Urgent Repair Requests Closed in August 2006 (99)
| School |
Description |
Open Date |
Close Date |
Time Elapsed |
| Langdon Elementary School |
FM-200446900 04 8/1/06 (Langdon) !!!VERY URGENT!!! Asbestos Assessment Required. 2nd Floor/Learning Center #2-A: Window that is supported by iron handles, attempting to fall. Request a welder to weld the damaged handles. Asbestos Code A - Clear for repairs on 04/20/04. Horne Engineering - Tony Marcolin (RG 05/03/04) |
April 20, 2004 |
August 1, 2006 |
833 days |
| Amidon Elementary School |
FM-200513644 05 8/1/06 Amidon Very Urgent Re-pave front concrete steps it has deteriorated. |
October 7, 2005 |
August 1, 2006 |
298 days |
| Amidon Elementary School |
FM-200512965 05 8/1/06 (Amidon) "Urgent" Exterior of building, Playground area. Repair rod iron gate and door to gate, there is a concern for the childrens safety. |
September 21, 2005 |
August 1, 2006 |
314 days |
| Eaton Elementary School |
FM-200506607 05 8/1/06 Eaton Boiler Room A/C system need to be charge. System is down. Urgent !!!!! |
June 10, 2005 |
August 1, 2006 |
417 days |
| John Burroughs ES |
FM-200456023 04 8/1/06 Burroughs First floor multi purpose VENTs Heater grates are broken need repairing. Code A - clear for repairs as of 10/12/04 safety Sylvia |
September 29, 2004 |
August 1, 2006 |
671 days |
| West Elementary School |
FM-200506598 05 8/1/06 West Boiler Room Repair or replace purge pump on chiller. Pump continously being reset, when in operation. Note: No window in school. Urgent !!!!! |
June 10, 2005 |
August 1, 2006 |
417 days |
| Ross Elementary School |
FM-200516840 /05 8/1/06 First floor, Stairwell "Urgent" Reattach handrail to wall in stairwell heading from main entrance to basement. Note: The principal called to emphasize that this is a safety problem. Asbestos Code A - Clear for repairs on 12/21/05. DCPS Safety - Richard Gibson (RG) |
December 21, 2005 |
August 1, 2006 |
223 days |
| West Elementary School |
FM-200506634 05 8/1/06 West Boiler Room Check chiller, Chiller is running but not cooling. Urgent !!! |
June 12, 2005 |
August 1, 2006 |
415 days |
| Hart Middle School |
FM-200446178 04 8/1/06 (Hart) !!!VERY URGENT!!! Asbestos Assessment Required. Second story window grate is hanging by one screw and when the wind blows it rocks back and foward. This issue is a great risk to our students, staff, and parents while on the playground. This is a emergency situation and need to be handle as soon as posible. Asbestos Code A - Clear for repairs on 04/22/04. DCPS Safety - Richard Gibson (RG) |
March 29, 2004 |
August 1, 2006 |
855 days |
| Emery Elementary School |
FM-200515074 05 8/1/06 Exterior of building. "Urgent" Reinstall handrail in front of building near gate entrance. |
November 3, 2005 |
August 1, 2006 |
271 days |
| Young Elementary School |
FM-200620746 06 8/2/06 Young Boiler Room Repair or replace domestic hot water heater and 1" gas line going to heater. No hot water in Building. Urgent !!! |
April 3, 2006 |
August 2, 2006 |
121 days |
| Seaton Elementary School |
FM-200506860 05 8/2/06 (Seaton) Very Urgent!!!! First Floor - Room 100A 1) Repair window its broken, the latch is the only thing keeping the window closed. 2) Replace glass its also broken 3) Top and bottom panes are also broken ( The window has a window guard ) |
June 16, 2005 |
August 2, 2006 |
412 days |
| Seaton Elementary School |
FM-200454921 04 8/2/06 (Seaton) URGENT First floor room 104 and 100A Window guards missing back of building. One guard room 104 and one guard 100A We have no outside lights. |
September 16, 2004 |
August 2, 2006 |
685 days |
| Rudolph Elementary School |
FM-200203648 02 8/2/06 (Rudolph) ***Urgent*** Basement Room 8 Fabricate and install exterior window guards to prevent repeated entry from vandals. |
February 28, 2002 |
August 2, 2006 |
1,616 days |
| Tubman Elementary School |
FM-200618759 06 8/4/06 Very Urgent: Unclog toilets in the boys restroom near the cafeteria. |
February 16, 2006 |
August 4, 2006 |
169 days |
| Watkins Elementary School |
FM-200508421 05 8/6/06 (Watkins) "Urgent" Floors 1, 2, 3, 4. Need plumbers to unstop all custodian sinks on the 1st through 4th floors, also unstop sink in teachers' restroom. |
July 22, 2005 |
August 6, 2006 |
380 days |
| Stanton Elementary School |
FM-200228394 03 8/7/06 Stanton - URGENT Third floor boys bathroom Three urinals in boys bathroom is stopped up. Need to be unstopped. |
April 7, 2003 |
August 7, 2006 |
1,218 days |
| Stanton Elementary School |
FM-200447814 04 8/7/06 (Stanton) !!!URGENT!!! North and South Side of Building: Faucets running; broken shut-off valve. |
May 11, 2004 |
August 7, 2006 |
818 days |
| Stanton Elementary School |
FM-200206081 02 8/8/06 Stanton Annex !!! Emergency !!! Emergency response pipe repair TSI removal custodial closet above the ceiling. Asbestos Assessment Required Asbestos Code A - Abated and cleared for repairs on 12-10-02 (LM/ 12-12-02) per Leroy Minton Jr. confirmation. Safety Office (202) 576-8962. Repair (2) each sewer ejector pumps and clean sewer ejector pit. 1) Cinder block wall entrance to sewer ejector room and Custodial Room where sewer ejector is located. Kitchen Sewage Drain is Backing up. |
April 18, 2002 |
August 8, 2006 |
1,573 days |
| Browne Junior High School |
FM-200626934 06 8/8/06 Water leaking into electrical fixtures constituting a clear and inimical threat to human life, health and safety "Girls Locker Room |
August 7, 2006 |
August 8, 2006 |
1 day |
| Aiton Elementary School |
FM-200622375 06 8/9/06 Third Floor-Room 302: Install an electrical line for canon copier/Fax Machine. Asbestos Code A - Clear for repairs on 05/16/06. DCPS Safety - Leroy Minton Jr. (RG 05/17/06) |
May 9, 2006 |
August 9, 2006 |
92 days |
| Jefferson JHS |
FM-200444015 04 8/9/06 (Jefferson) FIRST FLOOR lock smith PANIC BAR NEED REPLACEING 7TH ST AND 9TH ST AND AUDITIORUM DOORS.urgent Account #: 415 K |
February 11, 2004 |
August 9, 2006 |
910 days |
| Winston EC |
FM-200459440 04 8/9/06 (Winston) !!!VERY URGENT!!! UNCLOG KITCHEN FLOOR DRAINS. WATER KEEPS BACKING UP. |
December 2, 2004 |
August 9, 2006 |
615 days |
| Draper Elementary School |
FM-200514710 /05 8/9/06 Draper Urgent Repair all plunbing on third floor in girls restroom |
October 27, 2005 |
August 9, 2006 |
286 days |
| Beers Elementary School |
FM-200218350 02 8/11/06 Beers Boiler Room Repair or replace sump pump is no longer working. (Pumps are by boiler room stairs.) URGENT!!!! |
September 26, 2002 |
August 11, 2006 |
1,415 days |
| Orr Elementary School |
FM-200516453 /05 8/11/06 Orr Boiler Room Repair or replace domestic hot water heater. Polit lite continously going out. No Hot Water in Building. Urgent !!!!! |
December 14, 2005 |
August 11, 2006 |
240 days |
| Clark Elementary School |
FM-200505732 05 8/11/06 Clark Boiler Room Check compressor, compressor will not shut off on pressure. Urgent !!!!! |
May 19, 2005 |
August 11, 2006 |
449 days |
| Hart Middle School |
FM-200621964 06 8/11/06 Hart Boiler Room Repair or replace Lochinvar, will not stay on. No hot water. Urgent !!!!! |
May 1, 2006 |
August 11, 2006 |
102 days |
| Woodson High School |
FM-200219925 /02 8/11/06 (lWoodson, H.D.) !!URGENT!! 7th Floor/Stairwell #4: Sink stopped up, and constantly running; unable to shut water off. Water running in-to hallway. |
October 23, 2002 |
August 11, 2006 |
1,388 days |
| West Elementary School |
FM-200622760 06 8/11/06 West Mechanical Room Repair or replace starter control inmechanical room on Air Handler Unit #3 Starter keep cutting off, you have to keep re-starting it over and over. AHU-3 mechanical room unit. Cool the office and Pre-Kinderganter room also hallway and classroom #3. Urgent !!!! |
May 16, 2006 |
August 11, 2006 |
87 days |
| Ballou Senior High School |
FM-200622157 06 8/14/06 BALLOU Boiler room URGENT Investigate and make corrections to chiller starter controls. Starter is make excessively loud noises. |
May 3, 2006 |
August 14, 2006 |
103 days |
| Patricia R Harris Ed Center |
FM-200446127 04 8/14/06 PR Harris Pressure wash all interior and exterior surfaces of the cooling tower Clean all spray nozzles and/or grommets. Replace all eliminators Inspect and properly adjust all floats Perform preventive maintenance on all auxiliary equipment (including but not limited to: greasing motors, replacing all belts, etc.) Clean all debris from jobsite Replace, as necessary, defective spray nozzle and/or grommet each Replace, as necessary, defective floats each Poc - Jay Dolphin - 576-3364 Asbestos Code A - Clear for repairs on 03/31/04. DCPS Safety - Richard Gibson (RG) |
March 30, 2004 |
August 14, 2006 |
867 days |
| Stanton Elementary School |
FM-200332781 03 8/14/06 Stanton !! Urgent !! Exterior 1. 1. Unclog outside drains . |
July 1, 2003 |
August 14, 2006 |
1,140 days |
| Ballou Senior High School |
FM-200511750 05 8/14/06 Ballou Boiler Room Boiler #3 down, will not come on. Boiler use for hot water for kitchen. Urgent !!!!! |
September 2, 2005 |
August 14, 2006 |
346 days |
| Seaton Elementary School |
FM-200455539 04 8/14/06 Seaton Ground - (Parking Lot) Repair or replace float switch to cooling tower. Chiller will not run. Urgent !!!! |
September 23, 2004 |
August 14, 2006 |
690 days |
| Shaw JHS |
FM-200624986 06 8/14/06 Shaw Rooftop Units Repair cooling tower has leaking 2" to 3"( inch) branch line flange leaking School has no windows. Urgent !!!!! |
June 29, 2006 |
August 14, 2006 |
46 days |
| John Burroughs ES |
FM-200455486 04 8/14/06 (Burroughs) 1st Floor/Health Suite: Replace carpet with vinyl floor tiles. Duplicate FM-200447799 Code A - clear for repairs as of 5/12/04 Horne Eng. Duplicate Sylvia Grimes safety. |
September 22, 2004 |
August 14, 2006 |
691 days |
| Woodson High School |
FM-200218504 02 8/15/06 (Woodson, H.D.) !!!VERY URGENT!!! Asbestos Assessment Reqd. Kitchen: Porcelain sink has fallen off wall in the kitchen; porcelain is ceramic ware, Unable to repair, as sink has broken into pieces. (Please replace porcelain sink) Asbestos Code A - Clear for repairs on 09/30/02. Horne Engineering - Philp Connolly (RG 10/02/02) |
September 27, 2002 |
August 15, 2006 |
1,418 days |
| Woodson High School |
FM-200215534 02 8/15/06 (Woodson, H.D.) !!!VERY URGENT!!! Ground floor/Kitchen: Sink backs up while running water. |
August 23, 2002 |
August 15, 2006 |
1,453 days |
| Merritt Middle School |
FM-200625731 06 8/16/06 MERRITT ES URGENT No Windows Restore power to RTU # 2 shorted out. Unit service main office. |
July 17, 2006 |
August 16, 2006 |
30 days |
| Seaton Elementary School |
FM-200506577 05 8/16/06 (SEATON) URGENT!!!!! First Floor - Library Room 103 1) Repair/Replace air condition unit in the ceiling, the breaker keeps tripping it cuts off and water starts running down causing damage to the ceiling tile. Note: Having interviews in this area on 6/13/05. Code A-clear for repair by DCPS Charles Buchanan on 6/13/05 |
June 9, 2005 |
August 16, 2006 |
433 days |
| Amidon Elementary School |
FM-200512257 05 8/16/06 Amidon Boiler Room Boiler #2 Repair or replace honeywell temperature control. Copper tubing element line broken. Per DC Boiler Inspector Urgent !!!! |
September 11, 2005 |
August 16, 2006 |
339 days |
| Clark Elementary School |
FM-200625451 06 8/16/06 Clark Boiler Room Repair or replace chiller. Unit is contenouosly being reset daily. Urgent !!!!! |
July 8, 2006 |
August 16, 2006 |
39 days |
| Clark Elementary School |
FM-200625671 06 8/16/06 Clark Boiler Room Repair or replace starter on chiller. Chiller not running after turning off on temp. Also running high refrigerant temp. Please address as soon as possible !!!!!! Urgent !!!!! |
July 14, 2006 |
August 16, 2006 |
33 days |
| Francis Junior High School |
FM-200442405 04 8/16/06 (Francis) 1st Floor/Girls Restroom: Re-inforce, or remove sink, kids playing, and standing on the sink. (Safety concern) Asbestos Code A - Clear for repairs on 01/08/04. Horne Engineering - Philp Connolly (RG 01/12/04) |
January 8, 2004 |
August 16, 2006 |
951 days |
| Woodson High School |
FM-200328988 03 8/16/06 (Woodson, H.D.) !!!VERY URGENT!!! Ground Floor/Kitchen: Sink stopped up, water running on the floor from around faucets, repair or replace. Floor is very wet and slippery; fear of employee injury (Safety Hazard) Ground Floor/Custodian office next to kitchen: Sinks stopped up, water running on floor, please replace faucets. |
April 23, 2003 |
August 16, 2006 |
1,211 days |
| Hardy Middle School |
FM-200455661 04 8/16/06 Hardy ( Filmore) Boiler Room #3 Boilers # 1,#2 and,#3 will not come on, check and service. Urgent !!!! |
September 24, 2004 |
August 16, 2006 |
691 days |
| Takoma Educational Center |
FM-200626446 06 8/16/06 Takoma Boiler Room Correct cooling problem with module units. Appears to be low on refrigerate or heat exchanger. Note: No outside windows Urgent !!!! |
July 27, 2006 |
August 16, 2006 |
20 days |
| Woodson High School |
FM-200329051 03 8/16/06 (Woodson, H.D.) !!!VERY URGENT!!! 3rd Floor/Boy bathroom: Water running from toilets flooding the floors through-out 3rd floor, and other floors. |
April 24, 2003 |
August 16, 2006 |
1,210 days |
| Lafayette Elementary School |
FM-200626447 06 8/16/06 Lafayette Boiler Room Correct cooling problem with module units. Appears to be low on refrigerate or heat exchanger. Urgent !!!! |
July 27, 2006 |
August 16, 2006 |
20 days |
| Woodson High School |
FM-200338377 03 8/16/06 (Woodson, H.D.) Ground Floor/Kitchen: Unclog grease trap that is stopped up; staff is subject to injury, as the kitchen floor is flooded with water. (Grease trap is clean) |
October 1, 2003 |
August 16, 2006 |
1,050 days |
| Garfield ES |
FM-200215468 02 8/17/06 Garfield F-303.4 Fire Code Violation Asbestos Assessment Reqd. 1st Floor Room 102/New Wing Broken door. Asbestos Code A - Clear for repairs on 08/26/02. DCPS Safety - Leroy Minton Jr. (RG 08/27/02) |
August 23, 2002 |
August 17, 2006 |
1,455 days |
| Amidon Elementary School |
FM-200623767 06 8/17/06 AMIDON roof top unit Urgent!!!! Charge roof top unit, it appears to be low on refrigerant, (one compressor is down) not drawing heat out of learning center. Replace temperature thermostat control. |
June 2, 2006 |
August 17, 2006 |
76 days |
| Benjamin Banneker Academic HS |
FM-200624019 06 8/17/06 Banneker Boiler Room Repair or replace B&G domestic hot water circulating pump and repair leaking flange. Urgent !!!! |
June 7, 2006 |
August 17, 2006 |
71 days |
| Montgomery ES |
FM-200446828 04 8/18/06 MONTGOMERY new building Urgent!!!!! No Air / No Windows Repair Trane air conditiong unit for day care. Unit is inoperable |
April 19, 2004 |
August 18, 2006 |
851 days |
| Benning Elementary School |
FM-200625582 06 8/18/06 Benning Boiler Room Unclog drain in boiler room floor Urgent !!!!! |
July 12, 2006 |
August 18, 2006 |
37 days |
| Duke Ellington School |
FM-200623910 06 8/18/06 Ellington Boiler Room Repair or replace chiller. Unit need to be reset after set temperature has been reach and unit shut off. Additionally chiller relay is arching and motor making loud noise. Unit is turn off at present. Chiller cools auditorium. Only chiller on site. Urgent !!!!! |
June 6, 2006 |
August 18, 2006 |
73 days |
| Emery Elementary School |
FM-200622773 06 8/18/06 Emery Roof (Cooling Tower) Replace float control, unable to adjace. *Call Solomon for more info. Radio #1861. Urgent !!!! |
May 16, 2006 |
August 18, 2006 |
94 days |
| Dunbar High School |
FM-200511626 05 8/18/06 Dunbar Boiler Room Multistack A/C controls won't start compressors Re: No communication. Urgent !!!!! |
August 31, 2005 |
August 18, 2006 |
352 days |
| Orr Elementary School |
FM-200624846 06 8/18/06 Orr Chiller Check and repair chiller, low refrig. pressure and check cooling fan controls. Summer School site. Urgent !!!! |
June 27, 2006 |
August 18, 2006 |
52 days |
| Ludlow-Taylor ES |
FM-200622957 06 8/18/06 Ludlow Taylor Boiler Room Asbestos assessment required Repair or replace rupture 3/4" bleeder inlet bleeder valve, chill water line in boiler room. Urgent !!!!! Asbestos Code A - Clear for repairs on 05/24/06. Tidewater - Shamika Parker (RG 05/30/06) |
May 18, 2006 |
August 18, 2006 |
92 days |
| Gage-Eckington ES |
FM-200513455 05 8/18/06 Gage-Eckington Boiler Room Repair or replace chillers appears to be control problem. No exterior window in building. Urgent !!!! |
October 4, 2005 |
August 18, 2006 |
318 days |
| Marshall Educational Center |
FM-200623226 06 8/21/06 Marshall Boiler Room Repair or replace 1-1/2" or 2" nipple on bottom of circulating pump strainer. No A/C in Building Urgent !!!!! |
May 24, 2006 |
August 21, 2006 |
89 days |
| Duke Ellington School |
FM-200622795 06 8/22/06 Ellington Chiller Repair or replace rupture chill water line on chiller. Urgent !!!!!! |
May 17, 2006 |
August 22, 2006 |
97 days |
| Ketcham Elementary School |
FM-200619146 06 8/23/06 Ketcham Boiler Room Replace safety relief valve on Boiler #3, leaking. Conbraco; Max PSI 15 1200 - pound per houl 3-213 This is all the information that was on valve |
February 27, 2006 |
August 23, 2006 |
177 days |
| Seaton Elementary School |
FM-200627368 06 8/23/06 Seaton Room #301 Repair rupture supply line in room #301. Can not be isolated. Urgent !!!! |
August 14, 2006 |
August 23, 2006 |
9 days |
| Burrville Elementary School |
FM-200628209 06 8/24/06 Burrville Boiler Room Repair or replace exterior lock to boiler room. Key will unlock lock, but the handler will not release lock. Engineer can not get into the boiler room. Urgent!!!! |
August 24, 2006 |
August 24, 2006 |
0 days |
| Deal Junior High School |
FM-200227010 03 8/25/06 Deal JHS Second Floor Hallway Second Floor Asbestos Assestment Required Ceiling wall and floor needs to be abated Floor needs to be busted up R/R busted radiator near room 204 below the window Third Floor Radiator going down to the rear exit This unit is isolated not operationing In-House Assessment by Sylvia Grimes DCPS Safety recieved 3/28/03. Area is clear to perform exploratory until pipe insulation is then visible. Sylvia Grimes Asbestos Code A - Clear for repairs on 04/18/03. Horne Engineering - Tony Marcolin (RG 04/18/03) |
March 13, 2003 |
August 25, 2006 |
1,261 days |
| Kenilworth ES |
FM-200221121 /02 8/25/06 KENILWORTH Boiler room "URGENT" Repair heat exchanger leaking at the flange. NOTE: IF NOT REPAIRED EXCHANGER WILL RUST OUT CAUSING BUILDING TO POSSIBLE HAVE NO HEAT. Code A - clear for repairs as of 10/1/03 by safety Sylvia Grimes. |
November 18, 2002 |
August 25, 2006 |
1,376 days |
| Park View ES |
FM-200205476 02 8/25/06 Park View Boiler Room 1.Asbestos assessment required 2.Repair/replace 2" steam supply line in mechanical room. NO HEAT !!! Asbestos Code A - Cleared for repairs and abated on 04-10-02 by Leroy Minton Jr (LM/01-13-04) Safety Office 202-576-8962. |
April 5, 2002 |
August 25, 2006 |
1,603 days |
| Coolidge High School |
FM-200227180 03 8/25/06 Coolidge Old Girls & Boys Basement Lockeroom Asbestos Assestment Required Abate ruptured steamline located in the walls in girls and boys bathroom in the basement old lockeroom Asbestos Code A clear for repairs on 03/27/03 DCPS Safety R. Edwards (RE) Also related to WO#s FM-200225384, FM-200221687, FM-200225417 & FM-200225418 |
March 17, 2003 |
August 25, 2006 |
1,257 days |
| Payne Elementary School |
FM-200228899 03 8/25/06 Payne Tunnel (Basement) 1.Assessment required in tunnel. 2.Repair steam leaks in tunnel areas Asbesos Code A Cleared for repairs DCPS Safety R. Edwards 11/2/04 Abatement conducted by EBG; Air Monitoring conducted by USA Environmntal Repairs conducted by M&M Welding Reinsulation not required according to DCPS Mechanical Maintenance 12/02/04 |
April 21, 2003 |
August 25, 2006 |
1,222 days |
| Benjamin Banneker Academic HS |
FM-200222255 02 8/25/06 Banneker Mechanical Room Second Floor Asbestos Assestment Required Complete installation of piping on air handler unis #1 and #2. New heating coils in units to service auditorium area. Note: Persons making installation did not complete return side of system (2" black pipe). Asbestos Code A - Clear for repairs on 12/17/02. DCPS Safety - Leroy Minton Jr. (RG 12/18/02) |
December 9, 2002 |
August 25, 2006 |
1,355 days |
| Plummer Elementary School |
FM-200339029 /03 8/25/06 Plummer Boiler Room Asbestor assessment required to 1" valve Replace 1" valve on city water line to Boiler #1. Building will has no heat. URGENT Asbestos Code B -on 10/07/05. Tidewater - Tony Marcolin (RG 10/11/05) Code A - abeted by Goel Contractors per Ricardo Eley comfirmed (RG 03/13/06) |
October 16, 2003 |
August 25, 2006 |
1,044 days |
| Beers Elementary School |
FM-200339363 /03 8/25/06 (Beers) !!!URGENT!!! Building #2: Boys, and girls bathrooms have all metal radiators that are very hot; children are burning with it. Please remove all radiators on the 1st, and 2nd floor. |
October 23, 2003 |
August 25, 2006 |
1,037 days |
| Benning Elementary School |
FM-200221568 /02 8/25/06 BENNING Boiler room 1. Asbestos assessment may be required. 2. Replace 8 " OS&Y valve on hot water supply that is not holding. Asbestos Code A-clear for repair by Horne Engineer Philip Connolly DCPS Safety Charles E. Buchanan on 11/26/02 |
November 25, 2002 |
August 25, 2006 |
1,369 days |
| Ferebee-Hope Elementary School |
FM-200332258 03 8/25/06 Ferebee-Hope Boiler Room Basement Pipe safety valves to floor (SAFETY CODE VIOLATION) |
June 20, 2003 |
August 25, 2006 |
1,162 days |
| Stuart-Hobson Middle School |
FM-200222588 /02 8/25/06 REPAIR/REPLACE VALVE (STOP/SAFETY) |
December 15, 2002 |
August 25, 2006 |
1,349 days |
| Duke Ellington School |
FM-200341536 /03 8/25/06 Ellington Room #16A Asbestos assessment required on Room #16A floor area. Repair or replace what appears to be a rupture heating line under floor area. Floor is very hot. Asbestos Code 'A' cleared for repairs 12/29/04. DCPS Safety R. Edwards (RE-12/29/04). Abatement conducted by Goel Constuction; Air Monitoring by USA Environmental Inc. Asbestos Code A - Clear for repairs on 12/16/03. Horne Engineering - Edward Rodriguez (RG 12/17/03) |
December 13, 2003 |
August 25, 2006 |
986 days |
| Bowen Elementary School |
FM-200335061 03 8/25/06 Bowen Boiler Room Boilers #1 and #2 has two (2) check valve each, that needs to be remove. Size of valves are 1" and 1/2". Code A- clear for repairs as of 9/9/03. by safety Sylvia Grimes. |
August 13, 2003 |
August 25, 2006 |
1,108 days |
| Cardozo High School |
FM-200221881 02 8/25/06 Cardozo Hallway by Room #10 Asbestos assessment required Replace rupture 3/4"steam line in hallway by room #10. Asbestos Code A - clear for repairs as of 12/3/02 by Horne Engineers Sharon Voss DCPS safety Sylvia Grimes |
December 3, 2002 |
August 25, 2006 |
1,361 days |
| Garnet-Patterson MS |
FM-200205600 02 8/25/06 Garnet-Patterson ****Emergency**** Asbestos Assessment Reqd. Uninsulated 2-inch pipe is leaking in the basement by the tunnel and the water is flooding the maintenance office. Asbestos code A - Clear for repairs on 04/08/02. DCPS Safety - Sheila R Howard (RG 04/08/02 ) |
April 8, 2002 |
August 25, 2006 |
1,600 days |
| Coolidge High School |
FM-200228088 03 8/25/06 Coolidge Boiler Room Provide 4 spirax sarco type 25P and 25PA pressire reducing valves. Type P A99 #54-819. Code A - clear for repairs as of 4/3/03 by Sylvia Grimes DCPS Safety. |
April 2, 2003 |
August 25, 2006 |
1,241 days |
| Gibbs Elementary School |
FM-200214005 02 8/25/06 Gibbs ****Urgent**** 2nd Floor Library Repair or replace leaking convector. |
August 12, 2002 |
August 25, 2006 |
1,474 days |
| Shaw JHS |
FM-200336696 03 8/25/06 (Shaw) !!!VERY URGENT!!! Boiler Room: Remove two (2) linear feet asbestos jacket insulation marked in red paint, in the boiler room. Asbestos Code A - Clear for repairs on 09/02/03. Horne Engineering - Edward Rodriguez (RG 09/03/03) |
September 2, 2003 |
August 25, 2006 |
1,088 days |
| Spingarn High School |
FM-200205628 02 8/25/06 Spingarn Basement kitchen storage room Replace defective reducing station in storeroom. Station by-pass too much steam setting off safety valve. |
April 9, 2002 |
August 25, 2006 |
1,599 days |
| Woodson High School |
FM-200228177 03 8/25/06 H.D.Woodson Boiler room Repair or replace leaks in the condensate return tank in the boiler room , the tank has insulation on it. Code A - clear for repairs as of 4/4/03 by Sylvia Grimes DCPS Safety. |
April 3, 2003 |
August 25, 2006 |
1,240 days |
| Coolidge High School |
FM-200225384 03 8/25/06 Coolidge Weight Room & Shower Room Asbestos Assessment Required Repair 2" inch. steam leak in wall of weight room and shower room Asbestos Code C sbestos Code A clear for repairs on 03/27/03 DCPS Safety R. Edwards (RE) Also related to WO#s FM-200221687, FM-200227180, FM-200225417 & FM-200225418 |
February 7, 2003 |
August 25, 2006 |
1,295 days |
| Coolidge High School |
FM-200225417 03 8/25/06 Coolidge Old Girls Gym (Small Shower) Asbestos assessment required Repair leaking 1/2" condensate line leaking behind wall in old girls gym small shower room. sbestos Code A clear for repairs on 03/27/03 DCPS Safety R. Edwards (RE) Also related to WO#s FM-200225384, FM-200221687, FM-200227180, & FM-200225418 |
February 10, 2003 |
August 25, 2006 |
1,292 days |
| Coolidge High School |
FM-200225418 03 8/25/06 Coolidge Old Girls Gym (Weight Room) Asbestos assessment required Repair leaking 1 1/4" steam pipe leaking behind wall in old girls gym weight room sbestos Code A clear for repairs on 03/27/03 DCPS Safety R. Edwards (RE) Also related to WO#s FM-200225384, FM-200221687, FM-200227180, & FM-200225417. |
February 10, 2003 |
August 25, 2006 |
1,292 days |
| Sousa Middle School |
FM-200224668 03 8/25/06 Sousa Boiler room ( URGENT} Asbestos assessment required Repair or replace leaking sections in the # 1 boiler, 2 of 3 boilers are down ,one boiler will not carry the building. Asbestos Code A - Clear for repairs on 01/28/03. Horne Engineering - Bipin Nanavaty ( RG 01/30/03) |
January 28, 2003 |
August 25, 2006 |
1,305 days |
| Davis Elementary School |
FM-200204875 02 8/25/06 (Davis) 1. Asbestos assessment required. Basement: Pipe tunnel compressed paper Pipe insulation Cementitious fittings Block pipe insulation Fiber release episode discovered by FA-Engineering. Horne Tracking #13094, 13095, 13096, & 13097. Asbestos Code A - Abated and cleared for repairs on 08-28-02 (LM 08-29-02) per Leroy Minton confirmation. Safety Office. (202) 576-8962. |
March 22, 2002 |
August 25, 2006 |
1,617 days |
| Terrell Mc ES |
FM-200219570 /02 8/28/06 (Terrell, M.C.) EMERGENCY!!! NO WORKING WATER FOUNTAINS ON THIRD FLOOR. NEED REPAIRS THAT CUSTODIANS CANNOT DO. Asbestos Code A - Cleared for repairs on 04-28-03 by Leroy Minton Jr. (LM/04-08-03) the Safety Office 202-576-8962. |
October 17, 2002 |
August 28, 2006 |
1,411 days |
| Stanton Elementary School |
FM-200329611 03 8/28/06 Stanton Outside gate Window well gate is off the wall. Urgent!!!!!!! |
May 5, 2003 |
August 28, 2006 |
1,211 days |
| Young Elementary School |
FM-200625314 06 8/28/06 Broken Storm Drain Cover On Playground Area. (Safety Hazard) |
July 6, 2006 |
August 28, 2006 |
53 days |
| West Elementary School |
FM-200625455 06 8/28/06 West Boiler Room Absetos assessment required Repair or replace return valve on Boiler #1. Valve is not holding. Can not isolate boiler properly. Urgent !!!!! Asbestos Code A - Clear for repairs on 07/11/06. Tidewater - Roger Small (RG 07/13/06) |
July 9, 2006 |
August 28, 2006 |
50 days |
| Oyster Elementary School |
FM-200617663 06 8/29/06 Oyster Classroom #300,Heat pump #301 Repair or replace heat pump (Keep cutting off) Made by Quay-A/C Company Part #210979ZOO Mode-WFDS136KZOO-ZOO AA12ZZB1 Volts 460 HZ 60 PH 3 Motor Volts 460 FLA 1.6 LRA 3.5 HZ 60 PH 1 HP 1/2 Compressor = 460 Volts FLA 1.6 LRA=33.0 HZ 60 PH 3 Urgent !!!! |
January 22, 2006 |
August 29, 2006 |
219 days |
| Malcolm X ES |
FM-200516026 05 8/29/06 Malcolm X Boiler Room Repair or replace air compressor, compressor is down. Urgent !!!! |
December 4, 2005 |
August 29, 2006 |
268 days |
| Oyster Elementary School |
FM-200506610 05 8/31/06 Oyster 2 nd Floor Electrical Room Repair or replace bad breaker switch for 2 heat pumps in classrooms. Breaker 20 amps, 225 amps-max. 48OY/227, 4 wires. Breaker in side Panel #N-22 Urgent !!!! |
June 10, 2005 |
August 31, 2006 |
447 days |
Routine Repair Requests Closed in August 2006 (802)
| School |
Description |
Open Date |
Close Date |
Time Elapsed |
| Kramer Middle School |
FM-200449904 04 8/1/06 Kramer First floor room 101 Security bars is needed on outside window. It appears that there was a breakin attemp. |
June 29, 2004 |
August 1, 2006 |
763 days |
| Rudolph Elementary School |
FM-200618225 06 8/1/06 Inspection or preventive maintenance on playground equipment. |
February 2, 2006 |
August 1, 2006 |
180 days |
| Watkins Elementary School |
FM-200626618 06 8/1/06 1st Floor, Broken Panic bar on the E St. side of the building. - Two sets of double doors. Door closest to 12 street panic bar is sticking. |
August 1, 2006 |
August 1, 2006 |
0 days |
| Rudolph Elementary School |
FM-200624515 06 8/1/06 Bulk Trash pick-up is needed - Exterior Of Building. |
June 20, 2006 |
August 1, 2006 |
42 days |
| Terrell Mc ES |
FM-200502599 05 8/1/06 Terrell, M.C. Perform PM to Chiller and all equipment. |
March 14, 2005 |
August 1, 2006 |
505 days |
| Aiton Elementary School |
FM-200442771 04 8/1/06 Aiton Boiler Room Boiler #2 replace transformer. |
January 15, 2004 |
August 1, 2006 |
929 days |
| Watkins Elementary School |
FM-200507318 05 8/1/06 Ground floor. Repair flush valves and unclog toilets and urinals. Also stop urinals from leaking. |
June 30, 2005 |
August 1, 2006 |
397 days |
| Key Elementary School |
FM-200501845 05 8/1/06 KEY ES Computer room Install an exhaust fan in computer lab equipment room, room is too hot and has no windows |
February 22, 2005 |
August 1, 2006 |
525 days |
| Garfield ES |
FM-200340342 /03 8/1/06 Garfield Kitchen Storage Room Repair or replace hood fan magnetic starter - maning loud noise. (Non Compensated overload relays) Full load motor amperes AH32-133-941 AH 32-O33-U Way Size 0 280/220 |
November 17, 2003 |
August 1, 2006 |
988 days |
| Takoma Educational Center |
FM-200623730 06 8/1/06 Outside Grounds/Repair the damage to the retaining wall. |
June 1, 2006 |
August 1, 2006 |
61 days |
| Brent Elementary School |
FM-200443201 04 8/1/06 Brent Boiler room Replace relief valve on the #1 boiler ,will not reseat.1-1/4" X 1-1/2" no9 insulation 60 psi relief pressure. |
January 24, 2004 |
August 1, 2006 |
920 days |
| Brent Elementary School |
FM-200506050 05 8/1/06 Brent Boiler room Repair or replace B&G Domestic hot water circulating pump on the water heater , seal and coupling in defective. |
May 27, 2005 |
August 1, 2006 |
431 days |
| Brent Elementary School |
FM-200625110 06 8/1/06 Remove lockers from rooms 205 & 204 Asbestos Code A - Clear for repairs on 07/05/06. Tidewater - Thomas Johnson (RG 07/05/06) SEE ASSESSMENTS |
July 3, 2006 |
August 1, 2006 |
29 days |
| Brent Elementary School |
FM-200625485 06 8/1/06 2nd Floor- Rooms 205 & 204 Remove lockers. |
July 10, 2006 |
August 1, 2006 |
22 days |
| Kramer Middle School |
FM-200625944 06 8/1/06 REPAIR OR REPLACE FENCE ON PLAYGROUND HOLDS HAVE BEN CUT IN FENCE. |
July 19, 2006 |
August 1, 2006 |
13 days |
| Bruce-Monroe Elementary School |
FM-200626060 06 8/1/06 remove graffiti from the walls of school |
July 20, 2006 |
August 1, 2006 |
12 days |
| Dunbar High School |
FM-200625942 06 8/1/06 BULK TRASH PICK UP IN PARKING LOT. |
July 19, 2006 |
August 1, 2006 |
13 days |
| Dunbar High School |
FM-200625517 06 8/1/06 repair or place hole in fence on n st side of building. |
July 11, 2006 |
August 1, 2006 |
21 days |
| Gibbs Elementary School |
FM-200626672 06 8/1/06 Small Playground E Street Side Turn off water valve. |
August 1, 2006 |
August 1, 2006 |
0 days |
| Kramer Middle School |
FM-200626159 06 8/1/06 repair fence in front of biulding two poles and ten foot of fence |
July 24, 2006 |
August 1, 2006 |
8 days |
| Johnson JHS |
FM-200504770 05 8/1/06 ( JOHNSON ) B Wing - Head Start, Room 104 1) Need two air conditioners installed in two windows. |
April 26, 2005 |
August 1, 2006 |
462 days |
| Kenilworth ES |
FM-200625442 06 8/1/06 Remove bulk trash from around the trash dumpster. |
July 7, 2006 |
August 1, 2006 |
25 days |
| Sousa Middle School |
FM-200444643 04 8/1/06 Sousa Boiler room Repair #3 Boiler , will not start. |
March 2, 2004 |
August 1, 2006 |
882 days |
| Dunbar High School |
FM-200502977 05 8/1/06 Dunbar Perform PM to Chiller and all equipment. |
March 21, 2005 |
August 1, 2006 |
498 days |
| Drew Elementary School |
FM-200625522 06 8/1/06 Exterior of Building/Small Children's Playground. Repair or Replace vandalized fence. |
July 11, 2006 |
August 1, 2006 |
21 days |
| Stanton Elementary School |
FM-200455647 04 8/1/06 Stanton Second floor girls bathroom Sink is leaking water badly. |
September 24, 2004 |
August 1, 2006 |
676 days |
| Coolidge High School |
FM-200217349 02 8/1/06 Coolidge SHS Ground Floor Outside By The Green House Replace motor on #1 split system cooling condenser for science labs. G.E Motor, Direct Drive, 1HP, 1125 RPM. Volts 208-230, Ph1, Amps 5.0 Unit Name Trane TTA120-5F=10A |
September 12, 2002 |
August 1, 2006 |
1,419 days |
| Tyler Elementary School |
FM-200618399 06 8/1/06 Inspection or preventive maintenance on playground equipment. |
February 7, 2006 |
August 1, 2006 |
175 days |
| Draper Elementary School |
FM-200618403 06 8/1/06 Inspection or preventive maintenance on playground equipment. |
February 7, 2006 |
August 1, 2006 |
175 days |
| Turner Elementary School |
FM-200448522 04 8/1/06 (Turner) !!!VANDALISM!!! Asbestos Assessment Required. 2nd Floor/Room #217: Weld windows shut in Assist. Principal's office, to prevent future break-in. Asbestos Code A - Clear for repairs on 05/27/04. Horne Engineering - Tony Marcolin (RG 05/28/04) |
May 26, 2004 |
August 1, 2006 |
797 days |
| Woodson High School |
FM-200517278 06 8/1/06 Ground floor, Kitchen. "Emergency" Need plumbers to assess and correct plumbing issue. Water is backing up out of floor drain all over the floor. |
January 9, 2006 |
August 1, 2006 |
204 days |
| Tubman Elementary School |
FM-200514088 /05 8/1/06 Tubman Third Floor - Girls Restroom 1) Replace spuds on commodes in Restrooms. |
October 21, 2005 |
August 1, 2006 |
284 days |
| Bunker Hill Elementary School |
FM-200626038 06 8/1/06 Second Floor/Rm. 220 - Leak in ceiling falling plaster & hole in ceiling where leak is occurring |
July 20, 2006 |
August 1, 2006 |
12 days |
| Smothers ES |
FM-200618391 06 8/1/06 Inspection or preventive maintenance on playground equipment. |
February 7, 2006 |
August 1, 2006 |
175 days |
| Wilson High School |
FM-200501527 05 8/1/06 Wilson W. Stadium Area Loose Hand Ralling |
February 10, 2005 |
August 1, 2006 |
537 days |
| Hart Middle School |
FM-200442905 04 8/1/06 Hart Boiler Room Boilers #2 & #3 Replace Honeywell R4140 Boiler Programmer with new-updated version, Note: Programmers are worn out and have to be manually operated, Information Honeywell Programmer R4140 L,M Series R4140L 1147 Volt 120 HZ 60 139694Y |
January 18, 2004 |
August 1, 2006 |
926 days |
| Stanton Elementary School |
FM-200503027 05 8/1/06 Stanton Kitchen: 1) Temperature for hot water at hand sink and 2 compartment sink is not sufficient, must be at least 110 degrees F. 2) Post handwashing sign in employee Restroom. |
March 21, 2005 |
August 1, 2006 |
498 days |
| Garfield ES |
FM-200626160 06 8/1/06 Repair basketball goal on playground |
July 24, 2006 |
August 1, 2006 |
8 days |
| Garfield ES |
FM-200626346 06 8/1/06 Dismantle playground equipment. |
July 25, 2006 |
August 1, 2006 |
7 days |
| Wilson J. O. ES |
FM-200626593 06 8/1/06 Third Floor/Across from the computer lab door arm closer missing. Completed, 7/28/06 |
August 1, 2006 |
August 1, 2006 |
0 days |
| Roosevelt High School |
FM-200446390 04 8/1/06 Roosevelt Boiler Room Repair Boiler #1 and #3, Boiler will not come on. Try to reset programmer, nothing happen. |
April 6, 2004 |
August 1, 2006 |
847 days |
| Wilson High School |
FM-200506328 05 8/1/06 Wilson, W. Boiler Room Repair six (6) leaks to three (3) univent coils. |
June 3, 2005 |
August 1, 2006 |
424 days |
| Johnson JHS |
FM-200505841 05 8/1/06 Johnson Boiler Room Repair oil heater for Trane A/C unit. Unit is down. |
May 23, 2005 |
August 1, 2006 |
435 days |
| Stanton Elementary School |
FM-200458696 /04 8/1/06 Stanton Throughout building and annex Girls and boys bathroom are in need of repairs, 1st floor girls sinks are clogged, boys urinals are in need of repair. 2nd floor girls and boys fixtures are in need of repair. Girls sink on 3rd floor is clogged and some urinals in boys bathroom and annex urinals are not working and fixtures. |
November 24, 2004 |
August 1, 2006 |
615 days |
| Plummer Elementary School |
FM-200625515 06 8/1/06 repair main stairway to school replace bottom step. |
July 11, 2006 |
August 1, 2006 |
21 days |
| Wilson High School |
FM-200506604 05 8/1/06 Wilson, W Boiler Room Leak test heating coils and reinstall in univents. |
June 10, 2005 |
August 1, 2006 |
417 days |
| Houston Elementary School |
FM-200625355 06 8/1/06 Survey/repair playground equipment; it is damaged. |
July 6, 2006 |
August 1, 2006 |
26 days |
| West Elementary School |
FM-200506656 05 8/1/06 West Boiler Room Chiller will not restart. |
June 13, 2005 |
August 1, 2006 |
414 days |
| Moten Elementary School |
FM-200459599 /04 8/1/06 Moten 4th Floor (410) Replace fan motor on univent , 4 fan motor unit. Pull out tray. Motek-Century Frame- H56L CY- 60 Amp-2 HP- 1/12 Mod.-CX-64ZF Volt 115 Ser. AM-9 RPM -715 Spec-19275 Code -A ENC-55-C-Cont. |
December 14, 2004 |
August 1, 2006 |
595 days |
| Hine JHS |
FM-200625518 06 8/1/06 repair hole in fence on basketball court. |
July 11, 2006 |
August 1, 2006 |
21 days |
| Bancroft Elementary School |
FM-200625516 06 8/1/06 repair or replace damged poles on wall at rear of building |
July 11, 2006 |
August 1, 2006 |
21 days |
| Smothers ES |
FM-200625527 06 8/1/06 Exterior of Building/East & West side of the playground. Repair or Replace vandalized fence. Note: One section is approximately 35 ft. and the other section is appoximately 75ft. |
July 11, 2006 |
August 1, 2006 |
21 days |
| Houston Elementary School |
FM-200626161 06 8/1/06 Make repars to playground equitment |
July 24, 2006 |
August 1, 2006 |
8 days |
| West Elementary School |
FM-200506626 05 8/1/06 West Boiler Room Chiller down in Hi head condenser pressure. |
June 11, 2005 |
August 1, 2006 |
416 days |
| Woodson High School |
FM-200625941 06 8/1/06 bulk trash pick up is needed by side parking lot. |
July 19, 2006 |
August 1, 2006 |
13 days |
| Terrell Mc ES |
FM-200618395 06 8/1/06 Inspection or preventive maintenance on playground equipment. |
February 7, 2006 |
August 1, 2006 |
175 days |
| Johnson JHS |
FM-200624022 06 8/2/06 Remove grafitti on the School sign at the front of the building. |
June 7, 2006 |
August 2, 2006 |
56 days |
| Ballou Senior High School |
FM-200617477 06 8/2/06 Replace entry door and lock to storage room near #121 north end of bldg. Asbestos Code A - Clear for repairs on 01/20/06. Tidewater - Thomas Johnson (RG 01/24/06) |
January 10, 2006 |
August 2, 2006 |
204 days |
| Ballou Senior High School |
FM-200621070 06 8/2/06 Survey:entry door to #312 3rd.floor,student kick it busting it at the top near closure. Asbestos Code B on 05/02/06. Tidewater - Henry Addison (RG 05/05/06) |
April 5, 2006 |
August 2, 2006 |
119 days |
| Macfarland Middle School |
FM-200623673 06 8/2/06 Marking of field for baseball game on 5/17/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Macfarland Middle School |
FM-200623660 06 8/2/06 Marking of field for baseball game on 5/18/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Meyer Elementary School |
FM-200624479 06 8/2/06 Playground/Remove rebar from concrete with torch. |
June 19, 2006 |
August 2, 2006 |
44 days |
| Hart Middle School |
FM-200619094 06 8/2/06 Basement, Boys' Restroom. "Emergency" Replace glass and reweld bars. Note: No way to secure school. Asbestos Code A - Clear for repairs on 02/27/06 Tidewater - Samuel May (RG 03/01/05) |
February 24, 2006 |
August 2, 2006 |
159 days |
| Hendley Elementary School |
FM-200624003 06 8/2/06 replace 30 feet of 10 foot fence at rear of biulding |
June 7, 2006 |
August 2, 2006 |
56 days |
| Malcolm X ES |
FM-200622176 06 8/2/06 Playground/Basketball Court. Need welders to weld backboard and rims together. |
May 3, 2006 |
August 2, 2006 |
91 days |
| Hyde Elementary School |
FM-200624524 06 8/2/06 Outside East Side Of Building/Basement Stairs - Drain Needs A Cover, Water Floods The Basement When It Rains. |
June 20, 2006 |
August 2, 2006 |
43 days |
| Jefferson JHS |
FM-200622407 06 8/2/06 Playground Repair/Replace basketball hoop. |
May 9, 2006 |
August 2, 2006 |
85 days |
| Leckie Elementary School |
FM-200623675 06 8/2/06 Marking of field for baseball game on 5/17/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Leckie Elementary School |
FM-200514681 /05 8/2/06 Leckie Emergency Kitchen-Entrance door to the kitchen lock is broken; Repair/Replace Note: Frame coming loose from the wall. |
October 26, 2005 |
August 2, 2006 |
280 days |
| Leckie Elementary School |
FM-200509265 05 8/2/06 Leckie Fire Code Violation Need to repair thumb turn locks on all class rooms |
August 1, 2005 |
August 2, 2006 |
366 days |
| Kimball Elementary School |
FM-200623674 06 8/2/06 Marking of field for baseball game on 5/17/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Benjamin Banneker Academic HS |
FM-200623662 06 8/2/06 Marking of field for baseball game on 5/18/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Benjamin Banneker Academic HS |
FM-200623677 06 8/2/06 Marking of field for baseball game on 5/17/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Wilson High School |
FM-200500360 05 8/2/06 Wilson, W. Commerical kitchen maintance (hood and duct improperly tagged). |
January 12, 2005 |
August 2, 2006 |
567 days |
| Wilson J. O. ES |
FM-200512189 05 8/2/06 Wilson, J. O. Fire Code Violation First Floor-Leak in ceiling in room 102 Asbestos Code A - Clear for repairs on 09/13/05. Tidewater - Tony Marcolin (RG 09/14/05) |
September 9, 2005 |
August 2, 2006 |
327 days |
| West Elementary School |
FM-200622453 06 8/2/06 (West) Outside playground: Unstop two (2) drains on kindergarten playground. |
May 10, 2006 |
August 2, 2006 |
84 days |
| Webb Elementary School |
FM-200624325 06 8/2/06 1st Floor- Exit Door Hobart Street Weld hinges back onto metal door. |
June 14, 2006 |
August 2, 2006 |
49 days |
| Walker-Jones EC |
FM-200624095 06 8/2/06 Power wash all grounds Inbetween walker jones and the clinic for a event tomorrow |
June 8, 2006 |
August 2, 2006 |
55 days |
| Ronald H. Brown MS |
FM-200623658 06 8/2/06 Marking of field for baseball game on 5/18/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Tyler Elementary School |
FM-200623678 06 8/2/06 Marking of field for baseball game on 5/17/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Tyler Elementary School |
FM-200623659 06 8/2/06 Marking of field for baseball game on 5/18/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Tubman Elementary School |
FM-200501864 05 8/2/06 ;TUBMAN FIRST fl. Girls Restroom Repair faucet on sink |
February 22, 2005 |
August 2, 2006 |
526 days |
| Takoma Educational Center |
FM-200622679 06 8/2/06 Fabricate urinal brackets 8 Total |
May 15, 2006 |
August 2, 2006 |
79 days |
| Takoma Educational Center |
FM-200510422 05 8/2/06 Takoma Fire Code Violation First Floor-Stage Area Stage left floor buckling up tripping hazards F110.1.1 Asbestos Code A - Clear for repairs on 08/17/05. Tidewater - Henry Addison (RG 08/18/05) |
August 15, 2005 |
August 2, 2006 |
352 days |
| Takoma Educational Center |
FM-200510420 05 8/2/06 Takoma Fire Code Violation Thru-Out Water damage see floor plans for more info Asbestos Code A - Clear for repairs on 08/17/05. Tidewater - Henry Addison (RG 08/23/05) (SEE ASSESSMENTS) |
August 15, 2005 |
August 2, 2006 |
352 days |
| Stuart-Hobson Middle School |
FM-200624634 06 8/2/06 open fence for repair work and put back when work is completed |
June 22, 2006 |
August 2, 2006 |
41 days |
| Cardozo High School |
FM-200504686 05 8/2/06 ( CARDOZO ) Third Floor - between 316 - 318 1) Repair broken hand rail, it's off the wall and brakets. |
April 25, 2005 |
August 2, 2006 |
464 days |
| Simon Elementary School |
FM-200623661 06 8/2/06 Marking of field for baseball game on 5/18/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Dunbar High School |
FM-200510908 05 8/2/06 Dunbar Fire Code Violation 5MW-Water leak into the light fixture IFC 110.0 Asbestos Code A - Clear for repairs on 08/22/05. Tidewater - Tony Marcolin (RG 08/23/05) |
August 22, 2005 |
August 2, 2006 |
345 days |
| Seaton Elementary School |
FM-200624488 06 8/2/06 Tenth Street Side Exit Door. "Attempted Break-In" Repair or Replace hardware that was damaged during an attempted break-in. Note: This door cannot be properly secured. |
June 19, 2006 |
August 2, 2006 |
44 days |
| Eliot Junior High School |
FM-200623671 06 8/2/06 Marking of field for baseball game on 5/17/06 |
June 1, 2006 |
August 2, 2006 |
62 days |
| Duke Ellington School |
FM-200515990 05 8/2/06 36 Street Side. Remove bulk trash asap! Note: These items consist of (2) pianos, desk, tables and file cabnets. |
December 2, 2005 |
August 2, 2006 |
243 days |
| Roosevelt High School |
FM-200623859 06 8/2/06 First floor, Main Office. Fabricate & Install a/c tray. |
June 5, 2006 |
August 2, 2006 |
58 days |
| Plummer Elementary School |
FM-200622641 06 8/2/06 First Floor-Girls Restroom: Repair the exterior window grate, it's hanging on one side. Note: Someone may have tried to break in. |
May 15, 2006 |
August 2, 2006 |
79 days |
| Gage-Eckington ES |
FM-200214257 02 8/2/06 Gage-Eckington 2nd Floor Level/Building Exterior Ramp Install gate at top of ramp. |
August 13, 2002 |
August 2, 2006 |
1,450 days |
| Park View ES |
FM-200510175 05 8/2/06 Park View Fire Code Violation Basement / Nurses Office Breech in ceiling Asbestos Code A - Clear for repairs on 08/16/05. Tidewater - Paul Berman (RG 08/18/05) |
August 11, 2005 |
August 2, 2006 |
356 days |
| Oyster Elementary School |
FM-200625127 /3/06 8/2/06 First Floor, Near Main Office/Busted cold water pipe in ceiling, causing damage to ceiling tiles |
July 3, 2006 |
August 2, 2006 |
30 days |
| Noyes Elementary School |
FM-200626676 06 8/2/06 Noyes Fire Code Violation First Floor-Fire extinguisher cabinet glass missing and door is hard to open stage facing right |
August 2, 2006 |
August 2, 2006 |
0 days |
| Noyes Elementary School |
FM-200621791 06 8/2/06 Exit Doors The middle-bar holder needs to be welded. It keeps falling out. |
April 26, 2006 |
August 2, 2006 |
98 days |
| Nalle Elementary School |
FM-200623831 06 8/2/06 Exterior Grounds - Playground Area - Remove fence parts so truck can enter back parking lot where the playground equipment was set on fire. |
June 5, 2006 |
August 2, 2006 |
58 days |
| Harris, C.W. ES |
FM-200508243 05 8/2/06 Harris, C.W. "Fire Code Violation" First Floor Roof is leaking, Ceiling is leaking (IFC 110.1) ACM cementitious fitting (HA057) is located approximately 5ft away from OSY joint on the pipe line where the leak is coming from, please do not disturb. Code A-clear for repair by Tidewater Thomas Johnson on 8/5/05. (SEE ASSESSMENTS) |
July 20, 2005 |
August 2, 2006 |
378 days |
| Nalle Elementary School |
FM-200623830 06 8/2/06 Exterior Grounds - Playground Area - Use torch to cut down burned playground equipment |
June 5, 2006 |
August 2, 2006 |
58 days |
| Nalle Elementary School |
FM-200623828 06 8/2/06 Exterior Grounds - Playground Area - Playground set on fire. Playground equipment burnt down. |
June 5, 2006 |
August 2, 2006 |
58 days |
| Watkins Elementary School |
FM-200621887 06 8/3/06 3rd Floor- Boys Restroom Repair and unclog lavatory. |
April 27, 2006 |
August 3, 2006 |
98 days |
| Watkins Elementary School |
FM-200512837 05 8/3/06 (Watkins) Second floor, Teachers' lounge 1) Replace sink and faucet. |
September 19, 2005 |
August 3, 2006 |
318 days |
| Noyes Elementary School |
FM-200511223 05 8/3/06 Noyes Fire Code Violation First Floor-Fire extinguisher cabinet glass missing and door is hard to open stage facing right |
August 25, 2005 |
August 3, 2006 |
343 days |
| Stanton Elementary School |
FM-200217059 02 8/3/06 Stanton Room 107 first toilet overflowing, second toilet leaking from bottom. |
September 9, 2002 |
August 3, 2006 |
1,424 days |
| Stanton Elementary School |
FM-200218060 02 8/3/06 Stanton 1st, 2nd & 3rd Floor Restrooms [Boys' & Girls'] & Health Suite 1. Tighten all fixtures in all restrooms; and 2. Need was ring on toilet that is lieaking from the bottom in the health suite boys' restroom. |
September 23, 2002 |
August 3, 2006 |
1,410 days |
| Takoma Educational Center |
FM-200625913 06 8/3/06 First Floor/Exit sign O.O.S adjacent to mech. room #4 |
July 19, 2006 |
August 3, 2006 |
15 days |
| Takoma Educational Center |
FM-200625904 06 8/3/06 Third Flooor/Exit sign over door #4 |
July 19, 2006 |
August 3, 2006 |
15 days |
| Bunker Hill Elementary School |
FM-200507862 05 8/3/06 (Bunker Hill) "Fire Code Violation" First Floor-Room 111 Evidence of a roof leak in ceiling (IFC 110.1) |
July 14, 2005 |
August 3, 2006 |
385 days |
| Deal Junior High School |
FM-200619252 06 8/3/06 Fire Code Violation Basement, First, and Second Floor-Exit Lights Not Illuminating (2000 IFC 1010.3) |
March 1, 2006 |
August 3, 2006 |
155 days |
| Takoma Educational Center |
FM-200625909 06 8/3/06 First Floor/Exit sign O.O.S over the exit door leading to the parking lot. |
July 19, 2006 |
August 3, 2006 |
15 days |
| Watkins Elementary School |
FM-200339631 /03 8/3/06 Watkins Forth Floor - Teachers Bathroom 1) Hot water continues to run in the sink, can't cut it off. |
October 29, 2003 |
August 3, 2006 |
1,009 days |
| Stanton Elementary School |
FM-200208764 02 8/4/06 Stanton Annex Girls' Restroom The toilet, 3rd from the window, will not flush. When flushing is tried, the water seems to rise. School in-house staff was unable to successfully snake the toilet out. Asbestos Code A - Clear for repairs on 01/15/03. Horne Engineering - Sherlly James (RG 01/17/03) |
May 31, 2002 |
August 4, 2006 |
1,526 days |
| Tubman Elementary School |
FM-200512086 05 8/4/06 Tubman Emergency Second Floor-Girls Restroom There is a ceiling leak in three places, repair the ceiling leak Asbestos Code A - Clear for repairs on 09/08/05. Tidewater - Tony Marcolin (RG 09/13/05) |
September 8, 2005 |
August 4, 2006 |
330 days |
| Watkins Elementary School |
FM-200501462 05 8/4/06 Watkins Install two faucets one on pot sinkin kitchen the other on lavatory sink. |
February 9, 2005 |
August 4, 2006 |
541 days |
| Watkins Elementary School |
FM-200342166 04 8/4/06 (Watkins) !!!EMERGENCY!!! 1st Floor Kitchen/Cafeteria: Busted hot water tank, water flooding the floor. |
January 2, 2004 |
August 4, 2006 |
945 days |
| Watkins Elementary School |
FM-200333836 03 8/4/06 (Watkins) Custodial Closets/Mop Sinks: Check mop sinks on all floors, There is no water flow from most of them. |
July 28, 2003 |
August 4, 2006 |
1,103 days |
| Watkins Elementary School |
FM-200218344 02 8/4/06 Watkins ****Emergency**** 4th Floor Boys' Restroom The pipe under a Bradley basin is leaking, may have ruptured. The leak is causing flooding across the floor. |
September 26, 2002 |
August 4, 2006 |
1,408 days |
| Tubman Elementary School |
FM-200512251 05 8/4/06 (Tubman) "Emergency" Third floor, Girls' restroom. Water is leaking from 3rd floor girls' restroom into 2nd floor girls restroom source of leak is not known. |
September 9, 2005 |
August 4, 2006 |
329 days |
| Stanton Elementary School |
FM-200203502 02 8/4/06 (Stanton Annex) Annex Building Boys Restroom Boys restroom in the Annex has three urinals which are not working [the water is not on]. The restroom has an odor. |
February 27, 2002 |
August 4, 2006 |
1,619 days |
| Stanton Elementary School |
FM-200218013 02 8/4/06 Stanton Annex ****Emergency**** Asbestos Assessment Reqd. 2nd Floor Teachers' Lounge Restroom A pipe has ruptured inside the back wall, behind the toilets, causing water with a strong sewage odor to penetrate into the principal's office below, causing damage to both the wall and carpeting. The pipe leak needs to be repaired (parents are already complaining of the odor). Asbesstos Code A-clear for repair by Horne Engineer Philip Connolly DCPS Charles E. Buchanan on 9/24/02 |
September 20, 2002 |
August 4, 2006 |
1,414 days |
| Peabody Elementary School |
FM-200626870 06 8/6/06 Peabody Boiler Room Calibrate #2 burner |
August 6, 2006 |
August 6, 2006 |
0 days |
| Peabody Elementary School |
FM-200626871 06 8/6/06 Peabody Boiler Room Repair sump pumps |
August 6, 2006 |
August 6, 2006 |
0 days |
| Peabody Elementary School |
FM-200626872 06 8/6/06 Peabody Boiler Room Repair or replace A.W.F. on #1 and #2 boilers |
August 6, 2006 |
August 6, 2006 |
0 days |
| Randle-Highlands ES |
FM-200626824 06 8/6/06 Ground Floor/Gym (Girls Restroom) - Replace balances and bulbs and reconnect heat detector due to water damage. |
August 4, 2006 |
August 6, 2006 |
2 days |
| Randle-Highlands ES |
FM-200626825 06 8/6/06 Rm. 2B11 - Replace balances and bulbs due to water damage. |
August 4, 2006 |
August 6, 2006 |
2 days |
| Watkins Elementary School |
FM-200512836 05 8/6/06 (Watkins) Second floor, Teachers' lounge. 1) Adjust gas line to properly install stove. |
August 4, 2005 |
August 6, 2006 |
367 days |
| Tyler Elementary School |
FM-200338854 /03 8/7/06 (Tyler) HEALTH CODE VIOLATION: Kitchen: Repair two (2) compartment sink drain. Hand sink is required by DC food codes to have mixing faucets for compliance. |
October 14, 2003 |
August 7, 2006 |
1,028 days |
| Stanton Elementary School |
FM-200219213 /02 8/7/06 (Stanton) !!!EMERGENCY!!! Kitchen supply room: Water leaking from domestic hot water pipes. |
October 10, 2002 |
August 7, 2006 |
1,397 days |
| Stanton Elementary School |
FM-200328996 03 8/7/06 Stanton Third Floor - Girls and Boys Bathroom 1) All toilets are over flowing...seems to be something in line... |
April 24, 2003 |
August 7, 2006 |
1,201 days |
| Stanton Elementary School |
FM-200333075 03 8/7/06 Stanton Ground Floor - Cafeteria 1.Repair leaking sink in the cafeteria . |
July 9, 2003 |
August 7, 2006 |
1,125 days |
| Stanton Elementary School |
FM-200447176 04 8/7/06 Stanton First second, third floor and annex Toilet and urinals threw main building and annex need to be fixed or repaired and maintenance closet on third floor. |
April 26, 2004 |
August 7, 2006 |
833 days |
| Reed LC |
FM-200625244 06 8/7/06 R/R exterior pole lighting on playground area and mezzanine area. |
July 5, 2006 |
August 7, 2006 |
33 days |
| Ketcham Elementary School |
FM-200220784 /02 8/7/06 Ketcham Kitchen Removal of electric socket sticking up out of the floor, people can trip and fall over them. They have not been used in year. |
November 13, 2002 |
August 7, 2006 |
1,363 days |
| Macfarland Middle School |
FM-200624627 06 8/7/06 replace fence at drive way it is about 90 feet of fence |
June 22, 2006 |
August 7, 2006 |
46 days |
| Sousa Middle School |
FM-200622378 9/06 8/7/06 Outside- Parking Lot Remove graffitti from the parking lot steps. |
May 9, 2006 |
August 7, 2006 |
90 days |
| Sousa Middle School |
FM-200621195 06 8/7/06 Playground Area/Repair fence that is bent due to a break in. |
April 11, 2006 |
August 7, 2006 |
118 days |
| Bunker Hill Elementary School |
FM-200453528 04 8/7/06 Bunker Hill 1) Repair plumbing in all areas of the building. |
August 27, 2004 |
August 7, 2006 |
710 days |
| Wilson J. O. ES |
FM-200624005 06 8/7/06 6th St Side Of Building - Repair or replace Fence, there is a big hole in the fence |
June 7, 2006 |
August 7, 2006 |
61 days |
| Wilson J. O. ES |
FM-200624004 06 8/7/06 Parking Lot On 7th St Side Of Building - Repair or replace Gate Has Been Knocked Down, |
June 7, 2006 |
August 7, 2006 |
61 days |
| Bowen Elementary School |
FM-200453455 04 8/7/06 Bowen Location Unknown 1) Install wall hung water cooler . |
August 27, 2004 |
August 7, 2006 |
710 days |
| Watkins Elementary School |
FM-200340154 /03 8/7/06 (Watkins) !!!EMERGENCY!!! Through-Out Building: There is a gas leak (smell) through-out the building. |
November 10, 2003 |
August 7, 2006 |
1,001 days |
| Winston EC |
FM-200206855 02 8/8/06 1st Floor 1-2 Center & Garage Trace water is leaking through the ceiling into the 1st floor, wetting the area and the garage. Water comes through when it rains. Need to identify source of run-off and repair. |
April 30, 2002 |
August 8, 2006 |
1,561 days |
| Walker-Jones EC |
FM-200622384 06 8/8/06 Playground Area. Weld slide pole to playground equipment. |
May 9, 2006 |
August 8, 2006 |
91 days |
| Shaed Elementary School |
FM-200442979 04 8/8/06 Shaed Front door The door will not secure at all. Code A-clear for repair by DCPS Charles Buchanan on 01/21/04 |
January 20, 2004 |
August 8, 2006 |
931 days |
| Seaton Elementary School |
FM-200506842 05 8/8/06 Seaton Rear of Building Repair damage caused by Break-in |
June 16, 2005 |
August 8, 2006 |
418 days |
| Aiton Elementary School |
FM-200626940 06 8/8/06 1st Floor- Main Office- Nurse's Suite Move outlet for copier. Note: Copier is needed as soon as possible for teachers to service students. |
August 7, 2006 |
August 8, 2006 |
1 day |
| Birney Elementary School |
FM-200624910 06 8/8/06 2nd Floor- Boy's Bathroom on both the Old Side & New Side Bathrooms need the hardware replaced. |
June 27, 2006 |
August 8, 2006 |
42 days |
| Winston EC |
FM-200503691 05 8/8/06 (Winston) OPEN TWO(2)CLOGGED OUTSIDE DRAINS. IN FRONT OF BLDG. UNDER CANOPY / RUN-OFF CAUSING SOIL EROSION |
April 7, 2005 |
August 8, 2006 |
488 days |
| Birney Elementary School |
FM-200500490 05 8/8/06 BIRNEY FIRST FL. BOYS BATHROOM REMOUNT SINK TO THE WALL Asbestos Code A - Clear for repairs on 10/27/05. Tidewater - Carlos Vera (RG 10/28/05) |
January 14, 2005 |
August 8, 2006 |
571 days |
| Plummer Elementary School |
FM-200618222 06 8/8/06 Inspection or preventive maintenance on playground equipment. |
February 2, 2006 |
August 8, 2006 |
187 days |
| Winston EC |
FM-200228185 03 8/8/06 (Winston) 3rd Fl. Gym / 2nd Fl. Library R/R- Need cover plates for exposed floor recepticles. |
April 2, 2003 |
August 8, 2006 |
1,224 days |
| Winston EC |
FM-200451289 04 8/8/06 (Winston) 3/4 Center/Open Space: Sinks over-flowing, backing up. |
August 2, 2004 |
August 8, 2006 |
736 days |
| Winston EC |
FM-200455292 04 8/8/06 Winston EMERGENCY There is a gas smell in the garage and it is very strong. Believe someone pulled gas in the sewage. |
September 21, 2004 |
August 8, 2006 |
686 days |
| Winston EC |
FM-200504753 05 8/8/06 (Winston) Asbestoa Assessment Required. Repair garbage disposal. Not working properly. (Health Inspection Report). April 26, 2005: We have not received a health inspection report in this office. |
April 21, 2005 |
August 8, 2006 |
474 days |
| Lafayette Elementary School |
FM-200623410 06 8/8/06 Repair the wall on the left side of the building next to the steps. Exterior/Brick |
May 26, 2006 |
August 8, 2006 |
74 days |
| Woodson High School |
FM-200617459 06 8/8/06 Fifth Floor - Barber Shop - Install (1) a/c unit in this classroom due to poor ventilation... |
January 17, 2006 |
August 8, 2006 |
203 days |
| Maury Elementary School |
FM-200501699 05 8/8/06 (Maury) 1st Floor/Main Office: Install electric control switch for heating, and a.c. unit. Code A-clear for repair by DCPS Charles Buchanan on 2/22/05 |
February 16, 2005 |
August 8, 2006 |
538 days |
| Stanton Elementary School |
FM-200451115 04 8/8/06 Stanton EMERGENCY Maintenance closet need to be unstopped on 3rd floor, Drain in kitchen stopped up, sink in maintenance office stopped up, annex sink utility in boys bathroom stopped up, outside drain near the entrance of 25th Street, Main building basement floor boys bathroom urinal stopped up, Ms. Sutherlands room toilet by wall need waxring, Replace commode in A-2. |
July 29, 2004 |
August 8, 2006 |
740 days |
| Stanton Elementary School |
FM-200449817 04 8/8/06 (Stanton) 1st Floor/Room #107 Repair or replace sink fixture, and valve that will not stop water from running. |
June 25, 2004 |
August 8, 2006 |
774 days |
| Stanton Elementary School |
FM-200449744 04 8/8/06 Stanton Portable cooler need installed are rooms 103 and 209. Room with no unit are Mr. Lavry A-13, 301, 313, 304 and 310. Cooler non working are rooms 212 and 210. |
June 24, 2004 |
August 8, 2006 |
775 days |
| Stanton Elementary School |
FM-200452629 04 8/8/06 Stanton EMERGENCY Room 106 sink need to be unstopped, girls bathroom in the annex. (sink, also need to be unstopped), Maintenance bathroom floor boys sink, need to be unstopped. Also boys bathroom 3rd floor urinal is broken. |
August 13, 2004 |
August 8, 2006 |
725 days |
| Stanton Elementary School |
FM-200442441 04 8/8/06 Stanton Annex, First, second and third floors Toilets and urinals through main building and annex need to be fix or repaired, and maintenance closet on third floor. |
January 9, 2004 |
August 8, 2006 |
942 days |
| Stanton Elementary School |
FM-200456059 04 8/8/06 Stanton Second floor boys bathroom Fixtures have been broken by students need fixing. |
September 29, 2004 |
August 8, 2006 |
678 days |
| Stanton Elementary School |
FM-200512921 05 8/8/06 Provide (5) filters for water coolers |
September 20, 2005 |
August 8, 2006 |
322 days |
| Draper Elementary School |
FM-200220805 /02 8/9/06 Draper Cafeteria Two sinks leaking need repair or replacement. Toilet in kitchen faulty. Faucets and waste lines are leaking. |
November 13, 2002 |
August 9, 2006 |
1,365 days |
| Nalle Elementary School |
FM-200623170 06 8/9/06 Basement (old bldg.)-Exit signs turned the wrong way, hallway through cafeteria |
May 23, 2006 |
August 9, 2006 |
78 days |
| Randle-Highlands ES |
FM-200509726 05 8/9/06 Randle-Highland Fire Code Violation - IFC - 901.6 Basement Floor - Room 2B01 1) Emergency lights not working. |
August 8, 2005 |
August 9, 2006 |
366 days |
| Draper Elementary School |
FM-200505574 05 8/9/06 (Draper) HEALTH CODE VIOLATION: 1) Repair leaking faucets on 2 compartment sinks. |
May 17, 2005 |
August 9, 2006 |
449 days |
| Draper Elementary School |
FM-200502350 05 8/9/06 Wilson Rm 300 Replace Classroom Door Draper Second fl. Boy's Restroom Unstop Toilets and Urnials, Repair Flush Valves |
March 8, 2005 |
August 9, 2006 |
519 days |
| Winston EC |
FM-200624972 06 8/9/06 Third Floor/Exit light out exit door to parking lot |
June 28, 2006 |
August 9, 2006 |
42 days |
| John Burroughs ES |
FM-200620037 06 8/9/06 Water fountain has hot water coming out and keep running none stop. |
March 15, 2006 |
August 9, 2006 |
147 days |
| Merritt Middle School |
FM-200626760 06 8/9/06 4th Floor- Learning Center Remove outlet |
August 3, 2006 |
August 9, 2006 |
6 days |
| Draper Elementary School |
FM-200442729 04 8/9/06 Draper 112 room kgn. and Room 111 Pre-K Replace toilets it leaking. |
January 14, 2004 |
August 9, 2006 |
938 days |
| Winston EC |
FM-200624990 06 8/9/06 Second Floor/Exit lights are not illuminating in classroom area |
June 29, 2006 |
August 9, 2006 |
41 days |
| Orr Elementary School |
FM-200624897 06 8/9/06 Fourth Floor/Electrical cover plate: (Missing) |
June 27, 2006 |
August 9, 2006 |
43 days |
| Draper Elementary School |
FM-200225267 03 8/9/06 Draper Kitchen There are pin holes that are in the pipes. Water is pouring from the bottom of sink. |
February 5, 2003 |
August 9, 2006 |
1,281 days |
| Draper Elementary School |
FM-200224720 03 8/9/06 Draper Second Floor - Next to Boys Bathroom 1) Unstop sink. |
January 28, 2003 |
August 9, 2006 |
1,289 days |
| Jefferson JHS |
FM-200339131 /03 8/9/06 (Jefferson) Need keys re made for doors through building. |
October 17, 2003 |
August 9, 2006 |
1,027 days |
| Truesdell Elementary |
FM-200625778 06 8/9/06 Sub Basement/Exposed Wiring x2 At Ceiling Level Electrical junction box in ceiling missing cover. Also, telephone box not covered. |
July 17, 2006 |
August 9, 2006 |
23 days |
| John Burroughs ES |
FM-200624936 06 8/9/06 Main Floor- Courtyard The outside drain needs to be unclogged. |
June 28, 2006 |
August 9, 2006 |
42 days |
| Draper Elementary School |
FM-200514298 /05 8/9/06 Draper Pre-Kgn - Room 111 1) Replace flus valves. Water will not stop running. |
October 23, 2005 |
August 9, 2006 |
290 days |
| Watkins Elementary School |
FM-200627154 06 8/9/06 First Floor/Female Restroom In The Rec Office & Female Restroom In Hallway, Toilets Are Clogged & Backing Up Through The Kitchen Floor Drains. |
August 9, 2006 |
August 9, 2006 |
0 days |
| Ronald H. Brown MS |
FM-200626986 06 8/9/06 Second Floor - Restore electrical service to disconnected air handle unit # 10. |
August 8, 2006 |
August 9, 2006 |
1 day |
| Aiton Elementary School |
FM-200623387 06 8/9/06 Second Floor/Teacher's Lounge - An outlet needs to be installed for the copy machine to work, the copy machine is being moved from the Nurse Suite Asbestos Code A - Clear for repairs on 05/31/06. Tidewater - Kenny Long(RG 06/01/06) |
May 26, 2006 |
August 9, 2006 |
75 days |
| Randle-Highlands ES |
FM-200625838 06 8/9/06 Ground Floor/Exit sign missing, Cafeteria exit toward Gym. |
July 18, 2006 |
August 9, 2006 |
22 days |
| Peabody Elementary School |
FM-200515435 /05 8/10/06 Peabody Boiler room Replace the gas pressure switch on the # 2 boiler |
November 15, 2005 |
August 10, 2006 |
268 days |
| Peabody Elementary School |
FM-200515436 /05 8/10/06 Peabody Boiler room Asbestos assessment required Replace ruptured 2" return line on the rear of # 2 boiler. Asbestos Code A - Clear for repairs on 11/16/05. Tidewater - Kenny Long |