| School | Description | Open Date | Close Date | Time Elapsed |
| Thomson Elementary School | FM-200117920 01 8/24/01 (THOMSON) FIRE CODE VIOLATION:F PAGE (2 OF 2) BASEMENT/NEXT TO GIRLS BATHROOM: EXPOSED WIRING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/21/01 RONALD EDWARDS - SAFETY -(202)576-6693 | August 20, 2001 | August 24, 2001 | 4 days |
| John Burroughs ES | FM-200106531 23/01 8/24/01 BURROUGHS LOWER LEVEL - CORRIDOR INSTALL WATER AND ELECTRICAL CONNECTIONS TO WALL MOUNT FOUNTAIN. PRESENTLY UNABLE TO USE. ALSO INSTALL WATER FILTERS. LOCATION: CORRIDOR NEAR BOYS RESTROOM. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/09/01. | March 23, 2001 | August 24, 2001 | 154 days |
| Janney Elementary School | FM-200111536 01 8/24/01 JANNEY FIRST FLOOR BOYS AND GIRLS RESTROOMS 1) REPLACE EIGHTEEN (18) HOT AND COLD PUSH TYPE FAUCET FIXTURES WITH TURN TYPE PUSH TYPE GETS STUCK AND TOPS COME OFF. PRESENT FIXTURES ARE CHICAGO FAUCETS. | May 30, 2001 | August 24, 2001 | 86 days |
| Powell Elementary School | FM-200116481 01 8/24/01 POWELL 1ST FLOOR BOYS RESTROOM ASBESTOS ASSESSMENT REQUIRED NEAR PLAYGROUND EXIT. BOYS RESTROOM THE THIRD & FIFTH URINALS ARE CLOGGED UP. TRIED TO UNCLOG WITHOUT SUCCESS. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY LM. 8/6/01 | August 1, 2001 | August 24, 2001 | 23 days |
| West Elementary School | FM-200106419 01 8/24/01 WEST FIRST (1ST) FLOOR - GIRLS BATHROOM BY GYMNASIUM FOUR (4) BOLT WALL TOILET NEED RUBBER RING. WATER LINK BEHIND TOILET. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/11/01. | March 21, 2001 | August 24, 2001 | 156 days |
| Beers Elementary School | FM-200116703 01 8/24/01 BEERS CAFETERIA ASBESTOS ASSESSMENT REQUIRED PLUMBING - BOYS BATHROOM HAND BOWL NEED TO BE MOUNTED TO THE WALL. NEED ATTENTION SOON AS POSSIBLE. HAZARD ASBESTOS ASSESSMET- CODE A (08-07-01) | August 3, 2001 | August 24, 2001 | 21 days |
| Beers Elementary School | FM-200116627 01 8/24/01 BEERS BLDG. 2 - 1ST& 2ND FLOOR ASBESTOS ASSESSMENT REQUIRED BOYS URINALS ARE NOT DRAINING, AND ODOR IS COMING FROM IT. TRIED TO PLUDGED THEM. UNSTOP URINALS IN BOYS BATHROOM ON 1ST , 2ND FLOOR. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY LM 8/7/01. | August 3, 2001 | August 24, 2001 | 21 days |
| Cardozo High School | FM-200118380 01 8/29/01 (CARDOZO) !!!!EMERGENCY!!!! GROUND FLOOR/BOYS RESTROOM: SNAKE OUT THREE (3) URINALS, BACKING UP. | August 24, 2001 | August 29, 2001 | 5 days |
| Anacostia Senior High School | FM-200118589 01 8/29/01 (ANACOSTIA) !!!!!!!!!!! EMERGENCY !!!!!!!!!!!!!!! 1ST FLOOR/ BOYS BATHROOM URINALS ARE STOPPED UP. | August 28, 2001 | August 29, 2001 | 1 day |
| Ludlow-Taylor ES | FM-200117962 01 8/29/01 (LUDLOW-TAYLOR) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/GIRLS BATHROOM: REPAIR DEFECTED LIGHT FIXTURE, HANGING. POC: R. THORNTON/W. HOLLIS. PHONE: 698-3244 CODE A CLEAR FOR REPAIR BY HORNE ENG. RAY AGNANT) 08-24-01 | August 21, 2001 | August 29, 2001 | 8 days |
| Jessie LaSalle Elementary | FM-200117851 01 8/31/01 (LASALLE) ASBESTOS ASSESSMENT REQ. ALL FLOORS, ALL BATHROOMS UNSTOP TOILETS. OUTSIDE DRAIN NEEDS TO BE UNSTOP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/22/01 HORNE ENGINEERS- DONALD MAGLIENTI | August 20, 2001 | August 31, 2001 | 11 days |
| Peabody Elementary School | FM-200117126 01 8/31/01 (PEABODY) 1. ASBESTOS ASSESSMENT REQUIRED. BASEMENT AND 1ST FLOOR: REPAIR OR REPLACE WATER FOUNTAIN AND COOLER IN THE FOLLOWING AREA: 1ST FLOOR HALLWAY, & BASEMENT CORRIDOR ADJACENT TO BATHROOM. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 08/13/01. SYLVIA GRIMES - SAFETY (202)576-5583 | August 10, 2001 | August 31, 2001 | 21 days |
| Cardozo High School | FM-200117090 01 8/31/01 (CARDOZO) 1. ASBESTOS ASSESSMENT REQUIRED. GROUND LEVEL/GIRLS BATHROOM: REPLACE THE WAX RING AND TOILET FLANGE; WATER LEAKING AND FLOODING FLOORS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 08/13/01. SYLVIA GRIMES - SAFETY (202)576-5583 | August 10, 2001 | August 31, 2001 | 21 days |
| Stuart-Hobson Middle School | FM-200117134 01 9/4/01 (STUART-HOBSON) 1. ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR/NEAR BOYS BATHROOM: WATER FOUNTAIN CONSTANTLY RUNNING, MAKING A LOT OF NOISE. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 08/13/01. SYLVIA GRIMES - SAFETY (202)576-5583 | August 10, 2001 | September 4, 2001 | 25 days |
| Johnson JHS | FM-200118981 01 9/4/01 JOHNSON BASEMENT, FIRST (1ST), SECOND (2ND), THIRD AND FOURTH (4) FLOOR. BOYS AND GIRLS RESTROOM BACK-UP IN COMMODES AND URINALS. ISOLATE EMERGENCY!!! | September 1, 2001 | September 4, 2001 | 3 days |
| Cooke H.D. Elementary School | FM-200118744 01 9/4/01 (COOKE, H.D.) 1ST FLOOR/ NEW WING BOYS BATHROOM REPAIR BOYS URINALS- SLOW DRAINAGE AND THE PRESSURE IS VERY LOW. (T-9) | August 29, 2001 | September 4, 2001 | 6 days |
| Clark Elementary School | FM-200114210 01 9/4/01 CLARK FIRST, SECOND, AND THIRD FLOOR BOYS RESTROOM 1) NO WATER IN SINKS EMERGENCY!! | June 28, 2001 | September 4, 2001 | 68 days |
| Garnet-Patterson MS | FM-200118625 01 9/4/01 (GARNET-PATTERSON) 2ND AND 3RD FLOORS HEALTH SUITE / TEACHERS LOUNGE !!!!!!!!!ISOLATE EMERGENCY!!!!!!!!! NO WATER FLOWING IN THE RESTROOM AND FAUCET. (LOW PRESSURE). | August 28, 2001 | September 4, 2001 | 7 days |
| Stuart-Hobson Middle School | FM-200107834 01 9/6/01 STUART-HOBSON ASBESTOS ASSESSMENT REQUIRED BATHROOMS ON 3RD FLOOR. DEMOLISH AND REMOVE FLOORING. # HRGM CORP. POC: JOHN RIDGLEY-202-253-8370 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. | April 9, 2001 | September 6, 2001 | 150 days |
| John Burroughs ES | FM-200117638 01 9/7/01 (BURROUGHS) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS BATHROOM SINK KNOBS ARE MISSING AND SINK WATER RUNS. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY RONALD EDWARD 8/18/01. (CEB) | August 16, 2001 | September 7, 2001 | 22 days |
| Johnson JHS | FM-200117493 01 9/7/01 JOHNSON BATHROOM - B WING AREA ASBESTOS ASSESSMENT REQUIRED EMERGENCY!!!!!!!!!!!!! BATHROOM TOILETS & UTILITY SINKS ARE CLOGGED UP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/29/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A - CLEAR FOR REPAIR ON 10/03/01, BY EDWARD RODRIGUEZ - HORNE ENGINEERING (RE-10/04/01) | August 15, 2001 | September 7, 2001 | 23 days |
| Watkins Elementary School | FM-200111456 01 9/7/01 WATKINS THIRD FLOOR BOYS RESTROOM 1) URINALS STOPPED UP PLUMBER REQUIRED TO SNAKE ASBESTOS CODE A-CLEAR FOR REPAIR URINAL LEAK IS CAUSE DAMAGE TO PLASTER CEILING IN BOYS TOILET ON SECOND FLOOR. INVESTIGATED BY CHARLES E BUCHANAN ON 6/5/01 | May 29, 2001 | September 7, 2001 | 101 days |
| John Burroughs ES | FM-200117642 01 9/7/01 (BURROUGHS) ASBESTOS ASSESSMENT REQ. BASEMENT/ BOYS BATHROOM SINK KNOBS ARE MISSING AND 3RD URINAL WATER RUNS. CODE A-CLEAR FOR REPAIR BY RONALD EDWARDS. CEB | August 16, 2001 | September 7, 2001 | 22 days |
| Kimball Elementary School | FM-200118105 01 9/10/01 (KIMBALL) ASBESTOS ASSESSMENT REQD. 1ST. FLOOR NEW WING BOYS BATHROOM ONE SINK NEEDS TO BE REPAIRED WHEN YOU TURN THE KNOB FOR HOT WATER IT RUNS CONTINUOUSLY ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 | August 22, 2001 | September 10, 2001 | 19 days |
| Shepherd ES | FM-200114982 01 9/10/01 SHEPHERD 1ST FL. & 2ND FL. 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 1-1/2" STEAM LINE THROUGH FL. TO TUNNEL IN 1ST FL. BOYS RESTROOM NEXT TO ROOM 102. 3. REPAIR PLASTER CEILING IN BOYS RESTROOM BY ROOM 102 AND FLOOR PATCH CONCRETE FLOOR IN 2ND FL. BOYS RESTROOM ABOVE 1ST FL. RESTROOM BY ROOM 102. HORNE ENG ASSESSED UNDER FM-200100533 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/10/01. | July 10, 2001 | September 10, 2001 | 62 days |
| Dunbar High School | FM-200117447 01 9/10/01 DUNBAR FIRST AND SECOND FLOOR MENS AND WOMEN RESTROOMS OUTSIDE OF ARMORY AREA (LOBBY), IN THE CORRIDOR ACROSS FROM THE AUDITORIUM,THE MEDIA CENTER,AND TEACHERS LOUNGE. 1) REPAIR OR REPLACE FLUSH VALVES IN THE ABOVE AREAS. | August 14, 2001 | September 10, 2001 | 27 days |
| Dunbar High School | FM-200117728 01 9/13/01 (DUNBAR) ASBESTOS ASSESSMENT REQ. FIELD RESTROOMS REPAIR COMMODES, FLUSH VALVES, SINK TRAPS, FAUCETS, AND SNAKE OUT DRAIN LINES. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY CEB. 8/21/01. | August 17, 2001 | September 13, 2001 | 27 days |
| Wilkinson ES | FM-200118137 01 9/13/01 (WILKINSON) ASBESTOS ASSESSMENT REQD. 2ND. FLOOR BOYS BATHROOM. 1-80 FLUSH VALVE FOR BOYS URINAL. CODE A-CLEAR FOR REPAIR BY HORNE ENG BIPIN NANAVATY 8/25/01. | August 22, 2001 | September 13, 2001 | 22 days |
| Kimball Elementary School | FM-200118107 01 9/13/01 (KIMBALL) ASBESTOS ASSESSMENT REQD. 2ND. FLOOR OPEN SPACE TEACHER BATHROOM ONE SINK NEEDS TO BE REPAIRED WHEN YOU TURN THE KNOB FOR HOT WATER IT RUNS CONTINUOUSLY ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 | August 22, 2001 | September 13, 2001 | 22 days |
| Wilkinson ES | FM-200118143 01 9/13/01 (WILKINSON) ASBESTOS ASSESSMENT REQD. 2ND. FLOOR BOYS BATHROOM. NEED TO REPLACE 2-110 FLUSH VALVE FOR URINAL CODE A-CLEAR FOR REPAIR BY HORNE ENG BIPIN NANAVATY 8/25/01. | August 22, 2001 | September 13, 2001 | 22 days |
| Kimball Elementary School | FM-200118115 01 9/13/01 (KIMBALL) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ OPEN SPACE BOYS BATHROOM ONE SINK NEEDS TO BE REPAIRED MISSING THE DRAIN TRAP (ASAP). CODE A-CLEAR FOR REPAIR BY HORNE ENG BIPIN NANAVATY 8/25/01. | August 22, 2001 | September 13, 2001 | 22 days |
| Wilkinson ES | FM-200118147 01 9/13/01 (WILKINSON) ASBESTOS ASSESSMENT REQD. 1ST. FLOOR KGN AREA GIRLS BATHROOM. NEED 2 SPUD FOR COMODE 110 FLUSH VALVE CODE A-CLEAR FOR REPAIR BY RONALD EDWARDS 8/25/01. | August 22, 2001 | September 13, 2001 | 22 days |
| Barnard Elementary School | FM-200106787 /01 9/14/01 BARNARD NEAR GIRLS RESTROOM 1ST FLOOR BUSTED STEAM LINE FIRST FLOOR NEAR GIRLS RESTROOM. IT CORP. CODE A- ASBESTOS ABATED ON 3/31/01. | March 28, 2001 | September 14, 2001 | 170 days |
| Ballou Senior High School | FM-200112300 01 9/15/01 BALLOU BASEMENT BOYS RESTROOM REPLACE ONE BROKEN AND LEAKING PNEUMATIC VALVE ON HW & CW FEEDWATER SUPPLY LINE. NOTE: LEAKING PNEUMATIC VALVE IS DAMAGING CEILING AREA. WP-200108521 | June 4, 2001 | September 15, 2001 | 103 days |
| Stevens Elementary School | FM-200114264 01 9/17/01 STEVENS LOWER LEVEL GIRLS RESTROOM 1) REPAIR TWO (2) DOOR COMING OFF HINGES ASBESTOS CODE A-CLEAR FOR REPAIR BY CHARLES E. BUCHANAN ON 6/29/01. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/14/01BY DCPS SAFETY RONALD EDWARD. | June 28, 2001 | September 17, 2001 | 81 days |
| Noyes Elementary School | FM-200119762 01 9/17/01 NOYES 1ST FLOOR MAIN OFFICE, 101 AUDITORIUM, GIRLS RESTROOM 123, ROOM 221, GIRLS RESTROOM, ROOM 218, ROOM 202 MOVE WATER COOLER NEAR ABOVE LOCATIONS. THEY ARE ALREADY DETACHED AND ON THE FLOOR. | September 13, 2001 | September 17, 2001 | 4 days |
| Payne Elementary School | FM-200102179 01 9/17/01 PAYNE FIRST (1ST) FLOOR - WOMENS RESTROOM NEW WING REPLACE HANDICAP RAIL TO AID TEACHER WITH A DISABILITY. MT-20001365 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/11/01. MR. LEROY MINTON - SAFETY (202)576-6691 | January 25, 2001 | September 17, 2001 | 235 days |
| Bell High School | FM-200117780 01 9/19/01 (BELL) 1. ASBESTOS ASSESSMENT REQUIRED. 3RD FLOOR/MALE TEACHERS RESTROOM. NEED NEW TOILET, ALSO, REPLACE FAUCETS ON ALL FLOORS/BOYS AND GIRLS BATHROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/27/01. RONALD EDWARDS - SAFETY (202)576-6693 | August 17, 2001 | September 19, 2001 | 33 days |
| Johnson JHS | FM-200119087 01 9/19/01 (JOHNSON) 2ND FLOOR/OUT SIDE GIRLS BATHROOM: NEW WATER COOLERS WERE INSTALLED TWO (2) WEEKS AGO. WATER COOLERS ARE LEAKING PROFUSELY, FLOODING THE AREA. | September 4, 2001 | September 19, 2001 | 15 days |
| Harris, C.W. ES | FM-200120079 01 9/19/01 HARRIS, C.W. SECOND FLOOR - GIRLS BATHROOM- 5-6 WING 1) STOP VALVE POPPED ON TOILET, WATER CONSTANTLY RUNNING. EMERGENCY!! | September 18, 2001 | September 19, 2001 | 1 day |
| Meyer Elementary School | FM-200119360 01 9/19/01 (MEYER) ASBESTOS ASSESSMENT REQ. BASEMENT/ GIRLS BATHROOM NEED (5) FIVE NEW SPUDS IN THE GIRLS BATHROOM, THEY ARE LEAKING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/10/01. LEROY MINTON - SAFETY (202)576-6693 | September 7, 2001 | September 19, 2001 | 12 days |
| Meyer Elementary School | FM-200119361 01 9/19/01 (MEYER) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BATHROOM NEED (2) TWO NEW SPUDS IN THE GIRLS BATHROOM, AND WE HAVE A CRACKED TOILET IN THE BOYS BATHROOM. ALSO NEED (2) TWO NEW WAX-RING IN THE BOYS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/10/01. LEROY MINTON - SAFETY (202)576-6693 | September 7, 2001 | September 19, 2001 | 12 days |
| Webb Elementary School | FM-200113808 01 9/19/01 WEBB FIRST FLOOR EXIT DOOR 1) REPLACE BROKEN DOOR CLOSURE NEAR GIRLS RESTROOM ASBESTOS CODE A-CLEAR FOR REPAIRS ON 06/22/01. RONALD EDWARDS - SAFETY (202)576-6693 | June 22, 2001 | September 19, 2001 | 89 days |
| Bell High School | FM-200118656 01 9/19/01 (BELL) 3RD FLOOR/ BOYS RESTROOM REPAIR CRACKED WALL HUNG COMMODE. URGENT REQUEST!!!!!! ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 | August 28, 2001 | September 19, 2001 | 22 days |
| Orr Elementary School | FM-200110104 01 9/21/01 ORR FIRST (1ST) FLOOR - UNISEX RESTROOM REPLACE LOCK ON RESTROOM DOOR | September 21, 2001 | September 21, 2001 | 0 days |
| John Burroughs ES | FM-200119579 01 9/21/01 (BURROUGHS) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS BATHROOM KNOB IS MISSING OFF THE SINK FAUCETS IS LEAKING WATER. WONT STOP RUNNING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/11/01. LEROY MINTON - SAFETY (202)576-6693 | September 10, 2001 | September 21, 2001 | 11 days |
| Reed LC | FM-200103275 5 2/8/01 9/21/01 REED 2nd FLOOR BOYS BATHROOM INSTALL ONE NEW SINK WITH FLOOR SUPPORT. ASBESTOS CODE A-CLEAR FOR REPAIR. HORNE ENG. BIPIN NANANATY 9/6/01. | February 8, 2001 | September 21, 2001 | 225 days |
| Thomas Elementary School | FM-200107135 01 9/25/01 THOMAS BASEMENT RESTROOM REPAIR RESTROOM DOOR AND REPLACE LOCK. LADIES & GENTLEMEN USE RESTROOM. REPLACE PARTITION DOORS IN BOYS & GIRLS RESTROOMS. 2ND FLOOR BOYS - 2 STALLS 3RD FLOOR BOYS - 3 STALLS 3RD FLOOR GIRLS - 2 STALLS ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/09/01. | April 2, 2001 | September 25, 2001 | 176 days |
| Ross Elementary School | FM-200109538 01 9/25/01 ROSS SECOND (2ND) FLOOR - TOP FLOOR FROM MAIN OFFICE EAST SIDE OF BUILDING 1) ASBESTOS ASSESSMENT REQUIRED 2) HAND RAILING HAS COME OFF THE SIDE OF THE WALL. THE RAIL IS INSIDE THE TEACHERS RESTROOM. EMERGENCY! SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS 0N 05/03/01. | May 3, 2001 | September 25, 2001 | 145 days |
| Moten Elementary School | FM-200116061 01 9/25/01 MOTEN 1ST FLOOR BOY BATHROOM ASBESTOS ASSESSMENT REQUIRED URINALS NEED REPAIR / REPLACE CONTROL STOP VALVE IN TWO (2) URINALS, NO ISOLATION VALVES. CODE A - CLEAR FOR REPAIRS AS OF 7/30/01 PER LEROY MINTON (SG). | July 27, 2001 | September 25, 2001 | 60 days |
| Eaton Elementary School | FM-200113789 01 9/26/01 EATON 1) FURNISH (1) CHANGE KEY FOR INTERIOR BOILER ROOM DOOR AND ONE KEY FOR ROOM 117 (BATHROOM). | September 24, 2001 | September 26, 2001 | 2 days |
| Backus Middle School | FM-200120001 01 9/26/01 (BACKUS) 1. ASBESTOS ASSESSMENT REQUIRED. 3RD FLOOR/TEACHERS BATHROOM: FOREIGN OBJECT STUCK IN LOCK, UNABLE TO RETRIEVE. NO ACCESS TO BATHROOM FOR TEACHERS/STAFF. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/17/01. LEROY MINTON - SAFETY (202)576-6691 | September 24, 2001 | September 26, 2001 | 2 days |
| Benning Elementary School | FM-200116215 01 9/26/01 (BENNING) FIRE CODE VIOLATION: F-608.5 PAGE (2 OF 4) 1. ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR/BOYS BATHROOM: LOCK NOT WORKING ON DOOR BY BOYS BATHROOM, CENTER (2). ASBESTOS CODE A-CLEAR FOR REPAIR BY L MINTON DCPS . ON 9/10/01 | September 24, 2001 | September 26, 2001 | 2 days |
| Moten Elementary School | FM-200102943 01 9/26/01 MOTEN 1ST & 2ND FLOOR RESTROOM REPAIR VENTS IN RESTROOM. RESTROOM VENTS IS NOT COMPLETE ON FIRST FLOOR AND SECOND FLOOR7/701 | February 5, 2001 | September 26, 2001 | 233 days |
| Thomas Elementary School | FM-200106933 01 9/26/01 THOMAS FIRST (1ST) FLOOR - NEW WING BOYS GYM RESTROOM EXTERIOR DOOR KNOB NEEDS LOCKS URGENT. | September 24, 2001 | September 26, 2001 | 2 days |
| Meyer Elementary School | FM-200120048 01 9/27/01 (MEYER) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ TEACHERS BATHROOM THE TEACHERS BATHROOM HOT WATER DOES NOT WORK. THE TEACHERS ARE COMPLAINING THAT THEY NEED HOT WATER TO WASH THEIR HANDS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/20/01. RICHARD E GIBSON - SAFETY (202)576-5584 | September 18, 2001 | September 27, 2001 | 9 days |
| Aiton Elementary School | FM-200118565 01 10/1/01 (AITON) 3RD FLOOR/BOYS RESTROOM CONVECTOR FRAME NEEDS TO BE REPLACED IN RESTROOM. CODE A - CLEAR FOR REPAIRS AS OF 9/24/01. STEPAHEN CALDWELL HORNE ENG. | August 28, 2001 | October 1, 2001 | 34 days |
| Terrell Mc ES | FM-200119161 01 10/2/01 (TERRELL, M.C.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR / GIRLS GYM RESTROOM REPLACE (1) 1 1/2 SPUD AND WASHER ON TOILET. REPAIR (2) BRADLEY BASINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/05/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | September 5, 2001 | October 2, 2001 | 27 days |
| Birney Elementary School | FM-200120546 01 10/2/01 BIRNEY THIRD (3RD) FLOOR - BOYS RESTROOM 1) ASBESTOS ASSESSMENT REQUIRED. 2) BUSTED PIPES BEHINDED WALL CONNECTED TO ONE OF THE URINALS. EMERGENCY!!!! CODE A - ASBESTOS ABATED ON 9/26/01 (SG) SYLVIA GRIMES (202) 576-5583. | September 26, 2001 | October 2, 2001 | 6 days |
| West Elementary School | FM-200119791 01 10/9/01 (WEST) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS BATHROOM ON THE LEFT SIDE OF THE LEARNING CENTER WALL TOILET LEAKS ON TO FLOOR WHEN IT IS FLUSHED. IT LEAKS FROM BEHIND THE TOILET. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/19/01. LEROY MINTON - SAFETY (202)576-6691 | September 14, 2001 | October 9, 2001 | 25 days |
| Macfarland Middle School | FM-200115802 01 10/9/01 MACFARLAND THIRD (3RD) FLOOR - BOYS RESTROOM CHECK ALL URINALS WATER PRESSURE IS VERY LOW ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/31/01. RONALD EDWARDS - SAFETY (202)576-6693 | July 24, 2001 | October 9, 2001 | 77 days |
| Stevens Elementary School | FM-200121009 01 10/9/01 (STEVENS) BASEMENT LEVEL URINALS BACKING UP, OVERFLOWING IN THE BOYS BATHROOM. | October 4, 2001 | October 9, 2001 | 5 days |
| Kramer Middle School | FM-200119866 01 10/9/01 (KRAMER) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS RESTROOM REPAIR/REPLACE HANDLE ON FIXTURE TO SINK. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/18/01 BY HORNE ENGINEER TROY WILCOME | September 14, 2001 | October 9, 2001 | 25 days |
| Harris, C.W. ES | FM-200119747 01 10/9/01 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. PRE-K K WING/ GIRL BATHROOM THIRD STALL NEEDS A NEW FLUSH VALVE ASSEMBLY WATER CONSTANTLY RUNNING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/17/01. LEROY MINTON - SAFETY (202)576-6691 | September 13, 2001 | October 9, 2001 | 26 days |
| West Elementary School | FM-200119788 01 10/9/01 (WEST) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM ON THE RIGHT SIDE OF THE LEARNING CENTER WALL TOILET LEAKS ON TO FLOOR WHEN IT IS FLUSHED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/18/01. LEROY MINTON - SAFETY (202)576-6691 | September 14, 2001 | October 9, 2001 | 25 days |
| Johnson JHS | FM-200115763 01 10/10/01 JOHNSON MAIN OFFICE / PRINCIPAL ASBESTOS ASSESSMENT REQUIRED BATHROOM TOILET IS BACKING UP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/29/01. LEROY MINTON - SAFETY (202)576-6691 | July 24, 2001 | October 10, 2001 | 78 days |
| Park View ES | FM-200121072 01 10/10/01 (PARKVIEW) 1ST FLOOR/TEACHERS RESTROOM: REPAIR OR REPLACE P-TRAP OTHER PIPES. PIPES ARE CORRODED. | October 5, 2001 | October 10, 2001 | 5 days |
| Raymond Elementary School | FM-200121056 01 10/10/01 (RAYMOND) 1ST FLOOR/ GIRLS BATHROOM !!! URGENT !!! REPAIR 2 SINKS. DRAIN PIPE BROKEN OFF. BATHROOM CLOSED DOWN. | October 4, 2001 | October 10, 2001 | 6 days |
| Ballou Senior High School | FM-200118507 01 10/10/01 BALLOU OUTSIDE - GROUNDS RESTROOM REMOVE SPIKES IN FACADE NEAR TOILETS, PATCH HOLES & PAINT POC: RICARDO WELCH (202)438-7469 ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER BILL CAMPION DO NOT SCRAPE ANY OF THIS PAINT SURFACE RE-PAINT OVER ONLY. | August 27, 2001 | October 10, 2001 | 44 days |
| Nalle Elementary School | FM-200120349 01 10/12/01 NALLE SECOND FLOOR - BOYS RESTROOM - OLD WING 1) LOW WATER PRESSURE IN URINALS. | September 24, 2001 | October 12, 2001 | 18 days |
| Stevens Elementary School | FM-200121069 01 10/12/01 (HENDERSON) BASEMENT/ BOYS ROOM !!! EMERGENCY !!! PIPE FOR URINALS IS CLOGGED. NEED ELECTRICAL SNAKE TO PREVENT FLOODING IN BATHROOM. | October 5, 2001 | October 12, 2001 | 7 days |
| Moten Elementary School | FM-200120330 01 10/12/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS RESTROOM (OLD WING) URINAL NEEDS TO BE UNCLOGGED. ATTEMPTS WITH PLUNGER AND ARGUR UNSUCESSFUL. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 21, 2001 | October 12, 2001 | 21 days |
| Hendley Elementary School | FM-200121173 01 10/12/01 (HENDLEY) !!EMERGENCY!! CAFETERIA RESTROOM: WATER RUNNING FROM BASE OF TOILET FLOODING THE FLOOR. | October 9, 2001 | October 12, 2001 | 3 days |
| Terrell Mc ES | FM-200119157 01 10/12/01 (TERRELL, M.C.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ PRE-K LARGE RESTROOM REPLACE HOT AND COLD WATER FAUCETS (SELF CLOSING) ON HAND BOWL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/05/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | September 5, 2001 | October 12, 2001 | 37 days |
| Nalle Elementary School | FM-200120353 01 10/12/01 NALLE SECOND FLOOR - TEACHERS RESTROOM - OLD WING 1) FAUCET ON LAVATORY SINKS, HOT WATER SIDE CONTINUES TO RUN. | September 24, 2001 | October 12, 2001 | 18 days |
| Nalle Elementary School | FM-200120378 01 10/12/01 NALLE SECOND FLOOR - TEACHERS MALE RESTROOM - NEW WING. 1) FAUCET ON SINK DOES NOT WORK. | September 24, 2001 | October 12, 2001 | 18 days |
| Nalle Elementary School | FM-200120387 01 10/12/01 NALLE FIRST FLOOR- BOYS RESTROOM - NEW WING 1) URINALS KEEP RUNNING. (3) | September 24, 2001 | October 12, 2001 | 18 days |
| Nalle Elementary School | FM-200120344 01 10/12/01 NALLE FIRST FLOOR-GIRLS RESTROOM-OLD WING 1) REPLACE DEFECTIVE FAUCETS. | September 24, 2001 | October 12, 2001 | 18 days |
| Stanton Elementary School | FM-200107931 01 10/12/01 STANTON ANNEX BUILDING THE BATHROOM DOOR IN TEACHER LOUNGE. THE HINGLES ARE OFF. SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/17/01. | April 9, 2001 | October 12, 2001 | 186 days |
| Nalle Elementary School | FM-200120390 01 10/12/01 NALLE FIRST FLOOR- GIRLS RESTROOM - NEW WING 1) SINK DOES NOT WORK AND TOILET IS STOPPED UP. | September 24, 2001 | October 12, 2001 | 18 days |
| Backus Middle School | FM-200119088 01 10/12/01 (BACKUS) 1ST FLOOR GIRLS BATHROOM/NEXT TO ROOM #100: TWO (2) NEWLY INSTALLED SINKS, STOPPED UP. (NEXT TO MAIN OFFICE) ISOLATE EMERGENCY!!! | September 4, 2001 | October 12, 2001 | 38 days |
| Moten Elementary School | FM-200120331 01 10/12/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ BOYS RESTROOM (NEW WING) URINAL OVERFLOWING. URINAL NEEDS TO BE UNCLOGGED. ATTEMPTS WITH PLUNGER AND ARGUR UNSUCESSFUL. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 21, 2001 | October 12, 2001 | 21 days |
| Miner Elementary | FM-200120191 01 10/15/01 (MINER) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ KITCHEN AND BATHROOM REPAIR OR REPLACE FAUCETS KITCHEN, MENS, AND BOYS BATHROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. LEROY MINTON - SAFETY (202)576-6691 | September 20, 2001 | October 15, 2001 | 25 days |
| Truesdell Elementary | FM-200121555 /01 10/15/01 (TRUESDELL) !!EMERGENCY!! ANNEX BUILDING/2ND FLOOR BATHROOM: BRADLEY BASIN LEAKING FROM THE BASE, FLOODING THE AREA. URINALS CONSTANTLY RUNNING AND FAUCETS NEED TO BE REPLACED. | October 12, 2001 | October 15, 2001 | 3 days |
| Harris, C.W. ES | FM-200119918 01 10/16/01 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. 3, 4 WING/ BOYS BATHROOM TWO (2) URINALS ON THE SAME LINE CLOGGED UP. FLUSH THE URINAL WATER OVER RUNS ONTO THE FLOOR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/19/01. HORNE ENGINEER RAY NANAVARY | September 17, 2001 | October 16, 2001 | 29 days |
| Takoma Educational Center | FM-200121488 /01 10/17/01 (TAKOMA) 3RD FLOOR/ ROOM 200 !!! EMERGENCY !!! RESET TOILET, THE SECOND STALL WAX RING IS NOT SET PROPERLY CAUSING DAMAGE TO THE CEILING IN THE GIRLS BATHROOM 2ND FLOOR. ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY DCPS SAFETY CHARES E. BUCHANAN | October 12, 2001 | October 17, 2001 | 5 days |
| Drew Elementary School | FM-200121532 /01 10/17/01 (DREW) 1ST FLOOR/ GIRLS BATHROOM !!! EMERGENCY !!! WATER IS RUNNING OUT OF THE COMMODE CONSTANTLY, AND IS OUT OF CONTROL. | October 12, 2001 | October 17, 2001 | 5 days |
| Slowe Elementary School | FM-200109340 01 10/17/01 SLOWE FIRST (1ST) FLOOR - NEW BUILDING/GIRLS RESTROOM 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR OR REPLACE CEILING. FROM WATER DAMAGE. HEALTH AND SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/15/01. | April 30, 2001 | October 17, 2001 | 170 days |
| Ludlow-Taylor ES | FM-200117960 01 10/17/01 (LUDLOW-TAYLOR) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/GIRLS BATHROOM: REPAIR DEFECTED CEILING. POC:R. THORNTON/W. HOLLIS. PHONE: 698-3244. CODE A CLEAR FOR REPAIR BY HORNE ENG. RAY AGNANT) 08-24-01 | August 21, 2001 | October 17, 2001 | 57 days |
| Turner Elementary School | FM-200120805 01 10/17/01 (TURNER) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS AND GIRLS BATHROOM CHANGE FLUSH HANDLES ON GIRLS AND BOYS TOILETS AND BOYS URINALS WHICH ARE OPERATED BY BATTERIES. NEED CHANGING A.S.A.P. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/03/01. LEROY MINTON - SAFETY (202)576-6691 | October 1, 2001 | October 17, 2001 | 16 days |
| Cardozo High School | FM-200120099 01 10/17/01 (CARDOZO) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM MOP SINK HAS STOPPAGE THAT NEEDS TO BE OPENED. POSSIBLE SNAKING NEEDED OR OPEN TRAP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/20/01. RICHARD E GIBSON - SAFETY (202)576-5584 | September 18, 2001 | October 17, 2001 | 29 days |
| John Burroughs ES | FM-200121780 /01 10/17/01 (BURROUGHS) 1ST FLOOR/ BOYS BATHROOM !!! EMERGENCY !!! DRAIN IS STOPPED UP AND WATER IS FLOWING OVER FROM SINK. | October 16, 2001 | October 17, 2001 | 1 day |
| Montgomery ES | FM-200120954 01 10/17/01 (MONTGOMERY) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM SPUD IS LEAKING ON A TOILET. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/06/01. LEROY MINTON - SAFETY (202)576-6691 | October 3, 2001 | October 17, 2001 | 14 days |
| Truesdell Elementary | FM-200121595 /01 10/17/01 (TRUESDELL) !!EMERGENCY!! 2ND FLOOR/GIRLS AND BOYS RESTROOM: REPAIR BRADLEY BASIN IN GIRLS RESTROOM, LEAKING AND FLOODING. REPAIR URINALS AND FAUCETTS IN THE BOYS RESTROOM. | October 15, 2001 | October 17, 2001 | 2 days |
| Stanton Elementary School | FM-200121764 /01 10/17/01 (STANTON ELEM.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ ROOM 103 !!! EMERGENCY !!! BATHROOM TOILET IS NOT OPERATING AT ALL WATER IS LEAKING AT RANDOM ON CLASSROOM RUG LEAVING A ODOR WHERE THE KINDERGARDENERS ARE KEPT. NEED TO BE REPAIRED BEEN HAVING PROBLEMS FOR SEVERAL MONTHS. TEACHER IS COMPLAINING DAILY. I DONT KNOW ANYTHING ELSE TO DO. | October 16, 2001 | October 17, 2001 | 1 day |
| Turner Elementary School | FM-200120806 01 10/17/01 (TURNER) ASBESTOS ASSESSMENT REQ. THRU-OUT BLDG. TIGHTEN UP ALL FAUCET HANDLES IN THE RESTROOMS KIDS ARE TWISTING THEM LOOSE CAUSING THE REATROOM TO FLOOD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/03/01. LEROY MINTON - SAFETY (202)576-6691 | October 1, 2001 | October 17, 2001 | 16 days |
| Moten Elementary School | FM-200120333 01 10/17/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 4TH FLOOR/ GIRLS RESTROOM (NEW WING) COMMODE NEEDS TO BE UNCLOGGED. ATTEMPTS WITH PLUNGER AND ARGUR UNSUCESSFUL. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 21, 2001 | October 17, 2001 | 26 days |
| Plummer Elementary School | FM-200112480 /01 10/18/01 PLUMMER FIRST FLOOR AUDITORIUM GIRLS RESTROOM 1) REPLACE SINK DUE TO VANDALISM JAGGED EDGES EXIST EMERGENCY!! ASBESTOS CODE A- CLEARED FOR REPAIRS ON 06/06/01. | June 5, 2001 | October 18, 2001 | 135 days |
| Key Elementary School | FM-200115474 /01 10/19/01 KEY 1ST & 2ND FLOOR ROOMS 103, 203, 206, LIBRARY & BOYS / GIRLS RESTROOM REPAIR 4 DOORS LOCKS ON ENTRY DOORS OF ABOVE LISTED ROOMS ON 1ST FLOOR. REPAIR 5 DOORS LOCKS ON ENTRY DOORS ON 2ND FLOOR. ROOM 203, 206, BOYS & GIRLS RESTROOM AND LIBRARY. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/01/01. HORNE ENGINEERING - ROGER KAGER (RG) | October 17, 2001 | October 19, 2001 | 2 days |
| Bowen Elementary School | FM-200120194 01 10/22/01 (BOWEN) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ LEARNING CTR. #1, BOYS BATHROOM WATER COMING FROM BEHIND THE URINE BOWL. IN NEED OF A PLUMMER. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 20, 2001 | October 22, 2001 | 32 days |
| Thomas Elementary School | FM-200120998 01 10/22/01 (THOMAS) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ GIRLS AND BOYS BATHROOM UNCLOG SINK AND TOILET AND REPLACE SPUD AND FLUSH VALVE IN THE GIRLS. BOYS-UNCLOG TOILET AND URINAL NEEDS FLUSH VALVE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD E GIBSON - SAFETY (202)576-5584 | October 4, 2001 | October 22, 2001 | 18 days |
| Tubman Elementary School | FM-200114683 01 10/22/01 TUBMAN FIRST FLOOR GIRLS RESTROOM #37 1) REPLACE TRAP DOOR IN OPENING IN PLASTER CEILING OR RESTRICT/ISOLATE OPENING IN PLASTER CEILING ON FIRST FLOOR POC: MR. JEWELL ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/03/01. | July 3, 2001 | October 22, 2001 | 111 days |
| Tubman Elementary School | FM-200119921 01 10/22/01 (TUBMAN) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ SPACE 18 BOYS RESTROOM RESTROOM/ ENTRANCE DOOR NEED TO BE ALIGN WITH DOOR FRAME. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/19/01 BY HORNE ENGINEER BIPIN NANAVARY | September 17, 2001 | October 22, 2001 | 35 days |
| Kimball Elementary School | FM-200119500 01 10/24/01 KIMBALL 1ST FLOOR/ NORTH WING BOYS BATHROOM 1) REPLACE BROKEN WINDOW. 2) WINDOW HAS A HAND SIZE HOLE IN IT A CHILD COULD PUT AN ARM THROUGH. | September 10, 2001 | October 24, 2001 | 44 days |
| Thomson Elementary School | FM-200120296 01 10/24/01 (THOMSON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ TEACHERS LOUNGE ROOM 208 !!! URGENT !!! BATHROOM IS OUT OF ORDER. LOW WATER PRESSURE. TOILET DOES NOT FLUSH. NEEDS REPAIR IMMEDIATELY. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/24/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 21, 2001 | October 24, 2001 | 33 days |
| Kramer Middle School | FM-200120258 01 10/24/01 (KRAMER) ASBESTOS ASSESSMENT REQ. 1ST, 2ND, AND BASEMENT/ BOYS RESTROOMS COMMODES LEAKING AROUND BASE WASH BASIN 2ND FLOOR DAMAGE FIXTURE. URINALS NOT WORKING. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/24/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 21, 2001 | October 24, 2001 | 33 days |
| Marshall Educational Center | FM-200122295 /01 10/26/01 (MARSHALL) !!!EMERGENCY!!! 1ST FLOOR BOYS RESTROOM/HANDICAP: SINK IS FALLING OFF THE WALL; NEEDS TO BE REPAIRED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/24/01. SYLVIA GRIMES - SAFETY (202)576-5583 (RG) | October 24, 2001 | October 26, 2001 | 2 days |
| Marshall Educational Center | FM-200122293 /01 10/26/01 (MARSHALL) ASBESTOS ASSESSMENT REQ. 2RD FLOOR/ GIRLS RESTROOM TWO COMMODE ARE LEAKING AND NEEDS TO BE REPAIRED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/24/01. SYLVIA GRIMES - SAFETY (202)576-5583 (RG) | October 24, 2001 | October 26, 2001 | 2 days |
| Stanton Elementary School | FM-200116233 01 10/26/01 STANTON MAINT. BUILDING - HEALTH SUITE BOY BATHROOM ASBESTOS ASSESSMENT REQUIRED THE BOYS BATHROOM SINKS NEEDS P.O. PLUG. URGENT!!!!! ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/17/01. LEROY MINTON - SAFETY (202)576-6691 | July 30, 2001 | October 26, 2001 | 88 days |
| Stanton Elementary School | FM-200118029 01 10/26/01 (STANTON) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ BOYS BATHROOM THIRD FLOOR BOYS BATHROOM, ARE TWO (2) URINAL THAT IS CLOGGED UP. CODE A - CLEARED FOR REPAIRS 8-31-01 (LM) SAFETY OFFICE 202-576-8962 | August 21, 2001 | October 26, 2001 | 66 days |
| Francis Junior High School | FM-200122004 /01 10/26/01 FRANCIS REPLACE DOOR LOCKS AND KEYS TO THESE AREAS. BOYS RESTROOM 1. SECOND (2ND) FLOOR ACROSS FROM CLASSROOM TEACHER LOUNGE 2. THIRD (3RD) FLOOR GIRLS RESTROOM 3. FIRST (1ST) FLOOR - ACROSS FROM ASST. PRINCIPALS OFFICE. ISOLATE EMERGENCY!!!! | October 24, 2001 | October 26, 2001 | 2 days |
| Dunbar High School | FM-200109105 01 10/26/01 DUNBAR FOOTBALL STADIUM BOYS RESTROOM SEND AN EXHAUST FAN BLADE PER SAMPLE. | April 25, 2001 | October 26, 2001 | 184 days |
| Hardy Middle School | FM-200121908 /01 10/26/01 (HARDY) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/GIRLS BATHROOM: ALL GIRLS BATHROOMS ON 1ST FLOOR NEED 1 1/4 EXTENSION TAIL PIECE (CHROME/REPLACED ALONG WITH NUTS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/23/01. LEROY MINTON - SAFETY (202)576-6691 (RG | October 18, 2001 | October 26, 2001 | 8 days |
| Kramer Middle School | FM-200122374 /01 10/26/01 (KRAMER) !!!EMERGENCY!!! BASEMENT LEVEL/GIRLS BATHROOM: ALL COMMODES ARE OVER-FLOWING NEXT TO CLASSROOM #10. | October 25, 2001 | October 26, 2001 | 1 day |
| Kimball Elementary School | FM-200122489 /01 10/29/01 (KIMBALL) !!!EMERGENCY!!! MIDDLE WING/BOYS BATHROOM: 1ST URINAL RUNNING OVER ON FLOOR; UNABLE TO SHUT OFF WATER TO URINAL. CONSTANTLY MOPPING UP WATER. PLEASE SEND REPAIR PERSONNEL BEFORE CLOSE OF BUSINESS TODAY, AS WATER WILL STILL BE RUNNING. | October 26, 2001 | October 29, 2001 | 3 days |
| Green Elementary School | FM-200102554 01 10/29/01 GREEN THROUGHOUT ENTIRE BUILDING 303 (1), GIRLS RESTROOM THIRD (3RD) FLOOR (1), BOYS RESTROOM THIRD (3RD) FLOOR (2), 307 (1), 223 (2), SECOND (2ND) FLOOR HALL AT PARKING ENTRANCE (2), SECOND (2ND) FLOOR CENTER HALL (2), GIRLS RESTROOM SECOND (2). MT-20 | January 31, 2001 | October 29, 2001 | 271 days |
| Cardozo High School | FM-200122315 /01 10/30/01 (CARDOZO) ASBESTOS ASSESSMENT REQ. STADIUM/ BOYS BATHROOM REPLACE MISSING URINAL. CODE A- CLEAR FOR REPAIRS AS OF 10/26/01 (SG) PER BIPIN NANAVATY HORNE ENG. INSPECTOR. | October 25, 2001 | October 30, 2001 | 5 days |
| Kimball Elementary School | FM-200118116 01 10/30/01 (KIMBALL) ASBESTOS ASSESSMENT REQD. BASEMENT FLOOR NEW WING BOYS BATHROOM ONE TOILETS NEEDS TO BE REPAIRED WHEN YOU FLUSH THE THE WATER IT RUNS FROM THE NECK OF THE FLUSH VALVE ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIR 10/11/01BY HORNE ENGINEER SAM EBRAHIM | August 22, 2001 | October 30, 2001 | 69 days |
| Nalle Elementary School | FM-200120352 01 10/30/01 NALLE ASBESTOS ASSESSMENT REQUIRED SECOND FLOOR - GIRLS RESTROOM 1) DOOR STICKING, WONT CLOSE PROPERLY. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 24, 2001 | October 30, 2001 | 36 days |
| Turner Elementary School | FM-200121866 /01 10/30/01 (TURNER) ASBESTOS ASSESSMENT REQ. TOILET (FIRST STALL) STOP UP IN BOYS RESTROOM 2ND FLOOR OLD BLDG. ASBESTOS CODE -A CLEARED FOR REPAIRS ON 10-18-01. (LM) SAFETY OFFICE 202-576-8962. | October 17, 2001 | October 30, 2001 | 13 days |
| Turner Elementary School | FM-200111342 01 10/30/01 TURNER FIRST AND SECOND FLOORS OLD AND NEW BUILDING 1) REPAIR BROKEN GLASS IN EXIT DOORS ACROSS FROM ROOMS 109 AND 209 (OLD BUILDING) 2) REPLACE MISSING GLASS OVER EXIT DOOR IN MAIN LOBBY (OLD BUILDING) 3) REPAIR GLASS IN EXIT DOOR ACROSS FROM BOYS RESTROOM (SECOND NEW BUILDING) | May 29, 2001 | October 30, 2001 | 154 days |
| Kimball Elementary School | FM-200118114 01 10/30/01 (KIMBALL) ASBESTOS ASSESSMENT REQD. BASEMENT FLOOR NEW WING GIRLS BATHROOM THREE TOILETS NEEDS TO BE REPAIRED WHEN YOU FLUSH THE THE WATER IT RUNS FROM THE NECK OF THE FLUSH VALVE ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIR 10/11/01BY HORNE ENGINEER SAM EBRAHIM | August 22, 2001 | October 30, 2001 | 69 days |
| Kimball Elementary School | FM-200118110 01 10/30/01 (KIMBALL) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ NORTHWING BOYS BATHROOM ONE URINAL NEED TO BE REPAIRED NOT FLUSHING PROPERLY (ASAP). ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A - CLEAR FOR REPAIR ON 10/03/01, BY SAM EBRAHIM - HORNE ENGINEERING (RE-10/04/01) | August 22, 2001 | October 30, 2001 | 69 days |
| Kimball Elementary School | FM-200118109 01 10/30/01 (KIMBALL) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ NORTHWING BOYS BATHROOM THREE URINALS NEED TO BE REPAIRED NOT FLUSHING PROPERLY (ASAP). ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A - CLEAR FOR REPAIR ON 10/03/01, BY SAM EBRAHIM - HORNE ENGINEERING (RE-10/04/01) | August 22, 2001 | October 30, 2001 | 69 days |
| Kimball Elementary School | FM-200118108 01 10/30/01 (KIMBALL) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ MIDDLE WING BOYS BATHROOM TWO URINALS NEED TO BE REPAIRED NOT FLUSHING PROPERLY (ASAP). ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIRS BY 10/13/01 HORNE ENGINEER SAM EBRAHIM | August 22, 2001 | October 30, 2001 | 69 days |
| Kimball Elementary School | FM-200118096 01 10/30/01 (KIMBALL) ASBESTOS ASSESSMENT REQD. 1ST. FLOOR NEW WING GIRLS BATHROOM TWO TOILETS NEED TO BE REPAIRED WHEN YOU FLUSH THE WATER IT RUN FROM THE NECK OF THE FLUSH VALVE ****ASAP**** ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 | August 22, 2001 | October 30, 2001 | 69 days |
| Kimball Elementary School | FM-200115486 01 10/30/01 KIMBALL BOYS BATHROOM NORTH WING 1ST FLOOR ASBESTOS ASSESSMENT REQ. 4 URINAL DONT FLUSH. 1 TOILET DONT FLUSH ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/25/01BY HORNE ENGINEER: SHERYEL JAMES | July 20, 2001 | October 30, 2001 | 102 days |
| Orr Elementary School | FM-200119478 01 10/30/01 (ORR) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ TEACHERS TOILET REALIGN TEACHERS BATHROOM DOOR. IT WONT CLOSE PROPERLY. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/13/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | September 10, 2001 | October 30, 2001 | 50 days |
| Kimball Elementary School | FM-200115485 01 10/30/01 KIMBALL BOYS BATHROOM MIDDLE WING 2N FLOOR ASBESTOS ASSESSMENT REQ. 1 URINAL DONT FLUSH. 3 URINALS GO DOWN SLOW. ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/25/01BY HORNE ENGINEER: SHERYEL JAMES | July 20, 2001 | October 30, 2001 | 102 days |
| Cardozo High School | FM-200122316 /01 10/30/01 (CARDOZO) ASBESTOS ASSESSMENT REQ. STADIUM/ GIRLS BATHROOM RESTORE WATER IN GIRLS BATHROOM SINK. CODE A - CLEAR FOR REPAIR AS OF 10/26/01 (SG) PER BIPIN NANAVATY HORNE ENG. INSPECTOR. | October 25, 2001 | October 30, 2001 | 5 days |
| River Terrace ES | FM-200122584 /01 10/31/01 RIVER TERRACE !!! EMERGENCY !! FIRST FLOOR - BOYS BATHROOM 1) BOYS BATHROOM STOPPED UP AND OVER FLOWING...THERE MUST BE SOMETHING IN THE LINE BECAUSE MORE THAN ONE TOILET IS BACKING UP.. | October 30, 2001 | October 31, 2001 | 1 day |
| Kimball Elementary School | FM-200118111 01 10/31/01 (KIMBALL) ASBESTOS ASSESSMENT REQD. 2ND. FLOOR OPEN SPACE GIRLS BATHROOM TWO TOILETS NEEDS TO BE REPAIRED WHEN YOU FLUSH THE THE WATER IT RUNS FROM THE NECK OF THE FLUSH VALVE ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 ASBESTOS CODE A-CLEAR FOR REPAIR 10/11/01BY HORNE ENGINEER SAM EBRAHIM | August 22, 2001 | October 31, 2001 | 70 days |
| Bowen Elementary School | FM-200121032 01 10/31/01 (BOWEN) HEALTH CODE VIOLATION: KITCHEN: REPAIR HAND-SINKS IN RESTROOM AND FOOD PREP, SO THAT THERE IS SUFFICIENT HOT WATER. | October 4, 2001 | October 31, 2001 | 27 days |
| Ronald H. Brown MS | FM-200119621 01 10/31/01 (BROWN, RON) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ MAIN OFFICE MENS RESTROOM NEED FACE BOWL REPAIRED. NO HOT OR COLD WATER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/18/01. LEROY MINTON - SAFETY (202)576-6691 | September 11, 2001 | October 31, 2001 | 50 days |
| Cleveland Elementary School | FM-200122416 /01 10/31/01 (CLEVELAND) !!!!!EMERGENCY!!!!! 1ST FLOOR/BOYS RESTROOM: URINALS CLOGGED/VERY BAD SMELL. NURSES HEALTH SUITE/TOILET OVER-FLOWING. 3RD FLOOR/BOYS BATHROOM- TWO (2) URINALS OVER- FLOWING WITH VERY BAD SMELL. 4:01 | October 25, 2001 | October 31, 2001 | 6 days |
| Draper Elementary School | FM-200103788 01 10/31/01 DRAPER SECOND FLOOR BOYS BATHROOM UNSTOP LAVATORY SINK AND REPLACE TWO FLUSH VALVE. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 04/13/01. ASBESTOS ABASEMENTON ON SECOND FLOOR IS COMPLETED. ASBESTOS CONTRACTOR IS NO LONG ON SITE REPAIRS CAN BE DONE. CEB 4/26/01 | February 16, 2001 | October 31, 2001 | 257 days |
| Draper Elementary School | FM-200105773 01 10/31/01 DRAPER SECOND (2ND) FLOOR - BOYS RESTROOM TWO (2) SINK STOP UP. CURRENTLY THERE IS NO OPERATING SINKS IN THIS REST ROOM. THIS WORK ORDER HAS BEEN UPGRADED TO AN URGENT PRIORITY. CODE A - ASBESTOS ABATED ON 9/13/01 (SG) PER LEROY MINTONS CONFIRMATION. | March 13, 2001 | October 31, 2001 | 232 days |
| Wilkinson ES | FM-200118139 01 10/31/01 (WILKINSON) ASBESTOS ASSESSMENT REQD. 2ND. FLOOR MEN BATHROOM. 1-8IN.SPEAD FOR SINK FAUCET CODE A-CLEAR FOR REPAIR BY HORNE ENG BIPIN NANAVATY 8/25/01. | August 22, 2001 | October 31, 2001 | 70 days |
| Raymond Elementary School | FM-200120513 /01 10/31/01 (RAYMOND) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ STAFF BATHROOMS THE BATHROOMS ON THE 2ND FLOOR OLD WING AND THE 2ND NEW WING NEED THE LOCKS REPAIRED STAFF AND MAINTENANCE STAFF MEMBERS ARE UNABLE TO GAIN ACCESS BECAUSE THE LOCKS WILL NOT OPERATE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | October 29, 2001 | October 31, 2001 | 2 days |
| Stanton Elementary School | FM-200122433 /01 11/2/01 (STANTON) ASBESTOS ASSESSMENT REQ. THE FIRST WINDOW IN GIRLS BATHROOM IS BROKEN IN HALF NEED TO BE FIXED RIGHT AWAY. ASBESTOS CODE A - CLEAR FOR REPAIRS 10/29/01. HORNE ENGINEERING - BIPIN NANAVTY (RG) | October 26, 2001 | November 2, 2001 | 7 days |
| Woodson High School | FM-200111581 01 11/6/01 WOODSON, H.D. SECOND, THIRD AND FOURTH FLOORS 1) REPAIR BREECH IN WALL BREECH IS A RESULT OF RESTROOM REPAIRS POC:WILLIAM MOODY (202)439-8268 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/18/01. | May 30, 2001 | November 6, 2001 | 160 days |
| Woodson High School | FM-200111292 01 11/6/01 WOODSON, H.D. SECOND, THIRD, AND FOURTH FLOORS BOYS AND GIRLS RESTROOMS AND HALLWAY 1) BREACH IN WALL PATCH HOLES ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/05/01. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-13-01 HORNE ENGINEER: SHARON VOSS | May 25, 2001 | November 6, 2001 | 165 days |
| Noyes Elementary School | FM-200116877 01 11/6/01 NOYES SECOND (2ND) FLOOR - BOYS RESTROOM URINALS LEAKING OVER AND WATER IS FLOODING THE FLOOR AND COMING DOWN IN HALLWAY TO FIRST (1ST) FLOOR. DAMAGING THE CEILING TILES. ISOLATE EMERGENCY !!! | August 7, 2001 | November 6, 2001 | 91 days |
| Stanton Elementary School | FM-200122415 /01 11/6/01 (STANTON) 2ND AND 3RD FLOOR 1) 2ND FLOOR TEACHERS LOUNGE RESTROOM HAS NO COLD WATER. 2) 3RD FLOOR GIRLS RESTROOM FAUCET NEEDS SECURE. | October 25, 2001 | November 6, 2001 | 12 days |
| Shaed Elementary School | FM-200120396 01 11/6/01 (SHADE) ASBESTOS ASSESSMENT REQ. GROUND/ BOYS RESTROOM BASIN IS PUTTING OUT HOT WATER ONLY. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/26/01. LEROY MINTON - SAFETY (202)576-6691 | September 24, 2001 | November 6, 2001 | 43 days |
| Shaed Elementary School | FM-200121166 01 11/6/01 (SHAED) ASBESTOS ASSESSMENT REQ. GROUND FLOOR/ GIRLS RESTROOM WATER LEAK, NEEDS TO BE SANDED AT ELBOW. ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER EDWARD RODRIGUEZ | October 9, 2001 | November 6, 2001 | 28 days |
| Ross Elementary School | FM-200120799 01 11/6/01 (ROSS) ASBESTOS ASSESSMENT REQ. BASEMENT/ GIRLS BATHROOM SINK IS LEAKING ALL OVER THE FLOOR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD E GIBSON - SAFETY (202)576-5584 | October 1, 2001 | November 6, 2001 | 36 days |
| Noyes Elementary School | FM-200119282 01 11/6/01 NOYES/HAMILTON FIRST FLOOR - 200G,200F,200H, AND BATHROOM. !) REPAIR ELECTRICAL PROBLEMS IN THE ABOVE AREAS. THERE IS NO POWER. | September 6, 2001 | November 6, 2001 | 61 days |
| Wilkinson ES | FM-200116545 01 11/6/01 WILKINSON URGENT FAUCET STEM IN HEALTH SUITE HAS BEEN REMOVED. SINK IS INOPERABLE IN THE NURSES BATHROOM CONTACT PERSON MR. JONES. WATER HAS BEEN SHUT OFF. BATHROOM NEEDED FOR POSSIBLE EMERGENCIES. ISOLATE NO PENETRATIONS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/01/01. HORNE ENGINEERING - TROY WILCOME (RG) | August 2, 2001 | November 6, 2001 | 96 days |
| Stoddert ES | FM-200120176 01 11/6/01 (STODDERT) !!!!! EMERGENCY !!!!!! TEACHER RESTROOM NEED SOMEONE TO SNAKE TOILET WHEN FLUSHING WATER COME UP ON OTHER SIDE OF TOILET REATROOM OUT OF SERVICE FOR (2) TWO DAYS. MUST BE SOMETHING IN LINE. | September 20, 2001 | November 6, 2001 | 47 days |
| Turner Elementary School | FM-200122133 /01 11/6/01 (TURNER) ASBESTOS ASSESSMENT REQ. THRU-OUT BLDG. TIGHTEN UP ALL FAUCET HANDLES IN THE RESTROOMS KIDS ARE TWISTING THEM LOOSE CAUSING THE RESTEOOM TO FLOOD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/23/01. HORNE ENGINEERING - SAM EBRAHIM (RG) | October 22, 2001 | November 6, 2001 | 15 days |
| Macfarland Middle School | FM-200120947 01 11/6/01 (MACFARLAND) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM 3 URINALS ARE STOPPED UP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD E GIBSON - SAFETY (202)576-5584 | October 3, 2001 | November 6, 2001 | 34 days |
| Brightwood Elementary School | FM-200105143 3/6/01 11/6/01 BRIGHTWOOD FIRST (1ST) FLOOR - BOYS BATHROOM REPLACE DOOR IN THE BOYS BATHROOM ON BACK SIDE EXTERIOR TOWARD PLAYGROUND. DOOR DAMAGED. PLEXIGLASS ALSO. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/05/01. | March 6, 2001 | November 6, 2001 | 245 days |
| Cardozo High School | FM-200122957 01 11/7/01 (CARDOZO) 2ND FLOOR/LADIES BATHROOM: TOILET DRAIN LINE IS LEAKING SEWAGE IN-TO THE 2ND FL. BATHROOM. DRAIN IS LOCATED ON THE 3RD FLOOR; WHEN TOILET IS FLUSHED, RAW SEWAGE LEAKS DOWN INTO THE 2ND FLOOR. | November 6, 2001 | November 7, 2001 | 1 day |
| Thomas Elementary School | FM-200114279 01 11/7/01 THOMAS FIRST FLOOR AND BASEMENT 1) REPLACE DOOR KNOBS ON EXTERIOR FRONT DOOR 2) REPAIR PANIC BAR ON EXTERIOR DOOR SOUTHSIDE OF BUILDING 3) REPAIR OR REPLACE CUSTODIANS OFFICE DOOR AND LOCK 4) REPAIR OR REPLACE RESTROOM DOOR LOCK IN BASEMENT 5) REPAIR OR REPLACE DOOR LOCK ON BOYS RESTROOM EXTERIOR DOOR | November 5, 2001 | November 7, 2001 | 2 days |
| Davis Elementary School | FM-200115184 01 11/9/01 (DAVIS) "EMERGENCY" 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR BATHROOM/NEXT TO ROOM #102: A TOTAL OF FOUR (4) URINALS BACKING UP, FLOODING BATHROOM FLOOR. (ADVISED TO ISOLATE AREA IF POSSIBLE, UNTIL REPAIRMEN ARRIVE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/13/01. | July 12, 2001 | November 9, 2001 | 120 days |
| Kramer Middle School | FM-200110237 01 11/9/01 KRAMER FIRST (1ST) FLOOR 1) ASBESTOS ASSESSMENT REQUIRED. 2) OFFICE NEXT TO WOMENS RESTROOM ON SOUTHEAST CORRIDOR. REPLACE ALL CEILING TILES. CODE A-CLEAR FOR REPAIR BY HORNE ENG. 8/13/01. (CEB) | May 14, 2001 | November 9, 2001 | 179 days |
| Shaed Elementary School | FM-200120588 01 11/13/01 SHEAD 1ST FLOOR BOYS BATHROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. ASSESSMENT NEEDED 1 ST FLOOR BOYS BATHROOM ABOVE BASEMENT CUSTODIAN OFFICE, DEMILITION WORK TO TILE FLOOR TO REMOVE REPTURE PIPE TO RADIATOR. ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER EDWARD RODRIGUEZ | September 27, 2001 | November 13, 2001 | 47 days |
| Davis Elementary School | FM-200116575 01 11/13/01 DAVIS LUNCHROOM BOYS BATHROOM ASBESTOS ASSESSMENT REQUIRED FURNISH & INSTALL A TOILET IN THE STALL OF BOYS BATHROOM LUNCHROOM. TOILET HAVE A CRACK ON THE SIDE AND BOTTOM BASE & WATER IS LEAKING FROM CRACKS. CODE A-CLEAR FOR REPAIR BY HORNE ENG 8/10/01. | August 2, 2001 | November 13, 2001 | 103 days |
| Beers Elementary School | FM-200122916 01 11/13/01 BEERS 1) BUILDING (3) - SECOND FLOOR BOYS BATHROOM URINAL HANGING OFF WALL CAN NOT CUT WATER OFF. 2) CAFETERIA- BOYS BATHROOM SINK IS HANGING OFF THE WALL. PERMIT DONE TO ISOLATE EMERGENCY.. If you have any questions please call 202-576-8962. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-07-01 HORNE ENGINEER : SHARON VOSS | November 6, 2001 | November 13, 2001 | 7 days |
| Cooke H.D. Elementary School | FM-200122969 01 11/13/01 (COOKE, H.D.) BASEMENT/ BOYS RESTROOM UNSTOP SINK NEEDS TO BE UNCLOGGED. | November 6, 2001 | November 13, 2001 | 7 days |
| Cooke H.D. Elementary School | FM-200122966 01 11/13/01 (COOKE, H.D.) 2ND FLOOR/ ROOM 211 PRE-K UNCLOG TOILET IN CLASSROOM RESTROOM. | November 6, 2001 | November 13, 2001 | 7 days |
| Cooke H.D. Elementary School | FM-200122928 01 11/13/01 (COOKE, H.D.) BASEMENT/GIRLS RESTROOM: TOTAL OF THREE (3) TOILETS CLOGGED, NEED TO BE SNAKED OUT. | November 6, 2001 | November 13, 2001 | 7 days |
| Davis Elementary School | FM-200101540 01 11/13/01 DAVIS 1ST FL. RESTROOM REAIR LEAKING URINAL | January 18, 2001 | November 13, 2001 | 299 days |
| Harris, C.W. ES | FM-200122528 /01 11/13/01 (HARRIS, C.W.) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/PRE-K WING: NEED NEW FLUSH VALVE IN GIRLS RESTROOM/ROOM #110. ASBESTOS CODE A - CLEAR FOR REPAIRS 10/30/01. HORNE ENGINEERING - BILL CAMPION (RG) | October 29, 2001 | November 13, 2001 | 15 days |
| Jessie LaSalle Elementary | FM-200115479 01 11/13/01 LASALLE BOYS RESTROOM ON 1ST FLOOR REPAIR / REPLACE INCADESCENT LIGHT FIXTURE. CODE A-CLEAR FOR REPAIR BY HORNE ENG 8/18/01. CEB | July 20, 2001 | November 13, 2001 | 116 days |
| Stanton Elementary School | FM-200122413 /01 11/13/01 (STANTON) 1ST FLOOR/ ANNEX BOYS BATHROOM TOILET NEEDS TO BE REPAIRED. | October 25, 2001 | November 13, 2001 | 19 days |
| Stanton Elementary School | FM-200122414 /01 11/13/01 (STANTON) BASEMENT/ BOYS BATHROOM TOILET NEEDS TO BE REPAIRED. | October 25, 2001 | November 13, 2001 | 19 days |
| Kramer Middle School | FM-200121784 /01 11/13/01 (KRAMER) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS RESTROOM SINK PIPING NEEDS REPAIR AND OR REPLACE. WATER RUNNING ON FLOOR. (NO PENETRATION) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/19/01. HORNE ENGINEERING - SHARON VOSS (RG) | October 16, 2001 | November 13, 2001 | 28 days |
| Coolidge High School | FM-200120314 01 11/13/01 COOLIDGE GROUND LEVEL BOYS RESTROOM URINALS CRACK AND WATER IS LEAKING FROM THE BOTTOM. WATER IS RUNNING DOWN IN ROOMS BELOW. BEFORE DAMAGE TO CEILING. ISOLATE EMERGENCY!!!! | September 21, 2001 | November 13, 2001 | 53 days |
| Draper Elementary School | FM-200121499 /01 11/13/01 (DRAPER) FIRE CODE VIOLATION: BASEMENT/BOYS BATHROOM: HOLE IN WALL.ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/16/01 HORNE ENGINEER TROY WILLCAME | October 12, 2001 | November 13, 2001 | 32 days |
| Ferebee-Hope Elementary School | FM-200122694 /01 11/13/01 (FEREBEE-HOPE) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ GIRLS BATHROOM PLUMBING: UNSTOP (2) TWO TOILETS. UNABLE TO UNCLOG USING PLUNGER AND ARGUR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. LEROY MINTON- SAFETY (202)576-6691(RG) | October 31, 2001 | November 13, 2001 | 13 days |
| Davis Elementary School | FM-200122600 /01 11/13/01 (DAVIS) ASBESTOS ASSESSMENT REQ. BASEMENT/ LUNCHROOM BOYS BATHROOM UNSTOP TOILET AND URINAL IN BOYS BATHROOM LUNCHROOM LOCAL SNAKE AND PLUNGER WAS NOT SUFFICIENT. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: SHARON VOSS | October 30, 2001 | November 13, 2001 | 14 days |
| Harris, C.W. ES | FM-200122188 /01 11/14/01 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. PRE-K WING/ 1ST FLOOR GIRLS BATHROOM 3RD STALL WATER PRESSURE WILL NOT CUT OFF. ASBESTOS CODE A - CLEARED FOR REPAIRS 10-24-01. (LM) SAFETY OFFICE 202-576-8962. | October 23, 2001 | November 14, 2001 | 22 days |
| Beers Elementary School | FM-200108872 01 11/16/01 BEERS 1ST FL. GIRLS RESTROOM REPLACE APPROXIMATELY 4 EA. CINDER BLOCKS THAT WERE REMOVED FROM INTERIOR WALL TO FACILITATE STEAMFITTING REPAIRS BY THE STEAMFITTING SHOP. Requester Phone: 698-1752 | March 30, 2001 | November 16, 2001 | 231 days |
| Beers Elementary School | FM-200108576 01 11/16/01 (BEERS) 1. ASBESTOS ASSESSMENT REQUIRED. CAFETERIA/LUNCH ROOM: GIRLS RESTROOM TOILET HAVE BEEN CRACKED, AND DISLOCATED FROM THE PLUMMING WALL, NEED TO BE REPLACED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/26/01. | April 17, 2001 | November 16, 2001 | 213 days |
| Plummer Elementary School | FM-200121345 /01 11/17/01 (PLUMMER) !!! URGENT !!! 1ST FLOOR/ AUDITORIUM RESTROOMS (GIRLS) PULL UP COMMODE AND SNAKE OUT DRAIN. HAS BEEN SNAKED OUT PREVIOUSLY WITHOUT TAKING OUT. DRAIN WILL NOT REMAIN UNCLOGGED. NOTE: GIRLS AND BOYS ARE USING ONE RESTROOM BECAUSE THIS ONE IS CLOSED. | October 10, 2001 | November 17, 2001 | 38 days |
| Patterson ES | FM-200111394 5/29/01 11/17/01 PATTERSON BOYS RESTROOM 1) REPLACE URINAL FLUSH HANDLE ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/04/01. LEROY MINTON - SAFETY (202)576-6691 | May 29, 2001 | November 17, 2001 | 172 days |
| King M L ES | FM-200122644 /01 11/17/01 (KING) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ ROOM 116 BATHROOM WE NEED TO HAVE (1) TOILET RESET IT IS LEAKING FROM THE BASE THE 1ST STALL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/05/01 LEROY MINTON - SAFETY (202)576-6691(RG) | October 30, 2001 | November 17, 2001 | 18 days |
| Beers Elementary School | FM-200121796 /01 11/17/01 (BEERS) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BLDG. #1 BOYS BATHROOM 2 URINALS ARE STOPPED UP. I TRYED PLUNGING IT DIDNT WORK. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/19/01. RONALD EDWARDS - SAFETY (202)576-6691 | October 16, 2001 | November 17, 2001 | 32 days |
| Davis Elementary School | FM-200122019 /01 11/17/01 (DAVIS) ASBESTOS ASSESSMENT REQ. BASEMENT/ LUNCHROOM BOYS BATHROOM UNSTOP TOILET AND URINAL IN BOYS BATHROOM LUNCHROOM. LOCAL SNAKE AND PLUNGER WAS NOT SUFFICIENT. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/20/01. RICHARD E GIBSON - SAFETY (202)576-5584 (RG) | October 19, 2001 | November 17, 2001 | 29 days |
| Ferebee-Hope Elementary School | FM-200122696 /01 11/17/01 (FEREBEE-HOPE) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM PLUMBING: TAKE (2) TWO TOLIETS UP FROM THE FLOOR TO UNSTOP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. LEROY MINTON- SAFETY (202)576-6691(RG) | October 31, 2001 | November 17, 2001 | 17 days |
| Anacostia Senior High School | FM-200121799 /01 11/17/01 (ANACOSTIA) !!!EMERGENCY!!! BASEMENT/ROTC BATHROOM: PLUMBING PROBLEM THROUGH-OUT THE BATHROOM. ALL URINALS ARE STOPPED UP, SHOWERS, AND SINKS. AT THIS POINT, BATHROOM HAS BEEN ISOLATED UNTIL REPAIR PERSONNEL ARRIVES. THIS BATHROOM IS MUCH NEEDED. | October 16, 2001 | November 17, 2001 | 32 days |
| Thomas Elementary School | FM-200121001 01 11/19/01 (THOMAS) ASBESTOS ASSESSMENT REQ. 1ST FLOOR OLD AND NEW WING REPLACE FAUCETS IN ROOM 100 RESTROOM AND GIRLS RESTROOM ALSO DIAPHRAM AND SPUD FLUSH VALVE IN COUNSELORS SUITE, FLUSH VALVE IN LOBBY RESTROOMS. UNCLOG SINK IN CUSTODIANS CLOSET. BOYS FAUCETS NEED REPLACING AND UNCLOG 2 URINALS. AUDUT RESTROOM FLUSH VALVE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD E GIBSON - SAFETY (202)576-5584 | October 4, 2001 | November 19, 2001 | 46 days |
| Cleveland Elementary School | FM-200122432 /01 11/19/01 (CLEVELAND) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ NURSES OFFICE RESTROOM TOILET IS STOPPED UP AND OVERFLOWS ONTO FLOOR. WE NEED TO HAVE IT UNCLOGGED. NO ONE CAN USE IT AT ALL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. LEROY MINTON - SAFETY (202)576-6691(RG) | October 26, 2001 | November 19, 2001 | 24 days |
| Ferebee-Hope Elementary School | FM-200123575 /01 11/19/01 (FEREBEE-HOPE) !!EMERGENCY!! 3RD FLOOR/GIRLS RESTROOM: COMMODES ARE BACKING UP AND FLOODING. WATER IS DAMAGING CEILING TILE IN 2ND FLOOR RESTROOM. | November 19, 2001 | November 19, 2001 | 0 days |
| Nalle Elementary School | FM-200120339 01 11/19/01 NALLE FIRST FLOOR-BOYS RESTROOM-OLD WING 1) URINALS FLOOD AND LEAKS. | September 24, 2001 | November 19, 2001 | 56 days |
| Jessie LaSalle Elementary | FM-200118742 01 11/20/01 (LASALLE) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ GIRLS BATHROOM REPLACE MISSING VENT ON DOOR. YOU CAN SEE DIRECTLY INTO BATHROOM. (T-9) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/30/01. HORNE ENGINEERS - TROY WILCOME | August 29, 2001 | November 20, 2001 | 83 days |
| Moten Elementary School | FM-200121260 /01 11/20/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ BOYS RESTROOM UNCLOG URINAL. UNSUCCESSFUL WITH PLUNGER. NO AUGER ON SITE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/22/01. LEROY MINTON - SAFETY (202)576-6691 (RG | October 10, 2001 | November 20, 2001 | 41 days |
| Ballou Senior High School | FM-200121410 /01 11/20/01 (BALLOU) ASBESTOS ASSESSMENT REQ. GIRLS RESTROOM THERE IS A 4 OR 5 INCH DRAIN PIPE THAT HAS A CRACK THE TOILET ABOVE. ASBESTOS CODE A-CLEAR FOR REPAIRS BY 10/17/01 HORNE ENGINEER : ROGER KAGER | October 11, 2001 | November 20, 2001 | 40 days |
| Garnet-Patterson MS | FM-200110898 01 11/20/01 GARNET-PATTERSON THIRD FLOOR-GIRLS BATHROOM 1) DOOR WILL NOT CLOSE PROPERLY. HARD TO OPEN AND CLOSE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/24/01. | May 24, 2001 | November 20, 2001 | 180 days |
| Ballou Senior High School | FM-200121661 /01 11/20/01 (BALLOU) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS RESTROOM OUTSIDE MAIN LOBBY REPAIR 1-URINAL AND 2 TOILETS THIS RESTROOM IS NEAR THE GYM AND IS USED A LOT. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/22/01. LEROY MINTON - SAFETY (202)576-6691 (RG | October 15, 2001 | November 20, 2001 | 36 days |
| Jessie LaSalle Elementary | FM-200117589 01 11/20/01 LASALLE THIRD FLOOR - GIRLS BATHROOM 1) REPLACE GIRLS BATHROOM ENTRANCE DOOR. (*** T-9 SCHOOL***) CODE A-CLEAR FOR REPAIR BY HORNE ENG 8/18/01. CEB | August 16, 2001 | November 20, 2001 | 96 days |
| Moten Elementary School | FM-200121263 /01 11/20/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 4TH FLOOR/ GIRLS RESTROOM (NEW SIDE) UNCLOG (1) COMMODE. UNSUCCESSFUL WITH PLUNGER. NO AUGER ON SITE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/22/01. LEROY MINTON - SAFETY (202)576-6691 (RG | October 10, 2001 | November 20, 2001 | 41 days |
| Meyer Elementary School | FM-200121471 /01 11/20/01 (MEYER) ASBESTOS ASSESSMENT REQ. BASEMENT/ TEACHERS BATHROOM THE TOLIET IN THE TEACHERS BATHROMM KEEPS RUNNING, HAD TO CUT IT OFF. PLEASE TAKE CARE OF THIS A.S.A.P. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD E GIBSON - SAFETY (202)576-5584 | October 11, 2001 | November 20, 2001 | 40 days |
| Montgomery ES | FM-200121347 /01 11/20/01 (MONTGOMERY) 2ND FLOOR/ BOYS BATHROOM !!! EMERGENCY !!! FLUSH VALVE ON URINAL IS LEAKING. NEEDS TO BE REPAIRED OR REPLACED. | October 10, 2001 | November 20, 2001 | 41 days |
| Savoy Elementary School | FM-200123719 /01 11/23/01 (SAVOY) !!!! EMERGENCY !!!! REQUEST TO UNSTOP TOILET IN BOYS RESTROOM 2ND STALL FROM ENTRANCE IN BOYS. TRIED TO UNSTOP BUT COULD NOT. SNAKE RESTROOM ON 1ST FLOOR RESTROOM GIRLS. | November 21, 2001 | November 23, 2001 | 2 days |
| Eastern High School | FM-200122921 01 11/23/01 (EASTERN) STADIUM/BOYS BATHROOM: REPLACE MIRROR IN BOYS BATHROOM, SOAP AND PAPER TOWEL DISPENSER, DUE TO VANDALISM. VANDALS ENTERED THE BUILDING FROM THE HATCH ON THE ROOF, RESECURE HATCH ON ROOF. (CHAMPIONSHIP FOOTBALL GAME SCHEDULED FOR 11/22/O1) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/20/01. HORNE ENGINEERING - EDWARD RODRIGUEZ (RG) | November 6, 2001 | November 23, 2001 | 17 days |
| Spingarn High School | FM-200123636 /01 11/23/01 (SPINGARN) "EMERGENCY" ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR/GIRLS BATHROOM AND 1ST FLOOR CORRIDOR 1) REPAIR/REPLACE RUPTURED WATER LINE AND SINK IN THE GIRLS BATHROOM. 2) REPAIR/REPLACE RUPTURED SUPPLY LINE ON WATER FOUNTAIN WHICH IS LEAKING IN THE 1ST FLOOR CORRIDOR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/20/01. HORNE ENGINEERING - TROY WILCOME (RG) | November 20, 2001 | November 23, 2001 | 3 days |
| Ross Elementary School | FM-200123630 /01 11/23/01 ROSS !! EMERGENCY!! BASEMENT LEVEL - GIRLS BATHROOM 1) WATER LEAKING FROM 2ND STALL AND FLOODING THE FLOOR. | November 20, 2001 | November 23, 2001 | 3 days |
| Amidon Elementary School | FM-200106827 01 11/24/01 AMIDON MULTIPLE - MULTIPLE FLOORS AND ROOMS 1) GYMNASIUM BOYS BATHROOM BRADLEY BASIN NEEDS STOP VALVE 2) GYMNASIUM GIRLS BATHROOM BRADLEY BASIN NOT WORKING 3) SECOND (2ND) FLOOR GIRLS BATHROOM BRADLEY BASIN NOT WORKING ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/15/01. HORNE ENGINEERING - SHERYLL JAMES | March 28, 2001 | November 24, 2001 | 241 days |
| Meyer Elementary School | FM-200121774 /01 11/26/01 (MEYER) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BASEMENT THE SINKS IN THE PRINCIPAL BATHROOM AND KINDERGARDEN IS BROKE. WATER KEEP RUNNING AND IT WONT STOP. PLEASE TAKE CARE OF THIS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD GIBSON - SAFETY (202)576-5584 (RG) | October 16, 2001 | November 26, 2001 | 41 days |
| Browne Junior High School | FM-200118085 01 11/26/01 (BROWNE) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM NEAR ROOM 131 REPAIR BROKEN DOOR CLOSER ON BATHROOM DOOR. Asbestos Code A - Clear for repairs on 10/01/01 Horne Engineer - Sheryl James (RE) | August 22, 2001 | November 26, 2001 | 96 days |
| Moten Elementary School | FM-200121259 /01 11/26/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ GIRLS RESTROOM REPLACE 2x4 CEILING TILE DAMAGED FROM LEAK. LEAK REPAIRED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/11/01. HORNE ENGINEERING - SHERYLL JAMES (RG) | October 10, 2001 | November 26, 2001 | 47 days |
| Eastern High School | FM-200123484 /01 11/27/01 (EASTERN) "EMERGENCY" WATER BACK UP IN VARIOUS LOCATIONS POSING SAFETY HAZARDS TO ANYONE WALKING THROUGH THE HALLWAYS. 1) FLOOR DRAINS IN GIRLS BATHROOM, ACROSS FROM RM B-77. 2) CUSTODIAL CLOSET NEXT TO ELEVATOR ON BASEMENT FLOOR BACKING UP FACEBOWL IN BOYS AND GIRLS BATHROOMS, AS WELL AS THE CUSTODIAL CLOSET. THE AFFECTED BATHROOMS ARE THE MAIN ONES USED DURING LUNCH. | November 16, 2001 | November 27, 2001 | 11 days |
| Stanton Elementary School | FM-200115943 01 11/27/01 STANTON MAIN BLDG. - GROUND FLOOR BOYS BATHROOM ASBESTOS ASSESSMENT REQUIRED THE BOYS BATHROOM HAVE A TOILET AND THREE URINALS STOPPED UP. WILL NOT STOP RUNNING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/01/01. RONALD EDWARD - SAFETY (202)576-6693 (RG) | July 26, 2001 | November 27, 2001 | 124 days |
| Stanton Elementary School | FM-200122818 01 11/29/01 (STANTON ANNEX) 1. ASBESTOS ASSESSMENT REQUIRED. ANNEX BUILDING /1ST FLOOR/BOYS BATHROOM: URINALS STOPPED UP AS YOU COME IN THE DOOR. (ASSESS WALL) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/15/01. HORNE ENGINEERING - RAY AGNANT | November 2, 2001 | November 29, 2001 | 27 days |
| Harris, C.W. ES | FM-200123487 /01 11/29/01 (HARRIS, C.W.) !!!EMERGENCY!!! EXPLORATORY DEMOLITION IN KITCHEN RESTROOM. 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR KITCHEN/BATHROOM: CAPPED OFF LINE BEHIND SINK IS LEAKING AND FLOODING THE FLOORS. UNABLE TO SHUT WATER OFF, WATER RUNNING PROFUSELY. ENVIROBATE (IT GROUP) 703-461-6848 CODE A - ASBESTOS ABATED ON 11/21/01 (SG) PER LEROY MINTONS CONFIRMATION. | November 16, 2001 | November 29, 2001 | 13 days |
| Park View ES | FM-200123760 /01 11/29/01 (PARK VIEW) !!EMERGENCY!! 2ND FLOOR/BOYS RESTROOM: WATER IS LEAKING FROM A CRACKED COMMODE, FLOODING THE RESTROOM FLOOR. | November 26, 2001 | November 29, 2001 | 3 days |
| Harris, C.W. ES | FM-200122788 01 11/29/01 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM 2ND STALL STOP VALVE WATER IS LEAKING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. LEROY MINTON - SAFETY (202)576-6691(RG) | November 1, 2001 | November 29, 2001 | 28 days |
| Stoddert ES | FM-200123863 /01 11/29/01 (STODDERT) "EMERGENCY" 1ST FLOOR/TEACHERS BATHROOM FECES CONSTANTLY BACKING UP AND SPILLING ONTO BATHROOM FLOOR. DEFINITE HEALTH HAZARD. | November 27, 2001 | November 29, 2001 | 2 days |
| Park View ES | FM-200123936 /01 11/29/01 PARK VIEW **EMERGENCY** THIRD FLOOR, BOYS BATHROOM STAND UP URINAL FLOODS WHEN FLUSHED. | November 28, 2001 | November 29, 2001 | 1 day |
| Stanton Elementary School | FM-200122427 /01 11/29/01 (STANTON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ GIRLS BATHROOM REPLACE TOILET. TOILET IS ON SITE. STAFF CANT REPLACE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/01/01. RONALD EDWARD - SAFETY (202)576-6693 (RG) | October 26, 2001 | November 29, 2001 | 34 days |
| Meyer Elementary School | FM-200121770 /01 11/29/01 (MEYER) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BASEMENT THE BOYS BATHROOM ON THE 1ST FLOOR AND THE GIRLS BATHROOM IN THE BASEMENT HAS (1) ONE & (2) TWO FLUSH VALVES LEAKING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD E GIBSON - SAFETY (202)576-5584 (RG) | October 16, 2001 | November 29, 2001 | 44 days |
| Cook J.F. Elementary School | FM-200122169 /01 11/29/01 (COOK, J.F.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS BATHROOM (2) TWO MIRRIORS NEED TO BE HUNG BACK UP ON THE WALL IN THE BOYS BATHROOM. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/01/01 HORNE ENGINEER: ROGER KAGER | October 23, 2001 | November 29, 2001 | 37 days |
| Webb Elementary School | FM-200122236 /01 11/30/01 (WEBB) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ MENS RESTROOM REPAIR URINAL LEAKING FROM WALL, POSSIBLE BROKEN NIPPLE. CODE A - CLEAR FOR REPAIRS AS OF 10/26/01(SG) PER RAYMOND AGNANT HORNE ENG. INSPECTOR. | October 24, 2001 | November 30, 2001 | 37 days |
| Watkins Elementary School | FM-200123128 /01 12/1/01 (WATKINS) GIRLS BATHROOM NEED LOCKSMITH TO INSTALLED LOCK ON THE DOOR. | November 29, 2001 | December 1, 2001 | 2 days |
| Garfield ES | FM-200121097 01 12/2/01 (GARFIELD) ASBESTOS ASSESMENT REQ. LL FLOOR/ BOYS RESTROOM NESR ROOM 37 CORRECT DRAINAGE PROBLEMS, REPAIR COMMODES AND REPAIR DRAIN LINE TO SINK. BATHROOMS SHUT DOWN. ASBESTOS CODE A-CLEAR FOR REPAIRS BY 10/17/01 HORNE ENGINEER : SAM EBRAHIM | October 5, 2001 | December 2, 2001 | 58 days |
| Hine JHS | FM-200118753 01 12/3/01 (HINE) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ OLD WING BOYS AND GIRLS BATHROOM REPLACE CIRCUIT BREAKER TO THE BOYS AND GIRLS BATHROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/06/01. HORNE ENGINEERS - TROY WILCOME (RG) | August 29, 2001 | December 3, 2001 | 96 days |
| Patricia R Harris Ed Center | FM-200120725 01 12/3/01 (HARRIS, P.R.) ASBESTOS ASSESSMENT REQ. MAIN FLOOR/ RESTROOM #7 REPAIR STAND UP TOILET. WATER KEEPS RUNNING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/22/01. LEROY MINTON - SAFETY (202)576-6691 (RG | October 1, 2001 | December 3, 2001 | 63 days |
| Brightwood Elementary School | FM-200123880 /01 12/5/01 BRIGHTWOOD **EMERGENCY** FIRST FLOOR, CUSTODIANS OFFICE BATHROOM HOT WATER FAUCET WILL NOT CUT OFF. | November 27, 2001 | December 5, 2001 | 8 days |
| Wilkinson ES | FM-200111941 01 12/5/01 WILKINSON FIRST FLOOR -BOYS AND GIRLS BATHROOMS. 1) RELOCATE SOAP AND PAPER TOWEL DISPENSERS ON WALLS. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | June 1, 2001 | December 5, 2001 | 187 days |
| Wilkinson ES | FM-200112301 01 12/5/01 WILKINSON FIRST FLOOR KINDERGARTEN AREA BOYS RESTROOM 1) REATTACH LOOSE SINK TO WALL ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | June 4, 2001 | December 5, 2001 | 184 days |
| Payne Elementary School | FM-200109131 01 12/5/01 (PAYNE) 3RD FLOOR CORRIDOR: REPLACE MISSING WINDOW PANE NEXT TO GIRLS RESTROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/18/01. | April 26, 2001 | December 5, 2001 | 223 days |
| Emery Elementary School | FM-200121776 /01 12/5/01 (EMERY) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ GIRLS BATHROOM BRADLEY BASIN LEAKING WATER IN BATHROOM. ASBESTOS CODE A-CLEAR FOR REPAIR BY 10-22-01 HORNE ENGINEER : SAM EBRAHIM | October 16, 2001 | December 5, 2001 | 50 days |
| Hearst Elementary School | FM-200124325 01 12/5/01 (HEARST) !!!EMERGENCY!!! 1ST FLOOR/BOYS BATHROOM: REPAIR OR REPLACE PIPE LEADING TO COMMODE LEAKING PRO- FUSELY. TOILET RUNNING, AND LEAKING PROFUSELY. | December 3, 2001 | December 5, 2001 | 2 days |
| Wilkinson ES | FM-200118412 01 12/5/01 (WILKERSON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM NEED TO REPLACE 1-180 FLUSH VALVE FOR BOYS URINAL. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/21/01. SHARON VOSS - HORNE ENGINEERS (RG) | August 27, 2001 | December 5, 2001 | 100 days |
| Park View ES | FM-200120784 01 12/5/01 PARKVIEW ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS RESTROOM REPAIR OR REPLACE BRADLEY BASIN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/09/01. HORNE ENGINEERING - RAYMOND AGNANT (RG | October 1, 2001 | December 5, 2001 | 65 days |
| Park View ES | FM-200120783 01 12/5/01 (PARK VIEW) ASBESTOS ASSESSMENT REQ. 1) LEAKS COMING FROM GIRLS BATHROOM THAT HAS BEEN RENOVATED. 2) BOYS RESTROOM LOWER LEVEL STILL BLOCKED OFF. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/19/01. HORNE ENGINEERING - RAYMOND AGNANT (RG) | October 1, 2001 | December 5, 2001 | 65 days |
| Wilkinson ES | FM-200118404 01 12/5/01 (WILKERSON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ MENS BATHROOM REPLACE 1- 8 INCH SPEED FOR SINK FAUCET (DECK MOUNT). ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/21/01. SHARON VOSS - HORNE ENGINEERS (RG) | August 27, 2001 | December 5, 2001 | 100 days |
| Benjamin Banneker Academic HS | FM-200124490 01 12/6/01 (BANNEKER) **EMERGENCY** 1ST FLOOR BYM/GIRLS RESTROOM REPLACE THREE (3) FLUSH VALVES IN #110 GIRLS RESTROOM | December 4, 2001 | December 6, 2001 | 2 days |
| Stevens Elementary School | FM-200122147 /01 12/6/01 STEVENS 1ST FL. GIRLS RESTROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE 1" STEAM LINE IN HALLWAY ON GROUND FLOOR, CEILING AND WALL PLASTER BRICK BY GIRLS BATHROOM, PIPE LEAKING OVER TOP OF DOOR. HOT. CODE A - CLEAR FOR REPAIRS AS OF 10/26/01 (SG) PER SHARON VOSS HORNE ENG. INSPECTOR. | October 23, 2001 | December 6, 2001 | 44 days |
| Ferebee-Hope Elementary School | FM-200110883 01 12/6/01 FEREBEE-HOPE SECOND FLOOR BOYS BATHROOM 1) UNSTOP TWO (2) TOILETS - UNABLE TO UNSTOP MANUALLY ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. RICHARD GIBSON- SAFETY (202)576-5584(RG) | May 23, 2001 | December 6, 2001 | 197 days |
| Moten Elementary School | FM-200121262 /01 12/6/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS RESTROOM REPLACE FLUSH VALVE ON URINAL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/22/01. LEROY MINTON - SAFETY (202)576-6691 (RG | October 10, 2001 | December 6, 2001 | 57 days |
| Draper Elementary School | FM-200100940 01 12/7/01 DRAPER BASEMENT - BOYS BATHROOM REPAIR HOLE IN WALL ASBESTOS ASSESSMENT REQUIRED | January 11, 2001 | December 7, 2001 | 330 days |
| Stanton Elementary School | FM-200121752 /01 12/10/01 (STANTON ELEM.) ASBESTOS ASSESSMENT REQ. ANNEX BOYS AND GIRLS RESTROOM BATHROOM WINDOWS IN THE ANNEX BUILDING NEED TO BE REPAIRED DO TO VANDALISM, THEY ARE FALLING APART PIECE BY PIECE NEED SOMEONE TO LOOK AT THEM. WE HAD TO NAIL THEM CLOSED FROM PREVIOUS ATTEMPTED BRAKE IN. WE NEED SOME KIND OF AIR CIRCULATING AROUND IN THERE. ASBESTOS CODE A-CLEAR FOR REPAIRS ON 10/19/01 BY HORNE ENGINEER : EDWARD RODRIGUEZ | October 16, 2001 | December 10, 2001 | 55 days |
| Cleveland Elementary School | FM-200117997 01 12/10/01 CLEVELAND BASEMENT AND THIRD FLOOR ALL BOYS AND GIRLS RESTROOMS 1) REMOVE PARTITIONS FROM CLEVLAND ELEM AND INSTALL IN RESTROOMS AT MINER ELEM SCHOOL. ASBESTOS CODE A-CLEAR FOR REPAIR 10/11/01BY HORNE ENGINEER STEPHEN CALDWELL | August 21, 2001 | December 10, 2001 | 111 days |
| Rudolph Elementary School | FM-200120070 01 12/11/01 (RUDOLPH) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM NEW DOOR CLOSER IN MIDDLE STAIRWELL ON NEW SIDE OF THE BUILDING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/15/01. HORNE ENGINEERING - EDWARD RODRIGUEZ (RG) | September 18, 2001 | December 11, 2001 | 84 days |
| Spingarn High School | FM-200111533 01 12/11/01 SPINGARN BASEMENT CUSTODIANS OFFICE RESTROOM 1) INSTALL LARGE ACCESS PANEL HOLE ALREADY IN WALL ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/20/01 BY DCPS SAFETY CHARLES E. BUCHANAN (202-567-5582) PLASTER WHITE NO ACM HA 017 BROWN COAT NO ACM HA 717 | May 30, 2001 | December 11, 2001 | 195 days |
| Hendley Elementary School | FM-200123782 /01 12/12/01 HENDLEY FIRST AND SECOND FLOOR ANNEX. BATHROOM DOORS NEED LOCKS. ASBESTOS CODE A-CLEAR FOR REPAIR ON11/27/01 BY HORNE ENGINEER : EDWARD RODRIGUEZ | December 10, 2001 | December 12, 2001 | 2 days |
| Spingarn High School | FM-200123950 /01 12/12/01 SPINGARN THIRD (3RD) FLOOR - BOYS AND GIRLS RESTROOM RE-KEY THE DOORS. THE KEYS ARE ON THE MASTER SET AND THE PRINCIPAL DONOT WANT TO KEEP USING THE (MASTER) KEY FOR STAFF, NEED SEPARATE KEYS. | December 10, 2001 | December 12, 2001 | 2 days |
| Ronald H. Brown MS | FM-200123298 /01 12/12/01 (BROWN, RON) 3RD FLOOR/ BOYS RESTROOM NEAR STAIRWELL #8 FLUSH VALVE ON THE TOILET IS NOT WORKING PROPERLY AND THE ODOR IS STRONG. | November 14, 2001 | December 12, 2001 | 28 days |
| River Terrace ES | FM-200124920 /01 12/13/01 (RIVER TERRACE) !!!EMERGENCY!!! ONE LEVEL/1ST FLOOR: SIX URINALS RUNNING OVER IN RESTROOM #5; FLOODING AND SMELLS OF URINE. | December 11, 2001 | December 13, 2001 | 2 days |
| Moten Elementary School | FM-200119935 01 12/13/01 (MOTEN) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ GIRLS BATHROOM (NEW SIDE) CEILING TILES NEED TO BE REPLACED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/19/01. HORNE ENGINEER STEPHEN CALDWELL | September 17, 2001 | December 13, 2001 | 87 days |
| Deal Junior High School | FM-200120409 01 12/17/01 (DEAL) ASBESTOS ASSESSMENT REQ. 1ST AND 2ND FLOORS/ GIRLS RESTROOM REHANG HANDICAP STALL DOOR IN GIRLS RFESTROOM AND REHANG STANDARD PARTITION DOOR IN GIRLS RESTROOM (2ND FLOOR BY ROOM 208). ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: SHARON VOSS | September 24, 2001 | December 17, 2001 | 84 days |
| Rudolph Elementary School | FM-200124713 01 12/17/01 (RUDOLPH) !!VERY URGENT!! 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/BOYS RESTROOM: UNCLOG TWO (2) URINALS. UNABLE TO CLEAR MANUALLY WITH PLUNGER. THIS RESTROOM IS ADJACENT TO THE PRINCIPALS OFFICE. THERE IS A CONSISTANT OFFENSIVE SMELL OF URINE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/07/01. RICHARD GIBSON - SAFETY (202)576-5584 (RG) | December 7, 2001 | December 17, 2001 | 10 days |
| Birney Elementary School | FM-200115472 01 12/17/01 BIRNEY BATHROOMS 3RD FLOOR 3RD FLOOR GIRLS BATHROOM TOILET STOP UP (NEW SIDE). BOYS BATHROOM (OLD SIDE) URINALS STOP UP. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/13/01. HORNE ENGINEER STEPHEN CALDWELL | July 20, 2001 | December 17, 2001 | 150 days |
| Merritt Middle School | FM-200124645 /01 12/19/01 (MERRITT) 1ST FLOOR/ BOYS RESTROOM WEST ENDOF BUILDING LOCK NEEDS TO BE REPLACED OR REPAIRED THE LOCK IN THIS DOOR IS FALLING OUT OF DOOR RESTROOMS MUST BE LOCKED AT ALL TIMES TO STOP VANDELISM. | December 17, 2001 | December 19, 2001 | 2 days |
| Merritt Middle School | FM-200124644 /01 12/19/01 (MERRITT) 1ST FLOOR/ BOYS RESTROOM (EAST) END BY MUSIC NEEDS LOCK REPLACED OR REPAIRED. DOOR LOCK IS VERY DIFFICULT TO OPEN. | December 17, 2001 | December 19, 2001 | 2 days |
| Dunbar High School | FM-200121884 /01 12/21/01 (DUNBAR) 3-W CAFETERIA !!! URGENT !!! NEED PLUMBER TO REPAIR SINK IN THE FEMALE HANDICAP RESTROOM. SINK SUPPORT BRACKET IS BROKEN. | October 18, 2001 | December 21, 2001 | 64 days |
| Roosevelt High School | FM-200107463 01 12/31/01 ROOSEVELT SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE. 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | April 5, 2001 | December 31, 2001 | 270 days |
| Adams Elementary | FM-200123663 /01 1/3/02 (ADAMS) ABESTOS ASSESSMENT REQUIRED 2ND FLOOR/TEACHERS LOUNGE BATHROOM THERE IS A SHORT IN THE LIGHT IN THE TEACHERS LOUNGE BATHROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/21/01 HORNE ENGINEERING - TROY WILCOME (RG) | November 20, 2001 | January 3, 2002 | 44 days |
| Simon Elementary School | FM-200124250 /01 1/7/02 (SIMON) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR/PRINCIPALS BATHROOM INSTALL AN OUTLET IN THE PRINCIPALS RESTROOM. ASBESTOS CODE A-CLEAR FOR REPAIR 12/05/01 BY HORNE ENGINEER: Z MAHNOOD | November 30, 2001 | January 7, 2002 | 38 days |
| Woodson High School | FM-200126154 /01 1/8/02 (WOODSON, H.D.) !!! EMERGENCY !!! GROUND FLOOR/ HOSPITALITY ROOM, BATHROOM UNCLOG TOILET INSIDE THIS RESTROOM. | December 27, 2001 | January 8, 2002 | 12 days |
| Macfarland Middle School | FM-200118394 01 1/8/02 (MACFARLAND) ASBESTOS ASSESSMENT REQ. BOYS BATHROOMS 1) URINALS ON THE 2ND FLOOR ARE STOPPED UP AND NEED SNAKING OUT. 2) 2 SINKS ARE DISCONNECTED AND NEED TO BE REPLACED ON 2ND FLOOR. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/25/01BY HORNE ENGINEER: SHARON VOSS | August 27, 2001 | January 8, 2002 | 134 days |
| Macfarland Middle School | FM-200118395 01 1/8/02 (MACFARLAND) ASBESTOS ASSESSMENT REQ. BOYS BATHROOMS 1) URINALS ON THE 3RD FLOOR ARE STOPPED UP AND NEED SNAKING OUT. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/25/01BY HORNE ENGINEER: SHARON VOSS | August 27, 2001 | January 8, 2002 | 134 days |
| Nalle Elementary School | FM-200120395 01 1/8/02 NALLE SECOND FLOOR- TEACHERS BATHROOM - NEW WING 1) REPLACE BROKEN DOOR. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: RAY AGNANT | September 24, 2001 | January 8, 2002 | 106 days |
| Eliot Junior High School | FM-200110616 01 1/8/02 (ELIOT) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR CUSTODIAL CLOSET/NEAR GIRLS BATHROOM: SINK FAUCET IS STRIPPED, WATER WILL NOT TURN OFF. WATER RUNS IN-TO THE SINK DRAIN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/03/01. RICHARD GIBSON- SAFETY (202)576-5584(RG) | May 18, 2001 | January 8, 2002 | 235 days |
| Hine JHS | FM-200119007 01 1/8/02 (HINE) 1. ASBESTOS ASSESSMENT REQUIRED. Floor 4th- Boy restroom, Replace missing toilet partitions. Requester Phone: 202 698-3330 ASBESTOS CODE A-CLEAR FOR REPAIR BY TROY WILCOME HORNE ENG. ON 9/10/01. | August 22, 2001 | January 8, 2002 | 139 days |
| Bowen Elementary School | FM-200107002 01 1/9/02 BOWEN ALL RESTROOM - THRU OUT BUILDING BOYS AND GIRLS WATER FAUCET FIXTURES ARE BROKEN NEEDS REPLACE ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/30/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | March 30, 2001 | January 9, 2002 | 285 days |
| Duke Ellington School | FM-200120213 01 1/9/02 (ELLINGTON) ASBESTOS ASSESSMENT REQ. 1ST FLOOR AND BASEMENT 1) MAIN OFFICE- NO WATER PRESSURE IN FACE BOWL 2) 1ST FLOOR WOMENS BATHROOM- NOT WORKING PROPERLY. 3) BOYS BATHROOM (DANCE STUDIO)- COMMODE NOT FLUSHING AND URINAL HAS MISSING SCREWS, IT LEAKS WHEN FLUSHED. 4) BASEMENT GIRLS BATHROOM- NOT FLUSHING PROPERLY. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/21/01. LEROY MINTON - SAFETY (202)576-6691 | September 20, 2001 | January 9, 2002 | 111 days |
| Janney Elementary School | FM-200113308 01 1/10/02 JANNEY FIRST FLOOR PRE-KINDERGARTEN ROOM 1) REPLACE TOILET STALL DOOR DOOR FELL OFF WHILE A STUDENT WAS USING RESTROOM STALL DOOR NEEDS TO BE RE-HUNG Asbestos code A-clear for repair by Charles E. Buchanan 6/15/01 Recommend that door be re-hung with door hinge. | June 14, 2001 | January 10, 2002 | 210 days |
| Kenilworth ES | FM-200108483 02 1/12/02 KENILWORTH FIRST (1ST), SECOND (2ND) AND THIRD (3RD) FLOOR THROUGHOUT BUILDING TH CHANGE LOCKES ON ALL CLASSROOM DOORS AND REKEY TO A MASTER. REKEY ALL CLASSROOM DOORS THROUGH-OUT 1ST, 2ND AND 3RD FLOORS OF BUILDING. ALSO REKEY LOCKS ON RESTROOM DOORS THROUGH OUT THE 1ST, 2ND AND 3RD FLOORS. SAFETY AND SECURITY HAZARD. | January 10, 2002 | January 12, 2002 | 2 days |
| Meyer Elementary School | FM-200127048 02 1/13/02 (MEYER) 1ST FLOOR/ BOYS BATHROOM AND COUNSELORS OFFICE THE LOCKS ON BOTH DOORS ARE BROKE. NEED A LOCKSMITH A.S.A.P. | January 11, 2002 | January 13, 2002 | 2 days |
| Deal Junior High School | FM-200126829 02 1/15/02 (DEAL) ASBESTOS ASSESSMENT REQUIRED BASEMENT GIRLS RESTROOM REPLACE BROKEN SINK. SINK NEEDS A "T" CONNECTION FOR DRAIN BELONGING TO THE OTHER SINK. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 01/08/02. HORNE ENGINEERING - STEPHEN CALDWELL (RG) CODE A- CLEAR FOR REPAIR BY CHARLES E. BUCHANAN ON 2/28/02 | January 4, 2002 | January 15, 2002 | 11 days |
| Ballou Senior High School | FM-200115393 01 1/15/02 (BALLOU) "EMERGENCY" 1. ASBESTOS ASSESSMENT REQUIRED. A-WING 1ST FLOOR/NEAR ROOM #117-A: BOYS URINAL LEAKING PROFUSELY IN THE BATHROOM, FLOODING THE HALLS; SHUT OFF VALVES ARE NOT HOLDING. CODE A - ASBESTOS ABATED ON 8/25/01 (SG) PER LEROY MINTONS CONFIRMATONS SAME AS fm-200115390. | July 19, 2001 | January 15, 2002 | 180 days |
| Janney Elementary School | FM-200120709 01 1/15/02 (JANNEY) ASBESTOS ASSESSMENT REQ. !!!! EMERGENCY !!!! FAUCETS IN BATHROOMS. THE SCHOOL HAS ONLY ONE BATHROOM FOR THE BOYS AND ONE FOR THE GIRLS. FAUCETS IN BOTH ARE NOT WORKING WELL -- HEALTH RISK. WE NEED FAUCETS THAT CAN TURN EASILY FOR YOUNGER STUDENTS. THE WORK DONE IN AUGUST WAS NOT ADAQUATE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/05/01. RICHARD E GIBSON - SAFETY (202)576-5584 | September 28, 2001 | January 15, 2002 | 109 days |
| Lincoln Middle School | FM-200127310 02 1/15/02 (LINCOLN) 3RD FLOOR/ BOYS BATHROOM !! EMERGENCY !! REPAIR THE BRADLEY BASIN IN THE BOYS BATHROOM. THE VALVE DOSENT HOLD TO SHUT THE WATER OFF. WATER IS FLOODING THE BATHROOM. | January 11, 2002 | January 15, 2002 | 4 days |
| Jessie LaSalle Elementary | FM-200119557 01 1/15/02 (LASALLE) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM REPLACE CRACKED FACE SINK. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | September 10, 2001 | January 15, 2002 | 127 days |
| Seaton Elementary School | FM-200124078 /01 1/15/02 (SEATON) ASBESTOS ASSESSMENT REQUIRED 1FST FLOOR KITCHEN UNCLOG COMMODE IN KITCHEN STAFF RESTROOM. UNABLE TO CLEAR BY USING PLUNGER AND HAND ARGUR ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/04/01. LEROY MINTON - SAFETY (202)576-6691 | November 29, 2001 | January 15, 2002 | 47 days |
| Deal Junior High School | FM-200124735 01 1/15/02 (DEAL) ASBESTOS ASSESSMENT REQUIRED 2ND FLOOR/BOYS RESTROOM REPLACE LEAKING & CRACKED DRAIN PIPE UNDER SINK IN THE 2ND FLOOR BOYS RESTROOM ASBESTOS CODE A - CLEAR FOR REPAIRS ON 01/08/02. HORNE ENGINEERING - STEPHEN CALDWELL (RG) | December 7, 2001 | January 15, 2002 | 39 days |
| Winston EC | FM-200125792 01 1/15/02 WINSTON !!!EMERGENCY!!! Replace washers,and leaky pipes on sinks in 4th Fl. cafeteria. Also replace washer on sink in girls bathroom rm# 229. Requester Phone: 645-3300 Web Form Location ID: 355 A CALL CAME IN FROM KAREN WALLS THIS AFTERNOON TO REPORT WATER FROM SINK IS LEAKING PROFUSELY, AND STATUS HAS BEEN UP-GRADED TO AN EMERGENCY. | December 7, 2001 | January 15, 2002 | 39 days |
| Thomson Elementary School | FM-200127084 02 1/15/02 (THOMSON) ***URGENT*** 1ST FLOOR ROOM 110 & BASEMENT BOYS RESTROOM 1) 1ST FLR ROOM 110, THERE IS LOW WATER PRESSURE & THE COMMODE IS NOT FLUSHING 2) BASEMENT/BOYS BATHROOM--WATER CUTOFF VALVE IS NOT WORKING ON THE URINAL, WATER IS LEAKING INSIDE THE WALL & COMMODE NOT FLUSHING POC: MELVIN MACK (202)576-8046 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 01/10/02. HORNE ENGINEERING - SAM EBRAHIM (RG) | January 9, 2002 | January 15, 2002 | 6 days |
| Thomson Elementary School | FM-200127085 02 1/15/02 (THOMSON) ***URGENT*** 1ST, 2ND & 3RD FLOOR RESTROOMS 1)1ST FLOOR, ROOM 106--COMMODE IS NOT FLUSHING & TANK NEEDS TO BE REPLACED OR REPAIRED 2) 2ND FLOOR COMMODE IS NOT FLUSHING & WATER PRESSURE IS LOW 3) 3RD FLOOR BOYS BATHROOM, URINALS ARE STOPPED UP. HAVE USED PLUNGER & SNAKE, BUT PROBLEM PERSISTS. | January 9, 2002 | January 15, 2002 | 6 days |
| Cook J.F. Elementary School | FM-200126911 02 1/16/02 (COOK,J.F.) **EMERGENCY** 1ST FLOOR BOYS BARHROOM THE URINALS IN THE 1ST FLOOR BOYS RESTROOM ARE ALL RUNNING NON-STOP (STOP-VALVE MAY BE STUCK) | January 7, 2002 | January 16, 2002 | 9 days |
| Meyer Elementary School | FM-200111478 01 1/16/02 MEYER FIRST FLOOR BOYS RESTROOM 1) REPLACE TWO BROKEN WINDOWS IN BOYS RESTROOM ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/04/01. HORNE ENGINEERING - DONALD MAGLIENTI | May 29, 2001 | January 16, 2002 | 232 days |
| Wilson J. O. ES | FM-200126873 02 1/16/02 (WILSON,J.O.) ***EMERGENCY*** 1ST FLOOR KITCHEN BATHROOM LIGHT FIXTURE IS SPARKING & HAS CAUSED THE CIRCUIT BREAKER TO POP OUT TO THE OFF POSITION. | January 7, 2002 | January 16, 2002 | 9 days |
| Backus Middle School | FM-200127400 02 1/16/02 (BACKUS) ***EMERGENCY*** 2ND FLOOR BOYS RESTROOM WINDOW PANE IN 2ND FLOOR BOYS RESTROOM HAS BEEN KNOCKED OUT DUE TO VANDALISM & NEEDS TO BE REPLACED. COLD AIR IS COMING IN ONTO THE WATER PIPES. | January 14, 2002 | January 16, 2002 | 2 days |
| Malcolm X ES | FM-200120085 01 1/17/02 (MALCOLM X) ASBESTOS ASSESSMENT REQ. 3RD AND 4TH FLOOR PEELING PAINT GIRLS BATHROOM MISSING TILE CUSTODIAN CLOSET MISSING TILE COUNSELERS OFFICE TEACHERS LOUNGE. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: BIPIN NANAVARY | September 18, 2001 | January 17, 2002 | 121 days |
| Smothers ES | FM-200201062 02 1/18/02 (SMOTHERS) !!!EMERGENCY!!! 1ST FLOOR/ROOM #102: LEAK IN BATHROOM COMING FROM 1/2 INCH COPPER PIPE. PIPE LEADING TO SINK AND TOILET, VALVES ARE LEAKING, AND BATHROOM FLOOR IS FLOODED. | January 15, 2002 | January 18, 2002 | 3 days |
| Malcolm X ES | FM-200122047 01 1/18/02 (MALCOLM X) 1. ASBESTOS ASSESSMENT REQUIRED. urine bowl in the 4th floor boys bathroom needs to be repaired. Requester Phone: 202 645 3409 Requestor Phone: 202 645 3409 ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: BIPIN NANAVARY | October 9, 2001 | January 18, 2002 | 101 days |
| Malcolm X ES | FM-200108567 01 1/18/02 (MALCOLM X) 4TH FLOOR/WOMENS RESTROOM WOMENS BATHROOM, FAUCET IN SINK IS NOT WORKING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/15/01. RONALD EDWARDS - SAFETY (202)576-6693 | April 17, 2001 | January 18, 2002 | 276 days |
| Spingarn High School | FM-200123195 01 1/18/02 (SPINGARN) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ BOYS RESTROOM REPAIR OR REPLACE (4) FOUR SINKS INSIDE THIS RESTROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/29/01. RONALD EDWARDS - SAFETY (202)576-6693 | November 9, 2001 | January 18, 2002 | 70 days |
| Hardy Middle School | FM-200201315 02 1/18/02 (HARDY/ FILLMORE) 3RD FLOOR/ BOYS BATHROOM !!! URGENT !!! URINAL IS BROKEN AND FILLED WITH URINE AND IS ABOUT TO OVERFLOW. MR. GARCIA FROM FACILITIES MANAGEMENT WILL BE AT THE SCHOOL ON 1/18/02. | January 17, 2002 | January 18, 2002 | 1 day |
| Spingarn High School | FM-200115599 01 1/18/02 SPINGARN BOYS RESTROOM SPACE #189 REPLACE COMMODE DUE TO FIRE DAMAGE - COMMODE IS CRACKED BADLY. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/20/01 BY DCPS SAFETY CHARLES E. BUCHANAN (202-567-5582) | July 23, 2001 | January 18, 2002 | 179 days |
| Ferebee-Hope Elementary School | FM-200115535 01 1/18/02 FEREBEE-HOPE SECOND (2ND) FLOOR - GIRLS LOCKER ROOM (RESTROOM) PLUMBING: UNCOLG AND REPLACE DELANY TYPE STOP VALVE WITH SLOAN TYPE VALVE AND FLUSHMETER. HEALTH HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/03/01. RICHARD GIBSON- SAFETY (202)576-5584(RG) | July 21, 2001 | January 18, 2002 | 181 days |
| Spingarn High School | FM-200111408 01 1/18/02 SPINGARN BASEMENT CUSTODIANS OFFICE RESTROOM 1) UNSTOP COMMODE IN CUSTODIANS OFFICE RESTROOM BLOCKAGE MAY BE IN WASTE LINE ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/20/01 BY DCPS SAFETY CHARLES E. BUCHANAN (202-567-5582) THE UNSTOP COMMODE WAS REPAIR BY BUILDING STAFF. | May 29, 2001 | January 18, 2002 | 234 days |
| Ferebee-Hope Elementary School | FM-200112163 01 1/18/02 FEREBEE-HOPE GROUND FLOOR D BUILDING WOMENS RESTROOM 1) REPLACE TWO (2) DELANY TYPE STOP VALVES AND REPLACE WITH SLOAN TYPE STOP VALVES AND FLUSHOMETER ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/21/01. LEROY MINTON - SAFETY (202)576-6691 | June 4, 2001 | January 18, 2002 | 228 days |
| Ferebee-Hope Elementary School | FM-200201008 02 1/18/02 (FEREBEE-HOPE) ***ABSOLUTE EMERGENCY*** 2ND FLOOR/LADY TEACHERS RESTROOM PIPE TO HAND SINK IS RUPTURED AT THE MAIN COLD WATER SUPPLY WHICH IS NOW SHUT OFF. POC: WILLIAM MOODY ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 HORNE ENGINEER: EDWARD RODRIZUEZ | January 14, 2002 | January 18, 2002 | 4 days |
| Malcolm X ES | FM-200109767 01 1/18/02 MALCOLM X SECOND (2ND) FLOOR 1) ASBESTOS ASSESSMENT REQUIRED. 2) BROKEN SINK IN BOYS RESTROOM. 3) WATER FOUNTAIN IN TEACHERS LOUNGE NOT WORKING. SAFETY HAZARD. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: BIPIN NANAVARY | May 8, 2001 | January 18, 2002 | 255 days |
| Kramer Middle School | FM-200124541 01 1/18/02 (KRAMER) ASBESTOS ASSESSMENT REQUIRED FIRST FLOOR/GIRLS RESTROOM REPAIR OR REPLACE CONTROL VALVE, TRAP & DRAIN PIPE WHERE SINK IS LEAKING WATER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/05/01. HORNE ENGINEERING - TROY WILCOME (RG) | December 5, 2001 | January 18, 2002 | 44 days |
| Malcolm X ES | FM-200119702 01 1/18/02 (MALCOLM X) major leak in the cafeteria ladies bathroom. Requester Phone: 202 645 3409 Requestor Phone: 202 645 3409 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/13/01. RONALD EDWARDS - SAFETY (202)576-6693 | August 28, 2001 | January 18, 2002 | 143 days |
| Kramer Middle School | FM-200201076 02 1/18/02 (KRAMER) ***EMERGENCY*** 1ST FLOOR PRINCIPALS OFFICE RESTROOM SHUT-OFF VALVE ON THE COMMODE IN THE PRINCIPALS OFFICE IS LEAKING WATER ONTO THE FLOOR & NEEDS IMMEDIATE ATTENTION. | January 15, 2002 | January 18, 2002 | 3 days |
| Turner Elementary School | FM-200115938 01 1/18/02 TURNER GIRLS RESTROOM - 3RD FLOOR ASBESTOS ASSESSMENT REQUIRED REMOVE PARTION WALL IN GIRLS RESTROOM ON 3RD FLOOR OLD SIDE . WALL HAS NO SUPPORT AND COULD FALL ON SOMEONE. (SAFETY HAZARD) SLATE WALL WEIGHS ABOUT 300 POUNDS. CODE A-CLEAR FOR REPAIR BY HORNE ENG. 8/13/01 (CEB) | July 26, 2001 | January 18, 2002 | 176 days |
| Payne Elementary School | FM-200201228 02 1/22/02 (PAYNE) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ GIRLS BATHROOM WINDOW PANE IS BROKEN AND NEEDS TO BE REPLACED. COLD AIR IS COMING IN THE BUILDING. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/18/02 BY HORNE ENGINEER: SHERYLL JAMES | January 16, 2002 | January 22, 2002 | 6 days |
| Garnet-Patterson MS | FM-200113876 01 1/23/02 GARNET-PATTERSON 1) ASBESTOS ASSESSMENT REQUIRED. 2) REMOVE TOILET GASKJETS ON FIRST (1ST) FLOOR BOYS RESTROOM. ENVIROBATE (IT GROUP) (703-461-6848 CODE A - ASBESTOS ABATED ON 6/25/01(SG) PER LEROY MINTONS CONFIRMATION WORK ORDER NUMBER WAS GENERATED JUNE 6TH, 2001 FOR A WORK PERMIT TO BE ISSUED. THIS IS A BACK LOG JOB. THIS WORK WAS NEVER ISSUED A TRUE WORK ORDER NUMBER. (SHEILA HOWARD) | June 22, 2001 | January 23, 2002 | 215 days |
| Patricia R Harris Ed Center | FM-200104724 01 1/23/02 HARRIS, P.R. MAIN ROOF 1. EXHAUST FAN MOTOR #34, NEW MOTOR, NEEDS PULLEY REPLACED. BELT ON SITE. HP 3/4, PH 3, RPM 1725, VOLT 208/230/460, FRAM 56DP, HZ 60. REPLACE PULLEY TO EXHAUST FAN. 2. EXHAUST FAN MOTOR #32 NEW MOTOR HAS BEEN INSTALLED CANNOT CHECK MOTOR START UP DUE TO OVERLOAD RELAY MISSING. SIZE: SPUAR-D B2-65, STARTER SIZE: NEMA SIZE 1, PH 3, MAX HP 7-1/2, 10 VOLT AC 200/230/380/460/575, TYPE SCO-3, FORM - S, SERIAL - A. 3. EXHAUST FAN MOTOR #42 BAD MOTOR BEARINGS, MOTOR TRY TO START THEN LOCK UP. G.E. MOTOR, SERIAL #311PO38A, HP 1/2, PH 3, HZ 60, RPM 1725, FRAM B55, VOLTS 230/460, AMP 2.8/1.4. 4. EXHAUST FAN MOTOR #29 MOTOR BEARING IS BAD AND FAN SHAFT BEARING IS BAD, ALL NEED REPLACING. SER. #311P0421, MOD. # FA74, HP 3/4, RPM 1725, VOLT 230/460, AMP 3.6/1.8, PH 3, FRAM D56, HZ 60. REPLACE MOTOR BEARING AND FAN SHAFT BEARING TO ABOVE EQUIPMENT. 5. EXHAUST FAN MOTOR #53 G.E. MOTOR NOT WORKING. REPLACE BROKEN 3-POLESWITCH, 10A, 250 VAC, 15A, 125 VAC, HP 1, PH 1.2, 125-480 VAC, HP 1, 3 PH, 125-500 VAC, OLD SWITCH BURN OUT. 6. EXHAUST FAN MOTOR #44 G.E./AC MOTOR BURN UP - REPLACE MOTOR SER. #311PO38A, HP 1/2, RPM 1725, VOLT 230/460, AMP 2.8/1.4, HZ 60, FRAM B56, PH 3. 7. EXHAUST FAN MOTOR #28 REPLACE TOGGLE SWITCH TO EXHAUST FAN MOTOR #28 FOR RESTROOMS. 3-POLE SWITCH, 10A, 250 VAC, 15A, 125 VAC, 1 HP, 1.2 PH, 125-480 VAC, 1 HP, 3 PH, 125-500 VAC, OLD SWITCH BURN OUT. | March 2, 2001 | January 23, 2002 | 327 days |
| Dunbar High School | FM-200107459 01 1/24/02 DUNBAR SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | April 5, 2001 | January 24, 2002 | 294 days |
| Eastern High School | FM-200122560 02 1/24/02 (EASTERN) ASBESTOS ASSESSMENT REQ. BATHROOMS THROUGH OUT REPLACE CYLINDERS IN STUDENT BATHROOMS ANS MAKE EXTRA KEYS. TO PROTECT STUDENT POPULATION WE MUST HAVE CONTROL OF BATHROOMS. STAFF IS POSSIBLY OPENING BATHROOMS FOR STUDENTS LEAVING OPEN WHEN CYLINDER WAS CHANGED SECURITY WILL BE OPENING AND MONITORING RESTROOMS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/21/01. HORNE ENGINEERING - BIPIN NANAVATY (RG) | January 22, 2002 | January 24, 2002 | 2 days |
| Stuart-Hobson Middle School | FM-200107836 01 1/24/02 STUART-HOBSON ASBESTOS ASSESSMENT REQUIRED BATHROOMS ON 2ND FLOOR. DEMOLISH AND REMOVE FLOORING. # HRGM CORP. POC: JOHN RIDGLEY-202-253-8370 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. | April 9, 2001 | January 24, 2002 | 290 days |
| Stuart-Hobson Middle School | FM-200107837 01 1/24/02 STUART-HOBSON ASBESTOS ASSESSMENT REQUIRED BATHROOMS ON 1ST FLOOR. DEMOLISH AND REMOVE FLOORING. # HRGM CORP. POC: JOHN RIDGLEY-202-253-8370 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. | April 9, 2001 | January 24, 2002 | 290 days |
| Garnet-Patterson MS | FM-200121809 02 1/27/02 (GARNET-PATTERSON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM DOOR CANT LOCK DOOR AT ALL. NEED REPAIR. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-16-01 HORNE ENGINEER: BILL CAMPION | January 25, 2002 | January 27, 2002 | 2 days |
| Turner Elementary School | FM-200126951 02 1/27/02 (TURNER) NEED THE LOCKS CHANGED IN THE FOLLOWING AREAS: NEW BLDG. : BOYS AND GIRLS BATHROOM, HALL DOORS, THE EXIT DOORS LEADING TO THE PLAYGROUND, 3RD FLOOR LOCKS NEED REPAIRED IN ROOM 307, NEW BLDG. ROOM 213. | January 25, 2002 | January 27, 2002 | 2 days |
| Woodson High School | FM-200201222 02 1/28/02 (WOODSON,H.D.) ASBSTOS ASSESSMENT REQUIRED FLOORS 1, 2 & 4 RESTROOMS & CUSTODIAN CLOSET REPLACE BROKEN WINDOWS IN THE CUSTODIAL CLOSET & RESTROOMS (SIZE 5X10). ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/18/02 BY HORNE ENGINEER: SHARON VOSS | January 16, 2002 | January 28, 2002 | 12 days |
| Leckie Elementary School | FM-200123287 /01 1/28/02 LECKIE LOCATION GROUND FLOOR BATHROOM ROOM14 1. ASBESTOS ASSESTMENT REQUIRED. 2. REPAIR LEAKING 3/4 INCH BLACK PIPE ON SUPPLY/RETURN LINE. CAPE (IT GROUP) 703-461-6848 CODE A - ABATED ON 11/15/01 CONFIRMED BY LEROY MINTON JR. - SAFETY (RG) | November 14, 2001 | January 28, 2002 | 75 days |
| Langdon Elementary School | FM-200120813 01 1/28/02 (LANGDON) repair the broken commodes in first floor boys bathroom near the entrance Requester Phone: 576-6048 Requestor Phone: 576-6048 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/07/01 RONALD EDWARDS - SAFETY (202)576-6693(RG) | September 25, 2001 | January 28, 2002 | 125 days |
| Birney Elementary School | FM-200117889 01 1/28/02 (BIRNEY) ASBESTOS ASSESSMENT REQ. 1ST. FLOOR BATHROOM BOYS BATHROOM 1ST. FLOOR OLDSIDE URINAL BROKEN NEED TO BE REPLACED AND ONE URINAL IS MISSING AND ALL URINALS NEED TO BE UNSTOPED. ASBESTOS CODE A-CLEAR FOR REPAIRS BY 10/17/01 HORNE ENGINEER : SAM EBRAHIM | August 20, 2001 | January 28, 2002 | 161 days |
| Rudolph Elementary School | FM-200119405 01 1/29/02 (RUDOLPH) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM OLD SIDE OF THE BUILDING BOYS BATHROOM NEEDS NEW FAUCET FOR WATER TO TURN ON AND OFF. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/10/01. RONALD EDWARDS - SAFETY (202)576-6691 | September 7, 2001 | January 29, 2002 | 144 days |
| Bruce-Monroe Elementary School | FM-200104153 01 1/30/02 BRUCE-MONROE 2ND & 3RD FLOOR GIRLS & BOYS RESTROOM CENTERS 201, 203, 204, 301, 302 &304 REPLACE OR REPAIR THEW BRADLEY BASINS IN THE GIRLS & BOYS BATHROOM. THEY ARE NOT WORKING. CHILDREN DO NOT HAVE ANY PLACE TO WASH THEIR HANDS. ASBESTOS CODE A-CLEAR FOR REPAIRS BY 10/17/01 HORNE ENGINEER : STEPHEN CALDWELL | February 22, 2001 | January 30, 2002 | 342 days |
| Bancroft Elementary School | FM-200114378 01 1/30/02 BANCROFT ROOF 1) ROOF DRAIN OVER TOP OF BOYS RESTROOM IS DAMAGED CEILING IN BOYS RESTROOM AND AROUND LIGHT FIXTURE WATER LEAKING AROUND ROOF DRAIN CAUSING MAJOR DAMAGE TO CEILING | June 29, 2001 | January 30, 2002 | 215 days |
| Whittier Elementary School | FM-200111643 01 1/30/02 WHITTIER FIRST FLOOR CUSTODIANS OFFICE RESTROOM 1) SUPPLY LINE BROKEN IN CUSTODIANS RESTROOM (NO HOT WATER) IN SINK. WILL REQUIRE PENETRATING FLOOR TO ACCESS LINE ASBESTOS CODE A - CLEAR FOR REPAIRS ON 9/24/01. LEROY MINTON - SAFETY (202)576-6691 (RG) ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER SHARON VOSS | May 30, 2001 | January 30, 2002 | 245 days |
| Payne Elementary School | FM-200202086 02 1/30/02 PAYNE BREAK-IN!!!! FIRST FLOOR GIRLS RESTROOM AND FIRST FLOOR CORRIDOR. 1) REPAIR OR REPLACE (2) EXTERIOR WINDOWS. | January 30, 2002 | January 30, 2002 | 0 days |
| Webb Elementary School | FM-200126909 02 1/30/02 (WEBB) **EMERGENCY** 2ND FLOOR/LEARING CENTER #2 1) BURST PIPE ON SINK IN MENS RESTROOM NEEDS REPAIR. 2) TURN-OFF VALVE IN BOYS RESTROOM NOT WORKING & A BUCKET IS BEING USED TO CATCH LEAKING WATER. | January 7, 2002 | January 30, 2002 | 23 days |
| Birney Elementary School | FM-200125570 /01 1/30/02 (BIRNEY) ASBESTOS ASSESSMENT REQUIRED 3RD FLOOR BOYS RESTROOM (OLD SIDE) REPLACE FAUCET ON SINK ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/22/01. RICHARD GIBSON - SAFETY (202)576-5584 (RG) | December 18, 2001 | January 30, 2002 | 43 days |
| Ronald H. Brown MS | FM-200201869 02 1/31/02 (BROWN, RON) 2ND FLOOR/ BOYS BATHROOM NEAR ROOM 231 REPAIR KEY AND KNOB LOCK ON BATHROOM DOOR. DOOR WILL NOT LOCK. | January 29, 2002 | January 31, 2002 | 2 days |
| Jefferson JHS | FM-200127246 02 1/31/02 (JEFFERSON) BASEMENT, 1ST, AND 2ND FLOORS/ ROOMS: 405, 216, BOYS BATHROOM IN BOYS GYM REPAIR OR REPLACE LOCKS. LOCKS ARE NOT FUNCTIONAL. | January 29, 2002 | January 31, 2002 | 2 days |
| Nalle Elementary School | FM-200105567 01 2/1/02 NALLE FIRST (1ST) FLOOR - GIRLS RESTROOM BY ROOM #130 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR A BUSTED PIPE IN GIRLS RESTROOM. SAFETY HAZARD. CODE A - ASBESTOS ABATED ON 4/30/01 (SG) PER LEROY MINTONS CONFIRMATION. | March 12, 2001 | February 1, 2002 | 326 days |
| Maury Elementary School | FM-200202152 02 2/1/02 (MAURY) ***EMERGENCY*** BASEMENT BOYS RESTROOM/WEST FUILDING URINALS ARE BACKED UP IN THE BASEMENT LEVEL BOYS RESTROOM & SPILLING OVER ONTO THE FLOOR. | January 30, 2002 | February 1, 2002 | 2 days |
| Montgomery ES | FM-200120695 01 2/1/02 (MONTGOMERY) OUTSIDE BATHROOM: URINALS CONTINUE TO RUN, FLOODING THE FLOOR AND OUT ON THE PLAYGROUND. | September 28, 2001 | February 1, 2002 | 126 days |
| Roosevelt High School | FM-200110950 01 2/1/02 ROOSEVELT FIRST FLOOR BOYS AND GIRLS RESTROOM 1) INSTALL NEW DOORS TO COMPLY WITH ADA CODE FOR SPECIAL NEEDS STUDENTS EXISTING DOORS ARE BADLY DAMAGED ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/24/01. | May 24, 2001 | February 1, 2002 | 253 days |
| Park View ES | FM-200125255 02 2/1/02 (PARKVIEW) 2ND FLOOR/ EXIT DOORS HALLWAY DOORS LOCKS ARE JAMMED KIDS CANT OPEN DOORS ON 2ND FLOOR BY BOYS BATHROOM. | January 30, 2002 | February 1, 2002 | 2 days |
| Roosevelt High School | FM-200118088 01 2/1/02 (ROOSEVELT) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ MENS BATHROOM REPLACE SINGLE HOT AND COLD WATER FAUCETS IN SINK. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/27/01. RONALD EDWARDS - SAFETY (202)576-6693 | August 22, 2001 | February 1, 2002 | 163 days |
| Nalle Elementary School | FM-200120278 01 2/1/02 NALLE ASBESTOS ASSESSMENT REQUIRED. FIRST FLOOR- RESTROOM-OLD WING 1) UNSTOP SINK IN RESTROOM. | September 21, 2001 | February 1, 2002 | 133 days |
| Houston Elementary School | FM-200108496 /01 2/1/02 HOUSTON FIRST (1ST) AND SECOND (2ND) FLOOR BOYS RESTROOMS PROVIDE AND INSTALL CAPS FOR OPEN DRAIN LINES FROM REMOVED URINALS. SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/29/01 RONALD EDWARDS - SAFETY (202)576-6693(RG) | April 16, 2001 | February 1, 2002 | 291 days |
| Garnet-Patterson MS | FM-200120594 01 2/4/02 (GARNET-PATTERSON) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS BATHROOM AND GIRLS BATHROOM REPAIR SPUD SEAL ON WATER CLOSET, IT IS SPLIT. WATER CLOSET IS STOPPED UP. ATTEMPT TO UNSTOP BUT STILL OVERFLOWING. P.S. CUT WATER OFF. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/22/01. LEROY MINTON - SAFETY (202)576-6691 (RG | September 27, 2001 | February 4, 2002 | 130 days |
| Harris, C.W. ES | FM-200111474 01 2/4/02 HARRIS, C.W. FIRST FLOOR GIRLS RESTROOM PRE-KINDERGARTEN AND KINDERGARTEN WING 1) REPLACE SINK ON BRACKET ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/21/01. LEROY MINTON - SAFETY (202)576-6691 | May 29, 2001 | February 4, 2002 | 251 days |
| Bancroft Elementary School | FM-200108799 01 2/4/02 BANCROFT PLAYGROUND GIRLS AND BOYS RESTROOM 1) ASBESTOS ASSESSMENT REQUIRED. 2) REPLACE WOODEN DOOR AND INSTALL TWO(2) METAL FIRE DOORS. SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/25/01. HORNE ENGINEERING - SHARON VOSS (RG) | April 20, 2001 | February 4, 2002 | 290 days |
| Sousa Middle School | FM-200114932 01 2/4/02 SOUSA VARIOUS LOCATIONS 1) TOILET NEEDS WAX RING IN MAIN OFFICE RESTROOM 2) THIRD TOILET FROM WINDOW NEEDS WAX RING IN BOYS RESTROOM 3) TOILET IS TOO SMALL (CHILDS TOILET) IN TEACHERS RESTROOM ON SECOND FLOOR TOILET TOO LOW TO FLOOR 4) FURNISH AND REPLACE TOILET ASBEOSTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER TROY WILCOME | July 9, 2001 | February 4, 2002 | 210 days |
| Hart Middle School | FM-200122880 01 2/4/02 (HART) !!!EMERGENCY!!! 3RD FLOOR/GIRLS BATHROOM: WATER RUNNING PROFUSELY BEHIND TOILET IN WALL DOWN THROUGH 2ND AND 1ST FLOOR, DAMAGING CEILING ON EACH FLOOR. (PLASTER FALLING FROM CEILING) | November 5, 2001 | February 4, 2002 | 91 days |
| Birney Elementary School | FM-200123272 /01 2/4/02 BIRNEY FIRST (1ST) FLOOR - BOYS RESTROOM 1) ASBESTOS ASSESSMENT REQUIRED. 2) CORRECT PLUMBING DEFICIENCIES. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/16/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | November 13, 2001 | February 4, 2002 | 83 days |
| Harris, C.W. ES | FM-200123347 /01 2/4/02 (HARRIS, C.W.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ KITCHEN KITCHEN BATHROOM WATER LEAKING FROM LINE. WALL HAS HOLE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/19/01. HORNE ENGINEERING - TROY WILCOME (RG) | November 14, 2001 | February 4, 2002 | 82 days |
| Hendley Elementary School | FM-200120712 01 2/4/02 (HENDLEY) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BATHROOMS R/R GIRLS AND BOYS TRAP SOLE SYSTEM (SINKS) 1 AND 2 LARGE SINK (BOYS). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/25/01. HORNE ENGINEERING - SHERYLL JAMES (RG) | September 28, 2001 | February 4, 2002 | 129 days |
| Randle-Highlands ES | FM-200201639 02 2/4/02 RANDLE-HIGHLANS !!!! EMERGENCY !!!! OLD BUILDING FIRST (1ST) FLOOR - BOYS RESTROOMS BOYS RESTROOM THREE (3 ) TOILETS BACK-UP. | January 24, 2002 | February 4, 2002 | 11 days |
| Slowe Elementary School | FM-200101292 01 2/4/02 SLOWE ALL CLASSROOM AND BATHROOM MT-20001746 ALL WORK HAS BEEN COMPLETED ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/13/01. CHARLES BUCHANAN - SAFETY (202)576-5582 (RG) | January 16, 2001 | February 4, 2002 | 384 days |
| Jefferson JHS | FM-200202010 02 2/4/02 JEFFERSON ASBESTOS ASSESSMENT REQUIRED BOYS GYM LOCKER ROOM BATHROOM 1) (5 INCH) WASTE LINE BUSTED IN WALL,LEAKING DOWN INTO CLASSROOM BATHROOM IN BASEMENT. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/29/02 BY HORNE ENGINEER: STEPHEN CALDWELL ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/29/02 BY HORNE ENGINEER: STEPHEN CALDWELL | January 29, 2002 | February 4, 2002 | 6 days |
| Noyes Elementary School | FM-200108278 01 2/4/02 (NOYES) (1) ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR/BOYS BATHROOM-NEW WING: REPLACE COMMODE IN BOYS BATHROOM, STUDENT STANDING ON COMMODE, CAUSING IT TO CRACK. PULLED AWAY FROM WALL, ALSO, SEWAGE IS EXPOSE. BATHROOM IS SHUT DOWN. CODE A- CLEAR FOR REPAIR AS OF 4/16/01. | April 12, 2001 | February 4, 2002 | 298 days |
| Raymond Elementary School | FM-200120515 01 2/4/02 (RAYMOND) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ GIRLS BATHROOM THE DRAIN PIPE CONNECTED TO THE HAND SINKS HAVE BROKEN COMPLETELY OFF. STUDENTS ARE UNABLE TO WASH HANDS BECAUSE THE WATER WILL RUN RIGHT ON THE FLOOR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | September 25, 2001 | February 4, 2002 | 132 days |
| Hart Middle School | FM-200202461 02 2/5/02 (HART) ***EMERGENCY*** BASEMENT & 3RD FLOOR GIRLS RESTROOMS THE WINDOWS ARE COMPLETELY BLOWN OUT IN THE BASEMENT & 3RD FLOOR GIRLS RESTROOMS AND NEED TO BE REPLACED (IT IS EXTREMELY COLD AND THE AIR IS BLOWING IN) | February 5, 2002 | February 5, 2002 | 0 days |
| West Elementary School | FM-200202490 02 2/6/02 (WEST) ***URGENT*** 1ST FLOOR TEACHER LOUNGE/LADIES RESTROOM THE WALL TOILET IN THE LADIES RESTSROOM ON THE RIGHT SIDE LEAKS ONTO THE FLOOR. | February 5, 2002 | February 6, 2002 | 1 day |
| Bell High School | FM-200122640 02 2/7/02 (BELL) ASBESTOS ASSESSMENT REQ. LOCKSMITH IS URGENTLY NEEDED TO REPAIR OR REPLACE LOCKS AND DOORKNOBS IN VARIOUS CLASSROOMS AND RESTROOMS TO MAKE THESE ROOMS MORE SECURE. THESE REQUESTS NEEDS IMMEDIATE REPLY. 1ST FLOOR-120A 2ND FLOOR-TEACHERS RESTROOM 3RD FLOOR-BOYS RESTROOM, 301 DOOR KNOB LOCK LOBBY FRONT OF BUILDING (MIDDLE DOOR) PANIC BAR NEEDS REPAIR OR REPLACE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/13/01. HORNE ENGINEERING - SAM EBRAHIM (RG) | February 5, 2002 | February 7, 2002 | 2 days |
| Bell High School | FM-200127276 02 2/10/02 (BELL) ASBESTOS ASSESSMENT REQUIRED 1) PANIC BARS ARE JAMMING ON THE FRONT ENTRANCE DOORS--CANNOT ENTER OR EXIT FROM THESE DOORS. 2) INSTALL A NEW LOCK ON THE BACK DOOR SO MS. WHITE CAN ENTER BUILDING IN THE MORNINGS. 3) INSTALL KNOB LOCKS ON DOORS TO ROOMS 401, 301, 308 & BOYS 3RD FLOOR RESTROOM, 2ND FLOOR MALE TEACHERS RESTROOM, & ROOM 120A. 4) INSTALL NEW LOCKS TO SECURE ROOM 322 &224C WHERE NEW COMPUTERS ARE BEING PLACED (DONORS OF THE COMPUTERS WILL REMOVE THEM BY 1/16/02 IF THE AREA WHERE THEY ARE IS NOT PROPERLY SECURED TO PREVENT THEFT). ASBESTOS CODE A-CLEAR FOR REPAIR ON 2/04/02 BY HORNE ENGINEER: EDWARD RODRIGOEZ | February 8, 2002 | February 10, 2002 | 2 days |
| Hine JHS | FM-200201444 02 2/12/02 (HINE) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR MEN & WOMEN TEACHER LOUNGE RESTROOMS NO POWER IN EITHER OF THE RESTROOMS. BREAKERS REMAIN IN THE "ON" POSITION EVEN WHEN POWER IS NOT BEING RECEIVED IN THE TWO AREAS--THE PROBLEM IS LONG-STANDING AND INTERMITTENT. NEED ELECTRICIAN ASSESSMENT TO SEE IF THERE MAY BE A SHORT. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/24/02 RICHARD GIBSON - SAFETY (202)576-5584 (RG)-01/24/02 | January 22, 2002 | February 12, 2002 | 21 days |
| Webb Elementary School | FM-200202700 02 2/12/02 WEBB !!!! EMERGENCY !!!! FIRST (1ST) FLOOR - CLASSROOM #141 WATER IS LEAKING NEAR THE CLASSROOM FROM THE AREA BY BOYS RESTROOM. | February 8, 2002 | February 12, 2002 | 4 days |
| Backus Middle School | FM-200122083 /01 2/12/02 (BACKUS) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/BOYS BATHROOM: RE-HANG NEWLY INSTALLED PARTITIONS SO THERE WILL BE PRIVACY FOR THE YOUNG MEN. ASBESTOS CODE A - CLEAR FOR REPAIRS 10/30/01. HORNE ENGINEERING - RAYNOMD AGNANT | October 22, 2001 | February 12, 2002 | 113 days |
| Ferebee-Hope Elementary School | FM-200117052 01 2/12/02 (FEREBEE-HOPE) 1. ASBESTOS ASSESSMENT REQUIRED. 4TH FLOOR/MENS RESTROOM: REPLACE FAUCETS HOT AND COLD+. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/01/01. RONALD EDWARDS - SAFFETY (202)576-6693 (RG) | August 9, 2001 | February 12, 2002 | 187 days |
| John Burroughs ES | FM-200120717 01 2/12/02 (BURROUGHS) !!!EMERGENCY!!! ANNEX-1ST FLOOR/BOYS LAVATORY: REPLACE FLANGE ON COMMODE; BATHROOM HAS BEEN CLOSED DOWN. | September 28, 2001 | February 12, 2002 | 137 days |
| Lincoln Middle School | FM-200202806 02 2/13/02 (LINCOLN) ***EMERGENCY*** 1ST FLOOR BOYS RESTROOM A COMMODE IS BACKED UP IN THE 1ST FLOOR BOYS RESTROOM, SENDING DIRTY WATER INTO THE 1ST KITCHEN. | February 11, 2002 | February 13, 2002 | 2 days |
| Cooke H.D. Elementary School | FM-200115530 01 2/13/02 H.D. COOKE SECOND FLOOR -RESTROOM 201 ASBESTOS ASSESSMENT REQD 1) REPLACE FLOOR AND WAX RING NEEDED ON THE TOILET . | July 21, 2001 | February 13, 2002 | 207 days |
| Davis Elementary School | FM-200117434 01 2/14/02 DAVIS GIRLS BATHROOM ACROSS FROM ROOM 204 ASBESTOS ASSESSMENT REQUIRED REPAIR DAMAGED CEILING IN GIRLS BATHROOM. DAMAGE IS COMING FROM OLD LEAKING VENT COVER. VENT COVER HAVE BEEN REPLACED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/16/01. HORNE ENGINEERS - BIPIN NANAVATY | August 14, 2001 | February 14, 2002 | 184 days |
| Spingarn High School | FM-200202833 02 2/14/02 SPINGARN !!!! EMERGENCY !!!! 1. FIRST (1ST) FLOOR - SECURITY OFFICE - RESTROOM. 2. THIRD (3RD) FLOOR - OFFICE #329A (ASSIST. PRINCIPAL) REPLACE THE LOCK FOR BOTH AREAS. SAFETY HAZARD. | February 11, 2002 | February 14, 2002 | 3 days |
| Wilson J. O. ES | FM-200120105 01 2/14/02 (WILSON, J.O.) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/ BOYS AND GIRLS RESTROOM ASSESS, ABATE, AND RESTORE ROOF TOP AND DRAINS. NOTE: DRAIN IS CLOGGED AND ROOF TOP LEAKS INSIDE RESTROOMS. ASBESTOS/LEAD CODE A-CLEAR FOR REPAIR BY 11/01/01 HORNE ENGINEER: BIPIN NANAVARY | September 18, 2001 | February 14, 2002 | 149 days |
| Turner Elementary School | FM-200202522 02 2/16/02 (TURNER) ASBESTOS ASSESSMENT REQUIRED 1ST, 2ND & 3RD FLOORS/NEW & OLD WINGS 1) 1ST FLOOR GIRLS & BOYS RESTROOMS: REKEY LOCKS NEW WING 2) 2ND FLOOR TEACHERS LOUNGE (#200) OLD WING: REKEY LOCKS 3) 3RD FLOOR COMPUTER ROOM #302/OLD WING: REKEY LOCKS ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/26/02. DCPS- SAFETY RICHARD GIBSON (202)576-5584 (RG 03/0102) WORK WAS DONE | February 14, 2002 | February 16, 2002 | 2 days |
| Watkins Elementary School | FM-200123274 /01 2/20/02 WATKINS !!! EMERGENCY !!! FOURTH (4TH) FLOOR - BOYS RESTROOM URINALS ARE STOPPED UP. THEY REQUIRE PLUMBER TO SNAKE IT OUT. | November 13, 2001 | February 20, 2002 | 99 days |
| Simon Elementary School | FM-200124717 01 2/20/02 (SIMON) !! URGENT !! ALL RESTROOMS BOYS AND GIRLS THERE ARE 8 RESTROOMS TOTAL THATS LOCKS NEED TO BE PUT ON DOORS TO BE SECURED DURING CLASSESS SO AS TO NOT HAVE A SITUATION WITH STUDENTS THAT ARE NOT SUPERVISED BY TEACHERS IT WILL ALLOW TEACHERS AND ATHER STAFF MEMBERS TO MONITOR RESTROOM BREAKS WITH CLASSES MORE ORDERLY. | December 7, 2001 | February 20, 2002 | 75 days |
| Simon Elementary School | FM-200124715 01 2/20/02 (SIMON) NEED LOCKS SMITH TO PUT LOCKS ON ALL BATHROOM DOORS ON BASEMENT THRU 3RD FLOOR. | December 7, 2001 | February 20, 2002 | 75 days |
| Walker-Jones EC | FM-200202735 02 2/20/02 (WALKER-JONES) ***URGENT*** 1ST, 2ND & 3RD FLOORS BOYS BATHROOMS THE URINALS ARE BACKING UP IN THE 1ST, 2ND & 3RD FLOOR BOYS BATHROOMS--WHEN FLUSHED, URINE FAILS TO GO DOWN. POC: MR. ROBINSON | February 11, 2002 | February 20, 2002 | 9 days |
| Hart Middle School | FM-200203166 02 2/21/02 (Hart) ***Emergency*** 2nd floor/Old Wing near Boys Restroom Lock on the door to the Asst. Principals office is not working & Asst. Principal cannot retrieve papers needed for an important afternoon meeting---needs access immediately & has been instructed by the L. Magazine not to break the lock to gain entry. | February 20, 2002 | February 21, 2002 | 1 day |
| Macfarland Middle School | FM-200103225 2/7/01 2/22/02 MACFARLAND - NOTE MS. SHEILA HOWARD WAS CALLED AND RESPONED - 02/07/01 CLASSROOM#259 Asbestos Code A - Clear for Repair 3-1-01 CEILING IS LEAKING, WATER SEEMS TO BE COMING FROM RESTROOM OVER CLASSROOM. REPAIR DAMAGED CEILING SO THE CLASS CAN MOVE BACK IN. Asbestos Code A - Clear for Repair 3-1-01 | February 7, 2001 | February 22, 2002 | 380 days |
| Patricia R Harris Ed Center | FM-200202654 02 2/22/02 (HARRIS,P.R.) ASBESTOS ASSESSMENT REQUIRED BOYS RESTROOM IN THE LITTLE GYM AREA NEXT TO THE OLD RECREATION OFFICE 1) THE TOILET IS NO LONGER SECURELY ANCHORED TO THE FLOOR & TURNS ALL THE WAY AROUND. TOILET NEEDS TO BE REANCHORED. | February 8, 2002 | February 22, 2002 | 14 days |
| Spingarn High School | FM-200202559 02 2/22/02 (SPINGARN) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/BOYS AND GIRLS RESTROOM: COMMODES ARE STOPPED-UP; NEED PLUMBER TO SNAKE OUT (2) IN GIRLS RESTROOM AND (2) COMMODES IN BOYS RESTROOM, BOTH ARE ON THE 1ST FLOOR. | February 6, 2002 | February 22, 2002 | 16 days |
| Shepherd ES | FM-200100992 1/01 2/23/02 (SHEPHERD) GROUND FLOOR OLD WING ROOM #101 RESTROOM - REPAIR HOLE IN WALLS IN ROOM #101 RESTROOM - FORMERLY MT-20001382 - SENT TO MS. SHEILA HOWARD FOR ASSESSMENT ON 01/11/01 CODE A - CLEAR FOR REPAIR AS OF 4/27/01. SAME AS FM-200102102 WORK IS COMPLETE. | January 11, 2001 | February 23, 2002 | 408 days |
| Cooke H.D. Elementary School | FM-200202667 02 2/25/02 (COOKE,H.D.) ***URGENT*** BASEMENT LEVEL BOYS RESTROOM 1) SNAKE OUT TOILET IN BOYS RESTROOM 2) INSTALL "P" TRAP ON SINK AND REPLACE FAUCETS | February 8, 2002 | February 25, 2002 | 17 days |
| Jessie LaSalle Elementary | FM-200203386 02 2/25/02 (Lasalle) ***Emergency*** 3rd Floor Replace glass in window in girls restroom on the 3rd floor. | February 25, 2002 | February 25, 2002 | 0 days |
| Cooke H.D. Elementary School | FM-200202666 02 2/25/02 (COOKE,H.D.) ***URGENT*** 3RD FLOOR BOYS & GIRLS RESTROOMS IN NEW WING OF BUILDING 1) URINALS IN BOYS 3RD FLOOR RESTROOM NEEDS UNSTOPPING 2) TOILETS IN GIRLS 3RD FLOOR RESTROOM NEEDS SNAKING OUT | February 8, 2002 | February 25, 2002 | 17 days |
| Cook J.F. Elementary School | FM-200125800 /01 2/26/02 (COOK,J.F.) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR BOYS BATHROOM THE URINALS IN THE 1ST FLOOR BOYS BATHROOM NEED REPAIR--SOME OF THEM RUN NON-STOP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/21/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) | December 19, 2001 | February 26, 2002 | 69 days |
| Gibbs Elementary School | FM-200117418 01 2/26/02 GIBBS SECOND FLOOR - GIRLS RESTROOM. 1) REPAIR TOILET WATER IS LEAKING FROM TOILET. | August 14, 2001 | February 26, 2002 | 196 days |
| Bell High School | FM-200127275 02 2/27/02 (BELL) ASBESTOS ASSESSMENT REQUIRED 1ST, 2ND & 3RD BATHROOMS & TEACHERS RESTROOM. 1) FLUSH VALVES NEEDED FOR THE 1ST FLOOR DAYCARE RESTROOM, 2ND & 3RD FLOOR GIRLS RESTROOM. THERE IS LITTLE TO NO PRESSURE & LITTLE OR NO WATER IN BOWLS TO FLUSH TOILETS. 2) 2ND FLOOR MEN TEACHERS BATHROOM HAS A PERSISTENT LEAK FROM A PIPE WITHIN THE WALL (WAS WORKED ON PREVIOUSLY BUT STILL PERSISTS). ***URGENT REQUEST*** ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/25/02 RONALD EDWARDS - SAFETY (202)576-6693 (RG)-01/28/02 | January 11, 2002 | February 27, 2002 | 47 days |
| Brightwood Elementary School | FM-200202715 02 2/27/02 (BRIGHTWOOD) ***URGENT*** 1ST FLOOR BOYS RESTROOM CUT-OFF VALVE TO URINAL IS NOT WORKING PROPERLY. WATER TO URINAL HAS BEEN SHUT OFF, BUT WATER IS STILL LEAKING OVER THE TOP OF THE VALVE. | February 8, 2002 | February 27, 2002 | 19 days |
| Brent Elementary School | FM-200202455 02 2/27/02 (BRENT) ***URGENT*** 2ND FLOOR GIRLS RESTROOM UNSTOP TOILET IN 2ND FLOOR GIRLS RESTROOM (AUGER USED TO NO AVAIL BY STAFF)--MAY NEED SNAKING OUT | February 5, 2002 | February 27, 2002 | 22 days |
| Bowen Elementary School | FM-200201992 02 2/27/02 (BOWEN) ***EMERGENCY*** 1ST FLOOR GYMNASIUM RESTROOMS (TEACHERS & POLICE BOYS CLUB) HOT WATER COMING INTO THE SINKS IN THE TEACHERS & POLICE BOYS CLUB RESTROOMS IS FAR TOO HOT (HOT ENOUGH TO CAUSE POSSIBLE SCALDING). | January 28, 2002 | February 27, 2002 | 30 days |
| West Elementary School | FM-200202487 02 2/27/02 (WEST) ***URGENT*** 1ST FLOOR BOYS RESTROOM/LEFT SIDE OF LEARNING CENTER A URINAL IS LEAKING DOWN THE WALL ONTO THE FLOOR. | February 5, 2002 | February 27, 2002 | 22 days |
| Stoddert ES | FM-200202240 02 2/27/02 (STODDERT) !!EMERGENCY!! 1ST FLOOR/TEACHERS BATHROOM: WATER COMING FROM THE BASE OF TOILET; APPEARS TO NEED WAX RING. FLOORS ARE FLOODED. | January 31, 2002 | February 27, 2002 | 27 days |
| Hine JHS | FM-200203454 02 2/28/02 Hine 2nd Floor B-Wing Boys Restroom Replace fixtures to two hand sinks in the 2nd floor boys restroom. | February 26, 2002 | February 28, 2002 | 2 days |
| Stevens Elementary School | FM-200203183 02 2/28/02 (Stevens) HEALTH CODE VIOLATION: Increase hot water pressure in restrooms. Replace cold water faucet where needed, expecially in girls restrooms/Two (2) week notice. Also, the school has been given (24) hours to provide hot water in childrens restroom. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/20/02. DCPS - SAFETY - RICHARD GIBSON (202)576-5584 (RG 02/20/02) | February 20, 2002 | February 28, 2002 | 8 days |
| Brent Elementary School | FM-200122609 /01 3/4/02 (BRENT) 1ST FLOOR/ GIRLS LAVATORY REPLACE BROKEN AIR VENT BETWEEN BATHROOM AND MAIN STORAGE ROOM. | October 30, 2001 | March 4, 2002 | 125 days |
| Coolidge High School | FM-200203718 02 3/5/02 (Coolidge) ***Emergency*** 1. Asbestos assessment required. Gym/Boys restroom. Newly installed urinal leaking profusely, down to the floor below. (plumbers needed) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/28/02. HORNE ENGINEERING - SHERYLL JAMES (RG 03/0102) | February 28, 2002 | March 5, 2002 | 5 days |
| Shaw JHS | FM-200110604 01 3/6/02 (SHAW) 1. ASBESTOS ASSESSMENT REQUIRED. 2ND FLOOR ORANGE HOUSE/BOYS BATHROOM: WHILE FLUSHING ONE TOILET, OTHERS OVER-FLOW. WATER IS LEAKING DOWN IN-TO THE MULTIPURPOSE ROOM. BILL CAMPION | May 18, 2001 | March 6, 2002 | 292 days |
| Macfarland Middle School | FM-200203263 02 3/6/02 (Macfarland) ***Emergency*** Ground,1st, 2nd & 3rd floor: Toilets are backing up in all restrooms. | February 21, 2002 | March 6, 2002 | 13 days |
| Amidon Elementary School | FM-200203510 02 3/6/02 (Amidon) ***Urgent*** 1st Floor Multi-purpose Room Repair leak coming from two sinks in the boys restroom in the multi-purpose room. The water is constantly leaking onto the floor in the cafeteria. | February 27, 2002 | March 6, 2002 | 7 days |
| Cook J.F. Elementary School | FM-200202466 02 3/6/02 (COOK,J.F.) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR BOYS & GIRLS RESTROOMS BOYS RESTROOM: FIRST URINAL AS YOU COME IN IS STOPPED UP. GIRLS RESTROOM: THE TOILET AT THE BACK OF THE RESTROOM IS LEAKING & THE FIRST TOILET IS STOPPED UP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/05/02. RICHARD GIBSON - SAFETY (202)576-5584 | February 5, 2002 | March 6, 2002 | 29 days |
| Moten Elementary School | FM-200120334 01 3/6/02 (MOTEN) ASBESTOS ASSESSMENT REQ. 4TH FLOOR/ BOYS RESTROOM (OLD WING) REPLACE NIPPLE TO SINK. WATER IS LEAKING BEHIND WALL. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: EDWARD RODCIGUEZ | September 21, 2001 | March 6, 2002 | 166 days |
| Coolidge High School | FM-200124886 /01 3/11/02 (COOLIDGE) ASBESTOS ASSESSMENT REQUIRED GROUND/NEW GYM--TEAM LOCK ROOM #21 (OFFICE OF COACH) THE RESTROOM IN THE OFFICE OF THE COACH HAS A DRAIN TAHT HAS A BAD SMELL & NEEDS TO BE SNAKED OUT. CODE A- CLEAR FOR REPAIR BY DCPS SAFETY( CHARLES BUCHANAN) ON3/02/02 (CEB) | December 10, 2001 | March 11, 2002 | 91 days |
| Beers Elementary School | FM-200203781 02 3/11/02 (Beers) ****Urgent**** 1st & 2nd Floors Bldg 2 Boys Restroom Several urinals are shut down because they are clogged up and need snaking. | March 4, 2002 | March 11, 2002 | 7 days |
| Payne Elementary School | FM-200203996 02 3/11/02 (Payne) ****Urgent**** 2nd & 3rd Floors/Boys Restrooms 2nd Floor: Toilets are clogged and flush valves not working properly. 3rd Floor: There is a major back up and flush valves are not working properly. | March 7, 2002 | March 11, 2002 | 4 days |
| Webb Elementary School | FM-200109652 01 3/11/02 WEBB FIRST (1ST) FLOOR - CLASSROOM #152 UNSTOP TOILET IN BOYS AND GIRLS RESTROOM. HEALTH HAZARD. TRIED TO UNSTOP MANUALLY. DUPLICATED COPY FM-200109651 | May 7, 2001 | March 11, 2002 | 308 days |
| Ross Elementary School | FM-200204007 02 3/11/02 (Ross) ****Urgent**** Basement Boys Restroom by Cafeteria The 2nd sink in the boys restroom is leaking & flooding from the J-trap (has been shut down). | March 7, 2002 | March 11, 2002 | 4 days |
| Lafayette Elementary School | FM-200201549 02 3/11/02 (LAFAYETTE) **URGENT** ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR TEAM 1 TOILET IN GIRLS BATHROOM RUNS OVER & WATER GURGLES WHEN GOING DOWN (TOILET HAS BEEN PLUNGED SEVERAL TIMES). ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/25/02 RONALD EDWARDS - SAFETY (202)576-6693 (RG)-01/28/02 | January 23, 2002 | March 11, 2002 | 47 days |
| Hendley Elementary School | FM-200204071 02 3/11/02 (Hendley) ****Urgent**** 1st, 2nd & 3rd Floor Teachers Restrooms 1) 1st floor: there is leaking from toilets in the annex 2) 2nd floor: there is leaking from the bottom of the toilet bowl onto the floor and the water will not cut off; and 3) 3rd floor: there is leaking from the 2wall urinals. | March 7, 2002 | March 11, 2002 | 4 days |
| Shaw JHS | FM-200125655 /01 3/11/02 (SHAW) ASBESTOS ASSESSMENT REQUIRED BASEMENT/MENS BATHROOM & KITCHEN TOILETS DO NOT FLUSH (TRIED TO FIX PROBLEM BUT DO NOT HAVE RIGHT TOOLS) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/27/02. DCPS- SAFETY RONALD EDWARDS (202)576-6693 (RG 03/0102) | December 18, 2001 | March 11, 2002 | 83 days |
| Hendley Elementary School | FM-200204069 02 3/11/02 (Hendley) ****Urgent**** 1st & 2nd Floor Teachers Restrooms 1st & 2nd floor teachers restrooms have water leaking from the bottom of the commode [may be coming from the drain line]. | March 7, 2002 | March 11, 2002 | 4 days |
| Stuart-Hobson Middle School | FM-200125684 /01 3/12/02 (STUART-HOBSON) ASBESTOS ASSESSMENT REQUIRED THIRD FLOOR GIRLS BATHROOM FLUSH VALVE ON COMMODE IS LEAKING IN GIRLS BATHROOM (TRIED TO CUT IT OFF, BUT IT IS AN OLD ONE). NEED IMMEDIATE ATTENTION DUE TO IT LEAKING DOWN INTO THE 2ND FLOOR GIRLS BATHROOM CEILING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/27/02. DCPS- SAFETY RONALD EDWARDS (202)576-6693 (RG 03/0102) | December 18, 2001 | March 12, 2002 | 84 days |
| Wilson J. O. ES | FM-200107956 01 3/12/02 WILSON, J.O. THIRD (3RD) FLOOR - LC 301/SOUTH 1) ASBESTOS ASSESSMENT REQUIRED. 2) REPAIR OR REPLACE DRAIN PIPE IN BOYS RESTROOM. NOTE: LEAKY PIPE IS CAUSING CEILING DAMAGE TO FLOORS BELOW THIS AREA. CODE A - ABATED 06/21/01 CONFIRMED BY SHEILA R HOWARD (RG) | April 9, 2001 | March 12, 2002 | 337 days |
| Tubman Elementary School | FM-200202964 02 3/12/02 (TUBMAN) 1ST FLOOR/SPACE 36-BOYS RESTROOM 2 COMMODES IN THE BOYS 1ST-FLOOR RESTROOM NEED SPUD REPLACEMENTS. | February 13, 2002 | March 12, 2002 | 27 days |
| Seaton Elementary School | FM-200127199 02 3/12/02 (SEATON) ASBESTOS ASSESSMENT REQUIRED SECOND FLOOR BOYS BATHROOM REPLACE WAX RING ON URINAL IN BOYS BATHROOM (SECOND URINAL FROM THE DOOR). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/2/02. DCPS- SAFETY RONALD EDWARDS (202)576-6693 (RG 03/0102) | January 10, 2002 | March 12, 2002 | 61 days |
| Beers Elementary School | FM-200126840 02 3/12/02 (BEERS) ASBESTOS ASSESSMENT REQUIRED 2ND FLOOR BUILDING 1/BOYS RESTROOM TOILET WATER IS LEAKING FROM THE BOTTOM OF THE TOILET WHICH HAS MISSING SCREWS & TOILET IS LOOSE AND UNSTABLE. CODE A- CLEAR FOR REPAIR BY CHARLES E. BUCHANAN ON 2/28/02 | January 4, 2002 | March 12, 2002 | 67 days |
| Thomas Elementary School | FM-200100510 01 3/13/02 THOMAS SCHOOL SECOND (2ND) FLOOR BOY RESTROOM FLOOR, REPAIR PAVEMENT FLOOR. | January 9, 2001 | March 13, 2002 | 428 days |
| Rudolph Elementary School | FM-200203685 02 3/13/02 (Rudolph) Basement Boys Bathroom - Middle Stairwell 1) Outside window broken,needs to be replaced. | February 28, 2002 | March 13, 2002 | 13 days |
| Jessie LaSalle Elementary | FM-200203786 02 3/13/02 (Lasalle) ***Urgent*** 2nd Floor Boys & Girls Restrooms 1 window pane is completely out & needs replacement in both the 2nd floor boys & girls restrooms. | March 4, 2002 | March 13, 2002 | 9 days |
| Beers Elementary School | FM-200203780 02 3/14/02 (Beers) ****Urgent**** 1st floor Bldg 2 Boys Restroom & Auditorium 1) 1st floor boys restroom has a light switch with exposed wires and the outlet is sparking. 2) 1st floor auditorium stage has 2 outlets with exposed wires where the outlet is sparking. 3) 4 light fixtures are broken [wire-base bulbs are hanging] and Mr. Lancaster received a mild shock when checking them. The replacement bulbs are available on-site. | March 4, 2002 | March 14, 2002 | 10 days |
| Garnet-Patterson MS | FM-200202599 02 3/14/02 (GARNET-PATTERSON) ASBESTOS ASSESSMENT REQUIRED 3RD FLOOR TEACHERS LOUNGE RESTROOM PROVIDE 6 COPY OF THE KEYS TO THE TEACHERS LOUNGE RESTROOM. CODE A- CLEAR FOR REPAIR BY CHARLES E. BUCHANAN ON 2/28/02 | February 7, 2002 | March 14, 2002 | 35 days |
| Savoy Elementary School | FM-200203545 02 3/14/02 (Savoy) ***Emergency*** 1st Floor Near Custodians Office (boys & girls restroom) Relace old single hot & cold faucets (4 hot & 4 cold) in each boys & girls restroom. The cold water faucets have been turned off, but the hot water sides could not be turned off--only reduced to a trickle. Water is going all over the floors. | February 27, 2002 | March 14, 2002 | 15 days |
| Tubman Elementary School | FM-200115123 01 3/14/02 TUBMAN SECOND (2ND) FLOOR - GIRLS RESTROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. EXPLORATORY DEMOLITION IN AMP #214. 3. FLOOR TILES REMOVAL IN AMP #190. 4. CEILING HAS A DEEP CRACK IN IT AND ITS PROPERTY DAMAGE. SUMMER SCHOOL IS GOING ON TOO. STUDENT IN THE BUILDING. SAFETY AND HEALTH HAZARD. ISOLATE EMERGENCY !!! DCB (IT GROUP)/703-461-6848 Code A clear for repair asbestos abatement date March 18, 2002 (DCPS Safety-Sheila R. Howard confirmed) | July 11, 2001 | March 14, 2002 | 246 days |
| Thomson Elementary School | FM-200204339 02 3/14/02 (Thomson) ****Urgent**** 3rd Floor Boys Restroom The 3rd floor boys restroom has stopped up urinals [have plunged & snaked without success]. | March 13, 2002 | March 14, 2002 | 1 day |
| Dunbar High School | FM-200204113 02 3/14/02 (Dunbar) 1st, 2nd , and 3rd floors/ Various Rooms Please "key alike" the following door locks that have been recently installed as part of ADA upgrade improvements: -womens restrooms (4) in one in front lobby, two in lower lobby, three in the cafeteria, and four in the library -the stage door,- the gymnasium door *all disconnect locks total of (14) cylinders including band room, multi-classroom. | March 8, 2002 | March 14, 2002 | 6 days |
| Malcolm X ES | FM-200203915 02 3/14/02 (Malcolm X) 1. Asbestos assessment required. sink in the boys bathroom on the fourth floor needs to be replaced. it is broken off of the wall. Code-A clear for repiar by horne engineer ( Z Mahmood ) 3/06/02 CEB | February 27, 2002 | March 14, 2002 | 15 days |
| Anacostia Senior High School | FM-200204293 02 3/14/02 (Anacostia) ****Urgent**** 1st Floor Ladies Restroom Toilets backing up and overflow is going down into the child-care center below in the basement. | March 12, 2002 | March 14, 2002 | 2 days |
| Hendley Elementary School | FM-200204460 02 3/15/02 (Hendley) 3rd Floor Room 302 & 2nd Floor Boys Restroom Replace or repair old locks on the door to the 2nd floor boys restroom and 3rd floor classroom 302. | March 14, 2002 | March 15, 2002 | 1 day |
| Oyster Elementary School | FM-200204512 02 3/19/02 (Oyster) ""Emergency"" 2nd Floor/Hall bathroom: Childrens bathroom stopped up, and running over. This is the only bathroom on this floor. | March 15, 2002 | March 19, 2002 | 4 days |
| Cooke H.D. Elementary School | FM-200203317 02 3/19/02 (Cooke, H.D.) Asbestos assessment req. Basement/ Boys Restroom Pipe leaking from ceiling in boys restroom. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/25/02 HORNE ENGINEER: BIPIN NANAVATY | February 22, 2002 | March 19, 2002 | 25 days |
| Sousa Middle School | FM-200203904 02 3/19/02 (Sousa) Asbestos assessment req. 1st floor/ Mens restroom Reanchor partition back to wall and floor center partition fell. Partition on site. Code-A clear for repiar by Horne Engineer ( Sharon Voss ) 3/07/02 CEB | March 5, 2002 | March 19, 2002 | 14 days |
| Cook J.F. Elementary School | FM-200202384 02 3/19/02 (COOK,J.F.) ***URGENT*** 1ST FLOOR BOYS & GIRLS RESTROOMS GIRLS RESTROOM: LAST & 2ND STALLS HAVE COMMODES WHICH ARE LEAKING BOYS RESTROOM: 1ST URINAL IS LEAKING ASBESTOS CODE A-CLEAR FOR REPAIR ON 2/05/02 BY HORNE ENGINEER: SHARON VOSS | February 4, 2002 | March 19, 2002 | 43 days |
| Savoy Elementary School | FM-200203481 02 3/19/02 (Savoy) Health code violation: Kitchen: Provide hot and cold water to hand sink inside bathroom for the employees. | February 26, 2002 | March 19, 2002 | 21 days |
| Cleveland Elementary School | FM-200203908 02 3/19/02 (Cleveland) ****Urgent**** 1st Floor by Boys Restroom Water fountain needs repair work done because it is very unstable . The water continues to leak from the trap onto the floor and the trap nut, which is split in half, should be replaced. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/06/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG 03/06/02) | March 5, 2002 | March 19, 2002 | 14 days |
| Clark Elementary School | FM-200203961 02 3/19/02 (Clark) Asbestos Assessment Required 1st, 2nd & 3rd Floors Girls Restrooms Unstop drain lines between floors of girls restroom which do not properly drain--the restrooms are located one above the other from the 3rd floor through 1st floor. Code-A clear for repiar by Horne Engineer ( Roger Kager ) 3/07/02 CEB | March 6, 2002 | March 19, 2002 | 13 days |
| Savoy Elementary School | FM-200204593 02 3/20/02 (Savoy) ****Urgent**** 1st Floor [Southend] There is an electrical outlet on the 1st floor [southend, between the boys & girls restrooms], that is sparking and not working properly. POC: Mr. Miller | March 18, 2002 | March 20, 2002 | 2 days |
| Beers Elementary School | FM-200202979 02 3/20/02 (BEERS) BUILDINGS 1, 2 & 3 RESTROOMS NEED DOOR LOCKS ON ALL RESTROOM DOORS THROUGHOUT THE BUILDINGS. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/19/02 HORNE ENGINEER: TROY WILCOME | February 13, 2002 | March 20, 2002 | 35 days |
| Payne Elementary School | FM-200204348 02 3/21/02 (Payne) 1st Floor Girls Restroom Replace broken scontrol stop-valves on one (1) commode in the 1st floor girls restroom. | March 13, 2002 | March 21, 2002 | 8 days |
| Payne Elementary School | FM-200204347 02 3/21/02 (Payne) 1st Floor Boys Restroom Replace broken stop-control valves on three (3) commodes in the 1st floor boys restroom. | March 13, 2002 | March 21, 2002 | 8 days |
| Payne Elementary School | FM-200204363 02 3/21/02 (Payne) 1st Floor Lobby Area Boys Restroom The urinals in the boys restroom need wax rings where water is leaking from them. | March 13, 2002 | March 21, 2002 | 8 days |
| Moten Elementary School | FM-200201253 02 3/22/02 (MOTEN) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ GIRLS BATHROOM CEILING TILE NEED TO BE REPLACED ON THE NEW SIDE. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/23/02 HORNE ENGINEERING - ROGER KAGER (RG)-01/24/02 | January 16, 2002 | March 22, 2002 | 65 days |
| Turner Elementary School | FM-200203523 02 3/25/02 (Turner) Restrooms (12 Boys & Girls)/All Floors Need cylinders locks rekeyed on all floors to girls & boys restrooms. | February 27, 2002 | March 25, 2002 | 26 days |
| Wilkinson ES | FM-200204892 02 3/27/02 (Wilkinson) 1. Asbestos assessment required. 1st Floor/Boys bathroom-58: Need to repair or replace locks on boys bathroom door, front and back. Code A-clear for repair by Horne Engineer ( Sam Ebrahim ) on 3/28/02 (CEB) | March 25, 2002 | March 27, 2002 | 2 days |
| Meyer Elementary School | FM-200203849 02 4/1/02 (Meyer) 1st Floor Landing Near 1st Floor Boys Restroom Replace broken door closure in the 1st floor landing [center stairwell] near the boys restroom--possible fire code violation. [Same as 200203858--will close.] | March 5, 2002 | April 1, 2002 | 27 days |
| Gage-Eckington ES | FM-200204868 02 4/2/02 Gage-Eckington 2nd Floor Intermediate & Primary Remove broken keys from locks and provide duplicate keys. Broken keys are located on the 2nd floor in two boys restrooms. Code A-clear for repair by Horne Engineer ( Stephen Caldwell ) on 3/26/02 (CEB) | March 22, 2002 | April 2, 2002 | 11 days |
| Bancroft Elementary School | FM-200203064 02 4/4/02 (Bancroft) ***Very Urgent*** Near Music Room/Boys Bathroom: Five (5) urinals are over-flowing in bathroom, flooding the floors, due to stopped up drain. | February 15, 2002 | April 4, 2002 | 48 days |
| Wilson J. O. ES | FM-200202104 02 4/4/02 (WILSON,J.O.) ***EMERGENCY*** ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR BOYS & GIRLS RESTROOMS ASSESS CEILING & WALLS BENEATH ROOF DRAINS IN THE BOYS AND GIRLS RESTROOMS.ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/30/02 BY HORNE ENGINEER: SAM EBRAHIM | January 30, 2002 | April 4, 2002 | 64 days |
| Beers Elementary School | FM-200202982 02 4/4/02 (BEERS) 1ST & 2ND FLOORS/BUILDING 2 BOYS RESTROOMS URINALS ARE CLOGGED & FLUSH BOWLS ARE NOT WORKING. WATER IS CONTSTANTLY FLOODING & ONE BATHROOM HAS BEEN PUT OF-OF-SERVICE DUE TO THIS SITUATION. | February 13, 2002 | April 4, 2002 | 50 days |
| Horace Mann Elementary School | FM-200100965 01 4/5/02 (Mann) FIRST (1ST) FLOOR BOYS RESTROOM, REPAIR PEELING PAINT AND CRUMBLING PLASTER ON CEILING ABOVE URINAL AT BASE OF J TRAP FROM SECOND (2ND) FLOOR URINAL. (AREA 3 1/2 FEET X 3 1/2 FEET) Code A-clear for repair by Horne Engineer ( Stephen Caldwell ) on 3/19/02 ( CEB) | January 11, 2001 | April 5, 2002 | 449 days |
| Reed LC | FM-200203588 02 4/8/02 (Reed) Asbestos Assessment Required 2nd Floor Male Restroom Near Steep #2 Reattach the p artition to the wall in the 2nd floor male restroom. CODE A- CLEAR FOR REPAIR BY HORNE ENGINEER( SAM EBRAHIM ) ON3/01/02 (CEB) | February 27, 2002 | April 8, 2002 | 40 days |
| Davis Elementary School | FM-200203181 02 4/8/02 (Davis) Asbestos Assessment Required Second Floor Rooms 202, 204 & 211; Boys & Girls Restrooms The doors (2nd floor) to rooms 202, 204, 211 and the boys & girls restrooms need realignment. POC: Ms. Chestnut ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/21/02. HORNE ENGINEERING - ROGER KAGER (RG 02/22/02) | February 20, 2002 | April 8, 2002 | 47 days |
| Tubman Elementary School | FM-200202870 02 4/8/02 (TUBMAN) 1ST FLOOR/ SPACE 36-BOYS RESTROOM 2 (TWO) COMMODES IN BOYS BATHROOM NEEDS THE SPUDS REPLACED. | February 12, 2002 | April 8, 2002 | 55 days |
| Ludlow-Taylor ES | FM-200204940 02 4/8/02 (Ludlow-Taylor) ****Urgent**** 1st Floor Girls Restroom 1. Asbestos assessment required. 2. Water is rapidly coming up from the floor from a leak where the convector pipe is located, in the 1st floor girls restroom. DCB (IT Group)/703-461-6848 Code A - Asbestos abated on 04/05/02 PER Sheila R Howard confirmation.( 04/08/02 RG) | March 26, 2002 | April 8, 2002 | 13 days |
| Smothers ES | FM-200201246 02 4/8/02 (SMOTHERS) !URGENT! 1ST FLOOR/GIRLS BATHROOM: P-TRAP ASSEMBLY LEAKING. | January 16, 2002 | April 8, 2002 | 82 days |
| Birney Elementary School | FM-200203339 02 4/9/02 (Birney) Asbestos assessment req. Basement/ Boys bathroom, Custodians office Basement boys bathroom new side need door--door will not line up with lock. Custodians office door needs to be repaired or replaced. Door will not close correctly,-not aligning in frame properly. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/26/02 HORNE ENGINEER: | February 22, 2002 | April 9, 2002 | 46 days |
| Cook J.F. Elementary School | FM-200126914 02 4/9/02 (COOK,J.F.) 1ST FLOOR GIRLS RESTROOM THE LAST TOILET IN THE REAR OF THE GIRLS 1ST FLOOR RESTROOM IS LEAKING & NEEDS REPAIR. | January 7, 2002 | April 9, 2002 | 92 days |
| Malcolm X ES | FM-200203913 02 4/9/02 (Malcolm X) 1. Asbestos assessment required. urinal on the fourth floor needs an emergency repair. it is leaking. boys bathroom. Code-A clear for repiar by horne engineer ( Z Mahmood ) 3/06/02 CEB | February 27, 2002 | April 9, 2002 | 41 days |
| Macfarland Middle School | FM-200203304 02 4/9/02 (Macfarland) 2nd floor/ Boys Restroom 7th grade wing Unstop commode in last stall boys restroom. Also snake out urinals main drain, water over flows and drains out slow. | February 22, 2002 | April 9, 2002 | 46 days |
| Deal Junior High School | FM-200119711 01 4/9/02 (DEAL) ASBESTOS ASSESSMENT REQ. 1,2,3, FLOORS/ ROOMS 112, 207, 305, 326, AND BOYS RESTROOM REPAIR LOCKS ON CLASSROOM DOORS UNABLE TO SECURE PROPERLY. ASBESTOS CODE A-CLEAR FOR REPAIRS BY 10/18/01 HORNE ENGINEER : SHARON VOSS | September 13, 2001 | April 9, 2002 | 208 days |
| Dunbar High School | FM-200204730 02 4/9/02 (Dunbar) **Very Urgent** 4th Floor/ME: Unstop toilets in the teachers lounge, and girls bathroom. Staff did not have any success in plunging. Please provide snake k-50 to run through the line. | March 19, 2002 | April 9, 2002 | 21 days |
| Powell Elementary School | FM-200202138 02 4/9/02 (POWELL) Toilet in boys restroom on second floor near playground. Can not unstop urinal, which runs over when flushed. | January 28, 2002 | April 9, 2002 | 71 days |
| Davis Elementary School | FM-200122036 /01 4/9/02 (DAVIS) !!EMERGENCY!! 1ST FLOOR/ACROSS FROM ROOM #103: UNSTOP THIRD URINAL IN BOYS BATHROOM, THERE IS A BACK-UP IN THE LINE AND THE URINAL IS OVER-FLOWING. POC: PALMER-4:10. | October 19, 2001 | April 9, 2002 | 172 days |
| Park View ES | FM-200204839 02 4/9/02 (Parkview) ******Emergency****** Ground Floor/Boys bathroom: Unstop 6-7 commodes located in boys bathroom; unable to use because of flooding. | March 22, 2002 | April 9, 2002 | 18 days |
| Merritt Middle School | FM-200204334 02 4/9/02 MERRITT !!!! emergency !!!! east end of building MONTESSORI AREA - third (3rd) floor staff restroom - first floor girls restroom - first floor hot water running - cannot cut the off valves | March 13, 2002 | April 9, 2002 | 27 days |
| Davis Elementary School | FM-200105956 01 4/9/02 DAVIS (WIN) OLD AND NEW WINGS .BOYS AND GIRLS RESTROOMS 1ST, 2ND AND BASEMENT .CORRIDORS - OLD & NEW WINGS .ALL INTERIOR DOORS AND EXTERIOR .CAFETERIA HRGM CONTRACTOR ASBESTOS CODE A-CLEAR FOR REPAIR ASSESED BY HORNE ENG 7/19/01 | March 15, 2001 | April 9, 2002 | 390 days |
| Benning Elementary School | FM-200125873 /01 4/10/02 (BENNING) ASBESTOS ASSESSMENT REQUIRED MAIN FLOOR HEALTH SUITE/WOMENS RESTROOM MAIN CUTTOFF VALVE NOT WORKING (ON-OFF KNOBS NOT WORKING & THREADS ARE GONE). THE SINK IN THE HEALTH SUITE IS LEAKING @ THE ELBOW (HAVE A BUCKET UNDER SINK TO CATCH WATER). | December 20, 2001 | April 10, 2002 | 111 days |
| Spingarn High School | FM-200127171 /01 4/10/02 SPINGARN 1ST FL. GIRLS BATHROOM SINK CLOG IN GIRLS BATHROOM BACKING UP IN ALL SINKS. NEED TO SNAKE LINE, ACROSS FROM ROOM 115. | December 18, 2001 | April 10, 2002 | 113 days |
| Amidon Elementary School | FM-200202015 02 4/10/02 (AMIDON) ***URGENT*** 2ND FLOOR GIRLS BATHROOM REPAIR/REPLACE TWO TOILETS IN THE 2ND FLOOR GIRLS BATHROOM (SAFETY HAZARD)--ONE STUDENT HAS ALREADY CUT HER HAND ON THE TOILET. | January 29, 2002 | April 10, 2002 | 71 days |
| Plummer Elementary School | FM-200124399 01 4/11/02 (PLUMMER) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR AUDITORIUM PAINT OR REPLACE LAVATORY PARTITIONS IN BOYS & GIRLS ROOMS ASBESTOS CODE A-CLEAR FOR REPAIR 12/05/01 BY HORNE ENGINEER: EDWARD RODRIGUEZ | December 3, 2001 | April 11, 2002 | 129 days |
| Garnet-Patterson MS | FM-200201818 02 4/11/02 (GARNET-PATTERSON) 2ND FLOOR/ BOYS BATHROOM REPAIR SPUD SEAL ON THE WATER CLOSET. BOTH SINKS NEED TO BE REATTACHED. | January 25, 2002 | April 11, 2002 | 76 days |
| Ferebee-Hope Elementary School | FM-200202696 02 4/11/02 (FEREBEE-HOPE) ***EMERGENCY*** D-BUILDING/1ST FLOOR: REPAIR LEAKING ON HOT WATER SUPPLY LINE IN ROOM #36, MENS RESTROOM; LEAK FROM SINK IS FLOODING THE FLOOR. CUT-OFF VALVES ARE NOT HOLDING. | February 8, 2002 | April 11, 2002 | 62 days |
| Coolidge High School | FM-200202890 02 4/11/02 (COOLIDGE) 2ND FLOOR/ NEW GYM-BOYS BATHROOM SURVEY AND REPAIR LEAKING URINAL, WHICH IS CREATING WATER DAMAGE IN THE CEILING BELOW. | February 12, 2002 | April 11, 2002 | 58 days |
| Eastern High School | FM-200122805 01 4/11/02 (EASTERN) ASBESTOS ASSESSMENT REQ. FOOTBALL FIELD/ BOYS AND GIRLS RESTROOM REPAIR LEAKING ROOF OVER FIELD RESTROOMS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/21/01. HORNE ENGINEERING - BIPIN NANAVATY (RG) | November 1, 2001 | April 11, 2002 | 161 days |
| Moten Elementary School | FM-200116774 01 4/12/02 MOTEN FIRST FLOOR- BATHROOM (100) 1) WATER IS OVERFLOWING FROM TOILET AND IS POURING INTO THE OFFICE. NO PENETRATIONS !! | August 6, 2001 | April 12, 2002 | 249 days |
| Seaton Elementary School | FM-200205515 02 4/12/02 SEATON 1ST, 2ND, AND 3RD FLOORS Need Brick wall put up for plumbers to install lavatory sinks. Two Location in each Bathrooms. Note: See Work Order FM-200115288 for Clearance. | April 5, 2002 | April 12, 2002 | 7 days |
| Cleveland Elementary School | FM-200105275 /8/01 4/15/02 CLEVELAND 3RD FL. BOYS RESTROOM REPAIR CONCRETE FL. AROUND PIPE TO HEATING UNIT ON 3RD FL. IN BOYS RESTROOM | March 8, 2001 | April 15, 2002 | 403 days |
| Amidon Elementary School | FM-200205326 02 4/15/02 Amidon First Floor - Girls Bathroom First Floor - Boys Bathroom Second Floor - Girls Bathroom 1) Paint Partitions ** Hands On D.C. Code A-clear for repair by Honre Engineer ( Stephen Caldwell) on 4/11/02 CEB | April 3, 2002 | April 15, 2002 | 12 days |
| Cleveland Elementary School | FM-200108465 16/01 4/15/02 CLEVELAND THIRD (3RD) FLOOR - BOYS RESTROOM FILL IN HOLE AROUND HEAT RISER (ON FLOOR). HOLE HAS NOT BEEN FILL IN WITH CEMENT. THE KIDS ARE DROPPING TRASH INSIDE THAT HOLE. HEALTH AND SAFETY HAZARD. | April 16, 2001 | April 15, 2002 | 364 days |
| Malcolm X ES | FM-200127184 02 4/16/02 (MALCOLM X) The sink in the health suite bathroom needs the drain pipe be replaced. It is not usable at this time and it is a health concern. | January 4, 2002 | April 16, 2002 | 102 days |
| Young Elementary School | FM-200204595 02 4/16/02 (Young) Asbestos Assessment Required Exploratory Demolition in AMP #166 and #167 2nd Floor Boys Restroom There is leaking coming from the 2nd floor boys restroom, causing the ceiling tiles in the music room below to fall. DCB (IT GROUP)/703-461-6848 Code A - Asbestos abated on 03/25/02 PER Leroy Minton Jr. confirmation 04/04/02.(RG) | March 18, 2002 | April 16, 2002 | 29 days |
| Hearst Elementary School | FM-200205703 02 4/16/02 Hearst ***Urgent**** 1st & 2nd Floor Boys & Girls Restrooms 1) The 1st floor boys restroom has two toilets that are continuously flushing. 2) The 2nd floor girls restroom has one toilet that is overflowing onto the floor. | April 11, 2002 | April 16, 2002 | 5 days |
| King M L ES | FM-200203355 02 4/16/02 (King) 2nd floor/ Boys Bathroom We need to have #4 toilet snaked out. It has stopped up. | February 22, 2002 | April 16, 2002 | 53 days |
| Simon Elementary School | FM-200116810 01 4/17/02 SIMON FIRST FLOOR - GIRLS RESTROOM 1) REPLACE FLUSH VALVES ON TWO COMMODES. CONTROL STOP VALVES DO NOT WORK. | August 7, 2001 | April 17, 2002 | 253 days |
| Backus Middle School | FM-200205670 02 4/17/02 Backus ****Emergency**** 3rd Floor Coaching Office Restroom Old-fashioned [not made any longer] valve system on toilet is not holding and each repair fails to hold. Water is flooding across the floor through to the ceiling below, where the plaster appears ready to peel & fall again because of water damage [was recently repaired & painted] from same source. | April 10, 2002 | April 17, 2002 | 7 days |
| Seaton Elementary School | FM-200205769 02 4/17/02 Seaton Third (3rd) Floor - Boys Restroom Furnish and Install lock for Boys Restroom. Lock broken and cannot be repaired. | April 12, 2002 | April 17, 2002 | 5 days |
| Johnson JHS | FM-200205961 02 4/18/02 (Johnson) ***Emergency*** Through-out the building: Toilets are backing up in teachers bathroom and girls and boys bathroom through-out the building flooding the floors. | April 17, 2002 | April 18, 2002 | 1 day |
| Barnard Elementary School | FM-200205748 02 4/18/02 Barnard ****Emergency**** 1st Floor Kitchen Sewage is backing up through the 1st floor kitchen drain & the kitchen restroom drain [although there is no flushing going on/area is being isolated]. | April 12, 2002 | April 18, 2002 | 6 days |
| Macfarland Middle School | FM-200204537 02 4/22/02 (MacFarland) Repair waste line in boys bathroom on the first floor--the pipe leaks when the urinals are flushed in the restroom above it. | March 15, 2002 | April 22, 2002 | 38 days |
| Cooke H.D. Elementary School | FM-200205918 02 4/23/02 Cooke, H.D. !!! Emergency !!! Ground - Boys & Girls Restroom Unclog Three (3) toilets. | April 16, 2002 | April 23, 2002 | 7 days |
| Ross Elementary School | FM-200205041 02 4/23/02 (Ross) **Emergency** Basement near girls restroom: Repair pipe leaking hot water down into the book room. This leak is on the opposite side of the room. (This service order request is to be re-assigned to the plumbers. (Per Mr. Mahoney) | March 28, 2002 | April 23, 2002 | 26 days |
| Seaton Elementary School | FM-200115288 01 4/23/02 SEATON 1ST, 2ND, AND 3RD FLOORS NEED ASBESTOS ASSESSMENT IN BOYS & GIRLS RESTROOMS. BOYS & GIRLS BY ROOM 111, ROOM 109, ROOM 208 AND CUSTODIAN ROOM. ROOMS 304 & 309 NEED WALLS ASSESSED SO PLUMBERS CAN INSTALL LAVATORIES LATER. WILL SUBMIT SEPERATE SERVICE ORDER FOR THE WORK. The plumbing shop needs to have the walls assessed in each restroom there is a total of four per floor, two in each restroom there is a total of twelve bradley basins involved. Leroy Minton DCPS Safety 04-01-02. POC: Thomas Gaddy 202-438-7390 plumbing supervisor must call for an escort DCB (IT Group) /703-461-6848 Code A - Asbestos abated on 04/04/02 PER Sheila R Howard confirmation04/04/02.(RG) Code A-clear for repair by Horne Engineer ( Roger Kager ) on 4/19/02 | July 16, 2001 | April 23, 2002 | 281 days |
| Cooke H.D. Elementary School | FM-200203529 02 4/23/02 (Cooke,H.D.) 3rd Floor Mens Restroom Unclog both toilets in the mens & principals restroom ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/06/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG 03/06/02) | February 27, 2002 | April 23, 2002 | 55 days |
| Bunker Hill Elementary School | FM-200117763 01 4/23/02 BUNKER HILL ASBESTOS ASSESSMENT REQUIRED BOYS RESTROOM SECOND FLOOR UPGRADE BOYS RESTROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/30/01. RONALD EDWARDS - SAFETY (202)576-6693 | August 17, 2001 | April 23, 2002 | 249 days |
| Reed LC | FM-200119851 01 4/23/02 (REED) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ GIRLS BATHROOM REPLACE A OFF SET FLANGE FOR A FLOOR MOUNTED TOILET IN GIRLS RESTROOM 2ND FLOOR BY STAIRWAY #7. TOILET WILL NOT STAY STATIONARY AND LEAKS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/17/01. LEROY MINTON - SAFETY (202)576-6691 | September 14, 2001 | April 23, 2002 | 221 days |
| Maury Elementary School | FM-200202900 02 4/29/02 (MAURY) LAVATORIES REPLACE FLUSH VALVES IN THE FOLLOWING AREAS: WEST BLDG. BOYS BATHROOM (10), GIRLS BATHROOM (2) EAST BLDG. GIRLS BATHROOM (3), BOYS BATHROOM (4) PRE-K (2), AND TEACHERS LOUNGE (1). 03/25/2002 11:49 SMC - | February 12, 2002 | April 29, 2002 | 76 days |
| Slowe Elementary School | FM-200206185 02 4/29/02 Slowe !!! Emergency !!! Basement/ Library Boys Restroom - Shower Area is flooding all over the floor, odor and smelling (Waste too). | April 22, 2002 | April 29, 2002 | 7 days |
| Walker-Jones EC | FM-200124695 01 4/29/02 (WALKER-JONES) 1ST FLOOR/ ROOM 106 REPAIR/REPLACE COLD WATER FAUCET IN RESTROOM. WATER LEAKS CONSTANTLY AND FLOODS RESTROOM AND CLASSROOM. | December 7, 2001 | April 29, 2002 | 143 days |
| Garnet-Patterson MS | FM-200206651 02 4/29/02 Garnet-Patterson ****Emergency**** Basement Girl's Restroom There is no water in the fixtures or toilet in the basement level girl's restroom. | April 25, 2002 | April 29, 2002 | 4 days |
| Ferebee-Hope Elementary School | FM-200206511 02 4/29/02 (Ferebee-Hope) ******Emergency****** 4th floor/boys bathroom, handicapped toilet: Toilet stopped up, valves are not holding to cut off water, also leaking from the base of toilet. | April 24, 2002 | April 29, 2002 | 5 days |
| Nalle Elementary School | FM-200120375 01 4/29/02 NALLE SECOND FLOOR - BOYS RESTROOM - NEW SIDE 1) URINALS NOT WORKING, 3RD URINAL LEAKS. | September 24, 2001 | April 29, 2002 | 217 days |
| Bowen Elementary School | FM-200206357 02 4/29/02 Bowen ****Urgent**** 1st Floor Girl's Restroom There is no water coming into the toilet bowls for flushing--they are not working properly in the 1st floor girl's restroom. | April 23, 2002 | April 29, 2002 | 6 days |
| Takoma Educational Center | FM-200205990 02 4/30/02 (Takoma) Gym/room #87 & 94: Restrooms need to be snaked out; contractor from ACOE just getting out of the area but the lavatories must be plunged daily for service of the students. Asbestos Code A - Clear for repairs on 04/18/02. DCPS Safety - Richard Gibson (RG 04/18/02) | April 17, 2002 | April 30, 2002 | 13 days |
| Amidon Elementary School | FM-200202894 02 4/30/02 (AMIDON) 1ST FLOOR/ PRE-K AND MULTIPURPOSE ROOM NEED SOMEONE TO PLEASE COME OUT TO CONNECT THE FAUCETS TO THE BASINS OF THE SINKS INSIDE THE BATHROOMS. THEY ARE SEPARATED FROM THE BASIN. | February 12, 2002 | April 30, 2002 | 77 days |
| Stevens Elementary School | FM-200205474 02 5/1/02 (Stevens) ***Very Urgent*** 1. Asbestos assessment required. Outside girls restroom: Light switch has a short, it sparks when it is turned on. Asbestos Code A - Clear For Repairs On 04/09/02. DCPS Safety - Leroy Minton Jr. (RG 04/10/02) | April 4, 2002 | May 1, 2002 | 27 days |
| Hardy Middle School | FM-200206979 02 5/3/02 Hardy-Fillmore !!! Emergency !!! Third (3rd) Floor - Boys Restroom Water is leaking on floor out of Restroom and running in Hallway. | May 1, 2002 | May 3, 2002 | 2 days |
| Harris, C.W. ES | FM-200204948 02 5/3/02 (Harris, C.W.) 1. Asbestos assessment required. 2nd floor/wing boys bathroom #5 & 6: Urinals (back-up in trap) Asbestos Code A - Clear For Repairs On 03/27/02. DCPS Safety - Leroy Minton Jr. (RG 03/27/02) | March 26, 2002 | May 3, 2002 | 38 days |
| Harris, C.W. ES | FM-200204947 02 5/3/02 (Harris, C.W.) 1. Asbestos assessment required. 1st floor/boys bathroom: Urinals backed up in trap. Asbestos Code A - Clear For Repairs On 03/27/02. DCPS Safety - Leroy Minton Jr (RG 03/27/02) It was discovered on 04-25-02 that this job would need O&M (clean-up) before the plumbing work could proceed. The O&M was conducted and cleared by Leroy Minton Jr. of DCPS Safety on 04-25-02. (LMJ) | March 26, 2002 | May 3, 2002 | 38 days |
| Thomas Elementary School | FM-200205657 02 5/3/02 Thomas Asbestos Assessment Reqd. 2nd Floor Girls Restroom/Old Wing 3rd hand-sink from the door is pulled away from the wall in the 2nd-floor girls restroom. Code A-clear for repair by Honre Engineer ( Sam Ebrahim) on 4/11/02 CEB | April 9, 2002 | May 3, 2002 | 24 days |
| Bunker Hill Elementary School | FM-200202986 02 5/3/02 (BUNKER HILL) 2ND FLOOR/ BOYS BATHROOM PLEASE REPLACE WAX RINGS ON (3) THREE WALL MOUNTED URINALS AND (2) TWO WALL MOUNTED TOILETS ON THE 2ND FLOOR BOYS BATHROOM MIDDLE WING. ALSO PLEASE REPLACE WAX RINGS ON (2) TWO WALL MOUNTED URINALS 2ND FLOOR BOYS BATHROOM, EAST WING. | February 13, 2002 | May 3, 2002 | 79 days |
| Payne Elementary School | FM-200205242 02 5/3/02 (Payne) 1. Asbestos assessment required. 2nd Floor/boys restroom; Replace control valves on three (3) commodes. Asbestos Code A - Clear For Repairs On 04/02/02. DCPS Safety - Richard Gibson (04/02/02) | April 2, 2002 | May 3, 2002 | 31 days |
| Shepherd ES | FM-200201305 02 5/3/02 (SHEPHERD) 2ND FLOOR/ OLD WING BOYS BATHROOM URINAL NEEDS TO BE SNAKED OUT. UNABLE TO UNCLOG WITH PLUNGER. | January 17, 2002 | May 3, 2002 | 106 days |
| Simon Elementary School | FM-200201328 02 5/3/02 (SIMON) ALL RESTROOMS THERE ARE AT LEAST 2 TO 4 COMMODES THAT NEED REPLACEMENT OF WAX RINGS IN ORDER TO STOP FLOODING, RUNNING WATER FROM COMMODES IN ALL THE BOYS/GIRLS RESTROOMS IN THE SCHOOL THIS IS THE 2ND AND 3RD WORK ORDER ON THIS. | January 18, 2002 | May 3, 2002 | 105 days |
| King M L ES | FM-200203315 02 5/3/02 (King) 1st floor/ Girls bathroom We need to have the #3 and #5 toilet reanchored. | February 22, 2002 | May 3, 2002 | 70 days |
| Ferebee-Hope Elementary School | FM-200206408 02 5/6/02 Ferebee-Hope 1. Second (2nd), Third (3rd and Four (4th) Boys Restrooms Repair/Replace faucet Six (6) 2. Girls Restrooms Repair/Replace faucet Six (6) | April 24, 2002 | May 6, 2002 | 12 days |
| Deal Junior High School | FM-200205426 02 5/6/02 (Deal) 1. Asbestos assessment required. 1st floor/boys bathroom: Repair urinal in boys bathroom; urinal is stopped up. The in-house staff attempted to unstop with K-50 for (1) hour. Not successful. Asbestos Code A - Clear For Repairs On 04/04/02. DCPS Safety - Richard Gibson(RG 04/04/02) | April 4, 2002 | May 6, 2002 | 32 days |
| Hardy Middle School | FM-200125929 /01 5/6/02 (HARDY) **EMERGENCY** THIRD (3RD) FLOOR - GIRLS RESTROOM ASBESTOS ASSESSMENT REQUIRED. NEED WALL ASSESSED SO PLUMBER CAN REATTACH COMMODE TO WALL. 1. REPAIR TWO (2) SINKS WITH LEGS ATTACHED, THEY ARE LEANING. 2. THE PIPES ARE LEAKING WATER FROM THE BOTTOM. SAFETY HAZARD. POC: CHANGE FOR ASBESTOS/ ASSIGN DATE 01-23-02 A. BUTLER #ID 748. Asbestos Code A - Clear For Repairs On 03/25/02. Horne Engineering - Sam Ebrahim (RG 03/27/02) | December 21, 2001 | May 6, 2002 | 136 days |
| Woodson High School | FM-200205293 02 5/7/02 (Woodson, H.D.) 1. Asbestos assessment required. Plaza/Teachers restroom with soda machine: Toilet leaks when flushed; flooding and running out in the stairwell. Asbestos code A - Clear for repairs on 04/05/02. DCPS Safety - Ronald Edwards (202) 576-6693 (RG 04/08/02 ) | April 2, 2002 | May 7, 2002 | 35 days |
| Merritt Middle School | FM-200206743 02 5/7/02 ****Urgent**** 1st Floor Girl's Toilet The middle toilet in girl's restroom off the east ramp needs new closet bolt pipe. A sleeve was put on 2 years ago, but is now is badly leaking and flooding the restroom floor every day. | April 26, 2002 | May 7, 2002 | 11 days |
| Turner Elementary School | FM-200204421 02 5/10/02 (Turner) 1st and 2nd floors/ Old and New side 1st floor old side the 4th and 6th toilets are stopped up, last two urinals that was remounted still leak, 2nd floor restroom old side 1st two urinals and 3rd toilet stopped up, newly installed water fountain, 2nd floor is still leaking after being installed. Newly installed fountain in cafeteria need to be serviced; students are unable to get water. Extremely hot weather, cool water is needed. | March 14, 2002 | May 10, 2002 | 57 days |
| Turner Elementary School | FM-200202992 02 5/10/02 (TURNER) 1ST FLOOR/ BOYS RESTROOM THE TWO URINALS THAT WERE PUT BACK ON THE WALL ARE LEAKING FROM THE WALL AND THE BOTTOM OF THE URINAL. ALSO NEED NEW FIXTURES FOR THE 3RD URINAL AND THE 4TH TOILET. WHEN YOU CUT THE WATER ON, IT STILL DOES NOT WORK. | February 13, 2002 | May 10, 2002 | 86 days |
| Ketcham Elementary School | FM-200207439 02 5/13/02 Ketcham 2nd Floor Boys' Restroom & Teachers' Lounge Replace one broken window pane in each restroom. POC: Wadsworth | May 9, 2002 | May 13, 2002 | 4 days |
| Lincoln Middle School | FM-200201250 02 5/15/02 (LINCOLN) !!! EMERGENCY !!! 3RD FLOOR/ BOYS BATHROOM REPAIR THE BRADLEY BASIN IN THE BOYS BATHROOM. THE VALVE DOSENT HOLD TO SHUT THE WATER OFF. WATER IS FLOODING THE BATHROOM. RECURRENT PROBLEM. | January 16, 2002 | May 15, 2002 | 119 days |
| Duke Ellington School | FM-200204265 02 5/16/02 ELLINGTON FIRST (1ST) FLOOR - GIRLS RESTROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE BROKEN COMMODE Code A-clear for repair by Horne Egineer on ( Bipin Nanavaty ) 3/13/02 (CEB) | March 11, 2002 | May 16, 2002 | 66 days |
| Macfarland Middle School | FM-200203306 02 5/16/02 (Macfarland) Asbestos assessment req. 1st floor and 2nd floor/ Girls and Boys Restroom 1st floor: boys restroom partition coming apart in the 1st stall. 2nd floor: girls restroom 2nd stall is coming apart. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/25/02 HORNE ENGINEER: PHELEP CONNOLLY | February 22, 2002 | May 16, 2002 | 83 days |
| Patricia R Harris Ed Center | FM-200207548 02 5/17/02 Harris,P.R. 1. Asbestos Assessment Reqd. Restrooms @ #6 Stairwell Area/Main Floor of Buidling 2. Replace the lock on one door [women's restroom], old lock will not hold. 3. Install a new lock on one door [girls' restroom] so door can be properly secured. Asbestos Code A - Clear for repairs on 6/13/02 DCPS Safety - R. Edwards (RE- 6/13/02) | May 10, 2002 | May 17, 2002 | 7 days |
| Emery Elementary School | FM-200127174 /01 5/22/02 (EMERY) Toilet in girls bathroom is leaking from bottom. | December 18, 2001 | May 22, 2002 | 155 days |
| Wilkinson ES | FM-200112307 01 5/22/02 WILKINSON SECOND FLOOR GIRLS RESTROOM 1) INSTALL KNOB LOCK WITH KEY ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | June 4, 2001 | May 22, 2002 | 352 days |
| Simon Elementary School | FM-200207735 02 5/22/02 Simon Break In !!!! Ground Floor - Girls Bathroom, 12,2, and 3. 1) Girl Bathroom - One window guard cut and one pried open. 2) Rooms - 12,2, and 13 - All doors have been damaged and wire glass need to be replaced. This is a multi -trade Carpentry-Welding-Glazing. | May 15, 2002 | May 22, 2002 | 7 days |
| Tubman Elementary School | FM-200111414 01 5/22/02 TUBMAN SECOND FLOOR SPACE 129 TEACHERS RESTROOM 1) REPLACE BATHROOM DOOR LOCK DOOR CANNOT BE LOCKED FROM INSIDE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/23/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | May 29, 2001 | May 22, 2002 | 358 days |
| Wilkinson ES | FM-200111434 01 5/22/02 WILKINSON FIRST FLOOR TEACHERS LOUNGE 1) WOMENS RESTROOM NEEDS LOCK INSTALLED WITH KEY ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | May 29, 2001 | May 22, 2002 | 358 days |
| Malcolm X ES | FM-200120074 01 5/22/02 (MALCOLM X) ASBESTOS ASSESSMENT REQ. 1ST FLOOR PEELING PAINT TEACHER LOUNGE MISSING TILE BOYS BATHROOM CUSTODIAN SUPPLY ROOM LIGHT COVERS MAJOR LEAK CAFETERIA LADYS BATHROOM MAIN OFFICE. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: BIPIN NANAVARY | September 18, 2001 | May 22, 2002 | 246 days |
| Wilkinson ES | FM-200111432 01 5/22/02 WILKINSON FIRST FLOOR TEACHERS LOUNGE 1) MENS RESTROOM NEEDS LOCK INSTALLED WITH KEY ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/25/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | May 29, 2001 | May 22, 2002 | 358 days |
| Bowen Elementary School | FM-200207733 02 5/22/02 Bowen First Floor - Custodial Office 1) Ruptured line in custodial office bathroom. Engineer can not isolate line, water is running in to Boiler Room. | May 15, 2002 | May 22, 2002 | 7 days |
| Brightwood Elementary School | FM-200205956 02 5/22/02 (Brightwood) 1st floor/girls bathroom: Replace toilet, water leaking; toilet has a hairline crack. Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) on 4/19/02 | April 17, 2002 | May 22, 2002 | 35 days |
| Brightwood Elementary School | FM-200205289 02 5/22/02 (Brightwood) 1. Asbestos assessment required. 1st floor/boys restroom: Repair 3" PVC trap on 3rd urinal; water leaking into boiler room. Code A-clear for repair by Honre Engineer ( Stephen Caldwell ) on 4/04/02 | April 2, 2002 | May 22, 2002 | 50 days |
| Eaton Elementary School | FM-200207415 02 5/23/02 Eaton !!! Emergency !!! Second (2nd) Floor - Boys Restroom Urinals is leaking water and flowing over floor. | May 8, 2002 | May 23, 2002 | 15 days |
| Turner Elementary School | FM-200205131 02 5/23/02 (Turner) 1. Asbestos assessment required. New building/3rd floor. Unstop third toilet in girls restroom; floods over when flushed. Asbestos code A - Clear for repairs on 04/05/02. DCPS Safety - Ronald Edwards (202) 576-6693 (RG 04/08/02 ) | March 29, 2002 | May 23, 2002 | 55 days |
| Beers Elementary School | FM-200203280 02 5/23/02 (Beers) 2nd Floor Building 3/Music Room 213 The restroom inside music room 213 has a faulty flush valve, which allows water to shoot out when commode is flushed [on-site school staff could not fix problem]. | February 21, 2002 | May 23, 2002 | 91 days |
| Sousa Middle School | FM-200207657 02 5/23/02 Sousa 1st Floor Male Teachers' Restroom & 3rd Floor Boys' Restroom 1. 1st Floor: Cylinder is has gone bad, needs to be replaced--door cannot be secured. 2. 3rd Floor: Cylinder is jammed and does not work, cannot lock the door--needs to be replaced. | May 14, 2002 | May 23, 2002 | 9 days |
| Kramer Middle School | FM-200206940 02 5/23/02 Kramer !!!Emergency!!! 2nd floor/boys restroom; Unstop commode, over-flowing. (Isolate emergency, no penetration Asbestos Code A - Clear for repairs on 05/01/02. DCPS Safety - Richard Gibson (RG 05/01/02) | April 30, 2002 | May 23, 2002 | 23 days |
| Stuart-Hobson Middle School | FM-200206667 02 5/23/02 Stuart-Hobson !!! Emergency !!! First (1st) Floor - Boys Restroom Urinals is flooding and the water is running down thru the ceiling in the Custodical Office. Cannot shut the valves off. | April 25, 2002 | May 23, 2002 | 28 days |
| Turner Elementary School | FM-200204835 02 5/24/02 (Turner) ****Urgent**** 3rd Floor Girls Restroom/New Wing Unstop third toilet in the girls restroom. Toilet floods over onto floor when flushed [health hazard]. | March 22, 2002 | May 24, 2002 | 63 days |
| Wilkinson ES | FM-200207813 02 5/24/02 Wilkinson ****Urgent**** 1st Floor Boys' Restroom Unclog stopped up urinal in the boys' restroom [staff was unable to clear it]. | May 15, 2002 | May 24, 2002 | 9 days |
| Walker-Jones EC | FM-200119192 01 5/24/02 (WALKER- JONES) ASBESTOS ASSESSMENT REQ. 1ST FLOOR/BY AUDITORIUM ROOM 100 REPLACE WAX RING-BATHROOM (TOILET). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/07/01. RONALD EDWARDS - SAFETY (202)576-669 (RG) | September 5, 2001 | May 24, 2002 | 261 days |
| Marshall Educational Center | FM-200207768 02 5/24/02 Marshall ****Emergency**** 2nd Floor Boys' Restroom When any of the urinals are flushed in the 2nd floor boys' restroom, all the commodes back up causing the water to run down into the lower level kindergarten area onto the carpeting. This is a persistent problem [Ref: FM-200207474 of 5/9/02]. | May 15, 2002 | May 24, 2002 | 9 days |
| Brightwood Elementary School | FM-200206945 02 5/24/02 Brightwood ****Emergency**** First Floor - Boys Bathroom 1) Urinal leaking down into Boiler Room. Leaking from 4 inch PCV trap. Reassigned/forwarded to BPO [Kramer] per James Vernon. | May 1, 2002 | May 24, 2002 | 23 days |
| Harris, C.W. ES | FM-200208200 02 5/24/02 Harris,C.W. ****Emergency**** 2nd Floor Boys' Restroom Repair copper water line (for convector). | May 22, 2002 | May 24, 2002 | 2 days |
| Reed LC | FM-200208192 02 5/30/02 (Reed) Fire code violation: 1. Asbestos assessment required. Auditorium: Door near boys bathroom will not open. Asbestos Code A - Clear for repairs on 05/22/02. DCPS Safety - Ronald Edwards (RG 05/23/02) | May 22, 2002 | May 30, 2002 | 8 days |
| Woodson High School | FM-200119923 01 6/3/02 (WOODSON, H.D.) ASBESTOS ASSESSMENT REQ. BATHROOM KEYS NEED LOCKSMITH TO CUT 24 KEYS FOR RESTROOMS TO BE GIVEN TO TEACHERS TO MONITOR AND LOCK RESTROOMS AFTER CLASSES. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/20/01. HORNE ENGINEERING - SHARON VOSS (RG) | September 17, 2001 | June 3, 2002 | 259 days |
| Kramer Middle School | FM-200208222 02 6/3/02 Kramer Basement/#25 Boys' Restroom Shut-off valve on urinal #4 does not work and needs repair or replacement. | May 22, 2002 | June 3, 2002 | 12 days |
| Kramer Middle School | FM-200208115 02 6/3/02 Kramer ****Very Urgent**** 1. Asbestos Assessment Reqd. 2nd Floor Girls' Restroom 2. The wall, under the Bradley basin, is leaking water onto the floor and needs repair. The wall itself is very wet and the area of repair is where contractors installed the new Bradley basin. Code A- Asbestos abated on 05/22/02 PER Leroy Minton Jr. confirmation. (RG 05/23/02) | May 21, 2002 | June 3, 2002 | 13 days |
| Ross Elementary School | FM-200208634 02 6/3/02 Ross ****Urgent**** Basement Boys' Restroom by the Cafeteria The 2nd toilet is flooding the floor and bubbling. There is something stuck in the toilet that cannot be cleared by the custodian. | May 29, 2002 | June 3, 2002 | 5 days |
| Browne Junior High School | FM-200204486 02 6/3/02 Browne 2nd fl. Parent Rm. to kitchen toilet 1. Asbestos assessment required. 2. Repair leaking 3/4" line leading from parent room 2nd fl. to kitchen bathroom (condensate return line). Code A-clear for repair by Horne Engineer ( Sam Ebrahim ) on 3/19/02 (CEB | March 15, 2002 | June 3, 2002 | 80 days |
| Walker-Jones EC | FM-200208561 02 6/3/02 Walker-Jones !!! Emergency !!! Girls' Restroom Replace a slow valve, water is leaking all over the floor. Main valve cannot be shut off. | May 28, 2002 | June 3, 2002 | 6 days |
| Walker-Jones EC | FM-200208609 02 6/3/02 Walker-Jones ****Very Urgent**** 2nd Floor Girls' Restroom by Room 210 Replace Sloan flushometers on the last toilet by the wall. The fixtures is consistently leaking with water running out of the flush valve handle and from the cut-off valve, causing flooding across the floor. The cut-off valve threads are stripped. | May 29, 2002 | June 3, 2002 | 5 days |
| Meyer Elementary School | FM-200203858 02 6/3/02 (Meyer) 1st Floor Landing Near 1st Floor Boys Restroom Replace broken door closure in the 1st floor landing [center stairwell] near the boys restroom--possible fire code violation. | March 5, 2002 | June 3, 2002 | 90 days |
| Nalle Elementary School | FM-200208207 02 6/3/02 Nalle ****Emergency**** 1st Floor New Wing/Boys' & Girls' Restrooms 1. Boys' Restroom: When any toilet is flushed, all the others backup & overflow. 2. Girls' Restroom: Water is constantly running--need flush valve replaced. | May 22, 2002 | June 3, 2002 | 12 days |
| Deal Junior High School | FM-200207230 02 6/3/02 Deal 3rd Floor Girls' Restroom Replace extention drain line under sink. The line is rusted and both sinks cannot be used. Asbestos Code A - Clear for repairs on 05/07/02. DCPS Safety - Richard Gibson (RG) | May 6, 2002 | June 3, 2002 | 28 days |
| Ballou Senior High School | FM-200206654 02 6/3/02 Ballou ****Emergency**** 1st Floor Male Staff Restroom The hand-basin is clogged and black sewer water is backing up into it and emitting a very bad odor. | April 25, 2002 | June 3, 2002 | 39 days |
| Cook J.F. Elementary School | FM-200208215 02 6/3/02 Cook, J.F. !!! Emergency !!! 1. First (1st) Floor - Girls Restroom Commodes are stopped up 2. First (1st) Floor - Boys Restroom Urinals are leaking and water is on the floor Safety Hazard. | May 22, 2002 | June 3, 2002 | 12 days |
| Harris, C.W. ES | FM-200208135 02 6/3/02 Harris,C.W. ****Urgent**** 2nd Floor Boys' Restroom The pipe running under the floor has a hole in it and the water leaking out of it is going down into the 1st floor restroom. | May 21, 2002 | June 3, 2002 | 13 days |
| Park View ES | FM-200204708 02 6/3/02 (Parkview) 2nd floor/ Hallway (near boys bathroom) Circuit breaker has shortage in the lights in the boys bathroom. Lights will not come on. | March 19, 2002 | June 3, 2002 | 76 days |
| Wilkinson ES | FM-200208721 02 6/3/02 Wilkinson 1st Floor Girls' Restroom & Ross Kindergarten Area Unclog toilet in girls' 1st-floor restroom & in the Ross kindergarten area restroom. | May 31, 2002 | June 3, 2002 | 3 days |
| Beers Elementary School | FM-200208068 02 6/3/02 Beers 2nd Floor Buidling 1 Boys' & Girls' Restrooms 1. Boys' restroom urinal is clogged & flush valve is rusted-- water goes everywhere. 2. Toilet is clogged & emitting a very bad odor--toilet cannot be flushed. | May 20, 2002 | June 3, 2002 | 14 days |
| Eaton Elementary School | FM-200207557 02 6/3/02 Eaton 2nd & 3rd Floors/Boys' & Girls' Restrooms 1. 2nd & 3rd floor boys' restrooms: Student tood on urinals causing the units to leak from the wall [one on each floor]. 2. 3rd floor girls restroom: Bradley basin does not work--no hand-wahsing facilities. Survey only No Penetration! | May 10, 2002 | June 3, 2002 | 24 days |
| Beers Elementary School | FM-200207387 02 6/3/02 Beers ****Urgent**** Building #3/1st, 2nd & 3rd Floors 1) 1st & 2nd floors/boys restroom: sinks are leaking from the joints; unable to stop flow of water because joints have rusted out. 2) 2nd floor: custodial closet has water coming up out of the slop sink & over- flowing onto the floor. | May 8, 2002 | June 3, 2002 | 26 days |
| Spingarn High School | FM-200208649 02 6/3/02 Spingarn ****Urgent**** 2nd Floor Boys' Restroom Two sinks in the boys' restroom cannot be cleared by custodian. | May 29, 2002 | June 3, 2002 | 5 days |
| Wilson J. O. ES | FM-200207669 02 6/4/02 Wilson,J.O. ****Emergency**** 1. Asbestos Assessment Reqd. 3rd Floor Boys' & Girls' Restrooms/Old Wing 2. Need survey & assessment for upgrade and replacement of all old plumbing fixtures in both the girls' & boy's 3rd floor restrooms. The old fixtures are constantly leaking and flooding down into the restroom areas below. [REF: FM-200123984 created 11/28/01 cleared for repair and concerning leaks resulting from the 3rd floor restroom problem]. Now the leaking has spread to the 1st floor restrooms where the the plaster ceiling fell in the boys' restroom. Also Ref: FM-200207670 created 5/14/02. This on going problem is both a health & safety hazard. Also, these areas cannot be effectively isolated because the problem is too widespread. Envirobate (IT Group)/703-461-6848 Asbestos Code A - Clear for repairs on 05/31/02. After further evaluation by DCPS (Mr. Hinton) , USACE (Robert Franklin) and Shaw Group (Vincent Reed) it was determined that the problem can be corrected by installing new flush valves and flanges. This was reported to Sheila R. Howard-DCPS Safety 05-31-02. Ricardo Welch of Structural Maintenance was informed and he stated he would assign the project to the evening shift. (DCPS Safety-Sheila R. Howard 05-31-02 at 1255) | May 14, 2002 | June 4, 2002 | 21 days |
| Wilson J. O. ES | FM-200207763 02 6/4/02 Wilson,J.O. 1. Asbestos Assessment Reqd. New Wing/1st, 2nd & 3rd Floor Restrooms Throughout 2. Survey, assess, abatement for restoration,replacement of all old, worn out, leaking, inoperable plumbing fixtures, valves, etc. in all restrooms in the new wing. Code A-clear for repair by Horne Engineer ( Stephen Caldwell ) on 5/16/02 | May 15, 2002 | June 4, 2002 | 20 days |
| Young Elementary School | FM-200208566 02 6/5/02 Young 1st Floor Next to Kindergarten Room Unstop urinal in the boys' restroom and the teachers' restroom. On-site staff could not get the problem cleared and the urinal & toilet are smelling. | May 29, 2002 | June 5, 2002 | 7 days |
| Ludlow-Taylor ES | FM-200207274 02 6/5/02 Ludlow-Taylor 3rd Floor Boys' Restroom Remount the 1st sink in the boys' restroom which has been pulled away from the wall. | May 7, 2002 | June 5, 2002 | 29 days |
| Moten Elementary School | FM-200207786 02 6/5/02 Moten 3rd Floor Teachers' Restroom The shut-off valves [both hot & cold] are leaking on the sink in the teacherr' 3-floor restroom. | May 15, 2002 | June 5, 2002 | 21 days |
| Cleveland Elementary School | FM-200203574 02 6/5/02 (Cleveland) ***Urgent*** 1st Floor Boys Restroom Sink Repair Bradley basin or install a new drain. The basin leaks from the bottom when water runs into the drain and spills onto the floor. | February 27, 2002 | June 5, 2002 | 98 days |
| Meyer Elementary School | FM-200115724 01 6/6/02 MEYER ALL BATHROOM DOORS ASBESTOS ASSESSMENT REQUIRED NEED TO CHANGE LOCKS ON ALL BOYS & GIRLS BATHROOM DOORS. ONE OF THE BOYS LOCK ON 1ST FLOOR WONT OPEN, THE LOCK KEEPS GOING AROUND & AROUND. NEED LOCKS AS SOON AS POSSIBLE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/04/01. HORNE ENGINEERING - DONALD MAGLIENTI | July 24, 2001 | June 6, 2002 | 317 days |
| Eliot Junior High School | FM-200208982 02 6/7/02 Eliot ****Emergency**** 2nd Floor Boys' Restroom Leaking face bowl can not be shut off and water is flooding across the floor. | June 5, 2002 | June 7, 2002 | 2 days |
| Francis Junior High School | FM-200208321 02 6/7/02 (Francis) Health code violation: Kitchen: Repair washer on girls hand sink in restroom. | May 23, 2002 | June 7, 2002 | 15 days |
| Garrison ES | FM-200207773 02 6/7/02 (Garrison) Fire code violation: 1. Asbestos assessment required. 1st Floor/East wing: Door needs to be checked, next to womens restroom. Asbestos Code A - Clear for repairs on 05/16/02. DCPS Safety - Leroy Minton Jr. (RG 05/16/02) | May 15, 2002 | June 7, 2002 | 23 days |
| Kramer Middle School | FM-200208773 02 6/7/02 Kramer 1. Asbestos Assessment Reqd. 1st Floor Girls' Restroom 2. Drain pipe under sink needs to be repaired or replaced. [Safety hazard] Asbestos Code A - Clear for repairs on 06/03/02. Horne Engineering - Troy Wilcome (RG 06/04/02) | June 3, 2002 | June 7, 2002 | 4 days |
| Kramer Middle School | FM-200208772 02 6/7/02 Kramer Basement Toom #25 Boys' Restroom Cut-off valve on urinal #4 needs to be repaired or replace. | June 3, 2002 | June 7, 2002 | 4 days |
| Powell Elementary School | FM-200203821 02 6/10/02 (Powell) 1. Asbestos assessment required. All faucets in all restrooms keeps coming lose and the screw that tighen the faucets is plastic an on it's way to break on all faucets in the building. Also the stand up urinals in Rm#107 does not work it is a new urinal, and both boys restrooms on the second floor faucets and urinals are new and do not flush properly. All faucets & urinals are new and we are having problems with them both not working properly some one need to come out and expect all the work that the contractor's did. Asbestos Code A - Clear for repairs on 05/13/02. DCPS Safety - Ronald Edwards (RG 05/14/02) | February 27, 2002 | June 10, 2002 | 103 days |
| Wilkinson ES | FM-200208990 02 6/10/02 Wilkinson 1st Floor [Space 52] Ross Kindergarten Restroom Replace old Delaney flush valve with a Sloan flush valve---old valve is not working. | June 5, 2002 | June 10, 2002 | 5 days |
| Maury Elementary School | FM-200209002 02 6/12/02 Maury 2nd Floor Boys' Restroom Repair Bradley basin that has a faulty shut-off valve. | June 5, 2002 | June 12, 2002 | 7 days |
| Park View ES | FM-200207859 02 6/12/02 Park View 2nd Floor Boys' Restroom A toilet needs to be snaked out in the 2nd-floor boys' restroom. It keeps flooding and something seems to be lodged in it. | May 16, 2002 | June 12, 2002 | 27 days |
| Davis Elementary School | FM-200208998 02 6/12/02 Davis ****Urgent**** 2nd Floor New Wing/Girls' Restroom Girls' restroom beside room 218 has a stopped-up toilet. Could not unstop the toilet with snake and plunger---need K50 snake. | June 5, 2002 | June 12, 2002 | 7 days |
| Seaton Elementary School | FM-200209056 02 6/12/02 Seaton !!! Emergency !!! Third (3rd) floor - Girls' Restroom Sink came off wall and broke in half. New install sink, please check all sinks for safety. First (1st), Second (2nd) and Third (3rd) Floor Girls' Restrooms. Please do safety check on all new sinks. Sink in house install new sink girls' restroom Third floor. | June 5, 2002 | June 12, 2002 | 7 days |
| Young Elementary School | FM-200205305 02 6/12/02 (Young) 1. Asbestos assessment required. 1st Floor/Kindergarten bathroom: Need plumber to unstop teachers toilet; staff tried to unstop toilet with no success. (25 ft snake could not reach the problem) Asbestos code A - Clear for repairs on 04/05/02. DCPS Safety - Ronald Edwards (202) 576-6693 (RG 04/08/02 ) | April 2, 2002 | June 12, 2002 | 71 days |
| Aiton Elementary School | FM-200202463 02 6/13/02 (AITON) 1. ASBESTOS ASSESSMENT REQUIRED. 3RD FLOOR/BOYS RESTROOM: REPLACE MISSING FIRE DOOR TO RESTROOM; THERE IS NO DOOR ON SITE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/22/02. DCPS - SAFETY - SHEILA R. HOWARD (RG 02/22/02) | February 5, 2002 | June 13, 2002 | 128 days |
| Raymond Elementary School | FM-200207257 02 6/13/02 Raymond ****Urgent**** 1. Asbestos Assessment Reqd. 1st Floor Girls' Restroom [New Wing] 2. A drain pipe has been broken away from the wall causing flooding across the floor [potential safety hazard to students]. The pipe needs to be replaced to deter large students from stepping on the pipe, causing it to break away from the wall. POC: Chandra Murchison Asbestos Code A - Clear for repairs on 5/07/02 Horne Engineering,Stephen Caldwell (RE- 5/08/02) | May 7, 2002 | June 13, 2002 | 37 days |
| Bunker Hill Elementary School | FM-200207297 02 6/13/02 (Bunker-Hill) !!!Emergency!!! 2nd Floor/Boys' Bathroom: Leaking from urinal; unable to cut off from stop control valves-- bathroom almost flooded out. | May 7, 2002 | June 13, 2002 | 37 days |
| Shaw JHS | FM-200127369 02 6/13/02 (SHAW) Main office restroom stoped up used pluger not working needs a snake please send help EMERGENCY!!! Requester Phone: 202 673 7203 Asbestos Code A - Clear for repairs on 05/08/02. DCPS Safety - Richard Gibson (RG 05/08/02) | January 9, 2002 | June 13, 2002 | 155 days |
| Shaw JHS | FM-200209576 02 6/14/02 Shaw Boys and girls bathroom rec area school side. Install two slide bolt on doors. Rec children are gaining access to school after hours. This creates a safety and security HAZARD!!! | May 16, 2002 | June 14, 2002 | 29 days |
| Simon Elementary School | FM-200207536 02 6/14/02 Simon ****Urgent**** Asbestos Assessment Reqd. 3rd Floor Boys Restroom Replace urinal that is broken away from the wall. The broken, cracked urinal is resting on the floor and the pipes in the wall are exposed. There is a foul smell coming from the hole. This restroom has been completely isolated to prevent any further damage. POC: Dennis Rowe/645-3360 Code A-clear for repair by Horne Engineer ( Troy Wilcome ) on 05/13/02 | May 10, 2002 | June 14, 2002 | 35 days |
| Harris, C.W. ES | FM-200209289 02 6/17/02 Harris,C.W. ****Urgent**** 1st Floor Teachers' Restroom The door is locked and can not be opened. | June 11, 2002 | June 17, 2002 | 6 days |
| Barnard Elementary School | FM-200206746 02 6/17/02 (Barnard) 1. Asbestos assessment required. 1st floor - New building: Repair four (4) light fixtures in the hallway. 1st floor - Old building: Girls restroom and hallway. Repair light fixtures in all areas; all are without lights. Code A-clear for repair by Horne Engineer by (Shron Voss ) on 5/01/02( CEB ) | April 26, 2002 | June 17, 2002 | 52 days |
| Beers Elementary School | FM-200209221 02 6/17/02 Beers ****Urgent**** 1st Floor Building I Auditorium 1. The exit door by the library has a broken lock making easy access for break-ins. 2. The auditorium restroom also has a broken lock on the door. | June 7, 2002 | June 17, 2002 | 10 days |
| Birney Elementary School | FM-200209666 02 6/19/02 (Birney) 1st Floor/Old side: Unstop two (2) urinals in the boys bathroom. | June 17, 2002 | June 19, 2002 | 2 days |
| Kramer Middle School | FM-200206088 02 6/20/02 Kramer !!! Emergency !!! Second (2nd) Floor - Next to Boys Restroom 1. Asbestos Assessment Required. 2. Pipes leaking water thru the walls. Causing damage the walls. Safety Hazard. POC: Tyrone Hopson, Principal CAPE (IT Group)/703-461-6848 Code A - Asbestos abated on 04/19/02 PER Leroy Minton Jr. confirmation. (RG 04/26/02) | April 18, 2002 | June 20, 2002 | 63 days |
| Wilson J. O. ES | FM-200208824 02 6/20/02 Wilson,J.O. 1. Asbestos Assessment Reqd. 3rd Floor/New Wing & 3rd Floor/Old Wing 2. Boys' restroom has missing urinals and a commode out of service. 3. Boys, restroom has 2 urinals & one commode out of service. Asbestos Code A - Clear for repairs on 06/04/02. DCPS Safety - Leroy Minton Jr. (RG) | June 3, 2002 | June 20, 2002 | 17 days |
| Sousa Middle School | FM-200205868 02 6/20/02 Sousa 1st Floor Boys & Girls Restrooms 1) The 3rd & 4th toilet in the boys restroom need wax rings. The toilets were running sending water across the floor [has now been turned off so the bottom of the partition frames will not corrode]. 2) The 3rd toilet from the entrance in the girls restroom is stopped up. The toilet close to the window leaks from the neck and needs a wax ring. The 3rd toilet from the left needs a wax ring. | April 16, 2002 | June 20, 2002 | 65 days |
| Wilson J. O. ES | FM-200114269 01 6/21/02 WILSON, J.O. FIRST FLOOR BOYS AND GIRLS RESTROOM EXIT DOORS 1) ACCESS, ABATE, AND RESTORE BOYS AND GIRLS RESTROOM EXIT DOORS UNABLE TO SECURE DOORS Asbestos Code A - Clear For Repairs On 03/08/02. Horne Engineering - Sheryll James (RG 03/11/02) | June 28, 2001 | June 21, 2002 | 358 days |
| Turner Elementary School | FM-200208140 02 6/21/02 (Turner) ***Very Urgent*** Old building-2nd Floor/Teachers Lounge: Water flooding the floors due to bad spud nut, one toilet stopped up. At this time, the engineer cut the water off, floors are a little more dry. Please repair so that the water can be turned on again, as the teachers have no other restroom on that floor. | May 21, 2002 | June 21, 2002 | 31 days |
| Duke Ellington School | FM-200202327 02 6/23/02 (ELLINGTON) ***URGENT*** 2ND FLOOR GIRLS RESTROOM & TEACHERS LOUNGE 1) THE HANDICAPPED COMMODE (VERY LAST COMMODE) NEEDS SNAKING 2) THE 2ND FLOOR TEACHERS LOUNGED FACE BOWL NEEDS TO BE SNAKED (WATER IS TURNED OFF TO ISOLATE THE PROBLEM) | February 1, 2002 | June 23, 2002 | 142 days |
| Wilkinson ES | FM-200204726 02 6/25/02 (Wilkinson) Asbestos Assessment Required 1st Floor Room 58B [Boys Restroom] Survey, replace or repair cap to the Bradley Basin head, due to vandalism & other missing parts. POC: Mr. Butler Asbestos Code A - Clear For Repairs On 03/23/02. DCPS Safety - Ronald Edwards (RG 03/25/02) | March 19, 2002 | June 25, 2002 | 98 days |
| Hine JHS | FM-200209609 02 6/25/02 Hine 3rd Floor Gym Shower Boys' Room Floor drain is stopped up and needs clearing. | June 14, 2002 | June 25, 2002 | 11 days |
| Stevens Elementary School | FM-200104502 /01 6/25/02 STEVENS BASEMENT, 2ND & 3RD FLOORS REPLACE THERMOSTATIC VALVES ON RADIATORS. RM # 31 (2) 1", RM #33 (2) 1", RM 32 (3) 1", RM #35 (3) 1", RM #37 (1) 1", RM #34 (1) 1", RM #36 (4) 1", RM #22 (2) 1", RM #21 (1) 1", RM #25 (3) 1", RM #26 (3) 1", RM #2 (1) 1", RM #3 (1) 1", RM #5 (2) 1", MAIN OFFICE (1), STAIRWAYS (3) 1", BOYS RESTROOM (1) 1", CAFETERIA (2). | February 28, 2001 | June 25, 2002 | 482 days |
| Shaw JHS | FM-200204714 02 7/2/02 (Shaw) 1. Asbestos assessment required. Boys rec bathroom partition has come off wall due to vandalism; needs to be reattached to wall. thank you. Asbestos Code A - Clear for repairs on 05/28/02. Horne Engineering - Sheryll James (RG 05/29/02) | March 12, 2002 | July 2, 2002 | 112 days |
| West Elementary School | FM-200210237 02 7/3/02 West 1. Asbestos Assessment Reqd. 1t Floor Learning Center Boys' Restroom 2. Replace urinal on the right side of the learning center. [In-house maintenance staff will fix it, but wall needs to be checked for asbestos.] Code A-clear for repair by Horne Engineer ( Bipin Nanavaty ) on 06/26/02 | June 25, 2002 | July 3, 2002 | 8 days |
| Stevens Elementary School | FM-200210276 02 7/3/02 (Stevens) ***Very Very Urgent*** 1st Floor/Bathroom: Busted pipe in the central hallway bathroom. Bathroom and hall flooded. | June 25, 2002 | July 3, 2002 | 8 days |
| Merritt Middle School | FM-200202329 02 7/3/02 (MERRITT) ASBESTOS ASSESSMENT REQUIRED 3RD FLOOR GYMNASIUM BOYS BATHROOM LIGHT WILL NOT COME ON. BREAKERS SUPPORTING THE LIGHTS ARE IN THE "ON" POSITION ALTHOUGH NOT DELIVERING POWER TO THE BATHROOM LIGHTS. Asbestos Code A - Clear for repairs on 05/10/02. DCPS Safety - Leroy Minton Jr. (RG 05/13/02) | February 1, 2002 | July 3, 2002 | 152 days |
| Ballou Senior High School | FM-200210226 02 7/3/02 Ballou ****Urgent**** 1. Asbestos Assessment Reqd. Ground-floor Level Boys' Restroom Urinal #1 will not flush and #5 is leaking from the wall. Asbestos Code A - Clear for repairs on, 6/26/02 DCPS Safety, R. Edwards (RE - 6/26/02) | June 25, 2002 | July 3, 2002 | 8 days |
| Wilkinson ES | FM-200120385 01 7/9/02 (WILKINSON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ ROOM 180 BOYS BATHROOM INSTALL LOCK ON DOOR. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/14/01. HORNE ENGINEERING - TROY WILCOME | September 24, 2001 | July 9, 2002 | 288 days |
| Reed LC | FM-200210523 02 7/12/02 Reed 1. Asbestos Assessment Reqd./Need Exploratory 1st Floor Early Childhood Boys' Restroom 2. Replace a broken toilet that leaks in the boys' restroom in this area. (Needs a hole in the wall Ref: FM-200121003 for prior clearance.) *Special Note: Philip Connolly of Horne Engineering wii need a work authorization to prform to light broscope procedure. DCPS Safety-Sheila R. Howard 07-10-02. POC: Melvin Mack (202)576-8046 | June 27, 2002 | July 12, 2002 | 15 days |
| Cardozo High School | FM-200210603 02 7/15/02 Cardozo ****Urgent**** Ground Floor Girls' Restroom Two basins in the girls' restroom are not draining at all---both are on the same drain line. | July 1, 2002 | July 15, 2002 | 14 days |
| Backus Middle School | FM-200205897 02 7/15/02 Backus ****Emergency**** 3rd Floor Womens Coaching Office Restroom Old-fashioned [not made any longer] valve system on toilet is not holding and each repair fails to hold. Water is flooding across the floor. | April 16, 2002 | July 15, 2002 | 90 days |
| Birney Elementary School | FM-200207568 02 7/15/02 Birney 1. Asbestos Assessment Reqd. 2nd Floor Boys' Restroom Replace door & door hardware. POC: Robert Gillespie Asbestos Code A - Clear for repairs on 05/16/02. DCPS Safety - Leroy Minton Jr. (RG 05/17/02) | May 10, 2002 | July 15, 2002 | 66 days |
| Payne Elementary School | FM-200210451 02 7/15/02 Payne 1st Floor Old Building Near Custodian's Office Girls' Restroom Repair or replace the flush valves on the 1st toilet---not working and there is no pressure. | June 26, 2002 | July 15, 2002 | 19 days |
| Moten Elementary School | FM-200209307 02 7/15/02 Moten Old side - First Floor Boys and Girls bathroom 1) Plumbers removed toilets but never came back to capp them off. Gas is coming up through the pipes.... | June 11, 2002 | July 15, 2002 | 34 days |
| Shaw JHS | FM-200210338 02 7/15/02 Shaw Commons area girls bathroom toliet stoped up. | June 19, 2002 | July 15, 2002 | 26 days |
| Shaw JHS | FM-200210340 02 7/15/02 Shaw Commons area girls bathroom toliet stoped up 1st floor | June 19, 2002 | July 15, 2002 | 26 days |
| Macfarland Middle School | FM-200109494 01 7/16/02 MACFARLAND FIRST (1ST) FLOOR - GIRLS RESTROOM 1) ASBESTOS ASSESSMENT REQUIRED 2) REPLACE SINK OFF WALL Code A-clear for repair by Horne Engineer ( Z Mahmood ) on 4/17/02 (CEB) | May 2, 2001 | July 16, 2002 | 440 days |
| Macfarland Middle School | FM-200206521 02 7/16/02 (Macfarland) 1. Asbestos assessment required. 2nd floor/boys restroom: Repair the door to the boys restroom, the door is rubbing against the frame. Code A-clear for repair by Horne Engineer by (Sam Ebrahim ) on 4/26/02 ( CEB ) | April 24, 2002 | July 16, 2002 | 83 days |
| John Burroughs ES | FM-200117781 01 7/17/02 BURROUGHS COUNSELOR OFFICE, MORTH HALL LADIES RESTROOM 14, 13, BACKHALL 1. ABESTOS ASSESSMENT REQUIRED. 2. REPLACE 3/4 VALVE AND TRAPS IN COUNSELOR OFFICE , MORTH HALL, LADIES RESTROOM 14, 13, AND BACK HALL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/01/01. HORNE ENGINEERING - EDWARD RODRIGEZ (RG) | August 17, 2001 | July 17, 2002 | 334 days |
| Backus Middle School | FM-200210952 02 7/17/02 (Backus) Fire code violation: Page 1 of 4 3rd Floor/Boys locker room: Door needs to be re-checked/Restroom. Asbestos Code A clear for repairs, on 7/11/02 DCPS Safety, L. Minton (RE - 7/11/02) | July 10, 2002 | July 17, 2002 | 7 days |
| Backus Middle School | FM-200210984 02 7/18/02 (Backus) Fire code violation: 1. Asbestos assessment required. 2nd floor: Door closure broken on girls and boys restroom door. Asbestos Code A clear for repairs, on 7/11/02 DCPS Safety, L. Minton (RE - 7/11/02) | July 10, 2002 | July 18, 2002 | 8 days |
| Thomson Elementary School | FM-200202548 02 7/19/02 Thomson 2nd & 3rd fl. 301A, Bathroom 2nd fl. 1. Asbestos assessment required. 2. R/R cracked radiator in room 301A. 3. R/R leaking radiator in bathroom 2nd fl., Principals bathroom. ASBESTOS CODE A-CLEAR FOR REPAIR ON 02/08/02 HORNE ENGINEER: TROY WILCOME | February 6, 2002 | July 19, 2002 | 163 days |
| Garrison ES | FM-200212459 02 7/22/02 (Garrison) !!!Emergency!!! East wing/1st Floor, boys bathroom: Attempted break-in left window guard rail pulled away from window. Break-in prior to this date transpired on 07/08/2002. | July 19, 2002 | July 22, 2002 | 3 days |
| Anacostia Senior High School | FM-200204613 02 7/24/02 (Anacostia) 1st Floor Bridge [Ladies Restroom] The toilets are stopped up again in the 1st-floor ladies restroom. No Penetration! | March 18, 2002 | July 24, 2002 | 128 days |
| Reed LC | FM-200212521 02 7/24/02 Reed ****Urgent**** 2nd Floor Boys' Restroom Learning Center 1 Two urinals will not flush---urine has been standing 1 or 2 weeks. Urinals need clearing. | July 22, 2002 | July 24, 2002 | 2 days |
| Bruce-Monroe Elementary School | FM-200203870 02 7/24/02 (Bruce-Monroe) !!!! Emergency !!!! 2nd floor/ 202 Girls Bathroom Valve has busted under the bradley basin and is leaking into another room and the ceiling is about to fall in. | March 5, 2002 | July 24, 2002 | 141 days |
| Reed LC | FM-200210452 02 7/24/02 Reed First floor- Early childhood boys restroom. Leaking from the wall. POC: Mr. Nelson and Mr. Coles building based staff # Horne Engineering will be drilling holes in wall. Code A-clear for repair by Horne Engineer ( EDward Rodriguez )on 07/08/02 DCPS CE Buchanan | June 27, 2002 | July 24, 2002 | 27 days |
| Beers Elementary School | FM-200204414 02 7/25/02 (Beers) 2nd floor/ Bldg. #3 - music room 213 Restroom inside music room when flushing stool lots of water shoots out from the flush valve. I tried to fix it. (on floor) | March 14, 2002 | July 25, 2002 | 133 days |
| Woodson High School | FM-200212396 02 7/25/02 Woodson H.D. Floors - 7th,6th,5th, and 4th Boys and Girls Restroom. 1) Urinals not working ,will not flush and commodes not working and will not flush. 2) 4 commodes and one leaking. 3) 4 Urinals are leaking. 4) Need (6) paper towels racks and (4) toilet seats. | July 18, 2002 | July 25, 2002 | 7 days |
| Brightwood Elementary School | FM-200204270 02 7/25/02 (Brightwood) 1st Floor Hallway [near boys restroom] Repair/replace broken faucet in hallway sink. | March 11, 2002 | July 25, 2002 | 136 days |
| Whittier Elementary School | FM-200210783 02 7/25/02 Whittier ****Urgent**** 1. Asbestos Assessment Reqd. 1st Floor New Wing/Boys' Restroom 2. A urinal is leaking from the wall in the 1st-floor boys' restroom-- water is shut off, but the leaks continues. Asbestos Code A - Cleared for repairs on 07-05-02 (LM) Leroy Minton Safety Office 202-576-8962. Code A-clear for repair by Horne Engineer ( Bipin Nanavaty )on 07/09/02 DCPS CE Buchanan | July 8, 2002 | July 25, 2002 | 17 days |
| Jessie LaSalle Elementary | FM-200210705 02 7/26/02 LaSalle 1st Floor Women & Men's Restrooms Replace wax rings in both of these 1st floor restrooms--water is leaking from the bottom of the commodes. | July 2, 2002 | July 26, 2002 | 24 days |
| Jessie LaSalle Elementary | FM-200210703 02 7/26/02 LaSalle Basement Room #23; 1st & 2nd Floor Hallway Boys' Restrooms 1. The recently installed commode is leaking from the bottom on the basement level. 2. The 1st & 2nd floor boys' restroom--each has a toilet in need of snaking. | July 2, 2002 | July 26, 2002 | 24 days |
| Miner Elementary | FM-200212787 02 7/26/02 Miner ****Urgent**** Repair ruptured pipe in the custodian closet---water is spreading into the hallway and into the restroom. | July 24, 2002 | July 26, 2002 | 2 days |
| Jessie LaSalle Elementary | FM-200210704 02 7/26/02 LaSalle ****Urgent**** 1. Asbestos Assessment Reqd. Basement Storage Room 2. There is leaking, through the waste lines from the 1st floor boys' & girls' restroom, into the basement storage room. Need repair as soon as possible. Asbestos Code A - Clear for repairs on 07/02/02. Horne Engineering - Sheryll James (07/03/02) | July 2, 2002 | July 26, 2002 | 24 days |
| Whittier Elementary School | FM-200212672 02 7/29/02 (WHITTIER) 1st-Floor Boys' Restroom/Old Wing 1. Two urinals are stopped up---need clearing; and 2. Replace control stop-valve. POC: Mr. Lewis | July 23, 2002 | July 29, 2002 | 6 days |
| Whittier Elementary School | FM-200212674 02 7/29/02 (WHITTIER) 2nd-Floor Boys' Restroom/New Wing Replace vacuum breaker and spud on urinal. POC: Mr. Lewis | July 23, 2002 | July 29, 2002 | 6 days |
| Browne Junior High School | FM-200212759 02 7/30/02 Browne 1. Asbestos Assessment Reqd. 2nd Floor Room 210 & Boys' Restroom near Room 131 2. Repair key and knob lock on Rm 210---door will not open once shut; and 3. Repair key & knob-lock on boys' restroom door---door will not open. | July 24, 2002 | July 30, 2002 | 6 days |
| Bell High School | FM-200213444 02 8/2/02 Bell Various Areas 1. 2nd flr. male teachers' & boys restrooms need repair or replacement of locks on the restroom doors; and rooms 120B, 407 & 408 also need lock repair or replacement. 2. The main entrance door [middle section] needs repair of replacement of the panic bar and door closer. 3. The rear door at the 1st landing to large parking lot on the right needs the panic bar repaired or replaced. | August 2, 2002 | August 2, 2002 | 0 days |
| John Burroughs ES | FM-200203898 02 8/5/02 (Burroughs) Lower Level/ Basement Restroom Boys urinals are stopped up when flushing water fills to the top, and takes a while to go down again. I tried to snake it myself not successful. Need snake to run thru the pipes. | March 5, 2002 | August 5, 2002 | 153 days |
| Kimball Elementary School | FM-200202532 02 8/6/02 (KIMBALL) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR/MIDDLE WING: REMOVE BROKEN FLOOR TILE 9 X 9 BURGUNDY, IN FRONT OF WATER COOLER. Hot method floor tile AMP room 55 / TSI, Clean up Boys room AMP room 65. Envirobate - Charles Crenshaw - 571-436-1150 Code A - Clear for repairs. Abated on 06-18-02 per leroy minton confirmation. (LM) Safety Office 202-576-8962. | February 6, 2002 | August 6, 2002 | 181 days |
| Coolidge High School | FM-200202898 02 8/7/02 (COOLIDGE) Asbestos Assessment Reqd. 2ND FLOOR/ TEACHERS RESTROOM REPLACE DOOR TO THIS RESTROOM, DUE TO VANDALISM. (WOODEN DOOR) Asbestos Code A - Clear for repairs on 05/15/02. DCPS Safety - Ronald Edwards (RG 05/16/02) | February 12, 2002 | August 7, 2002 | 176 days |
| Takoma Educational Center | FM-200122555 /01 8/7/02 (TAKOMA) ASBESTOS ASSESSMENT REQ. 3RD FLOOR/ ROOMS: 221 AND 222 RESTROOMS THE BOYS AND GIRLS RESTROOMS ARE IN NEED OF SERVICE. THE PRESSURE SEEMS TO BE VERY LOW, SOME FIXTURES NEED TO BE REPLACED AND ALSO UNSTOPPAGE IS NEEDED. WATER MUST BE POURED IN TOILETS AND URINALS TO BE FLUSHED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/05/01 HORNE ENGINEERING - SAM EBRAHIM(RG) | October 30, 2001 | August 7, 2002 | 281 days |
| Takoma Educational Center | FM-200213533 02 8/7/02 Takoma Second Floor - Girls Bathroom 1) Install toilet ( Replace existing toilet) No penetrations ... | August 5, 2002 | August 7, 2002 | 2 days |
| Eastern High School | FM-200213357 02 8/9/02 Eastern ****Urgent**** 1. Asbestos Assessment Reqd. 1st Floor Main Office 2. Furnish and install commode in main office restroom for use of principal [replacement needs to take place as soon as possible]. Code A-clear for repair by Charles Buchanan on 8/01/02 | July 31, 2002 | August 9, 2002 | 9 days |
| Sousa Middle School | FM-200205839 02 8/9/02 Sousa ****Urgent**** 2nd Floor Boys & Girls Restrooms 1) Two toilets need wax ring and tightening. Water is running out from the back of the toilets when flushed. 2) The toilets on the right-hand side of the girls restroom need wax rings. One toilet needs a control stop-valve, the other one needs a flush valve. | April 16, 2002 | August 9, 2002 | 115 days |
| Ludlow-Taylor ES | FM-200213651 02 8/16/02 (Ludlow-Taylor) Fire code violation: Page 1 of 1 2nd Floor/Boys bathroom: Door hardware broken. Asbestos Code A - Clear for repairs on 08/07/02. DCPS-Safety - Leroy Minton Jr. (RG 08/08/02) | August 6, 2002 | August 16, 2002 | 10 days |
| Coolidge High School | FM-200213549 02 8/19/02 Coolidge 1. Asbestos Assessment Reqd. 2nd Floor Teachers' Restroom 2. Install a lock on the new door to the teachers' restroom--- wooden door & frame. Asbestos Code A - Clear for repairs on 08/05/02. DCPS Safety - Richard Gibson (RG) | August 5, 2002 | August 19, 2002 | 14 days |
| Whittier Elementary School | FM-200214837 02 8/19/02 Whittier Principal's Office Bathroom Loose bricks above the skylight is falling through. This is a dangerous situation requiring immediate attention. | August 16, 2002 | August 19, 2002 | 3 days |
| Wilkinson ES | FM-200214296 02 8/19/02 Wilkinson 1st Floor Room 111 [Women's Restroom] Repair or replace leaking faucet on sink. | August 14, 2002 | August 19, 2002 | 5 days |
| Eastern High School | FM-200214090 02 8/20/02 Eastern Exterior Grounds/Stadium Restrooms Furnish and replace cylinder locks--need to bar vandals and other unauthorized persons from accessing the boys' & girls' restsroom under the press box [also, equipment: footballs, etc., are stored near the corner of the stadium. Eastern is the site for the Turkey Bowl championshp game and the area of the restrooms need to be as secure as is possible. | August 12, 2002 | August 20, 2002 | 8 days |
| Eastern High School | FM-200213557 02 8/20/02 Eastern ****Urgent**** Stadium/Boys' Restroom Repair or replace the vandalized lock in the boys' restroom. There have been homeless persons sleeping on the school grounds, posing a serious safety hazard to persons who may use the stadium area legitimately [there could be physical attacks]. | August 5, 2002 | August 20, 2002 | 15 days |
| Johnson JHS | FM-200204575 02 8/20/02 (Johnson) 1st & 3rd Floor Water Coolers by Elevator & Girls Restroom Increase water pressure in the coolers on the 1st floor by the girls restroom and on the 3rd floor by the elevator. All other water coolers should be checked out for proper water pressure. | March 18, 2002 | August 20, 2002 | 155 days |
| Garrison ES | FM-200201463 02 8/20/02 GARRISON (T-9) FIRST (1ST) FLOOR - WOMEN RESTROOM AND ROOM #111 WELDON WINDOW GUARD TO WOMEN RESTROOM AND REMOVED BROKEN WIRE MESS GLASS. | January 22, 2002 | August 20, 2002 | 210 days |
| Wilkinson ES | FM-200214297 02 8/20/02 Wilkinson 1st Floor Room 103 [Principal's Restroom] Repair or replace leaking faucet on sink--water is running. | August 14, 2002 | August 20, 2002 | 6 days |
| Johnson JHS | FM-200202949 02 8/20/02 (JOHNSON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ (WATER COOLER) NEXT TO GIRLS BATHROOM STUDENT VANDALIZED WALL MOUNTED WATER COOLER PULLING IT DOWN FROM THE WALL. NEEDS TO BE REPAIRED OR REPLACED. Code A-clear for repair by Horne Engineer ( Troy Wilcome ) 0n 3/20/02 (CEB) | February 13, 2002 | August 20, 2002 | 188 days |
| Savoy Elementary School | FM-200212662 02 8/20/02 Savoy ****Very Urgent**** 2nd Floor Teachers' Lounge Restroom Repair pipe in the teachers' lounge [water leaking through to the 1st-floor hallway ceiling tile]. | July 23, 2002 | August 20, 2002 | 28 days |
| Harris, C.W. ES | FM-200205882 02 8/20/02 Harris, C.W. Second (2nd) Floor - Boys Restroom Urinal next to partition needs a new wax rings, water running onto the floor. Safety Hazard. | April 16, 2002 | August 20, 2002 | 126 days |
| Woodson High School | FM-200214278 02 8/20/02 Woodson,H.D. ****Urgent**** 5th Floor Room 511 Replace existing flush valve that is leaking in the restroom. | August 13, 2002 | August 20, 2002 | 7 days |
| Eastern High School | FM-200214154 02 8/20/02 Eastern Outside Grounds/Stadium Replace lock on boys' corner restroom that was broken during an act of vandalism. [NOTE: The stadium is the site for the Turkey Bowl--season begins end of August 2002] | August 13, 2002 | August 20, 2002 | 7 days |
| Park View ES | FM-200125257 /01 8/20/02 (PARKVIEW) 2ND FLOOR/ GILRS BATHROOM TOILET LEAKING AROUND THE PIPE WHEN YOU FLUSH. | December 13, 2001 | August 20, 2002 | 250 days |
| Turner Elementary School | FM-200214149 02 8/22/02 Turner 3rd Floor /Old & New Wings 1. The sink in the boys' restroom next to the wall has a leaking P-trap and supply line; 2. Third urinal needs a vacuum breaker; 3. All supply lines on sinks are leaking; and 4. The 3rd floor boys' urinal (new wing) is not flushing properly. | August 13, 2002 | August 22, 2002 | 9 days |
| Seaton Elementary School | FM-200115137 01 8/22/02 SEATON THIRD (3RD) FLOOR - NEW TEACHER RESTROOM REPLACE ELECTRICAL CORD FOR WATER COOLER ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/27/01 LEROY MINTON - SAFETY (202)576-6691 (RG) | July 11, 2001 | August 22, 2002 | 407 days |
| Moten Elementary School | FM-200215117 02 8/26/02 Moten 2nd, 3rd & 4th Floors 1. 2nd floor boys' toilets--stop water coming from the wall behind the urinal. Water shut-off valve is not working; 2. 3rd floor teachers' & girls' restrooms---repair or replace leaking faucets; and 3. 4th floor girls' restroom---repair or replace shut-off valve, water is running. | August 20, 2002 | August 26, 2002 | 6 days |
| Shaed Elementary School | FM-200120708 01 8/26/02 (SHAED) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ GIRLS RESTROOM WATER LEAKING FROM CEILING. ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/23/01 HORNE ENGINEER : TROY WILCOME HORNE ENG (TROY WILCOME) REVISITED SHAED ES (02-11-02) AND DETERMINED THAT THE THIRD FLOOR RESTROOM WOULD NOT HAVE ANY ASBESTOS IMPACT. MELVIN MACK ANF JEFFERY GRAHAM VOICED CONCERN 02-11-02. DCPS SAFETY-SHEILA R. HOWARD 02-11-02 | September 28, 2001 | August 26, 2002 | 332 days |
| Smothers ES | FM-200207407 02 8/26/02 Smothers 1. Asbestos Assessment Reqd. 1st Floor Girls' Lavatory 2. Repair three [3] stall partitions are loose in the 1st floor girls' restroom. The screws were not connected through into the wood supports and the doors are shifting. Code A clear for repairs as of 5/9/02 Horne Engineers James. | May 8, 2002 | August 26, 2002 | 110 days |
| Wilkinson ES | FM-200215337 02 8/26/02 Wilkinson 1st Floor Rm. 90 Women's Bathroom (pre-K area) Repair/replace key lock (knob-lock---knob is broken). | August 22, 2002 | August 26, 2002 | 4 days |
| Emery Elementary School | FM-200108709 01 8/27/02 EMERY SECOND (2ND) FLOOR - BOYS RESTROOM 1) ASBESTOS ASSESSMENT REQUIRED. 2) TWO (2) URINALS IN RESTROOM ARE CLOG AND NEED TO BE REHUNG ON THE WALL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/01/01. (SAME AS WO #FM-200108539) | April 18, 2001 | August 27, 2002 | 496 days |
| Stanton Elementary School | FM-200214061 02 8/27/02 Stanton Basement - Boys Restroom next to Cafeteria 1) Toilet needs vacuum breaker repaired. | August 12, 2002 | August 27, 2002 | 15 days |
| Eastern High School | FM-200215087 02 8/27/02 Eastern ****Urgent**** Basement & 1st Floor Custodial Closets/Basement Girls' Restroom 1. Unstop drains in the basement & 1st floor custodial closets, sinks leaking also. 2. Water is leaking from sinks in basement girls' restroom across from D77. Eastern will be the site of the superindent's conference on Wednesday 21 August 2002. | August 20, 2002 | August 27, 2002 | 7 days |
| Cooke H.D. Elementary School | FM-200215193 02 8/27/02 Cooke,H.D. ****Urgent**** Basement Girls' Restroom 3rd toilet on the left side has very low water pressure. Waste will not pass through the pipes. | August 21, 2002 | August 27, 2002 | 6 days |
| Turner Elementary School | FM-200214141 02 8/27/02 Turner 1st & 2nd Floors--Girls' Restroom/New Wing & Custodial Closet/Old Wing 1. 1st Floor girls' restroom has a cold-water faucet that is not working and needs to be repaired or replaced; 2. 2nd Floor girls' restroom needs three (3) new toilet seats; 3. The cold-water faucet does not cut off in the first sink; and 4. The custodial closet (2nd flr./old wing) needs the faucet replaced. | August 13, 2002 | August 27, 2002 | 14 days |
| Ferebee-Hope Elementary School | FM-200206849 02 8/27/02 Asbestos Assessment Reqd. 4th Floor Boys Restroom Install missing wall-mounted urinal [#6]. Asbestos Code A - Clear for repairs on 05/01/02. Horne Engineering - Z Mahmood (RG 05/02/02) | April 30, 2002 | August 27, 2002 | 119 days |
| Oyster Elementary School | FM-200215580 02 8/28/02 Oyster ****Very Urgent**** 2nd Floor Boys' & Girls' Classroom Restrooms 2. Two (2) toilets are backing up and causing flooding into the music room below [Rm. 208], damaging the ceiling tiles and getting into the light fixtures, burning out the ballasts. Repair the plumbing problem to stop the damage to the area below. | August 26, 2002 | August 28, 2002 | 2 days |
| Eastern High School | FM-200214153 02 8/28/02 Eastern Outside Grounds/Stadium--Corner Boys' Restroom Repair or replace broken urinal and face bowl in boys' corner urinal. [NOTE: The stadium is the site for the Turkey Bowl--season begins end of August 2002] | August 13, 2002 | August 28, 2002 | 15 days |
| Meyer Elementary School | FM-200107738 01 8/29/02 MEYER FIRST (1ST) FLOOR - BOYS BATHROOM 1) ASBESTOS ACCESS MAY BE REQUIRED. 2) THE HANDICAPPED SINK IN BOYS TOILET, WAS BROKE FROM IN WALL. NEED TO BE REPLACE BACK OR THE WALL AS SOON AS POSSIBLE. CODE A- CLEAR FOR REPAIR AS OF 4/16/01 | April 7, 2001 | August 29, 2002 | 509 days |
| Eastern High School | FM-200214268 02 8/29/02 Eastern ****Urgent**** Outside Grounds/Stadium Restrooms Principal is requesting that protective bars be placed over the existing doors to the stadium restrooms [there has been constant vandalism committed in the restrooms]. | August 13, 2002 | August 29, 2002 | 16 days |
| Houston Elementary School | FM-200213755 02 8/29/02 (Houston) Fire code violation: 1st Floor/next to teachers lounge: Boys room not closing properly. Asbestos Code A - Clear for repairs on 08/09/02. DCPS-Safety - Leroy Minton Jr. (RG 08/09/02) | August 7, 2002 | August 29, 2002 | 22 days |
| Spingarn High School | FM-200215952 02 8/29/02 Spingarn Room 116 - 1st fl. near boys restroom Check fan on condenser. Fan will not come on. | August 28, 2002 | August 29, 2002 | 1 day |
| Clark Elementary School | FM-200216206 02 8/30/02 Clark ****Urgent**** Kitchen Restroom in Cafeteria Faucet in kitchen bathroom needs repairs. The faucet is leaking badly and knobs are missing. | August 30, 2002 | August 30, 2002 | 0 days |
| Tyler Elementary School | FM-200216184 02 8/30/02 Tyler ****Urgent**** 1st Floor Girls' Restroom Replace leaking cut-off valve on hand basin. Valve is leaking because it is badly cracked. | August 30, 2002 | August 30, 2002 | 0 days |
| Johnson JHS | FM-200215354 02 8/30/02 Johnson 2nd Floor Men's Bathroom Near Rm. 205 Unstop commodes in the men's bathroom. | August 22, 2002 | August 30, 2002 | 8 days |
| Wilkinson ES | FM-200216317 02 9/3/02 (Wilkinson) !!!Very Urgent!!! 1st Floor/Boys toilet-Room #58: Cut off valve leaking water flooding the bathroom. | September 3, 2002 | September 3, 2002 | 0 days |
| Oyster Elementary School | FM-200216395 02 9/3/02 (Oyster) !!!Emergency!!! 3rd Floor/Room #304: Bathroom directly over classrooom leaking from white colored pipe, smells of urine. | September 3, 2002 | September 3, 2002 | 0 days |
| Hart Middle School | FM-200216314 02 9/3/02 Hart ****Urgent**** Basement, 2nd & 3rd Floor Girls' Restrooms There is a mixing valve problem. There is hot water passing through the flush valves into the toilets. | September 3, 2002 | September 3, 2002 | 0 days |
| Gibbs Elementary School | FM-200214600 02 9/4/02 Gibbs - f-303.4 First floor - Nurse office 1. Door need adjustment betweem bathroom and patient room in nurse office. | August 15, 2002 | September 4, 2002 | 20 days |
| Clark Elementary School | FM-200216078 02 9/4/02 Clark First Floor - Cafeteria 1) Faucet in Kitchen bathroom need repair. Faucet is leaking and knobs are missing. | August 29, 2002 | September 4, 2002 | 6 days |
| Sousa Middle School | FM-200215889 02 9/4/02 Sousa 2nd Floor Girls' Restroom Main 4 1/2" waste line is stopped up, and the 2nd toilet from the wall needs new wax rings. | August 28, 2002 | September 4, 2002 | 7 days |
| Gibbs Elementary School | FM-200201226 02 9/4/02 (GIBBS) 2ND FLOOR/ BOYS RESTROOM REPLACE LEAKING HOT AND COLD FAUCETS ON SINKS AND WATER LINES. | January 16, 2002 | September 4, 2002 | 231 days |
| Sousa Middle School | FM-200215888 02 9/5/02 Sousa Emergency !! 3rd Floor Boys' Restroom Stall (1) toilets is stopped up--need clearing.. Toilet need to be pulled from the wall and gate valve have to be cleared, and stop valve needs to be replace. Asbestos Code A - Clear for repairs on 09/05/02. Horne Engineering - Roger Kager (RG 09/05/02) | August 28, 2002 | September 5, 2002 | 8 days |
| Barnard Elementary School | FM-200216480 02 9/5/02 Barnard First Floor - New Building, Girls Bathroom 1) Bradley Basin running constantly with hot water, will not cut off. | September 4, 2002 | September 5, 2002 | 1 day |
| Truesdell Elementary | FM-200216677 02 9/5/02 Truesdell Emergency!! First Floor - Annex Building - Boys Bathroom 1) Please repair decaying Bradley Basin, that is causing a leak, which is causing kids to fall. | September 5, 2002 | September 5, 2002 | 0 days |
| Emery Elementary School | FM-200215377 02 9/6/02 (Emery) Replace two sets of faucets in boys' bathroom [confirm location in field]. | August 19, 2002 | September 6, 2002 | 18 days |
| Drew Elementary School | FM-200116918 01 9/6/02 DREW 2ND FLOOR - BOYS RESTROOM ASBESTOS ASSESSMENT REQUIRED REPAIR OR REPLACE 2 URINALS. URINALS DO NOT FIT PROPERLY AGAINST WALL & WATER LEAKS WHEN FLUSHED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/27/01. HORNE ENGINEERING - SAM EBRAHIM (RG) | August 8, 2001 | September 6, 2002 | 394 days |
| Emery Elementary School | FM-200215319 02 9/6/02 (Emery) One urinal in boys' bathroom need to be unclogged--staff tried but could not get unclogged. | August 19, 2002 | September 6, 2002 | 18 days |
| Garnet-Patterson MS | FM-200216702 02 9/6/02 Garnett Patterson (Urgent work needed for voting poll.) Auditorium Bathroom 1) Repair concrete lavatory flooring where steam pipe was repaired. Refer to request FM-200201701 floor has been cleared. | September 5, 2002 | September 6, 2002 | 1 day |
| Macfarland Middle School | FM-200216310 02 9/9/02 MacFarland ****Urgent**** 1st Floor Handicapped Restroom Sinks and toilets are backing up and need snaking/clearing. | September 3, 2002 | September 9, 2002 | 6 days |
| Merritt Middle School | FM-200216384 02 9/9/02 (Merritt) !!!Very Urgent!!! 1st Floor/West-Bathroom on the ramp: Elbow pipe has deteriorated, leaking water and flooding the bathroom floor. | September 3, 2002 | September 9, 2002 | 6 days |
| Patricia R Harris Ed Center | FM-200216610 02 9/9/02 Harris,P.R. Auditorium Repair or replace broken door lock at boys' restroom. | September 5, 2002 | September 9, 2002 | 4 days |
| Coolidge High School | FM-200217061 02 9/10/02 Coolidge ****Urgent**** 1st Floor Main Office/Principal's Restroom Unstop sink--needs snaking. | September 9, 2002 | September 10, 2002 | 1 day |
| Garrison ES | FM-200215427 02 9/10/02 Garrison Men's Restroom Repair/replace nonfunctioning hot water faucet. | August 23, 2002 | September 10, 2002 | 18 days |
| Whittier Elementary School | FM-200214832 02 9/10/02 Whittier 1st Floor Girls' Bathroom Replace missing flush valve on commode. | August 16, 2002 | September 10, 2002 | 25 days |
| Wilson J. O. ES | FM-200215405 02 9/11/02 Wilson,J.O. ****Emergency**** 1st Floor Girls' Restroom Adjacent to the All-Purpose Room The toilet keeps backing up, have tried plunging---now needs to be snaked. All other restrooms on 1st floor are closed for repair and this is the only toilet in use on this floor. | August 23, 2002 | September 11, 2002 | 19 days |
| Cardozo High School | FM-200205464 02 9/11/02 (Cardoza) 1st floor/boys bathroom: Need plumber to unstop #7 urinal; water backing up and unable to flush. | April 4, 2002 | September 11, 2002 | 160 days |
| Cardozo High School | FM-200208638 02 9/11/02 (Cardozo) !!Emergency!! 1st Floor/Boys bathroom: All urinals are stopped up; when flushing one urinal, all other urinals will over-flow. Engineer stated that he would contain the water from the flood, also isolate bathroom as the water will be turned off until the repair personnel arrive. | May 29, 2002 | September 11, 2002 | 105 days |
| Malcolm X ES | FM-200216253 02 9/11/02 (Malcolm X) Fire code violation: 1. Asbestos assessment required: 1st Floor/Headstart bathroom: Door hard to open. Asbestos Code A-clear for repair On 9/03/02 DCPS Charles E. Buchanan | August 30, 2002 | September 11, 2002 | 12 days |
| Hart Middle School | FM-200217204 02 9/11/02 Hart School Breach in boys' bathroom on the ground floor | September 10, 2002 | September 11, 2002 | 1 day |
| Wilson J. O. ES | FM-200215611 02 9/11/02 (Wilson, J.O.) 1st Floor/Old side: Repair or replace faucets in the boys and girls restroom, adjacent to the all purpose room. | August 26, 2002 | September 11, 2002 | 16 days |
| Wilson J. O. ES | FM-200213350 02 9/11/02 Wilson,J.O. 1st Floor Girls' Restroom Snake out backed up toilet that will not flush properly. | July 31, 2002 | September 11, 2002 | 42 days |
| Shepherd ES | FM-200205697 02 9/12/02 Shepherd First (1st) Floor - Girls Restroom Repair window. Doesnot function properly, possible problem with sash cord. Window will not stay up. Asbestos Code A - Clear for repairs on 04/11/02. DCPS Safety - Leroy Minton\ Sheila R Howard (RG 04/11/02) The window in the girls restroom and the boys restroom are nailed close due to the accident that harmed a child's hand in 2001. (Sheila R Howard) | April 10, 2002 | September 12, 2002 | 155 days |
| River Terrace ES | FM-200217068 02 9/12/02 (River Terrace) !!!VERY URGENT!!! 1st Floor: Intermediate Side/Boys bathroom: Hand bowls and urinals stopped up. "NEED REPAIRS BEFORE VOTER ELECTION DAY/09/10/02" | September 9, 2002 | September 12, 2002 | 3 days |
| Brightwood Elementary School | FM-200215505 02 9/13/02 (Brightwood) !!URGENT!! Teachers lounge: Repair or replace faucetts in teachers lounge that continues to run, unable to turn off. 2nd floor bathroom inside main office , leaking from trap under sink. | August 23, 2002 | September 13, 2002 | 21 days |
| Brightwood Elementary School | FM-200215608 02 9/13/02 (Brightwood) 1st Floor/Girls restroom: Toilet running all the time. Asbestos Code A - Clear for repairs on 08/27/02. DCPS Safety - Richard Gibson (RG 05/27/02) | August 26, 2002 | September 13, 2002 | 18 days |
| Brightwood Elementary School | FM-200216277 02 9/13/02 Brightwood Asbestos Assessment Reqd. 2nd Floor Teachers' Lounge & 1st Floor Girls' Restroom 1. Remove face basin and cap water lines--basin is not in use; and 2. Girls' 1st floor restroom has a toilet that keeps running. Asbestos Code A-clear for repair by Horne Engineer Bipin Nanavaty On 9/03/02 DCPS Charles E. Buchanan | August 30, 2002 | September 13, 2002 | 14 days |
| Ludlow-Taylor ES | FM-200216709 02 9/13/02 Ludlow-Taylor ****Urgent**** 2nd Floor Staff Restroom The hot water is continuously running into the basin and cannot be turned off--shut off valve not working. | September 5, 2002 | September 13, 2002 | 8 days |
| Barnard Elementary School | FM-200217565 02 9/16/02 Barnard ****Urgent**** 1st Floor & Room 215 1. Toilet is backed up in the 1st floor girls' restroom [2nd toilet]; and 2. Repair/replace faucet in room 215--water is continuously running. | September 16, 2002 | September 16, 2002 | 0 days |
| Malcolm X ES | FM-200216219 02 9/16/02 (Malcolm X) Fire code violation: 1. Asbestos assessment required. 3rd Floor/Girls bathroom: Door not aligned. Asbestos Code A-clear for repair On 9/03/02 DCPS Charles E. Buchanan | August 30, 2002 | September 16, 2002 | 17 days |
| Malcolm X ES | FM-200216195 02 9/16/02 (Malcom X) Fire code violation: Boys bathroom: Door closer broken. | August 30, 2002 | September 16, 2002 | 17 days |
| Eastern High School | FM-200214156 02 9/16/02 Eastern Outside Grounds/Stadium--Girls' Press Box Restroom Repair or replace three (3) broken face bowls. [NOTE: The stadium is the site for the Turkey Bowl--season begins end of August 2002] | August 13, 2002 | September 16, 2002 | 34 days |
| Shaed Elementary School | FM-200216338 02 9/17/02 Shaed Areas Listed Throughout Repair of replace leaking or defective flush valves in the following areas: 1. 2nd floor girls' restroom: 5 toilets/2 not working; boys' restroom: 5 urinals/1 not working & 4 toilets/2 not working; boys' restroom: 1 urinal/not working 2. 3rd floor girls restroom: 5 toilets/2 not working; Bradley basin not working; boys' restroom: 5 urinals/2 not working; 4 toilets/2 not working, and 2 Bradley basins/1 not working; girls' restroom: 2 toilets/1 not working; 1 sink/not working; boys' restroom: 1 urinal/not working; 3. Ground level: girls' restroom 2 Bradley basins/1 not working; multi-service center 2 sinks/1 not working; 4. 1st floor nurses' office: 1 sink/not working; boys' restroom 4 toilets/1 not working; boys' restroom 1 sink/not working. | September 3, 2002 | September 17, 2002 | 14 days |
| Shaed Elementary School | FM-200202705 02 9/17/02 SHAED SECOND (2ND) FLOOR - GIRLS RESTROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. WATER LEAKING FROM CEILING MUST BE REPAIRED BY PLUMBERS OBSERVED FROM SEWER LINES. POC: ROGER KAGER OF HORNE ENG. ASBESTOS CODE A-CLEAR FOR REPAIR ON 02/08/02 HORNE ENGINEER: ROGER KAGER | February 8, 2002 | September 17, 2002 | 221 days |
| Ballou Senior High School | FM-200216316 02 9/17/02 Ballou ***Urgent*** 1st Floor 7D Police Office Restroom Toilet will not flush. | September 3, 2002 | September 17, 2002 | 14 days |
| Hart Middle School | FM-200217196 02 9/17/02 (Hart) ****Emergency**** 1st Floor Girls Locker-room Restroom Toilet on end has water flooding overf the restroom floor----shut-off valve turned off, but water continues to flood across the floor and has gone through the ceiling below causing falling tiles. | September 10, 2002 | September 17, 2002 | 7 days |
| Bell High School | FM-200217791 02 9/18/02 (Bell) !!!EMERGENCY!!! 1st, 2nd & 3rd Floor/Through-out building: All toilets, boys and girls, overflowing when flushing. When a toilet is flushed. all other toilets over-flows. There are flooded bathrooms on each floor. | September 18, 2002 | September 18, 2002 | 0 days |
| King M L ES | FM-200217809 02 9/18/02 (King) !!!VERY URGENT!!! 3rd Floor/boys restroom: Floor drain stopped up, flooding the floors, and running out in the hallway. | September 18, 2002 | September 18, 2002 | 0 days |
| Shepherd ES | FM-200217874 02 9/19/02 Shepherd Old & New Wings by Office Near Boys' Restrooms Repair leaking lines in the old and new wings. | September 19, 2002 | September 19, 2002 | 0 days |
| Dunbar High School | FM-200217567 02 9/19/02 Dunbar ****Urgent**** 1st Floor Teachers' Lounge The lock on the door to the female restroom is not working--the cylinder spins and the door will not open or lock. | September 16, 2002 | September 19, 2002 | 3 days |
| Hendley Elementary School | FM-200217950 02 9/23/02 (Hendley) !!Very Urgent!! 1st Floor/Boys bathroom: Urinal constantly running, flooding the bathroom floor. | September 19, 2002 | September 23, 2002 | 4 days |
| Wilkinson ES | FM-200215949 02 9/23/02 Wilkinson F303.4 Fire code violation: Second floor - Men and Women restroom Missing hardware. | August 28, 2002 | September 23, 2002 | 26 days |
| Sousa Middle School | FM-200205842 02 9/24/02 Sousa Asbestos Assessment Reqd. 1st Floor Boys Restroom Furnish and replace existing window panes with plexiglass. Asbestos Code A - Clear for repairs on 04/17/02. Horne Engineering - Troy Wilcome (RG 04/18/02) | April 16, 2002 | September 24, 2002 | 161 days |
| Thomson Elementary School | FM-200217986 02 9/24/02 Thomson Basement,First and Second Floor 106,204,Basement Boys Room. 1) Turn off water in the following room to have sinks removed and relocated to Logan Building Rooms 106,204, and Basement Boys Room ( East Side). Amend - Disconnect and remove from wall (4) antique pedestal sinks for transport to Logan by others. Disconnect (2+?) floor drinking fountain ( for asbestos tile removal ) . Disconnect one gas stove in Teachers Lounge. | September 20, 2002 | September 24, 2002 | 4 days |
| Patricia R Harris Ed Center | FM-200218070 02 9/25/02 Harris,P.R. ****Emergency**** 1st Floor Stairwell #5/Boys' Restroom Water was coming up from the toilet and the water was shut down on Sunday during emergency response, affecting that entire side of the building. Need completion and restoring water to area. | September 23, 2002 | September 25, 2002 | 2 days |
| Woodson High School | FM-200216400 02 9/26/02 (Woodson, H.D.) Fire code violation: Basement/Girls room: Exit light out in girls room/left side. | September 3, 2002 | September 26, 2002 | 23 days |
| Woodson High School | FM-200216584 02 9/26/02 (Woodson, H.D.) Fire code violation: 7th Floor/Teachers bathroom: Bad door closer. | September 5, 2002 | September 26, 2002 | 21 days |
| Garfield ES | FM-200215462 02 9/27/02 Garfield F-303.4 Fire Code Violation 1st Floor/New Wing Girls' Restroom Replace door hardware. | August 23, 2002 | September 27, 2002 | 35 days |
| Woodson High School | FM-200216686 02 9/27/02 (Woodson, H.D.) Fire code violation: 2nd floor: Teachers bathroom door needs adjusting. Asbestos Code A - Clear for repairs on 09/06/02. DCPS Safety - Leroy Minton Jr. (RG 09/09/02) | September 5, 2002 | September 27, 2002 | 22 days |
| Woodson High School | FM-200216586 02 9/27/02 (Woodson, H.D.) Fire code violation: 7th/Floor/Teachers bathroom in stairway #4" Leak from ceiling. Asbestos Code A - Clear for repairs on 09/05/02. DCPS Safety - Leroy Minton Jr. (RG 09/06/02) | September 5, 2002 | September 27, 2002 | 22 days |
| Woodson High School | FM-200216754 02 9/27/02 (Woodson, H.D.) Fire code violation: 1st Floor/Teachers bathroom: Exposed wiring. | September 6, 2002 | September 27, 2002 | 21 days |
| John Burroughs ES | FM-200216455 02 9/30/02 Burroughs First Floor - New Boys Restroom 1) Boys annex bathroom (2) toilets leak from the bottom when flushing. First Floor - New Wing - Girls Restroom 2) Toilet leaks when flushing. Lower Level - Girls Restroom 3) Two toilets leaks water when flushing. First Floor - Teachers Restroom Women 4) Water leaks from bottom of toilet. Asbestos Code A - Clear for repairs on 09/04/02. DCPS Safety - Richard Gibson (RG) | September 4, 2002 | September 30, 2002 | 26 days |
| Stanton Elementary School | FM-200218092 02 9/30/02 Stanton 3rd Floor Girls' Restroom Repair faucets in third floor girls' restroom. | September 23, 2002 | September 30, 2002 | 7 days |
| Stanton Elementary School | FM-200218056 02 9/30/02 Stanton ****Urgent**** 3rd Floor Boys' Bathroom Replace faulty faucet. | September 23, 2002 | September 30, 2002 | 7 days |
| Tubman Elementary School | FM-200214937 02 9/30/02 Tubman 2nd Floor space 131 [Girls' Restroom] Replace four (4) commodes in restroom for use when school opens on 3 September 2002. | August 19, 2002 | September 30, 2002 | 42 days |
| Harris, C.W. ES | FM-200218538 02 9/30/02 Harris, C.W. Attempted Break-In Emergency !! First Floor - Main Office - (2), 145 (1) , Asst. Principal Office (1), Pre-K Girls Bathroom (2) , 144 - (1). 1) Replace broken windows | September 30, 2002 | September 30, 2002 | 0 days |
| Woodson High School | FM-200216628 02 9/30/02 (Woodson, H.D.) Fire code violation: 3rd Floor/Teachers bathroom: Door needs adjusting. | September 5, 2002 | September 30, 2002 | 25 days |
| Tubman Elementary School | FM-200204306 02 9/30/02 TUBMAN !!!! EMERGENCY !!!! FIRST (1ST) FLOOR - BOYS RESTROOM PLACE THE SINK BACK ON THE WALL. STUDENT WAS SWINGING AND THE SINK HAS FALLEN. SAFETY HAZARD. Code A-clear for repair by Horne Egineer on ( Sharon Voss ) 3/13/02 (CEB) | March 12, 2002 | September 30, 2002 | 202 days |
| Patricia R Harris Ed Center | FM-200207547 02 10/1/02 Harris,P.R. 1. Asbestos Assessment Reqd. Teachers Restroom I 2. The stall (partition?) is broken away from the wall and is starting to destroy the all altogether. Repair wall & rehang or replace stall (partition?). Asbestos Code A - Clear for repairs on 6/13/02 DCPS Safety - R. Edwards (RE- 6/13/02) Damaged or missing stall partitions were also observed in the following areas All Boys and Girls Restrooms on the Ground floor, located near stairwells 1-8. also 1st floor, Boys and Girls Lockerroom restrooms. (R. Edwards -6/13/02) | May 10, 2002 | October 1, 2002 | 144 days |
| Hart Middle School | FM-200218732 02 10/2/02 Hart Third Floor - Girls Bathroom 1) First stall reanchor commode. 2) 3rd and 4th stall replace flush valve 3) 1st, 3rd and 4th lavatory sink, replace single lever self closing faucets and remove stoppage. | October 2, 2002 | October 2, 2002 | 0 days |
| Eastern High School | FM-200218636 02 10/2/02 Eastern Ground floor - Locker room Girl locker room leading to restroom wall has a large hole in it. Six feet high x three foot wide (Brick). Asbestos Code A - Cleared for repairs on 10-02-02 (LM/10-02-02) Leroy Minton Jr. Safety Office (202-) 576-8962. | October 1, 2002 | October 2, 2002 | 1 day |
| Kimball Elementary School | FM-200217831 02 10/3/02 Kimball ****Urgent**** 1st & 2nd Floor North Wing Boys' Restrooms 1. Change faucet on slop sink--water runs all night and cannt be shut off on the 1st floor boys' restroom. We have to turn the main water off; and 2. Change two flush valves on both urinals, where the water cannot be turned off on the 2nd floor in the boys' restroom. | September 18, 2002 | October 3, 2002 | 15 days |
| Browne Junior High School | FM-200218081 02 10/4/02 Browne Emergency !! Third Floor - Boys and Girls Bathroom and Male and Female lavatory 1) Correct problem with toilets and urinals, some will not stop running,some have broken handles, sinks have no running water, and toilets and urinals will not flush. | September 23, 2002 | October 4, 2002 | 11 days |
| Ketcham Elementary School | FM-200218754 02 10/4/02 Ketcham First Floor - Breaker gone bad on first floor, hallway and boys bathroom lights won't come on. Second Floor - Breaker needs to be replaced on second floor, security lights are out. Second Floor - Boys bathroom lights are out. | October 3, 2002 | October 4, 2002 | 1 day |
| Woodson High School | FM-200216401 02 10/8/02 (Woodson, H.D.) Fire code violation: 1. Asbestos assessment required. Basement/Girls bathroom: Ceiling tile missing. Asbestos Code A - Clear for repairs on 09/05/02. DCPS Safety - Leroy Minton Jr. (RG 09/06/02) | September 3, 2002 | October 8, 2002 | 35 days |
| Turner Elementary School | FM-200217812 02 10/8/02 (Turner) !!!VERY URGENT!!! Through-out building: 3rd urinal from wall is leaking, flooding floor (old building) , sink next to mirror in boys restroom leaking from the supply line. on the 3rd floor/ Old side, urinal leaking from wall next to stall (leaking (new side) | September 18, 2002 | October 8, 2002 | 20 days |
| Moten Elementary School | FM-200216957 02 10/8/02 Moten F-303.4 Fire Code Violation 1st Floor Restroom Door closer broken. | September 9, 2002 | October 8, 2002 | 29 days |
| Woodson High School | FM-200216626 02 10/8/02 (Woodson, H.D.) Fire code violation: 4th Floor/Boys restroom: Door needs repairing (2nd) one. | September 5, 2002 | October 8, 2002 | 33 days |
| Woodson High School | FM-200216666 02 10/8/02 (Woodson, H.D.) Fire code violation: 4th Floor/Girls bathroom: Door closer broken. | September 5, 2002 | October 8, 2002 | 33 days |
| Woodson High School | FM-200216676 02 10/8/02 (Woodson, H.D.) Fire code violation: 3rd Floor/Mens bathroom: Ceiling tile to be replaced. | September 5, 2002 | October 8, 2002 | 33 days |
| Moten Elementary School | FM-200216870 02 10/9/02 Moten F-303.4 Fire Code Violation Asbestos Assessment Reqd. 3rd Floor Boys' Restroom Door not closing properly. | September 6, 2002 | October 9, 2002 | 33 days |
| Moten Elementary School | FM-200216875 02 10/9/02 Moten F-303.4 Fire Code Violation 3rd Floor Women's Restroom Missing hardware on door. | September 6, 2002 | October 9, 2002 | 33 days |
| Moten Elementary School | FM-200216848 02 10/9/02 Moten F-303.4 Fire Code Violation 4th Floor Boys' Restrooms Door closer broken. | September 6, 2002 | October 9, 2002 | 33 days |
| Bunker Hill Elementary School | FM-200124879 /01 10/10/02 (BUNKER HILL) ASBESTOS ASSESSMENT REQUIRED 1ST & 2ND FLOOR BATHROOMS FURNISH & INSTALL EIGHT 98) WAX O-RINGS ON URINAL AND TOILETS. WATER IS CONSTANTLY ON THE FLOOR, POSING A SLIPPING/SAFETY HAZARD. CODE A- CLEAR FOR REPAIR BY CHARLES E. BUCHANAN ON 2/28/02 | December 10, 2001 | October 10, 2002 | 304 days |
| Spingarn High School | FM-200103064 6/01 10/10/02 (SPINGARN) 1ST FLOOR/BOYS BATHROOM: REPAIR OR REPLACE PARTITIONS THAT WAS DAMAGED BY FIREMAN. Asbestos Code A - Clear for Repair 2-28-01 | February 6, 2001 | October 10, 2002 | 611 days |
| Jessie LaSalle Elementary | FM-200217129 02 10/10/02 LaSalle 1st & 3rd FLoor Boys' Restrooms Replace windows that have been broken out in the boys' restrooms. | September 10, 2002 | October 10, 2002 | 30 days |
| Beers Elementary School | FM-200118369 01 10/10/02 (BEERS) ASBESTOS ASSESSMENT REQ. 2 FLOOR/ PRINCIPAL OFFICE PRINCIPAL BATHROOM WINDOW HAS EASY ACCESS FOR BREAK-IN, LOCK IS BROKEN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/26/01 LEROY MINTON - SAFETY (202) 576-6691 (RG) | August 24, 2001 | October 10, 2002 | 412 days |
| Jessie LaSalle Elementary | FM-200207262 02 10/10/02 LaSalle 2nd & 3rd Floors Toilet Spud Kits 1) Need spud rings for bathroom toilets, 2nd floor women's & girls' 2) Need spud rings in 3rd floor boys' bathroom toilets | May 7, 2002 | October 10, 2002 | 156 days |
| Beers Elementary School | FM-200206517 02 10/10/02 Beers Asbestos Assessment Reqd. Building 3, 1st Floor Boy's Restroom The partition door to the handicapped tilet has been broken off and needs to be put back on or replaced. Code A-clear for repair by Horne Engineer by ( Philip Connolly ) on 4/26/02 ( CEB ) | April 24, 2002 | October 10, 2002 | 169 days |
| Shepherd ES | FM-200218298 02 10/10/02 Shepherd Old Wing Boys' & Girls Restrooms by Office 1. Repair plumbing; and 2. Reset toilet. | September 25, 2002 | October 10, 2002 | 15 days |
| Stanton Elementary School | FM-200122419 /01 10/10/02 (STANTON) 3RD FLOOR, 2ND FLOOR AND BASEMENT CLASSROOMS #301, 307, 309, NORTH EAST STEPS #209, TEACHERS LOUNGE AND BOYS RESTROOM. REPAIR LIGHTSS AND PROVIDE COVERS FOR LIGHT FIXTURE THAT HAVE FOUR (4) TUBS. | October 25, 2001 | October 10, 2002 | 350 days |
| Wilson High School | FM-200218503 02 10/11/02 Wilson,W. 1st Floor Boys' Locker Room & Boys Restroom Near Room 142 1. Replace/repair toilet in the coach's office. The toilet does not flush properly; and 2. Repair/replace toilets in the boys' restroom near classroom 142. The toilet does not flush properly. | September 27, 2002 | October 11, 2002 | 14 days |
| Sousa Middle School | FM-200218430 02 10/11/02 Sousa 1st Floor Teachers' Restrooms/Mens' and Womens' Furnish and replace cracked and distorted windows. | September 27, 2002 | October 11, 2002 | 14 days |
| Wilson High School | FM-200218505 02 10/11/02 Wilson,W. 1st Floor Girls' Restroom Replace broken faucets in the girls' restroom. | September 27, 2002 | October 11, 2002 | 14 days |
| Tubman Elementary School | FM-200204420 02 10/15/02 (Tubman) 2nd floor/ Space 128 boys restroom Restroom door needs to be realigned with the door frame. | March 14, 2002 | October 15, 2002 | 215 days |
| Walker-Jones EC | FM-200216794 02 10/15/02 Walker-Jones ****Very Urgent**** Basement, 1st, 2nd & 3rd Floors 1. Basement: Repair or replace faulty flush valves in the girls' restroom; and repair flush valves in the open space boys' restroom; 2. 1st Floor: Repair urinal and commode in men's restroom; 3. 2nd Floor: Repair commode in teachers' restroom; repair commode and urinals in men's restroom; and 4. 3rd Floor: REpair flush valves in both girls' and boy's restrooms. | September 6, 2002 | October 15, 2002 | 39 days |
| Patricia R Harris Ed Center | FM-200217182 02 10/15/02 Harris,P.R. Teachers restroom third floor stairwell 1 area Door will not close and sticks bad. Asbestos Code A-clear for repair by DCPS Charles E Buchanan on 9/11/02 | September 10, 2002 | October 15, 2002 | 35 days |
| Woodson High School | FM-200217982 02 10/15/02 Woodson,H.D. Ladies restroom - plaza area Lock on door not working by bank. | September 20, 2002 | October 15, 2002 | 25 days |
| Bunker Hill Elementary School | FM-200118650 01 10/16/02 (BUNKER HILL) ASBESTOS ASSESSMENT REQ. UPGRADE BATHROOM REPAIR LEAK. Asbestos Code A - Clear For Repairs On 10/01/01. Horne Engineering - Edward Rodriguez (RG 03/28/02) | August 28, 2001 | October 16, 2002 | 414 days |
| Garnet-Patterson MS | FM-200206802 02 10/16/02 Basement Cafeteria/Workers Lavatory in Rear The toilet will not flush in the cafeteria worker's restroom. They are having to put water in the tank in order for the commode to flush. The seating level of the toilet is also too low to comforably accomdate adult users; it needs to be higher and larger. | April 29, 2002 | October 16, 2002 | 170 days |
| Seaton Elementary School | FM-200216171 02 10/16/02 Seaton 1) Make electrical connection to new Bradley Basin in Boys and Girls Restrooms. | August 30, 2002 | October 16, 2002 | 47 days |
| Woodson High School | FM-200219291 /02 10/16/02 Woodson, H.D. Third floor - Boys restroom Replace lock in door / broken restroom was set on fire need to secure it until it can be clean and painted. | October 11, 2002 | October 16, 2002 | 5 days |
| Leckie Elementary School | FM-200216167 02 10/16/02 Leckie 2nd Floor Boys' Restroom Urinal will not flush. | August 30, 2002 | October 16, 2002 | 47 days |
| Amidon Elementary School | FM-200121905 /01 10/16/02 (AMIDON) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM REPAIR OR REPLACE TOLIET AND FLANG. TOILET IS BROKEN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/20/01. RICHARD E GIBSON - SAFETY (202)576-5584 (RG) | October 18, 2001 | October 16, 2002 | 363 days |
| Wilkinson ES | FM-200218920 02 10/17/02 Wilkinson - T-5 First floor - room 90 girl bathroom Pre area Replace it in center set faucet for pre-k student area. Need to unstop commode in house try. | October 7, 2002 | October 17, 2002 | 10 days |
| Hart Middle School | FM-200218731 02 10/20/02 Hart Old Building - First Floor Boys Bathroom 1) 1st, 3rd and 4th stall reanchor commode. 2) 5th urinal needs handle kit. 3) 2nd urinal handle kit vaccum breaker diaphram. | October 2, 2002 | October 20, 2002 | 18 days |
| Sousa Middle School | FM-200217836 02 10/21/02 (Sousa) Fire code violation: Page 4 of 6 1st Floor/Teachers restroom: Exposed wiring improper fixture. | September 18, 2002 | October 21, 2002 | 33 days |
| Hart Middle School | FM-200218735 02 10/21/02 Hart Old Building - First Floor - Girls Bathroom 1) 1st and 3rd stall replace flush valve. 2) 5th stall replace vaccum breaker. 3) 6th stall reanchor commode. 4) 1st thru 4th lavatory sink remove stoppage. | October 2, 2002 | October 21, 2002 | 19 days |
| Whittier Elementary School | FM-200219637 /02 10/22/02 Whitter Tunnel Area- Boiler room Check 3/4" steam line leaking ,black iron pipe. Steam is going to girls bathroom. EMERGENCY!!!!! | October 18, 2002 | October 22, 2002 | 4 days |
| Tubman Elementary School | FM-200219602 /02 10/22/02 Tubman First Floor - Teachers Lounge Bathroom Ladies 1) Toilets leaking at bottom in both stalls. Please replace wax ring, water is leaking around commode very fast. See Mr. Quintus for exact location | October 17, 2002 | October 22, 2002 | 5 days |
| Savoy Elementary School | FM-200219346 /02 10/24/02 (Savoy) Health Code violation: Kitchen/Bathroom sink: Faucets continues to leak on hot water side. They have been repaired on a regular basis to the point where no longer can be repaired. Inspectors have failed the kitchen for inspection; needs new faucets. | October 11, 2002 | October 24, 2002 | 13 days |
| Hart Middle School | FM-200218729 02 10/24/02 Hart Second floor - New Wing - Girls Bathroom 1) 4th stall reanchor commode. 2) 5th stall reanchor commode 3) 7th stall reanchor commode tighten spud. 4) 8th and 10th stall clear stoppage and replace flush valve. | October 2, 2002 | October 24, 2002 | 22 days |
| Simon Elementary School | FM-200218736 02 10/24/02 (Simon) 1st Floor/Boys and girls restroom: Commodes needs replacement in boys (1), and girls need (1). Bowl is cracked, and water runs when on, also, flush valves need repairs on some urinals and commodes. | October 2, 2002 | October 24, 2002 | 22 days |
| Anacostia Senior High School | FM-200219989 /02 10/25/02 (Anacostia) 1st Floor/Gym area: Students kicked window out in the boys restroom. (Window size - 28" x 42") | October 24, 2002 | October 25, 2002 | 1 day |
| Nalle Elementary School | FM-200216089 02 10/28/02 (Nalle) 1. Asbestos assessment required. Urgent!! Replace toilets in girls'bathrooms and urinals in boy' bathrooms on first and second floors old wing. The toilets and urinals are constantly leaking causing a severe health and safety hazard. Repair exhaust fans on the roof. There is no ventilation in any of the rest rooms. The exhaust fans do not work. This situation compounds the existing health hazard created by the leaking toilets and urinals. Account #: 288 Asbestos Code A - Clear for repairs on 10/25/02. DCPS-Safety - Leroy Minton Jr. (RG 10/28/02) | July 30, 2002 | October 28, 2002 | 90 days |
| Whittier Elementary School | FM-200218380 02 10/29/02 (WHITTIER) 1. Asbestos Assessment Reqd. 1st-Floor Boys' Restroom/Old Wing 2. Replace cracked toilet. Toilet is cracked at the top, but is leaking from the bottom. POC: Mr. Lewis Asbestos Code A - Clear for repairs, on 7/25/02 DCPS Safety - L. Minton (RE-7/25/02) | September 26, 2002 | October 29, 2002 | 33 days |
| Wilson High School | FM-200202251 02 10/29/02 WILSON, W. HEALTH CODE !!! URGENT REQUEST !!! GYMNASIUM, FIRST, SECOND AND THIRD FLOOR REPAIR/REPLACEE BROKEN AND MISSING FAUCETS IN THE FOLLOWING LOCATIONS: BOYS BATHROOM: GYM AREA (2) FAUCETS 1ST FLOOR (3) FAUCETS 2ND FLOOR (2) FAUCETS 3RD FLOOR (2) FAUCETS GIRLS BATHROOM: GYM AREA (2) FAUCETS STUDENTS UNABLE TO WASH HANDS. | January 31, 2002 | October 29, 2002 | 271 days |
| Barnard Elementary School | FM-200217879 02 10/29/02 Barnard New Building, second floor Girls & boys Bathroom One toiletr stopped up also one urinal. | September 19, 2002 | October 29, 2002 | 40 days |
| Barnard Elementary School | FM-200217968 02 10/29/02 Barnard 1st Floor Girls' Restroom/Old Wing The #2, 16, 17 & 19 toilets are stopped up with debris. | September 20, 2002 | October 29, 2002 | 39 days |
| Barnard Elementary School | FM-200217970 02 10/29/02 Barnard 1st Floor Girls' Restroom/Old Wing The #6 toilet is leaking from the handle; #10 is leaking from the tailpipe with water shooting out. | September 20, 2002 | October 29, 2002 | 39 days |
| Whittier Elementary School | FM-200218362 02 10/31/02 Whittier Throughout Building Replace four (4) toilets in the boys' and girls' restrooms throughout the building. | September 26, 2002 | October 31, 2002 | 35 days |
| Stevens Elementary School | FM-200214328 02 10/31/02 Stevens Basement/Girls' Restroom 1. Toilet will not flush/shut-off valve needs to be replaced; 2. Basement near girls' restroom, slop sink is stopped up and attempts to unstop it have been unsuccessful; and 3. Pipe feeding water to commodes is leaking and needs repair. POC: Mr. Taylor | August 14, 2002 | October 31, 2002 | 78 days |
| Brent Elementary School | FM-200202435 02 10/31/02 (BRENT) 3RD FLOOR/BOYS RESTROOM: A TOTAL OF TWO (2) URINALS LEAKING FROM BASE OF COMMODE; NEED A WAX RING. Code A-clear for repair by Honre Engineer ( Troy Wilcome ) on 4/05/02 | February 5, 2002 | October 31, 2002 | 268 days |
| Ballou Senior High School | FM-200217025 02 10/31/02 Ballou ****Urgent**** 1st & 2nd Floor Boy's Restrooms Repair badly leaking toilets in 2nd floor boys' restsroom, which are leaking into the 1st floor restroom, damaging the ceiling tiles in the 1st floor boys' restroom. | September 9, 2002 | October 31, 2002 | 52 days |
| Macfarland Middle School | FM-200206235 02 10/31/02 MacFarland Third (3rd) Floor - Boys Restroom Repair wastline in floor under urinals in the boys Restroom the wastline is leaking down into bathroom below it. Code A-clear for repair by Horne Engineer by ( Bipin Nanavaty ) on 4/24/02 ( CEB ) | April 22, 2002 | October 31, 2002 | 192 days |
| Brightwood Elementary School | FM-200217636 02 10/31/02 Brightwood ****Urgent**** 1st Floor Boys' Restroom Three (3) urinals are clogged in the boys' restroom. It is urgent the urinals are unclogged as there are no other restrooms on any other floor for male students in this old facility. | September 17, 2002 | October 31, 2002 | 44 days |
| Johnson JHS | FM-200214985 02 10/31/02 Johnson 1st Floor Girls' Restroom near Auditorium 1. Unstop drain; and 2. Replace faulty faucet. | August 19, 2002 | October 31, 2002 | 73 days |
| Johnson JHS | FM-200216337 02 10/31/02 Johnson 3rd FLoor Female Teachers' Restroom The hand basin is clogged and needs clearing. | September 3, 2002 | October 31, 2002 | 58 days |
| Johnson JHS | FM-200217146 02 10/31/02 Johnson Various Areas Repair plumbing fixtures in the boys' & girls' restroom in the main building throughout. Alos check out the 4th floor girls' restroom. | September 10, 2002 | October 31, 2002 | 51 days |
| Wilkinson ES | FM-200218486 02 10/31/02 (Wilkinson) This is a very !!!URGENT!!! request. 2nd Floor/Womens bathroom: Repair or replace flush, and cut off valves; water continues to run full force. | September 27, 2002 | October 31, 2002 | 34 days |
| Hendley Elementary School | FM-200218493 02 10/31/02 (Hendley) !!!EMERGENCY!!! Basement/Girls restroom next to cafeteria: "Hot water" from sink faucets is flooding the floors; cut off valves are not working and the hot water cannot be shut off. | September 27, 2002 | October 31, 2002 | 34 days |
| Lincoln Middle School | FM-200219422 /02 10/31/02 (Lincoln/Taft) First Floor - Boys bathroom: All urinals are stopped up. | October 15, 2002 | October 31, 2002 | 16 days |
| Whittier Elementary School | FM-200212664 02 10/31/02 (WHITTIER) Girls' Restroom/Old Side Replace control-stop valve to prevent water from leaking from the base of toilet [previous repair did not hold]. | July 23, 2002 | October 31, 2002 | 100 days |
| Green Elementary School | FM-200213992 02 10/31/02 Green ****Urgent**** 2nd & 3rd Floor Boys' and Girls' Restrooms 1. Repair two urinals in the 3rd floor boys' restroom, and snake out 3 toilets in area #314/3rd floor boys' restroom; 2. Snake out 2 urinals in the 2nd floor boys' restroom, and snake out three toilets in the 2nd floor girls' [space 211] girls' restroom; and 3. Repair one urinal in the 1st floor boys' restroom on the lobby level. | August 9, 2002 | October 31, 2002 | 83 days |
| Stevens Elementary School | FM-200216243 02 11/1/02 Stevens 1. Asbestos Assessment Reqd. 2nd Floor Teachers' Lounge 2. 2" line is cracked and leaking through and into the 1st floor restroom below--needs repair. Asbestos Code A-clear for repair by Horne Engineer Edward Rodriguez On 9/05/02 DCPS Charles E. Buchanan | August 30, 2002 | November 1, 2002 | 63 days |
| Shaw JHS | FM-200218540 02 11/1/02 Shaw Urgent!! First Floor- Breezeway ( closet) 1) The breaker is out, their are no lights in the Girls and Boys Bathroom on the First Floor. | September 30, 2002 | November 1, 2002 | 32 days |
| School WW High School | FM-200218401 02 11/1/02 School Without Walls ****Urgent**** Basement Girls' Restroom Three commodes are stopped up. Maintenance staff was unable to clear the commodes---need to be cleared with longer snake. | September 26, 2002 | November 1, 2002 | 36 days |
| Birney Elementary School | FM-200216271 02 11/1/02 Birney 2nd Floor Girls' & Boys' Restrooms 1. Girls' & boys' restroom in the new wing needs the circuit breaker replaced; and replace non-working lights; and 2. The light on exit 5 stairway near the 2nd floor landing need to be replaced or repaired. POC: Robert Gillespie | August 30, 2002 | November 1, 2002 | 63 days |
| Ludlow-Taylor ES | FM-200207732 02 11/3/02 Ludlow-Taylor Third (3rd) Floor - Boys' Restroom 1. Asbestos Assessment Required. 2. Water is backing up and leaking down from the third (3rd) floor thru Ceiling. Ceiling needs to be repair/replace. Safety Hazard. Code A - Asbestos abated on 06/17/02 PER: Leroy Minton Jr. comfirmation. (RG 06/19/02) | May 14, 2002 | November 3, 2002 | 173 days |
| Rudolph Elementary School | FM-200220769 /02 11/13/02 Rudolph Kitchen/Cafeteria 1) Lavatory bathroom sink water pressure is to low. Week of 11/4-11/8 - FM-200220691 | November 13, 2002 | November 13, 2002 | 0 days |
| Harris, C.W. ES | FM-200220644 /02 11/13/02 Harris, C.W. First floor - Girls bathroom Sink is broken off bracket. Week of 11/4/02-11/08/02 FM-200220881 Asbestos Code A-clear for repair by Charles Buchanan on 11/12/02 DCPS Charles E Buchanan | November 12, 2002 | November 13, 2002 | 1 day |
| Sousa Middle School | FM-200220503 02 11/13/02 Sousa Ladies teacher restroom first floor Furnish and replace lock on door with extra keys for teachers. Teachers can not open doors. We have only one key and its a master key to the entire building or make keys for lock that we already have. Principal needs master key for new locks which was put in building. | November 1, 2002 | November 13, 2002 | 12 days |
| Browne Junior High School | FM-200220597 02 11/13/02 Browne Kitchen Restroom Repair approximately 1" inch. leaking line in women's restroom heating (return condensate line) has insulation and needs to be checked for asbestos in return line Asbestos Code A - Clear for Repairs on 11/05/02 Horne Engineering - Sheryll James ( RG 11/07/02) | November 1, 2002 | November 13, 2002 | 12 days |
| Davis Elementary School | FM-200215524 02 11/14/02 Davis F-608.1 Fire Code Violation Asbestos Assessment Reqd. Basement Teachers' Restroom/New Wing Need door adjustment. Asbestos Code A - Clear for repairs on 08/27/02. DCPS Safety - Leory Minton Jr. (RG 08/27/02) | August 23, 2002 | November 14, 2002 | 83 days |
| Cooke H.D. Elementary School | FM-200212288 02 11/14/02 Cooke,H.D. Basement Boys' & Girls' Restroom 1. Toilet in the boys' restroom needs to be unclogged; 2. Last toilet/left-hand side of girl's restroom will not flush. | July 16, 2002 | November 14, 2002 | 121 days |
| Malcolm X ES | FM-200216249 02 11/15/02 (Malcolm X) Fire code violation: 1. Asbestos assessment required: Kindergarten bathroom: Door closer broken on door | August 30, 2002 | November 15, 2002 | 77 days |
| Garfield ES | FM-200215486 02 11/15/02 Garfield F-608.1 Fire Code Violation Asbestos Assessment Reqd. Lower Level Main Building/Boys' Restroom Door needs adjustment. Asbestos Code A - Clear for repairs on 08/26/02. DCPS Safety - Leroy Minton Jr. (RG 08/27/02) | August 23, 2002 | November 15, 2002 | 84 days |
| Moten Elementary School | FM-200216932 02 11/15/02 Moten F-110.1 Fire Code Violation Asbestos Assessment Reqd. 1st Floor Hallway Girls' Bathroom/New Wing Ceiling falling in. Asbestos Code A - Clear for repairs on 09/09/02. Horne Engineering - Sheryll James (RG 09/10/02) | September 9, 2002 | November 15, 2002 | 67 days |
| Garnet-Patterson MS | FM-200121808 /01 11/15/02 (GARNET-PATTERSON) ASBESTOS ASSESSMENT REQ. AUDITORIUM/ BATHROOM LIGHT SWITCHES ARE NOT WORKING. NO LIGHT IN THE BATHROOM. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-16-01 HORNE ENGINEER: BILL CAMPION | October 17, 2001 | November 15, 2002 | 394 days |
| Moten Elementary School | FM-200216865 02 11/15/02 Moten F-110.1 Fire Code Violation Asbestos Assessment Reqd. 3rd Floor Boys' Restroom Across From Elevator Missing ceiling tile. Asbestos Code A - Clear for repairs on 09/16/02. DCPS Safety - Leroy Minton Jr. (RG 09/17/02) | September 6, 2002 | November 15, 2002 | 70 days |
| Moten Elementary School | FM-200216863 02 11/15/02 Moten F-110.1 Fire Code Violation Asbestos Assessment Reqd. 3rd Floor Girls' Restroom Across From Room 321 Missing ceiling tile. Asbestos Code A - Clear for repairs on 09/16/02. DCPS Safety - Leroy Minton Jr. (RG 09/17/02) | September 6, 2002 | November 15, 2002 | 70 days |
| Moten Elementary School | FM-200216826 02 11/15/02 Moten F-303.4 Fire Code Violation Asbestos Assessment Reqd. Ground Floor Boys' Restroom Door sticks. Asbestos Code A - Clear for repairs on 09/16/02. DCPS Safety - Leroy Minton Jr. (RG 09/17/02) | September 6, 2002 | November 15, 2002 | 70 days |
| Peabody Elementary School | FM-200217644 02 11/15/02 (Peabody) !!!URGENT!!! Basement/Girls and boys bathroom: Faucets on sinks are inoperable, no water available. | September 17, 2002 | November 15, 2002 | 59 days |
| Eastern High School | FM-200221005 /02 11/15/02 Eastern Stadium - Girls Restroom 1) Replace restroom lock , door can not be opened.. ( Football Playoffs ) | November 14, 2002 | November 15, 2002 | 1 day |
| Sousa Middle School | FM-200205862 02 11/15/02 Sousa 3rd Floor Boys & Girls Restrooms 1) Two toilets in the girls restroom from the window on the right side are stopped up. 2) A urinal in the boys restroom needs a wax ring. The toilet will not go down. Two toilets needs a wax ring. 3) The teachers lounge toilet is stopped up. | April 16, 2002 | November 15, 2002 | 213 days |
| Winston EC | FM-200215665 02 11/15/02 Winston F-608.1 Fire Code Violation Asbestos Assessment Reqd. 3rd Floor Kindergarten Girls' Restroom Door out of alignment. Asbestos Code A - Clear for repairs on 08/28/01. DCPS Safety - Leroy Minton Jr. (RG 08/28/02) | August 27, 2002 | November 15, 2002 | 80 days |
| Cooke H.D. Elementary School | FM-200212292 02 11/15/02 Cooke,H.D. 3rd Floor Principal's Restroom & 3rd Floor [Bldg. 2] Boys' Restroom 1. Toilet in principal's restroom needs unclogging; and 2. Shut-off valve on the 2nd urinal in the boys' restroom [bldg. 2] needs to be replaced. | July 16, 2002 | November 15, 2002 | 122 days |
| Davis Elementary School | FM-200215537 02 11/15/02 Davis F-608.1 Fire Code Violation Asbestos Assessment Reqd. Corridor Door by Main Lobby Restrooms Door needs adjustment. Asbestos Code A - Clear for repairs on 08/27/02. DCPS Safety - Leory Minton Jr. (RG 08/27/02) | August 23, 2002 | November 15, 2002 | 84 days |
| Davis Elementary School | FM-200215536 02 11/15/02 Davis F-608.1 Fire Code Violation Asbestos Assessment Reqd. 1st Floor Old Wing Room 105 [Restroom] Door needs adjustment. Asbestos Code A - Clear for repairs on 08/27/02. DCPS Safety - Leory Minton Jr. (RG 08/27/02) | August 23, 2002 | November 15, 2002 | 84 days |
| Eastern High School | FM-200221052 /02 11/17/02 Eastern Stadium - Restroom 1) Paint entrance doors to girls restrooms. | November 15, 2002 | November 17, 2002 | 2 days |
| Patricia R Harris Ed Center | FM-200221157 /02 11/18/02 Harris, P.R. Ground floor - Girl restroom at # 8 stairwell Toilets will not flush, all of them backed up and ron over. Please respond!!!! | November 18, 2002 | November 18, 2002 | 0 days |
| Thomas Elementary School | FM-200221200 /02 11/19/02 Thomas Second floor - Boys and girls restroom Survey and replace brackets to hold privacy partition door to the wall and unstop toilet in girls restroom. | November 18, 2002 | November 19, 2002 | 1 day |
| Cleveland Elementary School | FM-200221148 /02 11/19/02 Cleveland First and second floor - boys restrooms Install spring or bradley basins and adjust so they may cut off automatic. | November 18, 2002 | November 19, 2002 | 1 day |
| Wilson J. O. ES | FM-200221373 /02 11/20/02 Wilson, J.O. First floor girls room Repair faucets on sink. | November 20, 2002 | November 20, 2002 | 0 days |
| Wilson J. O. ES | FM-200220081 /02 11/20/02 (Wilson, J.O.) Old side/1st Floor: Repair or replace (2) cylinders to boys and girls restroom doors. Note: Request that door cylinders be keyed to new system for security reasons. Asbestos Code A - Clear for repairs on 10/28/02. DCPS Safety - Leroy Minton Jr. (RG 10/29/02) | October 25, 2002 | November 20, 2002 | 26 days |
| Montgomery ES | FM-200221288 /02 11/20/02 (Montgomery) !!!VERY URGENT!!! 1st Floor/Boys restroom: Replace flush valves; engineer does not have the proper tools to remove the old equipment. (Please assist.) | November 19, 2002 | November 20, 2002 | 1 day |
| Ronald H. Brown MS | FM-200221336 /02 11/21/02 Brown, Ron (Roper) First floor - Boys restroom First urinals not working will not flush. Need new flush valves. | November 19, 2002 | November 21, 2002 | 2 days |
| Barnard Elementary School | FM-200221293 /02 11/21/02 Barnard First floor new bldg. girls bathroom Replace flush valve assembly. | November 19, 2002 | November 21, 2002 | 2 days |
| Montgomery ES | FM-200104084 01 11/21/02 S. MONTGOMERY SECOND (2ND) FLOOR - LEARNING CENTER #2 BOYS AND GIRLS RESTROOMS REPAIR/REPLACE BRADLY BASENT (NO WATER) | February 21, 2001 | November 21, 2002 | 638 days |
| Park View ES | FM-200202811 02 11/22/02 (PARK VIEW) ***EMERGENCY*** 1ST FLOOR RESTROOM IN HALLWAY OUTSIDE KITCHEN; IN THE KITCHEN & TEACHERS LOUNGE URINALS/COMMODES ARE NOT WORKING & ARE BACKED UP IN THE HALLWAY OUTSIDE THE KITCHEN, KITCHEN, AND TEACHERS LOUNGE, SENDING WATER INTO THE BASEMENT BELOW IN SPITE OF SNAKING & PLUNGING. HAVE TOPPED OFF THE PROBLEM AREAS TO PREVENT FURTHER SPILLAGE [THE ONLY DRAIN LINE IS IN THE KITCHEN]. | February 11, 2002 | November 22, 2002 | 284 days |
| Clark Elementary School | FM-200210331 02 11/22/02 Clark EMPLOYEES RESTROOM REQUIRE SELF CLOSING DOOR. | June 17, 2002 | November 22, 2002 | 158 days |
| Ferebee-Hope Elementary School | FM-200214575 02 11/25/02 Ferebee-Hope F-110.1(1) Fire Code Violation 1. Asbestos Assessment Reqd. 3rd Floor Boys' Bathroom 2. Ceiling tiles need replacement. AsbestosCode A-clear for repair by Horne Engineer ( Troy Welcome ) Charles Buchanan on 8/19/02 | August 15, 2002 | November 25, 2002 | 102 days |
| Winston EC | FM-200221501 /02 11/25/02 Winston First floor - room 129 Remove key broken off in knob - teachers bathroom. | November 21, 2002 | November 25, 2002 | 4 days |
| Aiton Elementary School | FM-200118566 01 11/25/02 (AITON) 4TH FLOOR/BOYS RESTROOM CONVECTOR FRAME NEEDS TO BE REPLACED IN RESTROOM. POC CARNAL BRADLEY 202-438 7437 CELL PHONE ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/28/01. HORNE ENGINEERING - ROGER KAGER (RG) | August 28, 2001 | November 25, 2002 | 454 days |
| Park View ES | FM-200221707 /02 11/26/02 (Parkview) !!!VERY URGENT!!! 1st Floor/Across from room #113: Girls bathroom stopped up and flooding the floors, engineers and staff are mopping up the water. This is a continuation of a previous problem. Also, the trap needs to be replaced on the sink in the Headstart room. | November 26, 2002 | November 26, 2002 | 0 days |
| Eastern High School | FM-200218635 02 12/2/02 Eastern Ground floor - Locker room Install one bathroom stall door (door in bathroom). | October 1, 2002 | December 2, 2002 | 62 days |
| Hine JHS | FM-200221004 /02 12/2/02 (Hines) !!!VERY URGENT!!! 2nd Floor/Rec. Area: Busted supply line on toilet in the girls restroom; room flooded. | November 14, 2002 | December 2, 2002 | 18 days |
| Eastern High School | FM-200209377 02 12/2/02 (Eastern) !!!!Very Very Urgent!!!! 1. Asbestos assessment required. Across from Room #222: Bathroom door has come completely off hinges; student was almost struck by door. Stafff was advised to take door down until repair personnel arrives. Asbestos Code A - Clear for repairs on 06/13/02. DCPS Safety - Leroy Minton Jr. (RG 06/14/02) | June 12, 2002 | December 2, 2002 | 173 days |
| Young Elementary School | FM-200221061 /02 12/4/02 Young First floor Need plumber to unstop two toilets in the kindergarten area. Unstop one toilet in the teacher's bathroom and one toilet in girls bathroom that are stopped up next to each other. Tried on site to unstop them but could not. | November 15, 2002 | December 4, 2002 | 19 days |
| Savoy Elementary School | FM-200219794 /02 12/4/02 (Savoy) Health Code violation: Kitchen/Bathroom: Commode in ladies room is not working in kitchen for employees. | October 22, 2002 | December 4, 2002 | 43 days |
| Emery Elementary School | FM-200123053 01 12/4/02 (EMERY) 2ND FLOOR/ BOYS BATHROOM 1 ONE URINAL NEEDS A WAX RING. 2 TWO NEED TO BE REHUNG ONTO THE WALL. | November 7, 2001 | December 4, 2002 | 392 days |
| Savoy Elementary School | FM-200219647 /02 12/4/02 (Savoy) Replace old and worn faucets in kitchen restroom; hot water side constantly | October 18, 2002 | December 4, 2002 | 47 days |
| Merritt Middle School | FM-200221567 /02 12/4/02 Merritt First Floor - Pre-Kindergarten 1) Repair or replace handle assembly on first toilet in bathroom. 2) Replace trap on first sink in bathroom. | November 22, 2002 | December 4, 2002 | 12 days |
| Savoy Elementary School | FM-200219792 /02 12/4/02 (Savoy) Health Code violation: Kitchen/Bathroom: No hot water at hand sink in restroom. | October 22, 2002 | December 4, 2002 | 43 days |
| Duke Ellington School | FM-200221444 /02 12/5/02 Ellington, Duke Basement - girls restroom Sink is broken need repair. | November 20, 2002 | December 5, 2002 | 15 days |
| Hine JHS | FM-200206226 02 12/5/02 Hine 1. First (1st) Floor - Girls Restroom Hand Sink fixture. Not working Hot water side. Compression Type fixtures. 2. Second (2nd) Floor - Girls Restroom Replace Toilet Flanges. | April 22, 2002 | December 5, 2002 | 227 days |
| Hendley Elementary School | FM-200221578 /02 12/5/02 Hendley Basement - Teachers Bathroom 1) Water coming from the bottom of the toilet. | November 25, 2002 | December 5, 2002 | 10 days |
| Johnson JHS | FM-200221392 /02 12/5/02 Johnson First floor boys bathroom near 106 Commodes need to be unstop. | November 20, 2002 | December 5, 2002 | 15 days |
| Gage-Eckington ES | FM-200218506 02 12/5/02 Gage-Eckington 1st Floor Boys' Restroom Replace flush valve. | September 27, 2002 | December 5, 2002 | 69 days |
| Slowe Elementary School | FM-200220457 /02 12/5/02 (Slowe) !!VERY URGENT!! 1st Floor/Boys and girls bathroom: Sewage pipe busted; bad smell everywhere. | October 31, 2002 | December 5, 2002 | 35 days |
| Roosevelt High School | FM-200221820 02 12/5/02 Roosevelt Basement - Ladies Restroom - Kitchen Area 1) Water is backing up out of toilets and drains. | December 2, 2002 | December 5, 2002 | 3 days |
| Gage-Eckington ES | FM-200220675 /02 12/5/02 Gage-Eckington First floor - Itermediate Unclog commode in girl's restroom. | November 12, 2002 | December 5, 2002 | 23 days |
| Eastern High School | FM-200221007 /02 12/5/02 Eastern Girls Restroom - Stadium 1) Repair light fixtures one inside and one outside. Football Playoffs. | November 14, 2002 | December 5, 2002 | 21 days |
| Stuart-Hobson Middle School | FM-200222015 02 12/5/02 Stuart Hobson First Floor - Girls Bathroom 1) Replace flush value,had to cut water off valve not holding. | December 4, 2002 | December 5, 2002 | 1 day |
| Woodson High School | FM-200220359 /02 12/5/02 Woodson H. D. Third Floor - Boys Bathroom, 316 1) There are no lights in the above aras. Circuit breaker may be blown, sparks are coming from switch. 2) Cafeteria - one half of the lights are out over the serving line in the kitchen. | October 31, 2002 | December 5, 2002 | 35 days |
| Watkins Elementary School | FM-200219960 /02 12/5/02 Watkins First floor Girls Bathroom toilet, no water coming into first stall toilet stool. Toilets stool need snake to unstop two (2). Asbestos Code A - Clear for repairs on 10/25/02. DCPS-Safety - Leroy Minton Jr. (RG 10/28/02) | October 24, 2002 | December 5, 2002 | 42 days |
| Watkins Elementary School | FM-200219964 /02 12/5/02 Watkins First floor - Boys First floor boys bathroom last stall toilet stopped up need snaking. | October 24, 2002 | December 5, 2002 | 42 days |
| Ross Elementary School | FM-200222127 02 12/6/02 Ross Girls Restroom Asbestos Assestment Required Repair 1/2" leaking nipple on steam line in girls restroom located in basement. Asbestos Code A-clear for repair by Horne Engineer Edward Rodriguez on 12/19/02 Charles E. Buchanan | December 5, 2002 | December 6, 2002 | 1 day |
| Gage-Eckington ES | FM-200103890 2/20/01 12/9/02 GAGE-ECKINGTON FIRST (1ST) FLOOR - PRIMARY GIRLS & BOYS BATHROOM 1) ASBESTOS ASSESSMENT REQUIRED 2) REPAIR/REPLACE FORMICA ON SINK COUNTER-TOPS. FORMICA IS BEGINNING TO POP UP AND WOOD IS FLAKING ON FLOOR. Asbestos Code A - Clear for Repair | February 20, 2001 | December 9, 2002 | 657 days |
| Moten Elementary School | FM-200221998 02 12/9/02 Moten Fourth floor - boys bathroom old side A window need to be repair or put plexiglass over it, it is broken. | December 3, 2002 | December 9, 2002 | 6 days |
| Whittier Elementary School | FM-200218334 02 12/9/02 (Whittier) ****Urgent**** 2nd Floor Principal's Office/Old Wing There is no water working in the principal's restroom. POC: Mr. Lewis | September 25, 2002 | December 9, 2002 | 75 days |
| Shaed Elementary School | FM-200221296 /02 12/10/02 Shaed First Floor - Boys Bathroom Ceiling. Asbestos assessment required Repair ruptured return and or supply line the ceiling unit heater , there are no isolation valves on the unit. Asbestos Code A-clear for repair by Horne Engineer Bipin Nanvaty DCPS Safety on 11/21/02 Charles E. Buchanan | November 19, 2002 | December 10, 2002 | 21 days |
| Wilkinson ES | FM-200215965 02 12/10/02 Wilkinson F-110.3 Fire code violation: First floor - Women restroom in lavatory area Hole in ceiling (possible water leak). Asbestos Code A - Clear for repairs on 08/29/02. Honre Engineering - Sam Ebrahim (RG 08/30/02) | August 28, 2002 | December 10, 2002 | 104 days |
| Ludlow-Taylor ES | FM-200222041 02 12/10/02 Ludlow Taylor Second Floor - Boys Bathroom 1) Install lock on new bathroom door. | December 4, 2002 | December 10, 2002 | 6 days |
| Birney Elementary School | FM-200220972 /02 12/16/02 (Birney) !!!URGENT!!! New wing, Basement/Boys bathroom: Busted pipe near vent, dripping hot water. Asbestos Code A-clear for repair by Horne Engineer Troy Wilcome on 11/15/02 DCPS Charles E. Buchanan | November 14, 2002 | December 16, 2002 | 32 days |
| Hine JHS | FM-200214026 02 12/16/02 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. 2nd Floor/Girls bathroom: Hole in ceiling. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | December 16, 2002 | 126 days |
| Hine JHS | FM-200214024 02 12/16/02 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. 2nd Floor/Boys bathroom door: Door is warped. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | December 16, 2002 | 126 days |
| Hine JHS | FM-200213955 02 12/16/02 (Hine) Fire code violation: 1. Asbestos assessment required. 1st floor/Girls bathroom: Door not latching. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 9, 2002 | December 16, 2002 | 129 days |
| Davis Elementary School | FM-200215546 02 12/16/02 Davis F-608.5 Fire Code Violation Asbestos Assessment Reqd. Cafeteria Exit Door by Boys' Restroom Needs adjustment. Asbestos Code A - Clear for repairs on 08/27/02. DCPS Safety - Leory Minton Jr. (RG 08/27/02) | August 23, 2002 | December 16, 2002 | 115 days |
| Ross Elementary School | FM-200221449 /02 12/18/02 Ross Basement 1.) A pipe that leaks from the sink that is in the cafeteria, next to the boys bathroom in the basement, need to be repaired. Safety hazard 2.) Room 103 - Pre-Kgn - The cold water knob is broken, need to be fixed or replaced. 3) Toilet need to be adjusted, because they are continuosly flushing. | November 20, 2002 | December 18, 2002 | 28 days |
| Deal Junior High School | FM-200218527 02 1/2/03 Deal Asbestos Assessment Reqd. Basement Girls' Restroom Replace broken sink that had fallen off the wall. The remaining sink cannot be used because of the joined drains. Asbestos Code A - Clear for repairs on 09/30/02. Horne Engineering - Troy Wilcome ( RG 10/01/02) | September 27, 2002 | January 2, 2003 | 97 days |
| Davis Elementary School | FM-200222986 /02 1/3/03 Davis Ground Replace broken urinal in boys room. | December 20, 2002 | January 3, 2003 | 14 days |
| Garnet-Patterson MS | FM-200223421 03 1/9/03 (Garnet-Patterson) Basement restroom: Install lavatory partitions in basement restroom, also, install handicap rails in stall. Permit issued to survey only !! ( 1/2/03) J. Eggleston Asbestos Code A-clear for repair by DCPS Safety Charles Buchanan 01/06/03 | January 2, 2003 | January 9, 2003 | 7 days |
| Watkins Elementary School | FM-200222897 /02 1/9/03 Watkins Replace two toilets on ground floor, boys and girls room. | December 20, 2002 | January 9, 2003 | 20 days |
| Randle-Highlands ES | FM-200223678 03 1/10/03 (Randle-Highlands) !!!EMERGENCY!!! Ground Floor/Kitchen restroom: A very foul odor coming from grease trap in the brand new school building. | January 9, 2003 | January 10, 2003 | 1 day |
| Beers Elementary School | FM-200207792 02 1/13/03 Beers 1st Floor Building 2 Replace the cracked bowl in the 1st floor girls' restroom. | May 15, 2002 | January 13, 2003 | 243 days |
| Gibbs Elementary School | FM-200223923 03 1/14/03 Gibbs Second Floor - Boys Bathroom 1) Unstop and repair (2) toilets and (2) flush valves on toilets. | January 14, 2003 | January 14, 2003 | 0 days |
| Kramer Middle School | FM-200208606 02 1/14/03 Kramer 1. Asbestos Assessment Reqd. 2nd Floor Girls Restroom 2. Repair the 19 1/2"x30" hole in the wall under the basin in the 2nd-floor girls' restroom. Asbestos Code A - Clear for repairs on 05/29/02. Horne Engineering - Sheryll James (RG) | May 29, 2002 | January 14, 2003 | 230 days |
| Miner Elementary | FM-200223834 03 1/14/03 (Miner) !!!VERY URGENT!!! 2nd Floor/Boys bathroom: Ruptured water line on sink; line was capped off and broke. | January 13, 2003 | January 14, 2003 | 1 day |
| Woodson High School | FM-200223892 03 1/14/03 Woodson SHS Ground Floor and 4th floor 1) Ground Floor - Kitchen - Service sink leaking in (2) different places. 2) 4th floor - Boys restroom commode is stopped up. | January 14, 2003 | January 14, 2003 | 0 days |
| Wilkinson ES | FM-200218040 02 1/14/03 Wilkinson 2nd Floor Room 184 Unclog commode in girls' restroom---staff tried and had no success. POC: E. Butler | September 20, 2002 | January 14, 2003 | 116 days |
| Stanton Elementary School | FM-200222326 /02 1/14/03 Stanton Third floor - girls bathroom Sink continues to leak. | December 10, 2002 | January 14, 2003 | 35 days |
| Duke Ellington School | FM-200114094 01 1/15/03 ELLINGTON FIRST (1ST) FLOOR 1) SINK STOPPED-UP. SECOND (2ND) FLOOR BY GIRLS RESTROOM 2) SINK STOPPED-UP. REAR HALLWAY- BOYS RESTROOM 3) SINK STOPPED-UP. BOTH SINK IN BACK HALLWAY 4) SINKS STOPPED-UP. ISOLATE EMERGENCY!!! | June 26, 2001 | January 15, 2003 | 568 days |
| Bunker Hill Elementary School | FM-200223889 03 1/15/03 Bunker Hill Emergency !!! First Floor - East Wing Girls Restroom 1) Repair sink that was knocked off wall and repair copper pipe. | January 14, 2003 | January 15, 2003 | 1 day |
| Terrell Mc ES | FM-200223870 03 1/16/03 Terrell, M. C. Water Cooler Replacement 1) First Floor near Boys and Girls Restroom (1). 2) 3rd floor corridor replace (2). 3) 2nd floor corridor replace (1). | January 13, 2003 | January 16, 2003 | 3 days |
| Davis Elementary School | FM-200217062 02 1/16/03 Davis First and second floor -- Room 115, Girl bathroom beside 218 Unstop sink in room 115 and toilet by sink in girls bathroom second floor. Could not unstop with snake and plunger thats on site need K50. | September 9, 2002 | January 16, 2003 | 129 days |
| Sousa Middle School | FM-200217715 02 1/17/03 (Sousa) Fire code violation: Page 1 of 6 Basement/Boys bathroom:l Hole in ceiling, paint peeling off. Asbesstos/Lead Code A-clear for repair by Horne Engineer Edward Rodriguez DCPS Charles E. Buchanan on 9/20/02 | September 17, 2002 | January 17, 2003 | 122 days |
| Francis Junior High School | FM-200223928 03 1/17/03 Francis Second floor - 221 storage Replace lock on storage room door inside (arrow), replace door handle lock (lock is broken) (arrow) and replace door handle lock on door it is broken off (boys restroom). | January 14, 2003 | January 17, 2003 | 3 days |
| Bell High School | FM-200223631 03 1/17/03 (Bell) !!!URGENTLY!!! Through-out building: Urgently in need of plumbing for restrooms: 1. 1st floor day care restroom, needs flush valve 2. 2nd floor boys restroom, needs urinal & toilet flush valve repair. 3. Teachers 2nd floor restroom, leak needs to be repaired. 4. Girls 2nd floor restroom, needs new faucet and flush valve. 5. 3rd floor boys & girls restrooms, needs faucet and flush valve. 6. 4th floor boys and girls restrooms, need new faucet and flush valve. | January 8, 2003 | January 17, 2003 | 9 days |
| Clark Elementary School | FM-200224092 03 1/17/03 (Clark) !!!VERY URGENT!!! 3rd Floor/Boys restroom: Repair bradley basin, broken stem. (Students are playing with the water as it pours out. | January 16, 2003 | January 17, 2003 | 1 day |
| Ludlow-Taylor ES | FM-200101918 01 1/17/03 (LUDLOW TAYLOR) 2ND FLOOR, BOYS RESTROOM: REPAIR OR REPLACE DOOR IN BOYS RESTROOM, DOOR WAS BROKEN BY SECURITY GUARD ATTEMPTING TO RESCUE A CHILD FROM THE BATHROOM. MT-20001328 | January 23, 2001 | January 17, 2003 | 724 days |
| Hine JHS | FM-200203459 02 1/17/03 Hine Asbestos Assessment Reqd. 3rd floor girls locker room Repair two door closures to restroom door and locker room door. Asbestos Code A - Clear for repairs on 6/12/02 DCPS Safety - Ronald Edwards (RE-6/12/02) | February 26, 2002 | January 17, 2003 | 325 days |
| Shaed Elementary School | FM-200217657 02 1/21/03 Shaed ****Emergency**** 3rd Floor Restroom A Bradley basin is running over and flooding the floor. The shut-off valve is broken on the hot-water side. | September 17, 2002 | January 21, 2003 | 126 days |
| Davis Elementary School | FM-200224198 03 1/21/03 Davis First Floor - Across from Principal's office ( Boys Bathroom) 1) Toilet backed up and water backing up through slop sink. | January 21, 2003 | January 21, 2003 | 0 days |
| West Elementary School | FM-200222863 /02 1/21/03 (West) !!!VERY URGENT!!! 2nd Floor/Boys restroom: Hot water running profusely, and spilling over on the floor; unable to find shut off valves. | December 19, 2002 | January 21, 2003 | 33 days |
| Randle-Highlands ES | FM-200223730 03 1/21/03 Randle Highland - Old Building Break-In !!!!! Old Building - Main Office and Bathroom 1) Window grates off both windows. | January 13, 2003 | January 21, 2003 | 8 days |
| Randle-Highlands ES | FM-200224184 03 1/21/03 Randle Highland ( Old Building ) Break-In !!! 1) Put peice of plywood over Mr. Jones Office window and secure grate back to window in bathroom. | January 21, 2003 | January 21, 2003 | 0 days |
| Backus Middle School | FM-200222408 /02 1/21/03 Backus First,Second and Third Floor 1) Unstop water fountain on second floor near boys lavatory ( over flow on floor). THE BELOW PART IS DONE 2) Flush valve sticks in girls bathroom on second floor. ( water keeps flushing). 3) Commodes (2) stopped up in girls bathroom on 1st floor( can not flush,smells bad). | December 12, 2002 | January 21, 2003 | 40 days |
| King M L ES | FM-200224245 03 1/21/03 (King) !!!VERY URGENT!!! 2nd Floor/Girls bathroom: Girls #7 toilet stopped up, water running over on the floor. (Custodian will isolate restroom until repair personnel arrives) | January 21, 2003 | January 21, 2003 | 0 days |
| Sousa Middle School | FM-200221056 /02 1/21/03 Sousa Boys restroom gym Partition has become detatch from floor and wall. Asbestos Code A - Clear for repairs on 11/15/02. Horne Engineering - Sheryll James (RG 11/15/02) | November 15, 2002 | January 21, 2003 | 67 days |
| Birney Elementary School | FM-200115473 01 1/21/03 BIRNEY BATHROOMS 2ND FLOOR 2ND FLOOR BOYS BATHROOM URINAL NEW SIDE LEAKING BEHIND URINALS. 2ND FLOOR GIRLS BATHROOM TOILET LEAKING FROM FLUSH VALVE. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/13/01. HORNE ENGINEER SHARON VOSS | July 20, 2001 | January 21, 2003 | 550 days |
| Barnard Elementary School | FM-200219826 /02 1/21/03 (Barnard) !!URGENT!! 1st floor/Boys bathroom: Leaks in toilet and sink, unable to shut off. | October 22, 2002 | January 21, 2003 | 91 days |
| Davis Elementary School | FM-200125871 /01 1/21/03 (DAVIS) ASBESTOS ASSESSMENT REQUIRED BASEMENT/BOYS BATHROOM & LUNCHROOM FOURTH STALL: BOLTS BROKE OFF TOILET & WATER IS COMING OUT WHEN TOILET FLUSHES. REPAIR OR REPLACE COMMODE. Asbestos Code A - Cleared for repairs on 11-27-02 (LM/11-29-02) Leroy Minton Jr. Safety Office (202) 576-8962. | December 20, 2001 | January 21, 2003 | 397 days |
| Stanton Elementary School | FM-200222521 /02 1/21/03 (Stanton) !!!URGENT!!! 1st Floor/Health Suite: Leaking pipe under sink in the health suite bathroom. | December 13, 2002 | January 21, 2003 | 39 days |
| Backus Middle School | FM-200222069 02 1/21/03 Backus Second floor FIRST PART IS COMPLETED Water fountain is stopped up. Girl bathroom on first floor water is running over, and a toilet is stopped up. DO THIS PART 2.) Gym bathroom the faucet is stopped up also the toilet in girls area. | December 4, 2002 | January 21, 2003 | 48 days |
| Spingarn High School | FM-200219636 /02 1/21/03 Spingarn First Floor - Girls Bathroom 1) Unstop (2) sinks in bathroom. | October 18, 2002 | January 21, 2003 | 95 days |
| Ludlow-Taylor ES | FM-200220955 /02 1/21/03 (Ludlow-Taylor) 1st Floor/Room #116: Sink stopped up in girls bathroom; appears to be backing up in staff bathroom. | November 14, 2002 | January 21, 2003 | 68 days |
| Backus Middle School | FM-200223642 03 1/22/03 (Backus) 3rd Floor/Girls gym restroom: A total of four (4) toilets stopped up, water overflowing. | January 8, 2003 | January 22, 2003 | 14 days |
| Langdon Elementary School | FM-200122725 /01 1/22/03 LANGDON 1ST FL. BOYS RESTROOM BY MAIN OFFICE 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE (1) 3/4" STEAM TRAP LOCATED ON RADIATOR. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: SAM EBRAHIM | October 31, 2001 | January 22, 2003 | 448 days |
| Davis Elementary School | FM-200201558 02 1/22/03 (DAVIS) ASBESTOS ASSESSMENT REQUIRED BASEMENT LUNCHROOM-BOYS BATHROOM BOLTS ARE BROKEN OFF IN THE 4TH STALL & WATER IS COMING OUT WHEN TOILET IS FLUSHED-- NEEDS BOLTS OR WHOLE UNIT REPLACED. CODE A -CLEAR FOR REPAIR BY HORNE ENGINEERING RAYMOND AGNANT 01-24-02 | January 23, 2002 | January 22, 2003 | 364 days |
| Patricia R Harris Ed Center | FM-200222357 /02 1/22/03 Harris, P.R. First Floor - Girls Bathroom Stairwell (8) 1) Urinal stopped up. | December 10, 2002 | January 22, 2003 | 43 days |
| Barnard Elementary School | FM-200220558 02 1/22/03 (Barnard) New building/2nd Floor girls bathroom: Bradley basin leaking water from gasket packing nut, and several places. | November 1, 2002 | January 22, 2003 | 82 days |
| Miner Elementary | FM-200223829 03 1/22/03 Miner Emergency !! 1) Repair busted water line in bathroom. | January 13, 2003 | January 22, 2003 | 9 days |
| Davis Elementary School | FM-200221399 /02 1/22/03 Davis Basement - lunchroom boys bathroom Urinal by sink is leaking from bottom, repair or replace urinal. | November 20, 2002 | January 22, 2003 | 63 days |
| Tubman Elementary School | FM-200217829 02 1/22/03 TUBMAN 1st Floor Custodian Closet [Space 31] 1. Repair primer on cold water line shut-off valve. The headstart class cannot use the restroom; and 2. The water in the head start class room cannot be used because the shut-off valve was cut off to the a water leak. | September 18, 2002 | January 22, 2003 | 126 days |
| Gibbs Elementary School | FM-200220120 /02 1/22/03 Gibbs Second Floor - Boys Bathroom 1) Boys Bathroom commode needs to be snaked out. | October 28, 2002 | January 22, 2003 | 86 days |
| Gibbs Elementary School | FM-200217899 02 1/22/03 Gibbs ****Urgent**** 1st Floor Boys' Restroom Repair broken/cracked urinal. Water is running onto the floor daily. POC: Mr. Manigan | September 19, 2002 | January 22, 2003 | 125 days |
| Maury Elementary School | FM-200223825 03 1/22/03 Maury First floor boys room east bldg. Unstop urinal. (Please expedite) | January 13, 2003 | January 22, 2003 | 9 days |
| Deal Junior High School | FM-200203603 02 1/22/03 (Deal) 2nd Floor & Basement Boys Restrooms Snake out urinals in the 2nd floor & basement boys restrooms which are backing up. | February 27, 2002 | January 22, 2003 | 329 days |
| Brightwood Elementary School | FM-200224200 03 1/22/03 Brightwood First Floor - Old Annex Side - Boys Bathroom 1) Busted Pipe | January 21, 2003 | January 22, 2003 | 1 day |
| Birney Elementary School | FM-200114050 01 1/22/03 BIRNEY THIRD FLOOR 1) URINAL LEAKING INSIDE WALL IN BOYS RESTROOM ON THIRD FLOOR (NEW SIDE) ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/13/01. HORNE ENGINEER STEPHEN CALDWELL | June 26, 2001 | January 22, 2003 | 575 days |
| Bowen Elementary School | FM-200223425 03 1/23/03 (Bowen) !!!VERY URGENT!!! Cafeteria/Workers restroom: Toilet backing up through floor drains in the cafeteria/kitchen, given off an un-pleasant odor. | January 2, 2003 | January 23, 2003 | 21 days |
| Hyde Elementary School | FM-200223859 03 1/23/03 Hyde First floor - Bathroom sink Is backup need to be snake out. | January 13, 2003 | January 23, 2003 | 10 days |
| Smothers ES | FM-200224343 03 1/24/03 Smothers First Floor - Girls Bathroom 1) Students broke the pipe under the sink and off the wall. There are (2) sinks in the bathroom and they are both on the same drain lines. Third Floor - Boys Bathroom 2) Sink off of wall / anchor brackets need to be put back up to hang sink. Asbestos Code A - Cleared for repairs on 01-22-03 by Leroy Minton Jr. (LM/01-21-03) Safety Office (202) 576-8962. | January 22, 2003 | January 24, 2003 | 2 days |
| Stanton Elementary School | FM-200224416 03 1/26/03 Stanton Third floor girls bathroom Window need repairing. | January 23, 2003 | January 26, 2003 | 3 days |
| Draper Elementary School | FM-200224651 03 1/27/03 Draper Second Floor Unstop drains in the Boys and Girls Bathrooms, water running into the halls | January 27, 2003 | January 27, 2003 | 0 days |
| Birney Elementary School | FM-200221822 02 1/27/03 Birney Second floor - boys restroom Repair partition hanging from wall. Safety concern Lead & Asbestos Code A - Clear for repairs on 12/03/02. Horne Engineering - Edward Rodriguez (RG 12/04/02) | December 2, 2002 | January 27, 2003 | 56 days |
| Plummer Elementary School | FM-200222190 02 1/27/03 Plummer Boys Bathroom,Cafeteria,Teachers Bathroom 2nd Floor, Boys Bathroom 3rd Floor. 1) Provide (6) diaphrams and (6) vacuum breakers for sloan flush valves. | December 9, 2002 | January 27, 2003 | 49 days |
| John Burroughs ES | FM-200224253 03 1/27/03 Burroughs First floor - new wing Boys restroom urinals leaks water, looks like it is coming from the bottom of the wall. | January 21, 2003 | January 27, 2003 | 6 days |
| Kimball Elementary School | FM-200222480 /02 1/27/03 (Kimball) !!!VERY URGENT!!! Middle wing/1st Floor: Water running in the 1st commode in the boys restroom; unable to shut water off. Repair or replace flush valves and shut off valves. | December 12, 2002 | January 27, 2003 | 46 days |
| Woodson High School | FM-200224676 03 1/28/03 Woodson SHS Lobby 1) Repair toilet and sink, girls room fixtures off wall. | January 28, 2003 | January 28, 2003 | 0 days |
| Truesdell Elementary | FM-200224621 03 1/28/03 (Truesdell) 1st Floor/Boys restroom: Urinal leaking, using buckets to contain water that is flooding out into the hallway. The water continues to run after shutting the valve off. | January 27, 2003 | January 28, 2003 | 1 day |
| Hine JHS | FM-200224510 03 1/29/03 (Hine) Lobby area:replace lock to girls restroom | January 16, 2003 | January 29, 2003 | 13 days |
| Turner Elementary School | FM-200224527 03 1/29/03 (Turner) 1st & 2nd Floor: Unstop toilet in the boys restroom, old side. Repair toilet in the teachers lounge, it is constantly running. | January 24, 2003 | January 29, 2003 | 5 days |
| Ballou Senior High School | FM-200214056 02 1/29/03 Ballou 1. Asbestos Assessment Reqd. 1st Floor Boys' Restroom 2. Scrape and replaster the water-damaged ceiling in the 1st floor restroom. Asbestos/Lead Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) Charles Buchanan on 8/15/02 | August 12, 2002 | January 29, 2003 | 170 days |
| Shaw JHS | FM-200224281 03 1/29/03 (Shaw) First floor -- Women's bathroom across from counselor's suite. First toilet and third toilet is clogged up. Will not flush. Account #: 423 | January 21, 2003 | January 29, 2003 | 8 days |
| Garnet-Patterson MS | FM-200224717 03 1/29/03 (Garnett-Patterson) 1st Floor/Girls restroom: Inside window broken on double window, no damage to the outside window. | January 28, 2003 | January 29, 2003 | 1 day |
| Hine JHS | FM-200123474 /01 1/29/03 (HINE) HEALTH CODE VIOLATION: 1. ASBESTOS ASSESSMENT REQUIRED. REPAIR AND REMOVE SCALING PAINTS INSIDE RESTROOM. REPAIR HOLES IN CEILING IN FRONT OF OFFICE. ASBESTOS CODE A-CLEAR FOR REPAIR 12/04/01 BY HORNE ENGINEER: SHERYLL JAMES | November 16, 2001 | January 29, 2003 | 439 days |
| Raymond Elementary School | FM-200224703 03 1/30/03 Raymond Room 119 Bathroom First Floor Asbestos Assestment Required Repalce busted heating coil in convector room 119 in kindergarten bathroom Note: Covector is isolated Asbestos Code A - Clear for repairs on 01/29/03. Horne Engineering - Sharon Voss ( RG 01/30/03) | January 28, 2003 | January 30, 2003 | 2 days |
| Bunker Hill Elementary School | FM-200224161 03 1/30/03 (Bunker Hill) Health Code Violation: 1. Asbestos assessment Required. Kitchen: Repair the loose plaster hanging from ceiling in the little girls, and employee restrooms. Asbestos Code A - Clear for repairs on 01/22/03. Horne Engineering - Edward Rodriguez (RG 01/23/03) | January 17, 2003 | January 30, 2003 | 13 days |
| Gibbs Elementary School | FM-200224923 03 1/30/03 Gibbs First floor - chair room Sewage is backing up into kitchen, principal bathroom, kindergarten and teacher bathroom. | January 30, 2003 | January 30, 2003 | 0 days |
| Johnson JHS | FM-200224340 03 1/30/03 Johnson First floor boys bathroom gym area Someone need to come out and cuttoff commode, water is continously to run. | January 22, 2003 | January 30, 2003 | 8 days |
| Sousa Middle School | FM-200208026 02 1/30/03 Sousa ****Emergency**** 1. Asbestos Assessment Reqd. 2nd Floor Girls' Restroom 2. Repair leaking pipe in wall causing leaking around a toilet and flooding of the restroom. Unable to cut the water off and isolate. Code A-clear for repair by Horne Engineer ( Troy wilcome) on 5/16/02 | May 20, 2002 | January 30, 2003 | 255 days |
| Harris, C.W. ES | FM-200225037 03 1/31/03 (Harris, C.W.) 1. Asbestos assessment required. 2nd Floor/Boys restroom: Busted supply line in floor, flooding. Asbestos Code A - Clear for repairs on 01/31/03. Horne Engineering - Troy Wilcome (RG 01/31/03) | January 31, 2003 | January 31, 2003 | 0 days |
| Eastern High School | FM-200225039 03 1/31/03 (Eastern) 1st Floor/Basement: Sink stopped up, water running in the girls restroom and other area's. | January 31, 2003 | January 31, 2003 | 0 days |
| King M L ES | FM-200224293 03 1/31/03 King, M.L.Jr. Second floor - girls bathroom Need to have #7 stall toilet snake out. It is stopped up and water is running on the floor causing flooding. EMERGENCY | January 21, 2003 | January 31, 2003 | 10 days |
| Plummer Elementary School | FM-200225064 03 2/3/03 Plummer Third Floor - Girls Bathroom and Auditorium 1) Unstop (2) toilets in girls bathroom . 2) Unstop (1) toilet in auditorium girls room. Note - These toilets are stopping up on a re-occurring basis . | February 3, 2003 | February 3, 2003 | 0 days |
| Patricia R Harris Ed Center | FM-200225060 03 2/3/03 Harris, P.R. Main floor - restroom the one next to #1 stairs Toilet needs to be pulled up from the floor because of blockage in the line. | February 3, 2003 | February 3, 2003 | 0 days |
| Raymond Elementary School | FM-200224544 03 2/4/03 (Raymond) New wing/1st Floor: Girls and boys bathroom: Sink leaking profusely. | January 24, 2003 | February 4, 2003 | 11 days |
| Brightwood Elementary School | FM-200224715 03 2/4/03 (Brightwood) Old Annex side/Boys restroom 1st floor: Ruptured copper pipe, leaking very badly, replace valves over hot water tank. | January 28, 2003 | February 4, 2003 | 7 days |
| Wilson High School | FM-200218319 02 2/4/03 Wilson,W. 1st Floor Boys' Locker Room 1. Replace cracked toilet in the restroom; and 2. Repair urinal in the team room that does not flush properly. | September 25, 2002 | February 4, 2003 | 132 days |
| Smothers ES | FM-200219698 /02 2/4/03 Smothers First Floor - Boys Bathroom 1) Repair leak that occurs when the recently installed urinals are used . Note - 5 out of 6 urinals had to be shut off to stop the water from leaking while they are on, which leaves an odor when the students use them. | October 18, 2002 | February 4, 2003 | 109 days |
| Hine JHS | FM-200214025 02 2/4/03 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. 2nd Floor: Girls bathroom not latching. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 4, 2003 | 176 days |
| Merritt Middle School | FM-200222724 /02 2/5/03 (Merritt) !!!URGENT!!! 3rd Floor/Gym office restroom: Hot water running very hard, making it uncomfortable for staff to perform with the steamed heat coming from that area. | December 17, 2002 | February 5, 2003 | 50 days |
| King M L ES | FM-200224886 03 2/5/03 King, M. L. Jr. First floor Need keys made for rooms 117 and 118 - Teachers bathroom in the lobby. | January 30, 2003 | February 5, 2003 | 6 days |
| Wilson High School | FM-200218393 02 2/5/03 Wilson,W. 1st Floor Boys' Restroom Repair toilet & urinal that do not flush properly. Replace urinal that was removed. | September 26, 2002 | February 5, 2003 | 132 days |
| Watkins Elementary School | FM-200223787 03 2/6/03 Watkins !!!VERY URGENT!!! Fourth floor boy bathroom Last stall toilet is busted need new toilet. | January 13, 2003 | February 6, 2003 | 24 days |
| Garnet-Patterson MS | FM-200201701 02 2/6/03 GARNET- PATTERSON AUDITORIUM RESTROOM, CAFETERIA STORAGE AREA 1. ASBESTOS ASSESSMENT REQUIRED. 2. DEMO THE FLOOR OF THE AUDITORIUM RESTROOM AND REMOVAL THE PIPE INSULATION OFF OF THE SPRAY PAINTED AREAS OF THE CAFETERIA STORAGE AREA AND REPAIR THE FLOOR. ED RODRIDUEZ-HORNE ENGINEERING OF HORNE HAS ALREADY WALKED THE SCOPE OF WORK WITH SHEILA HOWARD OF DCPS SAFETY AND CARNAL BRADLEY OF DCPS MECH. MAIN (01-24-02) TSI REMOVAL IN RESTROOM DCB (IT GROUP)/703-461-6848 CODE A - ASBESTOS ABATED ON 01/31/02 PER SHEILA R. HOWARD CONFIRMATION. (RG 02/27/02) No Permit was issued on 3/14/02. J. Eggleston | January 24, 2002 | February 6, 2003 | 378 days |
| Watkins Elementary School | FM-200219962 /02 2/6/03 Watkins Fourth floor - boys Boys bathroom last stall toilet, is busted, need new toilet. Asbestos Code A - Clear for repairs on 10/25/02. Horne Engineering - Philp Connolly (RG 10/28/02) | October 24, 2002 | February 6, 2003 | 105 days |
| Gage-Eckington ES | FM-200225201 03 2/10/03 Gage-Eckington Second floor girls restroom main lobby There are six (6) stalls, two (2) of them need handles replaced, water will not stop running or dripping causing floods all day. | February 5, 2003 | February 10, 2003 | 5 days |
| Bowen Elementary School | FM-200225502 03 2/10/03 (Bowen) 1st Floor/Boys restroom: Toilet in last stall backing up, and spilling over. (No success with plunger) | February 10, 2003 | February 10, 2003 | 0 days |
| Spingarn High School | FM-200225331 03 2/10/03 (Spingarn) !!!EMERGENCY!!! 1st Floor/Boys bathroom: All urinals stopped up. (Continues to back up in other area's) | February 6, 2003 | February 10, 2003 | 4 days |
| Payne Elementary School | FM-200202544 02 2/11/03 Payne Tunnel 1) TSI, Removal in Tunnel Exploratory Demo in 2nd floor Boys Room. 2) Fiber Release Clean-up in AMP #129. 1. Asbestos assessment required on restricted tunnel. 2. Makea all necessary repairs on steam and return lines in tunnel area. Emergency. POC: HAWKINS, CLARENCE 202- 4387367 DCB (IT Group)/ 703-461-6848 CODE A - ASBESTOS ABATED ON 02/16/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/20/02) | February 6, 2002 | February 11, 2003 | 370 days |
| Simon Elementary School | FM-200225020 03 2/11/03 Simon First floor - Girls bathroom You have to flush the toilet many times in order for it to flush all the way. | January 31, 2003 | February 11, 2003 | 11 days |
| Ballou Senior High School | FM-200224679 03 2/11/03 (Ballou) 1st Floor water coolers: 1. Fountain near boys restroom - Replace push plate. 2. Water fountain outside maint. office - Re-anchor to wall, replace filter, and cooler. (Wall hung) 3. Water cooler near room #111 - replace. (No filter) 4. Water cooler near room #115 - re-anchor, (No filter) Replace Bubbler. 5, Water cooler near gym - replace 2nd cooler, remove stoppage, no filter, (Wall hung) 6. Water cooler near library - water line outside jacket replace. Asbestos Code A - Clear for repairs on 02/10/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) | January 28, 2003 | February 11, 2003 | 14 days |
| Park View ES | FM-200224438 03 2/12/03 Parkview First and Second Floor - Boys and Girls Bathroom 1) Make repairs to exposed sanitary piping at ceiling from above urinals. Poc - Preston McCrary - 240-832-7573 Asbestos Code A - Clear for repairs on 01/28/03. Horne Engineering - Sharon Voss ( RG 01/30/03) | January 23, 2003 | February 12, 2003 | 20 days |
| Maury Elementary School | FM-200225385 03 2/12/03 Maury First Floor P.E. Room and First Floor Boys Room East Building. 1) Replace leaking wax ring in P.E. Room. 2) Replace leaking wax ring in Boys Room. March 26, 2003 Corected copy: 1st Floor/East building, P.E. room: Unstop 4" inch wastline on toilets in the boys restroom. | February 7, 2003 | February 12, 2003 | 5 days |
| Malcolm X ES | FM-200224876 03 2/12/03 Malcolm X 1) 4th floor 6 grade classroom - circuit breaker is gone. 2) 4th floor Boys and Girls bathroom - no lights. | January 30, 2003 | February 12, 2003 | 13 days |
| Bunker Hill Elementary School | FM-200222133 02 2/12/03 Bunker Hill Nurse's Restroom Asbestos assessment required Boiler #1 repair and replace crack section. Asbestos Code A - Clear for repairs on 12/09/02. Horne Engineering - Sheryll James (RG 12/12/02) | December 6, 2002 | February 12, 2003 | 68 days |
| Merritt Middle School | FM-200220069 /02 2/12/03 (Merritt) Health Code Violation: !!VERY URGENT!! 1st Floor/Cafeteria staff restroom: Faucets needs to be replaced, hot water continues to run. Water is 150 degree of temperature, and running very hard. | October 25, 2002 | February 12, 2003 | 110 days |
| Ludlow-Taylor ES | FM-200225207 03 2/13/03 Ludlow-Taylor First floor recreation office and custodian room Unstop sink in bathroom. | February 5, 2003 | February 13, 2003 | 8 days |
| Lincoln Middle School | FM-200224778 03 2/13/03 Lincoln / Taft Second floor - Office off from gym EMERGENCY Restroom - toilet needs to repaired, sink no water supply to both toilet and sink. Shower not working, no water supply replace fixtures thru out. | January 29, 2003 | February 13, 2003 | 15 days |
| Ronald H. Brown MS | FM-200222705 /02 2/14/03 Brown, Ron Third floor boys lavatory near stairwell # 10 Expose wires in bathroom. Students removed lightswitch plate, pulled out wires, remove caps so lights will not come on. Urgent Plear repair. | December 17, 2002 | February 14, 2003 | 59 days |
| King M L ES | FM-200225834 03 2/14/03 Paul !!! URGENT !!! FIRST FLOOR - BOYS RESTROOM 1) Repair or replace urinal traps and pipes . ( very bad smell - Health Hazard ) | February 14, 2003 | February 14, 2003 | 0 days |
| Cardozo High School | FM-200225850 03 2/14/03 (Cardozo) 1st & 3rd Floors/Boys bathrooms: Unstop urinals in 1st and 3rd floor boys bathrooms. Urinals are backing up, flooding the floors when flushed. Water supply turned off to stop flooding; restore water supply to sink. | February 14, 2003 | February 14, 2003 | 0 days |
| Ross Elementary School | FM-200224247 03 2/14/03 (Ross) !!!URGENT!!! Basement/Boys restroom: 1st urinal leaking from the bottom flooding the floors. Custodian shut down until repair personnel arrives. | January 21, 2003 | February 14, 2003 | 24 days |
| Cardozo High School | FM-200223587 03 2/14/03 (Cardozo) 1st Floor/Boys restroom: A total of three (3) urinals needs snaking out. | January 7, 2003 | February 14, 2003 | 38 days |
| Woodson High School | FM-200225715 03 2/14/03 (Woodson, H.D.) !!!URGENT!!! 4th Floor/Boys restroom: Toilet is backing up, please unstop. | February 12, 2003 | February 14, 2003 | 2 days |
| Wilkinson ES | FM-200215978 02 2/21/03 Wilkinson F110.3 Fire code violation: First floor - Girls restroom Need drain cover. | August 28, 2002 | February 21, 2003 | 177 days |
| Beers Elementary School | FM-200122717 /01 2/21/03 (BEERS) ASBESTOS ASSESSMENT REQ. BLDG. #1, 2, AND 3 ALL BATHROOMS THROUGH OUT THE BUILDING NEED LOCKS ON DOORS. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-07-01 HORNE ENGINEER : SHARON VOSS | October 31, 2001 | February 21, 2003 | 478 days |
| Ferebee-Hope Elementary School | FM-200214618 02 2/21/03 Ferebee-Hope F-110.2(1) Fire Code Violation Swimming Pool Level Men's Restroom There is a hole in the wall. Asbestos Code A - Clear for repairs on 08/19/02. DCPS Safety - Leroy Minton Jr (RG 08/20/02) | August 15, 2002 | February 21, 2003 | 190 days |
| Roosevelt High School | FM-200225156 03 2/21/03 (Roosevelt) 2nd Floor/Boys bathroom: Due to vandalism, replace sink inside this boys restroom. | February 4, 2003 | February 21, 2003 | 17 days |
| Woodson High School | FM-200226116 03 2/24/03 (Woodson, H.D.) !!!VERY URGENT!!! 3rd Floor/Boys & Girls restroom: When commode is flushed in these restrooms, all other toilets back up, and run over from the 7th floor to the basement. (Appears to be a major back-up) | February 24, 2003 | February 24, 2003 | 0 days |
| Emery Elementary School | FM-200223754 /02 2/24/03 (Emery) Principal office bathroom toilet is clog water is coming out of bathroom in to office floor !!!EMERGENCY!!! | November 12, 2002 | February 24, 2003 | 104 days |
| Woodson High School | FM-200226094 03 2/24/03 (Woodson, H.D.) 5th Floor/Boys bathroom: Flush valve leaking profusely; running out in the hallway. Unit broke on flush valve; need a complete flush valve unit. (Unable to shut off water) | February 24, 2003 | February 24, 2003 | 0 days |
| Whittier Elementary School | FM-200225781 03 2/24/03 (Whittier) !!!VERY URGENT!!! 1st Floor/Girls restroom: Total of two (2) commodes overflowing with water, spilling over, flooding the floor (Unable to locate shut off valves) | February 13, 2003 | February 24, 2003 | 11 days |
| Orr Elementary School | FM-200214659 02 2/24/03 Orr F-303.4 Fire Code Violation 1st Floor Girls' Bathroom Missing hardware on bathroom door. | August 15, 2002 | February 24, 2003 | 193 days |
| Thomas Elementary School | FM-200220363 /02 2/25/03 Thomas First floor - Kitchen restroom Survey restroom door and shave the bottom or top of the door, so that it may close and open for privacy. Asbestos Code B- by Horne Engineer Sheryll Jones on 11/12/02 DCPS Charles E Buchanan DCPS Follow up investigation found that the damage door was a wooden door therefore a code A-clear for repair was giving by DCPS Safety Charles E. Buchanan on 11/12/02 | October 31, 2002 | February 25, 2003 | 117 days |
| Gibbs Elementary School | FM-200214581 02 2/25/03 Gibbs - f-110.1(1) Second floor - Girls restroom Hole in ceiling "unsafe conditions". | August 15, 2002 | February 25, 2003 | 194 days |
| Sousa Middle School | FM-200205865 02 2/26/03 Sousa Gym Office Restroom & Boys & Girls Restrooms 1) The gym office toilet needs a wax ring the toilet will not flush properly. 2) In the boys restroom toilet will not flush properly. 3) The last toilet in the girls restroom will not flush properly and the frist toilet is stopped up. | April 16, 2002 | February 26, 2003 | 316 days |
| Hine JHS | FM-200214022 02 2/28/03 (Hine) Fire code violation: Page 5 of 6 1. Asbestos assessment required. Recreation office: Bathroom door sticks. Asbestos Code A-clear for repair by DCPS Leroy Minton On 8/16/02 Charles Buchanan | August 12, 2002 | February 28, 2003 | 200 days |
| Hyde Elementary School | FM-200226365 03 2/28/03 Hyde Boys Toilet - Basement Repair leaking radiator in basement boys restroom. | February 27, 2003 | February 28, 2003 | 1 day |
| Tubman Elementary School | FM-200204435 02 3/3/03 TUBMAN THROUGH-OUT ENTIRE BUILDING 1. ASBESTOS ASSESSMENT REQUIRED. 2. PLASTER, SPRAY-ON REMOVAL IN SECOND (2ND) FLOOR RESTROOM AMP #214. DCB (IT GROUP)/703-461-6848 Code A - Clear for Repair asbestos abatement date 03-20-02. DCPS Safety- Sheila R. Howard 03-26-02 confirmation | March 14, 2002 | March 3, 2003 | 354 days |
| Roosevelt High School | FM-200204751 02 3/3/03 (Roosevelt) Exploratory Demo 1. Asbestos assessment required. 2nd floor/boys restroom: Repair and replace existing sink and supply line; supply line is busted off in wall. (Assessment needed) Vincent Reed - Poc 576-6130 It Group Code A - Asbestos abated on 03/22/02 PER Leroy Minton Jr. confirmation 04/04/02.(RG) | March 20, 2002 | March 3, 2003 | 348 days |
| Duke Ellington School | FM-200202326 02 3/3/03 (ELLINGTON) ***URGENT*** ASBESTOS ASSESSMENT REQUIRED BASEMENT/SUB-BASEMENT DANCE STUDIO 2ND FLOOR GIRLS RESTROOM 1) BOYS RESTROOM HAS BROKEN PARTITIONS WHICH NEED REPAIR OR REPLACEMENT (THEY ARE TORN AWAY FROM THE FLOOR) 2) GIRLS 2ND FLOOR RESTROOM NEEDS BROKEN PARTITIONS REPAIRED OR REPLACED Asbestos Code A - Clear for repairs on 06/07/02. DCPS Safety - Ronald Edwards (RG06/10/02) Note: repaired anda replaced toilet in girls restroom and dance studio | February 1, 2002 | March 3, 2003 | 395 days |
| Rudolph Elementary School | FM-200221876 02 3/3/03 Rudolph First floor - Boys restroom Broken toilet in boys bathroom . | December 2, 2002 | March 3, 2003 | 91 days |
| Eaton Elementary School | FM-200225163 03 3/3/03 Eaton Third floor boys restroom Urinal felled off the wall need remounting. Asbestos Code A - Clear for prepairs on 02/05/03. Horne Engineering - Troy Wilcome (RG 02/06/03) | February 4, 2003 | March 3, 2003 | 27 days |
| Wilson J. O. ES | FM-200207670 02 3/3/03 Wilson,J.O. ****Urgent**** 1. Asbestos Assessment Reqd. 1st Floor Boys' Restroom Ceiling 2. Repair plaster ceiling that has fallen in as a result of ongoing flooding from the 3rd & 2nd floor boys' & girls' restrooms above [Ref: FM-200207669 created 5/14/02]. This ceiling repair cannot take place until the repairs requested for the 3rd floor problems are abated. Envirobate (IT Group)/703-461-6848 Asbestos Code A - Clear for repairs on 05/31/02. After further evaluation by DCPS (Mr. Hinton) , USACE (Robert Franklin) and Shaw Group (Vincent Reed) it was determined that the problem can be corrected by installing new flush valves and flanges. This was reported to Sheila R. Howard-DCPS Safety 05-31-02. Ricardo Welch of Structural Maintenance was informed and he stated he would assign the project to the evening shift. (DCPS Safety-Sheila R. Howard 05-31-02 at 1255) | May 14, 2002 | March 3, 2003 | 293 days |
| Stanton Elementary School | FM-200220704 /02 3/4/03 Stanton - T-9 Annex Boys bathroom first urinal coming off the wall. Third urinal is leaking. Asbestos Code A-clear for repair by Horne Engineer Bipin Nanvaty on 11/15/02 DCPS Charles E. Buchanan | November 12, 2002 | March 4, 2003 | 112 days |
| Beers Elementary School | FM-200208744 02 3/4/03 Beers Throughout Entire Building Plumbing all faucet handles need to be Restroom Six (6) faucets in restrooms)) I fixed some of them. Asbestos Code A - Clear for repairs on 05/31/02. DCPS Safety - Richard Gibson | May 31, 2002 | March 4, 2003 | 277 days |
| Moten Elementary School | FM-200225888 03 3/5/03 Moten Fourth floor girls bathroom new side Entrance first sink retighten packing nut on cold water, stop control. Second sink replace drain and seal on sink. Entrance (L) fourth and fifth stall repair flush valve fourth stall remove stoppage. | February 14, 2003 | March 5, 2003 | 19 days |
| Moten Elementary School | FM-200225886 03 3/5/03 Moten First floor girls bathroom old side Last stall near window re-anchor commode. | February 14, 2003 | March 5, 2003 | 19 days |
| Duke Ellington School | FM-200203914 02 3/5/03 (Ellington) Asbestos Assessment Required Sub-basement Dance Studio & 2nd Floor Girls Restroom 1) A stall paritition in the sub-basement girls restroom in the dance studio requires reanchoring to the floor. 2) The handicapped stall partition in the 2nd floor girls restroom needs reanchoring. Code-A clear for repiar by horne engineer ( Stephen Caldwell ) 3/06/02 CEB | March 5, 2002 | March 5, 2003 | 365 days |
| Bowen Elementary School | FM-200213326 02 3/6/03 (Bowen) ****EMERGENCY*** Boys gym: Toilet backed up, and over-flowing in the boys bathroom. | July 30, 2002 | March 6, 2003 | 219 days |
| Beers Elementary School | FM-200211144 02 3/6/03 Beers 1st Floor Boys' Restroom/Bldg. 1 The 1st-floor boys' restroom is cracked and, when flushing, water shoots out---please repair or replace. | July 12, 2002 | March 6, 2003 | 237 days |
| Woodson High School | FM-200226481 03 3/6/03 Woodson, H.D. Second floor boys bathroom Replace cracked commode, broken during repair. | March 4, 2003 | March 6, 2003 | 2 days |
| Lincoln Middle School | FM-200224775 03 3/6/03 Lincoln / Taft Second floor - Office off from gym EMERGENCY Request that locks be changed for four (4) doors. Two (2) exit doors, One (1) restroom door, and one (1) closet door. Same key. | January 29, 2003 | March 6, 2003 | 36 days |
| Bowen Elementary School | FM-200212936 02 3/6/03 (Bowen) 1st Floor/Gymnasium: Over flow when flushing in boys bathroom. Slops on 1st and 3rd floors needs handles and knobs. | July 25, 2002 | March 6, 2003 | 224 days |
| Moten Elementary School | FM-200225903 03 3/6/03 Moten Second floor old side boys bathroom Entrance (L) first and fourth stall re-anchor commode. Last stall repair flush valve. | February 14, 2003 | March 6, 2003 | 20 days |
| Brightwood Elementary School | FM-200205284 02 3/7/03 Brightwood First (1st) Floor - Girls Restroom 1. Asbestos Assessment Required. 2. Need to install a door. Knob on entrance Door knob is missing. Hard for Students to open. Code A-clear for repair by Honre Engineer ( Stephen Caldwell ) on 4/04/02 | April 2, 2002 | March 7, 2003 | 339 days |
| Takoma Educational Center | FM-200226696 03 3/7/03 TAKOMA Second Floor - Girls Restroom Water is backing up from the the floor drain . drain need to be snaked out . | March 6, 2003 | March 7, 2003 | 1 day |
| Lincoln Middle School | FM-200226604 03 3/7/03 LINCOLN - TAFT Second floor - teachers restroom new side Restroom is unisex, door do not lock once you enter it. | March 5, 2003 | March 7, 2003 | 2 days |
| Maury Elementary School | FM-200226444 03 3/7/03 MAURY FIRST FLOOR - EAST BUILDING EMERGENCY 1. PLEASE UNCLOG TWO URINALS IN THE BOYS RESTROOM IN THE EAST BLDG . | March 3, 2003 | March 7, 2003 | 4 days |
| Birney Elementary School | FM-200111636 01 3/10/03 BIRNEY BASEMENT BOYS RESTROOM 1) REPLACE HOLE IN WALL IN BOYS RESTROOM NEW SIDE 2) SECOND FLOOR NEW SIDE CLOSET HOT WATER RUNNING CANT TURN OFF ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/10/01. | May 30, 2001 | March 10, 2003 | 649 days |
| Webb Elementary School | FM-200225256 03 3/10/03 (Webb) 2nd Floor/Boys restroom: Repair four (4) urinals need to be unclog. | February 5, 2003 | March 10, 2003 | 33 days |
| Anacostia Senior High School | FM-200226832 03 3/11/03 ANACOSTIA !! URGENT !! Frist floor - New wing girls restroom no running water in this restroom. Repair broken faucet also. Asbestos Code A - Clear for repairs on 03/13/03. Horne Engineering - Donald Maglienti (RG 03/14/03) | March 10, 2003 | March 11, 2003 | 1 day |
| Webb Elementary School | FM-200225245 03 3/12/03 (Webb) 2nd Floor/Boys restroom: Urinals torn away from the wall. Asbestos Code A-clear for repair by Horne Engineering Troy Wilcome on 02/07/03 Charles Buchanan | February 5, 2003 | March 12, 2003 | 35 days |
| Nalle Elementary School | FM-200214972 02 3/12/03 Nalle F-110.1 Fire code violation: Boys bathroom - fisrt and second floor Hole in walls. | August 19, 2002 | March 12, 2003 | 205 days |
| Turner Elementary School | FM-200215246 02 3/12/03 Turner Fire code violation Second floor - Beside boys bathroom Breech in the wall. | August 21, 2002 | March 12, 2003 | 203 days |
| Birney Elementary School | FM-200213839 02 3/12/03 (Birney) Fire code violation: Page 1of 2 1. Asbestos assessment required. 3rd Floor: Hole in boys bathroom not covered. Asbestos Code A - Clear for repairs on 08/09/02. DCPS-Safety - Leroy Minton Jr. (RG 08/09/02) | August 8, 2002 | March 12, 2003 | 216 days |
| Patricia R Harris Ed Center | FM-200218119 02 3/13/03 Harris,P.R. 1st Floor Boys' Restroom by Urinals Repair masonry block where plumbers opened a hole to effect earlier repair. | September 23, 2002 | March 13, 2003 | 171 days |
| Harris, C.W. ES | FM-200220646 /02 3/13/03 Harris, C.W. Third floor - Boys bathroom second toilet Toilet need to be mounted down to floor. Week of 11/4/02-11/08/02 FM-200220884 Asbestos Code A-clear for repair by Charles E. Buchanan on 11/12/02 DCPS Charles E Buchanan | November 12, 2002 | March 13, 2003 | 121 days |
| Langdon Elementary School | FM-200117779 01 3/13/03 LANGDON THROUGHOUT BLDG. 1. ABESTOS ASSESSMENT REQUIRED. 2. REPLACE 3/4 STEAM RADIATOR VALVE - TEACHER RESTROOM, S.W. STAIRWAY 1ST & 2ND FL., 1ST FL. - LADIES RESTROOM; R/R RADIATOR AND VALVE IN ROOM 125, REPLACE 3/4" STEAM STOP VALVE IN HALL. R/R RADIATOR AND STOP VALVE IN ROOM 194, REPLACE RADIATOR IN BOYS RESTROOM, REPLACE RADIATOR 3/4 VALVES IN WEST HALL, REPLACE RADIATOR 3/4 VALVES IN GIRLS RESTROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/04/01. HORNE ENGINEERING - STEPHEN CALDWELL (RG) | August 17, 2001 | March 13, 2003 | 573 days |
| Barnard Elementary School | FM-200120698 01 3/13/03 (BARNARD) ASBESTOS ASSESSMENT REQ. REPLACE FLOOR TILE IN ALL ROOMS THAT THE ARMY CORP OF ENGINEERS REMOVED FLOOR TILE. (RM. 203, 206 A AND B, 308, 226, HEALTH SUITE BY RE closed Safety Office THE BATHROOM, 211, AND 101 IN OLD BLDG. | September 28, 2001 | March 13, 2003 | 531 days |
| Langdon Elementary School | FM-200124660 /01 3/14/03 (LANGDON) Hot water leaking out of the Boys Bathroom Radiator Trap on the 1st floor (space 68)and the Radiator Trap in the Cafeteria (basement). Requester Phone: (202) 576-6048 Web Form Location ID: 262 Request or Phone: (202) 576-6048 Code A-clear for repair by Horne Engineer ( Sam Ebrahim ) on 4/15/02 Same work order has FM-200122725 Tracking # 10294 The code A was change to a code B for exploratory in Boys Bathroom Radiator Trap on the 1st floor. Fireproofing clean up in AMP rooms 16 and 185/EXP Demo 1st floor Boys Restroom. Envirobate - Charles Crenshaw - 571-436-1150 | October 29, 2001 | March 14, 2003 | 501 days |
| Slowe Elementary School | FM-200224983 03 3/14/03 (Slowe) !!!URGENT!!! Second Floor/boy's restroom Unclogged three (3) urinals backing up.slop sink. | January 31, 2003 | March 14, 2003 | 42 days |
| Lincoln Middle School | FM-200226688 03 3/14/03 Lincoln/Taft Second floor girls restroom Two (2) broken windows need to be replaced. | March 6, 2003 | March 14, 2003 | 8 days |
| Barnard Elementary School | FM-200203036 02 3/17/03 BARNARD GIRL'S RESTROOM FIRST FLOOR 1.) ASBESTOS ASSESSMENT REQUIRED 2.) REPAIR SHORT NIPPLE ON SUPPLY LINE TO RADIATOR IN THE GIRLS RESTROOM. LINE CAN NOT BE ISOLATED AND IS LEAKING LIVE STEAM WHICH POSES AS A SAFETY HAZARD FOR STUDENTS. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/19/02 HORNE ENGINEER: TROY WILCOME TRACKING # 12384 | February 15, 2002 | March 17, 2003 | 395 days |
| Seaton Elementary School | FM-200205747 02 3/17/03 Seaton Boiler Room Replace 1 1/4" valve in the boiler room that feeds bathroom above. Sited by health inspector. | April 12, 2002 | March 17, 2003 | 339 days |
| Ronald H. Brown MS | FM-200226149 03 3/17/03 Brown, Ron First floor Boys restroom near stairway # 10 need new toilet, old one broken due to student vandalism. | February 25, 2003 | March 17, 2003 | 20 days |
| Dunbar High School | FM-200220316 /02 3/17/03 (Dunbar) Re-mount ADA sink with CMU imbedded carrier in the library/Media girls restroom. Asbestos Code A - Clear for repairs on 03/07/03. Horne Engineering - Roger Kager (RG 03/07/03) | October 29, 2002 | March 17, 2003 | 139 days |
| Bunker Hill Elementary School | FM-200216223 02 3/17/03 Bunker 2nd Floor Girls' & Boys' Restrooms/West Wing 1. Repair leaking commode in the girls' restroom; 2. Replace valve on commode in boys' toilet that is continuously running. and 3. Repair urinal in boys' restroom that is leaking. . | August 30, 2002 | March 17, 2003 | 199 days |
| Amidon Elementary School | FM-200218940 02 3/17/03 (Amidon) !!!URGENT!!! 1st Floor/Gym: Need someone to come out to repair the bradley basins in th gym. The one in the boys bathroom is leaking from the bottom, and the one in the girls bathroom is spraying water on-to the floor. Asbestos Code A - Clear for repairs on 10/08/02. DCPS Safety - Leroy Minton Jr. (RG 10/10/02) | October 7, 2002 | March 17, 2003 | 161 days |
| Thomson Elementary School | FM-200204412 02 3/17/03 (Thomson) ****Emergency**** Basement Boiler Room There is a leak in the ceiling [coming from the cold water supply line {3/4-inch galvanized copper pipe}] near boiler #1. The leak is between the T and the elbow & the water runoff is collecting in the restroom above. POC: Mr. Oneill Asbestos Code A - Clear For Repairs On 03/14/02. Richard Gibson - DCPS-Safety (RG 03/14/02) | March 14, 2002 | March 17, 2003 | 368 days |
| Garfield ES | FM-200215448 02 3/18/03 Garfield F-303.4 Fire Code Violation 2nd Floor/New Wing Room 200 [Restroom] Replace door hardware. | August 23, 2002 | March 18, 2003 | 207 days |
| Garfield ES | FM-200215457 02 3/18/03 Garfield F-303.4 Fire Code Violation 2nd Floor/New Wing Boys' Restroom Replace door hardware. | August 23, 2002 | March 18, 2003 | 207 days |
| Garfield ES | FM-200215463 02 3/18/03 Garfield F-303.4 Fire Code Violation 1st Floor Room 100 [Restroom] Need door hardware. | August 23, 2002 | March 18, 2003 | 207 days |
| Garfield ES | FM-200215472 02 3/18/03 Garfield F303.4 Fire Code Violation 1st Floor New Wing/Boys' Restroom Missing hardware. | August 23, 2002 | March 18, 2003 | 207 days |
| Marshall Educational Center | FM-200107468 01 3/19/03 MARSHALL SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE. 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | April 5, 2001 | March 19, 2003 | 713 days |
| Macfarland Middle School | FM-200202474 02 3/19/03 (MACFARLAND) 3RD FLOOR BOYS GYM REPAIR ALL RADIATOR GUARDS IN BOYS GYM & REHANG ON THE WALL (SAFETY HAZARD). 3RD FLOOR GYM BOYS BATHROOM GROUNDS REPAIR A CONCRETE HOLE IN BOYS BATHROOM FLOOR 3 X 3 HOLE | February 5, 2002 | March 19, 2003 | 407 days |
| Thomas Elementary School | FM-200226843 03 3/19/03 (Thomas) 1st & 2nd Floor: Repair or replace locks so that the doors can be secured in the following area's: All purpose room, dressing room, girls restrooms, closets, and main office restroom. | March 11, 2003 | March 19, 2003 | 8 days |
| Whittier Elementary School | FM-200219276 /02 3/19/03 Whittier Second floor - Girls restroom new side Toilet is stopped up in-house was not able to unstop toilet. Asbestos Code A - Clear for repairs on 10/15/02. DCPS Safety - Leroy Minton Jr. (RG 10/16/02) | October 11, 2002 | March 19, 2003 | 159 days |
| Hart Middle School | FM-200227173 03 3/19/03 HART First Floor - Boys Restroom And Teachers Restroom (New wing) Second Floor - Hallway Custodian Closet ( New wing - by stairwell #4) 1. Furnish and install locks . | March 17, 2003 | March 19, 2003 | 2 days |
| Whittier Elementary School | FM-200212671 02 3/19/03 (WHITTIER) 1. Asbestos Assessment Reqd. 1st-Floor Girls' Restroom/Old Wing 2. Reattach sinks to wall in girls' restroom---sinks are hanging away from the wall. Asbestos code A-clear for repair by Horne Engineer ( Sharon Voss ) on 8/06/02 DCPS Charles Buchanan | July 23, 2002 | March 19, 2003 | 239 days |
| Marshall Educational Center | FM-200124091 /01 3/20/03 MARSHALL SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 20, 2003 | 475 days |
| Bell High School | FM-200227265 03 3/20/03 (Bell) 2nd Floor/Mens Teachers Bathroom: Repair existing toilet , vandalized by students. Custodial staff unable to control water. | March 18, 2003 | March 20, 2003 | 2 days |
| Ferebee-Hope Elementary School | FM-200124090 /01 3/20/03 FEREBEE HOPE SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 20, 2003 | 475 days |
| Woodson High School | FM-200124095 /01 3/20/03 WOODSON, HD SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 20, 2003 | 475 days |
| Roosevelt High School | FM-200124092 /01 3/20/03 ROOSEVELT SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 20, 2003 | 475 days |
| Ferebee-Hope Elementary School | FM-200226098 03 3/20/03 Ferebee-Hope First floor - Mens bathroom by main office Plumbing need K-50 to unstop toilet. | February 24, 2003 | March 20, 2003 | 24 days |
| Dunbar High School | FM-200124085 /01 3/20/03 DUNBAR SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 20, 2003 | 475 days |
| Reed LC | FM-200124086 /01 3/20/03 MARIE REED SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 20, 2003 | 475 days |
| Wilson High School | FM-200124088 /01 3/20/03 W. WILSON SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 20, 2003 | 475 days |
| Cook J.F. Elementary School | FM-200225764 03 3/21/03 Cook. J.F. First floor room 102 The sink in the bathroom is stopped up. | February 13, 2003 | March 21, 2003 | 36 days |
| Bunker Hill Elementary School | FM-200227228 03 3/21/03 Bunker 2nd Floor - Boys Restrooms/West Wing 1. Repair urinal in boys restroom that is leaking. . | March 18, 2003 | March 21, 2003 | 3 days |
| Ludlow-Taylor ES | FM-200227456 03 3/24/03 LUDLOW - TAYLOR !! EMERGENCY !! First Floor - Men Restroom 1. Please unclog toilet in the men restroom out side the multi purpose room. | March 21, 2003 | March 24, 2003 | 3 days |
| Clark Elementary School | FM-200226993 03 3/24/03 (Clark) 3rd Floor/Girls & Boys restroom: Repair or replace valves on 1st toilet that does not flush. 3rd Floor/Boys restroom: Unstop all toilets running over. Shut off valve is in on position . | March 13, 2003 | March 24, 2003 | 11 days |
| Brookland Elementary | FM-200227371 03 3/24/03 (Brookland) Ground Floor/Girls bathroom: All toilets are stopped up, custodian closed the bathroom down. Please respond, as no other bathroom on that floor. | March 20, 2003 | March 24, 2003 | 4 days |
| Patricia R Harris Ed Center | FM-200227502 03 3/25/03 Harris, P.R. Main floor - restroom 5, 6 and 7 The faucets are all loose and need to be tightened up. They are stripped and need parts. | March 24, 2003 | March 25, 2003 | 1 day |
| Macfarland Middle School | FM-200222544 /02 3/25/03 (Macfarland) This is a request for a work permit to replace wax ring on commode in the boys restroom | December 10, 2002 | March 25, 2003 | 105 days |
| Turner Elementary School | FM-200227365 03 3/25/03 TURNER First Floor - Girls Restroom ( Old side ) 1. Unstop sink in the girls restroom . | March 20, 2003 | March 25, 2003 | 5 days |
| Shaw JHS | FM-200124094 /01 3/25/03 SHAW SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 25, 2003 | 480 days |
| Cardozo High School | FM-200124089 /01 3/25/03 CARDOZO SWIMMING POOL 1) SWEEP MOP AND CLEAN SWIMMING POOL,POOL DECK,AND BATHROOM OF DIRT AND DEBRIS. 2) CHECK EQUIPMENT IN FILTRATION ROOM, FOR PROPER OPERATION. 3) OPEN-UP AND VALVE-OVER ALL PERTINENT VALVES ASSOCIATED WITH FILLING SWIMMING POOL 4) ADD CHEMICALS TO SWIMMING POOL THROUGH AUTOMATION SYSTEM. 5) CHECK WATER BALANCE 6) BACK WASH POOL. 7) CHECK D.E. TANK. 8) CHECK SAND FILTRATION SYSTEM. | November 30, 2001 | March 25, 2003 | 480 days |
| Patricia R Harris Ed Center | FM-200227504 03 3/25/03 Harris, P.R. Main floor boys restroom# 1 stairwell area The urinal will run over when you flush it. The urinal need a flush valve also and need to be unstop. It seems to be something stuck in the line . | March 24, 2003 | March 25, 2003 | 1 day |
| Webb Elementary School | FM-200227618 03 3/25/03 WEBB SECOND FLOOR - BOYS RESTROOM 1. UNSTOP URINALS IN THE BOYS RESTROOM . | March 25, 2003 | March 25, 2003 | 0 days |
| Spingarn High School | FM-200117388 01 3/25/03 SPINGARN 1ST, 2ND & 3RD FLOOR RESTROOMS ASBESTOS ASSESSMENT REQUIRED THERE IS NO HOT WATER IN THE RESTROOMS THROUGHOUT THIS BLDG. MIDDLE STATES ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/04/01. HORNE ENGINEERING - EDWARD RODRIGUEZ | August 14, 2001 | March 25, 2003 | 588 days |
| Turner Elementary School | FM-200121882 /01 3/25/03 (TURNER) !!!EMERGENCY!!! OLD BUILDING/GIRLS BATHROOM: 1. ASBESTOS ASSESSMENT REQUIRED FOR FLOOR AND CEILING. 2. REPAIR/REPLACE LEAKS ON SUPPLY AND RETURN LINE ON RADIATOR. LINE CAN NOT BE SECURED. LEAK IS BELOW FLOOR LEVEL. CODE A - ASBESTOS ABATED ON 10/30/01 (SG) PER SHEILA HOWARDS PRIORITY LIST. | October 18, 2001 | March 25, 2003 | 523 days |
| Cardozo High School | FM-200117971 01 3/25/03 (CARDOZO) GROUND FLOOR/ GIRLS BATHROOM REPLACE LAKING STOP VALVE ON SINK-COMPRESSION INLET 1/2 INCH x 3/8 INCH. CHECK COMPRESSION RISER TUBES WATER SUPPLY. | August 21, 2001 | March 25, 2003 | 581 days |
| Payne Elementary School | FM-200219685 /02 3/25/03 Payne First floor - Boys restroom Repair or replacement of urinals. Water is leaking from it. May be wax ring. | October 18, 2002 | March 25, 2003 | 158 days |
| Macfarland Middle School | FM-200222545 /02 3/25/03 (Macfarland) This request is to unclogg main line to urinals in the boys restroom on the first floor by the media center. | December 10, 2002 | March 25, 2003 | 105 days |
| Turner Elementary School | FM-200227412 03 3/25/03 TURNER Ground Floor - Kitchen And Restroom 1. Unclog floor drains in kitchen ,repair line twist handle on pot sink and toilets in restroom . | March 21, 2003 | March 25, 2003 | 4 days |
| Powell Elementary School | FM-200103042 01 3/25/03 POWELL ROOF (NEW ADDITON) REPAIR OR REPLACE EXHAUST FAN THAT IS INOPERABLE AND OUTDATED. THERE IS NO INFORMATION ON UNIT DUE TO OUTDATED EQUIPMENT. EXHAUST FAN IS NEED TO PULL EXHAUST FROM BATHROOMS NEW ADDITION. | February 6, 2001 | March 25, 2003 | 777 days |
| Cooke H.D. Elementary School | FM-200221204 /02 3/26/03 Cooke, H.D. - T-9 Basement boys restroom Pipe leaking from ceiling. Asbestos Code A-clear for repair by Horne Engineer Bipin Nanavaty DCPS Safety on 11/21/02 Charles E. Buchanan | November 18, 2002 | March 26, 2003 | 128 days |
| Benning Elementary School | FM-200227566 03 3/26/03 (Benning) !!!VERY URGENT!!! Learning Center #1: Unable to unstop sink in the girls bathroom; appears to be a problem in the junction line. 03/26/03: call came in from engineer stating, water is coming out the sink, flooding the floors. | March 24, 2003 | March 26, 2003 | 2 days |
| Clark Elementary School | FM-200227167 03 3/26/03 CLARK THIRD FLOOR - BOYS RESTROOM 1. Unclog all toilets in the boys restroom . March 25, 2003: A call came in from the engineer stating, repairs were never made. Conditions has worsened; students have fallen on the wet floor, possible of injury to others. (Locations/Boys and Girls toilets) | March 17, 2003 | March 26, 2003 | 9 days |
| Bunker Hill Elementary School | FM-200222132 02 3/26/03 Bunker Hill Nurse's Restroom Asbestos assessment required Repair and replace leaking steam coil in Nurse Office restroom on 1st floor. Asbestos Code A - Clear for repairs on 12/09/02. Horne Engineering - Sheryll James (RG 12/12/02) | December 6, 2002 | March 26, 2003 | 110 days |
| Garnet-Patterson MS | FM-200206233 02 3/27/03 Garnet-Patterson !!! Emergency !!! Basement - Bathroom in Lunch Room Tank on toilet is not filling up with water. I check the valves and its is on! No hot water, and low water pressure also, almost no water in toilet behind cafeteria in bathroom used by workers, also. A.S.A.P. | April 22, 2002 | March 27, 2003 | 339 days |
| Garnet-Patterson MS | FM-200218414 02 3/27/03 Garnet-Patterson 2nd Floor Health Suite Restroom Both toilets are backed up and need to be cleared. | September 26, 2002 | March 27, 2003 | 182 days |
| Emery Elementary School | FM-200227809 03 3/27/03 EMERY Second Floor Boys Restroom . 1. Unstop five urinals in the boys restroom . ( URGENT ) | March 27, 2003 | March 27, 2003 | 0 days |
| Garnet-Patterson MS | FM-200209614 02 3/27/03 Garnet-Patterson 2nd Floor Health Suite Snake out the toilet in the bathroom on the left side of the health suite office. | June 14, 2002 | March 27, 2003 | 286 days |
| West Elementary School | FM-200227106 03 3/28/03 WEST First Floor - Storerooms 1. Storeroom inside of maintenance office , 2. Storeroom beside maintenace office , in gym on the left side , 3. Learning center storeroom left and right side of boys restrooms all need new door knobs . Asbestos Code - A Cleared for repairs on 03-26-03 by Leroy Minton Jr (LM/03-25-03) Safety Office 202-576-8962. | March 14, 2003 | March 28, 2003 | 14 days |
| Shaw JHS | FM-200225992 03 3/28/03 Locksmith needed for two area,s 1.First floor room 147 Ms. wiggins 2. Basement teacher,s restroom by Mr. Wright room. Please send someone to fix these two locks. Code A - Clear for repairs on 03/26/03. DCPS Safety - Saeed Rahimi (RG 03/27/03) | February 5, 2003 | March 28, 2003 | 51 days |
| Ludlow-Taylor ES | FM-200111656 01 3/28/03 LUDLOW-TAYLOR THIRD FLOOR WOMENS RESTROOM 1) REPLACE SINK LARGE HOLE ON BOTTOM OF SINK ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/21/01. LEROY MINTON - SAFETY (202)576-6691 | May 30, 2001 | March 28, 2003 | 667 days |
| Roosevelt High School | FM-200227294 03 3/31/03 ROOSEVELT Ground Floor - Kitchen and Ladies restroom 1. Repair two flush valves inside of ladies room and existing hand sinks . Asbestos Code A - Clear for repairs on 03/19/03. DCPS Safety - Richard Gibson (RG) | March 19, 2003 | March 31, 2003 | 12 days |
| Gibbs Elementary School | FM-200224280 03 3/31/03 Gibbs First floor - Kgn Front door to classroom and their bathroom is falling off the hinges. Asbestos Code A-clear for by Safety Office on 01/29/03 Charles Buchanan | January 21, 2003 | March 31, 2003 | 69 days |
| Eaton Elementary School | FM-200225168 03 3/31/03 Eaton Third floor girls room 301 west Replace broken hinges on girls toilet door. | February 4, 2003 | March 31, 2003 | 55 days |
| Roosevelt High School | FM-200225155 03 3/31/03 (Roosevelt) Ground floor/Boys locker room: Repair four (4) broken commodes inside boys bathroom; at present, bathrooms are out of order, and can't be used. | February 4, 2003 | March 31, 2003 | 55 days |
| Ronald H. Brown MS | FM-200227588 03 3/31/03 BROWN, RON (ROPER) Second floor - Boys restroom and room 224 Boys restroom by gym and room 224 keys were lost. Need new keys or replace locks. | March 25, 2003 | March 31, 2003 | 6 days |
| Bunker Hill Elementary School | FM-200228067 03 4/1/03 BUNKER-HILL First Floor - East Wing 1. Repair and or replace faucet in teachers restroom . | April 1, 2003 | April 1, 2003 | 0 days |
| Ballou Senior High School | FM-200118039 01 4/1/03 (BALLOU) ASBESTOS ASSESSMENT REQD. GROUND FLOOR OUTSIDE ROOM A-1-TEACHERS RESTROOM CYLINDER ON LOCK IS CONSTANTLY TURNING *LOCKSMITHS NEEDED* ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/29/01. RONALD EDWARDS - SAFETY (202)576-6693 | August 21, 2001 | April 1, 2003 | 588 days |
| Bunker Hill Elementary School | FM-200227849 03 4/1/03 (Bunker-Hill) East Wing/1st Floor: Unable to use bradley basin for washing hands in the girls restroom. (No water available) | March 28, 2003 | April 1, 2003 | 4 days |
| Hendley Elementary School | FM-200120055 01 4/1/03 (HENDLEY) ASBESTOS ASSESSMENT REQ. KEYS ARE NEEDED FOR THE BUILDING, BATHROOM KEYS FOR 2ND AND 3RD FLOORS, ROOMS 302 AND 305. 15- BATHROOM KEYS 10- ELEVATOR KEYS 1 EACH- 302 AND 305 ASST. PRINCIPALS OFFICE NEED THE LOCK CHANGED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/21/01. LEROY MINTON - SAFETY (202)576-6691 | September 18, 2001 | April 1, 2003 | 560 days |
| Eliot Junior High School | FM-200227388 03 4/2/03 Eliot Boys restroom first floor Water running on floor. | March 20, 2003 | April 2, 2003 | 13 days |
| Birney Elementary School | FM-200120920 01 4/2/03 (BIRNEY) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS BATHROOM NEW SIDE CEILING IN BOYS BATHROOM NEED TO BE REPLACED BECAUSE ASBESTOS HAD TO CHECK FOR A LEAK IN THE CEILING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/16/01. HORNE ENGINEERING - TROY WILCOME (RG) | October 3, 2001 | April 2, 2003 | 546 days |
| Patricia R Harris Ed Center | FM-200120729 01 4/2/03 (HARRIS, P.R.) ASBESTOS ASSESSMENT REQ. #1 STAIRWELL/ TEACHERS RESTROOM DOOR WILL NOT CLOSE. NEEDS TO BE CUT DOWN SO IT WILL CLOSE. ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/23/01 HORNE ENGINEER : EDWARD RODRIGUEZ | October 1, 2001 | April 2, 2003 | 548 days |
| Beers Elementary School | FM-200227999 03 4/3/03 Beers First floor restrooms Boys and girls have cinderblocks missing, pipe fitter doing pipe work. Have the cinderblocks in house. Principal request. | April 1, 2003 | April 3, 2003 | 2 days |
| Merritt Middle School | FM-200219132 02 4/4/03 Merritt Kitchen staff restroom, Staff restroom in Pre-k area Hot water faucets cannot turn it off, and it continousl to run it is very dangerous. | October 9, 2002 | April 4, 2003 | 177 days |
| Patricia R Harris Ed Center | FM-200224218 03 4/4/03 Harris, P.R. First floor - Boys restroom by stairwell #1 Ground floor - Boys restroom by stairwell #7 Urinal bowl when flushed, leaks on floor. Pull from wall due to students standing on it. Remove from wall secure brackets and reinstall bowl. Asbestos Code A - Clear for repairs on 01/23/03. Horne Engineering - Bipin Nanavaty (RG 01/24/03) | January 21, 2003 | April 4, 2003 | 73 days |
| Patricia R Harris Ed Center | FM-200206647 02 4/4/03 Harris,P.R. Ground Floor/Restroom @ #85 Stairway The toilet will not flush [needs parts]. | April 25, 2002 | April 4, 2003 | 344 days |
| Sousa Middle School | FM-200228342 03 4/5/03 (Sousa) Boys restroom on 2nd floor. 1st toilet will not hold water. Water leaking from back of toilet. | April 3, 2003 | April 5, 2003 | 2 days |
| Payne Elementary School | FM-200227170 03 4/7/03 (Payne) !!!VERY URGENT!!! New Wing/1st Floor boys restroom: Water leaking from flush valves; unable to shut off the water. 03/20/03, calls came in today, conditions are critical. | March 17, 2003 | April 7, 2003 | 21 days |
| Deal Junior High School | FM-200226503 03 4/7/03 Deal Basement girls restroom and bookroom Survey electrical problem. No lights in these arears. Breaker will not reset. | March 4, 2003 | April 7, 2003 | 34 days |
| Spingarn High School | FM-200223744 03 4/7/03 Spingarn Cafe. Bathroom Replace hot water coil in cafeteria bathroom 6' X 23" | January 13, 2003 | April 7, 2003 | 84 days |
| Coolidge High School | FM-200227181 03 4/8/03 Coolidge Old Girls & Boys Basement Lockeroom Asbestos Assestment Required Abate ruptured steamline in ceiling boys bathroom old lockeroom Asbestos Code A - Clear for repairs on 03/19/03. Horne Engineering - Bipin Nanavaty (RG 03/20/03) | March 17, 2003 | April 8, 2003 | 22 days |
| Coolidge High School | FM-200228196 03 4/8/03 Coolidge High School Repair hole in the wall in the basement next to the boys restroom | April 3, 2003 | April 8, 2003 | 5 days |
| Eastern High School | FM-200122666 /01 4/9/03 (EASTERN) ASBESTOS ASSESSMENT REQ. BASEMENT/ HANDICAP RESTROOM, GYM REPLACE DOOR KNOB ON BATH WITH CYLINDER LOCK AND ARM HANDLE. AASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: RAYMOND AGNANT | October 31, 2001 | April 9, 2003 | 525 days |
| Coolidge High School | FM-200224145 03 4/9/03 Coolidge Ground - Boys Restroom 1) Install new sink inside this restroom. Newly installed sink vandalized broken off wall. | January 17, 2003 | April 9, 2003 | 82 days |
| Birney Elementary School | FM-200213841 02 4/10/03 (Birney) Fire code violation: Page 1of 2 1. Asbestos assessment required. 2nd Floor/Boys restroom: Hole in ceiling (Boys restroom) Cover hole in wall. Asbestos Code A - Clear for repairs on 08/09/02. DCPS-Safety - Leroy Minton Jr. (RG 08/09/02) | August 8, 2002 | April 10, 2003 | 245 days |
| Eastern High School | FM-200226278 03 4/10/03 Eastern Stadium bathroom shed door. Repair or replace locks in shed that holds equipment. Welders came by to survey to put security device on locks to prevent vandalism. | February 26, 2003 | April 10, 2003 | 43 days |
| Johnson JHS | FM-200228559 03 4/10/03 JOHNSON EMERGENCY Second Floor - Girls Restroom 1. Toilet over flowing can't shut off valve , second and first floors is flooded . | April 10, 2003 | April 10, 2003 | 0 days |
| Cook J.F. Elementary School | FM-200228697 03 4/11/03 Cook, J.F. First floor an other areas Water running in boys room. | April 11, 2003 | April 11, 2003 | 0 days |
| Ferebee-Hope Elementary School | FM-200214576 02 4/11/03 Ferebee-Hope F-110.1(1) Fire Code Violation 1. Asbestos Assessment Reqd. 2nd Floor Girls' Bathroom & Custodian's Closet 2. Ceiling tiles need replacement. AsbestosCode A-clear for repair by Horne Engineer ( Troy Welcome ) Charles Buchanan on 8/19/02 | August 15, 2002 | April 11, 2003 | 239 days |
| Payne Elementary School | FM-200226991 03 4/13/03 Payne 1st Floor Hall Lobby Asbestos assessment need 1st floor Hall Lobby by Girls bathroom, Plaster ceiling and pipe insulation. Repair steam leak pipe in wall and ceiling of 1st floor hall lobby by girls restroom. | March 13, 2003 | April 13, 2003 | 31 days |
| Houston Elementary School | FM-200228790 03 4/15/03 Houston Emergency First floor Principal Cut off valve is leaking. there is a bucket under toilet to catch water. There is carpet in the bathroom. | April 15, 2003 | April 15, 2003 | 0 days |
| Kenilworth ES | FM-200228454 03 4/16/03 Kenilworth Third floor boys restroom Repair wall in re-hang sink (cinder block). | April 8, 2003 | April 16, 2003 | 8 days |
| Brent Elementary School | FM-200217148 02 4/16/03 (Brent) "URGENT" 3rd Floor: Brick mason needed to repair area in the boys bathroom on the 3rd floor; need to re-hang urinals. (Re: FM-200202435) | September 10, 2002 | April 16, 2003 | 218 days |
| Eastern High School | FM-200228591 03 4/18/03 Eastern Rooms 342, 149 and stadium girls bathroom Room 342 - replace lock cylinder that has been removed due to vandalism, the room is full of sewing machines the class has been abushed right now equipment is unsecured. Room 149 lock can be jammed to open and closed having problems securing room. Repair replace girls stadium bathroom lock. | April 10, 2003 | April 18, 2003 | 8 days |
| Cook J.F. Elementary School | FM-200201439 02 4/21/03 (COOK,J.F.) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR BOYS BATHROOM REPAIR/REPLACE TWO 8-INCH SPEED FAUCETS WHICH ARE LEAKING. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/28/02 RICHARD GIBSON - SAFETY (202)576-5584 (RG)-01/28/02 | January 22, 2002 | April 21, 2003 | 454 days |
| Garnet-Patterson MS | FM-200209615 02 4/22/03 Garnet-Patterson 3rd Floor Boys' Restroom Replace door closer on the 3rd floor boys' restroom door. | June 14, 2002 | April 22, 2003 | 312 days |
| Rudolph Elementary School | FM-200226677 03 4/22/03 RUDOLPH First Floor - Old Wing Near Room 104 Boys restroom repair commode , water leaks when you flush . ( located next to the window ) | March 6, 2003 | April 22, 2003 | 47 days |
| Woodson High School | FM-200328960 03 4/22/03 (Woodson, H.D.) 3rd Floor/Boys restroom: Water coming from under commode, flooding the floors in the halls, and classrooms. | April 22, 2003 | April 22, 2003 | 0 days |
| Wilkinson ES | FM-200328979 03 4/23/03 (Wilkinson) !!!VERY URGENT!!! 1st Floor Cafeteria restroom #126: Toilet over flows when flushed. | April 23, 2003 | April 23, 2003 | 0 days |
| Kenilworth ES | FM-200217961 02 4/30/03 Kenilworth ****Urgent**** Asbestos Assessment Reqd. 3rd Floor Boys' Restroom Two sinks are backed up and there is water running from one to the other. [NOTE: After observing the job, it was decided that the wall had to be penetrated to effect repair.] Asbestos Code A - Cleared for repairs on 10-21-02 (LM 10/24/02) Leroy Minton Jr. Safety Office 202-576-8962. | September 20, 2002 | April 30, 2003 | 222 days |
| Orr Elementary School | FM-200223871 03 4/30/03 (Orr) 1st Floor/Kindergarten classroom: When commode is flushed, water is coming from under the toilet. (Smell of urine present in bathroom) Asbestos Code A - Clear for repairs on 01/14/03. Horne Engineering - Troy Wilcome (RG 01/15/03) | January 13, 2003 | April 30, 2003 | 107 days |
| Patricia R Harris Ed Center | FM-200224809 03 4/30/03 Harris, P.R. No. #8 restroom Top floor #2 Water keeps running from spud nut and will not stop. | January 29, 2003 | April 30, 2003 | 91 days |
| Patricia R Harris Ed Center | FM-200224810 03 4/30/03 Harris, P.R. No. #7 restroom main floor Stand up toilet will not flush. | January 29, 2003 | April 30, 2003 | 91 days |
| Davis Elementary School | FM-200329292 03 5/1/03 (Davis) Basement/Lunchroom: Repair or replace lock cylinder to exit door, near girls bathroom as soon as possible. Engineer unable to get in. | April 30, 2003 | May 1, 2003 | 1 day |
| Anacostia Senior High School | FM-200329444 03 5/2/03 (Anacostia) Basement/ROTC Bathrooms: Backup in toilets, and urinals. Water pouring out toilet. | May 2, 2003 | May 2, 2003 | 0 days |
| Nalle Elementary School | FM-200329385 03 5/4/03 J.C Nalle E.S Bathroom Steamline (Trap) First Floor Insulate 1 1/2 copper line and return steam trap. Pre-K student burned her face due to uncovered line | May 2, 2003 | May 4, 2003 | 2 days |
| Savoy Elementary School | FM-200220258 /02 5/5/03 (Savoy) No hot water at hand sink in restroom. The is an emergency request. | October 22, 2002 | May 5, 2003 | 195 days |
| Coolidge High School | FM-200329131 03 5/5/03 Coolidge Ground - Boys Restroom 1) Install two sink inside this restroom due to vandalizum. New work order. | April 28, 2003 | May 5, 2003 | 7 days |
| Wilkinson ES | FM-200225369 03 5/5/03 Wilkinson Second floor - boys bathroom Urinal is backing up and cut off valve is stripped need replacing. | February 6, 2003 | May 5, 2003 | 88 days |
| Tubman Elementary School | FM-200329762 03 5/8/03 (Tubman First floor space 18 boys restroom Replace valve assembly on urinal. | May 8, 2003 | May 8, 2003 | 0 days |
| Walker-Jones EC | FM-200219131 02 5/8/03 Walker-Jones Mechanical Room/Closet Repair/replace defective motor for restroom exhaust fan. Fan: Howell electric motor Serial # 4630 F1 1 HP 440/220 V A203 1730 RPM 3 PH | October 9, 2002 | May 8, 2003 | 211 days |
| Kimball Elementary School | FM-200210532 02 5/9/03 Kimball 1. Asbestos Assessment Reqd. 1st Floor Boys' Bathroom/Middle Wing 2. Scrape and paint ceiling. Asbestos/Lead Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) on 07/01/02 DCPS CE Buchanan | June 27, 2002 | May 9, 2003 | 316 days |
| Stevens Elementary School | FM-200202776 02 5/12/03 STEVENS GRD. FL. BOYS BATHROOM, SOUTH SIDE OF BUILDING. 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR/REPLACE 1/2" RETURN LINE (STEAM PIPE IN BOYS BATHROOM--THE LINE IS IN THE WALL AND LEAKING. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/13/02 HORNE ENGINEER: Z MAHMOOD | February 11, 2002 | May 12, 2003 | 455 days |
| Hearst Elementary School | FM-200228606 03 5/12/03 Hearst Second floor girls bathroom Overflowing toilet need repairing. | April 10, 2003 | May 12, 2003 | 32 days |
| Payne Elementary School | FM-200228500 03 5/13/03 Payne First and second floor boys bathroom old bldg. Repair or replace flush valves and wax ring on urinals, can not turn off stop valve. | April 9, 2003 | May 13, 2003 | 34 days |
| Payne Elementary School | FM-200112337 01 5/13/03 PAYNE SECOND FLOOR BOYS RESTROOM NEW WING 1) WATER IS LEAKING FROM BASE UNDER SINK POSSIBLE BROKEN NIPPLE IN WALL Exp Demo 2nd floor boys bathroom. TSI repair AMP room 22,29,3,50,77,98, 119,120,129,102,55 fam room. Envirobate - Charles Crenshaw - 571-436-1150. Code A Clear for Repair asbestos abatement was 06-24-02 confirmed by Leroy Minton DCPS Safety Sheila R. Howard DCPS Safety 06-28-02. | June 4, 2001 | May 13, 2003 | 708 days |
| Malcolm X ES | FM-200216239 02 5/13/03 (Malcolm X) Fire code violation: 2nd Floor/Mens bathroom: Missing door knob from door. | August 30, 2002 | May 13, 2003 | 256 days |
| Patricia R Harris Ed Center | FM-200228757 03 5/14/03 Harris, P.R. Ground floor boys restroom big gym The toilet is out of order, will not flush. Please respond ASAP | April 15, 2003 | May 14, 2003 | 29 days |
| Merritt Middle School | FM-200222460 /02 5/14/03 (Merritt) !!!URGENT!!! 1st Floor/Cafeteria: Hot water constantly running hard in the bathroom; the water has been turned off, and each time it is turned on, it is running very hard. (Water is scalding hot) | December 12, 2002 | May 14, 2003 | 153 days |
| Merritt Middle School | FM-200221596 /02 5/14/03 (Merritt) 1st Floor girls restroom/East ramp: Tighten toilet to floor, flange, wax ring, and closets bolts, possible needs replacing. | November 25, 2002 | May 14, 2003 | 170 days |
| Shepherd ES | FM-200228078 03 5/14/03 (Shepherd) 2nd Floor/New wing: Repair pipe in boys bathroom, due too student standing on pipe breaking it. This is a cold water pipe leading from sink that had been dismounted. Water is running down to the other floors, including library halls, also, light fixtures. Shut off valve has been located, and the water is shut off. | April 1, 2003 | May 14, 2003 | 43 days |
| West Elementary School | FM-200224395 03 5/14/03 West First floor boys restrooms Wall urinal leaks from the wall in boys restroom in the right side of learning center also left side boys restroom toilet is stopped up my snake is not long enough to unstop it. See maintenance staff. | January 23, 2003 | May 14, 2003 | 111 days |
| Woodson High School | FM-200227874 03 5/14/03 (Woodson) !!!EMERGENCY!!! 3rd Floor/Girls restroom: Commode stopped up, and running over, as other toilets are flushed, all other toilets over-flow, and water, fecal matter, and other runs from the seventh floor too the bottom. | March 28, 2003 | May 14, 2003 | 47 days |
| Bancroft Elementary School | FM-200228583 03 5/14/03 Bancroft First floor main bldg. boys bathroom Replace packing behind second urinal. Asbestos Code A - Clear for repairs on 04/11/03. Horne Engineering - Tony Marcolin (RG 04/14/03) | April 10, 2003 | May 14, 2003 | 34 days |
| Stuart-Hobson Middle School | FM-200330010 03 5/15/03 (Stuart-Hobson) !!!VERY URGENT!!! 1st Floor/Boys restroom: Students pulled sink off wall; pipes broken, and water flooded the floors. Engineers have water under control. The water has been shut off. | May 9, 2003 | May 15, 2003 | 6 days |
| Bancroft Elementary School | FM-200227490 03 5/15/03 (Bancroft) !!!VERY URGENT!!! First floor open space (unisex bathroom) Replace flush valve, will not flush and backing up. | March 24, 2003 | May 15, 2003 | 52 days |
| Payne Elementary School | FM-200228462 03 5/15/03 (Payne) New wing,1st Floor/Girls restroom: Repair or replace flush valve on two (2) commodes; no water pressure. | April 8, 2003 | May 15, 2003 | 37 days |
| Drew Elementary School | FM-200201769 02 5/15/03 (DREW) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR BOYS RESTROOM REPAIR/REPLACE INTERNAL TRAP IN COMMODE, COMMODE WILL NOT RETAIN WATER. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/28/02 RICHARD GIBSON - SAFETY (202)576-5584 (RG)-01/28/02 | January 25, 2002 | May 15, 2003 | 475 days |
| Drew Elementary School | FM-200224389 03 5/15/03 (Drew) !!!URGENT!!! 1st Floor/Boys restroom: Urinal fallen off wall. Girls restroom/2nd and 4th commode stopped up. | January 22, 2003 | May 15, 2003 | 113 days |
| Truesdell Elementary | FM-200329738 03 5/15/03 (Truesdell) 1st floor/Girls restroom: !!VERY URGENT!! Both sinks are leaking from traps. Room #100: Both sinks are leaking from traps; floors are flooded. Instructed engineer to turn water off. | May 7, 2003 | May 15, 2003 | 8 days |
| Hendley Elementary School | FM-200225262 03 5/15/03 (Hendley) !!!URGENT!!! Through-out building: Low water pressure in bathrooms through-out the building. | February 5, 2003 | May 15, 2003 | 99 days |
| Gage-Eckington ES | FM-200329820 03 5/15/03 (Gage-Eckington) !!!VERY URGENT!!! 1st and 2nd Floor: Toilets running over in boys and girls bathroom, flooding the floors. | May 8, 2003 | May 15, 2003 | 7 days |
| Ferebee-Hope Elementary School | FM-200226860 03 5/15/03 (Ferebee-Hope) !!!EMERGENCY!!! 2nd Floor/Girls restroom: Valve broken that supply water to toilets, broken; water has been shut off on all floors to prevent flooding. | March 11, 2003 | May 15, 2003 | 65 days |
| Bancroft Elementary School | FM-200227491 03 5/15/03 (Bancroft) !!!VERY URGENT!!! First bldg. boys bathroom near auditorium Replace packing behind second urinals. | March 24, 2003 | May 15, 2003 | 52 days |
| Backus Middle School | FM-200228696 03 5/15/03 Backus First floor male restroom Repair two (2) urinals, they are leaking. | April 11, 2003 | May 15, 2003 | 34 days |
| Bancroft Elementary School | FM-200227492 03 5/15/03 (Bancroft) !!!VERY URGENT!!! Second floor girls bathroom Sink needs to be replace due to a child sitting on it. It has become a safety hazard with sharp pipes hanging out. | March 24, 2003 | May 15, 2003 | 52 days |
| Turner Elementary School | FM-200224442 03 5/15/03 Turner First and second floor - New bldg. New faucet is needed for sink in nurse office(first floor) and boys restroom (second floor), valves are turn off but water continue to run. Urgent | January 23, 2003 | May 15, 2003 | 112 days |
| Harris, C.W. ES | FM-200329302 03 5/15/03 (Harris) !!!URGENT!!! C.W. Harris Second Floor 5/6 Wing Boy's Restroom: Unstop 2 urinals; Girl's Restroom: Unstop 3 water closets (all will be marked with grey tape) Asbestos Code A - Cleared for repairs on 04-30-03 by Leroy Minton Jr. (LM/04-08-03) the Safety Office 202-576-8962. | April 30, 2003 | May 15, 2003 | 15 days |
| Harris, C.W. ES | FM-200329152 03 5/15/03 Harris, C.W.) Kindergarten wing/1st Floor: Main line stopped up in the girls bathroom. (Sink is off wall, and P-Trap is present. When toilet is flushed, water runs through P-Trap flooding the floors. | April 28, 2003 | May 15, 2003 | 17 days |
| Harris, C.W. ES | FM-200226366 03 5/15/03 Harris, CW First floor -boys bathroom Flood from two hand sinks were the water is not going down. Line is sealed off. | February 27, 2003 | May 15, 2003 | 77 days |
| Harris, C.W. ES | FM-200224384 03 5/15/03 Harris, C.W. First floor - boys bathroom Two sinks are backed up inside the line in the wall. | January 22, 2003 | May 15, 2003 | 113 days |
| Harris, C.W. ES | FM-200220645 /02 5/15/03 Harris, C.W. First floor - Boys bathroom Sink is crack around the faucet, water runs on floor . Broken off bracket. Week of 11/4/02-11/08/02 FM-200220882 Asbestos Code A-clear for repair by Charles E. Buchanan on 11/12/02 DCPS Charles E Buchanan | November 12, 2002 | May 15, 2003 | 184 days |
| Benjamin Banneker Academic HS | FM-200109580 01 5/15/03 (BANNEKER) 1. ASBESTOS ASSESSMENT REQUIRED. BASEMENT/BATHROOM KITCHEN: TOILET BACKED UP, ATTEMPTED TO SNAKE OUT. NEED PLUMBER. ASBESTOS CODE A - CLEAR FOR REPARS ON 06/05/01. | May 3, 2001 | May 15, 2003 | 742 days |
| Ross Elementary School | FM-200329120 03 5/15/03 Ross Bsement Boys restroom urinal will not flush. | April 28, 2003 | May 15, 2003 | 17 days |
| Tyler Elementary School | FM-200228365 03 5/16/03 (Tyler) Teacher restroom Replace flange and wax ring. | April 7, 2003 | May 16, 2003 | 39 days |
| Stuart-Hobson Middle School | FM-200225322 03 5/16/03 Stuart-Hobson Basement hall by restroom Water fountain is leaking underneath on to the floor. | February 6, 2003 | May 16, 2003 | 99 days |
| Jessie LaSalle Elementary | FM-200228460 03 5/16/03 LA SALLE EMERGENCY Basement - Boys Restroom 1. Shut off valve on sink is broken ,water is constantly running on the floor . | April 8, 2003 | May 16, 2003 | 38 days |
| Stanton Elementary School | FM-200330177 03 5/16/03 Stanton !! EMERGENCY !! Third Floor - Restrooms 1. Unstop toilets in the grils and boys restrooms . | May 15, 2003 | May 16, 2003 | 1 day |
| Houston Elementary School | FM-200226954 03 5/16/03 (Houston) Bathroom in room 147 water is not working. Children are not able to wash their hands. | March 11, 2003 | May 16, 2003 | 66 days |
| Slowe Elementary School | FM-200329233 03 5/16/03 Slowe Kitchen 1) Toilet backing up in bathroom. | April 30, 2003 | May 16, 2003 | 16 days |
| Gage-Eckington ES | FM-200329137 03 5/19/03 Gage-Eckington Second floor - Teacher lounge restroom There are two (2) toilets located in teachers restroom one (1) need to be fixed will not flush causing a odor also leaking water. Have several drinking fountains need repairing do to vandalism, not working etc....... We are limited drinking fountains. | April 28, 2003 | May 19, 2003 | 21 days |
| Eastern High School | FM-200224976 03 5/19/03 Eastern Stadium bathroom Furnish and install metal guards on doors in four bathrooms inside of football stadium, because vandals are destroying bathroom from time to time breaking lock cylinders and going into the bathrooms vandallizing face bowls, lights and dispenser. Furnish and install metal guards over scoreboard lights to prevent vandals from breaking bulbs, two (2) securegates into stadium to prevent vandals from entrance. | January 31, 2003 | May 19, 2003 | 108 days |
| Bancroft Elementary School | FM-200228199 03 5/19/03 Bancroft First floor open space unisex bathroom Replace flush valve, will not flush and backing up. Teachers bathroom replace towel, traps and other parts. | April 3, 2003 | May 19, 2003 | 46 days |
| Orr Elementary School | FM-200225279 03 5/19/03 (Orr) Open space, 1st Floor/bathroom: Tomb stone clamps, broken on light fixtures. This open space is for kindergarten class. | February 5, 2003 | May 19, 2003 | 103 days |
| Whittier Elementary School | FM-200209015 02 5/19/03 Whittier !!! Emergency !!! Basement - Outside Boys Restroom Install window guard | June 5, 2002 | May 19, 2003 | 348 days |
| Adams Elementary | FM-200330342 03 5/19/03 (Adams) !!!URGENT!!! 3rd Floor/Girls restroom: Busted pipe on the north side of the wall, water has been shut-off, and still running. | May 19, 2003 | May 19, 2003 | 0 days |
| Walker-Jones EC | FM-200222625 /02 5/19/03 Walker-Jones Second and third floor Install window cages to the boys and girls restrooms. | December 16, 2002 | May 19, 2003 | 154 days |
| Tubman Elementary School | FM-200330108 03 5/20/03 (Tubman) !!!VERY URGENT!!! 2nd Floor/Teachers Lounge bathroom: Key broke off in door of restroom. | May 13, 2003 | May 20, 2003 | 7 days |
| Slowe Elementary School | FM-200222280 /02 5/20/03 Slowe First floor boys restroom Boys restroom need bricks replaced under the sink. Asbestos Code A - Clear for repairs on 12/10/02. Horne Engineering -Donald Maglienti (RG 12/12/02) | December 10, 2002 | May 20, 2003 | 161 days |
| Hearst Elementary School | FM-200118882 01 5/20/03 (HEARST) 1. ASBESTOS ASSESSMENT REQUIRED. 1ST FLOOR RESTROOM: TOILETS OVERFLOWED ON THE FIRST FLOOR NEAR MAIN OFFICE, SPILLING, AND SOAKING CARPET IN CORRIDOR; RAW SEWAGE IS PRESENT. ASBESTOS CODE A - CLEAR FOR REPAIR ON 08/30/01. LEROY MINTON - SAFETY (202)576-6691 | August 30, 2001 | May 20, 2003 | 628 days |
| Burrville Elementary School | FM-200330336 03 5/21/03 Burrville Second floor north side girls bathroom Sink can off wall. | May 19, 2003 | May 21, 2003 | 2 days |
| Wilkinson ES | FM-200215997 02 5/21/03 Wilkinson F-110.1(1) 1999 D.C. supp. Fire code violation: First floor - Restroom between exit and room 192 Open ceiling. Asbestos Code A-clear for repair 8/29/02 DCPS Charles E. Buchanan | August 28, 2002 | May 21, 2003 | 266 days |
| Merritt Middle School | FM-200221705 /02 5/21/03 (Merritt) 1st Floor/Boys and girls restroom door: Lock inoperable on both doors; keys spin around in the cylinder when placed inside, trying to turn the locks. | November 26, 2002 | May 21, 2003 | 176 days |
| Woodson High School | FM-200330323 03 5/21/03 Woodson, H.D. Plaza Principals restroom Repair lock on door. Principal unable to gain entry. | May 19, 2003 | May 21, 2003 | 2 days |
| Beers Elementary School | FM-200119366 01 5/21/03 (BEERS) ASBESTOS ASSESSMNET REQ. BUILDING #2 / 2ND FLOOR GIRLS AND BOYS BATHROOMS GIRLS BATHROOM SINK LOOSE. BOYS BATHROOM SINK LOOSE, NO HOT WATER. * SINK MISSING GIRLS BATHROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/10/01. LEROY MINTON - SAFETY (202)576-6693 | September 7, 2001 | May 21, 2003 | 621 days |
| Beers Elementary School | FM-200329061 03 5/22/03 Beers First and second floor bldg 1and 2 Bldg. 2 first floor boys restroom first toilet stool needs to be replaced or repaired, please survey. Bldg. 1 second floor boys restroom urinal stopped up. Tried to fix (strong odor) fixtures need to be replaced/repaired. Bldg. 3 second floor girls and boys restrooms, fixtures have come apart, rusted. | April 25, 2003 | May 22, 2003 | 27 days |
| Walker-Jones EC | FM-200329300 03 5/23/03 (Walker Jones) ** URGENT DUE TO RECENT BREAK-IN ** The grate on the outside of the window of the basement boys bathroom is broken. Need welding and bolting to brick wall. | April 30, 2003 | May 23, 2003 | 23 days |
| Hendley Elementary School | FM-200228931 03 5/27/03 (Hendley) 2nd Floor/Boys restroom: Leaking profusely from cut-off valves, repair or replace. | April 22, 2003 | May 27, 2003 | 35 days |
| Coolidge High School | FM-200226949 03 5/28/03 (Coolidge( 2nd Floor/Girls restroom: Unstop toilet, staff was not successful in using the auger or plunger. Students will use the toilet even when it is closed off causing the bathroom to flood. | March 12, 2003 | May 28, 2003 | 77 days |
| Turner Elementary School | FM-200330637 03 5/28/03 Turner URGENT First and Third Floor 1. Replace broken suppy lines on two sinks in the girls restroom 3rd floor (old bldg ) , boys restroom first floor old bldg urinal continuous to run and flood the floor . | May 23, 2003 | May 28, 2003 | 5 days |
| Takoma Educational Center | FM-200330361 03 5/29/03 Takoma !! URGENT !! Second Floor - Girls Restroom 1. Repair leaking handicap toilet . | May 20, 2003 | May 29, 2003 | 9 days |
| Beers Elementary School | FM-200222670 /02 5/30/03 (Ross) 1. Asbestos assessment required. Basement-Boys bathroom/Next to cafeteria: Repair of replace door, rotted away from hinges. Asbestos Code A - Cleared for repairs on 01-17-03 by Leroy Minton Jr. (LM/01-17-03) Safety Office (202) 576-8962. | December 16, 2002 | May 30, 2003 | 165 days |
| Beers Elementary School | FM-200218886 02 5/30/03 Beers First and second floor - Bldg. 0ne, two and three Custodian closet and bathroom doors, door check are damaged and broken. Asbestos Code A-clear for repair by DCPS Safety on 10/07/02 DCPS Charles E. Buchanan | October 4, 2002 | May 30, 2003 | 238 days |
| Beers Elementary School | FM-200217947 02 5/30/03 (Beers) 1st & 2nd Floors/Bldgs. 1, 2 & 3 The custodian closet and restroom doors have broken hardware [door closers] that need to be replaced. | September 19, 2002 | May 30, 2003 | 253 days |
| Whittier Elementary School | FM-200330871 03 5/30/03 (Whittier) !!!VERY URGENT!!! 1st Floor/Boys Bathroom: Repair control valve, water continues to run since last night; unable to shut water off. | May 29, 2003 | May 30, 2003 | 1 day |
| Powell Elementary School | FM-200228726 03 5/30/03 (Powell) Playground exit door steps are breaking up need to be repaired. near restroom door on old side of building. | March 5, 2003 | May 30, 2003 | 86 days |
| Leckie Elementary School | FM-200329854 03 6/2/03 Leckie Boys and girl restroom Sink need to be remote to wall. | May 9, 2003 | June 2, 2003 | 24 days |
| Shepherd ES | FM-200228163 03 6/2/03 Shepherd First floor new wing office corridor, teachers bathroom and library corridor Replace ceiling tiles damaged by second floor flood. Check light fixtures in exit area since flood gushed through it. Asbestos Code A - Clear for repairs on 04/07/03. Horne Engineering - Bipin Nanavaty (RG 04/08/03) | April 2, 2003 | June 2, 2003 | 61 days |
| Smothers ES | FM-200331010 03 6/2/03 (Smothers) 1st Floor/Girls Restroom: Window grate fell from girls restroom to playground below; "just so fortunate, students were not playing in that area at the time". Please replace window grate on window, to prevent vandals from gaining entry to the building. ATTENTION: Requesting a survey of window grates through-out the building for the safety of the students, and staff, as there could be other window grates that are not secure. | June 2, 2003 | June 2, 2003 | 0 days |
| Gage-Eckington ES | FM-200329091 03 6/3/03 (Gage-Eckington) 2nd Floor/Teacher Lounge: There are two (2) toilets located in restroom, one (1) need to be repaired. This broken toilet will not flush, causing an odor, also, leaking water. | April 25, 2003 | June 3, 2003 | 39 days |
| Patricia R Harris Ed Center | FM-200330599 03 6/3/03 Harris, P.R. Girls locker room restroom Commode flush half way. Need to be adjusted repair needed. Plummer needed. | May 22, 2003 | June 3, 2003 | 12 days |
| Patricia R Harris Ed Center | FM-200330603 03 6/3/03 Harris, P.R. Girls restroom # 8 Commode stopped up need to be snake out. Plummer needed. | May 22, 2003 | June 3, 2003 | 12 days |
| Kimball Elementary School | FM-200330710 03 6/3/03 (Kimball) !!!URGENT!!! North Wing/1st Floor: Replace windows in the following rooms: Speech room, Boys, and girls bathroom, and classroom #103. | May 27, 2003 | June 3, 2003 | 7 days |
| Patricia R Harris Ed Center | FM-200330601 03 6/3/03 Harris, P.R. 104 B Counselor office restroom Need plummer - short flush on commode. Repair needed. Possible adjusting is needed. | May 22, 2003 | June 3, 2003 | 12 days |
| Smothers ES | FM-200219042 02 6/3/03 Smother First and second floor 1.) First floor boys bathroom, water to five urinals being cut off, due to pipe leakage and stopped up urinals, water supply line leaking behind the wall. 2.) Drinking fountain stopped up on second floor in hallway. Asbestos Code A - Clear for repairs on 10/09/02. Horne Engineering - Philp Connolly (RG 10/11/02) | October 8, 2002 | June 3, 2003 | 238 days |
| Anacostia Senior High School | FM-200214734 02 6/3/03 (Anacostia) Fire code violation: Page 1 of 6 1. Asbestos assessment required. 3rd Floor: Hole in wall next to girls bathroom. Asbestos code A-clear for repair by Horne Engineer ( Sharon Voss ) on 8/19/02 Charles E. Buchanan | August 16, 2002 | June 3, 2003 | 291 days |
| Patricia R Harris Ed Center | FM-200330600 03 6/3/03 Harris, P.R. Boys restroom # 1 Need plummer. Problem with 1-handle (sticks on urinal) Some area commode stopped up- flush halfway only needs to be adjusted. | May 22, 2003 | June 3, 2003 | 12 days |
| Patricia R Harris Ed Center | FM-200330605 03 6/3/03 Harris, P.R. Girls restroom # 6 Two (2) leaking handles and one (1) short flush on commode. Repair / Replace. Plummer needed. | May 22, 2003 | June 3, 2003 | 12 days |
| Thomas Elementary School | FM-200330816 03 6/4/03 Thomas First and Second Floor - Girls Restrooms 1. Repair and or replace locks on girls restrooms . Asbestos Code A - Clear for repairs on 05-28-03 by Ed Rodrigues (LM/05-29-03) Safety Office 202-576-8962 | May 29, 2003 | June 4, 2003 | 6 days |
| Coolidge High School | FM-200330709 03 6/4/03 (Coolidge) Ground Floor/Boys bathroom: Two (2) urinals stopped up, over-flowing, and flooding the floors. | May 27, 2003 | June 4, 2003 | 8 days |
| Gibbs Elementary School | FM-200227665 03 6/4/03 Gibbs Second floor boys restroom Urinal will not flush also need a cut off valve the old one is not working. | March 26, 2003 | June 4, 2003 | 70 days |
| Gibbs Elementary School | FM-200216788 02 6/5/03 Gibbs 2nd Floor Boys' Restroom Repair Bradley basin in boys' area. | September 6, 2002 | June 5, 2003 | 272 days |
| Ross Elementary School | FM-200227771 03 6/5/03 Ross The railing have come out of the wall between the first and second floor stairwell. On the North side is were the repair is needed. Hazard The boys and girls bathroom door is coming off the hinges, hazard to the children. Asbestos Code A - Clear for repairs on 03/27/03. Horne Engineering - Sharon Voss (RG 03/28/03) | March 27, 2003 | June 5, 2003 | 70 days |
| Montgomery ES | FM-200331161 03 6/5/03 (Montogomery) !!!VERY URGENT!!! 1st Floor/Girls Bathroom: Crack in floor around the toilet, water is running from that crack in the floor, flooding the bathroom floor. Request water to be shut-off until the plumbers arrive. | June 3, 2003 | June 5, 2003 | 2 days |
| Merritt Middle School | FM-200224848 03 6/5/03 (Merritt) 3rd Floor/Locker corridor: Request keys made for the adult staff restroom, only two (2) keys available. | January 29, 2003 | June 5, 2003 | 127 days |
| Gage-Eckington ES | FM-200226227 03 6/5/03 Gage-Eckington Teachers restroom - First floor The lighting in the teachers restroom need to be checked. Put up a new balance was unable to make it work. Very much needed. | February 25, 2003 | June 5, 2003 | 100 days |
| Ronald H. Brown MS | FM-200329016 03 6/5/03 Brown, Ron (Roper) Third floor hallway Wall outlet needs to be replace or repaired - next to girls restroom. | April 24, 2003 | June 5, 2003 | 42 days |
| Gibbs Elementary School | FM-200227285 03 6/6/03 Gibbs First floor boys restroom Urinal constantly keep leaking attempted to repair it needs a plummer. | March 19, 2003 | June 6, 2003 | 79 days |
| Drew Elementary School | FM-200331364 03 6/6/03 Drew Boys Bathroom - 4th floor 1) Water shooting out of supply line going to sink. Cut off line is not holding. | June 6, 2003 | June 6, 2003 | 0 days |
| Key Elementary School | FM-200331307 03 6/6/03 Key First floor teacherd restroom (main office) Unclog commode. Cell phone was drop in it. | June 5, 2003 | June 6, 2003 | 1 day |
| Browne Junior High School | FM-200329425 03 6/6/03 (Browne) Repair wall, and ceiling in both bathrooms, has loose peeling paint, must be a smooth surface easly cleanable. Baseboards loose from wall under three (3) compartment sink in need of repair/seal. Lead & Asbestos Code A - Clear for repairs on 05/05/03. Horne Engineering - Edward Rodriguez (RG 05/05/03) | May 2, 2003 | June 6, 2003 | 35 days |
| Patricia R Harris Ed Center | FM-200330595 03 6/7/03 Harris, P.R. First floor cafeteria managers office Restroom in cafeteria mgr. toilet need a stop valve or kit (stopvalve kit) and 1 flush master on commode. Replacement needed. | May 22, 2003 | June 7, 2003 | 16 days |
| Cardozo High School | FM-200331354 03 6/8/03 Cardozo Ground floor girls bathroom Replace stop valve and flush valve on toilet.domestic hot and cold faucets. | June 5, 2003 | June 8, 2003 | 3 days |
| Merritt Middle School | FM-200331020 03 6/9/03 (Merritt) !!!VERY URGENT!!! West End/Girls bathroom and East end boys bathroom Two (2) commodes stopped up, and another toilet needs a wax ring and two urinals are stopped up. Floors are flooding, and the restroom is closed down. | June 2, 2003 | June 9, 2003 | 7 days |
| Tubman Elementary School | FM-200330916 03 6/10/03 Tubman First floor boys restroom Commode need a wax ring. | May 30, 2003 | June 10, 2003 | 11 days |
| Ludlow-Taylor ES | FM-200331459 03 6/11/03 (Ludlow-Taylor) !!!VERY URGENT!!! 3rd Floor/Girls bathroom: Toilet backing up, running over on the floor; water flooding the room below. (Shut off valves are not holding) | June 9, 2003 | June 11, 2003 | 2 days |
| Green Elementary School | FM-200215150 02 6/11/03 (Green) !!!Emergency!!! Emergency electrical service requested in the following area's: 2nd Fl. boys' bathroom & 1st Fl. girls' bathroom, across from main office: Water constantly running; electric eye on bradley basin need repair, discharges from spread head on its own. 3rd Floor/Boys restroom: No electric service to bradley basin for the electric eye. | August 20, 2002 | June 11, 2003 | 295 days |
| Brightwood Elementary School | FM-200331461 03 6/11/03 (Brightwood) !!!VERY URGENT!!! Boys Bathroom: A total of three (3) urinals stopped up; students continues to use urinals with the fowl odor present. | June 9, 2003 | June 11, 2003 | 2 days |
| Garfield ES | FM-200224269 03 6/11/03 Garfield ll-i - main bldg. Boys bathroom drains need to be snaked out. (urinals) | January 21, 2003 | June 11, 2003 | 141 days |
| Nalle Elementary School | FM-200215894 02 6/11/03 Nalle 1st Floor Boys' Restroom & Throughout 1. Install wax ring on wall-hung toilets [no penetration]; and 2. Check plumbing throughout building. | August 28, 2002 | June 11, 2003 | 287 days |
| Roosevelt High School | FM-200329749 03 6/12/03 (Roosevelt) Teaachers Cafeteria, and Ladies bathroom in the kitchen: Water fountain stopped up; Need P-Trap in womens bathroom in the kitchen due to leak. | May 8, 2003 | June 12, 2003 | 35 days |
| John Burroughs ES | FM-200331087 03 6/13/03 Burrough Boys restroom - lower level Two (2) sink knobs need replacing, do not have any to change myself. | June 3, 2003 | June 13, 2003 | 10 days |
| John Burroughs ES | FM-200331090 03 6/13/03 Burrough First floor - boys restroom Three (3) urinals are stopped up, tried snaking it to unclog did not work. | June 3, 2003 | June 13, 2003 | 10 days |
| Ferebee-Hope Elementary School | FM-200331637 03 6/13/03 Ferebbe-Hope First floor "C" bldg. outside bathroom Repair or replace water cooler. | June 11, 2003 | June 13, 2003 | 2 days |
| Eastern High School | FM-200331443 03 6/13/03 (Eastern) !!!EMERGENCY!!! Football Field/Girls bathroom: Replace (4) broken mirrors due to vandalism. ( 24" X 36" ) Asbestos Code A - Clear for repairs on 06/09/03. Horne Engineering - Tony Marcolin (RG 06/09/03) | June 6, 2003 | June 13, 2003 | 7 days |
| Eastern High School | FM-200331442 03 6/13/03 (Eastern) !!!EMERGENCY!!! Football Field/Girls bathroom: Repair or replace broken faucets due to vandalism; every thing in this bathroom must be operational by June 11, 2003. Repair Breech in wall behind plumbers... | June 6, 2003 | June 13, 2003 | 7 days |
| Patricia R Harris Ed Center | FM-200225059 03 6/16/03 Harris, P.R. Main floor - restroom the one next to #1 stairs Toilet (stand up) urinal needs to come off wall because of blockage in the line. | February 3, 2003 | June 16, 2003 | 133 days |
| Hearst Elementary School | FM-200331035 03 6/16/03 Hearst First Floor - Boys Restroom 1. Repair and or repalce faucet on sinks . | June 3, 2003 | June 16, 2003 | 13 days |
| King M L ES | FM-200228496 03 6/16/03 King, M.L. Jr. First floor lobby bathroom Need to have a key made for the lobby bathroom, the key the old one broke. | April 9, 2003 | June 16, 2003 | 68 days |
| Merritt Middle School | FM-200223523 03 6/17/03 (Merritt) 3rd Floor gym: Repair glass in door leading to girls restroom. | January 3, 2003 | June 17, 2003 | 165 days |
| Stoddert ES | FM-200331611 03 6/17/03 Stoddert First Floor 1. Repair sink in the girls restroom is falling off the wall . | June 11, 2003 | June 17, 2003 | 6 days |
| Eastern High School | FM-200329025 03 6/17/03 Eastern Stadium / girls bathroom Replace valve that control water for irrgation to water the football field - main water valve in girls bathroom behind face bowl - pipe is busted - both problems has to be repaired at the same time. The water line controls water to girls bathroom in stadium and irrgation system to water the football stadium - bathroom have to water field to maintain football field. | April 24, 2003 | June 17, 2003 | 54 days |
| Slowe Elementary School | FM-200330509 03 6/17/03 Slowe school Second floor boy restroom Boys restroom need bricks replaced under the sink | May 21, 2003 | June 17, 2003 | 27 days |
| Davis Elementary School | FM-200331503 03 6/17/03 Davis Boys bathroom - lunchroom in basement Toilet by sink bolts broke off and when you flush water comes out from bottom sides. Repair or replace toilets. | June 9, 2003 | June 17, 2003 | 8 days |
| Burrville Elementary School | FM-200331999 03 6/18/03 (Burrvile) !!!VERY URGENT!!! 1st Floor/Restroom: Repair leaking waste line, leaking in 1st floor restroom. | June 17, 2003 | June 18, 2003 | 1 day |
| Spingarn High School | FM-200224727 03 6/18/03 (Spingarn) 3rd Floor boys bathroom/Near room #314: Request locksmith to replace lock to door, old lock was broken and destroyed. | January 28, 2003 | June 18, 2003 | 141 days |
| King M L ES | FM-200331311 03 6/18/03 King, M.L. First floor boys bathroom Need to have # 2 unrinal snake out, urinal is stopped up water is running on the floor. | June 5, 2003 | June 18, 2003 | 13 days |
| Browne Junior High School | FM-200331836 03 6/18/03 Browne First And Second Floor 1.Repair key and knob lock on the girls restroom doors - ( new side ). Asbestos Code A - Clear for repairs on 06/16/03. Horne Engineering - Troy Wilcome (RG 06/17/03) | June 16, 2003 | June 18, 2003 | 2 days |
| Burrville Elementary School | FM-200329742 03 6/19/03 Burrville 1) Gym - Repair broken panic bar. 2) Second Floor - Mens Bathroom inside of Learning Center - Lock Broken. Asbestos Code A - Cleared for repairs on 05-30-03 by Leroy Minton Jr. (LM/05-03-30) Safety Office 202-576-8962. | May 8, 2003 | June 19, 2003 | 42 days |
| Stanton Elementary School | FM-200332156 03 6/20/03 Stanton Third Floor 1. Unstop the urinals in the boys restroom . | June 19, 2003 | June 20, 2003 | 1 day |
| Stanton Elementary School | FM-200225263 03 6/20/03 Stanton Second floor Bathroom sink is holding water in the sink. URGENT | February 5, 2003 | June 20, 2003 | 135 days |
| Cleveland Elementary School | FM-200225044 03 6/23/03 Cleveland Third floor - boy's restroom Bradley basin is leaking water onto the floor. The kids are slipping and falling in the water. This is a safety hazard for us. | January 31, 2003 | June 23, 2003 | 143 days |
| Cooke H.D. Elementary School | FM-200215208 02 6/23/03 Cooke,H.D. Basement Girls' Restroom Water shut-off valve is not working in the last toilet on the right side of the restroom. The water cannot be turned on. | August 21, 2002 | June 23, 2003 | 306 days |
| Woodson High School | FM-200224436 03 6/23/03 Woodson, H.D. Third floor - Boys bathroom Toilet backing up into corridor. URGENT | January 23, 2003 | June 23, 2003 | 151 days |
| Stuart-Hobson Middle School | FM-200331295 03 6/23/03 Stuart Hobson Emergency !!! Third Floor, Second Floor, First Floor and Basement 1) Leaking down from the third floor bathroom. All the urnials are stopped up, can not use any of the boys bathrooms. Leak has flooded the storage room in the basement. When the toilet is flushed in the Boys Gym the water goes into the Boiler Room. Asbestos Code A - Clear for repairs on 06/05/03. Horne Engineering - Bipin Nanavaty (RG 06/05/03) | June 5, 2003 | June 23, 2003 | 18 days |
| Duke Ellington School | FM-200202325 02 6/23/03 (ELLINGTON) ***URGENT*** VARIOUS AREAS OF SCHOOL 1) BASEMENT/SUB-BASEMENT: LEAKING URINAL IN BOYS RESTROOM DUE TO FAULTY HARDWARE 2) GIRLS RESTROOM: A COMMODE IS NOT FLUSHING & NEEDS TO BE SNAKED 3) HEALTH SUITE: TWO TOILETS IN UINISEX RESTROOM HAVE LEAKING BECAUSE OF FAULTY HARDWARE 4) DANCE STUDIO/MAIN OFFICE: FAULTY HARDWARE CAUSING LEAKING FROM FLUSH MECHANISM. BOYS RESTROOM: A URINAL IS LEAKING & ALSO NEEDS TO BE REANCHORED TO THE WALL. | February 1, 2002 | June 23, 2003 | 507 days |
| Duke Ellington School | FM-200223823 03 6/24/03 Ellington, Duke Girls restroom R St. The toilet's (water stop) is broken need new one. | January 13, 2003 | June 24, 2003 | 162 days |
| Duke Ellington School | FM-200114102 01 6/25/03 ELLINGTON DANCE STUDIO 1) BOYS RESTROOM - URINALS NOT WORKING PROPERLY. BASEMENT 2) BOYS RESTROOM - URINALS NOT WORKING PROPERLY. FIRST (1ST) FLOOR 3) BOYS RESTOOM - URINALS NOT WORKING PROPERLY. CAFETERIA - KITCHEN 4) SINK HANDLE BROKEN. | June 26, 2001 | June 25, 2003 | 729 days |
| Beers Elementary School | FM-200224349 03 6/25/03 Beers Bldg #2 first floor Girls restroom petition door broken. Urgent Asbestos Code A - Clear for repairs on 01/27/03. Horne Engineering - Troy Wilcome (RG 01/28/03) | January 22, 2003 | June 25, 2003 | 154 days |
| Johnson JHS | FM-200331174 03 6/25/03 Johnson URGENT First Floor - nurses and principal bathroom Unstop toilets. | June 4, 2003 | June 25, 2003 | 21 days |
| Clark Elementary School | FM-200332148 03 6/25/03 Clark First floor health suite Water is off in the health suite bathroom. The nurse need the water, please send a plummer to take care of this problem, this is not sanitary. | June 19, 2003 | June 25, 2003 | 6 days |
| Benning Elementary School | FM-200222332 /02 6/26/03 Benning Girls Restroom Second Floor Repair/replace inoperable exhaust fan. | December 10, 2002 | June 26, 2003 | 198 days |
| Moten Elementary School | FM-200224228 03 6/26/03 (Moten) First floor - room 108 restroom Water around the base of toilet need a new wax ring. | January 21, 2003 | June 26, 2003 | 156 days |
| Garfield ES | FM-200224270 03 6/27/03 Garfield Repair or replace water supply lines in boys bathroom on the second floor new wing. (All of them) | January 21, 2003 | June 27, 2003 | 157 days |
| Seaton Elementary School | FM-200331684 03 6/30/03 " EMERGENCY " Seaton Between Boy's & Girl's Restroom Second Floor Ruptured 2"inch lines between the boys and girls restroom *The wall is already marked* Asbestos Code A - Clear for repairs on 06/27/03. Horne Engineering - Bipin Nanavaty (RG 07/02/03) | June 12, 2003 | June 30, 2003 | 18 days |
| Kramer Middle School | FM-200227269 03 7/1/03 Kramer Through out Water damage to the following and repair the following areas: Ceiling fell in boys restroom room-115 Ceiling leak room 313 Kitchen wall and ceiling Teachers lounge walls room 5 Asbestos Code A - Clear for repairs on 03/19/03. Horne Engineering - Sharon Voss (RG 03/20/03) | March 18, 2003 | July 1, 2003 | 105 days |
| Garfield ES | FM-200226870 03 7/1/03 GARFIELD Assess walls and pipes for asbestos coating materials LOWER LEVEL - MAIN BUILDING 1. PLUMBING REPAIRS IN THE BOYS AND GIRLS RESTROOMS . Asbestos Code A - Clear for repairs on 04/17/03. Horne Engineering - Sharon Voss (RG 04/18/03) | March 11, 2003 | July 1, 2003 | 112 days |
| Merritt Middle School | FM-200332772 03 7/1/03 Merritt First floor boys bathroom Unstop three toilets. Toilets are backing up. | July 1, 2003 | July 1, 2003 | 0 days |
| Eliot Junior High School | FM-200332763 03 7/1/03 (Eliot) 3rd Floor/Gym: Leaking in girls restrooms; water running down in the transistion office below. (Toilet leaking under commode) | July 1, 2003 | July 1, 2003 | 0 days |
| Garfield ES | FM-200220826 /02 7/2/03 Garfield Lower level 1 - Boys bathroom by music room Urinal sprayers need to be replaced. Six all together | November 13, 2002 | July 2, 2003 | 231 days |
| Webb Elementary School | FM-200332519 03 7/2/03 WEBB !! EMERGENCY !! Second Floor - Boys Restroom (AMP 216) 1) Pipe burst behind wall in boys restroom . 2) Close big hole made by plumbers . Asbestos Code A, clear for repairs 6/25/03 Horne Engineering, Troy Wilcome (RE-6/25/03) Extension to of FM-2003302416 Ronald Edwards - 202-439-8094 | June 25, 2003 | July 2, 2003 | 7 days |
| Coolidge High School | FM-200332841 03 7/2/03 Coolidge Emergency Ground floor Urinal and toilet are backing up in boys bathroom. | July 2, 2003 | July 2, 2003 | 0 days |
| Truesdell Elementary | FM-200332451 03 7/7/03 Truesdell First floor boys bathroom Need new faucet on sink or repair. What is there 3 toilets do not work, pipes leak, damage pipes. | June 25, 2003 | July 7, 2003 | 12 days |
| Truesdell Elementary | FM-200332452 03 7/7/03 Truesdell First floor Room 100 P-K class Bathroom toilets need wax rings. | June 25, 2003 | July 7, 2003 | 12 days |
| Benjamin Banneker Academic HS | FM-200331772 03 7/7/03 (Banneker) FIRE CODE VIOLATION: 2nd Floor/Boys bathroom: Brokenr door hardware. | June 13, 2003 | July 7, 2003 | 24 days |
| Harris, C.W. ES | FM-200329612 03 7/7/03 Harris, C.W. First floor girls bathroom Repair the hole in the wall. Cinder block repair. Asbestos Code A - Clear for repairs on 05/06/03. Horne Engineering - Sharon Voss (RG 05/08/03) | May 5, 2003 | July 7, 2003 | 63 days |
| Johnson JHS | FM-200332773 03 7/8/03 Johnson Second floor female teachers bathroom Unstop toilet. | July 1, 2003 | July 8, 2003 | 7 days |
| Stanton Elementary School | FM-200331141 03 7/8/03 Stanton URGENT Bottom floor Cafeteria bathroom sink leak water need plummer. | June 3, 2003 | July 8, 2003 | 35 days |
| Whittier Elementary School | FM-200223827 03 7/9/03 Whittier First floor - girls restroom Two sinks leaking from trap or around elbow. | January 13, 2003 | July 9, 2003 | 177 days |
| West Elementary School | FM-200224396 03 7/10/03 West First floor boys and girls restrooms By the gym can not find shut off valve to fix water leak on the toilets. See maintenance staff. | January 23, 2003 | July 10, 2003 | 168 days |
| Whittier Elementary School | FM-200225268 03 7/11/03 Whittier First floor girls restroom (New bldg.) Repair or replace flush valves on two(2) toilets and something is stopping them up. We have plug but unable to remove object. | February 5, 2003 | July 11, 2003 | 156 days |
| Rudolph Elementary School | FM-200332958 03 7/11/03 (Rudolph) !!!URGENT!!! 1st Floor/Teachers Lounge Restroom: Key broke off in door. | July 7, 2003 | July 11, 2003 | 4 days |
| Takoma Educational Center | FM-200333024 03 7/14/03 (Takoma) Second floor - grils restroom green team area Two (2) handle broken repair or replace handle. | July 8, 2003 | July 14, 2003 | 6 days |
| Takoma Educational Center | FM-200333028 03 7/14/03 (Takoma) Second floor -boys restroom yellow team area One (1) urinal broken repair or replace. | July 8, 2003 | July 14, 2003 | 6 days |
| Adams Elementary | FM-200333169 03 7/14/03 (Adams) !!!EMERGENCY!!! 1st Floor/Girls bathroom: Toilet continues to run, and leaking from the flush valve, flooding the floors. (Unable to shut water off) | July 10, 2003 | July 14, 2003 | 4 days |
| Plummer Elementary School | FM-200333130 03 7/14/03 Plummer First Floor 1) Repair or and replace broken toilet in girls restroom | July 10, 2003 | July 14, 2003 | 4 days |
| Birney Elementary School | FM-200227190 03 7/14/03 BIRNEY First And Second Floors - Boys And Girls Restrooms 1. Repair lights in the girls and boys restrooms on the old side of the building . The lights are not working . ( Changed the bulbs still nothing) Asbestos Code A - Clear for repairs on 03/18/03. DCPS Safety - Richard Gibson (RG) | March 18, 2003 | July 14, 2003 | 118 days |
| Garnet-Patterson MS | FM-200333216 03 7/15/03 Garnet-Patterson Second floor boys bathroom Face bowl is broken, replace. | July 14, 2003 | July 15, 2003 | 1 day |
| Reed LC | FM-200333266 03 7/16/03 Reed, Marie Boys and girls room second floor Install new #111 flush valves an stops. | July 15, 2003 | July 16, 2003 | 1 day |
| Takoma Educational Center | FM-200333031 03 7/16/03 (Takoma) Third floor - girls restroom orange team area One (1) handle leaks, one (1) bradley basin needs adjusting, repair / replace. | July 8, 2003 | July 16, 2003 | 8 days |
| Brightwood Elementary School | FM-200332897 03 7/18/03 Brightwood First floor boys bathroom The wash bowl is broken need to be replaced over demountable. | July 3, 2003 | July 18, 2003 | 15 days |
| Gage-Eckington ES | FM-200333393 03 7/18/03 (Gage Eckington) 2nd Floor/Nurses Bathroom: Water leaking from under the sink, flooding the floors. | July 17, 2003 | July 18, 2003 | 1 day |
| Hine JHS | FM-200331391 03 7/18/03 Hine Boiler Room Asbestos Assestment Required Repair or replace 2" chill water line above Boiler #2 right hand side. Asbestos maybe located on the line it is leaking very badly . Code A -clear for repairs as of 6/11/03 by DCPS Sylvia Grimes. Girls restroom above boiler room need toilet remove and valve is not holding. Re-Opened Exploratory Needed for Girls Bath Room on 1st Floor along with water line above Boiler #2. See Attached Map POC: Kingwood / Sylvia Grimes Asbestos Code A - Clear for repairs on 06/12/03. Horne Engineering - Philp Connolly (RG 06/16/03) Repairs were made by the Steamfitting Shop and it was cleared by Asbestos Assestment Management See information above. 1. Pipe has to be insulated 12" of 1 1/2 pipe (Safety) 2. Repair black wall in bathoom. 1st fl. girls bathroom (Grounds) 3. Replace toilet in 1st floor girls bathroom (Plumbers) | June 6, 2003 | July 18, 2003 | 42 days |
| Backus Middle School | FM-200222409 /02 7/24/03 Backus Third and Second Floor 1) Repair broken windows in the following rooms: 303 - 2 , 304 - 2 , 202 - 3 , Boys Bathroom - 2 , 211 - 1 , and 210 - 1. | December 12, 2002 | July 24, 2003 | 224 days |
| Harris, C.W. ES | FM-200218371 02 7/24/03 Harris,C.W. ****Very Urgent/BREAK-IN**** 1st Floor Restroom/Primary Wing Replace broken window pane. | September 26, 2002 | July 24, 2003 | 301 days |
| Woodson High School | FM-200333564 03 7/25/03 (Woodson, H.D) Plaza/Principal's Office: Unable to gain entry to the principals closet, and bathroom, need locksmith to change locks. | July 22, 2003 | July 25, 2003 | 3 days |
| Ballou Senior High School | FM-200332874 03 7/28/03 Ballou Room 204, boys and girls restroom near gym, teachers restroom and 2nd floor awing Repair doors in the above areas. | July 3, 2003 | July 28, 2003 | 25 days |
| Webb Elementary School | FM-200333170 03 7/31/03 (Webb) 1st Floor/Boys Restrooms: Repair large breech in wall. Asbestos Code A - Clear for repairs on 07/15/03. Horne Engineering - Roger Kager (RG 07/16/03) | July 10, 2003 | July 31, 2003 | 21 days |
| Cardozo High School | FM-200331353 03 8/4/03 Cardozo Third floor girls bathroom Replace domestic hot and cold faucets. | June 5, 2003 | August 4, 2003 | 60 days |
| Dunbar High School | FM-200334196 03 8/4/03 Dunbar !! Emergency !! First Floor - Gymnasium 1. Repair and or replace shut- off valve inside of the boys restroom . | August 4, 2003 | August 4, 2003 | 0 days |
| Ronald H. Brown MS | FM-200334123 03 8/4/03 Brown, Ron (Roper) Third floor girls restroom Stairwell # 9 second toilet from left leaks from spual nut. | August 1, 2003 | August 4, 2003 | 3 days |
| Ronald H. Brown MS | FM-200334127 03 8/5/03 Brown, Ron (Roper) First floor Boys and girls restroom Boys by stairwell # 10 need new toilets seats. | August 1, 2003 | August 5, 2003 | 4 days |
| Draper Elementary School | FM-200332898 03 8/7/03 Draper !! Urgent !! First Floor 1. Replace missing urinal in boys restroom . 2. Unstop the middle urinal . | July 3, 2003 | August 7, 2003 | 35 days |
| Moten Elementary School | FM-200333622 03 8/8/03 (Moten) FIRE CODE VIOLATION: 4th Floor/Boys Bathroom: Door closer near Room #415. | July 22, 2003 | August 8, 2003 | 17 days |
| Ronald H. Brown MS | FM-200334124 03 8/8/03 Brown, Ron (Roper) Second floor girls restroom Girls restroom by stairwell # 9 to # 11 leak froom ceiling # 11 leak from spual nut. | August 1, 2003 | August 8, 2003 | 7 days |
| Ronald H. Brown MS | FM-200334126 03 8/8/03 Brown, Ron (Roper) First floor main office Ladys restroom leak from hot water nob. | August 1, 2003 | August 8, 2003 | 7 days |
| Gage-Eckington ES | FM-200334618 03 8/11/03 Gage-Eckington First floor Boys restroom There are 3 urinals and 4 toilets, one toilet need to be fixed when flushed it rund into the next toilet causing a back up. Odor | August 7, 2003 | August 11, 2003 | 4 days |
| Whittier Elementary School | FM-200334625 03 8/11/03 Whittier Second floor main office Replace the pea trap under neath sink in restroom. Slop sink drain is leaking at the bottom and needs a cover over the drain. | August 7, 2003 | August 11, 2003 | 4 days |
| Backus Middle School | FM-200334699 03 8/11/03 Backus Health Code !! Kitchen Restroom 1) Repair faucet on hand sink. | August 8, 2003 | August 11, 2003 | 3 days |
| Kimball Elementary School | FM-200334212 03 8/13/03 Kimball First floor north wing boys bathroom Replace the faucet on the slop sink, can not recieve water. Need water urgent. | August 4, 2003 | August 13, 2003 | 9 days |
| Dunbar High School | FM-200119819 01 8/13/03 (DUNBAR) 1. ASBESTOS ASSESSMENT REQUIRED. GIRLS BATHROOM: REPAIR HAND WASHING SINK IN GIRLS BATHROOM. (STADIUM) POC: WILLIAM MOODY 202 439-8268 CELL PHONE ASBESTOS CODE A-CLEAN FOR REPAIR ON 9/19/01 BY HORNE ENGINEER STEPHEN CALDWELL | September 14, 2001 | August 13, 2003 | 698 days |
| Ballou Senior High School | FM-200332875 03 8/13/03 Ballou Replace locks to the following restroom in armor, parenting cntr., datd entrance office, room 308, 206, A123 and registra office also 210 and maintenance office also door fr. mainoffice to principal area. | July 3, 2003 | August 13, 2003 | 41 days |
| Gage-Eckington ES | FM-200334702 03 8/13/03 Gage-Eckington First floor Boys and girls restroom Restroom on 2nd floor main lobby need to be unstopped. Some are in need of handles, flush valves, and spuds. Need a plummer. | August 8, 2003 | August 13, 2003 | 5 days |
| Stanton Elementary School | FM-200335030 03 8/14/03 Stanton Third floor boys bathroom Sink in the boys bathroom and two urinals are clogged need plumber. URGENT | August 13, 2003 | August 14, 2003 | 1 day |
| Cardozo High School | FM-200331349 03 8/14/03 Cardozo Girls bathroom - ground floor Replace 3/4" inch valve on copper domestic hot water pipe. | June 5, 2003 | August 14, 2003 | 70 days |
| Ferebee-Hope Elementary School | FM-200333397 03 8/15/03 (Ferebee-Hope) 1st Floor/Family Service: Repair hot, and cold water faucets that are not working. (No water comes out) There is only one sink in this to restroom. | July 17, 2003 | August 15, 2003 | 29 days |
| Hine JHS | FM-200332445 03 8/15/03 Hine Second floor girls restroom Remove commode. Re-install after steam line is repaired. | June 25, 2003 | August 15, 2003 | 51 days |
| Jefferson JHS | FM-200335193 03 8/15/03 Jefferson Basement - Band Room B- 19 1. Unclog commode in band room bathroom. | August 14, 2003 | August 15, 2003 | 1 day |
| Bruce-Monroe Elementary School | FM-200335234 03 8/18/03 (Bruce-Monroe) Unstop fixture in room 201 teachers, Third floor mop closet need new 8" faucets, Room 301 and 302 Boys restroom urinals need to be unstopped, and custodial closet hot water running first floor. | August 14, 2003 | August 18, 2003 | 4 days |
| Miner Elementary | FM-200334795 03 8/18/03 (Miner) !!!VERY URGENT!!! 1st Floor/Room #101: Replace commode in students classroom. (restroom) Water running on the floor. | August 11, 2003 | August 18, 2003 | 7 days |
| Garfield ES | FM-200335091 03 8/19/03 Garfield Second Floor 1. Locksmith needed to repair lock on boys restroom door. (key keeps turning the cylinder around) | August 13, 2003 | August 19, 2003 | 6 days |
| Slowe Elementary School | FM-200334425 03 8/20/03 Slowe First floor boys restroom OB Repair urinals. 1 low pressure 2 are running non-stop. | August 5, 2003 | August 20, 2003 | 15 days |
| Slowe Elementary School | FM-200334427 03 8/20/03 Slowe Second floor boys restroom OB Low pressure all urinals. | August 5, 2003 | August 20, 2003 | 15 days |
| Bunker Hill Elementary School | FM-200334399 03 8/20/03 Bunker Hill Second floor boys restroom / middle wing Secure window guard (safety hazard). | August 5, 2003 | August 20, 2003 | 15 days |
| Slowe Elementary School | FM-200334426 03 8/20/03 Slowe Second floor boys restroom Urinal will not flush. | August 5, 2003 | August 20, 2003 | 15 days |
| Leckie Elementary School | FM-200336028 03 8/21/03 (Leckie) Kitchen restroom Survey and repair light fixture. light continue to blow. | August 21, 2003 | August 21, 2003 | 0 days |
| Slowe Elementary School | FM-200334424 03 8/22/03 Slowe First floor girls restroom OB Need 2 flush valves. | August 5, 2003 | August 22, 2003 | 17 days |
| Slowe Elementary School | FM-200334421 03 8/22/03 Slowe First floor boys restroom Flush valve needed and leak repaired on thidr urinal. | August 5, 2003 | August 22, 2003 | 17 days |
| Slowe Elementary School | FM-200334420 03 8/22/03 Slowe First floor girls restroom Last toilets leaks when water is turned on. | August 5, 2003 | August 22, 2003 | 17 days |
| Emery Elementary School | FM-200335742 03 8/22/03 Maury Basement girls restroom Unstop 2 toilets. | August 19, 2003 | August 22, 2003 | 3 days |
| Simon Elementary School | FM-200333636 03 8/22/03 (Simon) FIRE CODE VIOLATION: 1st Floor: Exit light out near boys bathroom. | July 22, 2003 | August 22, 2003 | 31 days |
| Maury Elementary School | FM-200335085 03 8/22/03 (Maury) FIRE CODE VIOLATION: 1st Floor/Near room #10L Defective door in boys bathroom. Asbestos Code A - Clear for repairs on 08/14/03. Horne Engineering - Troy Wilcome (RG 08/18/03) | August 13, 2003 | August 22, 2003 | 9 days |
| Walker-Jones EC | FM-200335208 03 8/22/03 Walker-Jones Basement boys restroom All urinals is backing up when one is flushed. | August 14, 2003 | August 22, 2003 | 8 days |
| Whittier Elementary School | FM-200336233 03 8/26/03 Whittier First floor Teacher and parent center Bathroom door locked need door unlock, and keys for bathroom door. | August 25, 2003 | August 26, 2003 | 1 day |
| Kramer Middle School | FM-200208730 02 8/27/03 Kramer 1st Floor Girls' Restroom Drain pipe under sink needs to be repaired and or replaced [safety hazard]. | May 31, 2002 | August 27, 2003 | 453 days |
| Beers Elementary School | FM-200335198 03 8/27/03 Beers First and second Floor Bldg. 3 All classroom doors and bathroom doors are damaged, lock and handles. Please survey and fix. | August 14, 2003 | August 27, 2003 | 13 days |
| Hyde Elementary School | FM-200217580 02 8/28/03 Hyde Basement Girls' Restroom Repair non-working toilet in girls restroom. | September 16, 2002 | August 28, 2003 | 346 days |
| Anacostia Senior High School | FM-200334746 03 8/29/03 (Anacostia) FIRE CODE VIOLATION: Upper level/New wing: Door closure, mens bathroom. | August 8, 2003 | August 29, 2003 | 21 days |
| Eliot Junior High School | FM-200334466 03 9/2/03 (Eliot) FIRE CODE VIOLATION: 1st Floor/Boys Bathroom: Door defective near room #101. Asbestos Code A - Clear for repairs on 08/06/03. Horne Engineering - Philp Connolly (RG 08/07/03) | August 5, 2003 | September 2, 2003 | 28 days |
| Patricia R Harris Ed Center | FM-200336765 03 9/3/03 Garnett Patterson !! Emergency !! Third Floor 1. Repair Busted water pipe in the boys restroom. | September 3, 2003 | September 3, 2003 | 0 days |
| Shaw JHS | FM-200336705 03 9/3/03 Shaw Install new wall hung sink in boys room, common area. | September 2, 2003 | September 3, 2003 | 1 day |
| Shepherd ES | FM-200336944 03 9/8/03 (Shepherd) !!!EMERGENCY!!! 1stl Floor/Boys Bathroom: Three (3) sinks running over flooding the floors. (None Stop) Unable to shut the water off. | September 5, 2003 | September 8, 2003 | 3 days |
| Aiton Elementary School | FM-200337048 03 9/9/03 (Aiton) !!!EMERGENCY!!! All Bathrooms Through Out the Building: Scalding hot water running from sinks where students wash hands. Water is very hot, and staff has a concern for those who could be injured. (Burned) | September 8, 2003 | September 9, 2003 | 1 day |
| Backus Middle School | FM-200332302 03 9/9/03 Backus First floor boys restroom Urinal leaking - not flushing properly. Repair / replace | June 23, 2003 | September 9, 2003 | 78 days |
| Webb Elementary School | FM-200125648 /01 9/9/03 (WEBB) ASBESTOS ASSESSMENT REQUIRED 1ST FLOOR BOYS RESTROOM REPAIR URINAL WHICH NEEDS A WAX RING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/22/01. RICHARD GIBSON - SAFETY (202)576-5584 (RG) | December 18, 2001 | September 9, 2003 | 630 days |
| Webb Elementary School | FM-200225259 03 9/9/03 (Webb) 2nd Floor - girls restroom: Repair one (1) toilet need to be unclog and four (4) sinks need to be unclog. Temperture on sinks need to be turn down. (Hot water side) URGENT | February 5, 2003 | September 9, 2003 | 216 days |
| Webb Elementary School | FM-200222699 /02 9/10/03 Webb Check and repair plumbing in boy's room second floor. | December 17, 2002 | September 10, 2003 | 267 days |
| Stuart-Hobson Middle School | FM-200332727 03 9/12/03 Stuart -Hobson !! Emergency !! Basement Floor 1.) Repair leaking commode in the girls shower room , had to cut off water to commode. 1st, 2nd&3rd Floor 2.) Repair toilet leaking from the spud in girls restroom , leaking in the cafeteria . | June 30, 2003 | September 12, 2003 | 74 days |
| Smothers ES | FM-200335319 03 9/12/03 Smother F-504.1 FIRE CODE VIOLATION First Floor Electrical panel box abd. next to boys bathroom. | August 14, 2003 | September 12, 2003 | 29 days |
| Garnet-Patterson MS | FM-200331159 03 9/12/03 (Garnet-Patterson) 2nd Floor/Boys Bathroom: Broken handsink | June 3, 2003 | September 12, 2003 | 101 days |
| Macfarland Middle School | FM-200337346 03 9/13/03 MacFarland Second and third floor boys restrooms Unclog urinals. | September 11, 2003 | September 13, 2003 | 2 days |
| Takoma Educational Center | FM-200333027 03 9/14/03 (Takoma) Third floor - teachers and men restroom Vacuum breaker leaks repair or replace. | July 8, 2003 | September 14, 2003 | 68 days |
| Park View ES | FM-200337261 03 9/15/03 Park View First floor Teachers restroom sinks is leaking water underneath. | September 11, 2003 | September 15, 2003 | 4 days |
| Park View ES | FM-200337256 03 9/15/03 Park View Second floor boys restroom Sinks are stop up and need to be snaked out. | September 11, 2003 | September 15, 2003 | 4 days |
| Plummer Elementary School | FM-200224606 03 9/16/03 Plummer Boys Bathroom,Cafeteria,Teachers Bathroom 2nd Floor, Boys Bathroom 3rd Floor. 1) Replace diaphrams and vacuum breakers for sloan flush valves in the above areas. | January 27, 2003 | September 16, 2003 | 232 days |
| Walker-Jones EC | FM-200337291 03 9/16/03 (Walker Jones) Second floor open space Repair the boys and girls restrooms they are not working. | September 11, 2003 | September 16, 2003 | 5 days |
| Truesdell Elementary | FM-200335607 03 9/17/03 (Truesdell) FIRE CODE VIOLATION: New wing/2nd Floor: Need door adjustments in girls and boys restroom. Asbestos Code A - Clear for repairs on 08/18/03. Horne Engineering - Sharon Voss (RG 08/20/03) | August 18, 2003 | September 17, 2003 | 30 days |
| Stanton Elementary School | FM-200220703 /02 9/17/03 Stanton - T-9 First Floor Boys bathroom last two urinals are not flushing properly. | November 12, 2002 | September 17, 2003 | 309 days |
| Truesdell Elementary | FM-200335605 03 9/17/03 (Truesdell) FIRE CODE VIOLATION: New wing/1st Floor: Need doors adjustment in boys and girls restroom. Asbestos Code A - Clear for repairs on 08/18/03. Horne Engineering - Sharon Voss (RG 08/20/03) | August 18, 2003 | September 17, 2003 | 30 days |
| Shaed Elementary School | FM-200337087 03 9/17/03 Shaed First & Third Floor 1. Repair water running faucet will not cut off , unable to locate cut off valve. 2. Repair -girls restroom toilet running . | September 9, 2003 | September 17, 2003 | 8 days |
| Eliot Junior High School | FM-200334489 03 9/17/03 (Eliot) FIRE CODE VIOLATION: Basement/Near All Purpose Room: Bathroom door defective. Asbestos Code A - Clear for repairs on 08/06/03. Horne Engineering - Philp Connolly (RG 08/07/03) | August 5, 2003 | September 17, 2003 | 43 days |
| Walker-Jones EC | FM-200337272 03 9/17/03 (Walker Jones) Second floor boys restroom Toilet needs to be removed from floor to be snaked out if drain line. | September 11, 2003 | September 17, 2003 | 6 days |
| Gibbs Elementary School | FM-200336376 03 9/23/03 Gibbs Second floor Boys restroom Sinks are not operating correctly no water. | August 27, 2003 | September 23, 2003 | 27 days |
| Spingarn High School | FM-200337769 03 9/23/03 (Spingarn) Basement/Boys Bathroom: Request locksmith to adjust the existing lock; unable to lock door. | September 18, 2003 | September 23, 2003 | 5 days |
| Meyer Elementary School | FM-200336344 03 9/23/03 Meyer Second floor boys bathroom The hold and cold knobs on the sinks are missing need four (4). | August 27, 2003 | September 23, 2003 | 27 days |
| Merritt Middle School | FM-200337883 03 9/23/03 (Merritt) !!!URGENT!!! Roof Top: Pump water from roof to prevent flooding; water is running down in the gym, boys bathroom. | September 23, 2003 | September 23, 2003 | 0 days |
| Beers Elementary School | FM-200337766 03 9/23/03 (Beers) Basement/Cafeteria: Boys, and girls restrooms are without lights; an attempt was made to correct the problem. | September 18, 2003 | September 23, 2003 | 5 days |
| Patricia R Harris Ed Center | FM-200336211 03 9/23/03 Harris, P.R. Ground floor boys restroom small gym area Toilet out of order will not flush. | August 25, 2003 | September 23, 2003 | 29 days |
| Rudolph Elementary School | FM-200221875 02 9/24/03 Rudolph First floor - Girls Restroom Water leaking from shut off valve in girls bathroom. | December 2, 2002 | September 24, 2003 | 296 days |
| Ferebee-Hope Elementary School | FM-200337597 03 9/24/03 Ferebee-Hope First floor D-building family service and mens bathroom by security Sink faucets leaking. Urinal flush valve leaking. | September 16, 2003 | September 24, 2003 | 8 days |
| Ferebee-Hope Elementary School | FM-200337599 03 9/24/03 Ferebee-Hope Second floor D-building mens bathroom U.D.C. Urinal replace flush valve. | September 16, 2003 | September 24, 2003 | 8 days |
| Garnet-Patterson MS | FM-200337865 03 9/24/03 Garnet-Patterson Basement - Cafeteria Bathroom 1) Sewage backing up through toilet, Cafeteria flooded , drain backed up. | September 23, 2003 | September 24, 2003 | 1 day |
| Davis Elementary School | FM-200337674 03 9/24/03 Davis First and second floor boys and girls bathroom new wing Need a plumber to check water pressure or repair faucets, shut off valves are on but there is little water pressure. | September 16, 2003 | September 24, 2003 | 8 days |
| Nalle Elementary School | FM-200120380 01 9/24/03 NALLE SECOND FLOOR - FEMALE RESTROOM - NEW WING 1) REPLACE LIGHTS WITH SURFACE MOUNT FIXTURES. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: RAY AGNANT | September 24, 2001 | September 24, 2003 | 730 days |
| Maury Elementary School | FM-200336899 03 9/24/03 Maury Second floor teachers bathroom Repair leaking faucet. Code A-clear for repair by DCPS Charles Buchanan on 9/9/03 | September 5, 2003 | September 24, 2003 | 19 days |
| Beers Elementary School | FM-200337540 03 9/25/03 Beers First floor bldg. # 2 Girls restroom is flowing, will not flush. R/R tried to fix it. Bldg. third and second girls restroom hardware is rusted out. R/R | September 15, 2003 | September 25, 2003 | 10 days |
| Cook J.F. Elementary School | FM-200336770 03 9/25/03 Cook ,J.F. Third Floor 1. Replace flush valve in teacher's lounge restroom. | September 3, 2003 | September 25, 2003 | 22 days |
| Bunker Hill Elementary School | FM-200337782 03 9/25/03 Bunker Hill Outside A.)Three storage rooms need new locks 1.When entering the parking lot to the left - red door. 2. Past the middle wing out side to the left - gray door. 3. 2nd floor - east wing teachers restroom locked - have no key . | September 19, 2003 | September 25, 2003 | 6 days |
| Ferebee-Hope Elementary School | FM-200337596 03 9/25/03 Ferebee-Hope First floor D-building family service and mens bathroom by security Two(2) toilets flush valve pipe to short (replace(leaking)). | September 16, 2003 | September 25, 2003 | 9 days |
| Maury Elementary School | FM-200336473 03 9/29/03 Maury Basement girls restroom Unstop two (2) toilets. | August 28, 2003 | September 29, 2003 | 32 days |
| Webb Elementary School | FM-200225257 03 9/30/03 (Webb) First floor/Boys restroom: Repair two (2) flush valves, not working and repair four (4) toilets flush valves. Repair four (4) sinks, that need to be unclog, also a faucet need repairing. URGENT | February 5, 2003 | September 30, 2003 | 237 days |
| Patricia R Harris Ed Center | FM-200336213 03 9/30/03 Harris, P.R. Main floor # 5 boys restroom The stand up urinal will not flush. | August 25, 2003 | September 30, 2003 | 36 days |
| Simon Elementary School | FM-200337594 03 9/30/03 Simon EMERGENCY Third floor boys bathroom The boys bathroom sink is dripping water, does not have a shut off valve. Water is all over the floor. | September 16, 2003 | September 30, 2003 | 14 days |
| Leckie Elementary School | FM-200337653 03 10/1/03 Leckie Second floor boys restroom Reanchorer commode to floor, replace complete assemble 110 flush and spud in restroom. | September 16, 2003 | October 1, 2003 | 15 days |
| Macfarland Middle School | FM-200336961 03 10/2/03 MacFarland Second Floor - Boys Restroom 1. Unclog urinals. | September 8, 2003 | October 2, 2003 | 24 days |
| Stanton Elementary School | FM-200336831 03 10/2/03 Stanton Second floor girls bathroom 2nd toilet from the right is broken need a new one. URGENT | September 4, 2003 | October 2, 2003 | 28 days |
| Macfarland Middle School | FM-200336964 03 10/2/03 MacFarland Second Floor - Boys Restroom 1.Replace broken commode. | September 8, 2003 | October 2, 2003 | 24 days |
| Barnard Elementary School | FM-200120702 01 10/2/03 (BARNARD) 1ST, 2ND, AND 3RD FLOORS/ HALLWAYS REPLACE BALLASTS IN THE FOLLOWING AREAS: HALLWAY (3RD FLOOR BLDG.) HALLWAY (2ND FLOOR NEAR RM. 202) GIRLS BATHROOM (OLD BLDG. 1ST FLOOR) HALLWAY (1ST FLOOR, OLD BLDG.) HALLWAY (1ST FLOOR, NEW BLDG.) | September 28, 2001 | October 2, 2003 | 734 days |
| Macfarland Middle School | FM-200337814 03 10/2/03 (Macfarland) 2nd & 3rd Floor/Boys Restroom: Unstop urinals. | September 22, 2003 | October 2, 2003 | 10 days |
| Barnard Elementary School | FM-200124036 /01 10/2/03 (BARNARD) OLD BUILDING, 1ST FLOOR/GIRLS BATHROOM: STOP VALVES ARE NOT HOLDING, TOILETS ARE RUNNING AND LEAKING FROM HANDLES. | November 29, 2001 | October 2, 2003 | 672 days |
| Barnard Elementary School | FM-200125992 /01 10/2/03 BARNARD FIRST (1ST) AND SECOND (2ND) FLOOR 1. ASBESTOS ASSESSMENT REQUIRED. 2. ROOM #101 (AMP #38) 12" X 12" PINK TILES. 3. ROOM #226 (AMP #113) 9" X 9" FLOOR TILES/ MASTIC MISSING. 4. HEALTH SUITE BY THE BATHROOM (AMP #71) APPROX. | December 21, 2001 | October 2, 2003 | 650 days |
| Barnard Elementary School | FM-200127406 02 10/2/03 (BARNARD) 2ND FLOOR-OLD BLDG./ TEACHERS LOUNGE BATHROOM REPLACE LIGHT FIXTURE. | January 14, 2002 | October 2, 2003 | 626 days |
| Barnard Elementary School | FM-200203265 02 10/2/03 (Barnard) Asbestos Assessment Required 1st Floor near Girls Restroom/Old Bodg. The water cooler has been pulled away from the wall and needs to be realigned to the wall. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/25/02 HORNE ENGINEER:STEPHEN CALDWELL | February 21, 2002 | October 2, 2003 | 588 days |
| Merritt Middle School | FM-200337179 03 10/2/03 Merritt !! Urgent !! Third Level 1. Open and repair lock on the boys restroom door. | September 10, 2003 | October 2, 2003 | 22 days |
| Kimball Elementary School | FM-200338332 03 10/3/03 Kimball Second Floor - Boys Bathroom and Health Suite 1) Install new toilets | October 1, 2003 | October 3, 2003 | 2 days |
| Deal Junior High School | FM-200338131 03 10/6/03 Deal Basement girls restroom Replace broken sink. Unable to use restroom because both sinks use same drain. Asbestos Code A - Clear for repairs on 09/29/03. Horne Engineering - Edward Rodriguez (RG 10/01/03) | September 29, 2003 | October 6, 2003 | 7 days |
| Plummer Elementary School | FM-200218841 02 10/7/03 Plummer Third floor Boys restroom next to room 209, check and repair three of four hand basins that do not work. Two have spigots that spin around with no water and one doesn't work at all urinals are inoperative none of them flush. First floor Boys room repair two of four hand basins that do not work. Check and repair two of six urinals that do not flush. | October 4, 2002 | October 7, 2003 | 368 days |
| Malcolm X ES | FM-200123395 /01 10/7/03 (MALCOLM X) ASBESTOS ASSESSMENT REQ. 2ND FLOOR/ BOYS RESTROOM REPLACE COMMODE DUE TO FIRE DAMAGE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/16/01. LEROY MINTON - SAFETY (202)576-6691 (RG) | November 15, 2001 | October 7, 2003 | 691 days |
| Shaw JHS | FM-200338551 03 10/8/03 (Shaw) URGENT:Teachers restrooms second floor 7th&8th grade houses next to teachers lounge toilets not working properly. needs to be repared or replaced. THANK YOU. | September 3, 2003 | October 8, 2003 | 35 days |
| Webb Elementary School | FM-200205917 02 10/8/03 Webb 2nd Floor Boys & Girls RestroomsUnclog hand sinks. P-traps were removed, but found to be clear. There is no hand-augur on site to snake out debris. Code A - Clear for repairs on 04-25-02. One foot of ACM insulation removed from a 3/4" pipeline to clear the way for necessary repairs on 04-25-02. (LMJ) Safety Office 202--576-8962. | April 16, 2002 | October 8, 2003 | 540 days |
| Shaw JHS | FM-200338333 03 10/8/03 (Shaw) URGENT: Girls restroom two toilets in need of repair. Two wax rings and calking are needed for this repair. Thanks. | September 16, 2003 | October 8, 2003 | 22 days |
| Backus Middle School | FM-200338676 03 10/8/03 (Backus) !!!VERY URGENT!!! 3rd Floor Girls Locker Room/Bathroom: Leaking down in 2nd floor kitchen; bathroom above Possible leaking from that bathroom. | October 8, 2003 | October 8, 2003 | 0 days |
| Eastern High School | FM-200336379 03 10/8/03 (Eastern) FIRE CODE VIOLATION; 2nd Floor/Girls bathroom: Defective door near room #217. Asbestos Code A - Clear for repairs on 08/28/03. Horne Engineering - Sheryll James (RG 08/29/03) | August 27, 2003 | October 8, 2003 | 42 days |
| Winston EC | FM-200221322 /02 10/9/03 Winston First and Second floor - rooms 226 and 149 Replace circle vanity sinks in teacher bathrooms. | November 19, 2002 | October 9, 2003 | 324 days |
| West Elementary School | FM-200228580 03 10/10/03 West Ground Floor - Main Hallway by Pre-K Girls and Boys Restroom and Maintenance Office 1) Repair or replace defective incandescent light fixtures. | April 10, 2003 | October 10, 2003 | 183 days |
| Davis Elementary School | FM-200338779 /03 10/10/03 Davis Emergency !! First Floor - Girls Bathroom across from 115. 1) Shut off valve broke off, small pipe under sink is flooding, Repair pipe and shut off valve. | October 10, 2003 | October 10, 2003 | 0 days |
| West Elementary School | FM-200227090 03 10/14/03 WEST First / Ground Floor - Cafeteria And Boys Restroom 1. Breaker is not working , it keep blowiing out the bulbs and shortage. 2. Replace wall light . Asbestos Code A - Clear for repairs on 03/14/03. DCPS Safety - Richard Gibson (RG) | March 14, 2003 | October 14, 2003 | 214 days |
| Park View ES | FM-200338070 03 10/14/03 Park View Teachers restroom Toilet is not working. | September 25, 2003 | October 14, 2003 | 19 days |
| Janney Elementary School | FM-200338122 03 10/14/03 Janney First floor Boys bathroom need the faucets put on washer and tighten up. | September 26, 2003 | October 14, 2003 | 18 days |
| Janney Elementary School | FM-200338123 03 10/14/03 Janney First floor Girls bathroom toilet do not flush. | September 26, 2003 | October 14, 2003 | 18 days |
| Ronald H. Brown MS | FM-200337794 03 10/15/03 Browne Center Third Floor 1. Repair electric power to light switch. ( restroom is dark ,no electricity coming from electric panel box). | September 19, 2003 | October 15, 2003 | 26 days |
| Plummer Elementary School | FM-200333132 03 10/16/03 Plummer First Floor 1) Repair broken radiator in the boys restroom . | July 10, 2003 | October 16, 2003 | 98 days |
| Dunbar High School | FM-200202441 02 10/16/03 (DUNBAR) ASBESTOS ASSESSMENT REQUIRED GIRLS RESTROOMS THROUGHOUT & BUSINESS OFFICE 5MW: ADJUST PRESSURE 4ME: INSTALL HOT-WATER CUT-OFF VALVE BUSINESS OFFICE RESTROOM: INSTALL CUT-OFF VALVE ASBESTOS CODE A-CLEAR FOR REPAIR ON 2/05/02 BY HORNE ENGINEER: TROY WILCOME | February 5, 2002 | October 16, 2003 | 618 days |
| Patricia R Harris Ed Center | FM-200330596 03 10/20/03 Harris, P.R. Boys restroom # 7 Urinal stopped up and overflowing commode. | May 22, 2003 | October 20, 2003 | 151 days |
| Hine JHS | FM-200333511 03 10/20/03 Hine Second Floor 1. Replace handle assembly in ladies restroom. Asbestos Code A - Clear for repairs on 07/22/03. Horne Engineering - Troy Wilcome (RG 07/23/03) | July 22, 2003 | October 20, 2003 | 90 days |
| Hine JHS | FM-200333515 03 10/20/03 Hine Third Floor 1. Replace sink fixture in men restroom . 2. Replace toilet diaphragm in ladies restroom. | July 22, 2003 | October 20, 2003 | 90 days |
| Hine JHS | FM-200333506 03 10/20/03 Hine Second Floor - B-Wing Boys Restroom 1. Unstop 2 sinks and replace fixtures . 2. Urinal need a diaphragm . | July 22, 2003 | October 20, 2003 | 90 days |
| Hine JHS | FM-200332887 03 10/20/03 Hine First & Second Floor 1. Replace flush valve in the 2nd stall in girls restroom on the 1st floor . 2. Replace flush valve in the 2nd stall in girls restroom ion the 2nd floor . | July 3, 2003 | October 20, 2003 | 109 days |
| Hine JHS | FM-200333521 03 10/20/03 Hine Third Floor 1. Replace handle assembly to the 5th urinal in boys restroom. | July 22, 2003 | October 20, 2003 | 90 days |
| Hart Middle School | FM-200339157 /03 10/21/03 (Hart) !!!VERY URGENT!!! Basement/Rec. Room: Boys and girls bathroom toilets, and urinals are stopped up. It is mandatory that we have access to these restrooms, as the Ballou High Schools students will be using them also. | October 20, 2003 | October 21, 2003 | 1 day |
| Garnet-Patterson MS | FM-200337915 03 10/21/03 (Garnett-Patterson) !!!EMERGENCY!!! Basement/Cafeteria Bathroom: Toilet backing up with sewage, and terrible odor. (Student/Staff having lunch) | September 23, 2003 | October 21, 2003 | 28 days |
| Moten Elementary School | FM-200222356 /02 10/21/03 (Moten) !!!VERY URGENT!!! Old side, 4th Floor/Boys bathroom: Commode vandalized, appears to be broken into many pieces. (To numerous to count) Asbestos Code A - Clear for repairs on 12/11/02. Horne Engineering - Tony Marcolin (RG 12/13/02) | December 10, 2002 | October 21, 2003 | 315 days |
| Park View ES | FM-200338069 03 10/21/03 Park View Second floor room 231 Boys restroom urinals is stopped up and sink is leaking water underneath. | September 25, 2003 | October 21, 2003 | 26 days |
| Lafayette Elementary School | FM-200337546 03 10/22/03 Lafayette Basement girls bathroom Pipe leaking in ceiling above sink. Bathroom in LAp Area. | September 15, 2003 | October 22, 2003 | 37 days |
| Turner Elementary School | FM-200338733 03 10/23/03 Turner Second floor old bldg. Second and third urinals in boys restroom leaking and water water fountain next to boys restroom leaking and coming off wall. Safety and health hazard. | October 9, 2003 | October 23, 2003 | 14 days |
| Backus Middle School | FM-200339119 /03 10/23/03 Backus Second floor room 205 Repir the door lock on room 205, and the teachers bathroom on the second floor repair the lock. | October 17, 2003 | October 23, 2003 | 6 days |
| Garfield ES | FM-200339074 /03 10/23/03 Garfield LL-girls bathroom two toilets in girls room need to be repaired, water is spraying from the bottom of the spuds. | October 17, 2003 | October 23, 2003 | 6 days |
| Patricia R Harris Ed Center | FM-200338418 03 10/23/03 Harris, P.R. / Patterson, W.B. Third floor both boys bathroom box room Replace face bowl faucets leaking , old, some missing. | October 2, 2003 | October 23, 2003 | 21 days |
| Johnson JHS | FM-200337637 03 10/23/03 Johnson Fourth floor boys bathroom Principal request that lock be change to the grandmaster. | September 16, 2003 | October 23, 2003 | 37 days |
| Hart Middle School | FM-200338576 03 10/24/03 Hart First Floor - Girls Bathroom - Unstop sink. First Floor - Boys Bathroom - Unstop urinal. | October 7, 2003 | October 24, 2003 | 17 days |
| Cardozo High School | FM-200339334 /03 10/25/03 (Cardozo) Dugout/Boys Bathroom: Unclog drains on two (2) urinals, both urinals will run over with water when flushed. | October 23, 2003 | October 25, 2003 | 2 days |
| Patricia R Harris Ed Center | FM-200334346 03 10/27/03 Harris, P. R. First Floor 1) Repair commodes, sink fixtures in (3) Boys Bathrooms and (3) Girls Bathrooms on First Floor near Multi Purpose Room. | August 5, 2003 | October 27, 2003 | 83 days |
| Wilson J. O. ES | FM-200339011 /03 10/27/03 Wilson, J.O. Third floor boys bathroom Snake out water closet constantly overflowing and backups. Sanitation hazard | October 16, 2003 | October 27, 2003 | 11 days |
| Webb Elementary School | FM-200338853 /03 10/27/03 (Webb) !!!URGENT!!! 1st Floor/Mens Bathroom: Sink hanging off wall, please re-attached. Asbestos Code A - Clear for repairs on 10/23/03. Horne Engineering - Edward Rodriguez (RG 10/27/03) | October 14, 2003 | October 27, 2003 | 13 days |
| Walker-Jones EC | FM-200329710 03 10/27/03 (Walker Jones) ** URGENT DUE TO RECENT BREAK-IN ** Grate that covers window in the basement girls' bathroom is broken and needs to be bolted to a brick wall. | May 5, 2003 | October 27, 2003 | 175 days |
| Turner Elementary School | FM-200339034 /03 10/27/03 (Turner) 1st and 3rd Old Building: 1st Floor boys and girls restroom, toilet stopped up. 3rd Floor restroom, urinal stopped up. | October 16, 2003 | October 27, 2003 | 11 days |
| Aiton Elementary School | FM-200337600 03 10/27/03 Aiton On all floors Faucets need to be repair or replace in all restrooms. | September 16, 2003 | October 27, 2003 | 41 days |
| Patricia R Harris Ed Center | FM-200331314 03 10/27/03 Harris, P.R. Main floor boys restroom next to # 1 stairs The sink is falling off the wall. This face bowl is falling off wall. Please respond this need to be repaired. ASAP Asbestos Code A - Clear for repairs on 06/05/03. Horne Engineering - Bipin Nanavaty (RG 06/06/03) | June 5, 2003 | October 27, 2003 | 144 days |
| Moten Elementary School | FM-200339472 /03 10/27/03 Moten Center Old Side - 4th floor - Girls Bathroom 1) Survey and see where water is coming from. | October 27, 2003 | October 27, 2003 | 0 days |
| Patricia R Harris Ed Center | FM-200228380 03 10/28/03 (Harris, P.R.) One floor - restroom # 3 ground floor Water main line need to be checked out. Some times the water backs up. | April 7, 2003 | October 28, 2003 | 204 days |
| Patricia R Harris Ed Center | FM-200228754 03 10/28/03 Harris, P.R. First,and ground floor #6 restroom, #1 on the first floor (sit down and standup) The toilet need to be reanchor to the wall; also the restroom on the main floor need to be anchored to the wall; also the partition are falling down too!! Asbestos Code A - Clear for repairs on 04/17/03. Horne Engineering - Troy Wilcome (RG 04/18/03) | April 15, 2003 | October 28, 2003 | 196 days |
| Maury Elementary School | FM-200339260 /03 10/28/03 Maury First floor teachers bathroom Unstop basin. | October 22, 2003 | October 28, 2003 | 6 days |
| Patricia R Harris Ed Center | FM-200228379 03 10/28/03 (Harris, P.R.) Third floor - restroom # 2 top floor Water comes from underneath when you flush the toilet. | April 7, 2003 | October 28, 2003 | 204 days |
| Patricia R Harris Ed Center | FM-200227892 03 10/29/03 Harris, P.R. Urgent Ground floor Restroom # 8 and 3 The restroom #8 has water coming from the bottom of the toilet and the restroom at # 3 has water overflowing whenever three or moore standup urinals are flushed at the same time. | March 31, 2003 | October 29, 2003 | 212 days |
| Patricia R Harris Ed Center | FM-200336210 03 10/29/03 Harris, P.R. Ground floor restroom # 18 and # 1 Will not flush need parts or snaking; Please respond ASAP. | August 25, 2003 | October 29, 2003 | 65 days |
| Roosevelt High School | FM-200339674 /03 10/29/03 (Roosevelt) !!!VERY URGENT!!! 3rd Floor/Ladies Bathroom near room #7 in O.B.E. area: Commode stopped up, and over-flowing when flushed. | October 29, 2003 | October 29, 2003 | 0 days |
| Backus Middle School | FM-200339116 /03 10/29/03 Backus First floor girls bathroom the sink is stopped up. The boys bathroom on the 2nd floor sink is falling down. and boys bathroom a toilet can not flush. Third floor girls bathroom toilet is stopped up. | October 17, 2003 | October 29, 2003 | 12 days |
| Deal Junior High School | FM-200339682 /03 10/30/03 Deal Third Floor - Gym - Boys Locker Bathroom 1) Repair leaking toilet that is leaking down in to room 211 from the Boys Gym Locker Room Bathroom. | October 30, 2003 | October 30, 2003 | 0 days |
| Patricia R Harris Ed Center | FM-200224801 03 10/30/03 Harris, P.R. ITV main floor Women restroom water in the sink will not stop running. | January 29, 2003 | October 30, 2003 | 274 days |
| Patricia R Harris Ed Center | FM-200330090 03 10/30/03 (Harris, P.R.) Ground Floor/#8 Restroom: Toilet is stopped up, and will not flush. | May 13, 2003 | October 30, 2003 | 170 days |
| Park View ES | FM-200339642 /03 10/30/03 Park View Health suite Restroom lock will not let you exit the restroom. | October 29, 2003 | October 30, 2003 | 1 day |
| Patricia R Harris Ed Center | FM-200227987 03 10/30/03 Harris, P.R. Top Second Floor - Restroom # 2 1) The toilet leaks from the bottom and the floor gets flooded. | April 1, 2003 | October 30, 2003 | 212 days |
| Patricia R Harris Ed Center | FM-200330597 03 10/30/03 Harris, P.R. Boys restroom # 3 Two toilets are leaking around handles. Repair / replace plummer needed. | May 22, 2003 | October 30, 2003 | 161 days |
| Savoy Elementary School | FM-200333776 03 10/31/03 (Savoy) FIRE CODE VIOLATION: 1st Floor/Storeroom: Door closure defective near girls bathroom. Asbestos Code A - Clear for repairs on 09/17/03. Horne Engineering - Bipin Nanavaty (RG 09/30/03) | July 25, 2003 | October 31, 2003 | 98 days |
| Eastern High School | FM-200336407 03 10/31/03 (Eastern) FIRE CODE VIOLATION: 3rd Floor/Near room #356: Three (3) door closures to boys bathroom. Asbestos Code A - Clear for repairs on 09/12/03. Horne Engineering - Philp Connolly (RG 09/15/03) | August 27, 2003 | October 31, 2003 | 65 days |
| Patricia R Harris Ed Center | FM-200337336 03 10/31/03 Patterson !! Emergency !! Third Floor 1. Replace stop valve in the teacher's restroom. | September 11, 2003 | October 31, 2003 | 50 days |
| Patricia R Harris Ed Center | FM-200331419 03 10/31/03 (Harris, P.R./W.B. Patterson) 3rd Floor/Girls restroom/Stairwell #4: Replace stop valve. | June 6, 2003 | October 31, 2003 | 147 days |
| Patricia R Harris Ed Center | FM-200228766 03 11/3/03 (Harris, P.R.) Ground Floor/Restroom #7: The stand-up urinal is hanging from the wall. | April 15, 2003 | November 3, 2003 | 202 days |
| Amidon Elementary School | FM-200339772 /03 11/3/03 Amidon First floor Teacher bathroom Toilet is stopped up, and it is passed my snake. Toilet is running into hall. | October 31, 2003 | November 3, 2003 | 3 days |
| Backus Middle School | FM-200338604 03 11/4/03 Backus First floor girls bathroom Need plumming work done badly. Sinks are stopped up and over flowing. | October 7, 2003 | November 4, 2003 | 28 days |
| Lincoln Middle School | FM-200329295 03 11/4/03 (Lincoln/Taft) 3rd Floor-Circuit breaker/Near girls restroom: Repair or replace one of the circuit breakers that has blown out. | April 30, 2003 | November 4, 2003 | 188 days |
| Lincoln Middle School | FM-200225540 03 11/4/03 Lincoln Second floor gym- boys side office No water supply to restroom needs to be restored. Toilet, shower and sink not working. Signs of structual damage from the busted steamline it can not release system. Asbestos Code A - Clear for repairs on 02/20/03. Horne Engineering - Troy Wilcome (RG02/28/03) | February 11, 2003 | November 4, 2003 | 266 days |
| Patricia R Harris Ed Center | FM-200334024 03 11/4/03 (Harris, P.R.) Ground Floor/Restroom #1: Toilet has an object stuck inside commode; unable to unstop. Please respond as soon as possible. (Summer school is in session) | July 30, 2003 | November 4, 2003 | 97 days |
| Patricia R Harris Ed Center | FM-200332124 03 11/4/03 Harris, P.R. Ground floor near stairwell #7 Boys bathroom toilet is backing up.( center toilet | June 19, 2003 | November 4, 2003 | 138 days |
| Tubman Elementary School | FM-200339194 /03 11/4/03 Tubman First floor space 53 teachers lounge restroom Replace hot water cut off valve on sink # 1. | October 21, 2003 | November 4, 2003 | 14 days |
| Patricia R Harris Ed Center | FM-200330598 03 11/4/03 Harris, P.R. Girls restroom # 2 Commode stopped up need to be snaked out by plummer. | May 22, 2003 | November 4, 2003 | 166 days |
| Patricia R Harris Ed Center | FM-200339199 /03 11/5/03 Harris, P.R. / Patterson, W.B. Third floor boys bathroom sws Unstop toilet. | October 21, 2003 | November 5, 2003 | 15 days |
| Davis Elementary School | FM-200339925 03 11/6/03 Davis First and basement bathrooms by 218 and 16 Repair lock cylinder to boys and girls bathroom by room 218 and girls bathroom door by room 16. | November 5, 2003 | November 6, 2003 | 1 day |
| Woodson High School | FM-200339641 /03 11/7/03 Woodson, H.D. Girls bathroom Commode running over, 3rd floor hallway and classroom. | October 29, 2003 | November 7, 2003 | 9 days |
| Spingarn High School | FM-200340046 03 11/10/03 (Spingarn) !!!EMERGENCY!!! 1st Floor/Boys Bathroom: Water shooting out from urinals, floors are flooding. (Unable to shut the water off) | November 6, 2003 | November 10, 2003 | 4 days |
| Harris, C.W. ES | FM-200338449 03 11/13/03 Harris, C.W. Second floor boys bathroom Urinal coming off the wall. Asbestos Code A - Clear for repairs on 10/03/03. Horne Engineering - Ray Agnant (RG 10/08/03) | October 3, 2003 | November 13, 2003 | 41 days |
| Gage-Eckington ES | FM-200338144 03 11/14/03 (Gage-Eckington) !!!VERY URGENT!!! First floor head start Girls restroom intermediate side Bathroom (2) toilets are dripping from handle, Need to replace and girl intermediaste side toilet will not flush. | September 29, 2003 | November 14, 2003 | 46 days |
| Green Elementary School | FM-200338617 03 11/14/03 Green First floor lobby Repair urinal in boy restroom in main lobby. Snake out urinals boy bathroom first floor. | October 7, 2003 | November 14, 2003 | 38 days |
| Woodson High School | FM-200340372 /03 11/17/03 (Woodson, H.D.) 3rd Floor/Boys Restroom: Water flooding the floors due to broken shut-off valve | November 17, 2003 | November 17, 2003 | 0 days |
| Stanton Elementary School | FM-200338175 03 11/18/03 Stanton First floor Boys and girls bathroom The glass need to be put back in. | September 29, 2003 | November 18, 2003 | 50 days |
| Emery Elementary School | FM-200337938 03 11/18/03 (Emery) Third Floor - Bathroom 1) Unclog bradley basin . | September 17, 2003 | November 18, 2003 | 62 days |
| Kramer Middle School | FM-200340349 /03 11/18/03 Kramer First Floor - Boys Bathroom 1) Ceiling Leaking. | November 17, 2003 | November 18, 2003 | 1 day |
| Jefferson JHS | FM-200338331 03 11/18/03 Jefferson All floors Windows falling out: Boys bathroom frame is broken | October 1, 2003 | November 18, 2003 | 48 days |
| Jefferson JHS | FM-200334447 03 11/19/03 Jefferson First floorhealth suite bathroom Replace cracked commode water spraying, can not use commode. | August 5, 2003 | November 19, 2003 | 106 days |
| Bell High School | FM-200340455 /03 11/19/03 (Bell) 2nd Floor/Boys and Girls Restroom: Repair urinal, and flush valve . | November 18, 2003 | November 19, 2003 | 1 day |
| Ludlow-Taylor ES | FM-200340493 /03 11/20/03 (Ludlow-Taylor) 1st Floor/Day Care: Sink stopped up in girls bathroom, running over. | November 19, 2003 | November 20, 2003 | 1 day |
| Ludlow-Taylor ES | FM-200339698 /03 11/20/03 Ludlow-Taylor First floor all purpose and third floor boys bathroom Repair urinal in men bathroom. Repair leak on 3rd stool on third floor. | October 30, 2003 | November 20, 2003 | 21 days |
| Ludlow-Taylor ES | FM-200339697 /03 11/20/03 Ludlow-Taylor Second floor boys bathroom R/R urinal, Will not flush. | October 30, 2003 | November 20, 2003 | 21 days |
| Bell High School | FM-200340599 /03 11/21/03 Bell Third floor boys restroom Snake out two urinals due to stoppage. One spud needed on toilet. Two set of self closing faucets needed. | November 21, 2003 | November 21, 2003 | 0 days |
| Turner Elementary School | FM-200339597 /03 11/21/03 (Turner) New Building/1st & 3rd Floor: Change lock on conference room door, outside, and inside. Also, remove broken key from lock of girls restroom door. Key is needed for room #317. | October 28, 2003 | November 21, 2003 | 24 days |
| Spingarn High School | FM-200337709 03 11/24/03 (Spingarn) !!!VERY URGENT!!! Basement/Barber Shop: Bathroom toilet backing up in the shower. 11/20/2003-Staff member called in to report repairs were never made, and problem still exist. | September 17, 2003 | November 24, 2003 | 68 days |
| Cooke H.D. Elementary School | FM-200337671 03 11/24/03 Cooke, H.D. Basement, 3rd floor new wing Boys and girls restroom Faucets are broken through out facility. Total of faucets that need repairing are 9 or replace. | September 16, 2003 | November 24, 2003 | 69 days |
| Davis Elementary School | FM-200340532 /03 11/24/03 Davis First and second floor boys and girls bathroom new wing Shutoff valves need to be replace under sink, water leaks out fast when you turn water pressure down. | November 20, 2003 | November 24, 2003 | 4 days |
| Bell High School | FM-200340600 /03 11/24/03 Bell Second floor boys restroom Replace existing knob lock. | November 21, 2003 | November 24, 2003 | 3 days |
| Hardy Middle School | FM-200340210 /03 12/1/03 (Hardy) !!!URGENT!!! 2nd Floor/Girls Bathroom: Stopped up sink, please repair before Friday, November 14. 2003 when special activities will begin. | November 12, 2003 | December 1, 2003 | 19 days |
| Harris, C.W. ES | FM-200340888 03 12/1/03 (Harris) !!!VERY URGENT!!! 2nd Floor/Boys Restroom: Leak in cold water supply line on sink; unable to shut water off. | December 1, 2003 | December 1, 2003 | 0 days |
| Davis Elementary School | FM-200340848 03 12/1/03 Davis Unstop toilets in girls room, new wing. | December 1, 2003 | December 1, 2003 | 0 days |
| Jefferson JHS | FM-200340906 03 12/1/03 (Jefferson) 1st Floor/Gym Area: Water constantly running in urinals, spilling over flooding the floor. (Unable to shut the water off) Gym Area: Hot water pipe busted in the coach staff bathroom; unable to shut off water. | December 1, 2003 | December 1, 2003 | 0 days |
| Backus Middle School | FM-200340540 /03 12/2/03 Backus Second and third floor rooms 205, 208, 210, 315 and girls gym bathroom Repair or replace locks and hardware in the above location. | November 20, 2003 | December 2, 2003 | 12 days |
| Maury Elementary School | FM-200340935 03 12/2/03 Maury First Floor - Boys Bathroom 1) Repair Bradley Basin. | December 2, 2003 | December 2, 2003 | 0 days |
| Hardy Middle School | FM-200339896 03 12/3/03 (Hardy) !!VERY URGENT!! 3rd Floor/Boys Bathroom: Toilets over-flowing in boys restroom, flooding the floors, running in-to the hallway. | November 4, 2003 | December 3, 2003 | 29 days |
| Jessie LaSalle Elementary | FM-200340088 03 12/3/03 LaSalle Third floor boys bathroom The last urinal in boys bathroom is stopped up. | November 7, 2003 | December 3, 2003 | 26 days |
| Woodson High School | FM-200340343 /03 12/5/03 Woodson SHS Water running in to hallways and classrooms. 1) 5th Floor - Girls Restroom - Water leaking from cut off valve. 2) 3rd Floor - Boys Restroom - Water running from under the commode. 3) Ground Floor - Kitchen - Water running from bottom of the pipe. 4) Ground Floor - Custodial Office - Water leaking from cut off valve. | November 17, 2003 | December 5, 2003 | 18 days |
| Bell High School | FM-200340596 /03 12/8/03 Bell Third floor girls restroom Three sinks need self closing valves. | November 21, 2003 | December 8, 2003 | 17 days |
| Browne Junior High School | FM-200340672 /03 12/9/03 (Browne Center) 3rd Floor/Boys Bathroom: Restore electrical power to lights. (Very dark to see) | November 24, 2003 | December 9, 2003 | 15 days |
| Eastern High School | FM-200340940 03 12/10/03 Eastern 348, across from 144 - across 162 - gym area Bathrooms from room 144 boys key knob malfunctions will lock child in bathroom (2) room 348 key knob lock can not opened from outside - 348 is copy room for teachers. Gym area 2 doors are hung the wrong way, panic bar is on inside - if doors is shut you can be trapped inside of gym area without key you can not exit. Safety Hazard | December 2, 2003 | December 10, 2003 | 8 days |
| Roosevelt High School | FM-200341306 03 12/10/03 (Roosevelt) Asbestos Assessment Required. Gym Area: Door closers needed in the following area's: 1. Door near bleachers inside gym. 2. Girls bathroom - Gym hallway. 3. Door leading to gym area. Repairs are to be made by December 11, 2003, for Special Education Compliance. Asbestos Code A - Clear for repairs on 12/10/03. Horne Engineering - Raymond Agnant (RG 12/10/03) | December 9, 2003 | December 10, 2003 | 1 day |
| Eastern High School | FM-200340939 03 12/11/03 Eastern Across B-78 from 144 - Across from 162 Bathrooms across boyd girls from room 144 - room 162 stadium bathroom boys under press box hole in urinal. Leaking from urinal boys leaking teachers bathroom from 162. Replace faucets in boys bathroom from B-78. | December 2, 2003 | December 11, 2003 | 9 days |
| Seaton Elementary School | FM-200332378 03 12/11/03 (Seaton) FIRE CODE VIOLATION; 1st Floor/Girls Bathroom: Water leaking down into electrical appliance. | June 23, 2003 | December 11, 2003 | 171 days |
| Merritt Middle School | FM-200339695 /03 12/12/03 Merritt First and third floor Main office, principal office, repair or replace faucet in the principal restroom water constantly running. Third floor locker area repair or replace flush valve in the boys restroom the urinal will not flush. | October 30, 2003 | December 12, 2003 | 43 days |
| Roosevelt High School | FM-200341410 /03 12/12/03 (Roosevelt) !!!VERY URGENT!!! Next Too Room #115: Sink needs to be hung on the wall in the girls bathroom. | December 10, 2003 | December 12, 2003 | 2 days |
| Jessie LaSalle Elementary | FM-200341304 03 12/15/03 LaSalle Third floor bathroom #rd toilet from enter 07 bathroom need wax ring. Water leaking non stop, Safety Hazard child may slip and hurt themselves. | December 9, 2003 | December 15, 2003 | 6 days |
| Maury Elementary School | FM-200341411 /03 12/16/03 (Maury) Repair locks in the following area's: P.E. office, 1st floor east bldg., girls restroom, 2nd floor east bldg., classroom 22, 2nd floor east bldg, doors will not lock. | December 10, 2003 | December 16, 2003 | 6 days |
| Simon Elementary School | FM-200341178 03 12/16/03 Simon Second floor boys restroom Can not shut off the valve. The adjustment screw is ate upon the urinal. | December 8, 2003 | December 16, 2003 | 8 days |
| Turner Elementary School | FM-200341608 /03 12/18/03 (Turner) New Side/1st Floor: Change locks to restroom on boys, and girls restroom. | December 15, 2003 | December 18, 2003 | 3 days |
| Terrell Mc ES | FM-200333724 03 12/22/03 (M.C. Terrell) FIRE CODE VIOLATION: 2nd Floor/Boys bathroom: Door defective. Code A-clear for repairs by Charles Buchanan DCPS Asbastos Compliance on 7/24/03 | July 23, 2003 | December 22, 2003 | 152 days |
| Terrell Mc ES | FM-200333726 03 12/22/03 (M.C. Terrell) FIRE CODE VIOLATION: 1st Floor/Mens Bathroom: Door defective. Code A-clear for repairs by Charles Buchanan DCPS Asbastos Compliance on 7/24/03 | July 23, 2003 | December 22, 2003 | 152 days |
| Terrell Mc ES | FM-200333722 03 12/22/03 (M.C. Terrell) FIRE CODE VIOLATION: 3rd Floor/Boys bathroom: 2nd door defective. Code A-clear for repairs by Charles Buchanan DCPS Asbastos Compliance on 7/24/03 | July 23, 2003 | December 22, 2003 | 152 days |
| Terrell Mc ES | FM-200333725 03 12/22/03 (M.C. Terrell) FIRE CODE VIOLATION: 2nd Floor/Girls bathroom: Door defective. Code A-clear for repairs by Charles Buchanan DCPS Asbastos Compliance on 7/24/03 | July 23, 2003 | December 22, 2003 | 152 days |
| Terrell Mc ES | FM-200333721 03 12/22/03 (M.C. Terrell) FIRE CODE VIOLATION: 3rd Floor/Girls bathroom: 2nd door defective. Code A-clear for repairs by Charles Buchanan DCPS Asbastos Compliance on 7/24/03 | July 23, 2003 | December 22, 2003 | 152 days |
| Brent Elementary School | FM-200341977 /03 12/23/03 (Brent) 3rd Floor/Boys Restroom: Students standing on urinal, causing urinal to come loose from the wall. | December 22, 2003 | December 23, 2003 | 1 day |
| Terrell Mc ES | FM-200342031 /03 12/23/03 Terrell, M.C. First Floor - Boys and Girls Bathroom 1) No lights, checked all switches... | December 23, 2003 | December 23, 2003 | 0 days |
| Truesdell Elementary | FM-200224790 03 12/30/03 (Truesdell) !!!VERY URGENT!!! Annex building/2nd floor Girls Bathroom: Water does not come out properly from bradley basin; when turned on, it drips. 0909/2003: Engineer calls in to report conditions are the same. | January 29, 2003 | December 30, 2003 | 335 days |
| Truesdell Elementary | FM-200342115 /03 12/30/03 (Truesdell) 1st Floor/Girls Restroom: Flush valve will not shut off. | December 29, 2003 | December 30, 2003 | 1 day |
| Truesdell Elementary | FM-200341948 /03 12/30/03 (Truesdell) !!!VERY URGENT!!! 1st Floor Annex/Girls Restroom: Repair bradley basin; shut off due to leak at the bottom. (Students are unable to wash hands while the water is shut-off) | December 22, 2003 | December 30, 2003 | 8 days |
| Birney Elementary School | FM-200342139 /03 12/31/03 (Birney) !!!EMERGENCY!!! 1st and 3rd Floor: Unclog slop sinks in custodian closets too prevent flooding near rooms #108, and #308. Also: Custodian Office Restroom: Water running profusely from shut-off valve. | December 30, 2003 | December 31, 2003 | 1 day |
| Payne Elementary School | FM-200334442 03 12/31/03 Payne Second floor boys restroom old building One urinal is not working due to low water pressure. | August 5, 2003 | December 31, 2003 | 148 days |
| Payne Elementary School | FM-200334441 03 12/31/03 Payne First floor lobby boys Restroom replace wax ring on urinals. | August 5, 2003 | December 31, 2003 | 148 days |
| Payne Elementary School | FM-200334440 03 12/31/03 Payne Second floor girls restroom old building Two commode not working, water pressure and one need a flush valves. Urgent | August 5, 2003 | December 31, 2003 | 148 days |
| Payne Elementary School | FM-200334435 03 12/31/03 Payne First floor girls restroom new wing Four toilets needs flush valves and has no water pressure. | August 5, 2003 | December 31, 2003 | 148 days |
| Payne Elementary School | FM-200334437 03 12/31/03 Payne First floor boys restroom new wing Three (3) urinals has no water pressure Second toilet has no water pressure. | August 5, 2003 | December 31, 2003 | 148 days |
| Payne Elementary School | FM-200334436 03 12/31/03 Payne Second floor boys restroom new wing First toilet bad flush valve and no water pressure. | August 5, 2003 | December 31, 2003 | 148 days |
| Beers Elementary School | FM-200340603 /03 1/5/04 Beers First floor bldg. #1 Girls restroom handicap toilet is broken. Water running out. Bdg. # 1 2nd floor sink is hanging off wall (girls restroom). | November 21, 2003 | January 5, 2004 | 45 days |
| Eliot Junior High School | FM-200340863 03 1/5/04 (Eliot) 1st Floor/Girls Restroom:l Water from radiator lines coming through the floor; needs to be capped off. | December 1, 2003 | January 5, 2004 | 35 days |
| Beers Elementary School | FM-200339115 /03 1/6/04 Beers Second floor bldg. # 1 Girls restroom sink is hanging from wall. | October 17, 2003 | January 6, 2004 | 81 days |
| Hendley Elementary School | FM-200341014 03 1/6/04 Hendley Third and second floor custodian closet Faucet are leaking hot water every day, because of that water leak the ceiling is falling, also 3rd and 2nd floor bathroom toilet 2nd one from thewall, the water just run and the valves are off and the water is still running. | December 3, 2003 | January 6, 2004 | 34 days |
| Ludlow-Taylor ES | FM-200226665 03 1/7/04 Ludlow-Taylor First floor boys bathroom Repair door so it can close, so gate can be unlocked. Asbestos Code A - Clear for repairs on 04/14/03. Horne Engineering - Sharon Voss (RG 04/15/03) | March 6, 2003 | January 7, 2004 | 307 days |
| Ludlow-Taylor ES | FM-200226663 03 1/7/04 Ludlow-Taylor First floor girls bathroom Repair or replace door so it can open, door is very hard to open, so gate can be unlocked. Asbestos Code A - Clear for repairs on 04/14/03. Horne Engineering - Sharon Voss (RG 04/15/03) | March 6, 2003 | January 7, 2004 | 307 days |
| Harris, C.W. ES | FM-200442364 04 1/7/04 (Harris, C.W.) 1st Floor/Girls Bathroom: Two (2) commodes stopped up, water shut off, and water running from the base of the toilet. Boys bathroom: Spud gone on urinal | January 7, 2004 | January 7, 2004 | 0 days |
| Takoma Educational Center | FM-200335797 03 1/9/04 (Takoma) FIRE CODE VIOLATION: 3rd Floor/Blue team: Girls restroom door needs adjustment. Asbestos Code A - Clear for repairs on 08/20/03. Horne Engineering - Sheryll James (RG 08/22/03) | August 19, 2003 | January 9, 2004 | 143 days |
| Macfarland Middle School | FM-200340187 /03 1/9/04 MacFarland Girls restroom in main hallway Repair restroom door, the door only has one hinge holding it. Code A-clear for repair by DCPS Charles Buchanan on 11-18-03 | November 12, 2003 | January 9, 2004 | 58 days |
| Macfarland Middle School | FM-200339860 03 1/9/04 (Macfarland) Asbestos Assessment Required. Repair fire door girls restroom third floor emergency. Asbestos Code A - Clear for repairs on 11/04/03. Horne Engineering - Bipin Nanavaty (RG 11/05/03) | November 3, 2003 | January 9, 2004 | 67 days |
| Stanton Elementary School | FM-200341795 /03 1/9/04 Stanton Second floor Bathroom urinals need to be unstopped. | December 18, 2003 | January 9, 2004 | 22 days |
| Takoma Educational Center | FM-200335872 03 1/9/04 (Takoma) FIRE CODE VIOLATION: 2nd Floor/Mens restroom: Need door adjustment. (Yellow team) Asbestos Code A - Clear for repairs on 08/20/03. Horne Engineering - Sheryll James (RG 08/22/03) | August 20, 2003 | January 9, 2004 | 142 days |
| Brightwood Elementary School | FM-200442477 04 1/12/04 Brightwood Emergency !!!! Annex - Boys Bathroom 1) Busted pipe. | January 12, 2004 | January 12, 2004 | 0 days |
| Wilson J. O. ES | FM-200335471 03 1/13/04 Wilson, J.O. F-343.5 FIRE CODE VIOLATION: First floor Kitchen bathroom doors defective. Asbestos Code A - Clear for repairs on 09/17/03. Horne Engineering -Troy Wilcome (RG 09/23/03) | August 15, 2003 | January 13, 2004 | 151 days |
| Woodson High School | FM-200336000 03 1/13/04 (Woodson) FIRE CODE VIOLATIONS: Ground Floor/Auditorium: Door hinge broke in the girls bathroom, and stage door. Asbestos Code A - Clear for repairs on 09/11/03. Horne Engineering - Roger Kager (RG 09/12/03) | August 21, 2003 | January 13, 2004 | 145 days |
| Murch Elementary School | FM-200442638 04 1/14/04 Murch Second floor boys restroom Unstop urinal needed water runs all over floor. One sink leaking (bad). | January 13, 2004 | January 14, 2004 | 1 day |
| Benning Elementary School | FM-200442733 04 1/14/04 Benning Learning center 1 Both girls bathroom water is shooting out of the drains. | January 14, 2004 | January 14, 2004 | 0 days |
| Hart Middle School | FM-200442451 04 1/15/04 Hart Need Girls bathroom 1st floor 2 panes, Gym classroom 1pane, Stairway #9 1 pane, Room 123 1 pane, Rec area 9 panes, room 134 new wing 1 pane and Kitchen 1 pane. | January 9, 2004 | January 15, 2004 | 6 days |
| Beers Elementary School | FM-200442544 04 1/15/04 Beers First and second floor Bldg. #3 Floor 1: Door / locks not working, Will not lock the children are getting in the room. Boys restroom first floor will not lock. Replace or repair. Room 217 door not working properly repair or replace. | January 12, 2004 | January 15, 2004 | 3 days |
| John Burroughs ES | FM-200442724 04 1/15/04 Burroughs First Floor - Boys Bathroom 1) Repair leaking nipple on urinal . | January 14, 2004 | January 15, 2004 | 1 day |
| Randle-Highlands ES | FM-200442988 04 1/20/04 Randle-Highlands Second floor staff bathroom Toilet is stopped up, can not unstopped it. | January 20, 2004 | January 20, 2004 | 0 days |
| Wilson J. O. ES | FM-200335465 03 1/20/04 Wilson, J.O. F-343.5 FIRE CODE VIOLATION: First floor Boys bathroom exit door hardware missing. Asbestos Code A - Clear for repairs on 09/17/03. Horne Engineering -Troy Wilcome (RG 09/23/03) | August 15, 2003 | January 20, 2004 | 158 days |
| Woodson High School | FM-200443029 04 1/21/04 Woodson, HD Emergency Third floor Boys restroom water is coming up from the bottom of toilet. The water is so bad it is going on the floors below. | January 21, 2004 | January 21, 2004 | 0 days |
| Ludlow-Taylor ES | FM-200443020 04 1/21/04 Davis First floor Kitchen Unstop toilet in bathroom. | January 21, 2004 | January 21, 2004 | 0 days |
| Francis Junior High School | FM-200442853 04 1/21/04 Francis First floor girls restroom Replace door knob, broken. | January 16, 2004 | January 21, 2004 | 5 days |
| Wilkinson ES | FM-200442297 04 1/21/04 (Wilkinson) 1st Floor/Main Office #99: Bathroom sink stopped up; in-house staff attempted too unstop with plunger, and it did not work. | January 6, 2004 | January 21, 2004 | 15 days |
| Davis Elementary School | FM-200443019 04 1/21/04 Davis First floor boys bathroom by 104 Repair wax ring to toilet second stall. | January 21, 2004 | January 21, 2004 | 0 days |
| Clark Elementary School | FM-200443063 04 1/22/04 Clark Urgent !! Second Floor - Boy Bathroom and First Floor Library 1) Second Floor - Bradley Basin continues to run. 2) First Floor - water in sink continues to run. | January 21, 2004 | January 22, 2004 | 1 day |
| Tubman Elementary School | FM-200442851 04 1/22/04 Tubman Space 37 girls bathroom Commode need a spud put on. | January 16, 2004 | January 22, 2004 | 6 days |
| Brightwood Elementary School | FM-200443103 04 1/22/04 (Brightwood) Annex Building Demountables: Provide and install heaters for hallways, and restrooms. The above area's are extremely cold. | January 22, 2004 | January 22, 2004 | 0 days |
| Davis Elementary School | FM-200341009 03 1/23/04 Davis First floor 115 bathroom and bathroom by 104 Replace damage crack toilet in room 115 and unclog two urinals in bathroom by 104, unable to unclog with snake and plunger on site. | December 3, 2003 | January 23, 2004 | 51 days |
| Merritt Middle School | FM-200443146 04 1/27/04 Merritt Gym - Girls Bathroom 1) Sink broke in Girls Bathroom, stunent sat on sink and broke the pipe...Water running everywhere. | January 23, 2004 | January 27, 2004 | 4 days |
| Sousa Middle School | FM-200220428 /02 1/27/04 Sousa Gym girls restroom First toilet will not flush properly, toilet has been snaked and plung. Fourth toilet needs stop valve so that toilet can be cut on and snaked. | October 31, 2002 | January 27, 2004 | 453 days |
| Woodson High School | FM-200443150 04 1/28/04 Woodson, HD Urgent !! Ground Floor : Repair Restrooms 1) Boys Locker Room Team Room #1 - Commode not working. 2) Team Room # 2 - Urinal not working. 3) Lobby - Boys urinal stopped up. 4) Girls LockerRoom - Commode not working. 5) Kitchen - Supply line leaking in Restroom. 6) Custodian Office - Commode not working and bowl is cracked. 7) Boys Restroom by Evevator # 1 - Replace toilet seat and paper towel box. | January 23, 2004 | January 28, 2004 | 5 days |
| Tubman Elementary School | FM-200442965 04 1/30/04 Tubman First floor space 37 girls restroom Commode need a wax ring. | January 20, 2004 | January 30, 2004 | 10 days |
| School WW High School | FM-200341074 03 2/2/04 School without walls Third floor teacher restroom Door need to be repair because door can not be shut. Door has come off hinges. Code A-clear for repair by DCPS Charles Buchanan on 12/ 05/03 | December 4, 2003 | February 2, 2004 | 60 days |
| Cook J.F. Elementary School | FM-200443345 04 2/2/04 Key Replacements for the boys and girls restroom. | January 29, 2004 | February 2, 2004 | 4 days |
| Eastern High School | FM-200336438 03 2/2/04 (Eastern) FIRE CODE VIOLATION: Basement/Near room #B-04: Boys bathroom door closure Asbestos Code A - Clear for repairs on 09/12/03. Horne Engineering - Philp Connolly (RG 09/15/03) | August 27, 2003 | February 2, 2004 | 159 days |
| Patricia R Harris Ed Center | FM-200442331 04 2/2/04 Harris, P.R. First floor food lab room 205 Need plummers to install P-trap with couplin next to garbage trap on sink. Also need girk trap and water supply lines in boys restroom top floor stairway #1. | January 7, 2004 | February 2, 2004 | 26 days |
| Stuart-Hobson Middle School | FM-200442939 04 2/2/04 Stuart-Hobson Third floor girl bathroom A toilet is leaking and the ceiling in the second floor bathroom has come in. | January 20, 2004 | February 2, 2004 | 13 days |
| Leckie Elementary School | FM-200341247 03 2/2/04 Leckie Third floor boys restroom Toilet broken in half need to replace toilet. Safety hazard for kids to use. | December 9, 2003 | February 2, 2004 | 55 days |
| Hine JHS | FM-200443600 04 2/3/04 (Hine) 3rd Floor/Restroom: Repair ruptured stop valve too toilet, and replace spud. (Leaking water) | February 2, 2004 | February 3, 2004 | 1 day |
| Bunker Hill Elementary School | FM-200443601 04 2/3/04 Bunker Hill Kgn Bathroom- 1ST Floor Repair or replace busted conventor coil in Kgn. Bathroom 1st floor. | February 2, 2004 | February 3, 2004 | 1 day |
| Meyer Elementary School | FM-200335662 03 2/4/04 Meyer All bathrooms The flush valve in the boys and girls bathrooms are leaking or will not flush. | August 19, 2003 | February 4, 2004 | 169 days |
| Emery Elementary School | FM-200334171 03 2/5/04 (Emery) Replace four faucet in men bathroom on the first floor across from main office. | July 31, 2003 | February 5, 2004 | 189 days |
| Park View ES | FM-200443585 04 2/6/04 (Park View) !!!VERY URGENT!!! Basement Floor/Boys Restroom: Repair shut-off valve, water flooding the floors. If DCPS Plumper find suspected asbestos pipe insulation doing digging call : Environmental Compliance 202- 576-5562, 202-439-7840 Code A-clear for repair by DCPS Charles Buchanan on 2/4/04 02/04/2004 12:07 CXB - | February 2, 2004 | February 6, 2004 | 4 days |
| Hine JHS | FM-200443856 04 2/10/04 (Hine) Outdoor mens restroom Water leaking behind wall to sink drain line. | February 9, 2004 | February 10, 2004 | 1 day |
| Eastern High School | FM-200443728 04 2/10/04 (Eastern) 1st & 3rd Floor: Boys & girls toilet across from room #162: Stopped up toilet. 3rd Floor/Room #324: Classroom bathroom stopped up. Teachers Lounge: Toilet stopped up. | February 5, 2004 | February 10, 2004 | 5 days |
| Jefferson JHS | FM-200443810 04 2/11/04 Jefferson Second Floor - Girls Restroom 1) Install 8" faucet on sinks. | February 9, 2004 | February 11, 2004 | 2 days |
| Hine JHS | FM-200443855 04 2/11/04 (Hine) Second Floor/girl Restroom: Unstop toilet. | February 9, 2004 | February 11, 2004 | 2 days |
| Hine JHS | FM-200443859 04 2/11/04 (Hine) Third floor boys restroom Unstop toilet. | February 9, 2004 | February 11, 2004 | 2 days |
| Park View ES | FM-200443934 04 2/11/04 Parkview Ground Floor - Boys Restroom 1) Repair brick wall and hole in concrete floor. | February 11, 2004 | February 11, 2004 | 0 days |
| Johnson JHS | FM-200443270 04 2/11/04 (Johnson) HEALTH CODE VIOLATION: EMERGENCY Kitchen: Area has been without hot water through-out school cafeteria, and restrooms. | January 27, 2004 | February 11, 2004 | 15 days |
| Malcolm X ES | FM-200442481 04 2/11/04 Malcolm Urgent !! 4th Floor - Bathrooms and Flood lights 1) Circuit Breaker needs repair. | January 12, 2004 | February 11, 2004 | 30 days |
| Hine JHS | FM-200443861 04 2/12/04 (Hine) Fourth floor ladies restroom Replace stop valve and flush valve. | February 9, 2004 | February 12, 2004 | 3 days |
| Jefferson JHS | FM-200336807 03 2/17/04 Jefferson Second floor girls bathroom Sink by the window need 2 push down handles, 2nd sink need faucet in place. | September 4, 2003 | February 17, 2004 | 166 days |
| Roosevelt High School | FM-200442809 04 2/17/04 Roosevelt First Floor - Girls Restroom by Room 117. 1) Repair ADA sinks due to vandalism. One is on the floor and the other is loose and may need re-installation. # Note - This effort is to support Middle States. | January 15, 2004 | February 17, 2004 | 33 days |
| Wilkinson ES | FM-200443014 04 2/17/04 Wilkinson First floor 44 women bathroom Need to replace faucet on sink, will not turn on. | January 21, 2004 | February 17, 2004 | 27 days |
| Roosevelt High School | FM-200443181 04 2/18/04 (Roosevelt) Girls room by room 117 Replace two wall hung lavatory sinks. | January 23, 2004 | February 18, 2004 | 26 days |
| Moten Elementary School | FM-200444148 04 2/18/04 Moten fourth floor boys restroom Water is shouting on everything, a kid broke something from the wall. | February 17, 2004 | February 18, 2004 | 1 day |
| Shepherd ES | FM-200330070 03 2/18/04 (Shepherd) !!!URGENT!!! 2nd Floor/Girls restroom: Replace two 2 wax rings | May 12, 2003 | February 18, 2004 | 282 days |
| Patricia R Harris Ed Center | FM-200342007 /03 2/20/04 Harris,P.R. Boys Restroom,Stair #5 Top Floor W.B. Patterson Side Repair hole in wall over top of urinals bowls. Cinder blocks was remove in order to repair leaking pipe. Repair to leaking pipe has been repaired. Approximate.. four (4) cinder blocks is needed to make repair | December 23, 2003 | February 20, 2004 | 59 days |
| Roosevelt High School | FM-200443752 04 2/21/04 Roosevelt First Floor - Boys Restroom 1) Handicap restroom has no running water. Student can't wash hands. ( Health Hazard) | February 6, 2004 | February 21, 2004 | 15 days |
| Murch Elementary School | FM-200207646 02 2/23/04 Murch 2nd Floor Boys' Restroom [Near 207] A stall door has fallen down and needs to be remounted. | May 14, 2002 | February 23, 2004 | 650 days |
| Stanton Elementary School | FM-200339599 /03 2/23/04 (Stanton) 3rd Floor/Boys Bathroom: Two (2) urinals clogged in boys bathroom. | October 28, 2003 | February 23, 2004 | 118 days |
| Park View ES | FM-200339586 /03 2/23/04 (Parkview) 2nd Floor/Room #232-B: Boys bathroom toilet leaking water from spud. | October 28, 2003 | February 23, 2004 | 118 days |
| Stanton Elementary School | FM-200226352 03 2/23/04 Stanton Third Floor - Boys bathroom Urinal is clogged. URGENT | February 27, 2003 | February 23, 2004 | 361 days |
| Cook J.F. Elementary School | FM-200338374 03 2/23/04 (Cook, J.F.) 1st Floor/Girls Restroom: Pipe leaking under commode, replace flush valve. Valve not holding, unable to shut off water. | October 1, 2003 | February 23, 2004 | 145 days |
| Ludlow-Taylor ES | FM-200443942 04 2/24/04 Ludlow-Taylor First floor girls restroom Drain to pipe connection on first sink is cracked, causing water to leak. | February 11, 2004 | February 24, 2004 | 13 days |
| Thomas Elementary School | FM-200112210 01 2/25/04 THOMAS FIRST, SECOND, AND THIRD FLOORS GIRLS RESTROOM, SCIENCE ROOM, AND HALLWAYS 1) REPAIR/REPLACE DOOR CLOSURES IN THE FOLLOWING AREAS: THIRD FLOOR EXIT DOOR, SECOND FLOOR SCIENCE CLOSET, FIRST FLOOR OLD WING GIRLS RESTROOM, FIRST FLOOR OLD WING EXIT DOOR, AND FIRST FLOOR NEW WING EXTERIOR DOOR FIRE CODE VIOLATIONS ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/21/01. | June 4, 2001 | February 25, 2004 | 996 days |
| Wilkinson ES | FM-200341737 /03 2/25/04 (Wilkinson) HEALTH CODE VIOLATION; Kitchen/Restroom: Provide hot water too handsinks. | December 17, 2003 | February 25, 2004 | 70 days |
| Ballou Senior High School | FM-200339297 /03 2/25/04 Ballou / Convention center First floor mens bathroom Two (2) sinks are stopped up plumbers are needed to unclog the drains. | October 22, 2003 | February 25, 2004 | 126 days |
| Jefferson JHS | FM-200444440 04 2/26/04 Jefferson Boys Bathroom - ( Area Unknown) 1) Unstop urinals in Boys Lavatory. | February 25, 2004 | February 26, 2004 | 1 day |
| Wilson J. O. ES | FM-200442694 04 2/26/04 Wilson, J.O, First floor girls bathroom Toilet is not working properly. | January 14, 2004 | February 26, 2004 | 43 days |
| Wilson J. O. ES | FM-200442695 04 2/26/04 Wilson, J.O, First floor boys bathroom old side The urinal is not working properly. | January 14, 2004 | February 26, 2004 | 43 days |
| Meyer Elementary School | FM-200444500 04 2/27/04 (Meyer) 2nd Floor/Boys Bathroom: Key broke off in door. | February 26, 2004 | February 27, 2004 | 1 day |
| Patricia R Harris Ed Center | FM-200443931 04 2/27/04 Harris, P.R. Girls Restroom at Stairwell # 6 1) Toilet out of order and is running over ,something inside of toilet the snake won't get out. | February 11, 2004 | February 27, 2004 | 16 days |
| Green Elementary School | FM-200336167 03 2/27/04 Green Remove electrical outlet in boys and girls restroom. Bradley basins that do not work. | August 25, 2003 | February 27, 2004 | 186 days |
| Winston EC | FM-200332460 03 2/27/04 Winston All floor bathrooms Replace sinks in rooms 368, 369, 210, 230, 131 and 111. Asbestos Code A - Clear for repairs on 02/20/04. Horne Engineering - Sheryll James (RG 02/20/04) | June 25, 2003 | February 27, 2004 | 247 days |
| Garnet-Patterson MS | FM-200333214 03 3/1/04 Garnet-Patterson Third floor Girls restroom Broken PCP pipe leading to the drain. Water was shut off. | July 14, 2003 | March 1, 2004 | 231 days |
| Draper Elementary School | FM-200444566 04 3/1/04 (Draper) !!!EMERGENCY!!! Through-Out Building: 1st, 2nd & 3rd Floor and Bathrooms, Basement and Teachers Lounge. Restore electrical power to these area's. | February 27, 2004 | March 1, 2004 | 3 days |
| Whittier Elementary School | FM-200443953 04 3/1/04 Whittier Second floor Principal restroom Replace faucet. (no cut off valve) Hot water runs continuously. | February 11, 2004 | March 1, 2004 | 19 days |
| Whittier Elementary School | FM-200443956 04 3/1/04 Whittier First floor girls restroom old side Toilet need to be remounted or wax ring. | February 11, 2004 | March 1, 2004 | 19 days |
| Garnet-Patterson MS | FM-200213072 02 3/1/04 Garnet-Patterson ****Emergency**** Basement Cafeteria [Girls' Restroom] Repair leaking pipe above ceiling in the female lavatory---leak was repaired, but has begun leaking again (auditorium is over top of area) and ceiling has fallen down. | July 26, 2002 | March 1, 2004 | 584 days |
| Stoddert ES | FM-200444460 04 3/1/04 Stoddert Urgent !!! First Floor - Girls Bathroom 1) Student sat on sink and sink is coming off of the walls. All bolts are broken. | February 26, 2004 | March 1, 2004 | 4 days |
| Garnet-Patterson MS | FM-200223657 03 3/1/04 (Garnet-Patterson) 1st Floor/Boys restroom: Hot water leaking from ruptured pipe. | January 9, 2003 | March 1, 2004 | 417 days |
| Wilkinson ES | FM-200444234 04 3/1/04 Wilkinson Second Floor - Boys Bathroom - 180 1) Urinal leaking from wall. Asbestos Code A - Clear for repairs on 02/23/04. Horne Engineering - Bjame Smith (RG 02/24/04) | February 19, 2004 | March 1, 2004 | 11 days |
| Wilkinson ES | FM-200444435 04 3/1/04 (Wilkinson) !!!URGENT!!! 1st Floor/Boys Bathroom #91: P-Trap leaking. | February 25, 2004 | March 1, 2004 | 5 days |
| Miner Elementary | FM-200443171 04 3/1/04 Miner Second floor room 211 and 209 and 225, First floor room 146 Boys an girls restroom toilets is not working. | January 23, 2004 | March 1, 2004 | 38 days |
| Malcolm X ES | FM-200338538 03 3/1/04 (Malcolm X) The bathroom door in the conference room needs to have the lock replaced. It was broken during a n emergency situation in which the lock had to be broken to gain access to the wash basin that was overflowing. | September 9, 2003 | March 1, 2004 | 174 days |
| Wilkinson ES | FM-200338002 03 3/2/04 (Wilkinson) 1st Floor/90-Girls and Women Bathroom: Repair or replace faucet. | September 24, 2003 | March 2, 2004 | 160 days |
| King M L ES | FM-200227509 03 3/2/04 (King) !!!VERY URGENT!!! Third floor/Boys restroom: We need to have # 3, 4 urinal snaked out; They are stopped up, and water is running on the floor. | March 24, 2003 | March 2, 2004 | 344 days |
| Wilkinson ES | FM-200337164 03 3/2/04 (Wilkinson) 1st Floor/Boys Bathroom: Unable to get water to come out of Bradley basin for washing hands. | September 9, 2003 | March 2, 2004 | 175 days |
| Wilkinson ES | FM-200443815 04 3/2/04 Wilkinsin First floor 90 girls bathroom Pre K area Need to repair or replace faucet, water is flowing from faucet can not cut off, in house tried. | February 9, 2004 | March 2, 2004 | 22 days |
| Wilkinson ES | FM-200444391 04 3/2/04 (Wilkinson) 1st Floor/Bathroom #90: Repair or replace single faucet in the girls restroom. | February 24, 2004 | March 2, 2004 | 7 days |
| King M L ES | FM-200340843 03 3/2/04 King, M.L. Third floor girls bathroom Need to have #1, #6 toilet repair, the water continue to run. | December 1, 2003 | March 2, 2004 | 92 days |
| King M L ES | FM-200340844 03 3/2/04 King, M.L. First floor girls bathroom Need to have #1 toilet repair, the water continue to run. | December 1, 2003 | March 2, 2004 | 92 days |
| Dunbar High School | FM-200118991 01 3/3/04 DUNBAR STADIUM BOYS AND GIRLS RESTROOM CONNECT HEATING DEFICENCIES IN RESTROOM. WP-200108905 | September 4, 2001 | March 3, 2004 | 911 days |
| Amidon Elementary School | FM-200444338 04 3/3/04 Amidon Teacher bathroon (Pre kindergarden) The bathroom inside room 134 is backed up. | February 23, 2004 | March 3, 2004 | 9 days |
| Jessie LaSalle Elementary | FM-200228569 03 3/4/04 (Lasalle) Basement/Cafeteria: Toilet stopped up in the boys bathroom; snake out toilet. | April 10, 2003 | March 4, 2004 | 329 days |
| Woodson High School | FM-200443155 04 3/4/04 Woodson, HD Urgent !! 4th,3rd,2nd,1st and Plaza - Repair Restrooms 1) 4th - Boys 2 urinals not working. 2) 4th - -Girls commodes not working and replace sinks. 3) 3rd Floor Stairwell 2 Mens urinals not working. 4) 2nd - Boys commode not working. 5) 1st - Stairwell #2 Mens cold and hot water in sink is not working. 6) Plaza - By bank hall Mens # 2 urinals not working. 7) Plaza - Ladies Restroom - Commode not working . 8) Plaza - Principal Office - Replace sink and faucet. | January 23, 2004 | March 4, 2004 | 41 days |
| Slowe Elementary School | FM-200223520 03 3/5/04 (Slowe) Basement/Library: Bathroom backing up in the toilet and shower. Asbestos Code A - Cleared for rpairs on 01-31-03 by Leroy Minton Jr (LM/02-03-03) Safety Office (202) 576-8962. | January 3, 2003 | March 5, 2004 | 427 days |
| Jessie LaSalle Elementary | FM-200444573 04 3/5/04 (Lasalle) !!!VERY URGENT!!! 2nd Floor/Boys Bathroom: Water coming through ceiling, running down walls, and sinks are stopped up. (Another bathroom is located just above this one) Asbestos Code A- Clear for repairs on 03/02/04. Horne Engineering - Philp Connolly (RG 03/02/04) | February 27, 2004 | March 5, 2004 | 7 days |
| Slowe Elementary School | FM-200336987 03 3/5/04 Slowe Water leaking wet ceiling tiles rooms are: Phys. office Boys restroom 1st floor old side Speech clinic 2nd ran room Rooms 117, 116, 126, 102, 100 and 122 | September 8, 2003 | March 5, 2004 | 179 days |
| Tubman Elementary School | FM-200444637 04 3/5/04 Tubman Secondf loor boys restroom Replace spud on urinal. | March 1, 2004 | March 5, 2004 | 4 days |
| Garfield ES | FM-200215441 02 3/5/04 Garfield F-608.1 Fire Code Violation 1. Asbestos Assessment Reqd. 2nd Floor Girls' Restroom/New Wing 2. Girls' restroom needs adjustment to door. Asbestos Code A - Clear for repairs on 08/26/02. DCPS Safety - Leroy Minton Jr. (RG 08/27/02) ## this door is out of line ## | August 23, 2002 | March 5, 2004 | 560 days |
| Payne Elementary School | FM-200334444 03 3/7/04 Payne Third floor boys restroom old building One commode is not working due to low water pressure. Same bathroom ceiling is falling down in bathroom. | August 5, 2003 | March 7, 2004 | 215 days |
| Miner Elementary | FM-200444561 04 3/8/04 (Miner) 2nd Floor/Room #208: Girls restroom toilet is not working. | February 27, 2004 | March 8, 2004 | 10 days |
| Miner Elementary | FM-200444564 04 3/8/04 (Miner) 2nd Floor/Room #210: Boys restroom urinals and toilet is stopped up. | February 27, 2004 | March 8, 2004 | 10 days |
| Brightwood Elementary School | FM-200444723 04 3/8/04 Brightwood First Floor - Boys Bathroom 1) Unstop urinal. | March 3, 2004 | March 8, 2004 | 5 days |
| Brightwood Elementary School | FM-200443936 04 3/8/04 (Brightwood) Repair or replace hot water shut off valve in the global village on first floor. Repair or replace leaking faucets in boys , girls and teachers bathroom in global village. Please tighten all faucets in the bathrooms in the global village. | February 11, 2004 | March 8, 2004 | 26 days |
| Burrville Elementary School | FM-200444420 04 3/8/04 Burrville First Floor - Boys Bathroom 1) Custodian changed vacuum breaker and diaphragm and water still continues to constantly run. | February 25, 2004 | March 8, 2004 | 12 days |
| Seaton Elementary School | FM-200444011 04 3/8/04 Seaton First, Secon and Third floor girls bathroom Remount proclain wall sink second floor girls. All sinks need to be reinforce. All sinks are wall hung. | February 12, 2004 | March 8, 2004 | 25 days |
| Miner Elementary | FM-200444838 04 3/8/04 (Miner) 175 Restroom in main office is not working. Flush valve will not let water through to the toilet. | March 4, 2004 | March 8, 2004 | 4 days |
| Miner Elementary | FM-200444563 04 3/8/04 (Miner) 1st Floor/Room #134: Sink restroom toilet is not working, and continues to run. | February 27, 2004 | March 8, 2004 | 10 days |
| Miner Elementary | FM-200444562 04 3/8/04 (Miner) 1st Floor/Room #148: Boys restroom toilets and urinals are not working. | February 27, 2004 | March 8, 2004 | 10 days |
| Wilkinson ES | FM-200222319 /02 3/8/04 Wlikinson First floor - 58 boys bathroom Electrician need to repair electric sensor on bradley basin, so it will cut off when it is not in use. | December 10, 2002 | March 8, 2004 | 454 days |
| Miner Elementary | FM-200444970 04 3/8/04 (Miner) 2nd Floor/Room #230: Boys restroom need new flush valve for toilets and there not enough pressure to flush toilets and urinals. Flush valve is not working properly and need to be change to regular flush valve. | March 8, 2004 | March 8, 2004 | 0 days |
| Woodson High School | FM-200443153 04 3/9/04 Woodson, HD Urgent !! 7th, 6th and 5th Floors : Repair Restrooms 1) 7th - Girls cold water running on sink 2) Stairwell #2 Mens urinal and commode needs repair. 3) 6th - Boys urinal needs repair 4) Room 610 - Kitchen sink is leaking, pipe cut in half. 5) 5th - Boys 2 urinals need repair 6) Stairwell #2 urinal needs repair. | January 23, 2004 | March 9, 2004 | 46 days |
| King M L ES | FM-200444902 04 3/9/04 King, M.L. Jr. Third floor girls bathroom Need to have # 1 toilet reanchor it move from side to side. | March 5, 2004 | March 9, 2004 | 4 days |
| King M L ES | FM-200444900 04 3/9/04 King, M.L. Jr. Third floor boys bathroom Need a washer for # 6 urinal it has a 180 flush valve. | March 5, 2004 | March 9, 2004 | 4 days |
| Gibbs Elementary School | FM-200112509 01 3/9/04 GIBBS SECOND FLOOR GIRLS RESTROOM 1) CEILING FALLING EMERGENCY!! ASBESTOS CODE A- CLEARED FOR REPAIRS ON 06/06/01. | June 5, 2001 | March 9, 2004 | 1,008 days |
| West Elementary School | FM-200442434 04 3/9/04 West First floor Need a plummer to check boys and girls bathroom by maintenance office. We are getting very strong sewage gas coming from drains and toilets. Boys water will not stop running from urinal, two toilets are crack can not turn water off. Sewage gas is coming out need some help. | January 9, 2004 | March 9, 2004 | 60 days |
| West Elementary School | FM-200223598 03 3/9/04 (West) 1st Floor/Boys and girls restroom: Unable to find shut off valve to shut water off. In order to repair water leak, we need to locate the shut off valve. | January 7, 2003 | March 9, 2004 | 427 days |
| John Burroughs ES | FM-200444956 04 3/9/04 Burroughs First floor new wing bathroom boys by 34 Sink stopped up water do not drain down. Censor sink. | March 8, 2004 | March 9, 2004 | 1 day |
| Miner Elementary | FM-200444969 04 3/10/04 (Miner) 1st Floor/Room #134: Girls restroom need new flush valve for toilets and thers not enough oressure to flush toilets and urinals. Flush valve is not woirking properly and need to be change to regular flush valve. | March 8, 2004 | March 10, 2004 | 2 days |
| Gibbs Elementary School | FM-200227958 03 3/10/04 (Gibbs) 1st Floor Kindergarten/Room #103: Restroom door is falling. (Hinges needed) !!Safety Hazard!! code A-clear for repair by DCPS Charles Buchanan on 4/02/03 | March 31, 2003 | March 10, 2004 | 345 days |
| Gibbs Elementary School | FM-200219327 /02 3/10/04 Gibbs 1) Repair light switch in Kitchen Bathroom. | October 11, 2002 | March 10, 2004 | 516 days |
| Gibbs Elementary School | FM-200335360 03 3/10/04 Gibbs HEALTH CODE VIOLATION Asbestos Assessment Required. Kitchen 1. Provide self closing device on bathroom or repair existing closing device on bathroom door. | August 15, 2003 | March 10, 2004 | 208 days |
| Benjamin Banneker Academic HS | FM-200224271 03 3/10/04 Banneker Bathrooms Assess and abate marked area of bathrooms for shut off valve installation. Asbestos Code A - Clear for repairs on 01/23/03. Horne Engineering - Troy Wilcome (RG 01/24/03) | January 21, 2003 | March 10, 2004 | 414 days |
| West Elementary School | FM-200223599 03 3/10/04 (West) 1st Floor/Boys restroom right side: Wall urinals leaks from the wall in the boys restroom in the right side of the learning center, also, left side boys restroom toilet is stopped up; snake ons-site is not long enough to unstop toilets. | January 7, 2003 | March 10, 2004 | 428 days |
| Benjamin Banneker Academic HS | FM-200222983 /02 3/10/04 Banneker Install cold water shut off valves in rooms below: Basement boys room Locker room, Boys Second floor boys bathroom Third floor boys bathroom Asbestos Code A - Clear for repairs on 12/19/02. Horne Engineering - Philp Connolly (RG 12/23/02) | December 20, 2002 | March 10, 2004 | 446 days |
| Benjamin Banneker Academic HS | FM-200218418 02 3/10/04 Banneker 1) Water clost gasket removal all bathrooms throughout the school. Charles Crenshaw - Envirobate Inc. - 571-436-1150 | September 26, 2002 | March 10, 2004 | 531 days |
| Benjamin Banneker Academic HS | FM-200104855 01 3/10/04 (BANNEKER) FOOD ESTABLISHMENT INSPECTION REPORT 1. ASBESTOS ASSESSMENT REQUIRED REMOVE SCALING PAINT FROM WALLS IN KITCHEN AND RESTROOMS. Lead & Asbestos Code A - Clear For Repairs On 04/02/02. Horne Engineering - Bipin Nanavaty (RG 04/02/02) | March 5, 2001 | March 10, 2004 | 1,101 days |
| Gibbs Elementary School | FM-200228464 03 3/10/04 (Gibbs) 2nd floor/ In front of girls bathroom: Broken floor tile/Asbestos hot spot. | April 8, 2003 | March 10, 2004 | 337 days |
| Patricia R Harris Ed Center | FM-200443933 04 3/11/04 Harris, P.R. Girl's Lockeroom - Main Floor 1) Two toilets in the Girls Restroom of the Girl's Lockeroom is running over. Can not get it unstopped.. | February 11, 2004 | March 11, 2004 | 29 days |
| West Elementary School | FM-200443075 04 3/11/04 (West) 2nd Floor/Library: Toilet will not flush in the boys bathroom; students are still using it that way. | January 21, 2004 | March 11, 2004 | 50 days |
| Beers Elementary School | FM-200445157 04 3/11/04 Beers First floor bldg. # 3 Girls restroom handle lock is not holding painters and plasters have equipment in restroom during repairs for safety door need to be lock. URGENT | March 10, 2004 | March 11, 2004 | 1 day |
| Bancroft Elementary School | FM-200445343 04 3/12/04 Bancroft Third floor boys bathroom The urinal keeps running, a worker broke something off and the shut off valve for the water can not be found. | March 12, 2004 | March 12, 2004 | 0 days |
| Jefferson JHS | FM-200444035 04 3/12/04 (Jefferson) sink on first floor boys and girl bathroom broken children cant wash their hand,s URGENT Account #: | February 10, 2004 | March 12, 2004 | 31 days |
| Sousa Middle School | FM-200444701 04 3/12/04 (Sousa) 1st Floor/Girls Restroom: Unable to shut hot water valve off, furnish and replace gasket. March 10, 2004: Plumbers came, made repairs on the valve. Engineer reports the water pressure is very low. | March 2, 2004 | March 12, 2004 | 10 days |
| Hendley Elementary School | FM-200443423 04 3/12/04 Hendley Repair plumbimng throughout building. 1. Second floor boys and girls toilet 2. Third floor boys and gilr toilets 3. Urinals boys room 4. Water fountains throughout 5. Unstop and repair sink main office 6. Plumbing in annex | January 30, 2004 | March 12, 2004 | 42 days |
| Bell High School | FM-200444793 04 3/12/04 Bell Second floor boy bathroom Water is coming from wall from the toilet. | March 3, 2004 | March 12, 2004 | 9 days |
| Leckie Elementary School | FM-200218199 02 3/14/04 Leckie Teachers' Restroom Repair leaking water cooler outside the teachers' restroom--it is leaking from the handle. | September 24, 2002 | March 14, 2004 | 537 days |
| Shepherd ES | FM-200228164 03 3/15/04 Shepherd New wing second floor Replace PVC exit pipe for sink in boys bathroom. Replaster wall around new pipes. Tighten bracket on second sink. Asbestos Code A-clear for repair by DCPS Safety Office Charles Buchanan on 5/08/03 | April 2, 2003 | March 15, 2004 | 348 days |
| Leckie Elementary School | FM-200218196 02 3/15/04 Leckie 2nd Floor Girls' Restroom Tighten all sink faucets. | September 24, 2002 | March 15, 2004 | 538 days |
| Shepherd ES | FM-200329865 03 3/15/04 (Shepherd) Second floor new wing Replace PVC, exit pipe for sink in boys bathroom. Replaster wall around new pipes. Reset sink. Tighten bracket on 2nd sink. Replace ceiling tiles ruined Asbestos Code A - Clear for repairs on 05/09/03. Horne Engineering - Bipin Nanavaty (RG 05/12/03) | May 9, 2003 | March 15, 2004 | 311 days |
| Cardozo High School | FM-200106899 01 3/15/04 CARDOZO GROUND - BOYS BATHROOM SURVEY AND CORRECT URINALS AND DRAINS STOPPAGES. BATHROOM HAS BEEN RENOVATED AND MADE HANDICAPPED ACCESSIBLE, DUE TO SOME URINALS STOPPAGES BATHROOM CANNOT BE USED BY MALE STUDENT. Asbsetos Code A - Clear for repairs 02/25/02 DCPS Safety - Ronald Edwards (RE | March 29, 2001 | March 15, 2004 | 1,082 days |
| Ferebee-Hope Elementary School | FM-200445294 04 3/15/04 Ferebee-Hope First floor C-hall by custodian closet lkadies and men bathrooms Replace knob lock on both bathroom. | March 12, 2004 | March 15, 2004 | 3 days |
| Leckie Elementary School | FM-200335824 03 3/15/04 Leckie Second and third floor Girls bathroom partitions need rehang. Asbestos Code A - Clear for repairs on 08/20/03. Horne Engineering - Tony Marcolin (RG 08/22/03) | August 20, 2003 | March 15, 2004 | 208 days |
| Leckie Elementary School | FM-200218202 02 3/15/04 Leckie 1st Floor Boys' Restroom & 1st Floor Girls' Restroom Boys' Restroom: 1. Replace flush valve on the 4th urinal and clear backup; 2. Replace aerator on 1st sink; 3. Replace vacuum breaker on 2nd commode and 1 1/2 extension tail pc to flush valve; and Replace diaphragm vacuum breaker on 3rd commode. Girls' Restroom: 1. Replace vacuum breaker on 1st commode and reanchor the commode; 2. Replace the 110 spud on the 4th commode. Asbestos Code A - Clear for repairs on 10/16/02. DCPS-Safety - Leroy Minton Jr. (RG 10/17/02) | September 24, 2002 | March 15, 2004 | 538 days |
| Leckie Elementary School | FM-200218194 02 3/15/04 Leckie 2nd Floor Boys' Restroom 1. Tighten all sink faucets; and 2. Urinal at the first right -- replace diaphragm and vacuum breaker. | September 24, 2002 | March 15, 2004 | 538 days |
| Ronald H. Brown MS | FM-200228633 03 3/15/04 (Brown, Ron (Roper) 1st Floor/Boys restroom: Floor drains backing up. Plumbers snaked out drains the night before, however, the problem is still there. | April 10, 2003 | March 15, 2004 | 340 days |
| Cardozo High School | FM-200114689 01 3/15/04 CARDOZO FIRST, SECOND, AND THIRD FLOOR BOYS RESTROOM AND SLOP CLOSETS 1) NO HOT AND COLD WATER SUPPLY TO SINKS AND SLOP SINKS FROM FIRST FLOOR TO THIRD FLOOR ON EAST SIDE OF BUILDING NO PENETRATIONS!! | July 3, 2001 | March 15, 2004 | 986 days |
| Leckie Elementary School | FM-200218200 02 3/15/04 Leckie Teachers' Restroom 1. Remove and clean the aerator in the last sink; and 2. Reanchor the commode in the 7th stall. | September 24, 2002 | March 15, 2004 | 538 days |
| Leckie Elementary School | FM-200337747 03 3/15/04 Leckie Second floor boys restroom Replace panic bar - hardware keep getting stuck. Door need security door. Asbestos Code A - Clear for repairs on 09/24/03. Horne Engineering - Tony Marcolin (RG 09/29/03) | September 17, 2003 | March 15, 2004 | 180 days |
| Leckie Elementary School | FM-200341804 /03 3/15/04 Leckie Third floor boys restroom Toilet broken in half need to replace toilet. Safety hazard for kids to used. | December 18, 2003 | March 15, 2004 | 88 days |
| Houston Elementary School | FM-200444020 04 3/16/04 Houston On hand we have 10 self closing basin faucets that need to be put in girls, boys and main office restroom. We do not have the tools to do it. | February 12, 2004 | March 16, 2004 | 33 days |
| Hine JHS | FM-200445059 04 3/16/04 Hine Second floor B wing girls restroom Replace stop valve and flush assembly, water running. | March 9, 2004 | March 16, 2004 | 7 days |
| Beers Elementary School | FM-200331321 03 3/16/04 Beers First floor bldg. #2 boys restroom Repair / replace commode. Water is lewaking from the base. | June 5, 2003 | March 16, 2004 | 285 days |
| Barnard Elementary School | FM-200445442 04 3/16/04 Barnard Second floor girls restroom Leak in the line, water was shut off and it is still leaking. | March 16, 2004 | March 16, 2004 | 0 days |
| Kramer Middle School | FM-200444895 04 3/16/04 Kramer !!!VERY URGENT!!! First floor girls restroom room 116 Sink fixtures need to be repaired or replaced. No hot water. Health hazard. 03/09/2004: Call came in today with a concern of having hot water too wash hands. | March 5, 2004 | March 16, 2004 | 11 days |
| Stuart-Hobson Middle School | FM-200205462 02 3/17/04 Stuart-Hobson !!! EMERGENCY !!! Second (2nd) Floor - Boys Restroom Back-ups and the valves have been cut off. | April 4, 2002 | March 17, 2004 | 713 days |
| Dunbar High School | FM-200226092 03 3/17/04 Dunbar Ground floor - Boys bathroom ADA door needs repair, students (ADA) can not get out. | February 24, 2003 | March 17, 2004 | 387 days |
| Leckie Elementary School | FM-200445259 04 3/17/04 Leckie 1) Third Floor - Boys Bathroom - Rehang sink. 2) Kitchen - Repair lavatory faucet. 3) Art Room - Second Floor - Install new faucet. 4) Second Floor - Closet needs new faucet. | March 12, 2004 | March 17, 2004 | 5 days |
| Stuart-Hobson Middle School | FM-200218492 02 3/17/04 (Stuart-Hobson) ***Urgent*** Basement Custodian's Office Restroom Replace faulty flush valve. When flushed, the water will not go down and the custodian's need to be able to use this restroom. | September 27, 2002 | March 17, 2004 | 537 days |
| Stuart-Hobson Middle School | FM-200208745 02 3/17/04 Stuart-Hobson Second (2nd) Floor - Boys' Restroom Sinks in Restroom all three supply lines are cut. Had to cut the cut off valve off due to they are leaking. Asbestos Code A - Clear For repairs on 05/05/03. Horne Engineering - Philp Connolly (RG 05/07/03) | May 31, 2002 | March 17, 2004 | 656 days |
| Tubman Elementary School | FM-200445441 04 3/18/04 Tubman Third floor boys restroom The urinal is running over need the plumber. ASAp | March 16, 2004 | March 18, 2004 | 2 days |
| Cardozo High School | FM-200340997 03 3/18/04 Cardozo Second floor Teacher lounge bathroom Repair stop valve leaking water supply pipe and leaking toilets. | December 3, 2003 | March 18, 2004 | 106 days |
| John Burroughs ES | FM-200445282 04 3/19/04 Burroughs First floor boys restroom by room 4 Urinal stopped up tryed to snake out but it did not work. | March 12, 2004 | March 19, 2004 | 7 days |
| Jefferson JHS | FM-200334446 03 3/19/04 Jefferson First floor gym coaches bathroom Replace broken hand basin and fixtures, basin leaking, fixtures are worn. | August 5, 2003 | March 19, 2004 | 227 days |
| Jessie LaSalle Elementary | FM-200445516 04 3/19/04 LASALLE third floor boys bathroom Repair rupture heating pipe to univent. | March 17, 2004 | March 19, 2004 | 2 days |
| Winston EC | FM-200221325 /02 3/22/04 Winston Second floor - 7-8 center 230 Replace missing and broken wall tiles in bathroom. Asbestos Code A-clear for repair by Horne Engineer Bipin Nanavaty DCPS Safety on 11/21/02 Charles E. Buchanan | November 19, 2002 | March 22, 2004 | 489 days |
| Randle-Highlands ES | FM-200445605 04 3/22/04 Randle Highland Basement Classroom - Girl Bathroom - 2B08 1) Unstop toilet..something is in the line. | March 19, 2004 | March 22, 2004 | 3 days |
| Winston EC | FM-200444236 04 3/22/04 (Winston) !!!URGENT!!! 2nd Floor/Boys Restroom-Room #229: Water running in toilet, unable to shut water off, broken shut-off valve. | February 19, 2004 | March 22, 2004 | 32 days |
| Cardozo High School | FM-200331352 03 3/22/04 Cardozo Boys bathroom -third floor Replace 5 (five) urinals stop and flush valves. Three (3) wax ring furnish and install new urinals. Replace 4 (four) self closing domestic hot and cold water faucets. | June 5, 2003 | March 22, 2004 | 291 days |
| Savoy Elementary School | FM-200329323 03 3/22/04 Savoy First, second and third floor boys and girls restroom The light switches on the outside door needs to be replaced with on and off switch instead of old switch. A little boy struck a paper clip into the switch outside the boys restroom on thitd floor and made the switch blown out and sparks flown out of switch. EMERGENCY | May 1, 2003 | March 22, 2004 | 326 days |
| Coolidge High School | FM-200337169 03 3/22/04 Coolidge Third Floor - Faculty Restroom 1. Unstop two sinks in restroom. | September 10, 2003 | March 22, 2004 | 194 days |
| Cardozo High School | FM-200339329 /03 3/22/04 (Cardozo) Asbestos Assessment Required. 1st Floor/Boys Bathroom: Replace door closure. Asbestos Code A - Clear for repairs on 10/27/03. Horne Engineering - Edward Rodriguez (RG 10/28/03) | October 23, 2003 | March 22, 2004 | 151 days |
| Hine JHS | FM-200445583 04 3/23/04 Hine First floor men restroom in lobby Replace sink fixtures and repair flush valve to toilet. | March 19, 2004 | March 23, 2004 | 4 days |
| Beers Elementary School | FM-200213555 02 3/23/04 Beers Bldg. 1--1st Floor Teachers' Restroom & Girls' Restroom; Bldg. 3 Custodian Closet 1. Hardware in the teachers' restroom in Bldg. 1 is rusted out and water constantly drips; and the girls' restroom has two (2) stopped up toilets; and 2. The custodian closet on the 2nd floor of bldg. 3 is clogged up and the water will not go down. | August 5, 2002 | March 23, 2004 | 596 days |
| Beers Elementary School | FM-200213554 02 3/23/04 Beers 1. Asbestos Assessment Reqd. 1st Floor Building 3 Girls' Restroom 2. The ceiling in the girls restroom is coming down and needs repair ASAP. Asbestos code A-clear for repair by Horne Engineer ( Ray Agnant ) on 8/08/02 DCPS Charles Buchanan | August 5, 2002 | March 23, 2004 | 596 days |
| Beers Elementary School | FM-200333190 03 3/24/04 Beers Second floor bldg. #1 Water is coming through roof hallway by boys and girls bathroom. contractors are doing pipe work also asbestos team. That area needs repair before contractors put up ceiling tile. | July 11, 2003 | March 24, 2004 | 257 days |
| Beers Elementary School | FM-200334010 03 3/24/04 Beers Second floor bldg. #3 Girls bathroom glass is out in window. Cafeteria / Auditorium hallway door by library glass is out. First floor showcase glass is out. Please survey and repair. Fire Code | July 30, 2003 | March 24, 2004 | 238 days |
| Beers Elementary School | FM-200334839 03 3/24/04 Beers !!!VERY URGENT!!! Asbestos Assessment Required. 1st Floor/Building #3: Ceiling fell in boys bathroom. Asbestos Code A - Clear for repairs on 09/11/03. Horne Engineering - Bipin Nanavaty (RG 09/12/03) | August 11, 2003 | March 24, 2004 | 226 days |
| Bancroft Elementary School | FM-200444334 04 3/24/04 Bancroft Basement music room bathroom Unstop all urinals, stopped up with something very large. | February 23, 2004 | March 24, 2004 | 30 days |
| Beers Elementary School | FM-200337269 03 3/24/04 Beers Cafeteria Boys and girls restrooms lights are out. Electrical problem- these bathrooms need to be use everyday. Tryed to fix them. | September 11, 2003 | March 24, 2004 | 195 days |
| Beers Elementary School | FM-200332038 03 3/24/04 (Beers) Building #3/1st & 2nd Floor: Broken windows in the girls, and boys restroom. | June 18, 2003 | March 24, 2004 | 280 days |
| Beers Elementary School | FM-200331594 03 3/24/04 Beers First floor bldg. # 1 and 2 Nurse office restroom toilets is cracked. Water flooding and also bldg. 2 restroom toilet (boys) new toilet need to be installed. | June 11, 2003 | March 24, 2004 | 287 days |
| Beers Elementary School | FM-200330139 03 3/24/04 (Beers) Building #3/2nd Floor: Cut-off valve is not working in the boys restroom; water is out of control. | May 14, 2003 | March 24, 2004 | 315 days |
| Beers Elementary School | FM-200330137 03 3/24/04 (Beers) Building #2/2nd Floor: Repair shut-off valve in the boys restroom that is not working, water is not flowing. (Restroom has very bad odor) | May 14, 2003 | March 24, 2004 | 315 days |
| Beers Elementary School | FM-200329080 03 3/24/04 (Beers) Building #3/Girls and boys bathroom: Ceiling damaged due to previous leak; ceiling is attempting to fall, please repair, and paint ceiling Lead & Asbestos Code A - Clear for repairs on 04/28/03. Horne Engineering - Edward Rodriguez (RG 04/29/03) | April 25, 2003 | March 24, 2004 | 334 days |
| Bancroft Elementary School | FM-200444464 04 3/24/04 (Bancroft Music room bathroom unstop all urinals, stopped Stopped up with something very large. | February 26, 2004 | March 24, 2004 | 27 days |
| Whittier Elementary School | FM-200445751 04 3/24/04 Whittier Main Office/Bathroom in Office Replace leaking union on steam trap in prinicpal's office restroom | March 24, 2004 | March 24, 2004 | 0 days |
| Beers Elementary School | FM-200444046 04 3/24/04 Beers Second floor bldg. 2 Plumbing - boys restroom first urinal flush cut off valve rusted out. R/R Bldg. 1st and 2 nd floor boys restroom unable to plunge urinal. The same bathroom survey toilet broken. R/R | February 12, 2004 | March 24, 2004 | 41 days |
| Beers Elementary School | FM-200442945 04 3/24/04 Beers First floor building 1 and 3 Exterior doors both handing off hinges first floor hall by library. Building 3 boys restroom first floor will not shut properly try to fix and classroom # 111 door will not close properly have to lift up to lock please survey. Code A-clear for repair by DCPS Charles Buchanan on 01/20/04 | January 20, 2004 | March 24, 2004 | 64 days |
| Cardozo High School | FM-200226846 03 3/25/04 (Cardozo) 2nd & 3rd Floor/Boys restroom: Plumbers needed to snake out this line; 2nd & 3rd floor should be snaked out to help restrooms on lower level. | March 11, 2003 | March 25, 2004 | 380 days |
| Hart Middle School | FM-200204633 02 3/25/04 (Hart) 1st Floor Girls Restroom & Boys Restroom Repair leaking commode in girls restroom #120; two toilets in girls restroom #222; 111 girls gym, & #136 girls restroom which has a leaking spud washer. Repair flush valve in boys gym restroom (1st flr.#112) and flush valve & broken toilet 1st flr #110. | March 19, 2002 | March 25, 2004 | 737 days |
| Hart Middle School | FM-200224710 03 3/25/04 (Hart) Basement/Boys restroom: Light fixture attempting to fall; please re-attach. | January 28, 2003 | March 25, 2004 | 422 days |
| Bowen Elementary School | FM-200445107 04 3/25/04 (Bowen) !!!VERY URGENT!!!+ Asbestos Assessment Required. 1st Floor/Girls Restroom: Door broken by student vandals. 3rd Floor/Room #300: Repair or replace door; hinges have come away from door. Code A - clear for repairs as of 3/10/04 by Ed Rodriguez. Per Mr. Clarence Coleman, locks are damaged and needs to be replaced , Room 301 and also Girls restroom. | March 9, 2004 | March 25, 2004 | 16 days |
| Hart Middle School | FM-200444188 04 3/25/04 (Hart) 1st Floor/Girls Restroom: Unable to open locked door, key spins around. | February 18, 2004 | March 25, 2004 | 36 days |
| Brightwood Elementary School | FM-200220127 /02 3/25/04 (Brightwood) Through-out: Leaking toilets in the boys and girls restroom. Asbestos Code A - Clear for repairs on 10/30/02. DCPS Safety - Leroy Minton Jr. (RG 10/31/02) | October 28, 2002 | March 25, 2004 | 514 days |
| Reed LC | FM-200445490 04 3/25/04 Reed Learning Center # 2, Teachers Restroom Replace flush valve and stop control valve. The flush valve and the stop control valves are bad. | March 17, 2004 | March 25, 2004 | 8 days |
| Cardozo High School | FM-200331351 03 3/25/04 Cardozo Boys bathroom - first floor Unstop clogged urinals | June 5, 2003 | March 25, 2004 | 294 days |
| Brightwood Elementary School | FM-200341800 /03 3/25/04 Brightwood Repair or replace water faucets in girls bathroom. Main building faucets run continously. | December 18, 2003 | March 25, 2004 | 98 days |
| Macfarland Middle School | FM-200445838 04 3/26/04 MacFarland Boys restroom Unstop four (4) urinals. | March 25, 2004 | March 26, 2004 | 1 day |
| Sousa Middle School | FM-200445885 04 3/26/04 Sousa Boys or Girls Bathroom 1) Water is coming from one of the following areas...Floors are flooding. | March 26, 2004 | March 26, 2004 | 0 days |
| Tubman Elementary School | FM-200445341 04 3/26/04 Tubman First floor boys restroom Repair concrete wall. | March 12, 2004 | March 26, 2004 | 14 days |
| Stanton Elementary School | FM-200445101 04 3/26/04 Stanton ( Maintenance T School Blitz ) Remodel Bathrooms - Annex and Second Floor 1) Teachers Bathroom in the annex and Teachers Lounge on the Second Floor, fixtures are so old and outdated. Asbestos Code A - Clear for repairs on 03/11/04. Horne Engineering - Bipin Nanavaty (RG 03/16/04) | March 9, 2004 | March 26, 2004 | 17 days |
| Patricia R Harris Ed Center | FM-200444904 04 3/26/04 Harris, P.R. EMERGENCY Ground floor restroom in Pre-K area Tile has come up from the floor and the little kids are eating this stuff. Asbestos Code A - Clear for repairs on 03/05/04. Horne Engineering - Bjames Smith (RG 03/08/04) | March 5, 2004 | March 26, 2004 | 21 days |
| Miner Elementary | FM-200445723 04 3/26/04 (Miner 2003) 1st Floor/Room #148: Repair broken lock on door to boys restroom. | March 23, 2004 | March 26, 2004 | 3 days |
| Horace Mann Elementary School | FM-200445681 04 3/26/04 Mann First Floor - Boys Bathroom Community Center - Girls Bathroom 1) Two (2) toilets are stopped up. | March 23, 2004 | March 26, 2004 | 3 days |
| Birney Elementary School | FM-200336826 03 3/29/04 Birney Basement teacher bathroom New side need light repair. Lights do not work. Put tubes in still do not work. Need ASAP Code A-clear for repair by Horne Engineer Tony Marcolin on 9/5/03 (CEB) | September 4, 2003 | March 29, 2004 | 207 days |
| Macfarland Middle School | FM-200445840 04 3/29/04 MacFarland URGENT Boys restroom Replace toilet commode in last stall. The base is broken around mount screws. This is a safety hazard. | March 25, 2004 | March 29, 2004 | 4 days |
| Kramer Middle School | FM-200445907 04 3/29/04 Kramer Basement girls restroom Cut off valve needs to be repaired or replaced. | March 26, 2004 | March 29, 2004 | 3 days |
| Seaton Elementary School | FM-200445799 04 3/29/04 Seaton Second floor boys restroom secure Secure urinal to wall may need to replace wax ring. Urinal is leaking when on. URGENT | March 24, 2004 | March 29, 2004 | 5 days |
| Jessie LaSalle Elementary | FM-200445818 04 3/29/04 LaSalle Principal's Bathroom 1) Toilet keeps running . Principal turned it off. Replace flush valve. | March 25, 2004 | March 29, 2004 | 4 days |
| Montgomery ES | FM-200126620 02 3/29/04 (MONTGOMERY) !!EMERGENCY!! 1ST FLOOR/PRE-KINDERGARTEN ROOMS #107/122 & MENS STAFF BATHROOM: WATER HOT IN COMMODE, STUDENTS COMPLAIN OF WATER BURNING THEM WHEN THEY SIT TO USE. | January 3, 2002 | March 29, 2004 | 816 days |
| Birney Elementary School | FM-200216172 02 3/29/04 Birney ****Urgent**** 2nd Floor Restrooms/New Wing Have no lights--need new circuit breaker put in place. | August 30, 2002 | March 29, 2004 | 577 days |
| Kramer Middle School | FM-200445914 04 3/29/04 Kramer Third floor restrooms Boys restroom 6th stall stopped up, commode snake neede. Firls restroom 6th stall control valve need to be fix or replaced. Water running. | March 26, 2004 | March 29, 2004 | 3 days |
| Montgomery ES | FM-200118852 01 3/29/04 SCOTT MONTGOMERY FIRST FLOOR ASST. PRINCIPAL BATHROOM 1) REPAIR DAMAGED WALL SURFACE, (PLASTER AND PAINT) TEST PAINT SURFACE FOR LEAD CONTENT. LEAD CODE A - CLEAR FOR REPAIR ON 08/15/01. RONALD EWARD - SAFETY (202)576-6693 | August 30, 2001 | March 29, 2004 | 942 days |
| Hendley Elementary School | FM-200446037 04 3/30/04 (Hendley) !!!VANDALISM!!! 2nd Floor/Girls Restroom: Door damaged by vandals; unable to use key. | March 29, 2004 | March 30, 2004 | 1 day |
| Marshall Educational Center | FM-200216631 02 3/30/04 Marshall Ground Floor Girls' Restroom Replace vandalized, broken hand bowl in girls' restroom. | September 5, 2002 | March 30, 2004 | 572 days |
| Wilkinson ES | FM-200445386 04 3/30/04 Wilkinson First floor 11 men bathroom Need to replace delaney with a sloan, it will not flush. | March 15, 2004 | March 30, 2004 | 15 days |
| Wilkinson ES | FM-200445374 04 3/30/04 Wilkinson Second floor 180 boys bathroom Need to unclog urinal, stopped up. | March 15, 2004 | March 30, 2004 | 15 days |
| Stevens Elementary School | FM-200216251 02 3/31/04 Stevens 1. Asbestos Assessment Reqd. Basement Girls' Restroom [B7] 2. Replace 3 missing partition doors. Asbestos Code A - Clear for repairs on 09/05/02. DCPS Safety - Leroy Minton Jr. (RG 09/06/02) | August 30, 2002 | March 31, 2004 | 579 days |
| Bell High School | FM-200445791 04 3/31/04 Bell A plumber is very urgently needed for second floor teacher restrooms need new toilet. Third and fourth floors boys restroom urinals need to be repaired or replaced. | March 24, 2004 | March 31, 2004 | 7 days |
| Leckie Elementary School | FM-200336206 03 4/1/04 (Leckie) Basement room 14 Need to repair or fabricate trap door in boys bathroom were valves are exposed. Asbestos Code A - Clear for repairs on 03/02/04. Horne Engineering - Tony Marcolin (RG 03/03/04) | August 25, 2003 | April 1, 2004 | 220 days |
| Reed LC | FM-200444927 04 4/1/04 Reed Girls Restroom/Recreation Room Repair or replace leaking valve in ceiling of Girls restroom in recreation | March 7, 2004 | April 1, 2004 | 25 days |
| Garnet-Patterson MS | FM-200446249 04 4/1/04 (Garnet-Patterson) !!!EMERGENCY!!! Leaking from Auditorium Restroom commode, down in-to cafeteria restroom. | April 1, 2004 | April 1, 2004 | 0 days |
| Patricia R Harris Ed Center | FM-200443024 04 4/1/04 Harris, P.R. Second floor teacher restroom # 7 Replace hot and cold water faucets. | January 21, 2004 | April 1, 2004 | 71 days |
| Kimball Elementary School | FM-200442826 04 4/1/04 (Kimball) !!!VERY URGENT!!! 1st Floor/Boys Restroom North Wing 2nd Floor/Boys Restroom North Wing: Urinals stopped up, both bathrooms flooded, need to be snaked out. | January 15, 2004 | April 1, 2004 | 77 days |
| Beers Elementary School | FM-200337536 03 4/5/04 Beers First floor bldg. # 3 Pre-K science lab and boys restroom doors lock R'/R.Classroom doors are not closing properly and are hard to open please survey and fix. | September 15, 2003 | April 5, 2004 | 203 days |
| Harris, C.W. ES | FM-200341742 /03 4/5/04 (Harris, C.W.) HEALTH CODE VIOLATION: Kitchen Restroom: Leaking in toilet room from roof. Asbestos Code A - Clear for repairs on 12/18/03. Horne Engineering - Edward Rodriguez (RG 12/22/03) | December 17, 2003 | April 5, 2004 | 110 days |
| Murch Elementary School | FM-200446358 04 4/6/04 Murch First and Second floor girls restroom Flush valves need to be replace. ASAP | April 5, 2004 | April 6, 2004 | 1 day |
| Payne Elementary School | FM-200330864 03 4/7/04 (Payne) New Wing-1st Floor/Girls bathroom: Leak in the area of the wax ring; toilet is very loose, and it appears that a flange is needed. Asbestos Code A - Clear for repairs on 07/23/03. Horne Engineering - Troy Wilcome (RG 07/24/03) | May 29, 2003 | April 7, 2004 | 314 days |
| Payne Elementary School | FM-200330627 03 4/7/04 Payne First Floor (new wing ) 1. Install toilet flange on fixture in kitchen restroom . 2. Install toilet flange on fixture . | May 22, 2003 | April 7, 2004 | 321 days |
| Gibbs Elementary School | FM-200445606 04 4/8/04 Gibbs Third floor girls restroom Commode need repairing, water keep coming on the floor and running on to floor because improperly installed. | March 19, 2004 | April 8, 2004 | 20 days |
| Gibbs Elementary School | FM-200445718 04 4/8/04 (Gibbs) Kitchen/Restroom: Need knobs for hot, and cold water faucets. | March 23, 2004 | April 8, 2004 | 16 days |
| Dunbar High School | FM-200336662 03 4/8/04 (Dunbar) !!!VERY URGENT!!! A-Building/Boys restroom: Urinals constantly running, and over-flowing; floors are flooded with water running down in the arts center on the ground floor. | September 2, 2003 | April 8, 2004 | 219 days |
| Dunbar High School | FM-200338533 03 4/8/04 (Dunbar) !!!EMERGENCY!!! Outside Stadium: Restore electrical power through-out the stadium, also there is no hot water. 10/09/03: Staff called in today with a concern of the need for repair of the lights, as there is a football game on tomorrow, Friday, October 10th, lights are not working in the restrooms, the ice machine is not working, and this affects all activity on the field. | October 6, 2003 | April 8, 2004 | 185 days |
| Ferebee-Hope Elementary School | FM-200338136 03 4/12/04 Ferebee-Hope Second floor D buildingmens bathroom Replace two faucets on sinks, repair PO plug under sink (water leaking on floor). | September 29, 2003 | April 12, 2004 | 196 days |
| Sousa Middle School | FM-200446554 04 4/12/04 Sousa Second floor boys restroom The 4th urinal clogged up, water will not drain, unstop clog. | April 9, 2004 | April 12, 2004 | 3 days |
| Walker-Jones EC | FM-200445449 04 4/12/04 Walker-Jones URGENT Repair or replace flush valve or cut off valve in restrooms in open space boys, girls, men and women restrooms across from teachers lounge, boys restroom need clears out, restrooms in room 107 need cut off valve. Comference room replace flush valve, Men and women restroom in open space have major back-up problems, Thid (3rd) floor boys restroom need spud. | March 16, 2004 | April 12, 2004 | 27 days |
| Draper Elementary School | FM-200222776 /02 4/13/04 (Draper) !!!VERY URGENT!!! 1. Asbestos assessment required. 1st Floor/Boys restroom: Boys urinal has fallen off wall; pipe came loose, and flush valves are broken. (Experienced flooding in this bathroom) Asbestos Code A - Clear for repairs on 12/19/02. Horne Engineering - Philp Connolly (RG 12/23/02) | December 18, 2002 | April 13, 2004 | 482 days |
| Dunbar High School | FM-200340232 /03 4/14/04 (Dunbar) Ground Floor/Training Room/Restroom: Repair broken shower. (No water) | November 13, 2003 | April 14, 2004 | 153 days |
| Spingarn High School | FM-200339057 /03 4/14/04 Spingarn Second floor room 211 B bathroom Requesting a plummer to replace cut off valve to stop water from running in the tub. TV | October 16, 2003 | April 14, 2004 | 181 days |
| King M L ES | FM-200446687 04 4/15/04 (King) Asbestos Assessment Required. 1st Floor/Boys Bathroom: Re-anchor trap door back in-to the floor. Asbestos Code A - Clear for repairs on 04/14/04. Horne Engineering - Roger Kager (RG 04/14/04) | April 13, 2004 | April 15, 2004 | 2 days |
| Hart Middle School | FM-200446700 04 4/15/04 (Hart) Room 229 new wing and girls restroom basement Need locks on the above rooms. | April 14, 2004 | April 15, 2004 | 1 day |
| Spingarn High School | FM-200339990 03 4/15/04 (Spingarn) 1st Floor/Boys Bathroom: Replace cracked sink, student vandals broke sink. Asbestos Code A - Clear for repairs on 11/06/03. Horne Engineering - Sheryll James (RG 11/12/03) | November 5, 2003 | April 15, 2004 | 162 days |
| Draper Elementary School | FM-200332899 03 4/16/04 Draper !! Urgent !! Second Floor 1.Unstop two urinals in 2nd floor boys room . 2. Unstop one commode in 2nd floor girls room. 3. Room #112, kindergarten restroom unstop one toilet in the unisex restroom and replace one cracked toilet . 4. 3rd floor boys room urinals leaking from the bottom . | July 3, 2003 | April 16, 2004 | 288 days |
| Spingarn High School | FM-200329053 03 4/20/04 (Spingarn) 3rd Floor/Girls restroom: Snake out stopped up sinks, unable to open with plunger. | April 24, 2003 | April 20, 2004 | 362 days |
| Birney Elementary School | FM-200445805 04 4/20/04 (Birney) !!!VANDALISM!!! !!!ASAP!!! New Side, 2nd Floor/Boys Bathroom: Total of two (2) urinals stopped up, need to be unclogged. (Possible vandalism) | March 24, 2004 | April 20, 2004 | 27 days |
| Draper Elementary School | FM-200228425 03 4/20/04 Draper Second, third floor and basement boys room Second floor 1. Unstop two urinals. 2. Repair one urinal that do not flush. Third floor 1. Repair leak that runs down wall in back of two urinals. 2. Unstop middle sink. 3. Unstop line, stoppage between sinks 2 & 3. Basement 1. Unstop two urinals. | April 8, 2003 | April 20, 2004 | 378 days |
| Brightwood Elementary School | FM-200333990 03 4/21/04 Brightwood Replace a crack toilet bowl in the boys bathroom. Need to install trap for the sink and nobs.(7) New automatic | July 30, 2003 | April 21, 2004 | 266 days |
| Benjamin Banneker Academic HS | FM-200446794 04 4/21/04 Banneker First floor girls restroom One (1) toilet not working, plummer is needed can not get toilet working. | April 16, 2004 | April 21, 2004 | 5 days |
| Eastern High School | FM-200341574 03 4/21/04 (Eastern) Kitchen drain blocked. Also bathroom drain, toilet flush backs up into tub. Associated with Special Education Renovation Program. Contact Quinten Washington, Project Manager, Planning Design and COnstruction at (202) 576-5593 or quinten.washington@k12.dc.us | December 9, 2003 | April 21, 2004 | 134 days |
| Stuart-Hobson Middle School | FM-200443187 04 4/21/04 (Stuart-Hobson) !!!URGENT!!! 3rd Floor/Boys Bathroom: Repair cut-off valves are broken under the sink. Students are unable to wash their hands; please respond as soon as possible. | January 23, 2004 | April 21, 2004 | 89 days |
| Brightwood Elementary School | FM-200333196 03 4/21/04 (Brightwood) 1st Floor/Boys Restroom: Repair or replace broken wash bowl in the boys restroom. | July 11, 2003 | April 21, 2004 | 285 days |
| Wilkinson ES | FM-200446884 04 4/22/04 Wilkinson First floor 105 and 106 health suite, 108 Elevator and 110 and 111 headstart bathroom Basement 8 mechanical room Second floor 132 Mr. Lee Need to re-key door locks. Need locksmith. | April 20, 2004 | April 22, 2004 | 2 days |
| Smothers ES | FM-200446988 04 4/22/04 Smothers First floor girls bathroom Sink knocked off the wall please put back up. | April 22, 2004 | April 22, 2004 | 0 days |
| Woodson High School | FM-200446987 04 4/22/04 Woodson, H.D. Third floor boys restroom Unstop commode. !!!EMERGENCY!!! April 22, 2004: approximately 12:00 p.m. call of concern from staff reporting commode is running over with waste into some office, and hallways. | April 22, 2004 | April 22, 2004 | 0 days |
| Stanton Elementary School | FM-200447037 04 4/23/04 Stanton First Floor 1) Repair and unstop urinals in Boys Bathroom, and install toilet. | April 23, 2004 | April 23, 2004 | 0 days |
| Coolidge High School | FM-200332515 03 4/23/04 Coolidge !! EMERGENCY !! Ground Floor 1. Repair the urinal and toilet in boys restroom that keeps backing up . | June 25, 2003 | April 23, 2004 | 303 days |
| Stanton Elementary School | FM-200446933 04 4/23/04 Stanton Annex Boys bathroom sink need to be unstopped. | April 21, 2004 | April 23, 2004 | 2 days |
| Burrville Elementary School | FM-200446996 04 4/23/04 (Burrville) !!!VERY URGENT!!! 2nd Floor/Kitchen & Bathroom Near Kitchen: Drains are backing up in the bathroom, also near kitchen. | April 22, 2004 | April 23, 2004 | 1 day |
| Bancroft Elementary School | FM-200446702 04 4/26/04 Bancroft Bathroom near Music room main bldg. Replace faucets on sink. Water constantly running. | April 14, 2004 | April 26, 2004 | 12 days |
| Hardy Middle School | FM-200446931 04 4/26/04 Hardy Boys bathroom first floor Lower pipe on sink is leaking, have bucket to catch water. | April 21, 2004 | April 26, 2004 | 5 days |
| Harris, C.W. ES | FM-200447014 04 4/26/04 Harris, C.W. Second floor boys bathroom Two urinals are stopped up, they are on the same line. | April 22, 2004 | April 26, 2004 | 4 days |
| Ballou Senior High School | FM-200447155 04 4/26/04 Ballou First Floor - Girls Bathroom 1) Unstop (2) toilets. | April 26, 2004 | April 26, 2004 | 0 days |
| King M L ES | FM-200340845 03 4/27/04 King, M.L. First floor boys bathroom Need to have sink #1 reanchor back to wall it is hanging off the wall. Asbestos Code A - Clear for repairs on 12/01/03. Horne Engineering - Ed Rodriguez (RG 12/03/03) | December 1, 2003 | April 27, 2004 | 148 days |
| Birney Elementary School | FM-200446930 04 4/27/04 Birney Basement Pre-K Room B-23 flush valve need to be replace (bathroom). ASAP | April 21, 2004 | April 27, 2004 | 6 days |
| Bancroft Elementary School | FM-200447015 04 4/27/04 Bancroft 1. First floor girls by room 213 repair toilet. 2. First floor by room 110 girls room repair toilet. 3. Second floor by room 225 repair boys toilet. 4. Second floor girls by room 224 Repair sinks and toilets. | April 22, 2004 | April 27, 2004 | 5 days |
| Kramer Middle School | FM-200447135 04 4/28/04 Kramer First and third floor girls restroom Cut-off valve need to be repaired or replace on commode. Six stalls. | April 26, 2004 | April 28, 2004 | 2 days |
| Cardozo High School | FM-200338578 03 4/29/04 Cardozo Second floor teacher lounge bathroom Repair leaking toilet drain that is leaking water from ceiling into classroom below. | October 7, 2003 | April 29, 2004 | 205 days |
| John Burroughs ES | FM-200447323 04 4/29/04 Burroughs Lower level boys restroom Boys urinals 2 of them stopped up tryed to snake did not work. | April 29, 2004 | April 29, 2004 | 0 days |
| Ballou Senior High School | FM-200447316 04 4/30/04 Ballou First floor In staff restroom repair flush valve and toilet . | April 29, 2004 | April 30, 2004 | 1 day |
| Merritt Middle School | FM-200339128 /03 4/30/04 Merritt First Floor Principal 1) Need a turn off valve in principals bathroom and sink needs to be repaired.. | October 20, 2003 | April 30, 2004 | 193 days |
| Merritt Middle School | FM-200337841 03 4/30/04 Merritt !! Emergency !! Second Floor 1. Unstop drain , water flooded the pre-k area , boys restroom,gym and teacher's office . | September 23, 2003 | April 30, 2004 | 220 days |
| Patricia R Harris Ed Center | FM-200221156 /02 5/3/04 Harris, P.R. Ground floor - Girl restroom at # 8 stairwell Door will not close. | November 18, 2002 | May 3, 2004 | 532 days |
| Macfarland Middle School | FM-200445870 04 5/4/04 (Macfarland) !!!VANDALISM!!! !!!URGENT!!! Asbestos Assessment Required. 2nd Floor/West Wing: Students knocked sink off wall in the girls restroom. Asbestos Code A - Clear for repairs on 03/26/04. Horne Engineering - Tony Marcolin (RG 03/30/04) | March 25, 2004 | May 4, 2004 | 40 days |
| Eastern High School | FM-200446875 04 5/4/04 Eastern Stadium girls bathroom Repair roof on stadium girls bathrooms. Roof leak, destroying bathroom ceiling. | April 20, 2004 | May 4, 2004 | 14 days |
| Brightwood Elementary School | FM-200445597 04 5/4/04 Brightwood Village Area 1) Unstop (2) toilets in Village area and Install new toilets in the Boys Bathroom on the First Floor, along with repairing faucets. | March 19, 2004 | May 4, 2004 | 46 days |
| Hart Middle School | FM-200204630 02 5/4/04 (Hart) Unstop hand sinks in the following locations: Basement: B03 Infant Center (10 loose hand sink B24/female restroom (1) sink 1st floor: classrooms 132 (1); 133 (1); 129 clinic (1); 120 girls restroom 2nd floor: girls toilet 222 (2); 207 H.E. Cooking (1) 3rd floor: 304 science (1) | March 19, 2002 | May 4, 2004 | 777 days |
| Hart Middle School | FM-200204629 02 5/5/04 (Hart) Repair/replace shower heads in the following locations: Basement: B01/custodians office (1) not working B07/Engineers office (1) missing B13k/Teachers restroom (1) missing B14/Female shower (4) missing 1st Floor: 112D/gym office boys (1) missing | March 19, 2002 | May 5, 2004 | 778 days |
| Takoma Educational Center | FM-200227424 03 5/6/04 Takoma First floor room 31 Rehang handicap bars in lobby ladies restroom. The bars are falling off and it needed, espically for our special need students. Asbestos Code A - Clear for repairs on 03/24/03. Horne Engineering - Troy Wilcome (RG 03/25/03) | March 21, 2003 | May 6, 2004 | 412 days |
| Duke Ellington School | FM-200447626 04 5/6/04 (Ellington) !!!EMERGENCY!!! 2nd Floor/Teachers Lounge Mens and women Restroom Tank top toilet stopped up, running over with sewage waste, into Assist. Principal's Office. | May 6, 2004 | May 6, 2004 | 0 days |
| Smothers ES | FM-200444078 04 5/7/04 (Smothers) VERY URGENT 2nd Floor/Main Office Restroom: Leaking from flush valve, unable to shut water off due to stripped valves. 2nd contact person: (202) 945-0559. | February 13, 2004 | May 7, 2004 | 84 days |
| Eliot Junior High School | FM-200446724 04 5/7/04 Eliot Boys Restroom Repair or replace steam leak in boys restroom. | April 14, 2004 | May 7, 2004 | 23 days |
| Ballou Senior High School | FM-200447667 04 5/10/04 Ballou First Floor- Staff Restroom 1) Repair flush valves. | May 10, 2004 | May 10, 2004 | 0 days |
| John Burroughs ES | FM-200447627 04 5/10/04 (Burroughs) HEALTH CODE VIOLATION: (Kitchen) Install hand sink in restroom. Asbestos Code A - Clear for repairs on 05/07/04. Horne Engineering - Bipin Nanavaty (RG 05/10/04) | May 6, 2004 | May 10, 2004 | 4 days |
| Miner Elementary | FM-200447258 04 5/11/04 Miner First floor room 114 Restroom drain is stopped up and drain in the shower is stopped up to. | April 28, 2004 | May 11, 2004 | 13 days |
| Amidon Elementary School | FM-200447061 04 5/12/04 Amidon First floor Pre -K and kindergarten The bathroom in the Pre-K room is flooding on the floor will not stop running put work order in March 24, 2004. The toilet in the kindergarten room will not flush. | April 23, 2004 | May 12, 2004 | 19 days |
| Slowe Elementary School | FM-200445308 04 5/12/04 (Slowe) Second floor boys restroom Low pressure in urinals. Health code | March 12, 2004 | May 12, 2004 | 61 days |
| Hart Middle School | FM-200446521 04 5/13/04 (Hart) Repair vandalized locks in the following locations: Rooms #316, 224, and old building, basement: girls bathroom needs a lock. 05/12/2004: Engineer called in reporting there is still trouble in room 326; Teacher, and her students were locked in this room today.(#316) | April 8, 2004 | May 13, 2004 | 35 days |
| Ludlow-Taylor ES | FM-200447516 04 5/13/04 Ludlow-Taylor Third floor women bathroom Repair leak from stool in bathroom, water is leaking down in 209 causing health and safety problem. | May 5, 2004 | May 13, 2004 | 8 days |
| Meyer Elementary School | FM-200446821 04 5/14/04 Meyer EMERGENCY Basement boys bathroom Most of the urinals are leaking. Need immediate attention. Water stays on the floor. | April 19, 2004 | May 14, 2004 | 25 days |
| Hine JHS | FM-200332886 03 5/16/04 Hine First Floor 1. Repair brick/ tile wall in the boys and girls restrooms . Asbestos Code A - Clear for repairs on 07/03/03. Horne Engineering - Roger Kager ( RG 07/08/03) | July 3, 2003 | May 16, 2004 | 318 days |
| John Burroughs ES | FM-200447322 04 5/17/04 Burroughs Lower level girls restroom Toilet cracked need replacing, sloam detach from toilet. | April 29, 2004 | May 17, 2004 | 18 days |
| Ferebee-Hope Elementary School | FM-200447986 04 5/18/04 Ferebee-Hope First Floor/Child and Family services mens restroom Replace tail pipe on flush valve for a urinal. | May 14, 2004 | May 18, 2004 | 4 days |
| Reed LC | FM-200224997 03 5/19/04 (Reed) Near Gym area/Girls and boys restroom: Needs a total of 20 flush valves to be changed, they are not woking. | January 31, 2003 | May 19, 2004 | 474 days |
| Bunker Hill Elementary School | FM-200226675 03 5/21/04 First floor bathroom east wing The foot paddle that turn the water off and on is broken. There is nowhere the kids can wash there hands. | March 6, 2003 | May 21, 2004 | 442 days |
| Macfarland Middle School | FM-200447072 04 5/21/04 MacFarland Seconf floor boys restroom Unclog main waste line to urinals. | April 23, 2004 | May 21, 2004 | 28 days |
| Marshall Educational Center | FM-200448318 04 5/23/04 Fix bathroom toilet in men's and ladies' room. Check chemical levels. | May 21, 2004 | May 23, 2004 | 2 days |
| Drew Elementary School | FM-200338437 03 5/24/04 (Drew) 1st Floor/Boys Bathroom: Constant drip on sinks supply line. | October 2, 2003 | May 24, 2004 | 235 days |
| Peabody Elementary School | FM-200447971 04 5/24/04 (Peabody) !!!URGENT!!! Basement/Boys Bathroom: Leaking commodes from base of toilet; replace wax ring. | May 14, 2004 | May 24, 2004 | 10 days |
| Duke Ellington School | FM-200224413 03 5/24/04 Ellington Emergency!!! All Girls Restrooms 1) Girls bathrooms are all off line. None are working. | January 23, 2003 | May 24, 2004 | 487 days |
| Thomas Elementary School | FM-200216165 02 5/24/04 (Thomas) 2nd FLoor Teachers' Restroom Repair or replace leaking flush valve. | August 30, 2002 | May 24, 2004 | 633 days |
| Duke Ellington School | FM-200225002 03 5/25/04 Ellington, Duke Basement - girls restroom R St. The toilet's (water stop) is broken need new one. | January 31, 2003 | May 25, 2004 | 480 days |
| Miner Elementary | FM-200448469 04 5/26/04 Miner Second floor boys restroom 210 and 230 Toilet and urinals not working. First floor boys restroom 148 Toilet and urinals are stopped up and sink is not working. | May 25, 2004 | May 26, 2004 | 1 day |
| Kimball Elementary School | FM-200448068 04 5/26/04 (Kimball) !!!EMERGENCY!!! 1st Floor/Northwing: Unstop urinal in the boys bathroom; floors are flooded. | May 18, 2004 | May 26, 2004 | 8 days |
| Miner Elementary | FM-200448468 04 5/26/04 Miner Second floor girls restroom 232 Toilet is not working. | May 25, 2004 | May 26, 2004 | 1 day |
| Jefferson JHS | FM-200448537 04 5/27/04 (Jefferson) 1st Floor/Boys Restroom: Secure window guards on window. | May 27, 2004 | May 27, 2004 | 0 days |
| Hine JHS | FM-200442616 04 5/27/04 Hine First floor outside boys restroom Floor flooded due to leaking drain line to hand sink. Breakage behind wall. Asbestos Code A - Clear for repairs on 01/13/04. Horne Engineering - Troy Wilcome (RG 01/14/04) | January 13, 2004 | May 27, 2004 | 135 days |
| Hine JHS | FM-200444558 04 5/27/04 (Hine) 1st Floor Lobby: Replace sink fixtures in mens restroom. | February 27, 2004 | May 27, 2004 | 90 days |
| Birney Elementary School | FM-200446932 04 5/27/04 Birney First floor teachers bathroom The lounge 1st toilet need to be repair can not cut off cut off valve . ASAP First floor custodian mop closet old side stopped up need unclogging. | April 21, 2004 | May 27, 2004 | 36 days |
| Ronald H. Brown MS | FM-200448464 04 5/28/04 Brown, Ron First floor kitchen Restroom in kitchen face bowl is stopped up, will not drain. Need sink unstopped. | May 25, 2004 | May 28, 2004 | 3 days |
| Spingarn High School | FM-200447892 04 5/28/04 Spingarn Through-out 1) Repair Bathrooms , flush valves,sinks,urinals etc. | May 13, 2004 | May 28, 2004 | 15 days |
| Hine JHS | FM-200333510 03 6/1/04 Hine Second Floor 1. Replace compression sink fixture in the girls restroom. | July 22, 2003 | June 1, 2004 | 315 days |
| Cardozo High School | FM-200340995 03 6/1/04 Cardozo First and second floor boys bathroom slop sink Unclog slop sink drains and replace traps. | December 3, 2003 | June 1, 2004 | 181 days |
| Jefferson JHS | FM-200448310 04 6/1/04 (Jefferson) lower basement girls bath room and boys bathroom sink need repair also urinals broken . Account #: 415 Asbestos Code A - Clear for repairs on 05/24/05. Horne Engineering - Bjarne Smith (RG 05/25/04) | May 20, 2004 | June 1, 2004 | 12 days |
| Hine JHS | FM-200333523 03 6/1/04 Hine Fourth Floor 1. Replace handle assembly in ladies restroom. 2. Replace handle to hot water on sink in men room . | July 22, 2003 | June 1, 2004 | 315 days |
| Hine JHS | FM-200333522 03 6/1/04 Hine Fourth Floor 1. Replace sink fixture in girls restroom. 2. Replace diaphragm on the 3rd urinal in boys room . | July 22, 2003 | June 1, 2004 | 315 days |
| Hine JHS | FM-200333514 03 6/2/04 Hine Third Floor 1. Replace spud on the last toilet . 2. Replace faucet on compression type sink girls restroom. | July 22, 2003 | June 2, 2004 | 316 days |
| Janney Elementary School | FM-200443647 04 6/2/04 (Janney) Outside Classroom/Demountables: There is a total of three (3) demountables, the plumbing problem is in the single demountable, as the other two (2) are standing together. Ruptured pipe in the classrooms bathroom. | February 3, 2004 | June 2, 2004 | 120 days |
| Harris, C.W. ES | FM-200443755 04 6/2/04 Harris, C.W. First floor girls bathroom Three toilets spuds are gone bad need replacement. | February 6, 2004 | June 2, 2004 | 117 days |
| Hine JHS | FM-200333513 03 6/2/04 Hine Third Floor - B Wing Girls Locker Room 1. Replace flange on the 2nd toilet and replace flush assembly on the 3rd toilet in girls restroom. | July 22, 2003 | June 2, 2004 | 316 days |
| Jessie LaSalle Elementary | FM-200446148 04 6/2/04 Lasalle First Floor - Boys and Girls Bathroom 1) Replace wax ring under toilet in the Boys and Girls Bathroom. Water runs from under commodes when you flush. | March 31, 2004 | June 2, 2004 | 63 days |
| Meyer Elementary School | FM-200448773 04 6/3/04 Meyer First floor teachers lounge The toilet will not flush. Need attention ASAP. Nurses suite bathroom toilet seat need replacing. | June 2, 2004 | June 3, 2004 | 1 day |
| Webb Elementary School | FM-200448836 04 6/3/04 (Webb) !!!VERY URGENT!!! 1st Floor/Boys Bathroom: Ruptured pipe on urinal, water running flooding the floors, unable to shut the water off. | June 3, 2004 | June 3, 2004 | 0 days |
| Duke Ellington School | FM-200225555 03 6/3/04 (Ellington) Second floor female restroom All toilets are broken need repairing. Plastering falling from the walls and ceiling and stall door is broken. It need repairing. | February 11, 2003 | June 3, 2004 | 478 days |
| Turner Elementary School | FM-200227714 03 6/7/04 (Turner) Old building/2nd Floor/Girls & boys restrooms: First toilet stopped up. Old building/2nd Floor, boys restroom | March 26, 2003 | June 7, 2004 | 439 days |
| Turner Elementary School | FM-200219931 /02 6/7/04 (Turner) Old building 3rd floor/Boys restroom: Sink next to wall mirror is leaking from supply line leading in-to wall; turned off to keep from flooding floors. | October 23, 2002 | June 7, 2004 | 593 days |
| Turner Elementary School | FM-200227711 03 6/7/04 (Turner) Old building/1st Floor: Faucet on sink broken in the boys restroom; needs to be replaced. | March 26, 2003 | June 7, 2004 | 439 days |
| Thomas Elementary School | FM-200336177 03 6/7/04 Thomas First, second and third floor Boys, girls, room 101, kitchen and adult restroom Unstop urinals, repair or replace flush valves, spuds, traps and faucets.Unstop sinks in the areas. | August 25, 2003 | June 7, 2004 | 287 days |
| Turner Elementary School | FM-200332474 03 6/7/04 (Turner) 1st Floor/New Building: Hot water faucets broken in boys restroom. | June 25, 2003 | June 7, 2004 | 348 days |
| Raymond Elementary School | FM-200448941 04 6/8/04 (Raymond) Old Wing/Staff Restroom: Key locked in staff room, along with a wallet, belonging to a parent. Parent is requesting her personal belongings for two (2) days. | June 4, 2004 | June 8, 2004 | 4 days |
| Turner Elementary School | FM-200443419 04 6/8/04 (Turner) Asbestos Assessment Required. New Building/2nd Floor/Boys Restroom: 1st urinal next to wall is leaking behind urinal. 2nd toilet does not flush. 02/10/2004: Duplicate request sent in, please repair as soon as possible. Asbestos Code A - Clear for repairs on 03/10/04. Horne Engineering - Sheryll James (RG 03/15/03) | January 30, 2004 | June 8, 2004 | 130 days |
| Turner Elementary School | FM-200443178 04 6/8/04 (Turner) 1st Floor Restroom/Old Side: Sink has been pulled partially off the wall, and just hanging; this is the only restroom available for the small students.There is a concern for this sink falling on a student. Asbestos Code A - Clear for repairs on 01/23/04. Horne Engineering - Troy Wilcome (RG 01/23/04) | January 23, 2004 | June 8, 2004 | 137 days |
| Shaw JHS | FM-200448881 04 6/9/04 Shaw URGENT First floor girls restroom commons Three toilets need to be repaired or replaced this is an urgent matter. | June 4, 2004 | June 9, 2004 | 5 days |
| Turner Elementary School | FM-200340456 /03 6/9/04 (Turner) 2nd Floor/Boys, and Girls Restroom: Repair toilets, and urinals in restrooms on old side. | November 18, 2003 | June 9, 2004 | 204 days |
| Turner Elementary School | FM-200332431 03 6/9/04 (Turner) Old Building/3rd Floor: Hot and cold water supply line leaks on one (1) sink; repair or replace one (1) hot water faucet on another sink; replace missing sink on the wall in the girls restroom. | June 25, 2003 | June 9, 2004 | 350 days |
| Gage-Eckington ES | FM-200448581 04 6/14/04 Gage-Eckington Teachers restroom First floor Keep flodding sink is clog and toilet is dripping. | May 28, 2004 | June 14, 2004 | 17 days |
| Hine JHS | FM-200447412 04 6/14/04 (Hine) !!!URGENT!!! Second Floor/Girls restroom Repair lock. Key is stuck in cylinder, unable to remove. | May 3, 2004 | June 14, 2004 | 42 days |
| Turner Elementary School | FM-200332427 03 6/14/04 (Turner) 1st Floor/Through-Out Building: Boys restroom old side, cold water faucets on both sinks, leaking from the supply line. Due to safety and health reasons, this request needs urgent attention. | June 25, 2003 | June 14, 2004 | 355 days |
| Turner Elementary School | FM-200332429 03 6/14/04 (Turner) 2nd Floor/Girls restroom/Old Building: Supply line leaking on two (2) sinks, need repair. Two (2) toilets in the old building needs repair. Boys restroom in the new building; hot water faucets needed on the 1st sink. | June 25, 2003 | June 14, 2004 | 355 days |
| Shaw JHS | FM-200448449 04 6/14/04 Shaw First floor 108 counsel restroom Flood in two rooms caused by toilet that is leaking and will not stop running, smelling carpet and restroom wet. NEED: toilet repaired or replaced. EMERGENCY | May 25, 2004 | June 14, 2004 | 20 days |
| Woodson High School | FM-200449307 04 6/14/04 (Woodson, H.D.) !!!EMERGENCY!!! 3rd Floor/Boys Bathroom: Commode is stopped up, leaking from the base of the toilet; unable to flush, as all other toilets in the building will run over. | June 14, 2004 | June 14, 2004 | 0 days |
| Bancroft Elementary School | FM-200448553 04 6/14/04 Bancroft Basement main bldg. boys bathroom new cafeteria Unstop urinal and replace flush valve unit. | May 27, 2004 | June 14, 2004 | 18 days |
| Turner Elementary School | FM-200219803 /02 6/14/04 (Turner) 2nd Floor/Boys restroom and Teachers lounge: Repair broken sink and wall urinal leaking and flooding the floor; also, repair stop valve on toilet thats leaking in teachers lounge. | October 22, 2002 | June 14, 2004 | 601 days |
| Bancroft Elementary School | FM-200449235 04 6/15/04 Bancroft First floor boys/girls bathroom primary Repair / Replace faucet, water leaking very badly. | June 10, 2004 | June 15, 2004 | 5 days |
| Bancroft Elementary School | FM-200449221 04 6/15/04 Bancroft Third floor girls bathroom (main bldg.) Replace broken faucet, water running continuosly and will not cut off. | June 10, 2004 | June 15, 2004 | 5 days |
| Bancroft Elementary School | FM-200449245 04 6/15/04 Bancroft First floor teachers bathroom main bldg. First floor girls bathroon main bldg. Third fllor boys bathroom main bldg Repair / replace 2 sinks that are constantly leaking water (teachers). Unstop 2 toilets or replace bad parts because of leaking water (girls), boys bathroom replace slop sink faucet, water running too slow and continuosly. | June 10, 2004 | June 15, 2004 | 5 days |
| Merritt Middle School | FM-200449059 04 6/15/04 (Merritt) !!!VERY URGENT!!! 3rd Floor/Locker Room Area: Unable to get into girls restroom, cylinder spins around when key is inserted. | June 8, 2004 | June 15, 2004 | 7 days |
| Duke Ellington School | FM-200448900 04 6/15/04 (Ellington) !!!EMERGENCY!!! Basement/Outside Boys Restroom: Leak in water supply line, 3 1/4 inch; need two (2) feet of pipe. (Pipe is leaking profusely, and water is starting to flood the floors) | June 4, 2004 | June 15, 2004 | 11 days |
| Bancroft Elementary School | FM-200449240 04 6/15/04 Bancroft First floor open space (teachers bathroom)(boys bathroom) Repair / replace toilet, need a flush unit (teachers). Two leaking sink faucets need repair / raplacing because they are constantly leaking. | June 10, 2004 | June 15, 2004 | 5 days |
| Patricia R Harris Ed Center | FM-200448224 04 6/15/04 Harris, P.R. Main floor boys restroom # 1 Repair toilet, it will not flush, something is in the line. Please respond. Top floor Toilet leaking. Please respond. Ground floor # 2, # 7 and 8 restroom #7 restroom the 22 the fourth stand up toilet are leaking from the stem and also from the bodyin # 8 there is a toilet leaking. We think that it is between toilet #1 and # 2. Repair the stand up toilet in # 2 restroom, the first one on the left: this one is leaking from the stem very bad. Top floor teachers restroom # 8 Repair parts needed for toilet; The one that is in this restroom will not flush at all. | May 20, 2004 | June 15, 2004 | 26 days |
| Bancroft Elementary School | FM-200449237 04 6/15/04 Bancroft First floor Open space (teachers bathroom near Franklins room) Repair / Replace two toilets . Repair / replace sink faucets. Repair / replace leaking faucet. | June 10, 2004 | June 15, 2004 | 5 days |
| Bancroft Elementary School | FM-200449228 04 6/15/04 Bancroft Third floor Primary girls bathroom Repair / replaced broken faucet. | June 10, 2004 | June 15, 2004 | 5 days |
| Bancroft Elementary School | FM-200449224 04 6/15/04 Bancroft First floor girls bathroom (main bldg.) Stopped up and may need to be snaked out or even replaced. (toilet)Re-attach partition railing. Sharp edge may cause someone to get hurt. | June 10, 2004 | June 15, 2004 | 5 days |
| Bancroft Elementary School | FM-200449222 04 6/15/04 Bancroft First floor boys bathroom (main bldg.) Re-attach urinal, hanging down and may come loose from the wall. Replace faucet, leaking water and will not cut off. | June 10, 2004 | June 15, 2004 | 5 days |
| Sousa Middle School | FM-200448622 04 6/15/04 Sousa Emergency Second floor girls bathroom Stem is broken, water is running on floor. | June 1, 2004 | June 15, 2004 | 14 days |
| Bancroft Elementary School | FM-200449239 04 6/16/04 Bancroft Third floor primay (girls bathroom)(boys bathroom) Repair / replace toilet, maybe stopped up (girls). Replace faucet and tighten or replace another faucet (boys). Urinal stopped up and will not flush. | June 10, 2004 | June 16, 2004 | 6 days |
| Spingarn High School | FM-200448731 04 6/16/04 (Spingarn) !!!URGENT!!! 1st Floor/Custodial Closet: Sink stopped up, backing up in girls bathroom sink. | June 2, 2004 | June 16, 2004 | 14 days |
| Bancroft Elementary School | FM-200449231 04 6/16/04 Bancroft Second floor Primary girls bathroom Repair / replaced leaking toilet. Replace faucet because there is no water coming through line. | June 10, 2004 | June 16, 2004 | 6 days |
| Hine JHS | FM-200333512 03 6/17/04 Hine Third Floor - B Wing Coach Office 1. Replace sink fixture in girls coach restroom. | July 22, 2003 | June 17, 2004 | 331 days |
| Bunker Hill Elementary School | FM-200449041 04 6/18/04 Bunker Hill Thru out the Buiding 1) Repair or replace urinals in Boys Lavatory across from 108 and Second Floor ( East Wing), Replace trap in sink and boys urinal on(Main Wing). Also Boys Bathroom urinals not working, leaking underneath(West Wing). | June 8, 2004 | June 18, 2004 | 10 days |
| Kramer Middle School | FM-200449205 04 6/18/04 Kramer First Floor - Boys Restroom - 115 1) Commode in 4th stall needs to be repaired. Water running from base. (Graduation is June 15, 2004) | June 10, 2004 | June 18, 2004 | 8 days |
| Malcolm X ES | FM-200446153 04 6/20/04 (Malcolm X) !!!URGENT!!! Asbestos Assessment Required. 3rd Floor/Girls Restroom: Water leaking from ceiling, portion of ceiling has fallen. (Possible coming from restroom above) Asbestos Code A - Clear for repairs on 03/31/04. Horne Engineering - Sheryll James (RG 04/05/04) | March 31, 2004 | June 20, 2004 | 81 days |
| Moten Elementary School | FM-200338694 03 6/21/04 (Moten) !!!VERY URGENT!!! 4th Floor/Beside Boys Bathroom: Faulty pipe busted behind the water fountain. | October 9, 2003 | June 21, 2004 | 256 days |
| Gibbs Elementary School | FM-200449345 04 6/21/04 Gibbs Basement custodian office Restroom toilet need a wax ring. | June 15, 2004 | June 21, 2004 | 6 days |
| Merritt Middle School | FM-200449526 04 6/21/04 Merritt Gym 1) Replace two sinks in the boys restroom , both of them are cracked on the side . | June 21, 2004 | June 21, 2004 | 0 days |
| Bunker Hill Elementary School | FM-200449656 04 6/22/04 (Bunker-Hill) !!!EMERGENCY!!! Middle Wing/1st Floor: Tremendous amount of water running out of the boys bathroom sink, flooding bathroom, and halls. (Unable to shut the water off) | June 22, 2004 | June 22, 2004 | 0 days |
| Moten Elementary School | FM-200225820 03 6/22/04 (Moten) Old side/3rd floor: Outside girls restroom water cooler inoperable. | February 13, 2003 | June 22, 2004 | 495 days |
| Murch Elementary School | FM-200449344 04 6/22/04 Murch Second floor girls bathroom north and boys bathroom Replace delany flush valves, replace defective faucets (single lever self closing faucets) in girls. Unstop urinals, thigten faucets and replace supply line in boys. | June 15, 2004 | June 22, 2004 | 7 days |
| Murch Elementary School | FM-200449343 04 6/22/04 Murch First floor girls and main office bathroom Second toilet will not flush. | June 15, 2004 | June 22, 2004 | 7 days |
| Ludlow-Taylor ES | FM-200445280 04 6/23/04 (Ludlow-Taylor) Third Floor/ladies bathroom Unstop both stools have to flush more than 3 times for water to go down.Replace faucet on sink in girls bathroom. | March 12, 2004 | June 23, 2004 | 103 days |
| Ludlow-Taylor ES | FM-200445279 04 6/23/04 (Ludlow-Taylor) 1st Floor/Daycare: Replace faucet on sink in girls bathroom. | March 12, 2004 | June 23, 2004 | 103 days |
| Ballou Senior High School | FM-200449018 04 6/24/04 Ballou Stay Sub-3 girls restroom Second toilet from door need to be snaked, slow moving water when flushed. | June 7, 2004 | June 24, 2004 | 17 days |
| John Burroughs ES | FM-200124888 /01 6/28/04 (BURROUGHS) ASBESTOS ASSESSMENT REQUIRED BASEMENT/LOW LEVEL RESTROOM 2ND DOOR PANEL BROK OFF COMPLETELY WHERE LITTLE BOYS WERE PLAYING ON IT. NEED REPAIR OR REPLACE- MENT. CODE A - CLEAR FOR REPAIRS ON 01/31/02 HORNE ENGINEERING - DONALD MAGLIENTI (RE) | December 10, 2001 | June 28, 2004 | 931 days |
| Stoddert ES | FM-200449805 04 6/28/04 Stoddert Second floor boys bathroom Replace faucet on sink, broke and water is leaking. URGENT | June 25, 2004 | June 28, 2004 | 3 days |
| Seaton Elementary School | FM-200217053 02 6/28/04 Seaton Third floor - Girls bathroom Replace shut off control stop valve (commode). Asbestos Code A-clear for repair by DCPS Charles E Buchanan on 9/11/02 | September 9, 2002 | June 28, 2004 | 658 days |
| Turner Elementary School | FM-200446509 04 6/28/04 Turner Second floor old and new side boys restrooms Control stop valve is stripped unable to shut off, water running on floor, urinal next to window boys restroom old side. Water is coming up out of toilet were spud is located, running on floor boys restroom new side. | April 8, 2004 | June 28, 2004 | 81 days |
| Jefferson JHS | FM-200444012 04 6/28/04 (Jefferson) URIAL IN BOYS BATHROOM NEED SNIKEN OUT.FIRST, SECOND,GYM, THIRD FLOOR. Account #: 415 K | February 12, 2004 | June 28, 2004 | 137 days |
| Stanton Elementary School | FM-200446928 04 6/29/04 Stanton Annex Boys bathroom urinals are not working, repair. | April 21, 2004 | June 29, 2004 | 69 days |
| Leckie Elementary School | FM-200445301 04 6/30/04 Leckie Third floor boys bathroom Sink need to be rehung or remounted back on wall. Asbestos Code A - Clear for repairs on 03/22/04. Horne Engineering - Sheryll James (RG 03/22/04) | March 12, 2004 | June 30, 2004 | 110 days |
| Leckie Elementary School | FM-200445299 04 6/30/04 Leckie First floor Library sink need new faucets kitchen sink restroom. | March 12, 2004 | June 30, 2004 | 110 days |
| Bunker Hill Elementary School | FM-200449630 04 6/30/04 Bunker Hill First Floor - Girls Bathroom - Middle Wing 1) Sink leaking from supply line. | June 22, 2004 | June 30, 2004 | 8 days |
| Turner Elementary School | FM-200445858 04 7/2/04 Turner First floor new side Repair urinal that is leaking from the wall in new side restroom middle urinal in boys restroom. | March 25, 2004 | July 2, 2004 | 99 days |
| Hyde Elementary School | FM-200445717 04 7/6/04 (Hyde) Asbestos Assessment Required. Basement/Boys Restroom: Commode needs flange, and wax ring; please repair. Asbestos Code A - Clear for repairs on 03/25/04. Horne Engineering - Bipin Nanavaty (RG 03/26/04) | March 23, 2004 | July 6, 2004 | 105 days |
| Hyde Elementary School | FM-200333577 03 7/6/04 Hyde Basement boys restroom B5A Girls restroom B-5 Boys toilet not working needs new diaphragm pressure valve. Girls restroom toilet do not work or flush. | July 22, 2003 | July 6, 2004 | 350 days |
| Stuart-Hobson Middle School | FM-200447550 04 7/7/04 Stuart-Hobson Third floor boys bathroom Two (2) commodes need flush valves due to they will not flush at all. These need immediate attention because students have to use the restroom. | May 5, 2004 | July 7, 2004 | 63 days |
| Bancroft Elementary School | FM-200443137 04 7/7/04 (Bancroft) Ingleside Street/Outside: Replace faucet, water protruding inside bathroom. | January 22, 2004 | July 7, 2004 | 167 days |
| Sousa Middle School | FM-200445892 04 7/7/04 Sousa Basement - Girls Bathroom 1) Need Brick Mason. | March 26, 2004 | July 7, 2004 | 103 days |
| Bancroft Elementary School | FM-200338693 03 7/7/04 Bancroft Bathroom boys third floor Need packing behind the urinal, Water coming down by the wall. Asbestos Code A - Clear for repairs on 10/14/03. Horne Engineering - Bipin Nanavaty (RG 10/22/03) | October 9, 2003 | July 7, 2004 | 272 days |
| Hine JHS | FM-200446979 04 7/7/04 Hine Outside Restroom ( Girls ) 1) Repair hole in wall. Asbestos Code A - Clear for repairs on 04/19/04. Horne Engineering - Tony Marcolin (RG 04/20/04) | April 22, 2004 | July 7, 2004 | 76 days |
| Beers Elementary School | FM-200447502 04 7/7/04 Beers Second floor bldg. 1 Boys restroom urinal water is not going down, smell is bad tryed to fix it. Please survey and repair. | May 5, 2004 | July 7, 2004 | 63 days |
| Stuart-Hobson Middle School | FM-200445487 04 7/7/04 Stuart-Hobson Second floor girls bathroom (7) Commodes do not work, they need flushs, they leak and drip down thru ceiling on first floor bathroom ceiling. We have only three commodes working. Also have blind teacher that have to use the bathroom. This considered an health hazard. We had to cut all commdoes off. | March 17, 2004 | July 7, 2004 | 112 days |
| Wilson J. O. ES | FM-200447572 04 7/12/04 Wilson, J.O. First floor girls restroom old side Repair or replace flanges to commodes, water is coming up, around base areas. | May 5, 2004 | July 12, 2004 | 68 days |
| Duke Ellington School | FM-200448526 04 7/12/04 (Ellington) Basement/Boys Bathroom: Commode coming up from floor in the handicap stall; need closet bolts to lock down commode. | May 26, 2004 | July 12, 2004 | 47 days |
| Thomas Elementary School | FM-200449475 04 7/13/04 Thomas First floor boys restroom Survey, repair or replace and install sliding bolt on exterior door to help secure it. | June 18, 2004 | July 13, 2004 | 25 days |
| Ferebee-Hope Elementary School | FM-200449949 04 7/13/04 Ferebee-Hope First floor Ms. Kittrells room girls bathroom second toilet Replace wax rings and tail pipe on flush valve leaking. | June 30, 2004 | July 13, 2004 | 13 days |
| Hine JHS | FM-200333491 03 7/13/04 Hine First Floor 1. Replace sink fixture in the principal's restroom . | July 21, 2003 | July 13, 2004 | 358 days |
| Ferebee-Hope Elementary School | FM-200449950 04 7/13/04 Ferebee-Hope First floor A-113-B kindergarten teachers bathroom Unstop toilet, replace handle and wax ring and mount toilet. (water coming out under toilet)Replace wax rings and tail pipe on flush valve leaking. | June 30, 2004 | July 13, 2004 | 13 days |
| Ferebee-Hope Elementary School | FM-200449948 04 7/13/04 Ferebee-Hope First floor Ms. Kittrells room boys bathroom Replace two (2) wax rings mount toilet to floor, replace handle on flush valve. | June 30, 2004 | July 13, 2004 | 13 days |
| Hine JHS | FM-200333486 03 7/13/04 Hine First Floor 1. Replace sink fixture in the girls restroom . | July 21, 2003 | July 13, 2004 | 358 days |
| Webb Elementary School | FM-200450123 04 7/13/04 Webb First floor girls restroom Repair 3 toilets need to be unstop qand replace flush valves. Unstop 4 sinks. Health hazard | July 12, 2004 | July 13, 2004 | 1 day |
| Hine JHS | FM-200333503 03 7/13/04 Hine First Floor - Nurses Suite 1. Replace toilet flange girls & boys restroom. 2. Replace sink fixture. | July 22, 2003 | July 13, 2004 | 357 days |
| Hine JHS | FM-200333488 03 7/15/04 Hine First Floor 1. Replace flange on toilet in the boys restroom . | July 21, 2003 | July 15, 2004 | 360 days |
| Hine JHS | FM-200333502 03 7/15/04 Hine First Floor 1. Replace sink fixtures in the girls and boys restroom. 2. Replace diaphragm on the 2nd toilet in girls restroom. | July 22, 2003 | July 15, 2004 | 359 days |
| Browne Junior High School | FM-200450084 04 7/15/04 (Browne) Second floor girls bathroom near 231 Replace all flush valves. | July 9, 2004 | July 15, 2004 | 6 days |
| Miner Elementary | FM-200447739 04 7/16/04 Miner First floor dining # 15 and boys restroom # 148 Sinks are not working. | May 10, 2004 | July 16, 2004 | 67 days |
| Miner Elementary | FM-200443172 04 7/16/04 Miner Second floor room 255 First floor room 144 and 136 Boys restroom urinals is stopped up. Boys room 144 urinals is stopped up. Girls toilet is not working. | January 23, 2004 | July 16, 2004 | 175 days |
| Kramer Middle School | FM-200449855 04 7/19/04 (Kramer) 2nd Floor/Boys Restroom: Repair or replace fixtures on sink. | June 28, 2004 | July 19, 2004 | 21 days |
| Gage-Eckington ES | FM-200450288 04 7/19/04 Gage-Eckington First floor girls restroom There are 5 toilets, 2 are stopped up. Need to be snaked out. Both running over when flushed. Tried to unstop them. | July 15, 2004 | July 19, 2004 | 4 days |
| Bancroft Elementary School | FM-200449238 04 7/19/04 Bancroft Third floor primay (girls bathroom)(boys bathroom) Repair / replace broken latch on door, jagged edges (girls)(boys). | June 10, 2004 | July 19, 2004 | 39 days |
| Shaed Elementary School | FM-200444584 04 7/20/04 Shaed First Floor - Boys Bsthroom 1) There are no lights at all in the bathroom. All ends are broken off. | March 1, 2004 | July 20, 2004 | 141 days |
| Hine JHS | FM-200333507 03 7/20/04 Hine Second Floor - B-Wing girls Restroom 1. Unstop sinks and replace fixtures . 2. Replace flange on 1st toilet. 3. Unstop the 2nd toilet. 4. Replace diaphragm on the 3rd toilet . | July 22, 2003 | July 20, 2004 | 364 days |
| West Elementary School | FM-200339684 /03 7/21/04 West Exterior check and repair concrete work way leaks into the ground floor of the ladies restroom. | October 30, 2003 | July 21, 2004 | 265 days |
| Hine JHS | FM-200333509 03 7/21/04 Hine Second Floor - Boys Restroom 1. 1st ,3rd and 4th urinal replace stop valve and flush assembly . 2. Replace vacuum breaker on the 1st toilet. | July 22, 2003 | July 21, 2004 | 365 days |
| Hine JHS | FM-200225225 03 7/21/04 (Hine) Floor 2nd: Boys Restroom Replace sink fixture and Unstop sink drain line No snake on site | January 30, 2003 | July 21, 2004 | 538 days |
| Hine JHS | FM-200447414 04 7/22/04 (Hine) !!!URGENT!!! Fourth Floor/corridor by girls restroom Repair water cooler it will not come out of bubbler. | May 3, 2004 | July 22, 2004 | 80 days |
| Hardy Middle School | FM-200444606 04 7/22/04 (Hardy) !!!VERY URGENT!!! 2nd Floor/Boys Bathroom: Repair or replace ruptured pipe under sink. (Feed pipe) | March 1, 2004 | July 22, 2004 | 143 days |
| Birney Elementary School | FM-200450399 04 7/23/04 (Birney) HEALTH CODE VIOLATION: !!!EMERGENCY!!! 24 Hours Notice/Kitchen and Cafeteria: Repair two (2) compartment sink faucet, it has continued to run a heavy flow of hot water. Pipe has a hole in the bathroom sink. | July 16, 2004 | July 23, 2004 | 7 days |
| Kramer Middle School | FM-200447648 04 7/23/04 Kramer Second floor boys restroom Fixtures on sinks need to be repair or replaced. | May 7, 2004 | July 23, 2004 | 77 days |
| Adams Elementary | FM-200450232 04 7/23/04 Adams Sink in main office first floor and lounge on second floor stopped up and third floor boys restroom four urinals stopped up. Girls restroom four flush handle not working on first floor. | July 14, 2004 | July 23, 2004 | 9 days |
| John Burroughs ES | FM-200450353 04 7/26/04 Burrough First floor girls restroom White sink need trap and drips. | July 16, 2004 | July 26, 2004 | 10 days |
| Watkins Elementary School | FM-200446779 04 7/27/04 Watkins Boys bathroom on 2nd floor First stall partition broken off need to be placed back. Code A -clear for repair as of 4/22/04 by safety Sylvia. | April 15, 2004 | July 27, 2004 | 103 days |
| Watkins Elementary School | FM-200446781 04 7/27/04 Watkins Third, fourth and first floor boys bathrooms Doors are falling off hinges need carpenter. Asbestos Code A - Clear for repairs on 04/16/04. Horne Engineering - Bjarne Smith (RG 04/19/04) | April 15, 2004 | July 27, 2004 | 103 days |
| Burrville Elementary School | FM-200449217 04 7/27/04 Burrville Second floor boys restroom Urinal need to be remounted. Sink need remounted on to wall. Asbestos Code A - Clear for repairs on 06/10/04. Horne Engineering - Philp Connolly (RG 06/14/04) | June 10, 2004 | July 27, 2004 | 47 days |
| Hine JHS | FM-200333518 03 7/27/04 Hine Third Floor - Corridor 1. Install water cooler by girls restroom. | July 22, 2003 | July 27, 2004 | 371 days |
| Turner Elementary School | FM-200447270 04 7/29/04 Turner Third floor Repair jammed lock on girls restroom new side door; Key will not go in. | April 28, 2004 | July 29, 2004 | 92 days |
| Merritt Middle School | FM-200450577 04 7/29/04 Merritt First floor office In the nurses restroom no hot water, and the toilet will not flush need to be repaired. | July 21, 2004 | July 29, 2004 | 8 days |
| Kramer Middle School | FM-200449856 04 7/29/04 (Kramer) !!!VERY URGENT!!! 3rd Floor/Restrooms: Snake needed to unstop commode in boys restroom. 3rd Floor/Girls Restroom: Repair or replace control valve, water running. | June 28, 2004 | July 29, 2004 | 31 days |
| Macfarland Middle School | FM-200450578 04 7/29/04 MacFarland First floor girls restroom Repair connection to shut off valve feed line to commode. The feeder line has a hole in it and it causing the restroom too flood. | July 21, 2004 | July 29, 2004 | 8 days |
| Burrville Elementary School | FM-200449216 04 7/29/04 Burrville Second floor girls restroom Sink need remounted on to wall. Asbestos Code A - Clear for repairs on 06/10/04. Horne Engineering - Philp Connolly (RG 06/14/04) | June 10, 2004 | July 29, 2004 | 49 days |
| Houston Elementary School | FM-200447792 04 7/30/04 Houston Second floor near girls restroom Kid were playing in hall and busted the fountain. Water was turned off and it is still leaking. | May 11, 2004 | July 30, 2004 | 80 days |
| Tubman Elementary School | FM-200446084 04 7/30/04 Tubman Second floor teachers restroom Replace toilet. ( 12") | March 30, 2004 | July 30, 2004 | 122 days |
| Wilkinson ES | FM-200450435 04 8/2/04 Wilkinson Second floor 184 girls bathroom Need to replace diaphram on commode, in house tried will not flush. | July 19, 2004 | August 2, 2004 | 14 days |
| Gibbs Elementary School | FM-200449082 04 8/2/04 Gibbs Basement office Restroom toilet needs a new spoud, water is running onto floor. | June 8, 2004 | August 2, 2004 | 55 days |
| Ludlow-Taylor ES | FM-200450531 04 8/2/04 Ludlow-Taylor First floorboys bathroom R /R flush valve on first urinal hard to flush. | July 20, 2004 | August 2, 2004 | 13 days |
| Beers Elementary School | FM-200447375 04 8/3/04 Beers URGENT Kitchen / cafeteria Two pot sinks are clouded and bathroom sink. Smell is bad tryed to fix it. | April 30, 2004 | August 3, 2004 | 95 days |
| Merritt Middle School | FM-200451017 04 8/3/04 Merritt Pre-K suit Teachers restroom hot water is not working, they are complaining. | July 28, 2004 | August 3, 2004 | 6 days |
| Miner Elementary | FM-200447329 04 8/3/04 Miner Second floor room 208 Girls restroom toilet is not working. | April 29, 2004 | August 3, 2004 | 96 days |
| Miner Elementary | FM-200447327 04 8/3/04 Miner First floor room 148 Boys restroom toilets are not working and urinals. | April 29, 2004 | August 3, 2004 | 96 days |
| Miner Elementary | FM-200447330 04 8/3/04 Miner Second floor room 255 and 210 Boys restroom urinals are stopped up and toilet. | April 29, 2004 | August 3, 2004 | 96 days |
| Miner Elementary | FM-200447332 04 8/3/04 Miner First floor room 134 Girls restroom toilet is not working and will not stop running. | April 29, 2004 | August 3, 2004 | 96 days |
| Merritt Middle School | FM-200450729 04 8/3/04 Merritt First and third floor Third floor locker area repair or replace flush valve in boys restroom the urinals not flushing. First floor mens restroom two commodes that do not flush at all or the sinks do not work either. | July 26, 2004 | August 3, 2004 | 8 days |
| West Elementary School | FM-200448376 04 8/3/04 West Second floor kitchen restroom Faucet is hanging off can not cut water off. Broken turn oof valve need to be fix before health inspector return. ASAP | May 24, 2004 | August 3, 2004 | 71 days |
| Ferebee-Hope Elementary School | FM-200450358 04 8/4/04 Ferebee-Hope First floor D-building Ms. Brown area first teachers bathroom First floor pool area life guard and bathroom area Replace faucets on sink D- building. Unstop floor drain in shower, replace shower head. | July 16, 2004 | August 4, 2004 | 19 days |
| King M L ES | FM-200447682 04 8/4/04 King, M.L. Third floor boy's bathroom Need to have # 4 toilet repair. It will not flush and it has no water pressure. | May 10, 2004 | August 4, 2004 | 86 days |
| Bell High School | FM-200443915 04 8/5/04 (Bell) Teachers restroom(s) on 1st floor near 129 JROTC needs to be checked to find out where water is coming from. | February 10, 2004 | August 5, 2004 | 177 days |
| Bell High School | FM-200341093 03 8/5/04 (Bell) Through-Out Building: Urgently in need of plumber for restrooms: 4th Floor/Boys Restroom: Need urinal repair. 2nd Floor/Boys Restroom: Continues to leak. 2nd Floor/Male teachers restroom: Continues to leak. 1st Floor/Male teachers restroom: Continues to leak. | December 4, 2003 | August 5, 2004 | 245 days |
| Benjamin Banneker Academic HS | FM-200449379 04 8/5/04 Banneker Kitchen restroom basement Toilet is backed up and need to have a plumber come out. Toilet has been plunged. | June 16, 2004 | August 5, 2004 | 50 days |
| Benjamin Banneker Academic HS | FM-200446797 04 8/5/04 Banneker Third floor girls restroom One (1) toilet has a bad shut off valve - toilet can not be worked on. | April 16, 2004 | August 5, 2004 | 111 days |
| Patricia R Harris Ed Center | FM-200446156 04 8/5/04 (Harris, P.R.) !!!VANDALISM!!! Main Floor #1: and Restroom 7 and 8 top floor Toilet out of order, and toilet seat is broken. (We have no tools at hand for this job) | March 31, 2004 | August 5, 2004 | 127 days |
| Savoy Elementary School | FM-200222471 /02 8/6/04 Savoy Third floor Girls bathroom There is a sink with a rusted through J-neck that needs to be replaced. The 4th stall needs the flush valve and neck replaced along with the diaphragm. Asbestos Code A - Clear for repairs on 12/17/02. DCPS Safety - Leroy Minton Jr. (RG 12/18/02) | December 12, 2002 | August 6, 2004 | 603 days |
| Savoy Elementary School | FM-200227512 03 8/6/04 Savoy Third floor girls/boys restroom Boys 3 standup urinal need to be sealed, leaking from the wall and cutoff valves not functioning properlyalso 1 sit down toilet. Girls restroom have 2 sinks that have J-neck pipes that need to be replaced. Pipes have holes in them. | March 24, 2003 | August 6, 2004 | 501 days |
| Savoy Elementary School | FM-200220260 /02 8/6/04 (Savoy) Toilet in ladies restroom for employees does not work Asbestos Code A - Clear for repairs on 04/18/03. DCPS Safety - Richard Gibson (RG) | October 22, 2002 | August 6, 2004 | 654 days |
| Bell High School | FM-200443840 04 8/11/04 (Bell) Asbestos Assessment required. Basement/Restroom: Water coming through wall, possible ruptured pipe. Asbestos Code A - Clear for repairs on 02/09/04. Horne Engineering - Bipin Nanavaty (RG 02/13/04) | February 9, 2004 | August 11, 2004 | 184 days |
| Turner Elementary School | FM-200451886 04 8/11/04 Turner Third floor boys restroom Repair urinal next to partian wall; wall it continues to run also unstop second toilet from wall. (new Bldg) | August 9, 2004 | August 11, 2004 | 2 days |
| Wilson J. O. ES | FM-200341289 03 8/11/04 (Wilson, J.O.) 1st Floor/Boys & Girls Restroom: Repair or replace cylinders to restrooms. (Re-key cylinders to new system) | December 9, 2003 | August 11, 2004 | 246 days |
| Ludlow-Taylor ES | FM-200450530 04 8/12/04 Ludlow-Taylor First floor woman bathroom and all purpose room R /R flush valve on first stool. DCPS is using all purpose for sumer camp. | July 20, 2004 | August 12, 2004 | 23 days |
| Whittier Elementary School | FM-200451846 04 8/12/04 Whittier Second floor principal office bathroom Need to furnish and install new faucet for sink. Old faucet been repair several times, hot water runs continuously unable to cut off water color is brown. | August 9, 2004 | August 12, 2004 | 3 days |
| Wilson J. O. ES | FM-200452686 04 8/12/04 (Wilson) Lock is needed for the bathroom in the main office also,for the Mechanical Room. Mr. Reddix is aware of the request. | August 10, 2004 | August 12, 2004 | 2 days |
| Cleveland Elementary School | FM-200451391 04 8/16/04 (Cleveland/K.C. Lewis) 1st Floor/Boys Restroom: Need the welders to come out and weld window guards that are loose. Please repair today, as vandals have easy access to the building. | August 3, 2004 | August 16, 2004 | 13 days |
| Ferebee-Hope Elementary School | FM-200446453 04 8/19/04 Ferebee-Hope First Floor D-Bldg. child family services women bathroom Unstop toilet, over flowing. Tried plugging did not work called in emergency 4/1/04. | April 7, 2004 | August 19, 2004 | 134 days |
| Tubman Elementary School | FM-200449335 04 8/19/04 (Tubman) !!!URGENT!!! 1st Floor/Grils Bathroom: Asbestos Assessment Required. Water leaking down from boys bathroom on the 1st floor, into ground floor. Asbestos Code A - Clear for repairs on 06/15/04. (To open floor but,if insulation is present STOP work and call Safety.) Horne Engineering - Tony Marcolin (RG 06/17/04) | June 15, 2004 | August 19, 2004 | 65 days |
| Tubman Elementary School | FM-200341492 /03 8/19/04 Tubman Space 36 - boys restroom Repair water leak in restroom causing water to leak into boiler room over top of boiler # 2. | December 12, 2003 | August 19, 2004 | 251 days |
| Johnson JHS | FM-200442328 04 8/20/04 Johnson Teacher lounge Principal request that electrican come out, bathroom light does not work. Asbestos Code A - Clear for repairs on 01/08/04. Horne Engineering - Sheryll James (RG 01/12/04) | January 7, 2004 | August 20, 2004 | 226 days |
| Turner Elementary School | FM-200453041 04 8/23/04 (Turner) !!!URGENT!!! 2nd & 3rd Floor: Keys are broke of in locks in the following locations: Rooms #202, 205, 307, 310, & girls restroom new side 3rd floor. | August 20, 2004 | August 23, 2004 | 3 days |
| Cleveland Elementary School | FM-200227035 03 8/23/04 (Cleveland) Asbestos Assessment Required. 2nd Floor/Boys restroom: We need an asbestos assessment on boys restroom ceiling on the 2nd floor. Lead & Asbestos Code A - Clear for repairs on 03/17/03. Horne Engineering - Sharon Voss (RG 03/18/03) | March 13, 2003 | August 23, 2004 | 529 days |
| Cleveland Elementary School | FM-200204864 02 8/23/04 Cleveland Second Floor Girls Restroom Repair bathroom sink so water flows into the sink. The lens cover for the sensor is missing and, therefore, when hands are placed in front of the sensor, there is no downward flow of water. | March 22, 2002 | August 23, 2004 | 885 days |
| Cleveland Elementary School | FM-200224552 03 8/23/04 Cleveland/ KC Lewis Second floor - boys restroom Repair stainless steel sink that has senors. There is no running water so the kids may wash there hands. | January 24, 2003 | August 23, 2004 | 577 days |
| Plummer Elementary School | FM-200452898 04 8/24/04 Plummer First floor auditorium boys restroom Replace flush valve. | August 18, 2004 | August 24, 2004 | 6 days |
| Plummer Elementary School | FM-200452899 04 8/24/04 Plummer First floor boys restroom Replace flush valve # 3 , 1toilet and 2 urinals. | August 18, 2004 | August 24, 2004 | 6 days |
| Plummer Elementary School | FM-200452894 04 8/24/04 Plummer Second floor cafe, third floor boys and girls restroom Replace flush valve in cafe. Replace 4 flush valves in boys and girls each. | August 18, 2004 | August 24, 2004 | 6 days |
| Wilson High School | FM-200452968 04 8/25/04 Wilson, W. First floor boys bathroom Unstop two urinals. | August 19, 2004 | August 25, 2004 | 6 days |
| Jefferson JHS | FM-200452865 04 8/25/04 Jefferson Basement room B 03 First floor girls bathroom Shower need unstopping in B-03. Toilet stopped up need snakin out on first floor. | August 18, 2004 | August 25, 2004 | 7 days |
| Johnson JHS | FM-200453171 04 8/25/04 Johnson Second floor teachers bathroom Fourth floor room 419 Door will not lock, teacher broke key in knob lock. Teacher door in room 419 will not open key broke in knob lock. | August 23, 2004 | August 25, 2004 | 2 days |
| Simon Elementary School | FM-200452954 04 8/25/04 Simon URGENT Basement Second floor 2 urinals need to be unclog. 1 urinal need to be unclog. Water is leaking from pipe in restroom in cafeteria. | August 19, 2004 | August 25, 2004 | 6 days |
| Harris, C.W. ES | FM-200453087 04 8/26/04 Harris, C.W. Second floor boys bathroom 3 and 4 wing Urinal need a new wax ring. | August 20, 2004 | August 26, 2004 | 6 days |
| Harris, C.W. ES | FM-200453089 04 8/26/04 Harris, C.W. Second floor boys bathroom 5 and 6 wing Urinal need a new wax ring. | August 20, 2004 | August 26, 2004 | 6 days |
| Backus Middle School | FM-200450792 04 8/27/04 (Backus) FIRE CODE VIOLATION: 3rd Floor/Gym: Exposed wires inside boys bathroom. | July 26, 2004 | August 27, 2004 | 32 days |
| Ross Elementary School | FM-200453281 04 8/31/04 (Ross) Basement/Boys Restroom: 1. Urinal not flushing. 1st Floor/Pre-K: 1. Toilet continues to run in the 2nd stall; unable to stop. | August 24, 2004 | August 31, 2004 | 7 days |
| Beers Elementary School | FM-200336703 03 9/1/04 (Beers) FIRE CODE VIOLATION: 2nd Floor/Boys and Girls bathroom: Electrical box not mounted to the wall next to water fountain. Asbestos Code A - Clear for repairs on 09/03/03. Horne Engineering - Edward Rodriguez (RG 09/04/03) | September 2, 2003 | September 1, 2004 | 365 days |
| John Burroughs ES | FM-200453721 04 9/2/04 Burrough Boys room first floor repair flush valves. | August 31, 2004 | September 2, 2004 | 2 days |
| Bowen Elementary School | FM-200453707 04 9/2/04 Bowen First floor lMens bathroom hallway and learning center 2 Need lock in mens bathroom and learning center need locks on both exit doors. Learning center 1 need lock on the storage. | August 31, 2004 | September 2, 2004 | 2 days |
| John Burroughs ES | FM-200453722 04 9/2/04 Burrough Repair flush valves on toilets in girls room first floor. | August 31, 2004 | September 2, 2004 | 2 days |
| Jefferson JHS | FM-200453024 04 9/3/04 (Jefferson) !!!URGENT!!! Lower Basement/Adult Bathroom: Water shoots out from under the sink when water is turned on. (Hot water) | August 19, 2004 | September 3, 2004 | 15 days |
| Spingarn High School | FM-200452140 04 9/7/04 Spingarn Third floor teacher restroom by 318 Requesting a plummer to replace diaphragm to second stall on the left. | August 11, 2004 | September 7, 2004 | 27 days |
| Macfarland Middle School | FM-200450594 04 9/7/04 (Macfarland) !!!URGENT!!! 1st Floor/Girls Restroom: Busted water feed line to toilet, leaking flush valve, and unable to shut the water off. (Water on floor) | July 21, 2004 | September 7, 2004 | 48 days |
| Stanton Elementary School | FM-200452998 04 9/7/04 Stanton Third floor boy and principal bathroom Boys and principal office sinks are clogged up and need plummer. | August 19, 2004 | September 7, 2004 | 19 days |
| Stoddert ES | FM-200453236 04 9/7/04 Stoddert First floor girls restroom Girls bathroom sink is hanging off of the wall. Asbestos Code A - Clear for repairs on 08/24/04. DCPS Safety - Leroy Minton Jr. ( RG 08/24/04) | August 24, 2004 | September 7, 2004 | 14 days |
| Nalle Elementary School | FM-200341819 /03 9/8/04 (Nalle) !!!URGENT!!! New Wing/Outside Boys Restroom: Light switch vandalized, student stuck a nickle in the light switch on the 2nd floor, smoke marks are present. | December 18, 2003 | September 8, 2004 | 265 days |
| Oyster Elementary School | FM-200453893 04 9/8/04 Oyster First floor girls restroom Toilet in the first stall is stopped up. It need unclogging. | September 3, 2004 | September 8, 2004 | 5 days |
| Woodson High School | FM-200453970 04 9/9/04 Woodson, H.D. Room - 511 and Bathroom over top of 511. 1) Water is leaking in classroom. | September 7, 2004 | September 9, 2004 | 2 days |
| Spingarn High School | FM-200452143 04 9/9/04 Spingarn Third floor teacher restroom by 314 Requesting a plumber to replace diaphragm on the first urinal. 2 urinal No # 2 need a spud. 3urinal no. # 5 need a diaphragm. | August 11, 2004 | September 9, 2004 | 29 days |
| Spingarn High School | FM-200452138 04 9/9/04 Spingarn Third floor boys restroom by 317 Requesting a plummer to replace stop control valve and diaphragm on the first urinal. Second urinal need a spud. Third urinal need stop control valve / diaphragm. | August 11, 2004 | September 9, 2004 | 29 days |
| John Burroughs ES | FM-200452017 04 9/9/04 (Burroughs) FIRE CODE VIOLATION: 1st Floor/Mens Restroom: Broken door closer. Asbestos Code A - Clear for repairs on 08/27/04. DCPS Safety - Leroy Minton Jr. (RG 08/28/04) | August 10, 2004 | September 9, 2004 | 30 days |
| Spingarn High School | FM-200452033 04 9/9/04 Spingarn Third floor girls restroom by 313 Requesting an plummer to replace diaphram on last stall on the left. | August 10, 2004 | September 9, 2004 | 30 days |
| Savoy Elementary School | FM-200329297 03 9/9/04 (Savoy) Through-Out the Building: Need light switch replacement on all switches near boys, and girls restrooms on all floors. Students are sticking objects in-to the current lights switches. | April 30, 2003 | September 9, 2004 | 498 days |
| Bancroft Elementary School | FM-200453840 04 9/9/04 Bancroft Second floor primary wing girls bathroom 1 commode, 1 sink has no running water, no parts.Repair ceiling approx> 1-2ft. | September 2, 2004 | September 9, 2004 | 7 days |
| Bancroft Elementary School | FM-200453842 04 9/9/04 Bancroft First and second floor open space (boys, girls and teachers bathroom) Replace leaking faucets, flush valve assemblies and stop valves. | September 2, 2004 | September 9, 2004 | 7 days |
| Hine JHS | FM-200453752 04 9/10/04 Hine Fourth floor mans restroom Leaking toilet fixtures - cut off valve not holding. | September 1, 2004 | September 10, 2004 | 9 days |
| Leckie Elementary School | FM-200454730 04 9/14/04 (Leckie) !!!VERY URGENT!!! 2nd Floor/Teachers Bathroom: Toilets leaking below in the main office. | September 14, 2004 | September 14, 2004 | 0 days |
| Spingarn High School | FM-200454727 04 9/14/04 (Spingarn) !!!VERY URGENT!!! 1st Floor/Boys Bathroom: Total of eight (8) urinals; all are stopped up, and running over. | September 14, 2004 | September 14, 2004 | 0 days |
| Stoddert ES | FM-200453238 04 9/15/04 Stoddert URGENT Second floor boys bathroom Replace faucet on sink, broke and water is leaking. | August 24, 2004 | September 15, 2004 | 22 days |
| Randle-Highlands ES | FM-200454077 04 9/15/04 Randle-Highland First and second floor restroom Repair urinals in booys bathroom 2003 and 2109 (water running constantly). | September 8, 2004 | September 15, 2004 | 7 days |
| Bancroft Elementary School | FM-200454812 04 9/16/04 (Bancroft EMERGENCY First floor boys bathroom The partition fell on a student (Jose Guzman). Need to be repair/ replace. Asbestos Code A - Clear for repairs on 09/15/04. DCPS Safety - Richard Gibson (RG) | September 15, 2004 | September 16, 2004 | 1 day |
| Birney Elementary School | FM-200453813 04 9/16/04 Birney First floor basement bathrooms Girls bathroom 1 toilet need unclogging, New side. | September 1, 2004 | September 16, 2004 | 15 days |
| Birney Elementary School | FM-200453812 04 9/16/04 Birney First floor boys bathrooms Boys bathroom need to have 2 toilets need unclogging. Boys bathroom old side have urinal need to be unclogged. ASAP | September 1, 2004 | September 16, 2004 | 15 days |
| Browne Junior High School | FM-200453746 04 9/17/04 Browne Second floor boys bathroom across from room 207 Some of the urinals are stopped up. Some flush valves need to be replaced. | September 1, 2004 | September 17, 2004 | 16 days |
| Stoddert ES | FM-200448371 04 9/20/04 Stoddert First floor girls restroom Sink is hanging off of the wall, need someone to replace the hedges. Asbestos Code A - Clear for repairs on 05/25/04. Horne Engineering - Bjarne Smith (RG 05/26/04) | May 24, 2004 | September 20, 2004 | 119 days |
| Watkins Elementary School | FM-200455090 04 9/21/04 Watkins Third floor Art room sink is stopped up. Boys bathroom need to replace bracket. Basin mixing valve need to be replace. | September 20, 2004 | September 21, 2004 | 1 day |
| Peabody Elementary School | FM-200454630 04 9/22/04 (Peabody) 2nd Floor/Restroom: Toilet leaking, need wax ring. | September 14, 2004 | September 22, 2004 | 8 days |
| Thomson Elementary School | FM-200454608 04 9/23/04 (Thomson/Logan) 1st Floor/Girls Restroom: Rehang sink. Repair water cooler by room #101 Repair water cooler by room #202 2nd Floor Boys Restroom: Urinal covered with bag Toilet covered with bag Sink trap leaking | September 14, 2004 | September 23, 2004 | 9 days |
| Merritt Middle School | FM-200453750 04 9/23/04 Merritt Third floor locker offiice Repair or replace flush valve in ladies restroom, it will not flush. | September 1, 2004 | September 23, 2004 | 22 days |
| Tubman Elementary School | FM-200336956 03 9/23/04 Tubman Second Floor - Boys Restroom # 128 1. Commode need a wax ring . 2. Urinal need a spud. Asbestos Code A - Clear for repairs on 09/08/03. Horne Engineering - Bipin Nanavaty (RG 09/09/03) | September 8, 2003 | September 23, 2004 | 381 days |
| Hearst Elementary School | FM-200453896 04 9/23/04 Hearst Second floor girls restroom Repair commode. | September 3, 2004 | September 23, 2004 | 20 days |
| Hearst Elementary School | FM-200453897 04 9/23/04 Hearst First floor boys restroom Urinal not working. | September 3, 2004 | September 23, 2004 | 20 days |
| Beers Elementary School | FM-200455460 04 9/24/04 Beers URGENT First and second floor hallways Look near girls restroom, water fountain is leaking from wall try to fix it can not shut off. Bad floor near teacher lounge, water fountain is not running also leaking. Asbestos Code A - Clear for repairs on 09/23/04. DCPS Safety - Leroy Minton Jr. (RG 09/23/04) | September 22, 2004 | September 24, 2004 | 2 days |
| Bancroft Elementary School | FM-200455590 04 9/28/04 Bancroft Basement bathroom (main bldg.) blue floor Bathroom with blue floor, change 2 flush valve assemblies on 2 toilets. | September 24, 2004 | September 28, 2004 | 4 days |
| Stanton Elementary School | FM-200455648 04 9/28/04 Stanton Bottom floor Lunchroom bathroom light fixture has come from wall Asbestos Code A - Clear for repairs on 09/27/04. DCPS Safety Leroy Minton Jr. (RG 09/28/04) | September 24, 2004 | September 28, 2004 | 4 days |
| Kelly Miller MS | FM-200455996 04 9/28/04 (Miller) !!!URGENT!!! 1st Floor/Boys Restroom: Stopped up toilet affecting the other bathrooms; when flushed, all others run over. | September 28, 2004 | September 28, 2004 | 0 days |
| Hine JHS | FM-200455704 04 9/30/04 Hine First floor mens restroom Repair handle assembly to toilet. | September 24, 2004 | September 30, 2004 | 6 days |
| Cardozo High School | FM-200331350 03 9/30/04 Cardozo Girls bathroom - ground floor Replace self closing faucets total 12. | June 5, 2003 | September 30, 2004 | 483 days |
| King M L ES | FM-200455629 04 9/30/04 King First floor girls bathroom Need to have # 2 toilet repair it will not flush. | September 24, 2004 | September 30, 2004 | 6 days |
| Sousa Middle School | FM-200456100 04 9/30/04 Sousa 1) Check out odor in Fan Room. Re-hang toilet in Girls Room in Basement Area. Install (2) free standing water cooler in Boys Gym and Lobby. | September 30, 2004 | September 30, 2004 | 0 days |
| Payne Elementary School | FM-200454874 04 10/1/04 Payne First floor boys restroom old bldg. Repair or replace door closer. Asbestos Code A - Clear for repairs on 09/16/04. DCPS Safety - Richard Gibson (RG) | September 16, 2004 | October 1, 2004 | 15 days |
| Langdon Elementary School | FM-200339123 /03 10/1/04 Langdon 2 ND Floor Boys Restroom Asbestos assessment required 2nd floor Boys restroom floor. Replace 1/2" busted steam pipe going through floor of 2nd floor Boys restroom. Urgency!!!!! Asbestos Code A - clear for repairs on 10/21/03. Horne Engineering - Troy Wilcome (RG 10/22/03) | October 20, 2003 | October 1, 2004 | 347 days |
| Miner Elementary | FM-200455722 04 10/3/04 Miner First floor restroom 175 Sink is leaking water under. | September 24, 2004 | October 3, 2004 | 9 days |
| John Burroughs ES | FM-200449605 04 10/4/04 Burrough First floor storage room and New wing girls restroom Sink is stopped up tried to snake. Girls restroom toilet broken plummer came and said he will be back, name Butler and have not return. | June 22, 2004 | October 4, 2004 | 104 days |
| Beers Elementary School | FM-200453798 04 10/5/04 Beers Cafeteria kitchen Slop sink pipe is rusted out, water is backing up with water and bathroom sink strong odor in the kitchen. Slop sink booster heater R/R. | September 1, 2004 | October 5, 2004 | 34 days |
| Ronald H. Brown MS | FM-200456308 04 10/5/04 Brown, Ron Third floor Near stairway # 9 middle stall leak w/flushing. Boys restroom near stairwell # 8 the last stall stop up need a snake. | October 1, 2004 | October 5, 2004 | 4 days |
| Ronald H. Brown MS | FM-200456309 04 10/5/04 Brown, Ron Second floor Girl restroom Need a plumber to fix two commodes in the girls restroom near stairwell # 11, both are coming up the wax ring and flooding the restroom the second stall and the last one. | October 1, 2004 | October 5, 2004 | 4 days |
| John Burroughs ES | FM-200455840 04 10/6/04 Burroughs First floor Teacher restroom both tiolets leaks water from base and screws and sink keep running washer gone bad. | September 27, 2004 | October 6, 2004 | 9 days |
| John Burroughs ES | FM-200456033 04 10/6/04 Burroughs First floor new wing Girls restroom toilet broken, Plumber came and said he will be back (butler) and have not come back. | September 29, 2004 | October 6, 2004 | 7 days |
| John Burroughs ES | FM-200456041 04 10/6/04 Burroughs First floor girls restroom Toilet want flush valves across from room # 13. | September 29, 2004 | October 6, 2004 | 7 days |
| John Burroughs ES | FM-200456044 04 10/6/04 Burroughs Lower level boys restroom Boys urinal metal plate coming off. | September 29, 2004 | October 6, 2004 | 7 days |
| Stoddert ES | FM-200456063 04 10/8/04 Stoddert First floor girls Restroom Replace sink in restroom. Third time sink have fallen down. Replace. Asbestos Code A - Clear for repairs on 10/06/03. DCPS Safety - Leroy Minton (RG 10/05/04) October 04, 2004: Call of concern came in today. | September 29, 2004 | October 8, 2004 | 9 days |
| Francis Junior High School | FM-200456306 04 10/12/04 Francis Restroom Second floor Change cut off valve by supply line. Water is leaking from elbow joint three quarter in. October 07, 2004: The water from supply line is now flooding the floors; using wet vac to contain the water. (VERY URGENT) | October 1, 2004 | October 12, 2004 | 11 days |
| Ross Elementary School | FM-200454341 04 10/13/04 (Ross) !!!URGENT!!! Basement/Boys Bathroom: Toilet in the 2nd stall will not flush. Basement/Cafeteria: Sink leaking at the bottom, water on floor. | September 10, 2004 | October 13, 2004 | 33 days |
| Hine JHS | FM-200456456 04 10/13/04 Hine First floor outside ladies restroom Replace toilet flange - water leaking from base of toilet. | October 5, 2004 | October 13, 2004 | 8 days |
| West Elementary School | FM-200454568 04 10/13/04 West FIRE CODE VIOLATION: First floor Storage room near the boys restroom door hardware broken. Asbestos Code A - Clear for repairs on 09/15/04. DCPS Safety - Leroy Minton Jr. (RG 09/15/04) | September 14, 2004 | October 13, 2004 | 29 days |
| Aiton Elementary School | FM-200456702 /04 10/14/04 Aiton Fourth floor boys restroom The sink need to be replace. The sink is broken. | October 12, 2004 | October 14, 2004 | 2 days |
| Webb Elementary School | FM-200450119 04 10/15/04 Webb Second floor boy restroom Repair 2 toilets need wax ring and flush valves. | July 12, 2004 | October 15, 2004 | 95 days |
| Hardy Middle School | FM-200456728 /04 10/15/04 (Hardy) 1st Floor/Boys Restroom: All urinals are stopped up, running over on floors. (No more restrooms on this floor). | October 12, 2004 | October 15, 2004 | 3 days |
| Webb Elementary School | FM-200442717 04 10/15/04 (Webb) 1st Floor/Boys Bathroom: Urinal needs wax ring, water running from the wall. | January 14, 2004 | October 15, 2004 | 275 days |
| Webb Elementary School | FM-200444298 04 10/15/04 Webb First and second floor boys and girls Need flush valves on toilets. September 01, 2004: Staff called in report the flush valves has ruptured in the girls restroom on the 1st floor, and water is flooding the floors. | February 20, 2004 | October 15, 2004 | 238 days |
| Jessie LaSalle Elementary | FM-200456587 04 10/18/04 (Lasalle) 2nd Floor/Restroom: Replace three (3) 110 flush valves on toilets in the girls restroom. Asbestos Code A - Clear for repairs on 10/07/03. DCPS Safety - Richard Gibson (RG) | October 7, 2004 | October 18, 2004 | 11 days |
| Thomas Elementary School | FM-200448627 04 10/18/04 Thomas Third floor Girls/boys restroom 200 and 204 Replace screen back in the windows from the outside to keep students from falling out and repair screen., | June 1, 2004 | October 18, 2004 | 139 days |
| Bruce-Monroe Elementary School | FM-200456767 /04 10/18/04 Bruce-Monroe Lockd on parent center/restroomon playground area need repair / replace, lock was vandalize over the holiday weekend. Breakin was motive please look into ASAP. Part of retaining wall on playground was used to dislocate lock. | October 13, 2004 | October 18, 2004 | 5 days |
| Bancroft Elementary School | FM-200456864 /04 10/18/04 Bancroft Repair leaking toilet, 2nd floor restroom. | October 15, 2004 | October 18, 2004 | 3 days |
| Webb Elementary School | FM-200450120 04 10/18/04 Webb First floor boy restroom Repair 3 urinals need wax ring. | July 12, 2004 | October 18, 2004 | 98 days |
| Stanton Elementary School | FM-200456843 /04 10/19/04 Stanton Second Floor - Girls Bathroom 1) Unstop toilet.. | October 15, 2004 | October 19, 2004 | 4 days |
| Bruce-Monroe Elementary School | FM-200336916 03 10/19/04 Bruce-Monroe Second floor rooms 201 and 204 center No water comes through line of sinks in ctr. # 201 / 202 hot water in staff restroom will not shut off unit was shut off by DCPS plummers No cold water in ctr. # 201 staff restroom, ctr. 203 sink area No water comes through line in boys restroom ctr. # 204 Toilet in staff restroom ctr. # 204. Closet snake will not unstop Mrs Phife. | September 5, 2003 | October 19, 2004 | 410 days |
| Wilson High School | FM-200456509 04 10/19/04 Wilson, W. First floor Auditorium lobby area Unstop toilet in girls bathroom in the auditorium area. | October 5, 2004 | October 19, 2004 | 14 days |
| Bancroft Elementary School | FM-200456911 /04 10/19/04 Bancroft Open space teachers bathroom Replace flush valve assembly, water leaking through floor onto light fixtures. | October 18, 2004 | October 19, 2004 | 1 day |
| West Elementary School | FM-200445729 04 10/19/04 (West) 1st Floor/Learning Center, and Main Office:s Need three (3) key entry lock for vault, boiler room, and main office restroom. | March 23, 2004 | October 19, 2004 | 210 days |
| Burrville Elementary School | FM-200455885 04 10/19/04 Burrville Second Floor Boys Restroom 1) Stop valve is broken on urinal. | September 28, 2004 | October 19, 2004 | 21 days |
| Burrville Elementary School | FM-200455635 04 10/19/04 Burrville Second Floor Boys Restroom Urinal is broken, has a hole in it, needs to be replaced. Water is backing up in the urinal . | September 24, 2004 | October 19, 2004 | 25 days |
| Backus Middle School | FM-200457082 /04 10/19/04 Backus Third floor teacher bathroom Pipe is leaking, box lavatory 3 urinals are stopped up. | October 19, 2004 | October 19, 2004 | 0 days |
| Ludlow-Taylor ES | FM-200457166 /04 10/20/04 (Ludlow-Taylor) !!!VERY URGENT!!! 2nd Floor/Girls Bathroom: Light cover fell, broke, and lights are out. Observed water in light covers. (Lights are on) | October 20, 2004 | October 20, 2004 | 0 days |
| Kimball Elementary School | FM-200453191 04 10/20/04 Kimball Second floor Middle wing girls bathroom Repair toilet, toilet will not flush. | August 23, 2004 | October 20, 2004 | 58 days |
| Ferebee-Hope Elementary School | FM-200457158 /04 10/21/04 (Ferebee-Hope) !!!EMERGENCY!!! 2nd Floor/Boys Bathroom: Water running from 4th urinal, flooding the floor. | October 20, 2004 | October 21, 2004 | 1 day |
| Bunker Hill Elementary School | FM-200456956 /04 10/21/04 Bunker Hill URGENT Middle wing girls bathroom on first floor toilet need to be replace. Middle wing second floor bathroom urinal is not working. | October 18, 2004 | October 21, 2004 | 3 days |
| Woodson High School | FM-200457224 /04 10/22/04 (Woodson, H.D.) !!!EMERGENCY!!! 3rd Floor: Un-stop existing toilets that are over-flowing. Restrooms are shut down. | October 21, 2004 | October 22, 2004 | 1 day |
| Patricia R Harris Ed Center | FM-200456959 /04 10/26/04 Harris, P.R. URGENT Ground floor restroom # 1 and # 8 Ground floor # 3 restroom Theses restrooms need parts to be repaired. (the trap need to be replaced in # 1 and the hand assembly or parts of it needs to be replaced. Toilet out of order will not flush needs plumbing parts on # 3 restroom. | October 18, 2004 | October 26, 2004 | 8 days |
| Patricia R Harris Ed Center | FM-200456957 /04 10/26/04 Harris, P.R. URGENT Main floor # 4 girls restroom Toilet has some kind of stoppage in it. We snaked it we plugged it an still it will not flushed. | October 18, 2004 | October 26, 2004 | 8 days |
| Meyer Elementary School | FM-200457109 /04 10/26/04 Meyer Basement and first floor Bathrooms are not working, the boys bathroom have water on the floor, and the girls also have water on the floor. First floor girls bathroom have (3) three commodes, that do not work. Need attention ASAP. | October 19, 2004 | October 26, 2004 | 7 days |
| Bruce-Monroe Elementary School | FM-200225808 03 10/26/04 (Bruce-Monroe) Boys Bathroom/Custodial Closet/Learning center #202 & 204: Bradley basin leaking. | February 13, 2003 | October 26, 2004 | 621 days |
| Patricia R Harris Ed Center | FM-200456958 /04 10/26/04 Harris, P.R. URGENT Ground floor restroom # 3 and # 7 Both of these restrooms have out of order toilets, They will not flush. | October 18, 2004 | October 26, 2004 | 8 days |
| Turner Elementary School | FM-200456553 04 10/27/04 (Turner) New Side/2nd Floor: Middle urinal is leaking from inside wall in boys restroom. First toilet needs to be plunged out, and the third toilet leaks, need flush valve assembly. Asbestos Code A - Clear for repairs on 10/12/04. DCPS Safety - Leroy Minton Jr. (RG 10/12/04) | October 6, 2004 | October 27, 2004 | 21 days |
| Merritt Middle School | FM-200457343 /04 10/27/04 Merritt (Montessori) Third floor All the bathrooms in the montessori school are backing. | October 22, 2004 | October 27, 2004 | 5 days |
| Ludlow-Taylor ES | FM-200457172 /04 10/27/04 Ludlow-Taylor Third floor boys bathroom R/R 1st urinal in boys bathroom leaking from side. | October 20, 2004 | October 27, 2004 | 7 days |
| Bancroft Elementary School | FM-200457118 /04 10/27/04 Bancroft Second floor primary wing (girls bathroom) Replace 2 faucets that do not have any running water. | October 19, 2004 | October 27, 2004 | 8 days |
| Bancroft Elementary School | FM-200457111 /04 10/27/04 Bancroft First and second floor open space bathroom teachers tan floor Replace diaphram on toilet in teachers bathroom. | October 19, 2004 | October 27, 2004 | 8 days |
| Moten Elementary School | FM-200456555 04 10/28/04 Moten 4th Floor - Old Side - Boys Bathroom 1) 2nd urnial is leaking from behind wall. Asbestos Code A - Clear for repairs on 10/12/04. DCPS Safety - Leroy Minton Jr. (RG 10/12/04) | October 7, 2004 | October 28, 2004 | 21 days |
| Wilkinson ES | FM-200457378 /04 10/28/04 Wilkinson First Floor, Gym Area - Boys Bathroom 1) Urinal over flowing , tried to unstop, had to cut off. | October 25, 2004 | October 28, 2004 | 3 days |
| Garfield ES | FM-200457685 /04 10/29/04 (Garfield) !!!EMERGENCY!!! Main Building/Lower Level/Boys Bathroom: Cut off valve blew off the wall; nipples has rusted out. (3/4 gate valve) Experiencing large amounts of water on floor. Water shut off. | October 29, 2004 | October 29, 2004 | 0 days |
| Eliot Junior High School | FM-200457686 /04 11/1/04 (Eliot) 1st Floor/Boys Bathroom: Total of 5 urinals clogged, standing urine, and very bad odor. | October 29, 2004 | November 1, 2004 | 3 days |
| Brightwood Elementary School | FM-200457257 /04 11/1/04 Brightwood !!!VERY URGENT!!! Main Building/1st Floor: Total of six (6) urinals clogged in the boys bathroom. | October 21, 2004 | November 1, 2004 | 11 days |
| Woodson High School | FM-200456388 04 11/1/04 Woodson, HD Ground floor Boys bathroom light need repairing. | October 4, 2004 | November 1, 2004 | 28 days |
| Woodson High School | FM-200456386 04 11/2/04 Woodson, HD Fourth floor Girls bathroom sink need repairing. | October 4, 2004 | November 2, 2004 | 29 days |
| Harris, C.W. ES | FM-200457154 /04 11/2/04 Harris, CW First floor Pre-K boys bathroom First toilet continues to run will not cut off. | October 20, 2004 | November 2, 2004 | 13 days |
| Birney Elementary School | FM-200457223 /04 11/3/04 Birney Second floor boys bathroom Boys bathroom old and new side have urinals stopped up. Need to be unclogged. | October 21, 2004 | November 3, 2004 | 13 days |
| Duke Ellington School | FM-200221427 /02 11/4/04 Ellington, Duke Sub-basement dance studio The urinals bowel in the boys restroom need repair. | November 20, 2002 | November 4, 2004 | 715 days |
| Shaed Elementary School | FM-200224119 03 11/4/04 Shaed First floor - boys restroom Replace or repair light fixtures( ends broke fixture rusted). | January 16, 2003 | November 4, 2004 | 658 days |
| Moten Elementary School | FM-200457510 /04 11/4/04 Moten EMERGENCY First floor boys bathroom (old side) All 4 urinals in need of repair. Health hazard | October 27, 2004 | November 4, 2004 | 8 days |
| Murch Elementary School | FM-200331696 03 11/4/04 Murch Second floor room 207 and 208 boys restrooms Unstop urinals in restrooms. | June 12, 2003 | November 4, 2004 | 511 days |
| Brent Elementary School | FM-200457002 /04 11/4/04 Brent Third floor boys restroom Urinal need to be replaced. | October 18, 2004 | November 4, 2004 | 17 days |
| Payne Elementary School | FM-200457545 /04 11/4/04 (Payne) !!!VERY URGENT!!! pep 2nd Floor/Boys Bathroom: The second toilet in restroom leaking, unable to shut the water off. (Water has covered the floor) | October 27, 2004 | November 4, 2004 | 8 days |
| Gibbs Elementary School | FM-200457683 /04 11/8/04 (Gibbs) 2nd Floor/Teachers Restroom: Toilets are not working properly. | October 29, 2004 | November 8, 2004 | 10 days |
| Whittier Elementary School | FM-200457247 /04 11/8/04 (Whittier) !!!VERY URGENT!!! 1st Floor/Girls Restroom: Sink has fallen off the wall with a small amount of leaking. Please respond before conditions are worse. Asbestos Code A - Clear for repairs on 10/26/04. DCPS Safety - Leroy Minton Jr. (RG 10/27/04) | October 21, 2004 | November 8, 2004 | 18 days |
| Benjamin Banneker Academic HS | FM-200457832 04 11/8/04 Banneker S.H. S. Third Floor Girls- Restroom One toilet is leaking , parts need to be replaced by a plumber. Turn-off valve is not holding. | November 2, 2004 | November 8, 2004 | 6 days |
| West Elementary School | FM-200457869 04 11/8/04 West #EMERGENCY First floor kindergarten boys restroom Toilet is clogged. Do not have a snake tried to unstop it, need help. | November 3, 2004 | November 8, 2004 | 5 days |
| Gibbs Elementary School | FM-200457953 04 11/8/04 (Gibbs) First Floor/Teachers Restroom: Restroom is stopped up with some kind of foriegn object need plumber. | November 5, 2004 | November 8, 2004 | 3 days |
| Kramer Middle School | FM-200457982 04 11/10/04 Kramer Middle Schoolt First Floor-Boys Restroom RM 115. Commode No. Four leaks water at the base. Commode No. Seven need to be Repaired. 11/05/2004 11:18 OB - | November 5, 2004 | November 10, 2004 | 5 days |
| Watkins Elementary School | FM-200455091 04 11/10/04 Watkins Second floor Boys bathrroom urinal hardware need replacing. Teachers lounge bathroomtoilet stool not getting water and no water through sink faucet. Library sink no water to faucet. | September 20, 2004 | November 10, 2004 | 51 days |
| Kramer Middle School | FM-200457981 04 11/10/04 Kramer Middle School Thruout-Boys Restroom Sinks have been vandalize. No water. Health Hazard. | November 5, 2004 | November 10, 2004 | 5 days |
| Kramer Middle School | FM-200457977 04 11/12/04 Kramer Middle School First Floor-Boys Restroom Second urinal is clogged up, snake may be needed. | November 5, 2004 | November 12, 2004 | 7 days |
| West Elementary School | FM-200456946 /04 11/12/04 West First floor Pre-K and main office Toilets will not flush, can not remove flush ometer top to install repair kit. Need someone to come and fix it or bring tod so it can be fix, it all so boys restroom by gym. | October 18, 2004 | November 12, 2004 | 25 days |
| Kimball Elementary School | FM-200456384 04 11/12/04 Kimball New wing teacher restroom basement level The knobs are broken. | October 4, 2004 | November 12, 2004 | 39 days |
| Gibbs Elementary School | FM-200458151 /04 11/12/04 (Gibbs) First Floor/girls restroom Toilet will not flush need repairing. | November 10, 2004 | November 12, 2004 | 2 days |
| Brookland Elementary | FM-200458239 /04 11/15/04 Brookland 1st Floor Between Boys Restroom & Music Room Asbestos assessment required Repair leak on hot water line on 1st floor hall between Boys restroom and Music Room. Code A-claer for repair by DCPS Charles Buchanan on 11/15/04 | November 15, 2004 | November 15, 2004 | 0 days |
| Wilson J. O. ES | FM-200208822 02 11/15/04 Wilson,J.O. 1. Asbestos Assessment Reqd. 2nd Floor/Old Wing; 2nd Floor/New Wing & 2nd Floor Open Space 2. 2nd floor old wing: Girls' restroom has one commode out of service; Boys' restroom has two urinals & one commode out of service. 3. 2nd floor new wing: Girls restroom has one commode out of service; Boys' restroom has some missing urinals. 4. 2nd floor open space boys' restroom has one urinal & 1 commode out of service. Asbestos Code A - Clear for repairs on 06/04/02. DCPS Safety - Leroy Minton Jr. (RG) | June 3, 2002 | November 15, 2004 | 896 days |
| Miner Elementary | FM-200458132 04 11/15/04 Miner Second Floor RM 232 Toilets in girls restroom are stoped-up 11/09/2004 14:58 OB - 11/09/2004 14:59 OB - | November 9, 2004 | November 15, 2004 | 6 days |
| Wilson J. O. ES | FM-200457924 04 11/15/04 Wilson,J.O. Kitchen bathroom Pipe is leaking from the bottom of the sink, and water is coming from one of the toilets flush handle. | November 4, 2004 | November 15, 2004 | 11 days |
| Miner Elementary | FM-200458134 04 11/15/04 Miner Second Floor RM 230 Urinals are stoped-up, in Boys restroom. 11/09/2004 14:58 OB - 11/09/2004 14:59 OB - | November 9, 2004 | November 15, 2004 | 6 days |
| Miner Elementary | FM-200456918 /04 11/15/04 Miner Second floor 230 boys restroom Toilets are stopped up. | October 18, 2004 | November 15, 2004 | 28 days |
| Brookland Elementary | FM-200457801 04 11/16/04 Brookland EMERGENCY Third floor boys bathroom Water is coming from under the toilet into the hallway. | November 1, 2004 | November 16, 2004 | 15 days |
| Wilkinson ES | FM-200458347 /04 11/17/04 Wilkinson Second floor boys bathroom Boys urinal is stopped up. | November 16, 2004 | November 17, 2004 | 1 day |
| Wilson J. O. ES | FM-200458323 04 11/17/04 Asbestos Assessment Req. 2nd floor/old wing; 2nd floor/new wing & 2nd floor open space. 2nd floor old wing: Girls- restroom has one commode out of service; Boy's restroom has two urinals and one commode out of service. 2nd floor new wing: Girls restroom has one commode out of service; Boys restroom has some missing urinals. 2nd floor open space boys restroom has one urinal and 1 commode out of service. PREVIOUSLY SUBMITTED UNDER FM-200208822 11/17/2004: Repairs are to be made under the previous service order. | November 4, 2004 | November 17, 2004 | 13 days |
| Brightwood Elementary School | FM-200458108 04 11/17/04 Brightwood Boys bathroom first floor Replace sink traps. | November 9, 2004 | November 17, 2004 | 8 days |
| Wilkinson ES | FM-200458153 /04 11/17/04 Wilkinson First floor 15-Kgn boys bathroom Need to replace 3 meter faucets, the tops are off. | November 10, 2004 | November 17, 2004 | 7 days |
| Rudolph Elementary School | FM-200457527 /04 11/18/04 Rudolph First floor old wing Boys bathroom broken flush valve need replace. | October 27, 2004 | November 18, 2004 | 22 days |
| Barnard Elementary School | FM-200458514 /04 11/23/04 Barnard First floor bathroom on room 171 office area The sink is leaking. The leak is a steady drip which appears to be coming from the supply line. Respond ASAP | November 19, 2004 | November 23, 2004 | 4 days |
| Miner Elementary | FM-200458489 /04 11/24/04 Miner Second Floor-Boys restroom 230 Urinals and toilets are stoped-up. | November 18, 2004 | November 24, 2004 | 6 days |
| Kimball Elementary School | FM-200458608 /04 11/24/04 Kimball Business managers bathroom The toilet is leaking down into the health suite. | November 23, 2004 | November 24, 2004 | 1 day |
| Browne Junior High School | FM-200455694 04 11/29/04 Browne Second floor boys bathroom Bathroom across from room 207 need new door locks and handle. | September 24, 2004 | November 29, 2004 | 66 days |
| Bancroft Elementary School | FM-200454405 04 11/30/04 Bancroft First and second floor open space boys, girls teachers bathroom Replace leaking faucets, flush valve assemblies, stop valve. | September 10, 2004 | November 30, 2004 | 81 days |
| Bell High School | FM-200454367 04 11/30/04 Bell Second floor girl restrooms Two doors need replacing. Fourth floor girls restroom Need partition and doors need repairing. Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Leroy Minton Jr. (RG 09/13/04) | September 10, 2004 | November 30, 2004 | 81 days |
| Bell High School | FM-200454369 04 11/30/04 Bell First floor boys restrooms Need flush valve for urinal no water running in toilet or urinal pipes leaking inside wall. First floor girls restroom Need 2 sinks, toilet need flush vlave no water running in toilets water leaking from ceiling. Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Leroy Minton Jr. (RG 09/13/04) | September 10, 2004 | November 30, 2004 | 81 days |
| Turner Elementary School | FM-200454466 04 11/30/04 (Turner) !!!EMERGENCY!!! Asbestos Assessment Required. 1st Floor/Near Girls Restroom: Nozzle broke on water fountain, sharpe edges exposed. Repair mouth piece broken by accident. | September 13, 2004 | November 30, 2004 | 78 days |
| Savoy Elementary School | FM-200454447 04 11/30/04 Savoy EMERGENCY Second floor boys and girls restroom Damaged ceiling need to be repair ASAP. Ceiling is in danger of falling has significant water damage. Asbestos Code A - Clear for repairs on 09/15/04. DCPS Safety - Leroy Minton Jr. (RG 09/16/04) | September 13, 2004 | November 30, 2004 | 78 days |
| Savoy Elementary School | FM-200454446 04 11/30/04 Savoy Third floor girls restroom 1st toilet -flush kit new anchor bolts 2nd toilet-flush kit new anchor bolts 3rd toilet - flush kit new anchor bolts 4th toilet - flush kit new anchor bolts 5th toilet - flush kit new anchor bolts 6th toilet - anchor bolts 7th toilet - flush kit 8th toilet - anchor bolts sink 1 new elbow and trap sink 2 faucet is loose sink 3 need new hot water knob. | September 13, 2004 | November 30, 2004 | 78 days |
| Eastern High School | FM-200454381 04 11/30/04 Eastern All first floor boys and girls restroom Repair all handicap faucets in all bathrooms due tp handicap students. We have (2) handicap students in school these items are not working properly. | September 10, 2004 | November 30, 2004 | 81 days |
| Savoy Elementary School | FM-200454444 04 11/30/04 Savoy Third floor teachers restroom Need flush kit and to be anchored. | September 13, 2004 | November 30, 2004 | 78 days |
| Wilkinson ES | FM-200447442 04 11/30/04 Wilkinson First floor 28 girl bathroom Second floor 182 women bathroom Need to repair or relace sink drains with over and p-traps is leaking in house tryed. | May 4, 2004 | November 30, 2004 | 210 days |
| Stanton Elementary School | FM-200453836 04 11/30/04 Stanton First floor girls bathroom Sink is clogged need plumber!!!!! | September 2, 2004 | November 30, 2004 | 89 days |
| Hearst Elementary School | FM-200454438 04 11/30/04 Hearst First and second floora Replace or service interior lighting in rooms 104, 102, girls bathroom, 099, 100, 201, 200, 206, 204, and 208B | September 13, 2004 | November 30, 2004 | 78 days |
| Stanton Elementary School | FM-200455655 04 11/30/04 Stanton Second floor boys bathroom Bathroom fixtures have been broken by the kids need fixing, | September 24, 2004 | November 30, 2004 | 67 days |
| Bancroft Elementary School | FM-200454415 04 11/30/04 Bancroft First and second floor open space bathroom teachers tan floor Replace diaphram on toilet in teachers bathroom. | September 10, 2004 | November 30, 2004 | 81 days |
| Bancroft Elementary School | FM-200454413 04 11/30/04 Bancroft Third floor boys bathroom (main bldg.) Replace/ Repair flush valve assemblies on 2 toilets. | September 10, 2004 | November 30, 2004 | 81 days |
| Bancroft Elementary School | FM-200454410 04 11/30/04 Bancroft Second floor girls bathroom (primary wing) 1 commode, 1 sink has no running water and no parts. | September 10, 2004 | November 30, 2004 | 81 days |
| Woodson High School | FM-200458783 /04 11/30/04 Woodson, H.D. 3rd floor bathroom Toilet is backin up into the halls and classroom. | November 29, 2004 | November 30, 2004 | 1 day |
| Savoy Elementary School | FM-200454451 04 11/30/04 Savoy EMERGENCY Third floor boys restroom 1st urinal - flush kit 6th urinal - flush kit 7th urinal - flush kit 1st toilet - anchor bolts 3rd toilet - flush kit Teacher restroom 3rd floor need new flush kit sink 1 no water at all sink 3 no hot water working. | September 13, 2004 | November 30, 2004 | 78 days |
| Bancroft Elementary School | FM-200454402 04 11/30/04 Bancroft Second floor primary wing (girls bathroom) Replace 2 faucets that do not have any running water. | September 10, 2004 | November 30, 2004 | 81 days |
| Malcolm X ES | FM-200457600 /04 12/1/04 (Malcolm X) !!!URGENT!!! 4th Floor/Ladies Bathroom: Toilet will not flush. Kindergarten: Water running over sink. | October 28, 2004 | December 1, 2004 | 34 days |
| King M L ES | FM-200456797 /04 12/1/04 (King) HEALTH CODE VIOLATION: Kitchen: 1. Sink in kitchen leaking at elbow; sink is slow to drain in restroom; must drain properly. 2. Valves must be mixing faucet; install. | October 13, 2004 | December 1, 2004 | 49 days |
| Draper Elementary School | FM-200457616 /04 12/1/04 (Draper) !!!EMERGENCY!!! 3rd Floor/Boys Restroom: Broken seal, flooding the restroom floors with water. | October 28, 2004 | December 1, 2004 | 34 days |
| Jessie LaSalle Elementary | FM-200457512 /04 12/2/04 LaSalle EMERGENCY Second and basement floor girls and boys bathroom Need the electrician to repair light switch and or lights. | October 27, 2004 | December 2, 2004 | 36 days |
| Stanton Elementary School | FM-200457483 /04 12/2/04 Stanton Second floor girls and boys Girls bathroom fixture in need of repairs. Boys water cooler need adjustment on all floors and filters. | October 27, 2004 | December 2, 2004 | 36 days |
| Kenilworth ES | FM-200457496 /04 12/2/04 Kenilworth First floor Teacher restroom Need to be repaired due to leak. | October 27, 2004 | December 2, 2004 | 36 days |
| Jessie LaSalle Elementary | FM-200457517 /04 12/2/04 LaSalle EMERGENCY Basement floor boys restroom Unstop urinal. | October 27, 2004 | December 2, 2004 | 36 days |
| Johnson JHS | FM-200457520 /04 12/2/04 (Johnson) !!!URGENT!!! Second floor teacher bathroom Teacher has broken her key off in bathroom door need to get door open. | October 27, 2004 | December 2, 2004 | 36 days |
| Miner Elementary | FM-200458902 04 12/3/04 Miner Second floor room 210 Urinals and toilets are stopped upin boys restroom. | December 1, 2004 | December 3, 2004 | 2 days |
| Emery Elementary School | FM-200457393 /04 12/3/04 (Emery) Asbestos Assessment Required. Replace broken sink in second floor bathroom. (boys can't wash there hands) | October 21, 2004 | December 3, 2004 | 43 days |
| Woodson High School | FM-200454508 04 12/3/04 (Woodson, H.D.) FIRE CODE VIOLATION: Plaza/Across from the Bank: Mens bathroom light not working. | September 13, 2004 | December 3, 2004 | 81 days |
| Woodson High School | FM-200454482 04 12/3/04 (Woodson, H.D.) 3rd Floor/Men's Bathroom: Exposed wiring. | September 13, 2004 | December 3, 2004 | 81 days |
| Leckie Elementary School | FM-200457431 /04 12/3/04 (Leckie) !!!URGENT!!! 2nd Floor/Boys Bathroom: No running water in sink. | October 26, 2004 | December 3, 2004 | 38 days |
| Hine JHS | FM-200453754 04 12/3/04 Hine Fourth floor Boys restroom Door will not unlock. | September 1, 2004 | December 3, 2004 | 93 days |
| Birney Elementary School | FM-200457460 /04 12/3/04 Birney First floor principal office Bathroom sink is leaking, need new faucets replace. URGENT | October 26, 2004 | December 3, 2004 | 38 days |
| Eliot Junior High School | FM-200457332 /04 12/3/04 Eliot First floor girls and second teachers No water in neither one of the bathrooms, hole in traps. | October 22, 2004 | December 3, 2004 | 42 days |
| Hine JHS | FM-200448388 04 12/6/04 (Hine) !!!URGENT!!! B-Wing/2nd Floor: Repair lock on girls restroom door. | May 24, 2004 | December 6, 2004 | 196 days |
| Birney Elementary School | FM-200458574 /04 12/6/04 Birney URGENT First floor boys bathroom Old side need 2nd urinal repaired it is leaking from wall. Asbestos Code A - Clear for repairs on 11/23/04. DCPS Safety - Leroy Minton Jr. (RG 11/23/04) | November 22, 2004 | December 6, 2004 | 14 days |
| Wilson High School | FM-200457316 /04 12/6/04 Wilson, W. First floor boys bathroom Replace toilet, the toilet has a hole on the top. The toilet is turned off. | October 22, 2004 | December 6, 2004 | 45 days |
| Woodson High School | FM-200454352 04 12/6/04 (Woodson, H.D.) FIRE CODE VIOLATION: 5th Floor/Stairwelll #4: Door closer broken in womens bathroom. Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Leroy Minton Jr. (RG 09/13/04) | September 10, 2004 | December 6, 2004 | 87 days |
| Hine JHS | FM-200457608 /04 12/6/04 (Hine) !!!URGENT!!! 1st Floor/Boys Restroom: Key continues to turn in cylinder, and will not unlock. | October 28, 2004 | December 6, 2004 | 39 days |
| Woodson High School | FM-200454497 04 12/6/04 (Woodson, H.D.) FIRE CODE VIOLATION: 1st Floor/Inside of Stairwell #2: Door closer in bathroom. Asbestos Code A - Clear for repairs on 09/14/04. DCPS Safety - Richard Gibson (RG) | September 13, 2004 | December 6, 2004 | 84 days |
| Emery Elementary School | FM-200452094 04 12/6/04 (Emery) FIRE CODE VIOLATIONS: 3rd Floor/Girls Bathroom. Broken door closer. Asbestos Code A - Clear for repairs on 08/16/04. DCPS Safety - Richard Gibson (RG) | August 10, 2004 | December 6, 2004 | 118 days |
| Meyer Elementary School | FM-200454356 04 12/7/04 Meyer Basement and first floor Bathrooms are not working, the boys and girls bathroom have water on the floor. First floor girls bathroom have 3 commodes that are not working. Need attention ASAP. | September 10, 2004 | December 7, 2004 | 88 days |
| Oyster Elementary School | FM-200448150 04 12/7/04 Oyster Classroom - 304 1) Water is leaking from Restrooms above Room 304. | May 19, 2004 | December 7, 2004 | 202 days |
| Aiton Elementary School | FM-200457252 /04 12/7/04 (Aiton) !!!URGENT!!! Asbestos Assessment Required. 1st Floor/Room #103: Leaking from ceiling; bathroom above. Code A-clear for repair by DCPS Charles buchanan on 10/25/04 | October 21, 2004 | December 7, 2004 | 47 days |
| Bell High School | FM-200454365 04 12/7/04 Bell Second floor Boys restroom need toilet flush valve. Girls restroom need two toilet flush valves. Third floor Boys restroom sink need to be replace or repair, no hot water line or leaking. | September 10, 2004 | December 7, 2004 | 88 days |
| Bancroft Elementary School | FM-200457678 /04 12/7/04 Bancroft Third floor Primary wing (boys bathroom) Replace 2 self closing faucets, on 2 sinks. | October 29, 2004 | December 7, 2004 | 39 days |
| Bancroft Elementary School | FM-200459291 04 12/7/04 Bancroft Third floor boys bathroom (primary wing) Replace faucets, water will not shut off. | December 7, 2004 | December 7, 2004 | 0 days |
| Dunbar High School | FM-200454340 04 12/8/04 Dunbar Fourth W, 2W, gym and bus suite floor boys restroom Repair / replace bradley basin, sink is inoperative and students are unable to wash their hands. | September 10, 2004 | December 8, 2004 | 89 days |
| Ferebee-Hope Elementary School | FM-200454070 04 12/8/04 Ferebee-Hope First floor Flush valve leaking and add flush. B building boys lockerroom teacher office. Replace broken toilet in bathroom. When flushing water shoot out from hole in toilet, maintenance office. | September 8, 2004 | December 8, 2004 | 91 days |
| Tubman Elementary School | FM-200454047 04 12/8/04 Tubman Second floor boys restroom Replace and caps on light fixtures. Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Leroy Minton Jr. (RG 09/13/04) | September 8, 2004 | December 8, 2004 | 91 days |
| Marshall Educational Center | FM-200454065 04 12/8/04 Marshall Replace missin ceiling tile throughout facility. Stage 1, 2, 3, bathrooms and gym. Asbestos Code A - Clear for repairs on 09/09/04. DCPS Safety - Richard Gibson (RG) | September 8, 2004 | December 8, 2004 | 91 days |
| Marshall Educational Center | FM-200454066 04 12/8/04 Marshall Boys bathroom Stage 3 boys bathroom need to be snaked out. | September 8, 2004 | December 8, 2004 | 91 days |
| Janney Elementary School | FM-200459231 04 12/8/04 Janney Emergency First floor boys restroom The urinal is leaking at the stem. | December 6, 2004 | December 8, 2004 | 2 days |
| Dunbar High School | FM-200454347 04 12/8/04 Dunbar Fourth W and 3 MEane 3 E floor boys and girls restroom Restroom partitions are damaged and missing. Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Leroy Minton Jr. (RG 09/13/04) | September 10, 2004 | December 8, 2004 | 89 days |
| Stevens Elementary School | FM-200459157 04 12/8/04 STEVENS Second Floor Staff Restroom TOILET OVER FLOWING | December 3, 2004 | December 8, 2004 | 5 days |
| Deal Junior High School | FM-200454041 04 12/8/04 Deal First and second floor boys restroom. auditorium and corridors Replace door closers (missing parts). No closers on site. Asbestos Code A - Clear for repairs on 09/13/04. DCPS Safety - Leroy Minton Jr. (RG 09/16/04) | September 8, 2004 | December 8, 2004 | 91 days |
| Whittier Elementary School | FM-200454004 04 12/9/04 (Whittier) !!!VERY URGENT!!! 1st Floor/Boys Restroom: Piece that holds flush valve, and control stop valve has ruptured, valves will not hold; water is running out profusely. | September 7, 2004 | December 9, 2004 | 93 days |
| Simon Elementary School | FM-200454019 04 12/9/04 Simon Urgent !!!! Second Floor - Boys Bathroom 1) Toilets are flooding, cut off valve won't hold and toilet is cracked. | September 8, 2004 | December 9, 2004 | 92 days |
| Randle-Highlands ES | FM-200459239 04 12/9/04 RFANDLE HIGHLANDS SECOND FL. RM 2209 REPAIR WATER LEAK BETWEEN BOYS & GIRLS RESTROOMS. Asbestos Code A - Clear for repairs on 12/07/04. DCPS Safety - Ricardo Eley (RG 12/07/04) | December 6, 2004 | December 9, 2004 | 3 days |
| Marshall Educational Center | FM-200453978 04 12/9/04 Marshall Third Floor - Restroom 1) Roof Leaking. | September 7, 2004 | December 9, 2004 | 93 days |
| Brent Elementary School | FM-200458310 /04 12/9/04 Brent Third Floor-Boys restroom Toilet in restroom is clogged. | November 16, 2004 | December 9, 2004 | 23 days |
| Hearst Elementary School | FM-200453895 04 12/10/04 Hearst Second floor boys restroom Has hazard plaster on walls is chipping. Asbestos Code A - Clear for repairs on 10/25/04. DCPS Safety - Leroy Minton Jr. (RG 10/25/04) | September 3, 2004 | December 10, 2004 | 98 days |
| Jessie LaSalle Elementary | FM-200459286 04 12/10/04 LaSalle Second floor boys bathroom Repair wax ring on urinal. | December 7, 2004 | December 10, 2004 | 3 days |
| Gage-Eckington ES | FM-200453968 04 12/10/04 Gage-Eckington First Floor - Boys Bathroom 1) Roof Leak. | September 7, 2004 | December 10, 2004 | 94 days |
| Wilkinson ES | FM-200459137 04 12/14/04 Wilkinson Second floor 180 - boys bathroom Need to replace commode it is crack and leaking water from rim. Also need to unclog urinal it keeps overflowing. In house has tried. | December 3, 2004 | December 14, 2004 | 11 days |
| Duke Ellington School | FM-200338107 03 12/14/04 Ellington !!!VERY URGENT!!! Subject: Keys for faculty members 15 copies of same keys for these areas, faculty bathroom, teacher lounge and resource room. : | September 26, 2003 | December 14, 2004 | 445 days |
| Webb Elementary School | FM-200459357 04 12/14/04 Webb First floor boys bathroom Need to unstop two urinals. | December 8, 2004 | December 14, 2004 | 6 days |
| Brent Elementary School | FM-200459483 /04 12/15/04 Brent Second floor Boys and girls bathroom has broken flush valves. No flush valves on site. | December 10, 2004 | December 15, 2004 | 5 days |
| Jessie LaSalle Elementary | FM-200453849 04 12/16/04 LaSalle First, second and third floor restrooms 1. Lights not working in 1st floor boys and girls restrooms. 2. Lights not working in 2nd floor boys restroom. | September 2, 2004 | December 16, 2004 | 105 days |
| Jessie LaSalle Elementary | FM-200453844 04 12/16/04 LaSalle First, second and third floor girls bathroom Replace mirrors inside the girls restrooms. Asbestos Code A - Clear for repairs on 09/02/04. DCPS Safety - Leroy Minton Jr. (RG 09/03/04) | September 2, 2004 | December 16, 2004 | 105 days |
| Jessie LaSalle Elementary | FM-200453846 04 12/16/04 LaSalle First, second, third floor and basement boys bathroom Partitions need to be replaced in all boys restrooms. Asbestos Code A - Clear for repairs on 09/02/04. DCPS Safety - Leroy Minton Jr. (RG 09/03/04) | September 2, 2004 | December 16, 2004 | 105 days |
| Jessie LaSalle Elementary | FM-200453847 04 12/16/04 LaSalle Basement boys bathroom Replace entry door. Asbestos Code A - Clear for repairs on 10/25/04. DCPS Safety - Leroy Minton Jr. (RG 10/25/04) | September 2, 2004 | December 16, 2004 | 105 days |
| Jessie LaSalle Elementary | FM-200453848 04 12/16/04 LaSalle Basement cafeteria boys bathroom Replace / repair second urinal near the stall. | September 2, 2004 | December 16, 2004 | 105 days |
| Woodson High School | FM-200453864 04 12/16/04 (Woodson) 5th Floor/Room #512: Leaking through ceiling from bathroom above. | September 2, 2004 | December 16, 2004 | 105 days |
| Brightwood Elementary School | FM-200459906 /04 12/21/04 BRIGHTWOOD FIRST FL. BOYS RESTROOM REPAIR BROKEN WATER PIPE 12/20/2004 14:02 OB - | December 20, 2004 | December 21, 2004 | 1 day |
| Wilson J. O. ES | FM-200459750 /04 12/23/04 Wilson, JO Second floor boys and girls restroom old side Replace or repair faucets. | December 17, 2004 | December 23, 2004 | 6 days |
| Roosevelt High School | FM-200453810 04 12/27/04 Roosevelt 1-2-3 floors Ladies bathroom across from main office need faucets, water constantly runs. Ladies restroom on second floor by room 215 has the same problem. Mens restroom next to room 318 sink is missing. Ladies bathroom next to room 317 need new faucets. | September 1, 2004 | December 27, 2004 | 117 days |
| Ludlow-Taylor ES | FM-200217935 02 12/27/04 Ludlow-Taylor Asbestos Assessment Reqd. 1st Floor Boys' Restroom Plaster hole in ceiling outside boys' restroom. Replace missing ceiling tiles. The ceiling is too high for building maintenance staff to reach. POC: R. Thornton Asbesstos Code A-clear for repair by DCPS Charles E. Buchanan on 9/20/02 | September 19, 2002 | December 27, 2004 | 830 days |
| Kimball Elementary School | FM-200453829 04 12/27/04 Kimball Basement - Teachers Bathroom 1) Lights outs , will not come on.. | September 2, 2004 | December 27, 2004 | 116 days |
| Birney Elementary School | FM-200453811 04 12/27/04 Birney Second floor bathrooms Boys bathroom new side have 2 urinals need unclogging. Boys bathroom old side have 2 toilets need to be unclogged. ASAP | September 1, 2004 | December 27, 2004 | 117 days |
| Bunker Hill Elementary School | FM-200453785 04 12/27/04 Bunker Hill Middle wing girls bathroom on 1 floor toilet need to be replace. Middle wing 2 floor boys bathroom urinal is not working. ASAP | September 1, 2004 | December 27, 2004 | 117 days |
| Benning Elementary School | FM-200453831 04 12/27/04 Benning Through-out 1) Repair Boys and Girls Restrooms in areas of concern. | September 2, 2004 | December 27, 2004 | 116 days |
| Tubman Elementary School | FM-200453804 04 12/27/04 Tubman First and second floor boys restroom Replace ballast in restrooms. Code A-clear repair by DCPS Charles Buchanan on 9/3/04 | September 1, 2004 | December 27, 2004 | 117 days |
| Turner Elementary School | FM-200459757 /04 12/27/04 Turner First floor principals office Unstop sink in principals restroom sewer water coming through drain, water is block. | December 17, 2004 | December 27, 2004 | 10 days |
| Tubman Elementary School | FM-200444780 04 12/28/04 Tubman Thoughout bldg. Replace / repair light fixtures in following locations: Room 106, 108, 111, 202, 204, 206, 306, 307, 308, 309, counselor office, nurse suite, boys bathroom on first floor. Asbestos Code A - Clear for repairs on 03/05/04. Horne Engineering - Bjame Smuth (RG 03/09/04) | March 3, 2004 | December 28, 2004 | 300 days |
| Ludlow-Taylor ES | FM-200444670 04 12/30/04 (Ludlow-Taylor) !!!VERY URGENT!!! 1st Floor Daycare/Girls Restroom: Restore electrical power too lights, bulbs has been changed. (Possible burned out ballast) | March 2, 2004 | December 30, 2004 | 303 days |
| Ludlow-Taylor ES | FM-200450529 04 12/30/04 Ludlow-Taylor First floor day care Replace ballast in light in boys bathroom bulb has been changed light still will not come on. Been cited by health department. Asbestos Code A - Clear for repairs on 07/21/04. DCPS Safety - Leroy Minton Jr. (RG 07/21/04) | July 20, 2004 | December 30, 2004 | 163 days |
| Johnson JHS | FM-200456618 04 1/3/05 Johnson Fitness Room Furnish three (3) service office Boys/Girls Restrooms. V 115 PH 1 Fr. 48 RPM 1725/1140 HP 1/3 / 1/9 | October 8, 2004 | January 3, 2005 | 87 days |
| Garfield ES | FM-200453766 04 1/3/05 Garfield LL Girls bathroom Near library needs door lock or knob with lock. | September 1, 2004 | January 3, 2005 | 124 days |
| Ludlow-Taylor ES | FM-200458342 /04 1/3/05 Ludlow-Taylor Third floor boys and girls Paint bathrooms. Staff can mot remove nasty words all on walls, need painting. Code A-clear for repair by DCPS Charles Buchanan on 12/08/04 | November 16, 2004 | January 3, 2005 | 48 days |
| Savoy Elementary School | FM-200456313 04 1/3/05 Savoy First, second and third floor restrooms 2nd floor girls restroom # 3 need snaking has been stopped up for (6 months), 1st floor boys restroom south side has large hole in toilet need to be replaced. 3rd floor boys restroom stall # 3 need spud and flush valve. | October 1, 2004 | January 3, 2005 | 94 days |
| Ludlow-Taylor ES | FM-200458515 /04 1/3/05 Ludlow-Taylor Third floor Need permit to paint girls and boys bathroom. | November 19, 2004 | January 3, 2005 | 45 days |
| Ludlow-Taylor ES | FM-200459123 04 1/3/05 Ludlow-Taylor First floor day care Replace washer in boys bathroom sink water will not stop running. | December 3, 2004 | January 3, 2005 | 31 days |
| Tubman Elementary School | FM-200454401 04 1/4/05 Tubman Second floor girls restroom Replace spud on commode. | September 10, 2004 | January 4, 2005 | 116 days |
| Kenilworth ES | FM-200456561 04 1/4/05 Kenilworth Urgent !!! First Floor - Teachers Bathroom 1) Water leaking from ceiling. Ceiling have fallen. Asbestos Code A - Clear for repairs on 10/27/04. DCPS Safety - Leroy Minton Jr. (RG 10/29/04) | October 7, 2004 | January 4, 2005 | 89 days |
| Stevens Elementary School | FM-200453388 04 1/4/05 Stevens URGENT Basement boys bathroom When flushed water shouts out back. | August 26, 2004 | January 4, 2005 | 131 days |
| Wilson High School | FM-200456512 04 1/4/05 Wilson, W. All bathrooms Paint all bathrooms throughout the building. Asbestos Code A - Clear for repairs on 10/06/03. DCPS Safety - Leroy Minton (RG 10/06/04) | October 5, 2004 | January 4, 2005 | 91 days |
| Ross Elementary School | FM-200452615 04 1/4/05 Ross Basement One urinal in the boys restroom is broken, need to be repaired. | August 13, 2004 | January 4, 2005 | 144 days |
| Stuart-Hobson Middle School | FM-200456082 04 1/5/05 Stuart-Hobson Second floor girls restroom Commode does not flush, need attention. Students have to use the restroom, also restroom door stalls 4 needs to be fix.Water fountains gone is leaking, ther others in not working. | September 29, 2004 | January 5, 2005 | 98 days |
| Takoma Educational Center | FM-200456481 04 1/5/05 Takoma EMERGENCY Third floor room 222 Plumbing work is needed in boys restroom. U*rinal leaks from behind keeping floor wet and the handicapp stall is place where the drains is. This is harazous because the student did not see the water and fell. He is handicapp. | October 5, 2004 | January 5, 2005 | 92 days |
| Shepherd ES | FM-200500157 05 1/6/05 Shepherd Old wing second floor boys restroom Fourth stall toilet need new flush valve. | January 5, 2005 | January 6, 2005 | 1 day |
| Brightwood Elementary School | FM-200457163 /04 1/6/05 (Brightwood) 1st Floor: Repair door closer in hallway, boys bathroom, and office. Code A-clear for repair by DCPS Charles Buchanan on 10/26/04 | October 20, 2004 | January 6, 2005 | 78 days |
| Shepherd ES | FM-200500154 05 1/6/05 Shepherd Old wing first and second floor boys restroom Urinal is clogged up attempt to unclog was unsucessful. | January 5, 2005 | January 6, 2005 | 1 day |
| Harris, C.W. ES | FM-200457157 /04 1/6/05 Harris, CW EMERGENCY Lights are very dim in boys bathroom on the first floor. | October 20, 2004 | January 6, 2005 | 78 days |
| Kramer Middle School | FM-200457217 /04 1/6/05 Kramer First floor boys restroom 115 Commode stall 4 leaking water at base. Commode stall 7 need spud replacement. | October 21, 2004 | January 6, 2005 | 77 days |
| Gibbs Elementary School | FM-200457682 /04 1/6/05 (Gibbs) 2nd Floor/E Street Side of Building/Girls Restroom: Leaking from the bottom of toilet into the boys bathroom below. Ceiling damaged. | October 29, 2004 | January 6, 2005 | 69 days |
| Stevens Elementary School | FM-200457955 04 1/6/05 Steven second floor Teachers Bathroom EMERGENCY! Floor needs to be repairded it is buckling. Ceiling underneath the floor need to be checked for damage. Asbestos Code A - Clear for repairs on 12/08/04. DCPS Safety - Leroy Minton Jr. (RG 12/08/04) | November 5, 2004 | January 6, 2005 | 62 days |
| Truesdell Elementary | FM-200500218 05 1/7/05 TRUESDELL FIRST FL. TEACHERS LOUNGE RESTROOM FLUSH VALVE LEAKING WATER ONTO FL. | January 7, 2005 | January 7, 2005 | 0 days |
| Eliot Junior High School | FM-200500206 05 1/7/05 Eliot First floor boys restroom The toilets are backing up and there is a smell to the front door. | January 7, 2005 | January 7, 2005 | 0 days |
| Jessie LaSalle Elementary | FM-200459534 /04 1/10/05 LA SALLE BOYS AND GIRLS RESTROOM 1) STOPPED UP SINKS ,LEAKING URINALS. | December 13, 2004 | January 10, 2005 | 28 days |
| Wilkinson ES | FM-200459140 04 1/10/05 Wilkinson Second floor 182 women bathroom Need to replace faucet it keep leaking. | December 3, 2004 | January 10, 2005 | 38 days |
| Bancroft Elementary School | FM-200500211 05 1/11/05 Bancroft First floor girls and boys restroom 1 toilets will not flush and stopped up. 2 sinks have no running water. | January 7, 2005 | January 11, 2005 | 4 days |
| John Burroughs ES | FM-200500216 05 1/11/05 Burroughs Lower level girls restroom Toilet broke from sloan, when flush water comes out the back. | January 7, 2005 | January 11, 2005 | 4 days |
| Tubman Elementary School | FM-200500208 05 1/12/05 Tubman Third floor boys and girls restroom Boys restroom urinal are leaking, girls in need of spud replacement on commode. | January 7, 2005 | January 12, 2005 | 5 days |
| Tubman Elementary School | FM-200500200 05 1/12/05 Tubman First floor boys restroom Replace spud on urinal. | January 7, 2005 | January 12, 2005 | 5 days |
| Bancroft Elementary School | FM-200453838 04 1/12/05 Bancroft Third floor boys bathroom (main bldg.) Replace / repair flush valve assemblies on 2 toilets. | September 2, 2004 | January 12, 2005 | 132 days |
| Slowe Elementary School | FM-200500292 05 1/13/05 Slowe First floor girls restroom Sink leaks and need new hardware. | January 11, 2005 | January 13, 2005 | 2 days |
| Gage-Eckington ES | FM-200204888 02 1/14/05 (Gage-Eckington) 1. Asbestos assessment required. 1st Floor/Intermediate restroom: Replace stall, or remove bracket from floor Code A-clear for repair by Horne Engineer ( Sharon Voss ) on 3/26/02 (CEB) | March 25, 2002 | January 14, 2005 | 1,026 days |
| Tyler Elementary School | FM-200460093 /04 1/18/05 Tyler Teacher Restroom and Office Restroom Repair leaking convertor coils in teacher restroom and office restroom. | December 29, 2004 | January 18, 2005 | 20 days |
| Montgomery ES | FM-200500487 05 1/18/05 (Montgomery) !!!EMERGENCY!!! 1st Floor/Learning Center #1: Flush valve broken on toilet in girls restroom; unable to shut-off. Toilet running over, water flooding the floor. (Staff attempting to shut the water off in the building. | January 14, 2005 | January 18, 2005 | 4 days |
| Hine JHS | FM-200455712 04 1/18/05 Hine Third floor room 300 Unstop drain line to science table. First floor outside mens restroom Replace wax ring to urinal. | September 24, 2004 | January 18, 2005 | 116 days |
| Dunbar High School | FM-200500632 05 1/19/05 DUNBAR FIFTH FL. BOYS RESTROOM BROKEN PIPE WATER IS ON THE FL. | January 19, 2005 | January 19, 2005 | 0 days |
| Shepherd ES | FM-200218017 02 1/24/05 Shepherd ****Emergency**** Boys' Restroom There are only two toilets in the boys' restroom for use of approx. 40 students and one of them is cracked. Need replacement [11" rough--need American standard to replace existing, cracked toilet. POC: J.T. Vernon 576-8046 Asbesstos Code A-clear for repair by Horne Engineer Philip Connolly DCPS Charles E. Buchanan on 9/24/02 | September 20, 2002 | January 24, 2005 | 857 days |
| Ludlow-Taylor ES | FM-200446336 04 1/25/05 Ludlow-Taylor First floor room 100 Repair stool in kindergarten bathroom. Water leaking under stool. | April 5, 2004 | January 25, 2005 | 295 days |
| Rudolph Elementary School | FM-200500734 05 1/25/05 Rudolph First floor boys restroom Replace two defective # 186 flush valve, One single lever self closing faucet one service sink faucet. | January 24, 2005 | January 25, 2005 | 1 day |
| Spingarn High School | FM-200459581 /04 1/26/05 Spingarn Second floor room 211B Requesting a plummer to change faucets in bathroom existing ones are broken. | December 14, 2004 | January 26, 2005 | 43 days |
| Turner Elementary School | FM-200500082 05 1/26/05 Turner First floor girls and boys restroom new bldg. Change locks on doors in hall leading to outside exit door. | January 4, 2005 | January 26, 2005 | 22 days |
| Truesdell Elementary | FM-200500677 05 1/26/05 Truesdell Second floor boys restroom Sink is coming off the wall. | January 21, 2005 | January 26, 2005 | 5 days |
| Truesdell Elementary | FM-200500347 05 1/26/05 Truesdell First floor boys restroom Sink is coming off the wall. | January 12, 2005 | January 26, 2005 | 14 days |
| Eastern High School | FM-200450744 04 1/27/05 Eastern Repair defective stairwell door by cafeteria and exit door by armory office. B-40 repair defective door, door closure repair or replace B-27. Door R/R by B-20, door to B-11 defective, Door to stair 6 by room 154 door closure, Room 160 defective, door closur b-84, Bathroom door defective by 217 and door to room 249 defective. Asbestos Code A - Clear for repairs on 09/08/04. DCPS Safety - Leroy Minton Jr. (RG 09/08/04) | July 26, 2004 | January 27, 2005 | 185 days |
| Marshall Educational Center | FM-200500165 05 1/27/05 Marshall. Thurgood Second floor First floor boys bathroom has a leak in the ceiling. Steam pipe. Asbestos Code A - Clear for repairs on 01/07/05. DCPS Safety - Charles Buchanan (RG 01/07/05) | January 5, 2005 | January 27, 2005 | 22 days |
| Turner Elementary School | FM-200500835 05 1/27/05 Turner Third floor girls restroom Repair leaking diaphagm flush valve on toilet next ti window in old side girls room it keeps leaking and can not stop dripping. Water running on floor. | January 26, 2005 | January 27, 2005 | 1 day |
| Takoma Educational Center | FM-200500186 05 1/27/05 Takoma 1st Floor in storage room by old generator Asbestos assessment required Repair or replace 1" ruptured riser for the bathrooms, line is isolated,(black pipe) | January 6, 2005 | January 27, 2005 | 21 days |
| John Burroughs ES | FM-200500145 05 1/28/05 Burroughs First floor women restroom Need toilet, toilet is broken. | January 5, 2005 | January 28, 2005 | 23 days |
| Hart Middle School | FM-200458110 04 1/31/05 (Hart) HEALTH CODE VIOLATION: Kitchen: Unable to gain access to restroom; provide a key to manager for access to restroom. | November 9, 2004 | January 31, 2005 | 83 days |
| Francis Junior High School | FM-200453110 04 1/31/05 Francis First floor boys restroom Cap off lines going sink (handicap) so that the urinal and commode can sink work all on the same line. | August 20, 2004 | January 31, 2005 | 164 days |
| Webb Elementary School | FM-200501026 05 1/31/05 WEBB FIRST FL BOYS RESTROOM 1) STOPPED-UP TOILET / BUSTED PIPE | January 31, 2005 | January 31, 2005 | 0 days |
| Browne Junior High School | FM-200458687 /04 2/1/05 Browne Ground floor new gym Girls locker room bathroom need new flush valves, and and the bathroom in the hallway. | November 24, 2004 | February 1, 2005 | 69 days |
| Wilkinson ES | FM-200500776 05 2/2/05 Wilkinson First floor Kgn. boys bathroom Need to unclog commode, keep running over. | January 25, 2005 | February 2, 2005 | 8 days |
| John Burroughs ES | FM-200458875 04 2/2/05 Burroughs Basement boys bathroom Radiator leaks from botto | December 1, 2004 | February 2, 2005 | 63 days |
| School WW High School | FM-200501109 05 2/2/05 SCHOOL WITHOUT WALLS Basement / Girls Restroom Sink is Cloged-up. | February 1, 2005 | February 2, 2005 | 1 day |
| Turner Elementary School | FM-200452171 04 2/3/05 (Turner) !!!URGENT!!! New Side/Boys Restroom: Unstop toilet on the 3rd floor in the boys restroom, attempted to unstop with a plunger/auger, and poured drain cleaner. (Un-successful with these methods) | August 11, 2004 | February 3, 2005 | 176 days |
| Jessie LaSalle Elementary | FM-200449080 04 2/3/05 Lassalle Basement, second and third floor custodian closet and boys and girls restrooms Repair breach in walls. October 07, 2004: Staff called in today. Code A-clear for repair by DCPS Charles Buchanan on 6/09/04 | June 8, 2004 | February 3, 2005 | 240 days |
| Dunbar High School | FM-200334956 03 2/7/05 Dunbar 1) Women Restroom next to Exit Door in 2E in the Media Center. Repair block wall to hang handicap sink. | August 12, 2003 | February 7, 2005 | 545 days |
| Cardozo High School | FM-200500071 05 2/8/05 Cardozo First floor girls restroom Unstop blockage in toilet, Replace leakage flush valve. | January 4, 2005 | February 8, 2005 | 35 days |
| Brent Elementary School | FM-200342019 /03 2/9/05 Brent Third Floor - Boys Bathroom - Student stood up on Urinal 1) Urinal coming off of wall , water coming out when urinal is flushed. | December 23, 2003 | February 9, 2005 | 414 days |
| Brent Elementary School | FM-200458541 /04 2/9/05 BRENT URGENT!!! Third Floor-Boys Restroom Repair Flush-Valve. There is no other resrroom on the FLOOR | November 19, 2004 | February 9, 2005 | 82 days |
| Woodson High School | FM-200501512 05 2/10/05 (Woodson, H.D.) !!!EMERGENCY!!! Basement Level/ROTC Area Restroom: Toilet backing up due too blockage; flooding the floors in the unisex restroom. | February 10, 2005 | February 10, 2005 | 0 days |
| Wilson J. O. ES | FM-200459901 /04 2/14/05 WILSON J.O. SECOND FL. /BOTH BOYS RESTROOMS/OPEN SPACE REPAIR THE LIGHT SWITCHES IN BOTH RESTROOMS. | December 20, 2004 | February 14, 2005 | 56 days |
| John Burroughs ES | FM-200501331 05 2/15/05 Burroughs Basement boys restroom Sink broke off the wall, not on the mounting any moore. | February 8, 2005 | February 15, 2005 | 7 days |
| Harris, C.W. ES | FM-200500290 05 2/16/05 Harris, CW First floor teachers bathroom Door will not ;ock or un;ock properly. | January 11, 2005 | February 16, 2005 | 36 days |
| Thomas Elementary School | FM-200501304 05 2/16/05 Thomas Second floor new wing boys restroom The sink is hanging off the wall. Asbestos Code A - Clear for repairs on 02/07/05. DCPS Safety - Richard Gibson (RG 02/07/05) | February 7, 2005 | February 16, 2005 | 9 days |
| Deal Junior High School | FM-200501681 05 2/16/05 Deal Boys Restroom / Basement Level Replace Commode | February 16, 2005 | February 16, 2005 | 0 days |
| Houston Elementary School | FM-200501186 05 2/17/05 Houston Throughout The toilets are moving in all bathroom, they need tighten. | February 3, 2005 | February 17, 2005 | 14 days |
| Maury Elementary School | FM-200501723 05 2/17/05 Maury Kaufman wing In the kaufman girls bathroom need to replace faucets. Have new faucets to replace but we can not cut off the hot and cold valve. | February 17, 2005 | February 17, 2005 | 0 days |
| Jessie LaSalle Elementary | FM-200448410 04 2/22/05 Lasalle Unstop toilets and urinals in boys and girls room through out building also sinks. | May 24, 2004 | February 22, 2005 | 274 days |
| Jessie LaSalle Elementary | FM-200336711 03 2/22/05 LaSalle Ground floor boys bathroom Faucet is corroded, it is a health hazard. | September 2, 2003 | February 22, 2005 | 539 days |
| Walker-Jones EC | FM-200500434 05 2/22/05 Walker-Jones URGENT First, secon and third floor Unstop all custodian closet sink. Unstop commodes on the third floor of girls bathroom. Repair urinal on first floor of boys bathroom. Repair sink drain line in kitchen. | January 14, 2005 | February 22, 2005 | 39 days |
| Park View ES | FM-200501835 05 2/22/05 PARKVIEW ES Library Repair ruptured steam line 3/4" in library area, and first floor boys restroom. | February 22, 2005 | February 22, 2005 | 0 days |
| Beers Elementary School | FM-200455496 04 2/22/05 Beers Second floor bldg. 1 teachers restroom Teachers restroom sink hardware rusted out - lots of water is sicking out - Please survey and fix. | September 22, 2004 | February 22, 2005 | 153 days |
| Beers Elementary School | FM-200445576 04 2/23/05 (Beers) Asbestos Assessment Required. Building #2/2nd Floor: Sink hanging from wall, pipes are bent in the girls restroom. Asbestos Code A - Clear for repairs on 03/23/04. Horne Engineering - Sheryll James (RG 03/25/04) | March 18, 2004 | February 23, 2005 | 342 days |
| Jessie LaSalle Elementary | FM-200449067 04 2/23/05 Lassalle Ground floor custodians restroom Replace cracked leaking sink. | June 8, 2004 | February 23, 2005 | 260 days |
| Kelly Miller MS | FM-200500414 05 2/23/05 MILLER THIRD FL GIRLS RESTROOM INSTALL SINK TO WALL Asbestos Code A - Clear for repairs on 01/14/05. DCPS Safety - Richard Gibson (RG) | January 13, 2005 | February 23, 2005 | 41 days |
| Walker-Jones EC | FM-200339653 /03 2/23/05 (Walker Jones) 2nd Floor Open Space/Boys and Girls Restroom: Back-up in plumbing line. | October 29, 2003 | February 23, 2005 | 483 days |
| Jessie LaSalle Elementary | FM-200449074 04 2/24/05 Lassalle All Boys, girls health suite and the teachers restroom Repair all sinks, urinals and toilets: 1. Sink faucets need to be tighten. 2. Several toilets and urinals handles need to be replaced. 3. Some of the spuds need to be replaced. 4. Replace flush valves. 5. Sinks need traps, 2 inch strainers, po plug and faucets replaced. 6. Replace sink in custodian restroom. | June 8, 2004 | February 24, 2005 | 261 days |
| Maury Elementary School | FM-200501968 05 2/24/05 MAURY P E Office Restroom Sink Cloged/ Toiilet over Flowing on to Floor. | February 24, 2005 | February 24, 2005 | 0 days |
| Murch Elementary School | FM-200500276 05 2/25/05 Murch Kaufman wing (boys and girls) Install faucet in restrooms. | January 10, 2005 | February 25, 2005 | 46 days |
| Turner Elementary School | FM-200501991 05 2/28/05 Turner !!!EMERGENCY!!! First floor oldside boys R/R Replace flush valve handle on 4th toilet. Will not flush when pulled down, unstop urinal in boys restroom next to window old side, 1st floor; remove sensor off urinal and replace with flush meter. March 10, 2005: The conditions are worse since request was submitted, and a permit was made previously. (A total of six (6) urinals need to be snaked out) | February 25, 2005 | February 28, 2005 | 3 days |
| Burrville Elementary School | FM-200501872 05 2/28/05 Burrville Second Floor - Girls Bathroom 1) Can't get flush valve top off to change the flush valve.. Toilet won't flush.. | February 23, 2005 | February 28, 2005 | 5 days |
| Rudolph Elementary School | FM-200502004 05 3/1/05 Rudolph Second floor new wing Boys bathroom broken commode need to be replace. ASAP | February 25, 2005 | March 1, 2005 | 4 days |
| Webb Elementary School | FM-200501076 05 3/1/05 WEBB Second FL BOYS RESTROOM Replace or repair bradley basin. | February 1, 2005 | March 1, 2005 | 28 days |
| Patricia R Harris Ed Center | FM-200501989 05 3/1/05 Harris, P.R. Second floor teachers bathrooms near stairway # 3 and 4 Repair flush valve on toilets. | February 25, 2005 | March 1, 2005 | 4 days |
| Browne Junior High School | FM-200458688 /04 3/2/05 Browne First floor new wing Girls and boys restrooms need flush valves. | November 24, 2004 | March 2, 2005 | 98 days |
| Webb Elementary School | FM-200458795 /04 3/2/05 Webb First floor The bathroom has water running from it, and it is flooding. | November 29, 2004 | March 2, 2005 | 93 days |
| Bancroft Elementary School | FM-200501075 05 3/2/05 Bancroft Main Building/girls Restroom Replacee faucets . no running water. Asbestos Code A - Clear for repairs on 02/01/05. DCPS Safety - Leroy Minton (RG 02/01/05) 02/01/2005 11:06 OB - | February 1, 2005 | March 2, 2005 | 29 days |
| Wilson J. O. ES | FM-200459872 /04 3/3/05 WILSON J.O. FIRST FL. /GIRLS RESTROOMS/OLD SIDE RE-ATTACH SINK TO WALL Asbestos Code A - Clear for repairs on 12/21/04. DCPS Safety - Richard Gibson (RG) | December 20, 2004 | March 3, 2005 | 73 days |
| Ronald H. Brown MS | FM-200226838 03 3/4/05 BROWN, RON (ROPER) First Floor - Boys Restroom near stairwell #10 1. The boys restroom need a new toilet installed , as soon as possible . Asbestos Code A - Clear for repairs on 03/12/03. Horne Engineering - Troy Wilcome (RG 03/13/03) | March 11, 2003 | March 4, 2005 | 724 days |
| Eastern High School | FM-200501168 05 3/4/05 Eastern Room 324 Unstop toilet in special Ed. bathroom. Urgent to get fixed, teachers need to use bathroom in room. | February 3, 2005 | March 4, 2005 | 29 days |
| Marshall Educational Center | FM-200502242 05 3/4/05 Marshall Second floor boys bathroom Stage 3 boys bathroom, all toilets are over flowing need to be snaked out from the building. | March 4, 2005 | March 4, 2005 | 0 days |
| School WW High School | FM-200502376 05 3/8/05 School without Walls Basement girls restroom The skylight window is hanging, closing the bathroom because do not want it to fall and hurt any body. | March 8, 2005 | March 8, 2005 | 0 days |
| Murch Elementary School | FM-200501964 05 3/8/05 Murch Second fl. Boys Restroom Rekpair Sink Faucett | February 24, 2005 | March 8, 2005 | 12 days |
| King M L ES | FM-200501985 05 3/9/05 KING First fl. Kitchen Restroom amd Girls Lobby Restroom Remount Toilets to the floor | February 25, 2005 | March 9, 2005 | 12 days |
| Tyler Elementary School | FM-200501956 05 3/9/05 Tyler Third fl. Boys Restroom Unclog Toilets and supply Wax ring | February 23, 2005 | March 9, 2005 | 14 days |
| Kimball Elementary School | FM-200502464 05 3/10/05 Kimball North Wing - Boys Bathroom - Second Floor 1) All urinals are backing up. | March 10, 2005 | March 10, 2005 | 0 days |
| Takoma Educational Center | FM-200502305 05 3/10/05 Takoma Pre K Area Repair or replace rupture coil in bathroom convector. | March 7, 2005 | March 10, 2005 | 3 days |
| Nalle Elementary School | FM-200443919 04 3/10/05 (Nalle) 1st Floor/Boys Bathroom: Students playing in water, one (1) student slipped on wet floor, and hit his head. It was reported that the water was coming from a leaking urinal, however, staff reported floor was checked at 12:00 a.m. and found dry. The injury occurred after 1:00 p.m., and water on the floor had come from the water that the students had thrown on the floor. Request plumber to investigate if there are urinals leaking. | February 10, 2004 | March 10, 2005 | 394 days |
| Wilson J. O. ES | FM-200459900 /04 3/11/05 WILSON J.O. THIRD FL. /GIRLS & BOYS RESTROOMS REPAIR FAUCETS & URINALS | December 20, 2004 | March 11, 2005 | 81 days |
| Wilson J. O. ES | FM-200459898 /04 3/11/05 WILSON J.O. THIRD FL. /BOYS RESTROOMS/OLD SIDE REPAIR URINALS NOT WORKING | December 20, 2004 | March 11, 2005 | 81 days |
| Jessie LaSalle Elementary | FM-200453079 04 3/11/05 LaSalle Third floor boys and girls restroom Repair or replace light ballast in room 304. Replace light fixtures in the third floor girls restroom. Asbestos Code A - Clear for repairs on 08/23/04. DCPS Safety - Leroy Minton Jr. (RG 08/23/04) | August 20, 2004 | March 11, 2005 | 203 days |
| Wilson J. O. ES | FM-200453410 04 3/11/05 Wilson, J.O. Third floor boys restrooms Replace or repair urinals to restrooms. Urinals do not work properly. | August 26, 2004 | March 11, 2005 | 197 days |
| Wilson J. O. ES | FM-200459887 /04 3/11/05 WILSON J.O. FIRST FL. /GIRLS RESTROOMS/NEW SIDE RE-ATTACH SINK TO WALL Asbestos Code A - Clear for repairs on 12/21/04. DCPS Safety - Richard Gibson (RG) | December 20, 2004 | March 11, 2005 | 81 days |
| Wilson J. O. ES | FM-200459868 /04 3/11/05 WILSON J.O. FIRST FL. /BOYS & GIRLS RESTROOMS/OLD SIDE REPAIR SINKS & FAUCETS | December 20, 2004 | March 11, 2005 | 81 days |
| Wilson J. O. ES | FM-200459896 /04 3/12/05 WILSON J.O. SECOND FL. /GIRLS & BOYS RESTROOMS/OLD SIDE REPAIR FAUCETS | December 20, 2004 | March 12, 2005 | 82 days |
| Wilson J. O. ES | FM-200459751 /04 3/12/05 Wilson, JO Third floor boys and girls restroom old side Need 2 urinals, four hand 2 girls and face had 2 girls. Repair or replace faucets and replace or repair 3 urinala not working. | December 17, 2004 | March 12, 2005 | 85 days |
| Wilson J. O. ES | FM-200459878 /04 3/12/05 WILSON J.O. FIRST FL. /BOYS RESTROOMS/NEW SIDE REPAIR SINK FAUCETS | December 20, 2004 | March 12, 2005 | 82 days |
| Wilson J. O. ES | FM-200500466 05 3/14/05 (Wilson, J.O) Teacher restroom in hall on the first floor. The sink is stopped up because the line going into the wll has a blockage. Needs to be snaked or somthing..... PLEASE RESPOND ASAP. Thanks | January 7, 2005 | March 14, 2005 | 66 days |
| Wilson J. O. ES | FM-200457829 04 3/14/05 Wilson, J.O. EMERGENCY First floor old side Lights keep going on and off in main hallway, and the boys bathroom might need a light switch the light are all out. Asbestos Code A - Clear for repairs on 11/02/04. DCPS Safety - Richard Gibson (RG) | November 2, 2004 | March 14, 2005 | 132 days |
| Wilson J. O. ES | FM-200339014 /03 3/15/05 Wilson, J.O. Second floor girls bathroom, (Old Wing) Asbestos Code A, clear for repairs on 10/16/03 for the ceiling surface that light fixture is mounted to. DCPS Safety, R. Edwards (RE-10/16/03) Repair or replace light fixture wiring will not sustain replacement ballast. Ceiling subject to water run off. | October 16, 2003 | March 15, 2005 | 516 days |
| Wilson J. O. ES | FM-200455022 04 3/15/05 Wilson, J.O. Second and third floor open space areas Upgrade lighting to restrooms (boys and girls). NOTE: m Flourescent lights are requested lighting in these areas not sufficient for students and teachers. Asbestos Code A - Clear for repairs on 09/22/04. DCPS Safety - Leroy Minton Jr. (RG 09/22/04) | September 17, 2004 | March 15, 2005 | 179 days |
| Roosevelt High School | FM-200502633 05 3/15/05 Roosevelt First Floor - Boys and Girls Bathroom By the Auditorium 1) Sink in Girls bathroom needs to be re-hung on the wall, the sink in the Boys Bathroom is coming off the wall. | March 14, 2005 | March 15, 2005 | 1 day |
| Wilson J. O. ES | FM-200452735 04 3/15/05 (Wilson, J.O.) !!!EMERGENCY!!! VANDALISM 3rd Floor/Open Space Boys Bathroom: Sparks coming from light switch, exposed wires hanging from wall. (Very dangerous) | August 16, 2004 | March 15, 2005 | 211 days |
| Wilson J. O. ES | FM-200501969 05 3/15/05 WILSON J O. URGENT URGENT Ground fl. Boys Restroom Light Switch not working | February 24, 2005 | March 15, 2005 | 19 days |
| Beers Elementary School | FM-200446443 04 3/16/05 Beers Second floor bldg. 2 Girls restroom sink is hanging from wall. Pipes are bent. Tryed to fix it. Please survey and repair. Asbestos Code A - Clear for repairs on 04/12/04. Horne Engineering - Sheryll James (RG 04/14/04) | April 7, 2004 | March 16, 2005 | 343 days |
| River Terrace ES | FM-200454582 04 3/16/05 River Terrace FIRE CODE VIOLATION: First floor Door will not open properly to the bathroom inside of the health suite.. Code A-clear for repair by DCPS Charles Buchanan on 9/16/04 Electrical door opening for handicap to opening door. | September 14, 2004 | March 16, 2005 | 183 days |
| Wilson J. O. ES | FM-200459899 /04 3/16/05 WILSON J.O. THIRD FL. /GIRLS RESTROOMS/OLD SIDE REPAIR FAUCETS | December 20, 2004 | March 16, 2005 | 86 days |
| Macfarland Middle School | FM-200502812 05 3/16/05 (Mac Farland) "Emergency" Second floor/Boys' restroom. Unclog main waste line to urinals in boys' bathroom . Note: Water is over flowing into the hallway. | March 16, 2005 | March 16, 2005 | 0 days |
| Patricia R Harris Ed Center | FM-200502659 05 3/16/05 Harris P R First fl Teachers Restroom fFluch Valve Not working 03/14/2005 11:21 OB - 03/14/2005 11:22 OB - | March 14, 2005 | March 16, 2005 | 2 days |
| Wilson J. O. ES | FM-200459890 /04 3/17/05 WILSON J.O. FIRST FL. /GIRLS & BOYS RESTROOMS RE-ATTACH SINK TO WALL IN GIRLS RESTROOM/ REPAIR FAUCETS IN BOYS RESTROOM Asbestos Code A - Clear for repairs on 12/21/04. DCPS Safety - Richard Gibson (RG) | December 20, 2004 | March 17, 2005 | 87 days |
| Ross Elementary School | FM-200501021 05 3/17/05 Ross EMERGENCY Basement boys and girls bathroom The doors are falling off the hinges. Need fixing before a child get hurt. Abestos Code A - Clear for repairs on 02/01/05. DCPS Safety - Leroy Minton Jr. (RG 02/11/05) | January 31, 2005 | March 17, 2005 | 45 days |
| River Terrace ES | FM-200501348 05 3/17/05 River Terrace Repair plumming in girls and boys Restroom by office 1. sinks , 2. toilets, and 3. faucets. Asbestos Code A - Clear for repairs on 02/10/05. DCPS Safety - Charles Buchanan (RG 02/11/05) | February 8, 2005 | March 17, 2005 | 37 days |
| Beers Elementary School | FM-200455047 04 3/17/05 Beers URGENT First and second floor bldg. 1-3 Girls and boys restrooms hardware is broken- no running water in one sinks, hanging off wall. Teachers lounge restroom and cafeteria broken bldg - 3 1st floor. Custodial slop sink stopped up. tried to fix these things. | September 17, 2004 | March 17, 2005 | 181 days |
| Bunker Hill Elementary School | FM-200337781 03 3/17/05 Bunker Hill First Floor 1. Replace toilet in girls restroom the third stall, water coming from the wall . Asbestos Code A - Clear for repairs on 09/25/03. Horne Engineering - Sheryll James (RG 09/26/03) | September 19, 2003 | March 17, 2005 | 545 days |
| Jessie LaSalle Elementary | FM-200502661 05 3/18/05 La Salle Second fl. Boys Restroom Stopped-up Urinal 03/14/2005 11:21 OB - 03/14/2005 11:22 OB - | March 14, 2005 | March 18, 2005 | 4 days |
| Birney Elementary School | FM-200502740 05 3/18/05 Birney First fl. Boys Restroom/ First fl. Mop Closet. Repair Urinalls and Unstop Sink Drain | March 15, 2005 | March 18, 2005 | 3 days |
| Wilson J. O. ES | FM-200502204 05 3/18/05 WILSON J O. URGENT URGENT Third floor boys restroom Stand up urinal will run over when you flush it. We snaked it, also plunged it and it will not function right. Please respond because now we only have one working in this restroom. | March 3, 2005 | March 18, 2005 | 15 days |
| Wilson J. O. ES | FM-200453409 04 3/18/05 Wilson, J.O. First, second and third floor boys and girls restrooms Replace or repair faucets to restrooms. NOTE: Many faucets does not work properly. (health hazard) | August 26, 2004 | March 18, 2005 | 204 days |
| Wilson J. O. ES | FM-200459797 /04 3/18/05 WILSON J. O. FIRST FL.- OLD SIDE/BOYS AND GIRLS RESTROOMS REMOUNT SINK TO WALLS/ CHANGE FFAUCETS. Asbestos Code A - Clear for repairs on 12/17/04. DCPS Safety - Richard Gibson (RG) | December 17, 2004 | March 18, 2005 | 91 days |
| Webb Elementary School | FM-200500314 05 3/21/05 Webb Second floor learning center 2 girls restroom The partition is preventing entrance to the restroom. Asbestos Code A - Clear for repairs on 01/11/04. DCPS Safety - Richard Gibson (RG) | January 11, 2005 | March 21, 2005 | 69 days |
| John Burroughs ES | FM-200501597 05 3/21/05 Burroughs First floor women restroom Toilet water coming out from bottom of toilet when flushing. Toilet stop water will not go down. | February 14, 2005 | March 21, 2005 | 35 days |
| John Burroughs ES | FM-200502238 05 3/21/05 Burroughs Girls restroom first floor Toilet stop up tried to snake, water goes down but rush backup like it is trying to over flow.Need key for room # 27. | March 4, 2005 | March 21, 2005 | 17 days |
| Jessie LaSalle Elementary | FM-200209335 02 3/22/05 LaSalle 3rd Floor Boys' Restroom The electric switch in the 3rd floor boys' restroom needs to be replaced. | June 12, 2002 | March 22, 2005 | 1,014 days |
| Wilson High School | FM-200501758 05 3/22/05 Wilson,W ( High School Bathroom Survey Report ) First Floor - Boys Restroom - Inoperable Stoppage Second Floor - Boys Restroom - Urinal Stoppage Third Floor - Boys Restroom - 5th Stall Commode Missing,3rd and 5th Commode Inoperable Gym Gym Restroom - Replace 8" Spread Faucets First Floor - Girls Restroom - 4 " Spread Faucets Needed,Handicapp Toilet Loose and 1st Commode Leaking and Loose From Spud. Third Floor - Girls Restroom - Repair Flush Valve Kit and Need Diaphram Kit | February 18, 2005 | March 22, 2005 | 32 days |
| Park View ES | FM-200502461 05 3/24/05 Park View Teacher Bathroom Asbestos assessment required Repair or replace broken return line in floor, radiator line. Floor need to be digged up. Ceramic tile with associated tile grout. Code A-clear for repair by DCPS Charles Buchanan on 3/10/05 Repair concrete floor in Teacher bathroom, Hallway and outside walk Grounds | March 10, 2005 | March 24, 2005 | 14 days |
| Murch Elementary School | FM-200445198 04 3/24/05 Murch 1ST Floor Boys Restroom Asbestos assessment required Repair or replace rupture 1" steam pipe in Boys restroom 1st floor. Steam is causing mold in Building. Pipe is rupture in the floor. Urgent !!!!! Asbestos Code A - Clear for repairs on 03/15/04. Horne Engineering - Tony Marcolin (RG 03/16/04) | March 11, 2004 | March 24, 2005 | 378 days |
| Webb Elementary School | FM-200456321 04 3/24/05 Webb EMERGENCY Second floor boys restroom The bradley basins has no running water. No place to wash hands. | October 1, 2004 | March 24, 2005 | 174 days |
| Ludlow-Taylor ES | FM-200501595 05 3/24/05 Ludlow-Taylor First floor day-care Unstop sink in girls bathroom. | February 14, 2005 | March 24, 2005 | 38 days |
| Jefferson JHS | FM-200502535 05 3/25/05 (Jefferson) Third floor/Boys resrroom. Repair or Replace lock on third floor boys' restroom, the current lock is jammed, consequently the door cannot be opened. | March 10, 2005 | March 25, 2005 | 15 days |
| Ferebee-Hope Elementary School | FM-200502424 05 3/25/05 Ferebee-Hope Third floor boys bathroom Flush valve and toilet is leaking very badly. | March 9, 2005 | March 25, 2005 | 16 days |
| Ross Elementary School | FM-200502298 05 3/25/05 Ross Boys Restroom Asbestos assessment required Repair or replace leaking return line in ceiling of Boys Restroom in basement. HA 020 cementitious fitting off white 4"-6" O-D fitting on block pipe insulation Yes Asbestos HA 019 pipe insulation white 4"-6" O-D preformed block pipe insulation Yes Asbestos Code B | March 7, 2005 | March 25, 2005 | 18 days |
| Wilson J. O. ES | FM-200459854 /04 3/26/05 WILSON J.O. FIRST FL. /OPEN SPACE RESTROOM/HEAD START AREA REPAIR TOLIETS AND SINKS AS NEEDED | December 20, 2004 | March 26, 2005 | 96 days |
| Payne Elementary School | FM-200502637 05 3/28/05 (Payne) First floor boys bathroom old building Remove censor from bathroom it do not work. Replace with flush valves. | March 14, 2005 | March 28, 2005 | 14 days |
| Wilkinson ES | FM-200503017 05 3/28/05 Wilkinson First floor Pre-K Boys bathroom The sink and toilet are off the wall. | March 21, 2005 | March 28, 2005 | 7 days |
| Payne Elementary School | FM-200457071 /04 3/28/05 Payne First floor old building Teacher bathroom replace broken glass in bathroom. Asbestos Code A - Clear for repairs on 10/25/04. DCPS Safety - Leroy Minton Jr. (RG 10/25/04) | October 19, 2004 | March 28, 2005 | 160 days |
| Webb Elementary School | FM-200456701 /04 3/28/05 Webb First and second floor Replace broken windows through out building. Areas room 133, cafeteria, boy restroom first and second floors. Code A-clear for repair by DCPS Charles Buchanan on 10/20/04 | October 12, 2004 | March 28, 2005 | 167 days |
| Beers Elementary School | FM-200503115 05 3/28/05 Beers Roof - Building 2 - Boys Bathroom 1) Leaking above slop sink. | March 23, 2005 | March 28, 2005 | 5 days |
| Meyer Elementary School | FM-200502994 05 3/28/05 Meyer URGENT First floor boys bathroom Urinal is leaking need attention. ASAP | March 21, 2005 | March 28, 2005 | 7 days |
| Savoy Elementary School | FM-200452674 04 3/29/05 Savoy First floor kitchen Kitchen restroom has hot water faucet that constantly runs. This faucet have been repaired some 6, 7 times and still is back to square 1. This faucet needs to be replaced not repaired any more. | August 13, 2004 | March 29, 2005 | 228 days |
| Clark Elementary School | FM-200502672 05 3/30/05 Clark First floor girls bathroom Toilet is crack and has came off the drain. | March 14, 2005 | March 30, 2005 | 16 days |
| Webb Elementary School | FM-200458351 /04 3/30/05 Webb First Floor Girls restroom Repair toilet ,The bolts holding the toilet to the floor are broker. water leaking onto floor. | November 16, 2004 | March 30, 2005 | 134 days |
| Clark Elementary School | FM-200502678 05 3/30/05 Clark UREGENT!!!!!!!!! URGENT!!!!!!!!! First fl. Girls Restroom Repair toilet/that is lying on its side | March 14, 2005 | March 30, 2005 | 16 days |
| Turner Elementary School | FM-200501979 05 3/31/05 Federick Douglass Earley Learning Center behind Turner Girls restroom Toilet partition pilaster is loose. Recommend - re-secure pilaster to partition with (3) screws. Asbestos Code A - Clear for repairs on 02/25/05. DCPS Safety - Richard Gibson (RG) | February 25, 2005 | March 31, 2005 | 34 days |
| Jefferson JHS | FM-200501498 05 3/31/05 Jefferson Bathroom by C. Wilson office Lock need to be place on and need key. | February 10, 2005 | March 31, 2005 | 49 days |
| Beers Elementary School | FM-200340604 /03 3/31/05 Beers URGENT Second floor bldg. #1 Boys bathrooms urinals are to high - !st and 2nd graders are urinating on the floor, please survey to change this. | November 21, 2003 | March 31, 2005 | 496 days |
| Jessie LaSalle Elementary | FM-200458735 /04 4/1/05 LaSalle Throughout (childrens) restroom Restrooms are to dark. The bulbs were change not making contact. | November 29, 2004 | April 1, 2005 | 123 days |
| Jessie LaSalle Elementary | FM-200449065 04 4/1/05 Lassalle First floor girls and women restroom Replace floor tiles. Code A-clear for repair by DCPS Charles Buchanan on 6/09/04 | June 8, 2004 | April 1, 2005 | 297 days |
| Jessie LaSalle Elementary | FM-200503431 05 4/1/05 Lalle Third fl. Girl's & Boy's Restrooms Replace Light Fixtures | March 30, 2005 | April 1, 2005 | 2 days |
| Gibbs Elementary School | FM-200502847 05 4/4/05 Gibbs URGENT First, second and third floor restrooms Hot and cold faucets need replacement or fixed throughout building. | March 17, 2005 | April 4, 2005 | 18 days |
| Ludlow-Taylor ES | FM-200502938 05 4/4/05 Ludlow-Taylor Third fl. Girls Restroom Replace Damage toilet (BROKEN) | March 18, 2005 | April 4, 2005 | 17 days |
| Gibbs Elementary School | FM-200502874 05 4/4/05 Gibbs Second floor girls restroom Commode is not working, need parts or replace cut off valve. | March 17, 2005 | April 4, 2005 | 18 days |
| Wilkinson ES | FM-200456355 04 4/4/05 Wilkinson First floor 110 boys bathroom / teacher lounge Need to replace seats and washers for sink. Need to replace diaphragm on commode. In house try keep leaking. | October 1, 2004 | April 4, 2005 | 185 days |
| Shaw JHS | FM-200502731 05 4/5/05 (Shaw) "A.S.A.P." First floor/Second floor Repair and Replace snaile-flush valves etc., in restrooms located in boys' 8th grade house, boys' 7th grade house and girls' gymnasium. | March 15, 2005 | April 5, 2005 | 21 days |
| Eaton Elementary School | FM-200502919 05 4/5/05 Eaton First floor kitchen restroom # 110-B Replace toilet servicing kitchen area, Porcelain is cracked. Toilet is inoperable. | March 18, 2005 | April 5, 2005 | 18 days |
| Eaton Elementary School | FM-200459997 /04 4/5/05 Eaton Ktichen restroom # 110-B Replace ptoilet servicing kitchen area, Procelain is cracked, topilet is improable. Toilet type (10"B). | December 22, 2004 | April 5, 2005 | 104 days |
| Thomas Elementary School | FM-200503075 05 4/5/05 (Thomas) "Urgent" First floor/New wing/ Counselor's suite/Cafeteria area. Repair or Replace trap, unclog sink in ladies room and also the toilet in the mens's restroom needs a flush valve (counselor"s suite). Repair or Replace flush valve , urinal overflows and trap needs to be replaced in the mens' room. Repair or Replace faucet and spud on toilet in ladies' room in (Cafeteria area). | March 22, 2005 | April 5, 2005 | 14 days |
| Garrison ES | FM-200503320 05 4/5/05 Garrison Second fl. East Boys Restroom Repair Urinal | March 28, 2005 | April 5, 2005 | 8 days |
| Marshall Educational Center | FM-200455122 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Stage # 1 girls bathroom missing ceiling tiles. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) | September 20, 2004 | April 5, 2005 | 197 days |
| Marshall Educational Center | FM-200455125 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Staff bathroom missing ceiling tile stage 1. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) | September 20, 2004 | April 5, 2005 | 197 days |
| Marshall Educational Center | FM-200455132 04 4/5/05 Marshall, Thurgood Fire Code Violation First floor Bathroom near nurse office missing ceiling tile girls. Asbestos Code A - Clear for repairs on 09/20/04. DCPS Safety - Richard Gibson. (RG) | September 20, 2004 | April 5, 2005 | 197 days |
| Jessie LaSalle Elementary | FM-200503538 05 4/6/05 La Salle Second fl. Girl's and Boy's Restrooms Repair Light Fixturers . | April 4, 2005 | April 6, 2005 | 2 days |
| Jessie LaSalle Elementary | FM-200447624 04 4/6/05 (Lasalle) !!!URGENT!!! Ground Floor/Cafeteria: Wires exposed, and sparks coming from lights in girls restroom. Need new light fixture installed. | May 6, 2004 | April 6, 2005 | 335 days |
| Beers Elementary School | FM-200502228 05 4/6/05 Beers 1 1/2 nipples, sink traps 1 1/2, closet flanges bldg. 2 2nd floor boys room. | March 4, 2005 | April 6, 2005 | 33 days |
| Wilkinson ES | FM-200503531 05 4/8/05 Wilkinson Library Woman's Restroom Replace Flush Valves | April 4, 2005 | April 8, 2005 | 4 days |
| Hine JHS | FM-200503567 05 4/8/05 Hine Second fl. B - Wing Girls Restroom Repair Toilets. | April 5, 2005 | April 8, 2005 | 3 days |
| Webb Elementary School | FM-200502506 05 4/11/05 Webb Second floor girls and boys restroom Stopped sink, boys trap need to be replaced. | March 10, 2005 | April 11, 2005 | 32 days |
| Wilkinson ES | FM-200501367 05 4/11/05 Wilkinson First floor kgn area boys restroom Need to replace 110 flush valve. | February 8, 2005 | April 11, 2005 | 62 days |
| Ballou Senior High School | FM-200503469 05 4/12/05 (Ballou) "Urgent" Replace or Repair lever handle on restroom in health suite. Note: Unable to secure door. | March 31, 2005 | April 12, 2005 | 12 days |
| Woodson High School | FM-200503910 05 4/12/05 (Woodson, H.D.) !!!VERY URGENT!!! 1st Floor/Teachers Bathroom: Repair or replace cut off valve on toilet; leaking profusely. | April 12, 2005 | April 12, 2005 | 0 days |
| Wilson J. O. ES | FM-200500474 05 4/13/05 (Wilson, J.O.) Toiles (stand up urinals) out of order;also none of the water runs in any of the face bowls kids cnnot wash hands; ;or use the urinals in this restroom (3rd Floor) | January 5, 2005 | April 13, 2005 | 98 days |
| Jessie LaSalle Elementary | FM-200503988 05 4/14/05 (Lasalle) !!!VERY URGENT!!! 2nd Floor/Boys Bathroom: #2 Urinal continues to run; unable to shut off. | April 13, 2005 | April 14, 2005 | 1 day |
| Wilson J. O. ES | FM-200221371 /02 4/14/05 Wilson, J.O. Second floor Boys room new side Reinstall 2 urinals on the wall. Asbestos Code A - Clear for repairs on 11/20/02. Horne Engineering - Bipin Nanavaty (RG 11/21/02) | November 20, 2002 | April 14, 2005 | 876 days |
| Wilson J. O. ES | FM-200459749 /04 4/14/05 Wilson, JO Second floor boys room new side REinstall two urinals on the wall. Asbestos Code A - Clear for repairs on 12/22/04. DCPS Safety - Leroy Minton Jr. (RG 12/22/04) | December 17, 2004 | April 14, 2005 | 118 days |
| Merritt Middle School | FM-200504079 05 4/15/05 (Merritt) "Urgent" First floor, Restrooms. Unstop sink in first floor ladies restroom, replace wax ring on toilet in first floor girls' restroom and Unstop sink in Principals restroom. | April 14, 2005 | April 15, 2005 | 1 day |
| Coolidge High School | FM-200502073 05 4/18/05 Coolidge New gym / girls restrooms Repair blockage inside one girls restroom and repair commode leaking down inside classroom. | February 28, 2005 | April 18, 2005 | 49 days |
| Shaed Elementary School | FM-200504192 05 4/18/05 ( SHAED ) EMERGENCY!!! First Floor - Boys Bathroom 1) Raw sewage is backing up through the line flooding the floor | April 18, 2005 | April 18, 2005 | 0 days |
| Coolidge High School | FM-200503647 05 4/19/05 ( COOLIDGE ) EMERGENCY!!! Ground Floor - Restroom, (near old girls gym) 1) Water leaking from the drain line and comming through the ceiling. | April 6, 2005 | April 19, 2005 | 13 days |
| Spingarn High School | FM-200500069 05 4/19/05 Spingarn Boys restroom Survey leak that runs down into the armory from the urinals. Need to be fixed so restroom can be used for basketball games. | January 4, 2005 | April 19, 2005 | 105 days |
| Savoy Elementary School | FM-200227511 03 4/19/05 Savoy Second floor boys restroom Standup urinal on the end of restroom cannot be unclogged tried plunger tried 25 feet snake will not unclog and cut off valve not working. Restroom closed because the kids know this and constantly flushes it until it runs over and flood the restroom, then it drips down to the first floor. | March 24, 2003 | April 19, 2005 | 757 days |
| Amidon Elementary School | FM-200459800 /04 4/19/05 Amidon First, second floor Doors falling off the hinges. Kitchen restroom metal door need door closer. Lobby door need door closer. Computer Lab metal door need door hinges. Library soided wooden door need to be replace. Classroom 218 wooden door need to be replace. Code A-clear for repair by DCPS Charles Buchanan on 2/01/05 | December 17, 2004 | April 19, 2005 | 123 days |
| Kimball Elementary School | FM-200504358 05 4/20/05 Kimball URGENT URGENT First fl. Teachers Restroom Toilet Flush Valve Broken from toilet Asbestos Code A - Clear for repairs on 04/20/05. DCPS Safety - Richard Gibson (RG) | April 20, 2005 | April 20, 2005 | 0 days |
| Spingarn High School | FM-200504232 05 4/20/05 ( SPINGARN ) Second Floor - Boys Bathroom 1) Repair urinals. | April 19, 2005 | April 20, 2005 | 1 day |
| Spingarn High School | FM-200452145 04 4/20/05 Spingarn Second floor teacher restroom by 218 Requesting a plumber to replace first and fourth urinal need a spud. Last 2 urinal need a diaphragm. | August 11, 2004 | April 20, 2005 | 252 days |
| Park View ES | FM-200502367 05 4/25/05 Park View Ground floor Repair leaking line on sink, teacher restroom. | March 8, 2005 | April 25, 2005 | 48 days |
| Backus Middle School | FM-200501644 05 4/26/05 Backus Second Floor - Boys Bathroom 1) Repair ( 2 ) urinals . When urinals are flushed water comes out on the floor. | February 15, 2005 | April 26, 2005 | 70 days |
| Cardozo High School | FM-200453774 04 4/27/05 Cardozo First floor girls and boys restroom mop closets. Mop closet sinks stopped up. EMERGENCY | September 1, 2004 | April 27, 2005 | 238 days |
| Adams Elementary | FM-200504747 05 4/27/05 (Adams) First floor, Boys' restroom. Replace wax rings on (2) commodes. | April 26, 2005 | April 27, 2005 | 1 day |
| Browne Junior High School | FM-200456644 04 4/28/05 Browne First floor pre new wing Girls bathroom 2 flush valves need to be replaced. Toilet is constantly running. | October 8, 2004 | April 28, 2005 | 202 days |
| Webb Elementary School | FM-200504821 05 4/28/05 (Webb) "Urgent" First floor, Learning Center/Second floor Replace flush valve on commode in (learning center). Unclog toilet in (second floor, boys' restroom). | April 27, 2005 | April 28, 2005 | 1 day |
| Whittier Elementary School | FM-200504869 05 4/29/05 ( WHITTIER ) First Floor - Girls Restroom 1) Stop sink leakage, can't cut the water off. | April 28, 2005 | April 29, 2005 | 1 day |
| Gage-Eckington ES | FM-200504772 05 4/29/05 Gage-Eckington Primary Side Girls Restroom/Mrs Wilsons Classroom Repair Toilets in both Areas Asbestos Code A - Clear for repairs on 04/26/05. DCPS Safety - Richard Gibson (RG) | April 26, 2005 | April 29, 2005 | 3 days |
| Jefferson JHS | FM-200504955 05 5/2/05 ( JEFFERSON ) Urgent!! Second Floor - Teachers Lounge Bathroom 1) Sink is over flowing with water, faucet wont cut off. ( the plumber shut the water off ) | April 29, 2005 | May 2, 2005 | 3 days |
| Marshall Educational Center | FM-200501765 05 5/4/05 Marshall First floor boys bathroom Water is backing up. | February 18, 2005 | May 4, 2005 | 75 days |
| Woodson High School | FM-200505081 05 5/4/05 Woodson H D Third fl. Boys Restroom Repair Toilet , it is Leaking around the Base. | May 3, 2005 | May 4, 2005 | 1 day |
| Nalle Elementary School | FM-200453122 04 5/4/05 (Nalle, J.C.) FIRE CODE VIOLATION: 1st Floor/Boys Bathroom: Door closer broken. Asbestos Code A - Clear for repairs on 08/26/04. DCPS Safety -Leroy Minton Jr. (RG 08/27/04) | August 20, 2004 | May 4, 2005 | 257 days |
| Clark Elementary School | FM-200504952 05 5/4/05 (Clark) "Emergency" Second & Third/Teachers' Restrooms. Repair leaking commodes, toilets are overflowing. Note: Custodians have shut the water off, but the teachers are unable to use these restroom. | April 29, 2005 | May 4, 2005 | 5 days |
| Wilkinson ES | FM-200456356 04 5/5/05 Wilkinson First floor 52 bathroom gym area Need to replace seat and washer for sink keep leaking. | October 1, 2004 | May 5, 2005 | 216 days |
| Wilkinson ES | FM-200504738 05 5/5/05 ( WILKINSON ) URGENT!!! First Floor - Pre K Boys Restroom 1) Neet to secure loose sink to wall | April 26, 2005 | May 5, 2005 | 9 days |
| Wilkinson ES | FM-200504739 05 5/5/05 ( WILKINSON ) URGENT!!! First Floor - Pre K Girls Restroom 1) Replace or Repair self closing faucet lever, water keeps running. | April 26, 2005 | May 5, 2005 | 9 days |
| Birney Elementary School | FM-200504857 05 5/5/05 (Birney) First floor, Boys' Restroom/New side. Replace (2) broken urinals. | April 28, 2005 | May 5, 2005 | 7 days |
| Ross Elementary School | FM-200503719 05 5/6/05 ( ROSS ) URGENT!!!!!! Second Floor - Teachers Restroom 1) Repair leaking toilet. | April 7, 2005 | May 6, 2005 | 29 days |
| Wilkinson ES | FM-200456357 04 5/6/05 Wilkinson First floor 65 gym office toilet bathroom Need to replace vaccum breaker leaking water when flush. | October 1, 2004 | May 6, 2005 | 217 days |
| Webb Elementary School | FM-200505260 05 5/9/05 (Webb) First floor, Boys' & Girls' restrooms /Teachers' restrooms. Boys' restroom unclog (2) urinals, also in boys' and girls' restrooms repair or replace broken faucets. Repair or Replace broken faucets in teachers' learning center 1 and teachers learning center 2. | May 9, 2005 | May 9, 2005 | 0 days |
| Murch Elementary School | FM-200505178 05 5/9/05 (Murch) "Urgent" First floor, Teacher's Restroom. Repair or Replace Cut off valve and Flush valve on toilet. Note: The toilet constantly runs and leaks. | May 5, 2005 | May 9, 2005 | 4 days |
| Savoy Elementary School | FM-200452636 04 5/9/05 Savoy EMERGENCY First floor Girls restroom on southened of hallway across from day care Exit door is jammed, looks as though someone tried to getr into it. Door will not open, this is a serious fire hazard and need to be taken seriously. Code A - clear for repairs as |