/KITCHEN: (1) ASBESTOS ASSESSMENT REQUIRED. Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Edward Rodriguez (RG 03/11/03) April 11, 2001 July 22, 2005 1,563 days
Cook J.F. Elementary School FM-200105342 3/8/01 7/22/05 (COOKE, J.F.) 1. ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR/CAFETERIA: INSTALL UTILITY SINK FOR SANITARY PURPOSES. ASBESTOS ASSESSMENT REQUIRED TO DO THE WORK. POC: BEN PETTIFORD/MR. GREENE BLDG. PERSONNEL (202) 673-7221 SCHOOL OFFICE HEALTH CODE. March 8, 2001 July 22, 2005 1,597 days
Clark Elementary School FM-200104416 01 7/22/05 Clark Boiler Room Replace leaking mechanical seals for circulating pump #1. February 27, 2001 July 22, 2005 1,606 days
Peabody Elementary School FM-200100036 /01 7/22/05 PEABODY BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. UNSTOP FLOOR DRAIN IN BOILER ROOM. FLOOR DRAIN MUST BE DUG UP. HEALTH HAZARD. POC MR. JOSEPH SAUNDERS CELL #439-7848 January 7, 2001 July 22, 2005 1,657 days
Powell Elementary School FM-200101646 01 7/22/05 POWELL ROOF OF THE NEW ADDITION REPAIR OR REPLACE EXHAUST FAN THAT IS INOPERABLE AND OUTDATED. THERE IS NO INFORMATION ON UNIT DUE TO OUDATED EQUIPMENT. EXHAUST FAN IS NEEDED TO PULL EXHAUST FROM BATHROOMS NEW ADDITION. January 19, 2001 July 22, 2005 1,645 days
Cardozo High School FM-200104495 01 7/22/05 CARDOZO BASEMENT FAN ROOM REPLACE OIL BEARINGS ON HEATING FANS #1, 2, 4 WITH GREASE BEARINGS, SEALS ON THE PULLEY SIDE WILL NOT HOLD OIL. MOTOR MFR. PEERLESS, MFR. ELLIOTT CO., HP 30, VOLTS 208/416, RPM 879, AMPS 86/43, PH 3. February 28, 2001 July 22, 2005 1,605 days
Cardozo High School FM-200104222 01 7/22/05 CARDOZO FAN ROOM TUNNEL ASBESTOS ASSESSMENT ASSESS PIPE WRAP MATERIAL FOR REMOVAL, IN THESE AREAS NORTH , WEST, SOUTH AND EAST. February 23, 2001 July 22, 2005 1,610 days
Cardozo High School FM-200104219 01 7/22/05 CARDOZO SB ROOM 22 & 20 ASBESTOS ASSESSMENT ASSESS PIPE WRAP MATERIAL FOR REMOVAL, FOR LEAKING GALVANIZED DOMESTIC COLD WATER PIPE. February 23, 2001 July 22, 2005 1,610 days
Cardozo High School FM-200104208 01 7/22/05 CARDOZO ROOM 82 - 104 FURNISH & INSTALL ELECTRIC OVER HEAD HEATERS IN AREAS THAT CANNOT BE HEATED EFFICIENTLY BY BOILERS. ROOM 9, CUSTODIAN MAINTENANCE OFFICE, February 23, 2001 July 22, 2005 1,610 days
Cardozo High School FM-200104204 01 7/22/05 CARDOZO 1 NORTH WEST ASBESTOS ASSESSMENT ASSESS PIPE WRAP MATERIALS FOR REMOVAL, FOR DOMESTIC COLD WATER SUPPLY PIPE LEAK. GALVANIZED. APPOX. 20" - 30" LONGx 3/4 " OR 1". ASBESTOS CODE A - CLEAR FOR REPAIR ON 07/20/01. February 23, 2001 July 22, 2005 1,610 days
Roosevelt High School FM-200101006 01 7/22/05 (ROOSEVELT) LIBRARY 2ND FLOOR LEVEL - PLASTER WALLS IN THE LIBRARY THAT WAS DAMAGE BY LEAKING GUTTERS, GUTTERS HAVE BEEN REPAIRED. FORMERLY - MT-20001169 Code A-clear for repair by Horne Egineer on ( ) 3/13/02 (CEB) Abatement code D Chase to code A- clear for repair by SR (CEB) January 11, 2001 July 22, 2005 1,653 days
Rudolph Elementary School FM-200104851 01 7/22/05 RUDOLPH 2ND FL. OUTS OF BOYS RESTROOM WINDOW REPAIR NOISY EXHAUST FAN MOTOR. EXHAUST. EXHAUST FAN IS EXCESSABLE THROUGH WINDOW. BUT SCAFFOLD OR EXTENSION LADDER MAY BE NEEDED. DUE TO LOCATION THE NOMENCLATURE IS NOT AVAILABLE. March 5, 2001 July 22, 2005 1,600 days
Cardozo High School FM-200102293 /01 7/22/05 CARDOZO BASEMENT - FAN ROOM - WEST SIDE REMOVE ASBESTOS PIPE INSULATION ON 1 1/4 COPPER PIPE, WATER SUPPLY PIPE APPROXIMATELY 10" - 12". ASBESTOS ASSESSMENT REQUIRED. January 26, 2001 July 22, 2005 1,638 days
Bunker Hill Elementary School FM-200101189 01 7/22/05 BUNKER HILL BOILER ROOM THE B & G MOTOR AND PUMP HAVE BEEN REMOVED AND NOT REPLACED. VOLTAGE 115, 2 BOLT FLANGE PIPING 3/4 BY 1 IN. HC-2000103 January 12, 2001 July 22, 2005 1,652 days
Shaed Elementary School FM-200101793 01 7/22/05 SHAED THROUGHOUT SCHOOL PRINCIPALS OFFICE & CLASSROOMS REKEY CLASS ROOMS (26) TO HAVE EACH ROOM THERE OWN KEY, AND 3 MASTER KEYS. January 22, 2001 July 22, 2005 1,642 days
Bunker Hill Elementary School FM-200100849 1/11/01 7/22/05 BUNKER HILL CAFETERIA STORAGE ROOM REPLACE CIRCULATING MOTOR ON HEAT EXCHANGER IN CEILING REAR AT CAFETERIA STORAGE ROOM. MOTOR HAS BEEN REMOVED BY MR. HOUSTON. HC-20000349 January 11, 2001 July 22, 2005 1,653 days
Shaed Elementary School FM-200104069 01 7/22/05 Shaed Boiler Room Survey, upgrade existing lighting in boiler room. Currently existing lighting is very poor. February 21, 2001 July 22, 2005 1,612 days
Shaw JHS FM-200100294 01 7/22/05 (SHAW) INTERIOR DOORS THROUGHOUT BUILDING NEED LOCKS KEYED TO ONE (1) MASTER KEY TO INTERIOR DOORS TO SCHOOL FORMERLY CF-20000193 January 8, 2001 July 22, 2005 1,656 days
Bunker Hill Elementary School FM-200100846 1/11/01 7/22/05 BUNKER HILL EAST WING BOYS RESTROOM ROOF REPLACE EXHAUST FAN MOTOR ON ROOF (NEW BLDG.) MOTOR HAS BEEN REMOVED. HC-20000407 January 11, 2001 July 22, 2005 1,653 days
Ronald H. Brown MS FM-200105301 01 7/22/05 BROWN, RON FIRST (1ST) FLOOR - AUDITORIUM MULFUNCTION OF LIGHTS ON THE CONTROL PANEL. WANT TO CELERBRATE RON BROWN BRITHDAY WITH PROGRAM, MARCH 22, 2001. March 7, 2001 July 22, 2005 1,598 days
Shepherd ES FM-200101417 01 7/22/05 SHEPHERD MAIN ENTRANCE LEAD ASSESSMENT FOR REPAINTING OF MAIN ENTRANCE DOORS FOR REPAINTING PURPOSES. (RESTORATION: REPAINT) ASBESTOS ASSESSMENT REQUIRED. MT-20001038 ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/19/02 HORNE ENGINEER: ROGER KAGER LEAD CODE A-CLEAR FOR REPAIR NO 2/19/02 HORNE ENGINEER: ROGER KAGER January 16, 2001 July 22, 2005 1,648 days
Shepherd ES FM-200102102 01 7/22/05 SHEPHERD GROUND FLOOR - OLD WING ROOM #101 RESTROOM REPAIR HOLE IN WALLS IN ROOM #101 RESTROOM ASBESTOS ASSESSMENT REQUIRED MT-20001382 ASBESTOS CODE A - CLEAR FOR REPAIR January 25, 2001 July 22, 2005 1,639 days
Shepherd ES FM-200107776 01 7/22/05 SHEPHERD ASBESTOS ASSESSMENT REQUIRED 1) FURNISH AND INSTALL CARPET IN ROOMS: 101, 103, 105, 132, 134, 212, 214 216, AND LIBRARY. # CB FLOORING, LLC April 7, 2001 July 22, 2005 1,567 days
Ronald H. Brown MS FM-200105187 01 7/22/05 BROWN, RON PRINCIPAL CARRIES ABOUT 30 KEYS FOR THE CLASSROOMS AND WANTS THE LOCKSMITH TO RE-KEY THE ROOMS TO ONE (1) MASTER KEY. March 7, 2001 July 22, 2005 1,598 days
Ronald H. Brown MS FM-200100840 1/11/01 7/22/05 BROWN, RON ROOF AREA ALL BOYS AND GIRLS EXHAUST FAN MOTORS LOCKING. HC-20000183 January 11, 2001 July 22, 2005 1,653 days
Brightwood Elementary School FM-200100310 1/8/01 7/22/05 BRIGHTWOOD THROUGHOUT BUILDING MAKE ONE (1) MASTER KEY FOR ALL CLASSROOMS FORMERLY CF-20000205 January 8, 2001 July 22, 2005 1,656 days
Spingarn High School FM-200104673 1/01 7/22/05 SPINGARN OUTDIE MECH. ROOM FOR THE GREENHOUSE SURVEY AND MAKE NECESSARY REPAIRS TO THE PEERLESS GAS BOILER. THE BOILER WILL NOT START, WILL NOT STAY LIT. March 1, 2001 July 22, 2005 1,604 days
Spingarn High School FM-200104716 2/01 7/22/05 SPINGARN BASEMENT NORTH TUNNEL SURVEY & RECONNECT STEAM OR RETURN LINES THAT WERE CAPPED ON VALVE OFF BY STEAM REPAIR SHOP. LINES ARE FOR 3/4" TO 2". March 2, 2001 July 22, 2005 1,603 days
Birney Elementary School FM-200101102 01 7/22/05 BIRNEY THIRD FLOOR - ROOM 308,COMPUTER ROOM SECOND FLOOR - ROOM 215 AND EXIT (6). FIRST FLOOR - GIRLS BATHROOM REPLACE BROKEN GLASS.... January 12, 2001 July 22, 2005 1,652 days
Stuart-Hobson Middle School FM-200101419 1/16/01 7/22/05 STUART-HOBSON FIRST (1ST) FLOOR - AUDITORIUM PLASTER FALLING FROM CEILING ON TO THE STAGE. ASBESTOS ASSESSMENT REQUIRED. - ASBESTOS CODE A - CLEAR FOR REPAIR (SEE ATTACHED SHEET) MT-20001147 January 16, 2001 July 22, 2005 1,648 days
Takoma Educational Center FM-200103877 01 7/22/05 TAKOMA 3RD FLOOR ROOM 208 & 2ND FLOOR ROOM 163 REPLACE 8IN. FAUCET SPREAD DUE TO WATER CONSTANTLY DRIPS WATER. February 20, 2001 July 22, 2005 1,613 days
Takoma Educational Center FM-200104297 01 7/22/05 TAKOMA 1) LIGHTS AND BALLAST REPLACEMENT, 277 VOLTS 2-TUBE BALLAST, 1 TUBE BALLAST, LONG LIFE ENERGY SAVER; F40CW/ES 1ST FL. RM#56, 73, 76, 72, 32, 13, 46, 1, 13, 35, 46 2ND FL. RM #113, 124, 143, 134, 154, 160,169,165, 167, 161, 62, 156, 152, 153, 155, 164, 172, 137, 145, 116 3RD FL. RM #186, 183, 196, 217, 226, 235, 233, 211, 219, 213, 232, 190 RM #101, 95,96,93,108, 86, 94, 90, 87, 88 ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/21/01. February 23, 2001 July 22, 2005 1,610 days
Takoma Educational Center FM-200508141 05 7/22/05 Takoma First fl. Trashroom Unstop. fl. Drain July 20, 2005 July 22, 2005 2 days
Thomas Elementary School FM-200100853 01 7/22/05 THOMAS BOILER ROOM REPLACE BURNED OUT STARTER CONTROL ON VACUUM PUMP #2. CONTROL IS NEEDED TO ENSURE PROPER OPERTION OF CONDENSATION SYSTEM. HC-20000476 January 11, 2001 July 22, 2005 1,653 days
Thomas Elementary School FM-200103838 01 7/22/05 Thomas Boiler Room Replace defective soleniod valve for make-up water supply for condensate return tank. automatic switch Co. cat. #8210D4, serial #R93018S, Rebuild Kit #302280, air insert Gas-5-125psi, water -5-125/psi, Lt. oil-5-100psi, volts: 208, Hz: 60, Watts: 6, Dia: 1", Ph: 1 February 20, 2001 July 22, 2005 1,613 days
Truesdell Elementary FM-200105333 01 7/22/05 TRUESDELL FIRST (1ST) FLOOR - MAIN LOBBY 1) ASBESTOS ASSESSMENT REQUIRED. 2) INSTALL A OUTLET IN WALL FOR THE METAL DETECTOR MACHINE. INSPECTOR: FIRE CODE VIOLATION 3) Asbestos Code A - Clear for Repair ON 03/13/01. Note: material in stock-Sheila H. March 8, 2001 July 22, 2005 1,597 days
Tubman Elementary School FM-200108156 01 7/22/05 (TUBMAN) (1) ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/MAIN OFFICE: REPAIR OR REPLACE LIGHT FIXTURES. ASBESTOS CODE A - CLEAR FOR REPARS ON 06/11/01. April 11, 2001 July 22, 2005 1,563 days
Bancroft Elementary School FM-200101091 01 7/22/05 BANCROFT ROOM 200B REPAIR UNIVENT HEATER THAT IS NOT WORKING. BEARING ASSEMBLY WORN TOTALLY OUT. CAN NOT BLOW HEAT OUT INTO THE ROOM. HC-20000599 January 12, 2001 July 22, 2005 1,652 days
Ballou Senior High School FM-200508375 05 7/22/05 Ballou Room #308, #309 and #310 Check and repair breaker for the following classrooms: #308, #309 and #310. Breakers for these rooms operate A/C window units are drawing high amos causing breaker to trip. (3) Three General electric 20 amp circuit breakers July 22, 2005 July 22, 2005 0 days
Ballou Senior High School FM-200508374 05 7/22/05 Ballou Hallway Panel Box Replace (2) two bad general electric 20 amp circuit breakers for operation of A/C window units in rooms #309 and #315. July 22, 2005 July 22, 2005 0 days
Watkins Elementary School FM-200455089 04 7/22/05 Watkins First Floor There is a busted pipe to urinal flooding the floor it needs to be replaced. Teachers restroom last toilet needs a flush valve kit. September 20, 2004 July 22, 2005 305 days
Ballou Senior High School FM-200508335 05 7/22/05 Ballou High School Repair 100 feet of fence on stadium July 21, 2005 July 22, 2005 1 day
Watkins Elementary School FM-200507319 05 7/22/05 Watkins First through Fourth floors. Repair Bradley Basins. June 30, 2005 July 22, 2005 22 days
Ballou Senior High School FM-200108002 01 7/22/05 BALLOU 1) INSTALL LIGHTS ACCORDING TO SCOPE. # ELS CONTRACTING , INC. April 10, 2001 July 22, 2005 1,564 days
Webb Elementary School FM-200101945 01 7/22/05 (WEBB) 1ST FLOOR: ELECTRICAL OUTLETS NEED TO BE INSTALLED FOR AIR CONDITIONERS WINDOW UNITS. Asbestos Code A - Clear for repairs on 03/10/03.- However CAUTION shall be use when installing A/C window unit as Ceiling isasbestos containing. Horne Engineering - Sharon Voss (RG 03/11/03) Tracking # 17524 January 23, 2001 July 22, 2005 1,641 days
Webb Elementary School FM-200104932 01 7/22/05 WEBB KITCHEN PAINT KITCHEN, CEILING, WALLS, WINDOWS, OFFICE, LOCKERS, RESTROOM, DOORS AND TRIM. AVA CONTRACTOR Lead Code B Asbestos Code A - Clear for repairs on 02/19/03. Horne Engineering - Edward Rodriguez (RG 02/20/03) March 5, 2001 July 22, 2005 1,600 days
Ballou Senior High School FM-200107970 01 7/22/05 BALLOU OUTSIDE REPLACE EXTERIOR LIGHTS AROUND SCHOOL ASBESTOS CODE A-CLREAR FOR REPAIR BY CHARLES E BUCHANAN 6/28/01 April 9, 2001 July 22, 2005 1,565 days
West Elementary School FM-200102141 01 7/22/05 WEST 2ND FL. MECH. ROOM #7/8 REPLACE UNIT HEATER MOTORS. NAME TRANE SER #7JF85741K, VOLTS 115, HZ 60, AMPS 1.80, RPM 1550. HEATER UNITS WILL NOT RUN TO MECH. ROOMS 7 & 8. January 25, 2001 July 22, 2005 1,639 days
West Elementary School FM-200105078 01 7/22/05 WEST BOILER ROOM R/R MOTOR TO HOT WATER HEATING CIRCULATOR PUMP #3. NAME BALDOR, PH 3, AMPS 21.5, CAT - M3710T, SPEC 37A073W452, FRAMER 213T, SER. F792, RPM 1725, HP 7-1/2. MOTOR IS INOPERABLE. March 7, 2001 July 22, 2005 1,598 days
Ballou Senior High School FM-200101667 01 7/22/05 BALLOU 1)MAIN OFFICE, PRINICIPAL, ASSISTANT PRINCIPALS OFFICE, ROOM A116, 126, A127, COUNSELORS OFFICE AND LIBRARY 2) ASBESTOS ASSESSMENT REQUIRED 3) REPAIR/REPLACE FLOORING MATERIAL MT-20001861 ASBESTOS CODE A-CLEAR FOR REPAIRS January 19, 2001 July 22, 2005 1,645 days
Whittier Elementary School FM-200101315 6/01 7/22/05 WHITTIER ADUITORIUM, CLASSROOMS, HALLWAYS, BATHROOM AND MULTI-PURPOSE FLOORING ASBESTOS ASSESSMENT REQUIRED. MT-20001752 ORIGINAL REQUEST DATE 01-16-01(FJ) January 16, 2001 July 22, 2005 1,648 days
Ballou Senior High School FM-200101372 01 7/22/05 BALLOU AUDITORIUM AND FIRST FLOOR- A- WING ASBESTOS ASSESSMENT REPLACE LIGHT FIXTURE, PAINT FIRST MT-20001784 ABS MGR. ADDED - ORIGINAL INITIATED 1/16/01 (FJ) INSTALL FLORESCENT TUBES IN (25) LIGHT FIXTURES. 5/29/01 January 16, 2001 July 22, 2005 1,648 days
Ballou Senior High School FM-200101357 01 7/22/05 BALLOU AUDITORIUM PAINT RENOVATION ASBESTOS ASSESSMENT REQUIRED MT-20001788 ORIGINAL REQUEST DATE 01-16-01(FJ) January 16, 2001 July 22, 2005 1,648 days
Aiton Elementary School FM-200105043 01 7/22/05 AITON INSTALL ASPHALT OVER EXISTING SURFACE, NO ACM TEST NEEDED HRGM CONTRACTOR Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Sharon Voss (RG 03/11/03) March 6, 2001 July 22, 2005 1,599 days
Aiton Elementary School FM-200101444 01 7/22/05 AITON KITCHEN REPLACE BROKEN AND MISSING (9x9) FLOOR TILE. MT-20001871 ASBESTOS ASSESSMENT REQUIRED. ORIGINAL REQUEST DATE 01-17-01 (FJ) January 17, 2001 July 22, 2005 1,647 days
Wilson High School FM-200102431 01 7/22/05 WILSON, W. TUNNEL BY PUMP ROOM & SEC B 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR LEAK ON 3/4" LINE TO DOMESTIC HOT WATER TANK BY PUMP ROOM IN STEAM TUNNEL AND LEAK ON 1-1/4" BLACK IRON PIPE IN STEAM TUNNEL B. BOTH AREAS CONTAIN ASBESTOS. POC MR. J. SAUNDERS OFFICE #698-1750. January 30, 2001 July 22, 2005 1,634 days
Wilson High School FM-200507841 05 7/22/05 W. Wilson School Repair Fence July 14, 2005 July 22, 2005 8 days
Woodson High School FM-200104603 01 7/22/05 WOODSON, H.D. GYM - 1ST FLOOR 1) ASBESTOS ASSESSMENT REQUIRED 2) NEED HELP TO SCRAP CEILING IN THE GYM. PLASTER IS PEELING FROM THE CEILING. BUILDING STAFF NEEDS A CHERRY PICKER OR A SCAFFOLD. CEILING IS APPROX. 40 FEET HIGH. STAFF WILL SCRAPE CEILING WITH PROPER EQUIPMENT. Lead & Asbestos Code A - Clear For Repairs On 03/11/02. Horne Engineering - Edward Rodriuez (RG 03/11/02) February 28, 2001 July 22, 2005 1,605 days
Woodson High School FM-200104886 01 7/22/05 Woodson, HD Boiler Room Repair leaking mechanical seals on feed water pumps for boilers #1 and #2. March 5, 2001 July 22, 2005 1,600 days
Young Elementary School FM-200100806 01 7/22/05 YOUNG 1ST FL CAFETERIA SURVEY AND REPAIR 2 WALL MOUNTED UNIVENTS THAT ARE NOT WORKING. THE CENTER UNIVENT HAS A BAD MOTOR (G.E. PART #274792). THE UNIVENT LEFT OF CENTER HAS VANDALIZED CONTROLS. THE CAFETERIA IS COLD. HC-20001194 January 10, 2001 July 22, 2005 1,654 days
Adams Elementary FM-200104063 01 7/22/05 BASEMENT PUMP ROOM REPAIR OR REPLACE LEAKING 6" MAIN SHUT OFF VALVE. February 21, 2001 July 22, 2005 1,612 days
Aiton Elementary School FM-200108603 01 7/25/05 AITON STAGE 1) REFINISHING THE STAGE TEST FOR LEAD LEAD CODE A - CLEAR FOR REPAIRS ON 04/27/01. April 18, 2001 July 25, 2005 1,559 days
Oyster Elementary School FM-200102753 01 7/25/05 OYSTER - REPAIR OR REPLACE MASONRY BLOCK WERE ELECTRICAL WORK WAS DONE. February 1, 2001 July 25, 2005 1,635 days
Ferebee-Hope Elementary School FM-200108259 01 7/25/05 FEREBEE-HOPE THIRD (3RD) FLOOR - ALL OPEN SPACE 1) ASBESTOS ASSESSMENT REQUIRED 2) CARPET REPAIRS: RE-GLUE CARPET SEAMS, ENTIRE AREA 23,430 SQIARE FEET. (DO TO FLOOD) Asbestos Code A - Clear For Repairs On 11/14/01. Horne Engineering - Bipin Nanavaty (RG 03/20/02) April 12, 2001 July 25, 2005 1,565 days
Gibbs Elementary School FM-200109683 01 7/25/05 GIBBS RM. 101, 102, 129, 310 1. ASBESTOS ASSESSMENT REQUIRED. 2. PURCHASE AND INSTALL 18,000 BTU AC WINDOW UNIT. Multi-Trade lead trade electrical/welding/carpentry. Need to determine fund to purchase AC's. 5-21-02. 3. INSTALL ELECTRICAL SERVICE TO EACH ONE. Requestor Phone: 698-1750 ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/25/01BY HORNE ENGINEER: SAM EBRAHIM May 4, 2001 July 25, 2005 1,543 days
Raymond Elementary School FM-200103052 /01 7/25/05 RAYMOND 1ST FL. BOILER ROOM REPAIR OR REPLACE STARTER CONTROL TO #2 HOT WATER HEATING CIRCULATING PUMP. NAME - CUTLER HAMER, SIZE -2, VOLTS 220, AMPS 45, SERIES B1, SER. # AN16GNO. COIL WILL NOT PULL IN TO OPERATE MOTOR OR THE CIRCULATING PUMP. February 6, 2001 July 25, 2005 1,630 days
Emery Elementary School FM-200103345 01 7/25/05 EMERY ENTIRE BUILDING RE-KEY THE BUILDING. February 8, 2001 July 25, 2005 1,628 days
Woodson High School FM-200109343 01 7/25/05 WO0DSON, H.D. FIRST (1ST) FLOOR - CORRIDOR OUTSIDE MEDIA CTR. 1) ASBESTOS ASSESSMENT REQUIRED. 2) CEILING IS BADLY DAMAGED DUE TO FLOODING. LEAK HAS BEEN FIXED CEILINGS NEEDS REPAIR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/15/01. April 30, 2001 July 25, 2005 1,547 days
Duke Ellington School FM-200103660 01 7/25/05 ELLINGTON 1ST FL, BASEMENT REPLACE/INSTALL THERMOSTATIC VALVES IN THE ABOVE LOCATIONS. THE FOLLOWING LOCATIONS NEED 1: 101, 103, 105, 115, 118, 3, 5, 41, 10. THE FOLLOWING LOCATIONS NEED 2: 108, 117, 120, 1, 2, CAFETERIA, DANCE ROOM, NURSE OFFICE, 24, GUIDANCE COUNSELOR. HALLWAY NEEDS 10, BASEMENT HALLWAY NEEDS 6, GYM NEEDS 14. 2ND. FL. REPLACE/INSTALL THERMOSTATIC VALVE ON RADIATORS IN THE ABOVE LOCATIONS 217,217A,200,252B,251,251A,252,254,264A,201A,220,216,205,208,201,250,260,262,264,265 THE LIBRARY NEEDS 4, HALLWAY NEEDS 3. 3RD. FLOOR REPLACE/INSTALL THERMOSTATIC VALVES ON RADIATORS IN CLASSROOMS THE FOLLOWING LOCATIONS NEED 1: 301,301A,313,317,318,320 AND HALLWAY ROOM 309 NEEDS 4. ROOM 314 NEEDS 3. February 14, 2001 July 25, 2005 1,622 days
Cardozo High School FM-200103353 01 7/25/05 CARDOZO NORTH WEST TUNNEL 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE LEAKING STEAM RETURN BLACK PIPE. PIPE IS 1-1/4" BY APPROX. 10 FT. LONG. February 8, 2001 July 25, 2005 1,628 days
Patricia R Harris Ed Center FM-200108925 01 7/25/05 (HARRIS, P.R.) 1. ASBESTOS ASSESSMENT REQUIRED. EXTERIOR EXIT: PAINT ALL EXTERIOR DOORS AROUND THE ENTIRE BUILDING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/14/01. April 20, 2001 July 25, 2005 1,557 days
Roosevelt High School FM-200507724 05 7/25/05 Roosevelt SHS - Stay Office 1. Perform electrical load survey iand install 1 20amp/208 plug for 24,000btu window a/c unit. 2. After approval by the Electrical Shop - Install 1 - 24,000btu window a/c unit. (Carpentry Shop) July 13, 2005 July 25, 2005 12 days
Rudolph Elementary School FM-200102569 01 7/25/05 (RUDOLPH) 2nd floor, Library: Library to be converted to computer lab. Security doors need to be installed. NOTE: FM-200105362 WAS SENT TO THE WELDERS ON 3-8-01 Asbestos Code A - Clear for repairs on 04/16/03. Horne Engineering - Sharon Voss (RG 04/17/03) January 31, 2001 July 25, 2005 1,636 days
Hart Middle School FM-200103072 01 7/25/05 HART 3RD FL. HALLWAY REPLACE SHAFT IN UNIVENT (HERMAN & NELSON) SHAFT SIZE: 2 FT. 1 INCH. 3 SQUIRREL CAGES AND MOTOR (HP 1/8, RPM 700, V 115, 200 SHAFT: 1-1/2" X 1/2". 5KCP39KGB909S. LUNCH ROOM - REPLACE 4 SQUIRREL CAGES UNIVENT LUNCH ROOM. February 6, 2001 July 25, 2005 1,630 days
Hart Middle School FM-200103076 01 7/25/05 HART THROUGHOUT BLDG. REPLACE UNIVENT COVERS IN ROOMS: 124, 123, 207, 206, 319, 317, 133, LOCKER ROOMS, AND HALLWAYS 1ST, 2ND AND 3RD FLOORS. HERMAN & NELSON UNIVENTS SIZE OF COVERS: 7-1/2" X 6-3/4". TOTAL NEEDED 35 COVERS. February 6, 2001 July 25, 2005 1,630 days
Cardozo High School FM-200103352 01 7/25/05 CARDOZO NORTH WEST TUNNEL 1. ASBESTOS ASSESSMENT IS NEEDED. 2. REPLACE DETERIORATING BLACK PIPE FOR STEAM SUPPLY. PIPE IS 3/4" X 10 FT. LONG AND IS LEAKING. February 8, 2001 July 25, 2005 1,628 days
Hearst Elementary School FM-200109052 01 7/25/05 HEARST ENTIRE BUILDING NEEDS TO BE PAINTED (INTERIOR) 1) ASBESTOS ASSESSMENT REQUIRED 2) THE PAINT IS DULL AND PEELING. THE P.T.A. IS PROVIDING NEW SHELVING FOR THE LIBRARY. PAINTING IS NEEDED IMMEDIATELY, IF POSSIBLE. THE ENHANCEMENT WILL IMPROVE THE SHCOOL CLIMATE. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/09/01. April 24, 2001 July 25, 2005 1,553 days
Woodson High School FM-200110226 01 7/25/05 WOODSON, H.D. FIRST (1ST) FLOOR - AUDITORIUM BUILD A SCALFOLD TO REPLACE EIGHT (8) LIGHTS. May 14, 2001 July 25, 2005 1,533 days
Adams Elementary FM-200102674 01 7/25/05 ADAMS BASEMENT PUMP ROOM REPAIR OR REPLACE LEAKING 6" MAIN BLDG. SHUT-OFF VALVE. February 1, 2001 July 25, 2005 1,635 days
Hendley Elementary School FM-200508588 05 7/25/05 Hendley Second fl. Annex Repair Lights in the Area July 25, 2005 July 25, 2005 0 days
School WW High School FM-200108252 01 7/25/05 (SCHOOL WITHOUT WALLS) 1ST FLOOR/ROOM #107: (ASBESTOS ASSESSMENT REQUIRED.) REPAIR LARGE STRUCTURAL CRACK IN WALL OF CLASSROOM. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/08/01. April 12, 2001 July 25, 2005 1,565 days
John Burroughs ES FM-200506472 05 7/25/05 Burroughs First fl. Boys Restroom /Lower level Water Fountain Unstop Urinals/ Change Battery Operrated Flush Valves to Manual/ Unstop water Fountian June 7, 2005 July 25, 2005 48 days
Johnson JHS FM-200102634 /01 7/25/05 JOHNSON GYMNASIUM - FIRST (1ST) FLOOR SOME AREA OF THE GYMNASIUM FLOOR NEED TO BE REPAIR. DUE TO WATER DAMAGE. ASBESTOS ASSESSMENT REQUIRED MT- 20001555 Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Bipin Nanavaty (RG 03/11/03) January 31, 2001 July 25, 2005 1,636 days
Shaw JHS FM-200102486 01 7/25/05 SHAW BOILER ROOM REPAIR OR REPLACE BELL AND GOSSETT CIRCULATING PUMP TO CONVERTER THAT SERVICES REHEAT COILS AND CONVECTORS. MAKE: BELL & GOSSETT, 153.1, RPM, MODEL 2-1/2 AB, SER., #147483, HP 2. January 30, 2001 July 25, 2005 1,637 days
Shaw JHS FM-200102488 01 7/25/05 SHAW BOILER ROOM REPLACE STARTER CONTROL TO HOT WATER SYSTEM CIRCULATING PUMP THAT SERVICE REHEATER COILS AND CONVECTOR. CONTROLS HAVE BEEN PULLED BUT NEVER REPLACED. MAKE: WESTINGHOUSE, COIL #480U, A200M2CX, 60 HZ, STYLE 765A842609, 44U, VOLTS 200 230 460/97S, 50SCB86G13, CWTEA. January 30, 2001 July 25, 2005 1,637 days
Shaw JHS FM-200109961 01 7/25/05 SHAW SECURE DOOR THAT LEADS TO GARAGE FROM ROOF OF DAY CARE CENTER. BREAK IN 5/4/01. SECURITY HAZARD. May 10, 2001 July 25, 2005 1,537 days
Key Elementary School FM-200110511 01 7/25/05 KEY TUNNEL AREA 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE RUPTURED 2" HEATING LINE (BLACK PIPE) IN CRAWL SPACE. May 17, 2001 July 25, 2005 1,530 days
Ronald H. Brown MS FM-200108371 01 7/25/05 RON BROWN TEACHERS DINING ROOM 1ST FL. 2. REPLACE WINDOW AC UNIT. COMPRESSOR MAY BE DEFECTIVE, TRIPS CIRCUIT BREAKER UPON CLOSING CIRCUIT. QUIETMASTER - 24, 000 BTU. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/22/01. April 13, 2001 July 25, 2005 1,564 days
Kimball Elementary School FM-200102570 /01 7/25/05 KIMBALL MIDDLE WING, NORTH WING, NEW WING, CAFETERIA OFFICE AND MAIN. OFFICE. REPLACE GLASS IN GIRLS BATHRIOOM-(MIDDLE WING), GIRLS BATHROOM - (NORTH WING), MAIN OFFICE- (MIDDLE WING), CAFETERIA OFFICE, (MIDDLE WING) AND CLASSROOMS - 112,105,005,104,212,210,106 AND 002. January 31, 2001 July 25, 2005 1,636 days
Kimball Elementary School FM-200109778 01 7/25/05 KIMBALL OUTSIDE EXTERIOR EXTERIOR BAY WINDOW OUTSIDE OF CLASSROOM #102 NORTH WING MONTOSORI NEEDS TO BE SCRAPE AND PAINTING. (METAL FRAME) May 8, 2001 July 25, 2005 1,539 days
King M L ES FM-200102643 01 7/25/05 KING KING THIRD (3RD) FLOOR LEAK IN GIRLS RESTROOM ON THE 3RD FLOOR WATER IS FLOODING THE FLOOR. (POSSIBLE ROOF LEAK) MT-20001575 January 31, 2001 July 25, 2005 1,636 days
Eastern High School FM-200456630 04 7/25/05 Eastern EMERGENCY Sub-basement outside locker room Unstop outside drain outside of boys locker room and unstop toilet across from gym. Football game 10/08/04 team has to jump or track over water outside. October 8, 2004 July 25, 2005 290 days
Lafayette Elementary School FM-200103626 01 7/25/05 LAFAYETTE FIRST (1ST) FLOOR - MAIN OFFICE AREA 1) ASBESTOS ASSESSMENT REQUIRED 2) INSTALLED CARPET TO GRAND HALL BY MAIN OFFICE AREA Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Troy Wilcome (RG 03/11/03) February 13, 2001 July 25, 2005 1,623 days
Turner Elementary School FM-200109983 01 7/25/05 TURNER SECOND (2ND) FLOOR - TEACHERS LOUNGE 1) ASBESTOS ASSESSMENT REQUIRED. 2) INSTALL NEW SECURITY DOOR IN ROOM #200; SEE PRINCIPAL ABOUT DETAILS. Code A-clear for repair by Horne Egineer on ( Sam Ebrahim ) 3/13/02 (CEB May 10, 2001 July 25, 2005 1,537 days
Marshall Educational Center FM-200109499 01 7/25/05 MARSHALL ASBESTOS AND LEAD ASSESSMENT REQUIRED 1) SWIMMING POOL/ELECTRICAL POC - RAJ SKULA/TIM KEENE -202-889-8400 ASBESTOS CODE A-CLEAR FOR REPAIR 6/9/01 May 3, 2001 July 25, 2005 1,544 days
Woodson High School FM-200102782 2/2/01 7/25/05 WOODSON, H.D. OUTSIDE PLAZA 1. ASBESTOS ASSESSMENT REQUIRED TO CONCRETE CEILING AND PIPE INSULATION. 2. REPAIR RUPTURED LINE. 3. INSULATE PIPE ( SIZE TO BE DETERMINED) 4. PLASTER WORK NEEDED. POC MR. BRADLEY CELL #438-7437 ASBESTOS CODE A - CLEAR FOR REPAIR (SEE ATTACHED SHEET) February 2, 2001 July 25, 2005 1,634 days
Leckie Elementary School FM-200110000 01 7/25/05 LECKIE OUTSIDE STRUCTURE IS NEEDED FOR REPAIR AROUND BUILDING. PLASTERING FALLING FROM BUILDING AND CRACKING. May 10, 2001 July 25, 2005 1,537 days
Eastern High School FM-200103411 01 7/25/05 EASTERN GROUND FLOOR AREA GREEN HOUSE AND CORRIDOR WINDOWS 1) REPAIR THE WINDOWS IN THE GREEN HOUSE AND THE WINDOWS IN THE CORRIDOR ON THE GYM HALLWAY. February 9, 2001 July 25, 2005 1,627 days
Eastern High School FM-200102863 01 7/25/05 EASTERN BASEMENT GREENHOUSE REPLACE (5) 2X8 PIECES OF LEXON . February 5, 2001 July 25, 2005 1,631 days
West Elementary School FM-200507894 05 7/25/05 (West) Unclog toilets, to identify areas see building personell July 15, 2005 July 25, 2005 10 days
Adams Elementary FM-200108374 01 7/25/05 ADAMS BASEMENT PUMP ROOM 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. R/R LEAKING 6" MAIN BUILDING SHUT OFF VALVE. Asbestos Code A - Clear for repairs on 03/06/03. Horne Engineering - Tony Marcolin (RG 03/07/03) April 13, 2001 July 25, 2005 1,564 days
Smothers ES FM-200103203 01 7/25/05 SMOTHERS - PLAYGROUND (WIN PROJECT) PROVIDE AND INSTALL PLAYGROUND EQUIPMENT. February 7, 2001 July 25, 2005 1,629 days
Brightwood Elementary School FM-200103023 2/5/01 7/25/05 BRIGHTWOOD FIRST (1ST) FLOOR - CLASSROOM 106, 107 AND 109. 1) ASBESTOS ASSESSMENT REQUIRED 2) THE DOORS IN CLASSROOM NEEDS TO BE RELINE OR REPLACE. *FIRE CODE VIOLATION. Code A-clear for repair by Horne Engineer (Philip Connolly ) on 4/01/02 (CEB) February 5, 2001 July 25, 2005 1,631 days
Horace Mann Elementary School FM-200110084 01 7/25/05 MANN MAIN BUILDING AT ROOF LINE REPLACE ALL EXISTING EXTERIOR LIGHTS AT ROOF LINE. INADEQUATE LIGHTS AND BROKEN COVER PLATS. May 11, 2001 July 25, 2005 1,536 days
Sousa Middle School FM-200109609 01 7/25/05 SOUSA 1) Asbestos Assessment Required. 2) Basement Floor - Girls Restroom Water Leaking in Bathroom. Fixture removed several weeks ago and it is leaking from hole in wall. Exp Demo ENVIROBATE (IT GROUP) 703-461-6848 CODE A - ASBESTOS ABATED ON 6/8/01 (SG) PER LEROY MINTONS CONFIRMATION. May 4, 2001 July 25, 2005 1,543 days
Brent Elementary School FM-200110026 01 7/25/05 BRENT FIRST (1ST) FLOOR - KITCHEN REPAIR FREEZER - VERY NOISY AND WHEN CUT OFF AND TURNED BACK ON, CAUSES BREAKER TO TRIPS. (SEND TO FOOD SERVICES) May 11, 2001 July 25, 2005 1,536 days
Garnet-Patterson MS FM-200110525 01 7/25/05 GARNET-PATTERSON KITCHEN SURVEY AND INSTALL INDEPENDENT HOT WATER HEATER FOR KITCHEN AREA. WP-200108858 May 17, 2001 July 25, 2005 1,530 days
Bowen Elementary School FM-200103493 01 7/25/05 BOWEN BOILER ROOM REPAIR STEAM LEAK IN TUNNEL ON SUPPLY LINE. 2 " PIPE. February 10, 2001 July 25, 2005 1,626 days
Moten Elementary School FM-200108613 01 7/25/05 MOTEN FOUR (4TH) FLOOR - ROOMS#415A, 418 AND 420 ,421,417,413,&4 TH FLOOR HALLWAY OF THE OLD AND NEW WING. 1) ASEBESTOS ASSESSMENT REQUIRED 2) CEILING TILE REQUESTED BY RICK ELEY AFTER A SITE VISIT WITH JEFFERY EDWARDS (4/18/01). Code A-clear for repair by Horne Engineer ( Shoron Voss ) 0n 3/20/02 (CEB) April 18, 2001 July 25, 2005 1,559 days
Spingarn High School FM-200108410 01 7/25/05 SPINGARN S. TUNNEL 1. ASBESTOS ASSESSMENT IS REQUIRED 2. REPAIR LEAKING 1" LINE, REPAIR LEAKING 2" LINE LEAKING IN THREE PLACES, REPAIR LEAKING 3/4" DRIP LEG. April 13, 2001 July 25, 2005 1,564 days
Spingarn High School FM-200110420 01 7/25/05 (SPINGARN) HEALTH CODE VIOLATION: KITCHEN: NEED GARBAGE DISPOSAL IN THE CAFETERIA TO DISPOSE OF FOOD WASTE. May 16, 2001 July 25, 2005 1,531 days
Spingarn High School FM-200110438 01 7/25/05 SPINGARN 1) ASBESTOS ASSESSMENT REQUIRED 2) EA ENGINEERING NEEDS LOCKSMITH SHOP ASSISTANCE FOR 6 MONTH PERIODIC SUVEILLANCE FOR THRU OUT THE BUILDING FRIDAY, MAY 18, 2001 AND MONDAY, MAY 21, 2001, MAY HAVE TO DRILL OUT LOCKS. POC: MR. ABDULLAH 202-438-7124 ( CODE A FOR WORK PERMIT ONLY) May 16, 2001 July 25, 2005 1,531 days
Draper Elementary School FM-200108818 01 7/25/05 DRAPER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 20, 2001 July 25, 2005 1,557 days
Macfarland Middle School FM-200103516 2/12/01 7/25/05 MACFARLAND EXTERIOR REPAIR OR REPLACE EXTERIOR LIGHTS ON THE END OF BUILDING NESR THE BALL PARK. STUDENTS ENTER AND EXIT DURING NIGHT PROGRAMS. February 12, 2001 July 25, 2005 1,624 days
Draper Elementary School FM-200103572 01 7/25/05 DRAPER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. CHECK RETURN STORAGE TANK FOR LEAK. February 13, 2001 July 25, 2005 1,623 days
Bowen Elementary School FM-200103491 01 7/25/05 BOWEN 2ND FL ELECTRIC ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR STEAM LEAK INSIDE WELL. NEW SIDE OF BLDG. February 10, 2001 July 25, 2005 1,626 days
Ballou Senior High School FM-200109571 01 7/25/05 (BALLOU-STAY) 1. ASBESTOS ASSESSMENT REQUIRED. SUB-BASEMENT/ALL CLASSROOMS: ELECTRICAL UPGRADE IN NEEDED ON LIGHTS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/09/01. May 3, 2001 July 25, 2005 1,544 days
Reed LC FM-200109614 01 7/25/05 REED BASEMENT CHILLER ROOM CHILL H20 PUMP #1 GASKET OR SEELS NEED TO BE REPLACED. PUMP IS CORRODING AND LEAKING. WP-200108831 May 7, 2001 July 25, 2005 1,540 days
Bell High School FM-200109615 01 7/25/05 BELL ROOF PROVIDE ELECTRICAL SERVICE TO RECEPTICAL ON ROOF NEAR COOLING TOWER, 120 VOLTS. UNABLE TO LOCATE POWER SOURCE. REPAIR ELEC. RECPTICAL, IF NEEDED. Requester Phone: 576-5316 Requestor Phone: 576-5316 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/03/01. April 16, 2001 July 25, 2005 1,561 days
Davis Elementary School FM-200110406 01 7/25/05 DAVIS OUTSIDE REPAIR TWO (2) EXTERIOR LIGHT FIXTURES. NO ASBESTOS IMPACT!! DANNY HUDSON: 576-8045 May 16, 2001 July 25, 2005 1,531 days
Coolidge High School FM-200110581 01 7/25/05 COOLIDGE STAIRWELLS - 2,3,4, AND 5 1) REPLACE (8) DOOR GLASSES ON THE FOLLOWING STAIRWELLS. May 18, 2001 July 25, 2005 1,529 days
Coolidge High School FM-200109916 01 7/25/05 COOLIDGE REPAIR LIGHTS ON FRONT OF SCHOOL PROVIDE NEW POWER SOURCE AND DISCONNECT FROM EXISTING HALLWAY CIRCUIT. May 10, 2001 July 25, 2005 1,537 days
Coolidge High School FM-200109577 01 7/25/05 COOLIDGE GROUND FL. B101 OFFICE 1. ASBESTOS ASSESSMENT REQUIRED. PROVIDE DEDICATED ELECTRICAL POWER SUPPLY LINE FOR AC UNIT THAT IS TO BE INSTALLED IN OFFICE WINDOW. Requester Phone: 576-6150 Requestor Phone: 576-6150 Asbestos Code A - Clear for repairs on 03/06/03. Horne Engineering -Edward Rodriguez (RG 03/07/03) April 16, 2001 July 25, 2005 1,561 days
Nalle Elementary School FM-200108269 01 7/25/05 NALLE SECOND (2ND) FLOOR - CLASSROOM 226 PARENT RESOURCE ROOM 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR LEAKING ROOF IN THIS CLASS ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/12/01. April 12, 2001 July 25, 2005 1,565 days
Nalle Elementary School FM-200109539 01 7/25/05 (NALLE) 1. ASBESTOS ASSESSMENT REQUIRED. MAIN ENTRANCE. CUSTODIAN STATES, KEYS ARE MISPLACED FOR MAIN ENTRANCE DOORS. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: RAY AGNANT May 3, 2001 July 25, 2005 1,544 days
Cooke H.D. Elementary School FM-200109706 01 7/25/05 COOKE, H.D. PLAYGROUND LOCATION: SMALL PLAYGROUND AREA, BROKEN SWINGS TWO (2) NEEDS REPAIR OR REPLACE May 8, 2001 July 25, 2005 1,539 days
Beers Elementary School FM-200508109 05 7/25/05 Beers Second Floor - Building (3) 1) Slop sink leaking, can not cut water off, water is flooding the floor. July 20, 2005 July 25, 2005 5 days
Woodson High School FM-200108532 01 7/25/05 (H.D. WOODSON) 3RD FLOOR/GIRLS RESTROOM: WATER BACKING UP THROUGH SINK AND DRINKING FOUNTAIN, FLOODING THE FLOORS. # DO NOT REMOVE FROM WALL WITHOUT AN ABESTOS ASSESSMENT. April 17, 2001 July 25, 2005 1,560 days
Peabody Elementary School FM-200103032 01 7/25/05 PEABODY THIRD FLOOR - MATERIAL ROOM II 1) ASBESTOS ASSESSMENT REQUIRED (CEILING) 2) PLASTER ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/18/01. February 6, 2001 July 25, 2005 1,630 days
Garfield ES FM-200103402 9/01 7/25/05 GARFIELD LL1 - BOYS BATHROOM A COMPLETE RENOVATION IS NEEDED DUE TP PLUMMING PROBLEMS TO SINK, TOILETS AND URINALS. BATHROOM HAS NOT BEEN USE SINCE AUGUST. Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Bipin Nanavaty (RG 03/11/03) February 9, 2001 July 25, 2005 1,627 days
Garfield ES FM-200103399 9/01 7/25/05 GARFIELD 1ST & 2ND FLOOR MAIN BLDG. 73 WINDOWS NEED SERVICING BALLAST NEEDED. ALL WINDOWS ARE VERY, VERY HARD TO OPEN. BSM HAS LIST. February 9, 2001 July 25, 2005 1,627 days
Garrison ES FM-200201279 02 7/25/05 (GARRISON) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ EAST WING UNDER STAIR CASE VERMONT AVE.BACK PLAYGROUND REPLACE EXIT DOORS, DOORS ARE DETERIORATED. January 17, 2002 July 25, 2005 1,285 days
Garrison ES FM-200201288 02 7/25/05 (GARRISON) 2ND FLOOR/ ROOMS 201 AND 203 REPAIR THUMB KNOBS. January 17, 2002 July 25, 2005 1,285 days
Garrison ES FM-200202098 02 7/25/05 (GARRISON) ASBESTOS ASSESSMENT REQUIRED NEED ASBESTOS CHECK OF THE EAST-SIDE STAIRS & VERMONT AVENUE WEST-SIDE STAIRS IN PREPARATION FOR PAINTING. ASBESTOS CODE A-CLEAR FOR REPAIR ON 2/04/02 BY HORNE ENGINEER: EDWARD RODRIGUEZ LEAD CODE B- DO NOT SCRAPE CHIP OR PEEL ANY OF THIS PAINT SURFACE RE-PAINT OVER ONLY. January 30, 2002 July 25, 2005 1,272 days
Garrison ES FM-200203358 02 7/25/05 (Garrison) 1. Asbestos Assessment Required. Computer Lab: Pan cake plug on floor, remove. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/26/02 HORNE ENGINEER: SHARON VOSS February 22, 2002 July 25, 2005 1,249 days
Garrison ES FM-200203564 02 7/25/05 (Garrison) Asbestos Assessment Required 2nd Floor Computer Lab Room 202 Furnish & install power-plug poles for the computer lab [Rm. 202] CODE A- CLEAR FOR REPAIR BY HORNE ENGINEER (Z MAHMOOD) ON3/01/02 (CEB) February 27, 2002 July 25, 2005 1,244 days
Garrison ES FM-200204481 02 7/25/05 Garrison 2nd Fl. Room 210 West Wing 1. Asbestos assessment required. 2. Replace thermostat on unit heater in room 210 "room overheating". March 15, 2002 July 25, 2005 1,228 days
Garrison ES FM-200206822 02 7/25/05 Multi-purpose Room Repair broken circuit-breaker. Multi-purpose area is too dark for lunch to be served. April 29, 2002 July 25, 2005 1,183 days
Garrison ES FM-200206824 02 7/25/05 Asbestos Assessment Reqd. Install 220V lines in the following areas to support A/C units for summer school session: Health Suite; Library II, Rooms 221 & 222. Code A-clear for repair by Horne Engineer by (Sam Ebrahim ) on 5/01/02( CEB ) April 29, 2002 July 25, 2005 1,183 days
Garrison ES FM-200211135 02 7/25/05 Garrison 1. Asbestos Assessment Reqd. 1t Floor Room 105 [Ms. Iverson's Classroom] 2. Install an electrical outlet in room 105 by the sink area. Asbestos/Lead Code A-clear for repair by Horne Engineer (Shephen Caldwell) on 7/16/02 Charles E. Buchanan DPCS July 12, 2002 July 25, 2005 1,109 days
Beers Elementary School FM-200109387 01 7/25/05 BEERS SECOND (2ND) FLOOR - BLDG. #1/SOCIAL WORKER ROOM 1) ASBESTOS ASSESSMENT REQUIRED 2) ELECTRICAL: SUPPLY POWER FOR AIR CONDITIONER 208 VOLTS, A/C MOUNTED IN WINDOW. (HEALTH HAZARD). May 1, 2001 July 25, 2005 1,546 days
Garfield ES FM-200108525 01 7/25/05 (GARFIELD) 1ST FLOOR/MAIN BUILDING: 1. ASBESTOS ASSESSMENT REQUIRED. HEAT PIPE IN HEALTH SUITE, & ROOMS #1-A, 1-B, 1-C, 1-3, & 1-G NEED TO BE SCRAPED AND RE-PAINTED. PAINT IS PEELING AND FALLING. April 17, 2001 July 25, 2005 1,560 days
Garrison ES FM-200216743 02 7/25/05 Garrison Paint interior doors same color. Need work order permit. September 6, 2002 July 25, 2005 1,053 days
Ferebee-Hope Elementary School FM-200109820 01 7/25/05 FEREBEE-HOPE 3RD FL. UNIT #1 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE COIL UNIT #1 LEAKING FROM CEILING. May 9, 2001 July 25, 2005 1,538 days
Garnet-Patterson MS FM-200457189 /04 7/26/05 Garnet-Patterson Boiler Room Boilers #1 thur #5 check the pump control. Water is not going into Boilers. October 20, 2004 July 26, 2005 279 days
Woodson High School FM-200105991 01 7/26/05 WOODSON, HD GROUND REPLACE DOORS. HOSPITALITY SUITE DOUBLE DOORS 32 x 81. AUDITORIUM DOUBLE DOORS 36 x 81 3/4, EXTERIOR 35 3/4 x 88, WEIGHT ROOM 31 3/4 x 81 3/4 , 31 3/4 x 81 3/4 ,MAIN LOBBY BY GYM DOUBLE DOORS 36 x 81. POOL DOORS INSIDE 5 SETS 35 #/4 x 81. ACTIVITY ROOM 2 SETS DOUBLE DOORS 31 #/4 x 81 3/4. Asbestos Code A - Clear for repairs on 03/06/03. Horne Engineering - Bipin Nanavaty (RG 03/07/03) March 16, 2001 July 26, 2005 1,593 days
Ballou Senior High School FM-200105849 01 7/26/05 BALLOU FITNESS CTR. 122 REPLACE MISSING AHU MOTOR (CEILING AREA) NOTE: AHU MOTR WAS TAKEN AWAY FROM SITE 2 YRS. AGO AND NEVER REPLACED (MECH. MAINT. SHOP). March 15, 2001 July 26, 2005 1,594 days
Merritt Middle School FM-200334812 03 7/26/05 Merritt East entrance to building Replace damage ceiling tile and grides by fire department. Asbestos Code A - Clear for repairs on 09/12/03. Horne Engineering - Edward Rodriguez (RG 09/16/03) August 11, 2003 July 26, 2005 715 days
Garnet-Patterson MS FM-200457190 /04 7/26/05 Garnet-Patterson Boiler Room Replace 1/4" copper line on Vacuum pump cooling line for pumps. October 20, 2004 July 26, 2005 279 days
Kimball Elementary School FM-200106417 /01 7/26/05 KIMBALL OUTSIDE WE NEED A FENCE PUT AROUND THE BUILDING, TO SECURE PROPERTY FROM TRASH, PETS, OFF THE GRASS OUTSIDE. DAMAGE TO PROPERTY. FOR MAINTAINING THE GROUNDS. 4 FT. CHANGE LINK FENCE. March 21, 2001 July 26, 2005 1,588 days
Roosevelt High School FM-200457191 /04 7/26/05 Roosevelt Boiler Room Boiler #3 Check short in control panel fuse holder. October 20, 2004 July 26, 2005 279 days
Eliot Junior High School FM-200105847 01 7/26/05 ELIOT 1ST FLOOR REMOVE & REPLACE BROKEN TILE OUTSIDE BOYS GYM FLOOR (9x9) . TILE DAMAGED BY LEAKING UNIVENT. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/15/01. HORNE ENGINEERING - ROGER KAGER March 15, 2001 July 26, 2005 1,594 days
Raymond Elementary School FM-200507609 05 7/26/05 First floor, New Wing/Boys' & Girls' toilet. Repair leaking toilets in boys' and girls' restroom water is leaking on the floor. July 8, 2005 July 26, 2005 18 days
Ballou Senior High School FM-200105844 01 7/26/05 BALLOU AUTO SHOP CEILING REPLACE (4) FOUR SHAFT BEARING ASSEMBLIES ON (2) TWO CEILING A.H.U. INFO: 1" SHAFT BEARINGS (4) FOUR. NOTE: MECHANICAL MAINTENANCE DIVISION HAS SAMPLE THAT WAS TAKEN AWAY AT SITE ALSO AHU IS 15 FT. IN THE CEILING AREA. March 15, 2001 July 26, 2005 1,594 days
Shaw JHS FM-200453797 04 7/26/05 Shaw Auditorium Replace broken fan shaft for air handler unit #2 in Auditorium Mach. room. September 1, 2004 July 26, 2005 328 days
Truesdell Elementary FM-200106470 01 7/26/05 TRUESDELL FIRST (1ST) FLOOR - KITCHEN 1) ASBESTOS ABATEMENT AND RESTORE REQUIRED 2) THE CEILING PAINT IS PEELING AND NEED TO REPAINT. 3) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/28/01. March 22, 2001 July 26, 2005 1,587 days
Hardy Middle School FM-200457186 /04 7/26/05 Filmore- Hardy Boiler Room Asbestos assessment may be required. Repair or replace rupture return line in turnell area. (Heating) Hot !!!! October 20, 2004 July 26, 2005 279 days
Roosevelt High School FM-200105550 01 7/26/05 ROOSEVELT FIRST (1ST), SECOND (2ND), THIRD (3RD) AND GROUND FLOORS FLOOR, REMOVE GRAFFITI FROM WALLS, DOORS, STAIRWALL, RESTROOM. THROUGH - OUT THE BUILDING (INTERIOR) March 12, 2001 July 26, 2005 1,597 days
Reed LC FM-200106423 3 3/21/01 7/26/05 REED PLAYGROUND - SIDE OF 18TH STREET SUPPLY AND INSTALL HANDRAIL NEAR TENNIS COURTS March 21, 2001 July 26, 2005 1,588 days
Malcolm X ES FM-200105815 14/01 7/26/05 MALCOLM-X REPAIR ELECTRICAL SERVICE TO OUTSIDE SCHOOL SIGN. March 14, 2001 July 26, 2005 1,595 days
Tubman Elementary School FM-200127035 02 7/26/05 (TUBMAN) 3RD FLOOR/ ROOM #302 CLASSROOM ENTRANCE DOOR NEEDS TO BE ALIGNED WITH THE DOOR FRAME. January 8, 2002 July 26, 2005 1,295 days
Shepherd ES FM-200457222 /04 7/26/05 (Sheperd) HEALTH CODE VIOLATION: Kitchen: Keep exterior roof clean. October 21, 2004 July 26, 2005 278 days
Hart Middle School FM-200105889 01 7/26/05 HART BASEMENT WOOD SHOP REPLACE 1/4" PIPE ABOUT 3" LONG ON BLEED VALVE ON COIL IN UNIVENT IN WOOD SHOP PIPE IS LEAKING (HOT WATER BOILERS). March 15, 2001 July 26, 2005 1,594 days
Shaw JHS FM-200508731 05 7/26/05 Shaw First fl Millieium Rm Repair Lighting in the Area July 26, 2005 July 26, 2005 0 days
Garfield ES FM-200105391 01 7/26/05 GARFIELD ASBESTOS AND PAINT ASSESSMENT AUDITORIUM PLASTERING NEEDED IN AUDITORIUM NEAR EXIT DOORS WALL CRUMBLING DUE TO WATER DAMAGE, AND PAINTING NEEDED ALSO. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/26/01 BY HORNE ENGINEER: TROY WILCOME March 9, 2001 July 26, 2005 1,600 days
Spingarn High School FM-200227548 03 7/26/05 Eastern Tunnel-Eaatside & 21B Replace approximately 7" (Ft) of 1-1/2" steam raiser in tunnel and in B31the piping is corroded and leaking bad. POC: Sylvia Grimes March 24, 2003 July 26, 2005 855 days
Hine JHS FM-200105875 01 7/26/05 HINE 1ST FL. ROOM 107 UNIVENT NEEDS TO BE HARD WIRED FROM PANEL BOX TO HEAT UNIT. (ELECTRICIANS) Requester Phone: 698-1750 Requestor Phone: 698-1750 March 15, 2001 July 26, 2005 1,594 days
Moten Elementary School FM-200105685 01 7/26/05 MOTEN 4TH FLOOR SCRAPE, PLASTER AND PAINT CORRIDOR AT SOUTH END OF BUILDING. Lead Code A-clear for repair by Horne Engineer (Bipin Nanavaty) 0n 3/22/02 (CEB Do not scrape, chip, or peel any of this painted surface-- repaint over only. March 13, 2001 July 26, 2005 1,596 days
Nalle Elementary School FM-200105753 01 7/26/05 NALLE FIRST (1ST) FLOOR - EXTERIOR DOOR BY PLAYGROUND REPLACE EXTERIOR DOOR ON 1ST FLOOR LEAVING UNTO PLAYGROUND. DOOR NEEDS REPLACING DUE TO VANDALISM. EMERGENCY. FIRE CODE Asbestos Code A - Clear for repairs on 03/07/03. Horne Engineering - Philp Connolly (RG 03/10/03) March 13, 2001 July 26, 2005 1,596 days
Bancroft Elementary School FM-200106284 01 7/26/05 BANCROFT 1ST FL. ROOM 212 MAIN BLDG. INSTALL NEW VARIABLE SPEED CONTROL UNIT TO CONTROL UNIVENT HEATER MOTOR. EXISTING CONTROL KNOB & ITS MOUNT ARE BROKEN OFF: HERMAN NELSON, MODEL #1001DJ, 60 CY, 110/220 VOLTS. March 21, 2001 July 26, 2005 1,588 days
Slowe Elementary School FM-200508336 05 7/26/05 Slowe School Repair 20 feet of fence on school hill July 21, 2005 July 26, 2005 5 days
Browne Junior High School FM-200106102 01 7/26/05 BROWNE 2ND FLOOR ROOM 211 BURN ROOM. REPAIR WALLS, CEILING AND FLOOR. NEED NEW LIGHTS AND ELECTRICAL OUTLETS. ROOM HAS BEEN VACANT FOR TWO YEARS. March 19, 2001 July 26, 2005 1,590 days
Moten Elementary School FM-200107326 01 7/27/05 MOTEN NEW WING AND FIRST FLOOR BATHROOM (GIRLS AND BOYS) 1) INSTALL PARTITIONS. SCOPE- TO SUPPLY ALL LABOR,MATERIALS,EQUIPMENT AND SUPERVISION TO PERFORM WORK. HRGM CORP. THE PARTITION REPLACEMENT IN COMPLETED. Asbestos Code A - Clear for repairs on 03/06/03. Horne Engineering - Bipin Nanavaty (RG 03/07/03) April 3, 2001 July 27, 2005 1,576 days
Wilkinson ES FM-200107368 /4/01 7/27/05 WILKINSON FIRST FLOOR ASBESTOS ASSESSMENT REQUIRED. REPLACE DOOR CLOSURES. April 4, 2001 July 27, 2005 1,575 days
Woodson High School FM-200106652 01 7/27/05 WOODSON, H.D. 1) ASBESTOS AND LEAD ASSESSMENT REQUIRED 2) COSMETOLOGY LAB - SEE SCOPE OF WORK. CEILING, DOORS, FLOOR, PIPES, PLASTER AND WALLS.. TIMKLINE (202) 253-2384 RAJ SKUKLA (202) 329-8047 HRGM CONTRACTOR (202) 889-8400 Cole A for asbestos/lead and clear for repair by Horne Engineer on 3/12/03 Charles Buchanan March 26, 2001 July 27, 2005 1,584 days
Takoma Educational Center FM-200106818 01 7/27/05 TAKOMA (EMERGENCY) 3RD FLOOR -200 GIRLS RESTROOM REPLACE COMMODE . THE COMMODE IS POSSIBLE CRACK CAUSING THE CEILING ON THE 2ND FLOOR TO BE DAMAGE. March 28, 2001 July 27, 2005 1,582 days
Clark Elementary School FM-200107549 01 7/27/05 (CLARK) (1) ASBESTOS ASSESSMENT REQUIRED. TOILET ROOM: REPAIR TOILET ROOM LOCKS, DOOR UNABLE TO CLOSE. April 6, 2001 July 27, 2005 1,573 days
Takoma Educational Center FM-200332798 03 7/27/05 (Takoma) Through-Out the Building: Plumbing work is requested for all restrooms due to new school year coming in effect, and water fountains. 1st fl. #55, 2nd fl. #127, 128, 148, & 147. 3rd fl. #199, 200, 207, 221 & 222. Gym #87, & 94. Water fountains #83 & 101. July 1, 2003 July 27, 2005 757 days
Powell Elementary School FM-200106968 01 7/27/05 POWELL BOILER ROOM REPLACE THREE (3/4") GATE VALVES AND FEED WATER REGULATOR THAT FEEDS THE HOT WATER HEATING SYSTEM. VALVES ARE BROKEN IN THE CLOSED POSITION. BY-PASS VALVE IS CRACKED TO KEEP THE SYSTEM FULL. NO INFORMATION IS ON THE REGULATOR. ASBESTOS CODE A-CLEAR FOR REPAIR ON 12-10-01 BY HORNE ENGINEER : TROY WILCOME March 30, 2001 July 27, 2005 1,580 days
Seaton Elementary School FM-200106980 01 7/27/05 SEATON ROOF ROOF LEAKING IN ALL PURPOSE ROOM. HEAVY RAIN CODE A - ASBESTOS ABATED ON 7/9/01 (SG) PER LEROY MINTONS CONFIRMATION. March 30, 2001 July 27, 2005 1,580 days
Tubman Elementary School FM-200444776 04 7/27/05 Tubman First floor Rec center Replace missing door knobs (2). Asbestos Code A - Clear for repairs on 03/08/04. Horne Engineering - Bjame Smuth (RG 03/09/04) March 3, 2004 July 27, 2005 511 days
Johnson JHS FM-200107180 01 7/27/05 JOHNSON GYM FURNISH ELECTRICAL OUTLETS AND LINES FOR SIX AIR CONDITIONS FOR THE GYM. INSTALL SIX AIR CONDITIONS FOR THE GYM. ASBESTOS CODE A- CLEARED FOR REPAIRS ON 06/05/01. April 2, 2001 July 27, 2005 1,577 days
Oyster Elementary School FM-200106960 01 7/27/05 OYSTER 1) CLASSROOM - 101 DOOR WONT CLOSE PROPERTY. REPAIR ALIGNMENT ON DOOR. 2) LIBRARIAN ROOM BROKEN DOOR NEEDS CLOSER. FIRE CODE VIOLATION Asbestos Code A - Clear for repairs on 03/01/03. Horne Engineering - Richard Byrd (RG 03/27/03) March 29, 2001 July 27, 2005 1,581 days
Coolidge High School FM-200107041 01 7/27/05 COOLIDGE outside of auditorium UNSTOP EXTERIOR DRAINS ON THE NORTHEAST & NORTHWEST SIDE OF AUDITORIUM. March 30, 2001 July 27, 2005 1,580 days
Amidon Elementary School FM-200107755 01 7/27/05 AMIDON HALLWAYS REPLACE ALL HALLWAYS LIGHTS ON BOTH HALLS OF SECOND FLOOR. (ELS) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/15/01. HORNE ENGINEERING - SHERYLL JAMES April 7, 2001 July 27, 2005 1,572 days
Ronald H. Brown MS FM-200107512 01 7/27/05 RON BROWN ASBESTOS ASSESSMENT REQUIRED BOY BATHROOM - 2ND AND 3RD FLOOR 1) 2ND FLOOR - PIPE LEAKING BEHIND WALL. (URINAL) 2) 3RD FLOOR - URINAL DRAINS VERY SLOW, KEEPS FLOODING FLOOR. April 6, 2001 July 27, 2005 1,573 days
Sousa Middle School FM-200106587 01 7/27/05 SOUSA MECHANICAL EQUIPMENT ROOM REPLACE CIRCULATING PUMP NOT WORKING. GYM AREA NEEDS HEAT. BELL GOSSETT 209157000, SERIAL #189101 225 FH58. March 26, 2001 July 27, 2005 1,584 days
Maury Elementary School FM-200506683 05 7/27/05 Maury ES Install window air conditioning unit computer room June 13, 2005 July 27, 2005 44 days
Roosevelt High School FM-200107470 01 7/27/05 ROOSEVELT CUPOLA 1) ERECT SCAFFOLD ON EXTERIOR CUPOLA TO ACCESS FACADE (60) FEET. 2)REMOVE ALL SIDING AND REPAIR ALL DETERIORATED FACADE. 3) INSTALL NEW HARDY PLANK SIDING WHERE APPLICABLE AND REPAIR ALL VISIBLE DEFECTS ON DAMAGED WOOD. 4) PREP ALL SURFACES TO INCLUDE CAULKING AND PRIME WITH ONE COAT OF PRIMER AND (2) COATS TO ALL OTHER SURFACES. 5) REPAIR ANY DAMAGE TO SURFACE TO SLATE ROOF SIX FEET OUT FROM ROOF. April 5, 2001 July 27, 2005 1,574 days
Tubman Elementary School FM-200106655 01 7/27/05 TUBMAN 1) ASBESTOS ASSESSMENT REQUIRED 2) INSTALL WINDOW A/C IN THE FOLLOWING AREAS: TEACHERS LOUNGE, HEALTH SUITE, ASSISTANT PRINCIPALS OFFICE, KINDERGARTEN AND COMPUTER ROOM. HRGM CONTRACTOR: RAJ SKUKLA (202 329-8047 TIM KLINE (202) 253-2384 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/19/01. March 26, 2001 July 27, 2005 1,584 days
Eastern High School FM-200106737 01 7/27/05 EASTERN SUB-BASEMENT - KITCHEN REPLACE LIGHT FIXTURE (4) TUBE FLORESENT IN KITCHEN FIRE CODE VIOLATION ASBESTOS CODE A-CLEAR FOR REPAIR ON 12/12/01 BY HORNE ENGINEER: SHARON VOSS March 27, 2001 July 27, 2005 1,583 days
Benning Elementary School FM-200106937 /01 7/27/05 BENNING LEARNING CENTER #1 1ST FLOOR ASSESS PLASTER & PEELING PAINT ON WALL IN MEDIA ROOM. WATER IS PENETRATING WALL FROOM OUTSIDE CAUSING DETERIORATION. March 29, 2001 July 27, 2005 1,581 days
Meyer Elementary School FM-200106904 01 7/27/05 MEYER KITCHEN SIX LIGHTS IN THE KITCHEN AREA WILL NOT COME ON. ENTIRE ROW OF LIGHT TUBES ARE OUT DIRECTLY OVER SERVING TABLES. BULB & BALLASTS HAS BENN CHANGED. NEED A ELECTRICIAN TO COME OUT. Code A-clear for repair by Horne Engineer ( Sharon Voss ) 0n 3/22/02 (CEB March 29, 2001 July 27, 2005 1,581 days
Savoy Elementary School FM-200508823 05 7/27/05 (Savoy) Kitchen. Install kline drain twist handle on pot sink in kitchen. July 27, 2005 July 27, 2005 0 days
Tubman Elementary School FM-200453272 04 7/28/05 (Tubman) 1st Floor/South Exit Door: Exit door is metal No asbestos Repair door frame, and closer. Cole A-clear for repair by DCPS Charles Buchanan on 9/01/04 August 24, 2004 July 28, 2005 338 days
Tubman Elementary School FM-200448445 04 7/28/05 Tubman First floor south corridor exit door Exit door will not close shut when exiting. Asbestos Code A - Clear for repairs on 06/03/04. Horne Engineering - Tony Marcolin ( RG 03/06 ) May 25, 2004 July 28, 2005 429 days
Tubman Elementary School FM-200445040 04 7/28/05 Tubman First floor hallway Install bulletin board (2) in cafeteria hallway. Asbestos Code A - Clear for repairs on 03/09/04. Horne Engineering - Philp Connolly (RG 03/09/04) March 9, 2004 July 28, 2005 506 days
Cardozo High School FM-200507680 05 7/28/05 Cardozo SHS Rooms# 116 & 120 1. Survey window a/c units - units are 115amp/208volts 2. Units will be upgraded to 20amps/230volts July 12, 2005 July 28, 2005 16 days
Harris, C.W. ES FM-200454148 04 7/28/05 Harris, C.W. Room #149 Frabricate and instll drip pan in univent to collect condensation that drips from coil. September 9, 2004 July 28, 2005 322 days
Cardozo High School FM-200507698 05 7/28/05 Cardozo SHS, Rm. 117, 217, 219, 305,307, 309, 311, 316, 320, 315, 317, 1. Electrical work is required for each room. 2. Install 1 ---- 20 amps - 230 volt window air conditioner units in each room listed 3. Room # 300 install 2 - 20amp / 230volt window a/c units 3. Room # 116 & 120 replace 2 - 24,000 btu window a/c units Asbestos Code A - Clear for repairs on 07/21/05. Tidewater - Tony Marcolin (RG 07/26/05) July 6, 2005 July 28, 2005 22 days
Thomas Elementary School FM-200454214 04 7/28/05 Nevel Thomas Exterior Grounds 1) Set up Air Pollution Equipment. September 9, 2004 July 28, 2005 322 days
Tyler Elementary School FM-200509058 05 7/29/05 repair down fence on baseball field July 29, 2005 July 29, 2005 0 days
Randle-Highlands ES FM-200508787 05 7/29/05 Randle-Highland Emergency !!! Exterior Grounds 1) Cap field pole knocked over by truck. July 27, 2005 July 29, 2005 2 days
Hardy Middle School FM-200508819 05 7/29/05 (Hardy) Main entrance door. Repair or Replace lock on main entrance door staff are unable to lock door and secure building. July 27, 2005 July 29, 2005 2 days
Randle-Highlands ES FM-200508818 05 7/29/05 Randle-Highlands Exterior Grounds Repair Exposed Electrical Wires July 27, 2005 July 29, 2005 2 days
Savoy Elementary School FM-200447470 04 7/29/05 Savoy EMERGENCY First floor kitchen J-trap needs to be replaced under sink in kitchen, has been labeled health hazard by health inspector. Also leaking ceiling in kitchen is declared health hazard by the health inspector. Asbestos Code A - Clear for repairs on 05/06/04. Horne Engineering - Philp Connolly (RG 05/06/04) May 4, 2004 July 29, 2005 451 days