"Boiler" Closed Repair Requests

Detailed Reports

School Description Open Date Close Date Time Elapsed
Lincoln Middle School FM-200106569 01 8/23/01 LINCOLN BOILER ROOM R/R TWO SEWER EJECTOR UNITS THAT ARE NOT WORKING. (NO INFORMATION AVAILABLE). March 26, 2001 August 23, 2001 150 days
Stuart-Hobson Middle School FM-200115162 01 8/23/01 STUART-HOBSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR CRACKED SHELL IN #2 BOILER. CODE A-CLEAR FOR REPAER BY HORNE ENG 8/8/01 July 12, 2001 August 23, 2001 42 days
Truesdell Elementary FM-200116795 01 8/23/01 TRUESDELL BOILER ROOM REPAIR OR REPLACE MAIN CURCUIT BREAKER FOR #1&#2 BOILERS. BREAKER IS STUCK IN THE OFF POSITION. NOTE: FOUR (4) 20 AMP BREAKERS. August 6, 2001 August 23, 2001 17 days
Bruce-Monroe Elementary School FM-200106071 01 8/23/01 BRUCE MONROE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE LEAKING 4" GATE VALVE. 3. Asbestos Code A - Clear for Repair On 03/23/01. March 19, 2001 August 23, 2001 157 days
Montgomery ES FM-200118276 01 8/24/01 (MONTGOMERY) OUTSIDE BOILER ROOM: UNSTOP DRAIN, MOSQUITOS AND BUGS ARE SURROUNDING THE STAGNANT WATER. August 23, 2001 August 24, 2001 1 day
Gibbs Elementary School FM-200116023 01 8/24/01 GIBBS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR FIRE DOOR INSULATION ON #1 & 2 BOILER. BOILERS FAILED INSPECTION. CODE A-CLEAR FOR REPAER BY HORNE ENG 8/8/01 July 27, 2001 August 24, 2001 28 days
Langdon Elementary School FM-200102438 /01 8/24/01 LANGDON BOILER ROOM REPAIR LOCHINVAR BOILER (HOT WATER HEATER), MUST BE RESET EVERYDAY. DOMESTIC HOT WATER TEMPATURE IS 80 DEGRESS. January 30, 2001 August 24, 2001 206 days
Dunbar High School FM-200117008 01 8/27/01 DUNBAR BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE A PIECE IF 2 INCH X 41 INCH LONG THREADED PIPE FOR NO. 4 RELIEF VALVE TO THE DRAIN. 3. REPLACE A LEAKING FIRE TUBE IN BOILER #2, SECOND ROW FROM TOP, NO. 11 TUBE FROM LEFT TO RIGHT. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/22/01. HORNE ENGINEERS - STEPHEN CALDWELL August 9, 2001 August 27, 2001 18 days
Dunbar High School FM-200117079 01 8/27/01 DUNBAR BOILER ROOM (1) ASBESTOS ASSESSMENT IS REQUIRED (2) BOILER # 1 REPLACE 6 TUBES ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/21/01. HORNE ENGINEERS - STEPHEN CALDWELL August 10, 2001 August 27, 2001 17 days
Orr Elementary School FM-200110494 01 8/27/01 ORR BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 4 5" OSY VALVE ON THE SUPPLY AND RETURN LINE FOR BOILER #1 & 2. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/06/01. May 17, 2001 August 27, 2001 102 days
Backus Middle School FM-200116243 01 8/27/01 BACKUS BOILER ROOM ASBESTOS ASSESSMENT IS REQUIRED. REPLACE LEAKING TUBES IN BOILER #2. CODE ACLEAR FOR REPAIR BY HORNE ENG. 8/7/01. July 31, 2001 August 27, 2001 27 days
Cook J.F. Elementary School FM-200117127 01 8/28/01 J.F. COOK BOILER ROOM SEND BURNER TECHNICIAN WITH CALIBRATION INSTRUMENTS TO PROPERLY CALIBRATION BURNERS ON BOILERS #1 AND #2. BURNERS NEED TO BE CALIBRATED PERIODICALLY TO ENSURE PROPER OPERATION AT ALL MODUCATION LEVELS. August 10, 2001 August 28, 2001 18 days
Webb Elementary School FM-200113825 01 8/29/01 WEBB BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REMOVE CHECK VALVE CAPS AND REPAIR LINES AS NEEDED ON #1 AND #2 BOILERS IN THE BACK. (3/4" LINE) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/16/01. June 22, 2001 August 29, 2001 68 days
Hart Middle School FM-200104883 01 8/30/01 Hart Boiler Room Replace leaking tubes in boiler #1 and #3. Tubes are leaking in the front of the boiler onto the burners. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/18/01. March 5, 2001 August 30, 2001 178 days
Montgomery ES FM-200115974 01 8/30/01 MONGOMERY BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REMOVE MANHOLE COVERS FROM BOILERS NUMBER 1 & 2. COVERS HAVE NOT BEEN REMOVED SINCE INSTALLATION AND CANNOT BE REMOVED BY ENGINEERS. NOTE: THIS WORK IS NEEDED SO BOILER CAN BE INSPECTED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/21/01 HORNE ENGINEERS- R AGNANT July 26, 2001 August 30, 2001 35 days
Meyer Elementary School FM-200114886 01 8/31/01 MEYER BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE 2" COPPER PIPE THAT HAS CORRODED ON FLANGE - 2" X 1-1/2" FEMALE ADAPTERS AND 2" COUPLINGS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/13/01. July 9, 2001 August 31, 2001 53 days
Patricia R Harris Ed Center FM-200116950 01 9/5/01 HARRIS, P.R. BOILER ROOM (1) ASBESTOS ASSESSMENT REQUIRED (2) REPAIR ONE (1) CONDENSER PUMP FOR COOLING TOWER. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 08/13/01. HORNE ENGINEERS August 8, 2001 September 5, 2001 28 days
Wilson High School FM-200116257 01 9/7/01 W. WILSON BOILER ROOM AREA PUMP ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 9 FT. OF SCHEDULE 80 HIGH PRESSURE STEAM SUPPLY LINE (BLACK IRON) TO STEAM RECIPROCATING PUMPS. (2" PIPE). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/23/01 HORNE ENGINEERS- TROY WILCOME July 31, 2001 September 7, 2001 38 days
Takoma Educational Center FM-200106245 01 9/7/01 TAKOMA BOILER ROOM FURNISH HVAC SHOP WITH (2) 8" 8 BOLTS FLANGE OS&Y VALVE FOR CHILL WATER LINE IN BOILER ROOM. VALVES ARE NOT HOLDING LETTING CHILL WATER AND HOT WATER GOT TO CONDENSOR. March 21, 2001 September 7, 2001 170 days
Orr Elementary School FM-200119355 01 9/7/01 QRR BOILER ROOM CHANGE CHILLER RUPTURE DISC WAS BLOWN DUE TO HIGH WATER TEMPERTURE GOING THROUGH CHILLER. September 7, 2001 September 7, 2001 0 days
Takoma Educational Center FM-200105079 01 9/7/01 TAKOMA BOILER ROOM REPLACE DEFECTIVE FEEDWATER REGULATOR ON HVAC WATER SYSTEM. RE: BOILERS TAKE ON WATER DURING OPERATION REDUCING HEAT TRANSFER AND FUE ECONOMY. March 7, 2001 September 7, 2001 184 days
Tubman Elementary School FM-200112619 01 9/7/01 TUBMAN FIRST FLOOR BOILER ROOM 1) REPLACE DOOR ASBESTOS CODE A - CLEAR FOR REPARS ON 06/11/01. June 6, 2001 September 7, 2001 93 days
Garfield ES FM-200113483 01 9/7/01 GARFIELD BOILER ROOM ASSESSMENT REQUIRED REPLACE ONE (1) FIRE TUBE IN BOILER #2, TUBE IS LEAKING AROUND FLANGE. ASBESTOS CODE A-CLEAR FOR REPAIRS ON 06/21/01. June 18, 2001 September 7, 2001 81 days
Harris, C.W. ES FM-200119345 01 9/8/01 C. W. HARRIS BOILER ROOM REPAIR LEAKING CONDENSOR LINE AND START A/C CHILLER. WP-200108644 September 6, 2001 September 8, 2001 2 days
Sousa Middle School FM-200100897 01 9/10/01 SOUSA BOILER ROOM OIL PUMP IS NOT WORKING PROPERLY. THE OIL IS NOT MOVING THROUGHOUT THE SYSTEM LIKE IT SHOULD BE. HC-20000172 January 11, 2001 September 10, 2001 242 days
Savoy Elementary School FM-200109234 01 9/10/01 SAVOY BOILER ROOM REPLACE ELECTRICAL CONTROL SWITCH FOR AC CONDENSOR PUMP. PART PUB A10D-1, CONTACT KIT 6-24-2, NEMA SIZE 2, PH-3, AMP 45, V-230, HP-15.; COIL NUMBER C-H 1889-13, 208V, 60 CYC. WP-200108683 April 30, 2001 September 10, 2001 133 days
Hart Middle School FM-200103074 01 9/10/01 HART BOILER ROOM REPAIR #2 BURNER. BURNER WILL NOT START. February 6, 2001 September 10, 2001 216 days
Orr Elementary School FM-200119051 01 9/11/01 ORR BOILER ROOM NEED TO REPLACE 50 AMP BREAKER FOR COOLING TOWER MOTOR. CURRENT CAN NOT FEED TO MOTOR. September 4, 2001 September 11, 2001 7 days
Shaw JHS FM-200119480 01 9/12/01 SHAW BOILER ROOM REPAIR BURNER ON #4 BOILER - WILL NOT START. WP-200108884 September 10, 2001 September 12, 2001 2 days
Backus Middle School FM-200104065 01 9/13/01 Backus Boiler Room Replace safety valve on boiler #1, existing valve will not reset properly. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/24/01. February 21, 2001 September 13, 2001 204 days
Deal Junior High School FM-200104409 01 9/13/01 Deal Boiler Room Replace hartford loop on boiler #2. Temporary repairs were made. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/15/01. February 27, 2001 September 13, 2001 198 days
Dunbar High School FM-200103300 01 9/13/01 DUNBAR BOILER ROOM ON THE 6TH FLOOR AUTOMATIC DRAIN VALVE IS BROKEN NEED TO BE REPLACE. February 8, 2001 September 13, 2001 217 days
Coolidge High School FM-200104023 01 9/13/01 COOLIDGE BOILER ROOM REPLACE QUICK OPEN AND SLOW OPEN VALVES ON SURFACE BLOW DOWN LINE TO #3 BOILER. February 21, 2001 September 13, 2001 204 days
Amidon Elementary School FM-200102659 01 9/13/01 AMIDON BOILER ROOM #1 BOILER HAS LEAKING TUBES (2). February 1, 2001 September 13, 2001 224 days
Coolidge High School FM-200104074 01 9/13/01 COOLIDGE GROUND FL. BOILER ROOM REPLACE LEAKING BLOW DOWN VALVE ON #3 BOILER SURFACE BLOW LINE. REPLACE ON E QUICK OPEN AND ONE SLOW OPEN VALVE. REPLACE THE FOLLOWING VALVES ON SURFACE BLOW DOWN LINES: ONE QUICK OPEN AND ONE SLOW OPEN. EXISTING VALVES ARE LEAKING. February 21, 2001 September 13, 2001 204 days
Bruce-Monroe Elementary School FM-200104343 01 9/13/01 Bruce Monroe Boiler Room Replace (2) defective control valves to water regulators on both boilers. Valves are faulty and leaks water uncontrolled into system. Valve Size: 1/2" February 26, 2001 September 13, 2001 199 days
Eliot Junior High School FM-200100191 01 9/13/01 ELIOT BOILER ROOM: REPAIR OR REPLACE 10 SECTIONS OF 4" RETURN LINE IN THE BOILER ROOM OVER DOOR, LEADING TO THE BUILDING. THE LINE HAS NEW INSULATION ON IT. SAFETY AND HEALTH HAZARD. HC-20000750 January 7, 2001 September 13, 2001 249 days
Takoma Educational Center FM-200102639 01 9/13/01 TAKOMA BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED ON CHILL WATER LINE OVER CHILLER AND AT PUMP VALVES (MARKED & TAGGED FOR IDENTIFICATION). REMOVE IF ASSESSED ASBESTOS. 2. REPLACE VALVES. POC: MR. TEMPLE CELL #345-1572 ASBESTOS CODE A - CLEAR FOR REPAIRS January 31, 2001 September 13, 2001 225 days
Cardozo High School FM-200104670 01 9/13/01 CARDOZO BASEMENT ROOM 19 REPLACE YARWAY SEATLESS VALVE ON #2 BOILER, REAR BLOW DOWN, 1-1/4" - TYPE B - FIG. 3484 - BASIC PRESS RATING 250 - BLOW OFF SERVICE 200. "VALVES NOT HOLDING" March 1, 2001 September 13, 2001 196 days
Coolidge High School FM-200104022 01 9/13/01 COOLIDGE GROUND FL. BOILER ROOM REPLACE QUICK OPENER AND SLOW OPENING VALVE ON BOTTOM BLOW DOWN LINE TO #2 BOILER, VALVES ARE LEAKING. February 21, 2001 September 13, 2001 204 days
Slowe Elementary School FM-200104072 01 9/13/01 Slowe Boiler Room Repair Leaking water leg on boiler #2. Note: Shclosser Contractors are working on request. February 21, 2001 September 13, 2001 204 days
Jefferson JHS FM-200104071 01 9/13/01 JEFFERSON BASEMENT EAST TUNNEL MAIN BLDG. REPLACE 3/4" NIPPLE ON STEAM SUPPLY LINE (BLACK PIPE). PIPE IS LEAKING IN TUNNEL, FLOODING THE TUNNEL & BOILER ROOM. February 21, 2001 September 13, 2001 204 days
Coolidge High School FM-200104665 01 9/13/01 COOLIDGE BOILER ROOM INSTALL A BYPASS LINE AROUND SOLENOID VALVE MOUNTED ON TOP OF VACUUM RECEIVER ON THE FRESH WATER SUPPLY LINE WITH A GATE VALVE, TO BE USED IN CASE THE SOLENOID FAILS TO WORK. INSTALL ON BOTH NEW VACUUM CONDENSATE RECEIVERS IN BOILER ROOM March 1, 2001 September 13, 2001 196 days
Shaw JHS FM-200104078 01 9/13/01 Shaw Boiler Room Replace corroded exterior shell and reinsulate boiler. February 21, 2001 September 13, 2001 204 days
Orr Elementary School FM-200101982 01 9/13/01 ORR BOILER ROOM BOILER #2, SURVEY TO REPAIR LEAKING SHELLS STAY BOLTS & TUBES. January 24, 2001 September 13, 2001 232 days
Garnet-Patterson MS FM-200100061 1/7/01 9/13/01 GARNET-PATTERSON BOILER ROOM REPAIR/REPLACE 20" PULL CHAIN-OS & Y ON HEADER TO #3 BOILER. HS-20000988 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/15/01 January 7, 2001 September 13, 2001 249 days
Bruce-Monroe Elementary School FM-200104352 01 9/13/01 Bruce Monroe Boiler Room (1) Asbestos Assessment Required (2) Replace (6) malfunctioning hot water supply, return and isolation valves (two of each). Valves are not holding. NEED ANOTHER ASSESSMENT PER C. BRADLEY 5/21/01 ASBESTOS CODE A -CLEAR FOR REPAIRS ON 03/06/01. February 26, 2001 September 13, 2001 199 days
Reed LC FM-200104192 2 2/23/01 9/13/01 REED BOILER ROOM REPAIR OR REPLACE LEAKING SAFETY VALVE ON ALL (3) BOILERS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/15/01 February 23, 2001 September 13, 2001 202 days
Deal Junior High School FM-200104410 01 9/13/01 Deal Boiler Room Repair/replace ruptured blowdown line of boiler #3. Line size: approximately 1 1/2" ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/15/01. February 27, 2001 September 13, 2001 198 days
Shaw JHS FM-200115782 01 9/14/01 SHAW BOILER ROOM 1. ASBESTOS ASSESSMENT NEEDED. 2. REPLACE FRONT REFRACTOR TO #4 BOILER. CODE A CLEAR FOR REPAIR DCPS SAFETY SRH 08-10-01 July 24, 2001 September 14, 2001 52 days
Hearst Elementary School FM-200104944 01 9/14/01 Hearst Boiler Room (1) Asbestos Assessment Required (2) Replace leaking elbow on 2" condensate line. (3) Asbestos Code A - Clear for Repair ON 03/12/01. March 5, 2001 September 14, 2001 193 days
West Elementary School FM-200107349 01 9/14/01 WEST BASEMENT BOILER ROOM REPLACE A 3" COOPER ELBOW ON CITY WATER LINE LOCATED IN CEILING ABOVE BOILER #2. ELBOW IS LEAKING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/18/01. April 4, 2001 September 14, 2001 163 days
Orr Elementary School FM-200109797 01 9/14/01 ORR BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2 REPLACE ALL LEAKING AND BADLY PITTED TUBES IN BOILER #1. WATER HAS FILLED FIRE BOX AND MAY HAVE CAUSE DAMAGE TO NEW BURNER ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/06/01. May 9, 2001 September 14, 2001 128 days
Bancroft Elementary School FM-200104917 01 9/14/01 Bancroft Boiler Room Pipe four (4) blowdown lines from boiler#1 and #2 water column to floor drains. (approximately 3/4). March 5, 2001 September 14, 2001 193 days
Rudolph Elementary School FM-200104947 01 9/14/01 Rudolph Boiler Room (1) Asbestos Assessment Required (2) Repair ruptured and leaking 1 1/2" line coming from bottom of heat exchanger in pump room. CODE A - ASBESTOS ABATED ON 5/2/01 March 5, 2001 September 14, 2001 193 days
Takoma Educational Center FM-200106237 01 9/14/01 TAKOMA BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE DEFECTIVE BYPASS AND ISOLATION VALVES ON CITY WATER MAKE-UP TO #1 & 2 BOILERS. VALVES ARE SIZE 1". VALVES WONT HOLD AND CAUSES WATER TO CONSTANTLY FILL WATER SYSTEM. 3. Asbestos Code A - Clear for Repair On 03/23/01. March 21, 2001 September 14, 2001 177 days
Amidon Elementary School FM-200106871 01 9/14/01 AMIDON BOILER ROOM REPLACE PRESSURE RELIEF VALVE ON #2 BOILER. NO. 174A, SIZE 2", SET 30 LBS., BTU/HR 381500, NAME IS WATTS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/19/01. March 29, 2001 September 14, 2001 169 days
Young Elementary School FM-200109818 01 9/14/01 YOUNG BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REMOVE 3 - THREE PLUGS FROM BOILER #1 AND REMOVE 3 THREE BOLTS FROM BOILER #2 FOR INSPECTION. NEED TO BE HEATED BY TORCH. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/04/01. May 9, 2001 September 14, 2001 128 days
Barnard Elementary School FM-200104740 /01 9/14/01 BARNARD BOILER ROOM PIPE FOUR FLOW DOWN LINE FROM BOILER #1 & 2 WATER COLUMN TO FLOOR DRAIN. (APPROX. 3/4" LINES). March 2, 2001 September 14, 2001 196 days
Stuart-Hobson Middle School FM-200105917 01 9/14/01 STUART-HOBSON BOILER ROOM TUNNEL AREA REPAIR ALL STEAM LEAKS IN TUNNELS. R/R 4" RETURN LINE LEAKING WATER ON FLOOR IN STORE ROOM AREA. March 15, 2001 September 14, 2001 183 days
Harris, C.W. ES FM-200110045 01 9/14/01 C.W. HARRIS BOILER ROOM 1. REPAIR RUPTURED PIPE LINE ABOVE CIRCULATOR PUMP TO BUILDING (PUMP #2). THIS WILL PROVIDE COOLING FOR THE BUILDING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/15/01. May 11, 2001 September 14, 2001 126 days
Coolidge High School FM-200104753 01 9/15/01 COOLIDGE BOILER ROOM & TUNNEL ENTRANCE 1. ASBESTOS ASSESSMENT REQUIRED. 2. R/R LEAKING STEAM LINE IN TUNNEL EMTRANCE BY BOILER ROOM. ASBESTOS ABATED ON 3/21/01. CODE A. March 2, 2001 September 15, 2001 197 days
Ballou Senior High School FM-200102666 01 9/15/01 BALLOU 1ST FL. ROOM 105 GREENHOUSE REPAIR OR REPLACE INTERNAL ELECTRICAL COMPONENT ON #5 BOILER. NOTE: BOILER WILL NOT IGNITE. INFO: GAMA FURNACE (GAS) #5 BOILER. MOD. # GMP150-5, SER. #5808604994, PART IGNITION IGNITER - NORTON 982, B1401015, MOD # 27 1 NW (SOLENOID & ELECRODE TEXAS INST. INT 21GL-2670, L220F30. B13709-14). February 1, 2001 September 15, 2001 226 days
Browne Junior High School FM-200103510 01 9/15/01 BROWNE BOILER ROOM SWITCH IS GONE AND THE BOILER IS FULL OF WATER. NEED A NEW SUMP PUMP. February 12, 2001 September 15, 2001 215 days
Brookland Elementary FM-200116656 01 9/15/01 BROOKLAND BOILER ROOM R/R CONDENSER PUM MOTOR. MOTOR HAS AN ELECTRICAL SHORT. WP-200108667 August 3, 2001 September 15, 2001 43 days
Brookland Elementary FM-200102682 /1/01 9/15/01 BROOKLAND BOILER ROOM R/R SUMP PUMP MOTOR IN THE BOILER, MOTOR IS BURNED OUT. WATER IS BACKING UP IN THE BOILER ROOM FROM PUMP PIT. INFORMATION ON THE MOTOR IS NOT VISIBLE. February 1, 2001 September 15, 2001 226 days
Brookland Elementary FM-200102681 /1/01 9/15/01 BROOKLAND BOILER ROOM R/R SEWAGE EJECTOR PUMP - MOTOR IN THE BOILER. INFORMATION IS AVAILABLE. February 1, 2001 September 15, 2001 226 days
Cardozo High School FM-200103675 01 9/15/01 CARDOZO BOILER ROOM REPLACE WATER FEEDERS ON BOILERS #1, 2 & 3. FEEDERS ARE MALFUNCTIONING. MCDONNELL & MILLER BOILER CONTROL M#151 MAX. BOILER PRESS 35 PSI. February 14, 2001 September 15, 2001 213 days
Ballou Senior High School FM-200118280 01 9/15/01 BALLOU BOILER ROOM REPLACE (2) FLOW SWITCHES ON THE CHILL-WATER AND CONDENSOR SW-LINES. INFO: MCDONNELL & MILLER FLOW SWITCH, FS 82. WP-200108521 August 23, 2001 September 15, 2001 23 days
Ballou Senior High School FM-200116922 01 9/15/01 BALLOU BOILER ROOM (1) ASBESTOS ASSESSMENT REQUIRED (2) DISASSEMBLE END BELLS ON CENTRIFUGAL A/C CHILLER. CODE A-CLEAR FOR REPAIR BY HORNE ENG. 8/12/01. (CEB) August 8, 2001 September 15, 2001 38 days
Bunker Hill Elementary School FM-200100718 1/10/01 9/15/01 BUNKER HILL BOILER ROOM REPLACE B56 REDUCING VALVE MODEL NO. B7, SEO OF 12, 12 LBS., TEMP. 225, MAX 125. HC-20000348 January 10, 2001 September 15, 2001 248 days
Eliot Junior High School FM-200117168 01 9/15/01 ELIOT BASEMENT BOILER ROOM BOILER #1 WILL NOT START OUT ON LOW GASLOCKOUT. WP-200108854 August 13, 2001 September 15, 2001 33 days
Ballou Senior High School FM-200100934 01 9/15/01 BALLOU BOILER ROOM FURNISH AC SHOP WITH (3) 10" 12 BOLT GATE VALVES AND (1) 2" VALVE FOR CHILL WATER LINE THIT IS NOT HOLDING AND IS LETTING HOT WATER GO INTO CHILLER. January 11, 2001 September 15, 2001 247 days
Cardozo High School FM-200103677 01 9/15/01 CARDOZO BOILER ROOM INSTALL ELECTRICAL SERVICE FOR BOILERS PUMP CONTROLS TO RETURN PUMPS AND TANK. MECDONNEL & MILLER - 150, BOILER #1, 2 & 3. February 14, 2001 September 15, 2001 213 days
Cardozo High School FM-200103999 01 9/15/01 CARDOZO GROUND FL. ROOMS 82 - 104 FURNISH AND INSTLL ELECTRIC OVER HEAD HEATERS IN FOLLOWING ARES THAT CANNOT BE HEATED EFFICICENTLY BY BOILERS: ROOM #9, CUSTODIAN MAINTENANCE OFFICE. TYPE: ELECTRIC RESISTANCE, FORCED AIR, 220 VOLTS 30 AMPS, VENDOR - GRAINGER. February 21, 2001 September 15, 2001 206 days
Birney Elementary School FM-200118197 01 9/15/01 BIRNEY BOILER ROOM REPAIR MAIN BURNER CONTACTOR. WP-200108639 August 23, 2001 September 15, 2001 23 days
Cardozo High School FM-200108379 01 9/15/01 CARDOZO BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. SURVEY AND CORRECT NON WORKING DAMPER CONTROLS ON BOILERS #1, #2, #3. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/07/01. April 13, 2001 September 15, 2001 155 days
Emery Elementary School FM-200118198 01 9/15/01 EMERY BOILER ROOM REPAIR BOILER #1 AND #2 WILL NOT START. August 23, 2001 September 15, 2001 23 days
John Burroughs ES FM-200108400 01 9/15/01 BURROUGHS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. R/R CONTROL SWITCH ON #1 RETURN PUMP. PUMP WILL NOT CUT OFF. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/02/01. April 13, 2001 September 15, 2001 155 days
Green Elementary School FM-200119295 01 9/15/01 GREEN BOILER ROOM REPAIR A/C UNIT, WILL NOT START. WP-200108643 September 6, 2001 September 15, 2001 9 days
Harris, C.W. ES FM-200110039 01 9/17/01 C.W. HARRIS BOILER ROOM REPLACE TRANSFORMER TO CIRCULATOR PUMP #1 (ELECTRICAL CONTROL PANEL). THIS WILL PROVIDE COOLING FOR THE BUILDING WP-200108644 May 11, 2001 September 17, 2001 129 days
Woodson High School FM-200114357 01 9/17/01 WOODSON H. D. BOILER ROOM ASBESTOS ASSESSMENT REQUIRED (1) ASBESTOS ASSESSMENT NEEDED ON INSULATION ON SUPPLY LINE 2 1/2" PIPE ON DOMESTIC HOT WATER TANK IN THE BOILER ROOM. (2) REPLACE 2 1/2" LEAKING SUPPLY LINE TO DOMESTIC HOT WATER TANK IN BOILER ROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/06/01. June 29, 2001 September 17, 2001 80 days
Woodson High School FM-200113806 01 9/17/01 H.D. WOODSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE PIPE THERMAL INSULATION ON HVAC EQUIPMENT AND LINES. BOILER NO. 1 12" X 3 FT., HARTFORD LOOP 10" X 3 FT., DOMESTIC TANK 4 FT. X 7 FT. JACKET, STEAM SUPPLY 10" X 7 FT., SIX (6) CHW PUMPS, 3 TO 10" DIA. JACKETS, STEAM CONVERTER NO 1 & 2, 20" X 12 FT. JACKETS, CAFE ABOVE CEILING UNITS NO 3 THRU 7, 1-1/4" X 50 FT. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/28/01. June 22, 2001 September 17, 2001 87 days
Ballou Senior High School FM-200115156 01 9/17/01 BALLOU BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. INSULATE ALL BOILER DOORS. REFRACTORY IN BOILER DOORS #1, 2, 3 AND 4. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY SG 8/10/01. July 12, 2001 September 17, 2001 67 days
Plummer Elementary School FM-200116029 01 9/17/01 PLUMMER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. INSULATE FRONT DOORS OF BOILER #1 & 2. DOORS HAVE NO INSULATION. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY CEB 8/6/01. July 27, 2001 September 17, 2001 52 days
Patricia R Harris Ed Center FM-200113464 01 9/17/01 P.R. HARRIS BOILER ROOM GROUND FLOOR 1. ASSESSMENT REQUIRED 2. REPAIR REFACTORY INSIDE FIRE BOX AND FRONT TUBE SHEET DOOR TO BOILER #1;#2; #3.REFACTORY IS CRACKING AND NEED REPLACING. ASBESTOS CODE A- CLEAR FOR REPAIRS ON 06/22/01. June 18, 2001 September 17, 2001 91 days
Browne Junior High School FM-200109822 01 9/17/01 BROWNE BOILER ROOM REPLACE MECHANICAL SEALS TO CONDENSER PUMP, LEAKING BADLY. WP-200108852 May 9, 2001 September 17, 2001 131 days
Benjamin Banneker Academic HS FM-200104435 01 9/17/01 Banneker Boiler Room Repair leaking chemical tank for boiler #3. The leak is on the small tank before going into the boiler. February 27, 2001 September 17, 2001 202 days
Gibbs Elementary School FM-200111948 01 9/17/01 GIBBS BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE DEFECTIVE RELIEF VALVE ON BOILER #1. MAKE: WATTS, MODEL - M, NO. 740, SIZE 2", SET 30 LBS., BTU RANGE 5,250.000. CODE A-CLEAR FOR REPAER BY HORNE ENG 8/8/01 June 1, 2001 September 17, 2001 108 days
Stuart-Hobson Middle School FM-200115161 01 9/17/01 STUART-HOBSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR REFRACTORY IN FIRE BOXES OF @1, #2, AND #3 BOILERS. ASBESTOS CODE A-CLEAR ASSESSED BY HORNE ENG ON 7/24/01 July 12, 2001 September 17, 2001 67 days
Gibbs Elementary School FM-200113544 01 9/17/01 GIBBS BASEMENT BOILER ROOM 1.ASSESSMENT REQUIRED 2.REPAIR OR REPLACE BOILER CLEAN OUT DOOR. INSULATION ON BOTH BOILER . ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/28/01. June 19, 2001 September 17, 2001 90 days
Johnson JHS FM-200119363 01 9/17/01 JOHNSON BOILER ROOM CHILLER OUT, PNEUMATIC PROBLEM. September 7, 2001 September 17, 2001 10 days
Adams Elementary FM-200115759 01 9/17/01 ADAMS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. RETHREAD BOILER #1 PIPING AS NEEDED. PIPE IS 2" BLACK IRON. CODE A-CLEAR FOR REPAER BY HORNE ENG 8/8/01 July 24, 2001 September 17, 2001 55 days
Webb Elementary School FM-200114034 01 9/17/01 WEBB BOILER ROOM 1. ASBESTOS ASSESSMENT IS REQUIRED. 2. REPLACE MISSING REFRACTORY IN FIREBOX OF #1 BOILER, AND BRICK WORK. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/12/01. June 26, 2001 September 17, 2001 83 days
Spingarn High School FM-200115750 01 9/17/01 SPINGARN STADIUM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE RAY-PAC GAS BOILER RUPTURED CAST IRON HEADER. July 24, 2001 September 17, 2001 55 days
Sousa Middle School FM-200114914 01 9/17/01 SOUSA BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE (2) SAFETY VALVES LEAKING ON BOILER #1, SET 15 PSI, 2-1/2", CAP. 4497, KUNKLE MODEL 930. CAST IRON BOILER BOILER FAILED D.C. INSPECTION. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/10/01. July 9, 2001 September 17, 2001 70 days
Benning Elementary School FM-200116024 01 9/17/01 BENNING BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE INSULATION ON FRON DOORS OF BOILER #1 & 2. INSULATION ON BOILER DOORS DID NOT PASS BOILER INSPECTION. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY CEB 8/6/01 July 27, 2001 September 17, 2001 52 days
Brookland Elementary FM-200115764 01 9/17/01 BROOKLAND BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR 3" CHILL WATER LINE IN BOILER ROOM (RUPTURE). CODE A-CLEAR FOR REPAIR BY HORNE ENG 8/1/01. July 24, 2001 September 17, 2001 55 days
Harris, C.W. ES FM-200100118 1/7/01 9/17/01 HARRIS, C.W. BOILER ROOM REPLACE TWO (2) PRESSURE GAUGES LOCATED ON THE CIRCULATING PIPE LINE. HC-20000957 January 7, 2001 September 17, 2001 253 days
Coolidge High School FM-200120029 01 9/18/01 COOLIDGE TUNNEL AREA BY BOILER ROOM REPLACE LEAKING 2 1/2 " RETURN LINE LOCATED IN TUNNEL AREA BY BOILER ROOM. ABOUT 20 FT. NEEDS TO BE REMOVED AND REPLACED. September 18, 2001 September 18, 2001 0 days
Coolidge High School FM-200108762 01 9/18/01 COOLIDGE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. REPAIR AND MAKE OPERABLE AIR COMPRESSOR FOR AC UNITS FOR NEW SCIENCE LABS. SUSPECT EITHER BENT CRANK SHAFT OR WARPED CONE BEARING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/04/01. April 19, 2001 September 18, 2001 152 days
Cleveland Elementary School FM-200108817 20/01 9/18/01 CLEVELAND 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 18, 2001 151 days
Whittier Elementary School FM-200120148 01 9/19/01 WHITTIER BOILER ROOM REPAIR BURNER ON #2 BOILER WILL NOT IGNITE. WP-200108692 September 19, 2001 September 19, 2001 0 days
Wilson High School FM-200119398 01 9/19/01 W. WILSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 2" X 8" SCHEDULE 80 BLACK IRON NIPPLE AND 2" UNION AT WATER COLUMN ON NO. 1 BOILER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/19/01. HORNE ENGINEER ROGER KAGER September 7, 2001 September 19, 2001 12 days
Malcolm X ES FM-200119053 01 9/19/01 MALCOLM X BOILER ROOM CHILLER KEEP GOING OUT ON LOW EVAPORATER PRESSURE. September 4, 2001 September 19, 2001 15 days
Harris, C.W. ES FM-200108644 01 9/20/01 C.W. HARRIS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01 April 18, 2001 September 20, 2001 155 days
Cook J.F. Elementary School FM-200108641 /18/01 9/20/01 J.F. COOK 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 18, 2001 September 20, 2001 155 days
Nalle Elementary School FM-200108653 01 9/20/01 NALLE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 18, 2001 September 20, 2001 155 days
Patricia R Harris Ed Center FM-200119263 01 9/20/01 HARRIS BOILER ROOM REPAIR #2 AIR COMPRESSOR MOTOR. MOTOR KEEP TRIPPING OUT ON OVER LOAD. OVER LOAD RELAY ARE SQUARE-O. SIZE -B15-5 September 6, 2001 September 20, 2001 14 days
Emery Elementary School FM-200108642 01 9/20/01 EMERY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIR AS OF 4/19/01 April 18, 2001 September 20, 2001 155 days
Adams Elementary FM-200108634 01 9/20/01 ADAMS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01. April 18, 2001 September 20, 2001 155 days
Meyer Elementary School FM-200108652 01 9/20/01 MEYER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 18, 2001 September 20, 2001 155 days
Birney Elementary School FM-200108639 01 9/20/01 BIRNEY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIR AS OF 4/19/01 April 18, 2001 September 20, 2001 155 days
Harris, C.W. ES FM-200110040 01 9/20/01 C.W. HARRIS BOILER ROOM REPAIR MECH. SEAL LEAK ON THE TOWER PUMP. THIS WILL PROVIDE COOLING FOR THE BUILDING WP-200108644 May 11, 2001 September 20, 2001 132 days
Kenilworth ES FM-200108646 01 9/20/01 KENILWORTH 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/19/01. April 18, 2001 September 20, 2001 155 days
Bruce-Monroe Elementary School FM-200108640 01 9/20/01 BRUCE-MONROE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIRS AS OF 4/19/01 April 18, 2001 September 20, 2001 155 days
Hendley Elementary School FM-200108645 01 9/20/01 HENDLEY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS , DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 18, 2001 September 20, 2001 155 days
Lafayette Elementary School FM-200108648 01 9/20/01 LAFAYETTE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01. April 18, 2001 September 20, 2001 155 days
Woodson High School FM-200117541 01 9/20/01 WOODSON SHS BASEMENT LEVEL- BOILER ROOM 1) SNAKE OUT DRAIN LINES, BOILER ROOM IS FLOODED. CODE A - CLEAR FOR REPAIRS AS OF 8/16/01 SYLVIA GRIMES 202 576-5583. August 15, 2001 September 20, 2001 36 days
Key Elementary School FM-200108647 01 9/20/01 KEY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01. April 18, 2001 September 20, 2001 155 days
Orr Elementary School FM-200108654 01 9/20/01 ORR 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMP, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 18, 2001 September 20, 2001 155 days
Green Elementary School FM-200108643 01 9/20/01 GREEN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIR AS OF 4/19/01 April 18, 2001 September 20, 2001 155 days
Malcolm X ES FM-200108649 01 9/20/01 MALCOLM X 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS , WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01. April 18, 2001 September 20, 2001 155 days
Barnard Elementary School FM-200108637 01 9/20/01 BARNARD 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01 April 18, 2001 September 20, 2001 155 days
Bancroft Elementary School FM-200108636 01 9/20/01 BANCROFT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01. April 18, 2001 September 20, 2001 155 days
Beers Elementary School FM-200108638 01 9/20/01 BEERS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIR AS OF 4/19/01 April 18, 2001 September 20, 2001 155 days
Noyes Elementary School FM-200108727 01 9/21/01 NOYES 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIR AS OF 4/19/01. April 19, 2001 September 21, 2001 155 days
Takoma Educational Center FM-200108805 01 9/21/01 TAKOMA 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS , PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 21, 2001 154 days
Watkins Elementary School FM-200108661 01 9/21/01 WATKINS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Payne Elementary School FM-200108680 01 9/21/01 PAYNE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Park View ES FM-200108729 01 9/21/01 PARK VIEW 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01. April 19, 2001 September 21, 2001 155 days
Ketcham Elementary School FM-200108676 01 9/21/01 KETCHAM 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Drew Elementary School FM-200108671 01 9/21/01 DREW 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Brookland Elementary FM-200108667 01 9/21/01 BROOKLAND 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Randle-Highlands ES FM-200108657 01 9/21/01 RANDLE HIGHLANDS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIR AS OF 4/18/01. April 18, 2001 September 21, 2001 156 days
Plummer Elementary School FM-200108800 /01 9/21/01 PLUMMER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 . April 20, 2001 September 21, 2001 154 days
Shepherd ES FM-200108686 01 9/21/01 SHEPHERD 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Wilkinson ES FM-200108693 01 9/21/01 WILKINSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS , DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Winston EC FM-200108664 /01 9/21/01 WINSTON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Walker-Jones EC FM-200108690 4/18/01 9/21/01 WALKER JONES 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMP, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Bowen Elementary School FM-200108694 01 9/21/01 BOWEN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Moten Elementary School FM-200108679 01 9/21/01 MOTEN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Murch Elementary School FM-200108726 01 9/21/01 MURCH 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01. April 19, 2001 September 21, 2001 155 days
Smothers ES FM-200108803 01 9/21/01 SMOTHERS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS , DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 21, 2001 154 days
Stevens Elementary School FM-200108804 01 9/21/01 STEVENS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 21, 2001 154 days
Thomson Elementary School FM-200108658 01 9/21/01 THOMSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/18/01. April 18, 2001 September 21, 2001 156 days
Whittier Elementary School FM-200108692 01 9/21/01 WHITTIER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Slowe Elementary School FM-200108689 01 9/21/01 SLOWE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Ross Elementary School FM-200108802 01 9/21/01 ROSS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 21, 2001 154 days
Wilson J. O. ES FM-200108813 01 9/21/01 J.O. WILSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS , PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 20, 2001 September 21, 2001 154 days
Webb Elementary School FM-200108691 01 9/21/01 WEBB 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Kimball Elementary School FM-200108722 01 9/21/01 KIMBALL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01. April 19, 2001 September 21, 2001 155 days
Powell Elementary School FM-200108801 01 9/21/01 POWELL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 20, 2001 September 21, 2001 154 days
Ferebee-Hope Elementary School FM-200108673 01 9/21/01 FEREBEE-HOPE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Truesdell Elementary FM-200108807 01 9/21/01 TRUESDELL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 21, 2001 154 days
Hyde Elementary School FM-200108721 01 9/21/01 HYDE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A- CLEAR FOR REPAIR AS OF 4/19/01. April 19, 2001 September 21, 2001 155 days
Benning Elementary School FM-200108666 01 9/21/01 BENNING 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Horace Mann Elementary School FM-200108724 01 9/21/01 MANN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR. AS OF 4/19/01. April 19, 2001 September 21, 2001 155 days
Brightwood Elementary School FM-200108717 01 9/21/01 BRIGHTWOOD 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/19/01. April 19, 2001 September 21, 2001 155 days
Garfield ES FM-200108720 01 9/21/01 GARFIELD 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 19, 2001 September 21, 2001 155 days
Houston Elementary School FM-200108675 01 9/21/01 HOUSTON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Davis Elementary School FM-200108670 01 9/21/01 DAVIS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Bunker Hill Elementary School FM-200108668 01 9/21/01 BUNKER HILL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Gibbs Elementary School FM-200108674 01 9/21/01 GIBBS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Peabody Elementary School FM-200108656 01 9/21/01 PEABODY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/19/01. April 18, 2001 September 21, 2001 156 days
Jessie LaSalle Elementary FM-200108723 /01 9/21/01 LASALLE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 19, 2001 September 21, 2001 155 days
Seaton Elementary School FM-200108684 01 9/21/01 SEATON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Eaton Elementary School FM-200108672 01 9/21/01 EATON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Tyler Elementary School FM-200108810 01 9/21/01 TYLER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01. April 20, 2001 September 21, 2001 154 days
Brent Elementary School FM-200108716 01 9/21/01 BRENT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR ON 04/19/01. April 19, 2001 September 21, 2001 155 days
John Burroughs ES FM-200108718 01 9/21/01 BURROUGHS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/19/01. April 19, 2001 September 21, 2001 155 days
Savoy Elementary School FM-200108683 01 9/21/01 SAVOY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Ludlow-Taylor ES FM-200108677 01 9/21/01 LUDLOW-TAYLOR 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Aiton Elementary School FM-200108665 01 9/21/01 AITON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/21/01 April 18, 2001 September 21, 2001 156 days
Clark Elementary School FM-200108719 01 9/21/01 CLARK 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/19/01. April 19, 2001 September 21, 2001 155 days
Oyster Elementary School FM-200108655 01 9/21/01 OYSTER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 18, 2001 September 21, 2001 156 days
Rudolph Elementary School FM-200108682 01 9/21/01 RUDOLPH 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Tubman Elementary School FM-200108809 01 9/21/01 TUBMAN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01. April 20, 2001 September 21, 2001 154 days
Simon Elementary School FM-200108687 01 9/21/01 SIMON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 18, 2001 September 21, 2001 156 days
Winston EC FM-200119577 01 9/24/01 WINSTON 4TH BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. INVESTIGATE AND MAKE CORRECTIVE MEASURES TO STOP WATER FROM AN UNKNOWN SOURCE FROM BACKUP INTO ELECTRICAL PANEL IN 4TH FLOOR BOILER ROOM LEVEL.ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/19/01. HORNE ENGINEER STEPHEN CALDWELL September 10, 2001 September 24, 2001 14 days
Lincoln Middle School FM-200100828 01 9/24/01 LINCOLN BOILER ROOM CALIBRATE #1 BOILER BURNER. HC-20000847 January 11, 2001 September 24, 2001 256 days
Walker-Jones EC FM-200120474 01 9/25/01 WALKER/JONES BOILER ROOM REPAIR BOILER #1 &#2 BURNERS, WILL NOT START. (OPEN LIMIT D8) WP-200108690 September 25, 2001 September 25, 2001 0 days
Sousa Middle School FM-200114913 01 9/25/01 SOUSA BASEMENT BOILER ROOM DUE TO FAILURE OF D.C. INSPECTION, REQUESTING FOR BURNER MECHANIC TO REPAIR AND ADJUST OIL BURNERS ON ALL (3) THREE BOILERS. BOILER SHOW VISIBLE SIGNS OF OVER HEATING, IMPROPER COMBUSTION AND HOT SPOTS. WP-200108891 July 9, 2001 September 25, 2001 78 days
Sousa Middle School FM-200119002 01 9/25/01 SOUSA BOILER ROOM BOILER #2 WILL NOT FIRED OFF DUE TO FLAME FAILURE. September 4, 2001 September 25, 2001 21 days
King M L ES FM-200108824 01 9/26/01 KING 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Kramer Middle School FM-200108869 01 9/26/01 KRAMER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Terrell Mc ES FM-200108841 01 9/26/01 M.C. TERRELL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Terrell Mc ES FM-200106890 01 9/26/01 M.C. TERRELL BOILER ROOM ASBESTOS ASSESSMENT REQUIRED FOR NEW BURNER. 1) CHECK BURNER RING AND BURNER CONE. CONTACT CURTIS EMERSON OFFICE 202-698-1753 CELL 202-438-7434 Requester Phone: 698-1752 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/06/01. March 29, 2001 September 26, 2001 181 days
Lafayette Elementary School FM-200109189 01 9/26/01 LAFAYETTE BOILER ROOM REPAIR TWO DOMESTIC AND TWO HEATING CIRCULATIUNG PUMPS, APPEARS TO BE A PROBLEM WITH STARTER CONTROLS. CITED BY HEALTH DEPT. ON 4-26-01 WITH A 24 HOUR WINDOW TO MAKE CORRECTION. NO DOMESTIC HOT WATER. April 26, 2001 September 26, 2001 153 days
Langdon Elementary School FM-200108825 01 9/26/01 LANGDON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Young Elementary School FM-200108849 01 9/26/01 YOUNG 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Jessie LaSalle Elementary FM-200112298 01 9/26/01 LASALLE BOILER ROOM CHECK BOILER #2. IT WILL NOT FIRE OFF. BURN WILL NOT PURGE MOTOR WILL START ONLY. WP-200108723 June 4, 2001 September 26, 2001 114 days
Jessie LaSalle Elementary FM-200117162 01 9/26/01 LASALLE BOILER ROOM REPAIR OR REPLACE BURNER ON BOILER #2. WILL NOT LITE OFF. WP-200108723 August 13, 2001 September 26, 2001 44 days
Leckie Elementary School FM-200108826 01 9/26/01 LECKIE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Takoma Educational Center FM-200119331 01 9/26/01 TAKOMA BOILER ROOM SEND SOMEONE OUT TO INSPACT GAS LINE TO BOILER #1. NOTE: GAS COMPANY WAS CALLED BY HEAD CUSTODIAN FOR A SMELL OF GAS IN BOILER ROOM AND GAS COMPANY PUT A TAAG ON GAS LINE. WP-200108805 September 6, 2001 September 26, 2001 20 days
Leckie Elementary School FM-200114569 01 9/26/01 LECKIE BOILER ROOM REPAIR OR REPLACE STANDBY PUMP CONTROL STARTER MAKING LOUD NOISE. WP-200108826 July 2, 2001 September 26, 2001 86 days
Amidon Elementary School FM-200108815 01 9/26/01 AMIDON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Burrville Elementary School FM-200108816 20/01 9/26/01 BURRVILLE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Browne Junior High School FM-200108852 01 9/26/01 BROWNE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Thomas Elementary School FM-200108846 01 9/26/01 THOMAS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Lincoln Middle School FM-200108873 01 9/26/01 LINCOLN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Lincoln Middle School FM-200116620 01 9/26/01 LINCOLN BOILER ROOM CALIBRATE BURNERS ON BOILERS #1, 2 AND 3. BURNERS NEED TO BE CALIBRATED PERIODICALLY TO ENSURE PROPER OPERATION AT MODULATION LEVELS. WP-200108890 August 3, 2001 September 26, 2001 54 days
Cardozo High School FM-200108903 01 9/26/01 CARDOZO 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Johnson JHS FM-200108868 01 9/26/01 JOHNSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS , ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Anacostia Senior High School FM-200108897 01 9/26/01 ANACOSTIA 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Stuart-Hobson Middle School FM-200108892 01 9/26/01 STUART-HOBSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Stoddert ES FM-200108837 0/01 9/26/01 STODDERT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Ludlow-Taylor ES FM-200113323 01 9/26/01 LUDLOW-TAYLORS E.S BOILER ROOM ROOM#210 CHECK AND REPAIR LEAKAGE ON PNEUMATIC CONTROL IN ROOM #210. WP-200108677 June 14, 2001 September 26, 2001 104 days
Ludlow-Taylor ES FM-200116608 01 9/26/01 LUDLOW-TAYLOR BOILER ROOM R/R PRESSURE REGULATOR FOR PNEUMATIC CONTROLS. HONEYWELL CONTROL SYSTEM PP-90181002-5 WP-200108677 August 3, 2001 September 26, 2001 54 days
Ronald H. Brown MS FM-200108883 01 9/26/01 RON BROWN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Stanton Elementary School FM-200108836 01 9/26/01 STANTON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Jefferson JHS FM-200108865 01 9/26/01 JEFFERSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Spingarn High School FM-200108917 01 9/26/01 SPINGARN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Janney Elementary School FM-200108823 01 9/26/01 JANNEY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Malcolm X ES FM-200120260 01 9/26/01 MALCOLM X BOILER ROOM REPAIR/REPLACE QUINCY AIR COMPRESSOR STARTER NEMA, SIZE 00, SQUARED D, 600V A.C. MAX., CLASS 8536, TYPE AG-2, SERIES C, SERIAL # 242-133-BB. MAKES LOUD NOISE AND TRIPS OUT OFTEN. 2 TO 3 MELTING ALLOY OVERLOAD RELAY. WP-200108649 September 21, 2001 September 26, 2001 5 days
Malcolm X ES FM-200120446 01 9/26/01 MALCOLM-X BOILER ROOM REPLACE SQUARE- D REGULATOR PSI ON AIR TANK. CLASS 9013 TYPE FHG9 VOLT 115 1 HP-1 1/2 3PH-2 SERIAL-B ON/PSI 100 OFF/PSI September 25, 2001 September 26, 2001 1 day
Sousa Middle School FM-200108891 01 9/26/01 SOUSA 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Meyer Elementary School FM-200104669 01 9/26/01 MEYER BOILER ROOM RE-LOCATED OR EXTEND HEAT PROBES FOR TEMPERATURE GAUGES ON BOILERS #1, #2. SENSITIVITY IS QUESTIONABLE. March 1, 2001 September 26, 2001 209 days
Sousa Middle School FM-200100893 01 9/26/01 SOUSA BOILER ROOMM CITY WATER, FLOAT SWITCH ON CONDENSATE TANK IS BROKEN. NEEDS TO BE REPLACED. HC-20000180 January 11, 2001 September 26, 2001 258 days
Sousa Middle School FM-200100021 01 9/26/01 SOUSA BOILER ROOM BURNER #1 IS GOING OUT ON PILOT FAILURE. BOILER WILL RUN BUT WILL GO OUT. NEED BOILER TO HEAT BUILDING. HC-20000689 January 7, 2001 September 26, 2001 262 days
Hine JHS FM-200108863 01 9/26/01 HINE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Backus Middle School FM-200108850 01 9/26/01 BACKUS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Miner Elementary FM-200108828 01 9/26/01 MINER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Cooke H.D. Elementary School FM-200108821 01 9/26/01 H.D. COOKE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Smothers ES FM-200116614 01 9/26/01 SMOTHER BOILER ROOM REPLACE 2 AQUASTATS ON BOILER #1 AND #2. AQUASTATS ON BOTH BOILERS ARE BAD. WP-200108803 August 3, 2001 September 26, 2001 54 days
Hearst Elementary School FM-200108822 01 9/26/01 HEARST 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Tubman Elementary School FM-200104404 01 9/26/01 Tubman Boiler Room Replace feed water regulators for boilers #1 and #2, existing regulators are nt controlling water flow. Honeywell Braukmann, D-60 series, pressure regulating valve max. Temperature water 180-F, Max. inlet pressure 300psi, outlet pressure range: 10-35psi. February 27, 2001 September 26, 2001 211 days
Coolidge High School FM-200108904 01 9/26/01 COOLIDGE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Ballou Senior High School FM-200108898 01 9/26/01 BALLOU 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Hart Middle School FM-200108862 01 9/26/01 HART 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIR AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Macfarland Middle School FM-200108878 01 9/26/01 MACFARLAND 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Reed LC FM-200104190 0 2/23/01 9/26/01 REED BASMENT BOILER ROOM REPAIR MODULATOR TO #1 BOILER. MODULATOR IS OUT OF BALANCE. February 23, 2001 September 26, 2001 215 days
Reed LC FM-200108831 01 9/26/01 REED 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Dunbar High School FM-200108905 01 9/26/01 DUNBAR 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Woodson High School FM-200108920 01 9/26/01 H.D. WOODSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Patricia R Harris Ed Center FM-200108861 01 9/26/01 P.R. HARRIS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, E LECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Orr Elementary School FM-200116890 01 9/26/01 ORR BOILER ROOM START BURNER ON BOILER #2 August 8, 2001 September 26, 2001 49 days
Marshall Educational Center FM-200108895 01 9/26/01 MARSHALL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Marshall Educational Center FM-200109285 01 9/26/01 MARSHALL BOILER ROOM REPLACE MISSING STARTER CONTROL FOR #1 COMPRESSOR. WP-200108895 April 30, 2001 September 26, 2001 149 days
Patterson ES FM-200108830 4/20/01 9/26/01 PATTERSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Wilson High School FM-200108919 01 9/26/01 W. WILSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Hardy Middle School FM-200108860 01 9/26/01 HARDY 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Shaw JHS FM-200108884 01 9/26/01 SHAW 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/19/01. April 20, 2001 September 26, 2001 159 days
Watkins Elementary School FM-200100044 /01 9/26/01 WATKINS BOILER ROOM R/R AIR COMPRESSOR, PUMP KNOCKS, ON START UP. MODEL #210, SER. 6037558 MAKE: QUINEY HC-20000963 January 7, 2001 September 26, 2001 262 days
Watkins Elementary School FM-200106563 01 9/26/01 WATKINS BASEMENT BOILER ROOM R/R MODULATING CONTROLS ON BOILER #1 & 2. March 24, 2001 September 26, 2001 186 days
Eastern High School FM-200108906 01 9/26/01 EASTERN 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Shaed Elementary School FM-200108834 01 9/26/01 SHAED 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Eaton Elementary School FM-200113789 01 9/26/01 EATON 1) FURNISH (1) CHANGE KEY FOR INTERIOR BOILER ROOM DOOR AND ONE KEY FOR ROOM 117 (BATHROOM). September 24, 2001 September 26, 2001 2 days
School WW High School FM-200108915 01 9/26/01 SCHOOLWITHOUT WALLS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Eliot Junior High School FM-200108854 01 9/26/01 ELIOT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Duke Ellington School FM-200108907 01 9/26/01 ELLINGTON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
West Elementary School FM-200100709 01 9/26/01 WEST BOILER ROOM REPAIR OR REPLACE SEWER EJECTOR PUMP #2. THERE IS NO INFORMATION ON PUMP. HC-20000833 January 10, 2001 September 26, 2001 259 days
Wilson J. O. ES FM-200108984 01 9/26/01 J.O. WILSON BOILER ROOM 1. SURVEY AND ASSESS FUEL OIL LEAK INTO SUMP PUMP PIT AND FLOOR DRAINS. 2. REMOVE FUEL OIL FROM SUMP PUMP PIT AND FLOOR DRAINS. 3. REPAIR BROKEN FUEL OIL LINE. CODE A FOR WORK PERMIT ONLY. MR. RICHARD GIBSON SAFETY (202)576-5584 April 23, 2001 September 26, 2001 156 days
Garrison ES FM-200108820 01 9/26/01 GARRISON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIR AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Rudolph Elementary School FM-200114413 01 9/26/01 RUDOLPH BOILER PUMP ROOM REPAIR H/W CIRC. HEATING SYSTEM THAT IS CONSTANTLY LEAKING WATER FROM THE OVERFLOW LINE. MAY HAVE A FAULTY PRESSURE REGULATOR OR RELIEF VALVE. PIPES HAVE NO INSULATION ON THEM. WP-200108652 June 29, 2001 September 26, 2001 89 days
West Elementary School FM-200108847 01 9/26/01 WEST 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Garnet-Patterson MS FM-200108858 01 9/26/01 GARNET-PATTERSON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Bell High School FM-200108900 01 9/26/01 BELL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Benjamin Banneker Academic HS FM-200108899 01 9/26/01 BANNEKER 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Randle-Highlands ES FM-200119021 01 9/26/01 RANDLE-HIGHLAND BOILER ROOM REPAIR OR REPLACE AIR COMPRESSOR. NO NAME PLATE. WP-200108654 September 4, 2001 September 26, 2001 22 days
Roosevelt High School FM-200108914 01 9/26/01 ROOSEVELT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Raymond Elementary School FM-200109333 01 9/26/01 RAYMOND 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/30/01. April 30, 2001 September 26, 2001 149 days
River Terrace ES FM-200115675 01 9/26/01 RIVER TERRACE BOILER ROOM REPLACE MCDONNELL & MILLER AUTOMATIC COMBINATION LOW WATER CUTOFF ON BOILER #2. WP-200108832 July 23, 2001 September 26, 2001 65 days
River Terrace ES FM-200108832 4/20/01 9/26/01 RIVER TERRACE 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 20, 2001 September 26, 2001 159 days
River Terrace ES FM-200100998 1/11/01 9/26/01 RIVER TERRACE BOILER ROOM REPAIR FLOAT BALL TO CONDENSATE TANK TO PROVIDE WATER CIRCULATION FOR WATER. HC-20000702 January 11, 2001 September 26, 2001 258 days
River Terrace ES FM-200100871 1/11/01 9/26/01 RIVER TERRACE BOILER ROOM REPAIR SHORTIGE IN CONDENSATE CONTROL BOX SWITCH, DOES NOT WORK. MT-20001238 January 11, 2001 September 26, 2001 258 days
Francis Junior High School FM-200108857 01 9/26/01 FRANCIS 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 September 26, 2001 159 days
Gage-Eckington ES FM-200108819 4/20/01 9/26/01 GAGE-ECKINGTON 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS , PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. CODE A - CLEAR FOR REPAIRS AS OF 4/20/01 April 20, 2001 September 26, 2001 159 days
Benjamin Banneker Academic HS FM-200117163 01 9/27/01 BANNEKER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE DETERIORATED REFRACTORY ON FRONT AND REAR FIRE DOORS BOILERS #1, 2 AND 3. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/07/01. HORNE ENGINEERS - STEPHEN CALDWELL (RG) August 13, 2001 September 27, 2001 45 days
Shaw JHS FM-200120275 01 9/28/01 SHAW BOILER ROOM R/R PROGRAM CONTRLS TO #4 BOILER. WILL NOT START. PROGRAM READ L1-13 AX. #3 LIMIT OPEN. BOILER SUPPLIES STEAM TO KITCHEN STEAMER. WP-200108884 September 21, 2001 September 28, 2001 7 days
Lincoln Middle School FM-200119354 01 9/28/01 LINCOLN BOILER ROOM UNSTOP WASTE LINE BACKING UP IN THE BUILDING (RAW SEWAGE IS BACKING UP IN THE BOILER ROOM) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/07/01. LEROY MINTON - SAFETY (202)576-6691 September 7, 2001 September 28, 2001 21 days
Plummer Elementary School FM-200120814 01 10/2/01 PLUMMER BOILER ROOM CHECK BOILER #2, WILL NOT FIRE OFF. October 2, 2001 October 2, 2001 0 days
Davis Elementary School FM-200120866 01 10/2/01 DAVIS BOILER ROOM CORRECT PROBLEM WITH BOILER #2. BOILER SEEMS TO HAVE NO ELCTRICAL PROBLEM. WP-200108670 October 2, 2001 October 2, 2001 0 days
Bruce-Monroe Elementary School FM-200120837 01 10/3/01 BRUCE-MONROE BOILER/MECH. ROOM SERVICE BURNER/CONTROL CYCLE ON BOILER #1. BURNER WILL NOT LIGHT OFF, FLAME FAILURE MAIN BURNER. RE: NO HEAT. October 2, 2001 October 3, 2001 1 day
Miner Elementary FM-200118859 01 10/4/01 MINER BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. TSI REMOVAL IN BOILER ROOM 3. R/R 2" HOT WATER SUPPLY LINE, LINE RUPTURED ABOVE DOMESTIC HOT WATER STORAGE TANK. ENVIROBATE (IT GROUP) CHARLES CRENSHAW 202-437-5673 Code A - Asbsetos Abated on 9/27/01 per Leroy Minton Confirmation, (RE 10/03/01) ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER SHERYLL JAMES August 30, 2001 October 4, 2001 35 days
Ballou Senior High School FM-200109824 01 10/9/01 BALLOU SUBLEVEL BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. BUSTED 2" FWS LINE (PIPE). REPLACE 10 FT. 2" OF BLACK PIPING ON THE FEEDWATER SUPPLY LINE THAT CONNECTS TO THE AIR-SEPERATOR AND THE EXPANSION- TANK. NOTE: THIS BUSTED SUPPLY LINE WILL EFFECT THE COOLING PUMPS AND CENTRAVAC CHILLER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/26/01. HORNE ENG. - SAM EBRAHIM May 9, 2001 October 9, 2001 153 days
Walker-Jones EC FM-200121148 01 10/9/01 (WALKER-JONES) ASBESTOS ASSESSMENT REQ. OUTSIDE 1ST STREET/ BOILER ROOM ENTRANCE WINDOW GUARD NEEDS WELDING DUE TO BREAK-IN THRU WINDOW LEADING TO BOILER ROOM. EMERGENCY!! SAM TAYLOR - SECURITY DUTY.. October 9, 2001 October 9, 2001 0 days
Moten Elementary School FM-200120873 01 10/10/01 MOTEN BOILER ROOM REPAIR RUPTURED 3/4" RETURN LINE (NO INSULATION). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/03/01. LEROY MINTON - SAFETY (202)576-6691 October 2, 2001 October 10, 2001 8 days
Woodson High School FM-200112726 01 10/11/01 H.D. WOODS BOILER ROOM REPAIR INOPERABLE AC CHILLERS #1 AND 2. UNIT FREQUENTLY SHUTS OFF WHILE UNDER LOAD. WP-200108920 June 7, 2001 October 11, 2001 126 days
Coolidge High School FM-200120020 01 10/11/01 COOLIDGE BOILER ROOM REPLACE MANHOLE COVER ON STREAM AND MUD DRUM. September 18, 2001 October 11, 2001 23 days
Woodson High School FM-200116953 01 10/11/01 WOODSON, H.D. BOILER ROOM (1) ASBESTOS ASSESSMENT REQUIRED (2) REPAIR TWO DUNHAM BUSH CHILLERS. CODE A-CLEAR FOR REPAIR BY HORME ENG. 8/14/01. (CEB) ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER EDWARD RODRIGUEZ August 8, 2001 October 11, 2001 64 days
Woodson High School FM-200109273 01 10/11/01 H.D. WOODSON BOILER ROOM REPAIR AIR COMPRESSOR #1 WITH DEFECTIVE PULLEY. WP-200108920 April 30, 2001 October 11, 2001 164 days
Bancroft Elementary School FM-200120640 01 10/11/01 BANCROFT ROOF TOP BOILER/AIR HANDLER ROOM R/R TWO FAULTY AIR HANDLER FAN MOTORS. ONE MOTOR BEARING MAKES LOUD NOISE AND OTHER MOTOR IS LOCKED UP. CENTURY TYPE - SC, PART #8-331262-03, HP 2.0, RPM 1725, AMP 6.6, VOLT 200/208, PART #6-332795-21, HP 3.0, RPM 1760, AMP 10.6, VOLT 200/208. WP-200108636 September 27, 2001 October 11, 2001 14 days
Woodson High School FM-200100915 1/11/01 10/11/01 WOODSON, H.D. BOILER ROOM REPAIR #1 & 2 BOILER FEED PUMPS IN THE HEATING PLANT, AND CONTROLS TO BOILER FEED PUMPS. BOILER FEED PUMPS LEAKING AND HAVE TO CONSTANTLY HAND FEED #1 & 2 BOILERS. HC-20000388 January 11, 2001 October 11, 2001 273 days
Meyer Elementary School FM-200120609 01 10/11/01 MEYER BOILER ROOM REPLACE WATER REGULATOR ON BOILER #1- BELL & GOSSETT REDUCING VALVE -3/4 INCH, M# 12, SET 12 LBS. H 68. September 27, 2001 October 11, 2001 14 days
Ludlow-Taylor ES FM-200121372 /01 10/11/01 LUDLOW TAYLOR BOILER ROOM START #2 BURNER CUTS OFF ON MAIN FLAME FAILURE. WP-200108677 October 11, 2001 October 11, 2001 0 days
Gibbs Elementary School FM-200121369 /01 10/11/01 GIBBS BOILER ROOM START #1 AND #2 BURNERS WILL NOT START. WP-200108674 October 11, 2001 October 11, 2001 0 days
John Burroughs ES FM-200118871 01 10/11/01 BURROUGHS BOILER ROOM REPLACE DEFECTIVE COUPLING FOR COND. RET. PUMP AND MOTOR #1. WP-200108718 August 30, 2001 October 11, 2001 42 days
Cardozo High School FM-200120672 01 10/11/01 CARDOZO BOILER ROOM REPAIR BOILER #1 BURNER KEEP GOING OFF ON PILOT FLAME FAILURE. IC-BURNER URGENT-ONLY BOILER #1 ABLE TO BE USED, #2 BOILER HAS LEAKING TUBES, #3 BOILER NEED TO BE INSPECTED FROM CLEANING. VERY URGENT. September 28, 2001 October 11, 2001 13 days
Cardozo High School FM-200121473 /01 10/12/01 CARDOZO BOILER ROOM REPLACE AUTOMATIC WATER FEEDERS - LOW WATER CUT OFF- MCDONNELL & MILLER BOILER CONTROL M#51, MAX. BOILER PRESSURE 35 PSI BOILERS #1, #2, #3. October 11, 2001 October 12, 2001 1 day
Hine JHS FM-200121368 /01 10/12/01 HINE BOILER ROOM START #1,#2 AND #3 BURNER WILL NOT START. WP-200108863 October 11, 2001 October 12, 2001 1 day
Hine JHS FM-200121371 /01 10/12/01 (HINE) !!EMERGENCY!! KITCHEN/BOILER ROOM: NO ELECTRICAL POWER TO HOT WATER HEATER. October 11, 2001 October 12, 2001 1 day
Takoma Educational Center FM-200121445 /01 10/12/01 TAKOMA BOILER ROOM REPLACE REDUCING REGULATOR VALVE ON REDUCING STATION ON PNEUMATIC SYSTEM FOR BUILDING SENDING TOO MUCH AIR THROUGH REEP POPING RELIEF VALVE MAY DAMAGE RENTALS FOR BUILDING. NEED WORK COMPLETED TO CHANGE OVER SYSTEM FOR HEAT. October 11, 2001 October 12, 2001 1 day
Walker-Jones EC FM-200121149 01 10/12/01 (WALKER-JONES) ASBESTOS ASSESSMENT REQ. GROUND FLOOR/ BOILER ROOM WINDOW WINDOW IN BOILER ROOM NEEDS REPLACING AND REGLAZING DUE TO BREAK-IN. EMERGENCY !!! SAM TAYLOR- SECURITY DUTY.. October 9, 2001 October 12, 2001 3 days
Deal Junior High School FM-200108853 01 10/15/01 DEAL 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. April 20, 2001 October 15, 2001 178 days
Miner Elementary FM-200121510 /01 10/15/01 MINER BOILER ROOM REPAIR OR REPLACE FLOAT SWITCH ON CONDENSATE RETURN TANK. TANK IS ALSO DUMPING WATER ON ELECTRICAL WIRES. October 12, 2001 October 15, 2001 3 days
Ross Elementary School FM-200121118 01 10/15/01 (ROSS) EMERGENCY !!!! OUTSIDE DRAIN/SOUTH SIDE: UNSTOP DRAIN OUTSIDE BOILER ROOM DOOR. DRAIN IS STOPPED UP, AND RISING HIGHER FROM A WATER HOSE THAT WAS USED THIS MORNING. IN THE EVENT OF A HARD RAIN, WATER WILL BE FLOOD- THROUGH THE BOILER ROOM DOOR. October 5, 2001 October 15, 2001 10 days
Bowen Elementary School FM-200120469 01 10/15/01 A.BOWEN BOILER ROOM 1.REPLACE OR REPAIR BOILER #1 RETURN PUMP, IT WILL NOT PUT WATER BACK INTO BOILER. WP-200108694 September 25, 2001 October 15, 2001 20 days
Roosevelt High School FM-200121578 /01 10/15/01 ROOSEVELT EMERGENCY!!! SWITCH GEAR ROOM 1) CAN NOT RE-SET SWITCH/ CAN NOT RUN BOILER FOR STEAM SO KITCHEN STAFF CAN COOK FOOD. October 15, 2001 October 15, 2001 0 days
Garnet-Patterson MS FM-200121579 /01 10/15/01 G.PATTERSON BOILER ROOM FABRICATE BOILER DOOR FOR BOILER #2 AND #3. October 15, 2001 October 15, 2001 0 days
Ballou Senior High School FM-200115294 01 10/16/01 BALLOU BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE FRONT MORRISON TUBER BURNER HUB ON #4 BOILER. CLEAVER BROOKS PACKAGED BOILER. BOILER INFO: CLEAVER BROOKS MOD. #760-125A, SER. #L47171. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/27/01 BY HORNE ENGINEER: EDWARD RODRIGUEZ July 16, 2001 October 16, 2001 92 days
Woodson High School FM-200121594 /01 10/16/01 WOODSON BOILER ROOM ASBESTOS ASSESSMENT REQUIRED REMOVE HAND HOLE COVER TO BOILER #1 October 15, 2001 October 16, 2001 1 day
Cardozo High School FM-200112302 01 10/16/01 CARDOZO BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. FURNISH AND INSTALL PIPING TO SAFETY RELIEF VALVES AND WITH PULL CHAINS. EACH BOILER HAS 3 (THREE) SAFETY VALVES AND THERE ARE 3 -BOILERS. VALVE SIZE APPROX. 4-1/4" - 4-1/2", TO FLOOR 16 FT. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/01/01. HORNE ENGINEERS - STEPHEN CALDWELL June 4, 2001 October 16, 2001 134 days
Cardozo High School FM-200121604 /01 10/16/01 CARDOZO BOILER ROOM REPLACE #2 SWITCH ON LOW WATER CUT OFF TO BOILER #1 October 15, 2001 October 16, 2001 1 day
Johnson JHS FM-200121577 /01 10/17/01 JOHNSON BOILER ROOM BOILER # 1 CALIBRATE BURNER INOPERABLE FIRING CYCLE October 15, 2001 October 17, 2001 2 days
Amidon Elementary School FM-200121800 /01 10/17/01 AMIDON BOILER ROOM BOILER # 1 REPAIR BURNER PROGRAMMER READING: BOILER IN HOLD PURGE D-8 LIMIT OPEN NO HEAT October 17, 2001 October 17, 2001 0 days
Orr Elementary School FM-200121816 /01 10/17/01 ORR BOILER ROOM REPAIR BOILERS #1 AND #2. WILL NOT START. October 17, 2001 October 17, 2001 0 days
Kimball Elementary School FM-200121682 /01 10/17/01 (KIMBALL) !!EMERGENCY!! BASEMENT LEVEL BOILER ROOM: SECURE MISSING PLYWOOD OVER MISSING WINDOW PANES. APPEARS THAT PERSON OR PERSON(S) UNKNOWN ATTEMPTED TO ENTER FROM THE OUTSIDE NEAR STAIRWAY. October 15, 2001 October 17, 2001 2 days
Garnet-Patterson MS FM-200121621 /01 10/17/01 GARNETT PATTERSON START BURNER ON #2 BOILER October 15, 2001 October 17, 2001 2 days
Young Elementary School FM-200119647 01 10/18/01 YOUNG BOILER ROOM RECHARGE A/C CHILLER. REPLACE REPTURE DISK. September 11, 2001 October 18, 2001 37 days
Terrell Mc ES FM-200120256 01 10/18/01 M.C. TERRELL BOILER ROOM A/C CHILLER NEEDS REFRIGERANT. WP-200108841 September 21, 2001 October 18, 2001 27 days
Young Elementary School FM-200121642 /01 10/19/01 C.YOUNG BOILER ROOM REPLACE PANIC BAR ON REAR DOOR OF BOILER ROOM PANIC BAR WILL NOT RELEASE ON ITS OWN. October 17, 2001 October 19, 2001 2 days
Randle-Highlands ES FM-200121936 /01 10/19/01 RANDLE-HIGHLANDS BOILER ROOM BOILER#1 REPAIR GAS LEAK ON GAS TRAIN October 19, 2001 October 19, 2001 0 days
Rudolph Elementary School FM-200121434 /01 10/22/01 RE-VISIT OR RETURN TO RUDOLPH BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE DEFECTIVE 3" ISOLATION VALVE ON 3" LINE BETWEEN BOILER #1 & #2. VALVE IS NOT HOLDING CAUSING WATER FROM BOILER #2 TO ENTER BOILER #1, ENGINEER CAN NOT MAINTAIN PROPER WATER LEVEL. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/15/01. HORNE ENGINEERING - EDWARD RODRIGUEZ (RG) CONNECT PERSON MR. LOPEZ 202-345-1558 MR. BRADLEY 202-438-7437 October 11, 2001 October 22, 2001 11 days
Bruce-Monroe Elementary School FM-200122112 /01 10/22/01 BRUCE-MONROE BIOLER ROOM REPAIR OR REPLACE FIRING SEQUENCE CONTROLLER FOR NUMBER TWO BOILER. BOILER STARTING SEQUENCE FAILS FOR MISS FIRE LOCKOUT. October 22, 2001 October 22, 2001 0 days
Plummer Elementary School FM-200114708 01 10/22/01 PLUMMER BASEMENT BOILER ROOM 1) DRAIN IS BACKING UP CAUSING FLOODING EMERGENCY!! July 5, 2001 October 22, 2001 109 days
Merritt Middle School FM-200108725 01 10/23/01 MERRITT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. PERFORM ON GOING REPAIRS TO HVAC EQUIPMENT SUCH AS: BURNERS, BOILER AUXILARY EQUIPMENT, CONDENSATE/CIRCULATING PUMPS, PNUEMATIC CONTROLS, COMPRESSORS, CHILLERS, ROOFTOP AC UNITS, WINDOW AC UNITS, SUMP PUMPS, AIR HANDLER UNITS, RETURN AIR FANS, DOMESTIC HOT WATER HEATERS, EXHAUST FANS, UNIT VENTILATORS, ELECTRIC HEATERS, COOLING TOWERS AND UNSTOP DRAINS. April 19, 2001 October 23, 2001 187 days
Johnson JHS FM-200119571 01 10/23/01 JOHNSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REMOVE TSI FROM AROUND BOILERS REPAIR TO BE MADE TO LEAKING MUD LEG ON FRONT RIGHT SIDE OF BOILER #3. CONTRACTOR: IT GROUP CHARLES CRENSHAW 202-437-5673 Code A - Asbsetos Abated on 9/25/01 per Leroy Minton Confirmation, (RE 10/03/01) September 10, 2001 October 23, 2001 43 days
Shaw JHS FM-200100049 01 10/24/01 SHAW BOILER ROOM 1. REPLACE RUPTURED DIES TO ROBERT SHAW PNEUMATIC CONTROL ON STEAM LINE TO CONVERTOR. 2. REPLACE ROBERT SHAW PNEUMATIC CONTROL VALVE ON STEAM LINE CONVERTOR. HC-20000948 January 7, 2001 October 24, 2001 290 days
Hart Middle School FM-200120637 01 10/24/01 HART BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE BOILER #1, #2 AND #3 WRAPED DRAFT AND FIRE DOORS ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/16/01 HORNE ENGINEER STEPHEN CALDWELL September 27, 2001 October 24, 2001 27 days
Turner Elementary School FM-200100894 01 10/24/01 TURNER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. EJECTOR PUMP IS NOT WORKING CAUSING WATER TO BACK UP ON TO BOILER ROOM FLOOR. HC-20000052 ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/10/01. MR. RICHARD GIBSON - SAFETY (202)437-5937 January 11, 2001 October 24, 2001 286 days
Woodson High School FM-200120891 01 10/24/01 H.D. WOODSON BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2. REPAIR REFACTORY TO DOORS OF #1 AND #2 BOILERS ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/03/01. HORNE ENGINEERING - BILL CAMPION (RG) October 3, 2001 October 24, 2001 21 days
Drew Elementary School FM-200100852 01 10/24/01 DREW BOILER ROOM REPLACE TWO PRESSURE GAUGES LOCATED ON THE CIRCULATING PIPE LINE. SIZE: 5" X 5", 1/4" PIPE. HC-20000959 January 11, 2001 October 24, 2001 286 days
Garfield ES FM-200104586 01 10/24/01 GARFIELD BOILER ROOM REPAIR STEAM CONVERTER TO AUDITORIUM AND LIBRARY IN BOILER ROOM. ACTUATOR NOT MODULATING HEAT IN THESE AREAS. March 1, 2001 October 24, 2001 237 days
Garfield ES FM-200103967 01 10/24/01 Garfield Boiler Room Repair/Replace float assembly on condensate tank. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/18/01. February 21, 2001 October 24, 2001 245 days
Kimball Elementary School FM-200122409 /01 10/25/01 KIMBALL BOILER ROOM REPAIR /REPLACE CONDENSATE CONTROL SYSTEM ON VACUUM TANK. MOTORS CONTANTLY RUN. October 25, 2001 October 25, 2001 0 days
Shaw JHS FM-200120874 01 10/25/01 SHAW BOILER ROOM 1. ASBESTOS ASSESSMENT IS REQUIRED. 2. REPAIR REFRACTORY IN #4 BOILER FIRE BOX (WALLS). October 2, 2001 October 25, 2001 23 days
Bowen Elementary School FM-200121805 /01 10/25/01 BOWEN BOILER ROOM CHECK BOILER #2,WILL NOT COME ON. GOES INTO FLAME FAILURE. October 17, 2001 October 25, 2001 8 days
Bowen Elementary School FM-200121911 /01 10/25/01 BOWEN,A BOILER ROOM BOILER NO.#1AND #2 IS IN FLAME FAILURE, LOCKOUT NO.#19 NO HEAT!!!! WP-200108694 October 18, 2001 October 25, 2001 7 days
Bowen Elementary School FM-200122109 /01 10/25/01 BOWEN BOILER ROOM REPAIR BURNER #1, IT CUTS OFF IN FLAME FAILURE. WP-200108694 October 22, 2001 October 25, 2001 3 days
Sousa Middle School FM-200122410 /01 10/25/01 KIMBALL BOILER ROOM REPAIR /REPLACE CONDENSATE CONTROL SYSTEM ON VACUUM TANK. MOTORS CONTANTLY RUN. October 25, 2001 October 25, 2001 0 days
Garnet-Patterson MS FM-200122076 /01 10/26/01 GARNETT-PATTERSON BOILER ROOM REPLACE PROGRAMMER CLIP ON #3 BOILER. WP-200108858 October 22, 2001 October 26, 2001 4 days
Davis Elementary School FM-200122140 /01 10/26/01 DAVIS BOILER ROOM REPAIR OR REPLACE LOW WATER CUTOFF ON BOILER#1, CUTOFF IS LEAKING BADLY. MFR, MCDONNEL MILLER #51 ASBESTOS CODE-A CLEAR FOR REPAIR BY HORNE ENGINEER : SHARON VOSS 10/24/01 (CEB) October 23, 2001 October 26, 2001 3 days
Cardozo High School FM-200121865 /01 10/26/01 (CARDOZO) !!!EMERGENCY!!! SUB-BASEMENT BOILER ROOM/FAN ROOM: FLOOR DRAIN BACKING UP. WHEN RUNNING WATER IN THE KITCHEN, WATER RUNS DOWN AND BACK-UP IN THE FAN ROOM. MS. SKELTON: 3:57 P.M. October 17, 2001 October 26, 2001 9 days
Draper Elementary School FM-200115368 01 10/27/01 DRAPER BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE (4) 2" TUBES IN BOILER #1 (LEAKING). CODE A CLEAR FOR REPAIR AS OF 7/25/01. July 18, 2001 October 27, 2001 101 days
Ballou Senior High School FM-200119046 01 10/30/01 (BALLOU) 1. ASBESTOS ASSESSMENT REQUIRED. ALLOU 1ST FL. NORTH HALLWAY PANEL H1 REPLACE (1) BROKEN 20 AMP. CIRCUIT BREAKER AND INCREASE THE REPLACMENT BREAKER WITH (1) ONE 40 AMP. NOTE: THIS BREAKER CONTROLS THE BOILER ROOM LIGHTING #12. INFO: PANEL H-1 FEDERAL PACIFIC MOD. 881185, VOL. 265/460, TYPE-NHDP PH. 3. Requester Phone: 645-3385 Requestor Phone: 645-3385 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/01/01. HORNE ENGINEERING - ROGER KAGER (RG) August 23, 2001 October 30, 2001 68 days
Jefferson JHS FM-200120532 01 10/31/01 JEFFERSON BOILER ROOM REPAIR BURNERS ON BOILERS #1,#2 AND#3. ASBESTOS CODE-A CLEAR FOR REPAIR BY HORNE ENGINEER : ROGER KAGER 10/24/01 (CEB) September 26, 2001 October 31, 2001 35 days
Stevens Elementary School FM-200120541 /01 10/31/01 STEVENS BASEMENT BOILER ROOM FURNISH LOCK FOR BOILER ROOM DOOR TO KEEP THE KIDS OUT OF THE BOILER ROOM. A LOCK THAT OPENS FROM INSIDE AND OUTSIDE. IT IS A SAFETY HAZARDS. EMERGENCY. October 29, 2001 October 31, 2001 2 days
Ballou Senior High School FM-200114630 01 11/1/01 BALLOU BOILER ROOM REPAIR TRANE CENTRIFIGAL A/C CHILLER. NOTE: WILL NOT MAINTAIN OIL PRESSURE, WILL NOT RUN OVERNIGHT. INFORMATION: TRANE #DCV-3A-C2-D-3 SERIAL # 11057 WP-200108521 July 3, 2001 November 1, 2001 121 days
Amidon Elementary School FM-200122585 /01 11/1/01 (AMIDON) !!!EMERGENCY!!! BOILER ROOM: REPAIR BURNER #1, CUTS OUT ON AIR/COM. (NO HEAT) WP-200108815. October 30, 2001 November 1, 2001 2 days
Shaw JHS FM-200122758 01 11/1/01 SHAW BOILER ROOM REPAIR #3 BURNER, CUTS OFF ON HIGH PRESSURE SWITCH. WP-200108884 November 1, 2001 November 1, 2001 0 days
Brent Elementary School FM-200120461 01 11/1/01 BRENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE 10 FEET OF 1 INCH BLACK PIPE FEED WATER LINE TO HOUSE PUMP ALSO NEED GATE VALVE. (LINE IS LEAKING AND VALVE IS NOT HOLDING.) POC CARNAL BRADLEY 202 438 7437 CELL PHONE ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/28/01. HORNE ENGINEERING - ROGER KAGER (RG) September 25, 2001 November 1, 2001 37 days
Bruce-Monroe Elementary School FM-200122081 /01 11/2/01 BRUCE-MONROE OLD BUILDING BIOLER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPAIR LEAKING RETURN LINE ON BOILER #3 HEATING SYSTEM. RE: NO HEAT ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/31/01 HORNE ENGINEER: SHERYLL JAMES October 22, 2001 November 2, 2001 11 days
Aiton Elementary School FM-200121765 /01 11/2/01 AITON BOILER ROOM CHECK PROBLEM WITH BOILER. BOILER #1 CONTINUES TO GO INTO FLAME FAILURE. BOILER #2 WILL NOT FIRE OFF AFTER GOING THROUGH PURGE. WP-200108665 October 16, 2001 November 2, 2001 17 days
Raymond Elementary School FM-200122488 01 11/3/01 RAYMOND 1ST FL. OLD BOILER ROOM PROVIDE INDIVIDUAL KEY TO LOCK ON DOOR TO OLD BOILER ROOM. TWO KEYS ARE NEEDED FOR ROVING ENGINEER TO GAIN ENTRANCE TO THAT AREA. November 1, 2001 November 3, 2001 2 days
Rudolph Elementary School FM-200121435 /01 11/3/01 RUDOLPH BOILER ROOM TSI, REMOVAL FROM BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR LEAK ON REAR OF BOILER #1. ASBESTOS CODE C ON 10/19/01 BY HORNE ENGINEER : EDWARD RODRIGUEZ ENVIROBATE (IT GROUP) 703-461-6848 ASBESTOS CODE A - ABATED ON 10-26-01. (LM) PER LEROY MINTONS CONFIRMATION SAFETY OFFICE (202) 576-8962. October 11, 2001 November 3, 2001 23 days
Randle-Highlands ES FM-200122764 01 11/3/01 RANDLE HIGHLAND BOILER ROOM REPLACE MCDONNEL 51 BOILER WATER CONTROL, WILL NOT CUT BOILER OFF. WP-200108657 November 1, 2001 November 3, 2001 2 days
Hart Middle School FM-200122498 /01 11/3/01 HART BOILER ROOM REPAIR #3 BOILER, BURNER CUT OFF ON FLAME FAILURE. WP-200108862 HOT October 29, 2001 November 3, 2001 5 days
Garnet-Patterson MS FM-200122331 /01 11/5/01 GARNETT-PATTERSON BOILER ROOM ADJUST BURNER ON #3 BOILER. BURNER GOES INTO FLAME FAILURE WHEN RUNNING IN HIGH FIRE (IT RUNS OK IN LOW FIRE). WP-200108858 October 25, 2001 November 5, 2001 11 days
Francis Junior High School FM-200122869 01 11/6/01 FRANCIS !!! EMERGENCY!!! EXTERIOR BOILER ROOM 1) SECURE OPENING WHERE VENTILATION LOUVERS ARE TORN FROM FRAME. POSSIBLE ATTEMPTED BREAK-IN. EMERGENCY PERMIT - AA - MUTAKABBIR November 5, 2001 November 6, 2001 1 day
Woodson High School FM-200120968 01 11/6/01 H.D. WOODSON HEATING PLANT, BOILER ROOM REMOVE ELECTRICAL CONDUIT FROM FLOOR AND RELOCATE CONDUIT AND ELECTRICAL LINES TO BURNER CONTROL FOR #(2) BOILER. D.C. BOILER INSPECTOR FAILED #(2) BOILER BECAUSE OF HAZARDOUS CONDITIONS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/04/01. HORNE ENGINEERING - ROGER KAGER (RG) October 3, 2001 November 6, 2001 34 days
Moten Elementary School FM-200123078 01 11/7/01 MOTEN BOILER ROOM REPAIR BURNED OUT WIRING IN STARTER OPERATING PUMP. November 7, 2001 November 7, 2001 0 days
Hart Middle School FM-200123016 01 11/7/01 HART BOILER ROOM CHECK BOILER #3, OUT ON FLAME FAILURE. November 7, 2001 November 7, 2001 0 days
Smothers ES FM-200121310 01 11/7/01 SMOTHERS FRONT DOOR/BOILER RM. ENTRANCE. KEY AND SUPPLY ROVING ENGINEER WITH KEY TO GAIN ACCESS TO BOILER ROOM. KEYS ARE NEEDED/ESSENTIAL FOR HEATING SCHOOL, AND CHECKING PLANT OPERATION DURING HEATING SEASON. NOTE: BOILERS CAN NOT BE TURNED ON BEFORE FACILITY OPENS W/O KEYS FOR ACCESS. November 5, 2001 November 7, 2001 2 days
River Terrace ES FM-200121312 01 11/7/01 RIVER TERRACE BOILER RM. SUPPLY ROVING ENGINEER WITH KEY TO GAIN ACCESS TO BOILER ROOM. KEYS ARE ESSENTIAL FOR HEATING SCHOOL PLANT AND CHECKING OPERATION DURING HEATING SEASON. NOTE: BOILERS CAN NOT BE TURNED ON BEFORE FACILITY OPENS W/O KEYS FOR ACCESS. November 5, 2001 November 7, 2001 2 days
Marshall Educational Center FM-200100041 01 11/8/01 MARSHALL BOILER ROOM: PNEUMATIC CONTROL ON THE MAN HEADER IS LEAKING PROFUSELY, NEEDS TO BE TIGHTENED AS SOON AS POSSIBLE. HC-20000663 January 7, 2001 November 8, 2001 305 days
Shaw JHS FM-200122812 01 11/8/01 SHAW BOILER ROOM REPAIR BURNER #4. DOWN FLAME AMPERFIER. WP-200108884 November 2, 2001 November 8, 2001 6 days
Terrell Mc ES FM-200121879 /01 11/8/01 M.C. TERRELL BOILER ROOM CALIBRATE BURNERS ON BOILERS 1 & 2 CONTRACTOR (ACI) JESSIE POOLE PROJECT MANAGER POC CURTIS EMERSON (DCPS) October 18, 2001 November 8, 2001 21 days
Wilkinson ES FM-200113488 01 11/8/01 WILKINSON BOILER ROOM REPLACE LOCK ON STORAGE ROOM DOOR IN BOILER ROOM. November 6, 2001 November 8, 2001 2 days
Deal Junior High School FM-200122059 /01 11/8/01 DEAL BOILER ROOM REPLACE MODULATING MOTOR ON BURNER FOR #3 BOILER. WP-200108853 October 22, 2001 November 8, 2001 17 days
Marshall Educational Center FM-200117935 01 11/8/01 MARSHALL BOILER ROOM REPAIR CHILLER. CHILLER IS DOWN. ONCE CHILLER STARTS, BREAKER SHUTS DOWN. WP-200108895 August 21, 2001 November 8, 2001 79 days
Shaw JHS FM-200123086 01 11/8/01 SHAW BOILER ROOM CHECK BOILER #3, GOING OFF ON FLAME FAILURE. November 8, 2001 November 8, 2001 0 days
Young Elementary School FM-200104193 01 11/9/01 YOUNG BASEMENT BOILER ROOM INSTALL REFRIGERANT MONITOR FOR R-123 CHILLER. NO MONITOR CREATES SAFETY HAZARD. February 23, 2001 November 9, 2001 259 days
Moten Elementary School FM-200123145 01 11/9/01 MOTEN BOILER ROOM REPLACE CUPLINK ON PUMP #1. November 9, 2001 November 9, 2001 0 days
Aiton Elementary School FM-200123019 01 11/9/01 AITON BOILER ROOM REPAIR AND CORRECT PROBLEM WITH BOILERS #1 AND #2. BOILERS GOES INTO FLAME FAILURE AFTER GOING OFF ON TEMPERATURE. November 7, 2001 November 9, 2001 2 days
Jefferson JHS FM-200122866 01 11/10/01 JEFFERSON BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE 3 LEAKING TUBES (2") IN BOILER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. HORNE ENGINEERING - BIPIN NANAVATY(RG) November 5, 2001 November 10, 2001 5 days
Terrell Mc ES FM-200123085 01 11/10/01 TERRELL,M.C. BOILER ROOM 1.ASSIST CONTRACTOR WITH BURNER REPAIRS. 2. BALANCE HEATING HOT WATER SYSTEM 3. CHECK FACITITY FOR OVERALL HEATING November 8, 2001 November 10, 2001 2 days
Ferebee-Hope Elementary School FM-200122682 01 11/11/01 (FEREBEE-HOPE) BASEMENT/OUTSIDE EXIT FROM BOILER ROOM: REPAIR OR REPLACE KNOB AND KEY LOCK AND FURNISH THREE (3) KEYS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/02/01. LEROY MINTON- SAFETY (202)576-6691(RG) November 9, 2001 November 11, 2001 2 days
Jessie LaSalle Elementary FM-200123027 01 11/11/01 (LASALLE) BASEMENT/ 3 AND MS. WILSONS OFFICE KEYS NEED REPLACING AND LOCKS NEED CHANGING IN ROOM #3. ALSO NEED KEYS TO MAIN DOOR, AND KEYS FOR BOILER ROOM. November 9, 2001 November 11, 2001 2 days
Spingarn High School FM-200110975 01 11/13/01 SPINGARN OUTSIDE OF BOILER ROOM 1) REPAIR EXTERIOR LIGHT DAMAGED BY VANDALS May 24, 2001 November 13, 2001 173 days
Watkins Elementary School FM-200120868 01 11/13/01 WATKINS BOILER ROOM REPAIR #2 BURNER CUT OFF FLAME AFTER TEMPERATURE IS REACHED WP-200108661 October 2, 2001 November 13, 2001 42 days
Smothers ES FM-200119390 01 11/14/01 SMOTHER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. INSULATE 30 FT OF 1-1/2 PIPE IN TUNNEL AREA IN BOILER ROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/04/01. HORNE ENGINEERING - EDWARD RODRIGUEZ September 7, 2001 November 14, 2001 68 days
River Terrace ES FM-200123067 01 11/15/01 RIVER TERRACE BOILER ROOM CALIBRATE FLAME FOR BURNER #1 DUE TO OVERFIRING. November 7, 2001 November 15, 2001 8 days
Shaw JHS FM-200122062 /01 11/15/01 SHAW BOILER ROOM REPLACE TEMPERATURE PILOT VALVE ON STEAM LINE TO HOT WATER HEATER. WP-200108884 October 22, 2001 November 15, 2001 24 days
Bruce-Monroe Elementary School FM-200122445 /01 11/15/01 BRUCE-MONROE OLD BLDG. BOILER RM. REMOVE PORTABLE POWER SOURCE AND REINSTALL COVER PANEL FOR ELECTRICAL BREAKER CABINET. Requester Phone: 541-6254 Requestor Phone: 541-6254 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/05/01 LEORY MINTON - SAFETY (202)576-6691 (RG) October 22, 2001 November 15, 2001 24 days
Noyes Elementary School FM-200123414 /01 11/15/01 NOYES BOILER ROOM SALVAGE AIR COMPRESSION AND REMOVE FROM FACILITY. November 15, 2001 November 15, 2001 0 days
Backus Middle School FM-200122698 /01 11/16/01 BACKUS BOILER ROOM REPAIR BURNER ON #2 BOILER. WP-200108850 October 31, 2001 November 16, 2001 16 days
Backus Middle School FM-200122864 01 11/16/01 BACKUS BOILER ROOM REPAIR OR REPLACE MOTOR TO BOILER #2. MOTOR IS SMOKING. November 5, 2001 November 16, 2001 11 days
Payne Elementary School FM-200123440 /01 11/17/01 PAYNE BOILER ROOM REPAIR OR REPLACE AIR COMPRESSOR. WP-200108680 November 15, 2001 November 17, 2001 2 days
Backus Middle School FM-200120911 01 11/17/01 BACKUS BOILER ROOM MAKE ELECTRICAL REPAIRS TO SERVICE PANNEL FOR #3 BOILER WP-200108850 October 3, 2001 November 17, 2001 45 days
Terrell Mc ES FM-200123433 /01 11/17/01 TERRELL,M.C. BOILER ROOM REPAIR PNEUMATIC LEAK IN CONTROL BOX IN UPPER LEVEL IN BOILER. November 15, 2001 November 17, 2001 2 days
Hearst Elementary School FM-200122111 /01 11/19/01 HEARST !!EMERGENCY!! BOILER ROOM NO LIGHTS IN BOILER ROOM ISOLATE EMERGENCY!!!! October 22, 2001 November 19, 2001 28 days
Terrell Mc ES FM-200122867 01 11/19/01 M.C. TERRELL BOILER ROOM 1) ASBESTOS ASSESSMENT IS REQUIRED 2) BOILER#1 REPAIR TUBE LEAK ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-07-01 HORNE ENGINEER : BIPIN NANAVATY November 5, 2001 November 19, 2001 14 days
Peabody Elementary School FM-200121395 /01 11/19/01 PEABODY BOILER ROOM REPLACE MCDONNELL MILLER LOW WATER CUT OFF ON #1 BOILER WP-200108656 October 11, 2001 November 19, 2001 39 days
Gibbs Elementary School FM-200111949 01 11/20/01 GIBBS BASEMENT BOILER ROOM REPAIR/REPLACE SEWER INJECTOR BEARER, BALL FLOAT AND PUSH ROD. DEFECTIVE AND MISSING PARTS. MAKE: CHICAGO, SER. # 7H 12831, TYPE VOSNSO-4, TDH-20, GPM 75. WP-200108674 June 1, 2001 November 20, 2001 172 days
Gage-Eckington ES FM-200119889 01 11/20/01 GAGE -ECKINGTON BOILER ROOM 1) TROUBLE SHOOT BURNER IN BOILER. ACI, INC JESSE POOLE- 301-779-3400 September 17, 2001 November 20, 2001 64 days
Shaw JHS FM-200109245 01 11/20/01 SHAW BOILER ROOM TROUBLE SHOOT AND REPAIR AC CHILLER, UNIT READS HI HEAD PREASSURE, UNIT HAS BEEN PURGED AND STRAINERS CLEANED. WP-200108884 April 30, 2001 November 20, 2001 204 days
Shaw JHS FM-200119052 01 11/20/01 SHAW ROOF AND BOILER ROOM COOLING TOWER WILL NOT RUN IN AUTOMATIC. SO CHILLER WILL NOT STAY ON LINE. September 4, 2001 November 20, 2001 77 days
Woodson High School FM-200110612 01 11/21/01 H.D. WOODSON BOILER ROOM REPAIR PNEUMATIC VALVE ON ZONE 1 FOR UPPER CLASSROOM AREA WITH NO AC. WP-200108920 May 18, 2001 November 21, 2001 187 days
Woodson High School FM-200121991 /01 11/23/01 H.D. WOODSON BOILER ROOM MAKE THE NECESSARY REPAIRS TO THE AIR COMPRESSOR, AIR COMPRESSOR TURNS CONTINUOUSLY DOES NOT REACH DESIRED PRESSURE. WILL CAUSE COMPRESSOR TO DAMAGE ITSELF. WP-200108920 October 19, 2001 November 23, 2001 35 days
Leckie Elementary School FM-200122977 01 11/23/01 LECKIE BOILER ROOM PM 1 EACH A/C CHILLER CLEAN CONDENSER TUBE AND CHECK ELECTRICAL CONTROLS. November 6, 2001 November 23, 2001 17 days
Draper Elementary School FM-200119019 01 11/23/01 DRAPER BOILER ROOM REPAIR OR REPLACE AIR COMPRESSOR. QUINCY COMPRESSOR-MODEL#A-416, SIZE 2 1/2 X 2 1/2 WP-200108654 September 4, 2001 November 23, 2001 80 days
Terrell Mc ES FM-200121873 /01 11/23/01 TERRELL,M.C. BOILER ROOM AIR COMPRESSER NEEDS A NEW STARTER SWITCH. TYPE: ALLEN &BRADLEY CO. AC AUTOMATIC STARTER CAT.NO 709-TAH SERIES L TYPE 2 BULLETIN 709 SIZE 00 208V-60CY 69A113 October 18, 2001 November 23, 2001 36 days
Brookland Elementary FM-200120473 01 11/23/01 BROOKLAND BOILER ROOM RESTART MULTI STACK UNIT CONDENSER PUMP WILL NOT PULL IN. WP-200108667 September 25, 2001 November 23, 2001 59 days
Woodson High School FM-200121948 /01 11/23/01 H.D. WOODSON BOILER ROOM MAKE THE NECESSARY REPAIRS TO PNEUMATIC CONTROLS ZONE 5. AIR LEAK CAUSED ZONE 5 TO CLOSE AND CANNOT HEAT GYM OR AUDITORIUM. WP-200108920 October 19, 2001 November 23, 2001 35 days
Raymond Elementary School FM-200116881 01 11/23/01 RAYMOND BOILER ROOM SURVEY AND MAKE NECESSARY REPAIRS TO CORRECT PROBLEM WHICH CAUSES CIRCUIT BREAKER TO TRIP WHEN COOLING TOWER IS IN OPERATION. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-06-01 HORNE ENGINEER : SHERYLL JAMES August 8, 2001 November 23, 2001 107 days
Ferebee-Hope Elementary School FM-200122975 01 11/23/01 FEREBEE HOPE BOILER ROOM PM 2 EACH A/C CHILLERS. CLEAN CONDENSON TUBES AND CHECK ELECTRICAL CONTROLS. November 6, 2001 November 23, 2001 17 days
Burrville Elementary School FM-200117584 01 11/23/01 BURRVILLE BOILER ROOM REPLACE KLOCKNER-MOELLER STARTER CONTROL ON HOT WATERCIRCULATING PUMP #2. LINE VOLT 460, OHASE S, COIL VOLT 120, HP 3, FLC. 4.8 ORDER #147037. WP-200108816 August 16, 2001 November 23, 2001 99 days
Maury Elementary School FM-200121802 /01 11/23/01 MAURY BOILER ROOM REPAIR OR REPLACE CIRCULATING PUMP MAGNETIC STARTER WILL NOT PULL IN. NO HEAT WP-20018895 October 17, 2001 November 23, 2001 37 days
West Elementary School FM-200106567 01 11/26/01 WEST BOILER ROOM REPAIR #1 BOILER. ONCE BOILER GOES THROUGH ITS CYCLE , IT WILL NOT LIGHT OFF. INOPERABLE. March 26, 2001 November 26, 2001 245 days
Seaton Elementary School FM-200123407 /01 11/26/01 SEATON BOILER ROOM REPLACE LOW WATER CUT OFF ON BOILER #1. TYPE: MCDONNELL; MODEL # 63 UNIT HAS A CRACKED HOUSING. November 15, 2001 November 26, 2001 11 days
Browne Junior High School FM-200104663 01 11/26/01 BROWNE BOILER ROOM REPLACE HEATING CIRCULATING PUMP THAT WAS REMOVED BY REPAIR SHOP. INFO TO BE SUPPLIED BY THE SHOP. March 1, 2001 November 26, 2001 270 days
West Elementary School FM-200117091 01 11/26/01 WEST BOILER ROOM REPAIR OR REPLACE OIL PUMP/FILTER TO OIL BURNER ON DOMESTICD HOT WATER HEATER. PUMP INFO: #A2VA-7116, MODEL NO, FILTER INFO: #1A-25A, MODEL NO., MAKE OF FILTER: GENERAL. WP-200108847 August 10, 2001 November 26, 2001 108 days
West Elementary School FM-200105075 01 11/26/01 WEST BOILER ROOM R/R #2 MOTOR TO OIL CIRCULATOR PUMP. NAME LELAND FARADAY MOD #G50978703, TYPE RP, VOLTS 209-220-440, FR G56, PH 3, RPM 1725. MOTOR WILL NOT RUN TO OPERATE OIL CIR. PUMP. ONLY 1 OF 2 OPERATING. March 7, 2001 November 26, 2001 264 days
Bruce-Monroe Elementary School FM-200108876 01 11/27/01 BRUCE MONROE BASEMENT BOILER ROOM REMOVE BULK TRASH ITEMS FROM BOILER ROOM. ITEMS ARE TOO LARGE FOR REGULAR TRASH PICK-UP AND SPECIAL HANDLING IS REQUIRED FOR DISPOSAL Requestor: 698-1750 April 6, 2001 November 27, 2001 235 days
River Terrace ES FM-200123778 /01 11/27/01 RIVER TERRACE BOILER ROOM PERFORM REPAIRS TO CANISTER FILTER ON REFRIGERATED DRYER FOR PNUEMATIC CONTROLS. COMPRESSOR AIR IS ESCAPING FROM FILTERS CONDENSATE DRAIN LINE. November 26, 2001 November 27, 2001 1 day
Ferebee-Hope Elementary School FM-200122122 /01 11/27/01 (FEREBEE-HOPE) ASBESTOS ASSESSMENT REQ. BASEMENT/ BOILER ROOM EXIT STEPS WELDERS: INSTALL AND REPAIR MISSING METAL STEPS (3 STEPS). ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/30/01 HORNE ENGINEER: BILL CAMPION October 22, 2001 November 27, 2001 36 days
Thomas Elementary School FM-200123780 /01 11/27/01 N. THOMAS BOILER ROOM CALIBRATE RESET FOR PNUEMATIC CONTROLS TO PREVENT HEATING SYSTEM FROM OVER HEATING November 26, 2001 November 27, 2001 1 day
Takoma Educational Center FM-200123428 /01 11/28/01 TAKOMA BOILER ROOM REPAIR OR REPLACE BURNER ON BOILER #2. BOILER KEEP GOING OUT ON FLAME FAILURE. November 15, 2001 November 28, 2001 13 days
Thomson Elementary School FM-200116407 01 11/28/01 THOMSOM BASEMENT BULK TRASH NEEDS TO BE REMOVED FROM BOILER ROOM IN THE BASEMENT. FIRE CODE VIOLATION August 1, 2001 November 28, 2001 119 days
Davis Elementary School FM-200123756 /01 11/28/01 DAVIS BOILER ROOM BOILER #2 WILL NOT START, WILL NOT COMPLETE PURGE. November 26, 2001 November 28, 2001 2 days
Terrell Mc ES FM-200123803 /01 11/28/01 M.C. TERRELL BOILER ROOM REPLACE 1" REGULATOR VALVE ON EXPANSION TANK. 25 HUB. STD. RANGE 25 - 75 PSI SET 50 PSI. November 26, 2001 November 28, 2001 2 days
Hart Middle School FM-200123376 /01 11/29/01 HART BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED. 2.REPAIR OR REPLACE RUPTURED EXPANISON TANK. 3.REPAIR OR REPLACE RUPTURED 1 1/2 " LINE TO EXPANSION TANK. 4. POC: WARREN YOUMANS 202 345-3331/CODE A -CLEARED FOR REPAIR BY HORNE ENGINEERS-RAYMOND AGNANT 11-15-01. (SRH 11-15-01) THE EXPANSION TANK ONLY CAN BE REPAIRED -RONALD CRITCHLOW THE ENGINEERING SUPERVISOR AND CARNAL BRADLEY THE STEAMFITTERS SUPERVISOR HAS BEEN INFORMED BY SHEILA HOWARD DCPS SAFETY TO REPAIR THE TANK AND DO NOT DISTURB THE BOILER INSULATION IN THE PROCESS. (11-15-01) November 15, 2001 November 29, 2001 14 days
Browne Junior High School FM-200112784 01 11/29/01 BROWNE GROUNDS OUTSIDE BACK OF BUILDING 1) STORM DRAIN STOPPED UP WATER LEAKING INTO SWITCH GEAR IN BOILER ROOM ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/03/01. RICHARD GIBSON- SAFETY (202)576-5584(RG) June 7, 2001 November 29, 2001 175 days
Browne Junior High School FM-200114944 01 11/30/01 BROWNE GROUNDS PARKING LOT 1) UNSTOP OUTSIDE STORM DRAIN NEAR BOILER ROOM IN PARKING LOT July 9, 2001 November 30, 2001 144 days
Ronald H. Brown MS FM-200123434 /01 12/1/01 BROWN,RON BOILER ROOMEXIT DOOR REPLACE RIM CYLINDER THUMB LATCH LOCK THAT IS KEYED FOR BUILDING. PRESENT YALE LOCK IS DEFECTIVE, UNABLE TO OPEN/SECURE FROM EXTERIOR OF BUILDING. November 29, 2001 December 1, 2001 2 days
Cleveland Elementary School FM-200123423 /01 12/1/01 (CLEVELAND) WE NEED TO HAVE A KEY MADE FOR BOILER ROOM DOOR. THE KEY IS NEEDED SO WE CAN HAVE BOTH LOCKS ON THIS DOOR. November 29, 2001 December 1, 2001 2 days
Smothers ES FM-200124194 /01 12/2/01 SMOTHERS GRD. FL. BOILER ROOM ASSIST MR. BARKSDALE WITH THE REPLACEMENT OF AUTOMATIC CITY WATER MAKEUP FEEDER AND WATER COLUM/LOW WATER CUT OFF/TRY COCKS. November 30, 2001 December 2, 2001 2 days
Marshall Educational Center FM-200118885 01 12/3/01 (MARSHALL) BOILER ROOM: 1. ASBESTOS ASSESSMENT REQUIRED. RESTORE ELECTRICAL POWER TO BUILDING. MAIN BREAKER KICKS OUT. Requester Phone: 698-1750 Requestor Phone: 698-1750 ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: STEPHEN CALDWELL August 16, 2001 December 3, 2001 109 days
Hart Middle School FM-200120623 01 12/3/01 HART BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.INSTALL LOW WATER FUEL CUT OFF-SAFETY DEVICE, LINE, AND GATE VALVE FOR ALL (3) BOILERS. 3. WIRE (LWFCO) AND TEST/DEMOSTRATE ALL (3) BOILERS TO ENGINEERS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/15/01. HORNE ENGINEERING - STEPHEN CALDWELL (RG) September 27, 2001 December 3, 2001 67 days
Burrville Elementary School FM-200124275 01 12/3/01 BURRVILLE BOILER ROOM BOILERS # 1 & 2 RESOLVE PROBLEM WITH BOILER. BOILERS WILL NOT MAINTAIN PROPER WATER LEVEL IN HIGH FIRE December 3, 2001 December 3, 2001 0 days
Aiton Elementary School FM-200114805 01 12/5/01 AITON BOILER ROOM ASBESTOS ASSESSMENT REQUIRED REPLACE PRESSURE RELIIEF VALUE ON BOILER #1. MAKE KUNKLE, MOD. #537-01 SET 35PSIG. CAT.#3903965, SIZE 1 1/2, BTU G95M ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/27/01. HORNE ENG. - SHANN VOSS (RG) July 6, 2001 December 5, 2001 152 days
Ketcham Elementary School FM-200116569 01 12/5/01 KETCHAM HALLWAY NEAR BOILER ROOM - GROUND FLOOR ASBESTOS ASSESSMENT REQUIRED ASSESS CEILING AND WALL FOR PLASTER & PAINTING. STEAM LEAK FROM BOILER ROOM HAS BEEN REPAIRED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/26/01. HORNE ENG. - SAM EBRAHIM (RG) August 2, 2001 December 5, 2001 125 days
Ronald H. Brown MS FM-200123995 /01 12/5/01 RON BROWN BOILER 1. ASBESTOS ASSESTMENT REQUIRED 2. REPAIR RUPTURE SUPPLY LINE IN BOILER ROOM NO HEAT IN BUILDING ASBESTOS CODE A-CLEAR FOR REPAIR ON11/29/01 BY HORNE ENGINEER : EDWARD RODRIGUEZ November 29, 2001 December 5, 2001 6 days
Gibbs Elementary School FM-200119379 01 12/5/01 GIBBS BASEMENT BOILER ROOM BOILERS #1 AND 2 WILL NOT START. WP-200108674 September 7, 2001 December 5, 2001 89 days
Gibbs Elementary School FM-200116248 01 12/5/01 GIBBS BOILER ROOM ASBESTOS ASSESSMENT REQUIRED. REPLACE REFRACTORY ON TUBE DOORS OF BOILER #1 AND #2. ASBESTOS CODE A-CLEAR FOR REPAIR BY STEPHEN HORNE ENG. ON 9/10/01. July 31, 2001 December 5, 2001 127 days
Dunbar High School FM-200124499 01 12/5/01 DUNBAR BOILER ROOM CHECK AND REPAIR BOILER #1. BOILER #1 WILL NOT START. December 4, 2001 December 5, 2001 1 day
Aiton Elementary School FM-200114814 01 12/5/01 AITON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE(1) LEAKING TUBE IN BOILER #2. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/27/01. HORNE ENG. - SHANN VOSS (RG) July 6, 2001 December 5, 2001 152 days
Ferebee-Hope Elementary School FM-200105266 01 12/6/01 FEREBEE-HOPE PENTHOUSE TOWER & BOILER ROOM 1. R/R TWO(2) HEAT CIRCULATING PUMPS, CASING RUSTED, PACKING NEEDED AND SHAFT FROZEN ON A-3. PENTHOUSE 2. REPLACE TWO (2) CARTRIDGE TYPE CIRCULATING PUMPS. WATER SEALS LEAKING. PUMPS INOPERABLE. D BLDG. BOILER ROOM March 8, 2001 December 6, 2001 273 days
Gibbs Elementary School FM-200124283 01 12/6/01 GIBBS BOILER ROOM SURVEY AND MAKE ADJUSTMENT TO FEED WATER REGULATOR December 3, 2001 December 6, 2001 3 days
Anacostia Senior High School FM-200109938 01 12/6/01 ANACOSTIA BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE GASKET ON STRAINER. GASKET LEAKS ON END 8" LINE. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/25/01. May 10, 2001 December 6, 2001 210 days
Ferebee-Hope Elementary School FM-200120167 01 12/6/01 FEREBEE-HOPE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REMOVE 2" NIPPLE FROM STEAM SIDE OF BOILER #1 (ONE). HEAT IS NEEDED. ASBESTOS CODE A-CLEAR FOR REPAIR NO 9/21/01 BY HORNE ENGINEER TROY WILCOME September 20, 2001 December 6, 2001 77 days
Ferebee-Hope Elementary School FM-200109389 01 12/6/01 (FEREBEE-HOPE) 1. ASBESTOS ASSESSMENT REQUIRED. EXTERIOR/BOILER ROOM AREA: REPAIR OR REPLACE HANDRAIL, ALSO, FABRICATE NEW HANDRAIL. (SAFETY HAZARD) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/01/01. MR. CHARLES BUCHANAN -SAFETY (202)439-7840 May 1, 2001 December 6, 2001 219 days
Ferebee-Hope Elementary School FM-200101222 01 12/6/01 FEREBEE-HOPE BOILER ROOM REPLACE TWO CARTRIDGE TYPE CIRCULATING PUMPS. WATER SEALS LEAKING. PUMPS INOPERABLE. HC-20000089 January 13, 2001 December 6, 2001 327 days
Leckie Elementary School FM-200122217 /01 12/7/01 LECKIE BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPAIR BREECHING ON BOILER #2.BREECHING NEED WELDING. October 24, 2001 December 7, 2001 44 days
Terrell Mc ES FM-200124276 01 12/7/01 MC TERRELL BOILER ROOM REPAIR TUBE LEAK IN BOILER # ONE ASBESTOS CODE A-CLEAR FOR REPAIR 11/30/01 BY HORNE ENGINEER: ROGER KAGER December 3, 2001 December 7, 2001 4 days
Leckie Elementary School FM-200114030 01 12/7/01 M.V.LECKIE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE FIREBOX REFRACTORY IN BOILER #1 AND #2.. June 26, 2001 December 7, 2001 164 days
Leckie Elementary School FM-200113484 01 12/7/01 M.V.LECKIE BOILER ROOM #2 BOILER 1. ASSESSMENT REQUIRED (2) REPLACE TWO (2) FIRE TUBE THAT LEAKING IN HOT WATER BOILER #2. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/25/01. June 18, 2001 December 7, 2001 172 days
Barnard Elementary School FM-200119662 01 12/11/01 BARNARD BOILER ROOM REPLACE FAULTY FLOAT SWITCH TO #51 MODEL AUTOMATIC WATER FEEDER TO BOILER #1. September 12, 2001 December 11, 2001 90 days
Harris, C.W. ES FM-200120944 01 12/11/01 C. W. HARRIS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE (1) 1" NIPPLE ON BOILER #2 FEED WATER LINE. NIPPLE IS BROKEN OFF IN TEE 1-1/4 X 1-1/4 X 1. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/03/01. LEROY MINTON - SAFETY (202)576-6691 (RG) October 3, 2001 December 11, 2001 69 days
Horace Mann Elementary School FM-200102041 01 12/12/01 MANN BOILER ROOM - STAIRWELL INSTALL HAND RAILS IN THE BOILER ROOM. 15 INCHES LENGTH. SAFETY HAZARD. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/28/01 RONALD EDWARDS - SAFETY (202)576-6693 January 24, 2001 December 12, 2001 322 days
West Elementary School FM-200125020 /01 12/12/01 WEST NEAR BOILER ROOM A WELDER IS NEEDED TO TACK-WELD GRATE NEAR BOILER ROOM. GRATE IS LOOSE AND NEED TO BE WELDED AND SECURED TO PREVENT AN ACCIDENT. NOTE: SAFETY HAZARD December 12, 2001 December 12, 2001 0 days
Kenilworth ES FM-200124028 /01 12/12/01 KENILWORTH BOILER ROOM AND TEACHERS LOUNGE FURNISH KEYS (2) TWO BOILER AND (1) ONE FOR TEACHER LOUNGE . December 10, 2001 December 12, 2001 2 days
Watkins Elementary School FM-200124962 /01 12/13/01 BRENT BOILER ROOM REPAIR BOILER #1 BURNER, IT CUT OFF ON FLAME FAILURE. December 12, 2001 December 13, 2001 1 day
Smothers ES FM-200124827 /01 12/14/01 SMOTHERS BOILER ROOM FURNSIH AND REPAIR SUMP PUMP IN BOILER ROOM. BOILER ROOM IS FLOODED. December 10, 2001 December 14, 2001 4 days
Backus Middle School FM-200124898 /01 12/15/01 SPEACIAL PROJECTS BOILER ROOM SPECAIL PROJECT TO CLEAN AND PREPARE HVAC EQUIPMENT FOR DC INSPECTION. December 11, 2001 December 15, 2001 4 days
Miner Elementary FM-200125522 /01 12/18/01 MINER BOILER ROOM REPAIR BOILER #1. BOILER KEEP CUTTING OFF ON FLAME FAILURE. ONLY WORING BOILER 1 OF 2 December 18, 2001 December 18, 2001 0 days
Rudolph Elementary School FM-200125524 /01 12/18/01 RUDOLPH BOILER ROOM REPAIR BOILER#2. BOILER OFF ON FLAME FAILURE. December 18, 2001 December 18, 2001 0 days
Miner Elementary FM-200125006 /01 12/18/01 MINER BOILER ROOM REPAIR OR REPLACE MOTORIZED GAS VALVE. BOILER GOES OUT IN FLAME FAILURE. EMERGENCY. December 12, 2001 December 18, 2001 6 days
Hine JHS FM-200124566 01 12/18/01 HINE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR/REPLACE 1-1/2" THREADED LEVER TYPE BLOWDOWN VALVES ON #1 BOILER FRONT AND REAR. BOILER OUT OF SERVICE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/05/01. HORNE ENGINEERING - STEPHEN CALDWELL (RG) December 5, 2001 December 18, 2001 13 days
River Terrace ES FM-200125636 /01 12/19/01 RIVER TERRACE BOILER ROOM CORRECT CAUSE FOR AIR COMPRESSOR PUMP MOTOR CONTINUOUSLY HAS TO BE RESET, CREATING OVERHEATING CONDITIONS IN BLDG. December 18, 2001 December 19, 2001 1 day
Ronald H. Brown MS FM-200125635 /01 12/19/01 RON BROWN BOILER ROOM PERFORM REPAIRS TO AIR COMPRESSOR. AIR COMPRESS CONTINUOUSLY HAS TO BE RESET. BLDG. IS PRESENTLY OVERHEATING. December 18, 2001 December 19, 2001 1 day
Shaed Elementary School FM-200123139 01 12/19/01 SHAED BOILER ROOM BOILER #1 KEEP GOING IN AND OUT ON FLAME FAILURE. November 9, 2001 December 19, 2001 40 days
Thomas Elementary School FM-200125525 /01 12/19/01 THOMAS BOILER ROOM BOILER #2 BURNER NEED ADJUSTING. (GAS FUMES) December 18, 2001 December 19, 2001 1 day
Dunbar High School FM-200123891 /01 12/19/01 DUNBAR ATTIC BOILER ROOM REPAIR BURNER CONTROLLER. BOILER WILL NOT START. RE: LOW WATER CONDITION, HOWEVER BOILER IS FULL TO CAPACITY. NO HEAT. November 27, 2001 December 19, 2001 22 days
Shaw JHS FM-200123725 /01 12/20/01 SHAW BOILER ROOM BOILER #3 WILL NOT START. SHUTS OFF FLAME FAILURE. 3-P HIGH PRESSURE. November 21, 2001 December 20, 2001 29 days
Murch Elementary School FM-200125821 /01 12/20/01 MURCH BOILER ROOM (TUNNEL) 1. ASBESTOS ASSESSMENT IS REQUIRED 2. REPAIR 1 AND 3 INCH RUPTURED LINES (BOILER ROOM IS FLOODING NEW HEATING PLANT) PIPES ARE UNINSULATED ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/20/01. SHEILA R HOWARD - SAFETY (202)576-8962 (RG) December 20, 2001 December 20, 2001 0 days
Johnson JHS FM-200124522 01 12/20/01 JOHSON BOILER ROOM BOILER #1 OFF ON FLAME FAILURE. December 5, 2001 December 20, 2001 15 days
Johnson JHS FM-200123288 /01 12/20/01 JOHNSON BOILER ROOM REPAIR PUMP #1 AND 2 BOTH PUMPS ARE INOPERABLE MECHANICAL SEALS ARE LEAKING. November 14, 2001 December 20, 2001 36 days
Johnson JHS FM-200123326 /01 12/20/01 JOHNSON BOILER ROOM REPAIR ON REPLACE HEATING HOT WATER CIRCULATING PUMPS. November 14, 2001 December 20, 2001 36 days
Kimball Elementary School FM-200101582 /01 12/21/01 KIMBALL BOILER ROOM REPLACE 2" RETURN LINE THREADED BLACK PIPE. HC-20000857 January 18, 2001 December 21, 2001 337 days
Randle-Highlands ES FM-200126088 /01 12/26/01 RANDLE-HIGHLAND BOILER ROOM REPAIR BOILER #1. BOILER WOULD NOT START. December 26, 2001 December 26, 2001 0 days
Kimball Elementary School FM-200126116 /01 12/27/01 KIMBALL BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPAIR OR REPLACE DOMESTIC HOT WATER LINE IS LEAKING OVER TOP OF BOILER#2. (INSTALLATION SIZE UNKNOWN) NO DOMESTIC HOT WATER CODE A - CLEAR FOR REPAIRS AS OF 12/28/01 (SG) PER STEPHEN CALDWELL HORNE ENGINEERS. December 27, 2001 December 27, 2001 0 days
Rudolph Elementary School FM-200125558 /01 12/28/01 RUDOLPH BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 3/4" GATE VALVE ON CITY MAKEUP LINE ON BOILER #1. "VALVE IS BROKEN IN THE OPEN POSITION". ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/19/01. HORNE ENGINEERING - STEPHEN CALDWELL (RG) December 18, 2001 December 28, 2001 10 days
Rudolph Elementary School FM-200123730 /01 12/28/01 (RUDOLPH) BOILER ROOM 1. BOILER #1 REPLACE 3/4 GATE VALVE ONLY 1 OF 2 BOILERS ARE OPERATING ASBESTOS CODE A-CLEAR FOR REPAIR ON11/28/01 BY HORNE ENGINEER : SAM EBRAHIM November 23, 2001 December 28, 2001 35 days
Kimball Elementary School FM-200126438 /01 12/31/01 KIMBALL BOILER ROOM CHECK AND REPAIR DOMESTIC HOT WATER HEATER. NO HOT WATER. PUMP NOT WORKING. December 31, 2001 December 31, 2001 0 days
Kenilworth ES FM-200126474 /01 1/2/02 KENILWORTH BOILER ROOM CHECK DOMESTIC HOT WATER HEATER. NO HOT WATER IN BUILDING. December 31, 2001 January 2, 2002 2 days
Kimball Elementary School FM-200126479 02 1/2/02 KIMBALL BOILER ROOM REPLACE RELIEF VALVE ON DOMESTIC HOT WATER HEATER. VALVE WILL NOT SEAL SHUT/ WATER CONTINUOUSLY RUNNING. January 2, 2002 January 2, 2002 0 days
Plummer Elementary School FM-200126444 /01 1/2/02 PLUMMER BOILER ROOM RESPOND TO NO HEAT, CALL EMERGENCY. December 31, 2001 January 2, 2002 2 days
Davis Elementary School FM-200126025 /01 1/2/02 DAVIS SCHOOL BOILER ROOM CORRECT ELECTRICAL PROBLEM WITH CIRCULATION PUMP December 22, 2001 January 2, 2002 11 days
Watkins Elementary School FM-200124548 01 1/2/02 WATKINS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE LEAKING TUBES IN BOILER #1.BOILER #1 HAS TWO TUBES LEAKING. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/05/01. HORNE ENGINEERING - TROY WILCOME (RG) December 5, 2001 January 2, 2002 28 days
Miner Elementary FM-200124737 /01 1/2/02 MINER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. BOILER#2 REPAIR 3 INCH RETURN LINE THAT FEEDS INTO A 1 1/2 INCH CHEMICAL FEED TANK ASBESTOS CODE A-CLEAR FOR REPAIR ON 12-10-01 BY HORNE ENGINEER : SHEREYLL JAMES December 10, 2001 January 2, 2002 23 days
Bancroft Elementary School FM-200126476 02 1/2/02 BANCROFT BOILER ROOM 1. ASBESTOS ASSESTMENT REQUIRED 2. REPAIR OR REPLACE RUPTURED 2 INCH CONDENSATE RETURN LINE ON SIDE OF BOILER NUMBER TWO. ASBESTOS CODE A-CLEAR FOR REPAIOR 01/02/02 BY HORNE ENGINEER : BILL CAMPION January 2, 2002 January 2, 2002 0 days
Burrville Elementary School FM-200123735 /01 1/3/02 BURRVILLE BOILER ROOM REPLACE SOLENOID VALVE ON CITY WATER LINE FEEDING CONDENSATE PIT. November 23, 2001 January 3, 2002 41 days
Clark Elementary School FM-200125596 /01 1/3/02 (CLARK) 1. ASBESTOS ASSESSMENT REQUIRED. BOILER ROOM: FURNISH MATERIALS TO REPLACE DEFECTIVE OUTLET VALVE ON LEAKING WATER METER. CITED BY WASA 12/17/01. (14 DAYS COMPLIANCE REQUIRED) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/18/01. HORNE ENGINEERING - STEPHEN CALDWELL (RG) December 18, 2001 January 3, 2002 16 days
Lincoln Middle School FM-200125586 /01 1/3/02 LINCOLN BOILER ROOM REPAIR OR REPLACE LEAKING TUBE IN BOILER #3, 3" TUBE, MAY BE LEAKING FROM CROWN SHEET, 5TH ROW FROM THE BOTTEM & 5TH TUBE FROM THE RIGHT SIDE. NO ASBESTOS ASSESSMENT NECESSARY. December 18, 2001 January 3, 2002 16 days
Lincoln Middle School FM-200124611 01 1/3/02 LINCOLN BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2.REPLACE LEAKING TUBES IN BOILER #3 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/07/01. HORNE ENGINEERING - TROY WILCOME (RG) December 6, 2001 January 3, 2002 28 days
Orr Elementary School FM-200126463 /01 1/3/02 ORR SCHOOL ASBESTOS ASSESTMENT REQUIRED BOILER ROOM REPLACE 2 INCH LEAKING TUBES IN NUMBER ONE BOILER CODE A- CLEAR FOR REPAIR BY HORNE ENGINEERING BY EDWARD RODRIGUEZ 12-31-01 (S.R. HOWARD- DCPS SAFETY12-31-01. December 31, 2001 January 3, 2002 3 days
Dunbar High School FM-200125646 /01 1/3/02 DUNBAR BOILER ROOM REPAIR OR REPLACE 2 COMPRESSORS IN THE BOILER ROOM URGENTLY NEEDED FOR HEATING. December 18, 2001 January 3, 2002 16 days
Thomas Elementary School FM-200125748 /01 1/4/02 THOMAS BOILER ROOM BURNER #2 NEED TO BE ADJUSTED, MAKE REPAIR TO FUEL VALVE, OUT ON FLAME FAILURE DO TO FUEL VALVE OPEN END SWITCH. December 19, 2001 January 4, 2002 16 days
Woodson High School FM-200124475 01 1/7/02 WOODSON BOILER ROOM FURNISH FUSE IN ORDER TO REPAIR SUMP PUMP FUSE TYPE: 10 BUSS 30AMP. MODEL NO. ATQR30 10 EACH FUSE TYPE: BUSS 1AMP. MODEL NO. ATQR1 10 EACH December 4, 2001 January 7, 2002 34 days
Garnet-Patterson MS FM-200126848 02 1/7/02 GARNET PATTERSON BOILER ROOM CHECK AND CORRECT PROBLEMS WITH BOILER #2, BOILER CONSTANTLY GOES OFF ON FLAME FAILURE. NOTE: THIS IS THE ONLY OPERATIONAL BOILER, BOILERS #1 AND #3 ARE DOWN FOR REPAIRS. January 7, 2002 January 7, 2002 0 days
Stevens Elementary School FM-200123257 /01 1/7/02 STEVENS BOILER ROOM REPAIR ATMOSPHERIC BOILER #2. BOILER WILL NOT START. November 13, 2001 January 7, 2002 55 days
Smothers ES FM-200100193 7/01 1/7/02 SMOTHERS BOILER ROOM BROKEN VALVE ON MAIN WATER LINE. WATER RUNNING EVERYWHERE. HC-20000320 January 7, 2001 January 7, 2002 365 days
Miner Elementary FM-200126532 02 1/7/02 MINER BOILER ROOM 1. REMOVE INSULATION FROM HARDFORD LOOP. LINE IS ON BOILER #2 (4" PIPE). 2. REPAIR OR REPLACE HARTFORD NIPPLE. POC: CARNAL BRADLEY 202 438-7437 ASBESTOS CODE A-CLEAR FOR REPAIR BY DCPS SAFETY OFFICE SRH. (CEB) ASBESTOS ABATED ON 1/5/02 (SG) PER SHEILA HOWARD CONFIRMATION. January 2, 2002 January 7, 2002 5 days
Park View ES FM-200125768 /01 1/8/02 (PARK VIEW) ***EMERGENCY*** BASEMENT/AUDITORIUM STAGE LIGHTS WILL NOT COME ON (THERE HAS BEEN ASBESTOS ABATEMENT GOING ON IN THE BOILER ROOM & PERHAPS SOMEONE TOUCHED A SWITCH OR SOMETHING). WE NEED THE ELECTRICIAN TO CHECK THE PROBLEM & GET THE LIGHTS ON IN TIME FOR TOMORROWS XMAS PROGRAM SO WE CAN AVOID SAFETY ISSUES. December 19, 2001 January 8, 2002 20 days
Woodson High School FM-200123042 01 1/8/02 H.D. WOODSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. MAKE THE NECESSARY REPAIRS TO THE CONDENSATE RETURN LINE TO THE CONDENSATE TANK IN THE PHYSICAL HEATING PLANT. RETURN LINE IS LEAKING CAUSING LOSS OF NEEDED WATER FOR HEATING PURPOSES. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: ROGER KAGER November 7, 2001 January 8, 2002 62 days
Ballou Senior High School FM-200115730 01 1/8/02 (BALLOU) "EMERGENCY" 1. ASBESTOS ASSESSMENT REQUIRED. NEXT TO BOILER ROOM: MAIN BREAKER TRIPPING; INTERFERING WITH AIR CONDITIONERS SERVICING CLASSROOMS ON THE 2ND AND 3RD FLOOR. CODE A-CLEAR FOR REPAIR BY DCPS SAFETY (CEB 7/27/01) July 24, 2001 January 8, 2002 168 days
Dunbar High School FM-200118829 01 1/9/02 (DUNBAR) 6TH FLOOR/BOILER ROOM: COMPRESSOR RUNNING HAND, NOT ON AUTOMATIC, AND CONTINUES TO TRIP BREAKER. (AIR CONDITIONING SLOWLY GOING DOWN) August 30, 2001 January 9, 2002 132 days
Woodson High School FM-200127071 01 1/9/02 WOODSON BOILER ROOM INSTALL PVC LINE FOR SUMP PUMP August 1, 2001 January 9, 2002 161 days
Emery Elementary School FM-200127202 02 1/12/02 EMERY BOILER ROOM CHECK BOILER, NO HEAT. January 10, 2002 January 12, 2002 2 days
Leckie Elementary School FM-200127193 02 1/12/02 LECKIE SCHOOL BOILER ROOM 1. ON BOILER NUMBER ONE REPLACE MCDONNELL PUMP CONTROL AND LOW/WATER CUTOFF NO. 150. 115 VOLTS, AMPS 1/2 2. ON BOILERS NO. 1 AND 2 REPLACE HONEYWELL MANUAL RESET TYPE 1 AQUASTAT, HIGH LIMIT CONTROL SWITCH OPEN ON TEMPERATURE INCREASE FULL LOAD = 8.0 /5.1, VOLTS 120V 240V, LOCKER ROTOR= 48.0/30.6 .25AMP AT .25-12VDC REV-A 97-2523 January 10, 2002 January 12, 2002 2 days
Roosevelt High School FM-200127365 02 1/15/02 ROOSEVELT BOILER ROOM TROUBLER SHOOT AND REPAIR CONDENSATE SYSTEM, CAN NOT KEEP BOILER #2 ON LINE AT THE SAME TIME, CUTS OFF ON LOW WATER. January 14, 2002 January 15, 2002 1 day
Thomson Elementary School FM-200127405 02 1/15/02 THOMSON GRD. FL. BOILER ROOM REPAIR OR REPLACE #1 BOILER BURNER CUT OFF ON FLAMER FAILURE. January 14, 2002 January 15, 2002 1 day
Ludlow-Taylor ES FM-200123726 /01 1/15/02 LUDLOW-TAYLOR BOILER ROOM REPAIR/REPLACE AUTOMATIC BLEEDER ON THE AIR COMPRESSOR, COMPRESSOR RUNS CONSTANTLY. November 21, 2001 January 15, 2002 55 days
Lincoln Middle School FM-200120942 01 1/15/02 LINCOLN BOILER ROOM SEND ELECTRICIAN TO CHECK CONTROL BOX TO THE HOT WATER CIRCULATING PUMPS. CONTROL BOX MAY HAVE SHORTED OUT. Requester Phone: 576-5316 Requestor Phone: 576-5316 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/17/01. RONALD EDWARDS - SAFETY (202)576-6693 (RG) September 25, 2001 January 15, 2002 112 days
Cardozo High School FM-200201127 02 1/16/02 CARDOZO SHS BOILER ROOM BOILER #1 WILL NOT START OUT ON FLAME FAILURE (ONLY 1 BOILER IS OPERATING) January 16, 2002 January 16, 2002 0 days
Davis Elementary School FM-200124225 /01 1/16/02 (DAVIS) ASBESTOS ASSESSMENT REQUIRED BASEMENT/LUNCHROOM REPLACE DAMAGED ELECTRIC BOX LOCATED BY BOILER ROOM DOOR. ASBESTOS CODE A-CLEAR FOR REPAIR 12/05/01 BY HORNE ENGINEER: Z MAHNOOD November 30, 2001 January 16, 2002 47 days
Aiton Elementary School FM-200127410 02 1/16/02 AITON BOILER ROOM REPAIR/REPLACE #1 BURNER, CUT OUT ON FLAME FAILURE. January 14, 2002 January 16, 2002 2 days
Shaw JHS FM-200127285 02 1/17/02 SHAW BOILER ROOM RESTORE ELECTRICAL CURRENT TO BOILERS. (BUILDING HAS NO HEAT). January 11, 2002 January 17, 2002 6 days
Terrell Mc ES FM-200127288 02 1/18/02 M.C. TERRELL BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE LEAKING TUBES IN BOILER #1. WATER LEAKING OUT FRONT AND BACK. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 BY HORNE ENGINEER: TROY WILCOME January 11, 2002 January 18, 2002 7 days
Tubman Elementary School FM-200118058 01 1/18/02 TUBMAN BOILER ROOM 1. ASSBESTOS ASSESSMENT REQUIRED. 2. BOILER #2, REPLACE RELIEF VALVES SIZES AZE SERIAN NO. 92508, MODEL M, NO. 740, SIZE 1-1/4 IN., SET 50 LB. BTU RATING 3,075.000 ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER TROY WILCOME August 22, 2001 January 18, 2002 149 days
Ferebee-Hope Elementary School FM-200201258 02 1/18/02 FEREBEE-HOPE BOILER ROOM BOILER #1 GOES OUT ON FLAME FAILURE. January 17, 2002 January 18, 2002 1 day
Brightwood Elementary School FM-200127326 02 1/18/02 (BRIGHTWOOD) ***EMERGENCY*** 1ST FLOOR BOILER ROOM EXIT DOORS REPLACE EXTERIOR ENTRANCE LOCKS (THEFT OCCURRED ON DEC. 26, 2001 WITH NO EVIDENCE OF BREAK-IN. REPORT FILED.) January 16, 2002 January 18, 2002 2 days
River Terrace ES FM-200122220 /01 1/18/02 RIVER TERRACE BOILER ROOM REPLACE DEFECTIVE S-51-2 MECHANICAL WATER FEEDER/LOW WATER CUT-OFF COMBINATION. FEEDER IS LEAKING AT FLOAT ASSEMBLY LINKAGE. MAKE MCDONNELL MILLER. S-51-2. October 24, 2001 January 18, 2002 86 days
Ludlow-Taylor ES FM-200127402 02 1/18/02 LUDLOW TAYLOR BOILER ROOM REPAIR BURNER #1, CUTS OFF ON HIGH LIMIT CONTROL. January 14, 2002 January 18, 2002 4 days
Wilson J. O. ES FM-200126633 02 1/21/02 J.O. WILSON BOILER ROOM REPAIR OR REPLACE BOILER #2 CUT OFFS ON FLAME FAILURE. January 3, 2002 January 21, 2002 18 days
Aiton Elementary School FM-200201443 02 1/22/02 AITON SCHOOL BOILER ROOM INVESTIGATE AND MAKE CORRECTIONS TO BOILER NUMBER 2, BURNER CONTINUOUSLY GOES OUT IN FLAME FAILURE. January 22, 2002 January 22, 2002 0 days
Cardozo High School FM-200201371 02 1/22/02 CARDOZO BOILER ROOM BOILER #3 OFF ON FLAME FAILURE. January 22, 2002 January 22, 2002 0 days
Garfield ES FM-200124205 /01 1/22/02 (GARFIELD) BOILER ROOM REPAIR OR ADJUST FLOAT ON CONDENSATE TANK. PER S.W.A.T. VISITATION/INSPECTION. November 30, 2001 January 22, 2002 53 days
Shepherd ES FM-200108536 01 1/23/02 SHEPHERD BOILER ROOM UNSTOP DRAIN IN BOILER ROOM. April 17, 2001 January 23, 2002 281 days
Patricia R Harris Ed Center FM-200115389 01 1/23/02 P.R. HARRIS BOILER ROOM REPAIR CONDENSER PUMP #4 IN BOILER ROOM FOR COOLING TOWER. MOTR HP 50, PUMP: ALLIS-CHALMERS, SERIAL NO. 741-15517-3-1, SIZE: 3 X 6 X 12, IMP. DIA. 10.60, GPM 1650, IN BRD. BRG 6209, RPM 1800, OUTB.BRG 5307, FT.HO 75, GASKET .015. WP-200108861 July 19, 2001 January 23, 2002 188 days
Shepherd ES FM-200124620 01 1/23/02 SHEPHERD BOILER ROOM 1) UNSTOP FLOOR DRAIN AND AREAWAY DRAINS OUT SIDE OF BOILER ROOM. December 6, 2001 January 23, 2002 48 days
Shaw JHS FM-200122053 /01 1/24/02 SHAW BOILER ROOM REPAIR #4 BOILER;. BOILER WILL NOT FIRE OFF. October 22, 2001 January 24, 2002 94 days
Shaw JHS FM-200115779 01 1/24/02 SHAW BOILER ROOM 1. ASBESTOS ASSESSMENT NEEDED IN FIRE BOX BOILERS 2 & 3. 2. REPAIR REFRACTORY IN FIREBOX OF BOILERS 2 & 3. CODE A CLEAR FOR REPAIR DCPS SAFETY SRH 08-10-01 July 24, 2001 January 24, 2002 184 days
Shaw JHS FM-200115783 01 1/24/02 SHAW BOILER ROOM 1. ASBESTOS ASSESSMENT NEEDED. 2. REPLACE REFRACTORY FLOORING IN #3 BOILER. POC SCOTT MC KENNA 571-212-2624 CELL PHONE CODE A-CLEAR FOR REPAIR BY HORNE ENG 8/15/01 (CEB) July 24, 2001 January 24, 2002 184 days
Shaw JHS FM-200115784 01 1/24/02 SHAW BOILER ROOM 1. ASBESTOS ASSESSMENT NEEDED. 2. PIPE SAFETY VALVES TO 6" ABOVE FLOOR LEVEL ON #2 & 4 BOILERS. POC :SCOTT MC KENNA 571-212-2624 CELL PHONE CODE A-CLEAR FOR REPAIR BY HORNE ENG 8/15/01 (CEB) July 24, 2001 January 24, 2002 184 days
Shaw JHS FM-200106867 01 1/24/02 SHAW BOILER ROOM REPLACE 3/4" SOLENOID VALVE ON CITY WATER LINE TO CONDENSATE TANK, VALVE DOES NOT OPERATE. March 29, 2001 January 24, 2002 301 days
Woodson High School FM-200201212 02 1/25/02 H.D. WOODSON BOILER ROOM PHYSICAL HEATING PLANT REPLACE (1) 2" LEAKING CROSS TEE ON THE RETURN LINE TO #2 BOILER TEE LEAKING BADLY, BOTH BOILERS ARE NEEDED DURING THE HEATING SEASON. NOTE: ASBESTOS ASSESSMENT NOT NEEDED, NO INSULATION ON THE RETURN LINE. CODE A -CLEAR FOR REPAIR BY DCPS SAFETY-SHEILA R. HOWARD 01-23-02 CONFIRMED WITH STEAMFITTING (CARNAL BRADLEY) AND THE BUILDING ENGINEER (EARL PARKER) January 16, 2002 January 25, 2002 9 days
Seaton Elementary School FM-200201714 02 1/25/02 SEATON SCHOOL BOILER ROOM 1. ASBESTOS ASSESTMENT NOT NEEDED 2. REPAIR/REPLACE LEAKING TUBE BOILER NUMBER TWO (2). January 24, 2002 January 25, 2002 1 day
Drew Elementary School FM-200123733 /01 1/25/02 DREW BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2.REPLACE (1) 3 INCH CLOSE NIPPLE ON BOILER #2 CLEAN OUT DRAIN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/26/01 HORNE ENGINEERING - EDWARD RODRIGUZE (RG) November 23, 2001 January 25, 2002 63 days
Wilson J. O. ES FM-200127314 02 1/26/02 J.O. WILSON BOILER ROOM REPAIR #1 BURNER, CUTS FLAME FAILURE. #2 BURNER IS RUNNING. January 11, 2002 January 26, 2002 15 days
Stuart-Hobson Middle School FM-200125304 /01 1/26/02 STUART-HOBSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 3" BLOWDOWN VALVE ON BOILER #3. REPAIR BLOWDOWN LINE ON GAUGE GLASS, LINE SIZES 1/2". ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/17/01. HORNE ENGINEERING - BILL CAMPION (RG) December 14, 2001 January 26, 2002 43 days
Rudolph Elementary School FM-200127287 02 1/28/02 RUDOLPH GRD. FL. BOILER ROOM/PUMP ROOM REPLACE LEAKING SHORT 2" NIPPLE ON H/W HEATING CIRC. SYSTEM LOCATED IN CEILING BETWEEN GATE VALVE (2") AND A (2") UNION ON THE SUCTION SIDE OF THE CIRC. PUMPS. THERE IS NO PIPE INSULATION ON AREA OF LEAK. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/16/02 RONALD EDWARDS-SAFETY (202)576-6691 (RG) ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/17/02 BY HORNE ENGINEER: RAY AGNANT January 11, 2002 January 28, 2002 17 days
Gage-Eckington ES FM-200126750 02 1/28/02 GAGE-ECKINGTON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. BOILER #1 HAS A HOLE IN SHELL AT THE BOTTOM OF BOILER (DO NOT KNOW THE LOCATION). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 01/08/02. HORNE ENGINEERING - EDWARD RODRIGUEZ (RG) January 4, 2002 January 28, 2002 24 days
Gage-Eckington ES FM-200120912 01 1/29/02 GAGE -ECKINGTON BOILER ROOM 1) TROUBLE SHOOT BURNER IN BOILER. ACI, INC JESSE POOLE- 301-779-3400 October 3, 2001 January 29, 2002 118 days
Miner Elementary FM-200126089 /01 1/29/02 MINER BOILER ROOM UNSTOP CATCH BASIN TO SUMP PUMP IN BOILER ROOM. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/26/01 DCPS SAFETY- R. EDWARDS (RE) December 26, 2001 January 29, 2002 34 days
Meyer Elementary School FM-200201784 02 1/29/02 MEYERS BOILER ROOM BOILER #2 NEEDS TO REPLACE AMPLIFIER. January 25, 2002 January 29, 2002 4 days
Burrville Elementary School FM-200125121 /01 1/29/02 BURRVILLE 1ST FL. BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. PIPE/THERMAL SYSTEM INSULATION NEEDS TO BE TESTED. 2. REPLACE APPROXIMATELY 20 FT. OF 1-1/2 BLACK PIPE ON HOT WATER HEATING SYSTEM BETWEEN AIR SEPERATOR & EXPANSION TANK. ASBESTOS CODE A-CLEAR FOR REPAIR ON 12/14/01 BY HORNE ENGINEER: TROY WILCOME December 13, 2001 January 29, 2002 47 days
Hart Middle School FM-200120638 01 1/30/02 HART BOILER ROOM 1.REPLACE FIVE (5) AUTOMATIC 1" AIR BLEEDERS ON RETURN LINE. BADLY LEAKING AND CORRODED BLACK PIPE, PIPE TO FLOOR DRAIN. ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER STEPHEN CALDWELL September 27, 2001 January 30, 2002 125 days
Bowen Elementary School FM-200202077 02 1/30/02 ANTHONY BOWEN (BOILER ROOM) 1. BOILER#2 REPAIR CONDENSATE RETURN PUMP (BOILERS WILL NOT OPERATE MANUAL OR AUTO) 2. BOILER #1 RESTORE ELECTRICAL CURRENT TO BURNER January 30, 2002 January 30, 2002 0 days
Slowe Elementary School FM-200202350 02 2/1/02 SLOWE BOILER ROOM 1. REPAIR #1 SUMP PUMP RUPTURED DISCHARGE LINE. 2. REPAIR #2 SUMP PUMP, WILL NOT CUT OFF FLOAT SWITCH HOT! FLOODED BOILER ROOM. February 1, 2002 February 1, 2002 0 days
Takoma Educational Center FM-200202226 02 2/3/02 TAKOMA !!! EMERGENCY !!! FIRST (1ST) FLOOR - #80 GENERAL STORAGE PLEASE REMOVE BROKEN-OFF KEY IN CYCLINDER TO HAVE ASSEST TO THE STORAGE ROOM. WE HAVE CONTRACTORS IN THE BUILDING WHO NEEDS ENTER IN THIS AREA BECAUSE THE BREACH OF THE BOILERS RUNS THIS WAY. * ALSO MAIN OFFICE SUPPLIES IS STORED IN THIS AREA. February 1, 2002 February 3, 2002 2 days
Bruce-Monroe Elementary School FM-200124654 01 2/3/02 BRUCE-MONROE BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE LEAKING TUBES IN BOILER #1 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/07/01. HORNE ENGINEERING - TROY WILCOME (RG) December 7, 2001 February 3, 2002 58 days
Kimball Elementary School FM-200115376 01 2/4/02 (KIMBALL) "EMERGENCY" 1. ASBESTOS ASSESSMENT REQUIRED. BASEMENT MIDDLE WING/BOILER ROOM: WATER RUNNING OUT OF TOILET AND SHOWER DRAIN, FLOODING THE FLOORS; APPEARS TO BE A BACK-UP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/19/01. July 18, 2001 February 4, 2002 201 days
Watkins Elementary School FM-200126590 02 2/5/02 WATKINS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED ON INSULATION. 2. REPLACE RELIEF VALVE ON BOILER #2. ASBESTOS CODE A-CEAR FOR REPAIR ON 1/04/01 BY HORNE ENGINEER: Z MAHMOOD January 3, 2002 February 5, 2002 33 days
Thomas Elementary School FM-200125287 /01 2/5/02 THOMAS BOILER ROOM 1. ASBESSTOS ASSESSMENT REQUIRED ON PIPE INSULATION. 2. REPAIR LEAKING RETURN ON BOILER #1. LEAK APPEARS TO BE COMING FROM THE HARTFORD LOOP. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/14/01. HORNE ENGINEERING - BIPIN NANAVATY (RG) December 14, 2001 February 5, 2002 53 days
Brent Elementary School FM-200202552 02 2/7/02 Brent Boiler room Drain in boiler room at chiller needs unstopping. February 6, 2002 February 7, 2002 1 day
Brent Elementary School FM-200115267 01 2/7/02 BRENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. DISCONNECT AND REMOVE LEAKING HOT WATER BOOSTER HEATER. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/27/01 BY HORNE ENGINEER: STEPHEN CALDWELL July 16, 2001 February 7, 2002 206 days
Dunbar High School FM-200122852 01 2/7/02 DUNBAR SHS BOILER ROOM BOILER#2 REPAIR ONE (1) LEAKING TUBE NOTE: TUBE IS MARKED ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/09/01 HORNE ENGINEER : BIPIN NANAVATY November 2, 2001 February 7, 2002 97 days
Dunbar High School FM-200119644 01 2/8/02 DUNBAR 6TH FLOOR BOILER ROOM REPLACE A LEAKING FIRE TUBE IN BOILER #2 FIFTH ROW FROM THE TOP, #11 TUBE FROM LEFT TO RIGHT. September 11, 2001 February 8, 2002 150 days
Kenilworth ES FM-200127250 02 2/8/02 KENILWORTH BOILER ROOM FURNISH MATERIALS TO REPLACE COUPLING ON DHW CIRCULATING PUMP(BELL & GOSSETT) January 10, 2002 February 8, 2002 29 days
Powell Elementary School FM-200202613 02 2/9/02 Powell Boiler room 1. Replace badly deteriorating heating return line. Lines are leaking causing system to shut down. 2. Replace severely warped 2-1/2 in. copper pipe on the domestic water line in tunnel. Line is ready to collapse. "HOT" 3. Add boiler drain to univent in classroom 213 for bleeding purposes. February 7, 2002 February 9, 2002 2 days
Woodson High School FM-200202495 02 2/11/02 H.D. WOODSON PHYSICAL HEATING PLANT, BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE (2) - 3" TUBES IN BOILER #2, TUBES ARE LEAKING AND NEED TO BE REPLACED AS SOON AS POSSIBLE BOTH BOILERS ARE NEEDED DURING THE HEATING SEASON. ATTN: MR. C. BRADLEY EMERGENCY ASBESTOS CODE A-CLEAR FOR REPAIR ON 2/05/02 BY HORNE ENGINEER: STEPHEN CALDWELL February 5, 2002 February 11, 2002 6 days
Woodson High School FM-200124468 01 2/11/02 WOODSON, H.D. BOILER ROOM !!!! EMERGENCY !!!! SUMP PUMP (AMP) FUSER HAS BLOWN AND WATER IS LEAKING ALL OVER THE FLOOR. ISOLATE EMERGENCY. December 4, 2001 February 11, 2002 69 days
Ludlow-Taylor ES FM-200120019 01 2/12/02 LUDLOW-TAYLOR BOILER ROOM NO ELECTRICAL CURRENT TO BURNER. CURRENT NEEDED TO RESTART BURNER ON BOILER #2. POC: DANNY HUDSON 202 345-1566 ASBESTOS CODE A-CLEAR FOR REPAIR ON11/28/01 BY DCPS SAFETY R. EDWARD September 18, 2001 February 12, 2002 147 days
Garfield ES FM-200202840 02 2/12/02 Garfield School (boiler Room) Replace 1 1/2" copper line from hot water heater to storage tank. Line has several pin holes and leaking from sweat joints. February 12, 2002 February 12, 2002 0 days
Terrell Mc ES FM-200202525 02 2/12/02 TERRELL,M.C. BOILER ROOM RESTORE ELECTRIC SERVICE TO BURNER TO BOILER #1 AND #2. NO HEAT IN BUILDING AT THIS TIME. February 6, 2002 February 12, 2002 6 days
Stevens Elementary School FM-200123143 01 2/13/02 STEVENS BOILER ROOM CHECK AND REPAIR BOILER #2 WILL NOT COME ON. November 9, 2001 February 13, 2002 96 days
Payne Elementary School FM-200202750 02 2/13/02 Payne Boiler room Repair or replace condensate pump control, unit will not put water back into boiler. Must hand feed boilers. February 11, 2002 February 13, 2002 2 days
Stevens Elementary School FM-200106765 /01 2/13/02 STEVENS BOILER ROOM REPLACE EXIT DOORS (1SET DOUBLE DOORS & 1 SINGLE DOOR) WOODEN FRAME AND DOORS DETERIORATED. TOP PORTION OF SINGLE DOOR FRAME COMING AWAY FROM WALL. ASBESTOS CODE A-CLEAR FOR REPAIR BY TROY WILCOME HORNE ENG. ON 9/10/01. March 27, 2001 February 13, 2002 323 days
Powell Elementary School FM-200124157 /01 2/13/02 POWELL BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 February 13, 2002 75 days
Turner Elementary School FM-200124677 /01 2/14/02 TURNER PLAYGROUND/BOILER ROOM UNSTOP DISCHARGE LINES FROM SEWER EJECTOR PUMP LOCATED IN THE BOILER ROOM. CODE FOR PLUMBERS. ASBESTOS CODE A-CEAR FOR REPAIR ON 1/03/01 BY HORNE ENGINEER: EDWARD RADRIGUEZ November 21, 2001 February 14, 2002 85 days
Turner Elementary School FM-200123056 01 2/14/02 TURNER BOILER ROOM 1. ABESTOS ASSESSMENT REQUIRED. 2. REPLACE RELIEF VALVE ON RETURN LINE. CO. WATTS, 50 LBS. SET, #174-1, SIZE 3/4 IN., 9507700 BTU, 965 IN., WATER CONSTANTLY RUNS. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/09/01 HORNE ENGINEER : SHARON VOSS November 7, 2001 February 14, 2002 99 days
Reed LC FM-200202907 02 2/14/02 Reed Boiler room Replace broken sewage injector pumps. February 12, 2002 February 14, 2002 2 days
Plummer Elementary School FM-200126723 02 2/21/02 PLUMMER BOILER ROOM REPAIR BURNER #1 WILL RUN BUT WITH DIFFICULTY. January 4, 2002 February 21, 2002 48 days
Plummer Elementary School FM-200126448 /01 2/21/02 PLUMMER BOILER ROOM REPAIR BURNER ON BOILER #1.BOILER WILL NOT START. December 31, 2001 February 21, 2002 52 days
Terrell Mc ES FM-200123875 /01 2/22/02 M.C. TERRELL BOILER ROOM REPAIR BURNERS ON BOILER #1 & #2 November 27, 2001 February 22, 2002 87 days
Terrell Mc ES FM-200202565 02 2/22/02 Terrell M. C. (boiler room) Repair boiler # 2 I.D. Fan will not run, boiler is on lock out. February 7, 2002 February 22, 2002 15 days
Janney Elementary School FM-200202356 02 2/22/02 JANNEY SCHOOL BOILER ROOM REPAIR/EPLACE FLOAT SWITCH ON CONDENSATE TANK ON FIRST FLOOR. February 4, 2002 February 22, 2002 18 days
Patricia R Harris Ed Center FM-200126456 /01 2/22/02 HARRIS P.R. BOILER ROOM SURVEY AND MAKE REPAIRS TO AIR COMPRESSOR. NUMBER 2 MOTOR CONTINUOUSLY TRIPPING OUT ON OVERLOAD. MOTOR: DOERR AC 3-PHASE, HP-7.5, VOLTS 230/460, AMPS- 22.0/11.0 RPM - 1740, HZ-60, FRAME L213T, SERIAL NO. -R90806DC741 December 31, 2001 February 22, 2002 53 days
Bowen Elementary School FM-200203065 02 2/22/02 (Bowen) ***Emergency*** Near Boiler room door: Stopped up drain out-side of cafeteria, backing up in boiler room. Approximately two (2) feet of water at the boiler room door area. February 15, 2002 February 22, 2002 7 days
Eaton Elementary School FM-200202538 02 2/22/02 Eaton Boiler room Replace boiler emergency switch contactors coil powered for #1 & 2 boilers. 30 amps, made by Cutler-Hammer, #C26DND330, volts, 104-120, 50-60 hz, 3Ls. February 6, 2002 February 22, 2002 16 days
Eastern High School FM-200125491 /01 2/22/02 EASTERN BOILER ROOM REPAIR AIR COMPRESSOR IN BOILER ROOM. 1. NEEDS SAFETY VALVES. 2. REPAIR #2 COMPRESSOR - WILL NOT OPERATE. EMERGENCY December 17, 2001 February 22, 2002 67 days
Bell High School FM-200124756 /01 2/22/02 BELL BOILER ROOM FURNISH AND INSTALL A NEW AIR COMPRESSOR FOR THE PNEUMATIC CONTROL. AIR COMPRESSOR NOT WORKING. ASSESSMENT MADE BY BOBBY DAVIS. December 10, 2001 February 22, 2002 74 days
Payne Elementary School FM-200203373 02 2/25/02 Payne (Boiler Room) 1. Repair or replace sump motor ( motor is operating however; no water is being removed February 25, 2002 February 25, 2002 0 days
Wilson J. O. ES FM-200202176 02 2/25/02 J.O. WILSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 2 TUBES LEAKING IN BOILER #2. CODE A - CLEAR FOR REPAIRS ON 01/31/02 HORNE ENGINEERING - TROY WILCOME (RE) January 30, 2002 February 25, 2002 26 days
Savoy Elementary School FM-200203484 02 2/27/02 SAVOY !!!! EMERGENCY !!!! BOILER ROOM PIPE IS BACK-UP IN THE BOILER ROOM WITH WASTE MATERIAL AND ETC. COMING OUT. SMELL/FOUL ODOR ALSO. February 26, 2002 February 27, 2002 1 day
Dunbar High School FM-200201964 02 2/27/02 DUNBAR BOILER ROOM SURVEY AND MAKE NECESSARY REPAIRS OR REPLACEMENT TO SHAFT AND BEARING ON AIR HANDLER UNIT #6 IN THE BOILER ROOM. THIS UNIT SERVICES THE 3RD, 4TH, AND 5TH FLOOR ON THE SOUTH SIDE OF THE BUILDING. January 28, 2002 February 27, 2002 30 days
Brookland Elementary FM-200203696 02 2/28/02 Brookland Boiler room PM multistack. February 28, 2002 February 28, 2002 0 days
Deal Junior High School FM-200203561 02 2/28/02 Deal Boiler room Repair or replace leaking hartford loop on boiler #3. Emergency. February 27, 2002 February 28, 2002 1 day
Deal Junior High School FM-200203560 02 2/28/02 Deal Boiler room Repair or replace burners on boiler #2. Burner will run but then shuts down. Emergency. February 27, 2002 February 28, 2002 1 day
Burrville Elementary School FM-200119291 01 2/28/02 BURRVILLE BOILER ROOM REPLACE LOW H20 CUT-OFF AND PUMP CONTROLS ON BOILER #1 & 2 MODEL #150. CONDENSATE PUMP CONTINUOUSLY RUNNING. WP-200108816 September 6, 2001 February 28, 2002 175 days
Brent Elementary School FM-200100891 01 2/28/02 BRENT BOILER ROOM REPAIR OR REPLACE 8" BALL FLOAT AND ROD TO SUMP PUMP. HC-20000336 January 11, 2001 February 28, 2002 413 days
Bruce-Monroe Elementary School FM-200121045 01 2/28/02 BRUCE-MONROE BOILER ROOM REPAIR HP NATURAL GAS TRAIN TO BOILERS. TRAIN LEAKING GAS FUMES INTO BOILER ROOM. RE: HEALTH HAZZARD, FIRE RISK & ENERGY LOSS. October 4, 2001 February 28, 2002 147 days
Bancroft Elementary School FM-200104399 01 2/28/02 BANCROFT BASEMENT BOILER ROOM MAKE ADJUSTMENT TO FLOAT CONTROL ON CONDENSATE RETURN TANK. LOOSING RETURN THROUGH OVERFLOW TO RETURN TANK, SO BOILER IS TAKING ON CITY WATER MAKE UP. February 27, 2001 February 28, 2002 366 days
Shaw JHS FM-200203732 02 3/1/02 Shaw Boiler room On boiler #3, adjust float on automatic city water feeder. Will not lock out controls when tested. February 28, 2002 March 1, 2002 1 day
Backus Middle School FM-200125625 /01 3/1/02 BACKUS BOILER ROOM REPAIR OR REPLACE AIR COMPRESSOR MOTOR NOT WORKING. A.O. SMITH CORP. HP 1-1/2, PH 2, VOLTS 220, MODEL - PB184MUI, SERIAL - C-61 December 18, 2001 March 1, 2002 73 days
Backus Middle School FM-200126439 /01 3/1/02 BACKUS BOILER ROOM MAKE CORRECTIVE REPAIRS TO NUMBER 2 BURNER PROGRAMMER CONTINUOUSLY GOING OUT ON FLAME FAILURE. ENGINEER HAS MADE SEVERAL ATTEMPTS TO RESET PROGRAMMER WILL RUN FOR SHORT TIME AND GO OUT ON FLAME FAILURE. December 31, 2001 March 1, 2002 60 days
Terrell Mc ES FM-200122063 /01 3/1/02 M.C. TERRELL BOILER ROOM REPAIR OR REPLACE MOTOR TO AIR COMPRESSOR. WP-200108884 October 22, 2001 March 1, 2002 130 days
Green Elementary School FM-200203607 02 3/1/02 Green Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Woodson High School FM-200203613 02 3/1/02 H.D. Woodson Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Savoy Elementary School FM-200203591 02 3/1/02 Savoy Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Harris, C.W. ES FM-200203611 02 3/1/02 C.W. Harris Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Burrville Elementary School FM-200203612 02 3/1/02 Burrville Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Dunbar High School FM-200203736 02 3/1/02 Dunbar Boiler Room Replace several leaking tubes in boiler #1, #2 and #3. See building eengineer for exact location. March 1, 2002 March 1, 2002 0 days
Orr Elementary School FM-200203608 02 3/1/02 Orr Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Winston EC FM-200203590 02 3/1/02 Winston Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Aiton Elementary School FM-200202733 02 3/1/02 Aiton School (Boiler Room) Correct problem with boiler burner #1, will not ignite after completing purge. February 11, 2002 March 1, 2002 18 days
Ballou Senior High School FM-200203596 02 3/1/02 Ballou Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Ferebee-Hope Elementary School FM-200203578 02 3/1/02 Ferebee-Hope Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Johnson JHS FM-200203582 02 3/1/02 Johnson Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Leckie Elementary School FM-200203579 02 3/1/02 Leckie Boiler room PM a/c chiller. February 27, 2002 March 1, 2002 2 days
Ronald H. Brown MS FM-200203656 02 3/2/02 Ron Brown Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Hine JHS FM-200203660 02 3/2/02 Hine Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Bruce-Monroe Elementary School FM-200203700 02 3/2/02 Bruce-Monroe Boiler room PM multistack. February 28, 2002 March 2, 2002 2 days
Seaton Elementary School FM-200203665 02 3/2/02 Seaton Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
West Elementary School FM-200203675 02 3/2/02 West Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Gage-Eckington ES FM-200203695 02 3/2/02 Gage-Eckington Boiler room PM multistack. February 28, 2002 March 2, 2002 2 days
Gibbs Elementary School FM-200203657 02 3/2/02 Gibbs Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Eaton Elementary School FM-200203688 02 3/2/02 Eaton Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Brent Elementary School FM-200203662 02 3/2/02 Brent Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Ludlow-Taylor ES FM-200203658 02 3/2/02 Ludlow-Taylor Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Raymond Elementary School FM-200203671 02 3/2/02 Raymond Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Bell High School FM-200203689 02 3/2/02 Bell Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Thomas Elementary School FM-200203699 02 3/2/02 Thomas. Boiler room PM multistack. February 28, 2002 March 2, 2002 2 days
Wilkinson ES FM-200203698 02 3/2/02 Wilkinson. Boiler room PM multistack. February 28, 2002 March 2, 2002 2 days
Shaed Elementary School FM-200203669 02 3/2/02 Shaed Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Dunbar High School FM-200203702 02 3/2/02 Dunbar Boiler room PM multistack. February 28, 2002 March 2, 2002 2 days
Walker-Jones EC FM-200203663 02 3/2/02 Walker-Jones Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Anacostia Senior High School FM-200203701 02 3/2/02 Anacostia Boiler room PM multistack. February 28, 2002 March 2, 2002 2 days
Clark Elementary School FM-200203677 02 3/2/02 Clark Boiler room PM a/c chiller. February 28, 2002 March 2, 2002 2 days
Wilson J. O. ES FM-200104498 2/28/01 3/4/02 WILSON, J.O. BOILER ROOM REPLACE #1 HOUSE CIRCULATING PUMP THAT IS MISSING / SEE C. EMERSON. February 28, 2001 March 4, 2002 369 days
Bowen Elementary School FM-200202428 02 3/4/02 ANTHONY BOWEN BOILER BOILERS # 1 & 2 REPAIR PUMP CONTROL, UNIT DOES NOT FEED CONDENSATE BACK TO BOILERS IN AN ADEQUATE AMOUNT OF TIME . BOILERS ARE CONSTANTLY CUTTING OFF ON LOW WATER. February 5, 2002 March 4, 2002 27 days
Watkins Elementary School FM-200202999 02 3/4/02 WATKINS BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2. BOILER #1 HAS (2) TWO LEAKING TUBES. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/14/02 HORNE ENGINEER: BIPIN NANAVATY February 14, 2002 March 4, 2002 18 days
Takoma Educational Center FM-200121622 /01 3/4/02 TAKOMA BOILER ROOM REPLACE REDUCING REGULATOR VALVE ON REDUCING SSTATION ON PNEUMATIC SYSTEM FOR BUILDING SENDING TOO MUCH AIR THROUGH REEP POPING RELIEF VALVE MAY DAMAGE CONTROLS FOR BUILDING. NEED WORK COMPLETED TO CHANGE OVER SYSTEM FOR HEAT. October 15, 2001 March 4, 2002 140 days
Wilson J. O. ES FM-200123401 /01 3/4/02 J.O. WILSON BOILER ROOM REPLACE LEAKING MECHANICAL SEALS ON NUMBER ONE PUMP. November 15, 2001 March 4, 2002 109 days
Hyde Elementary School FM-200103237 01 3/4/02 HYDE BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE TWO (2) INCH SOLENOID VALVE ON BOILER FEED LINE FROM CONDESATE RETURN TANK ON BOILER #2. VALVE IS LEAKING AND CAN NOT BE REPAIRED. VALVE IS 110 VOLT, 110 AMP, MODEL #5211AF02N5JJ2, SERIAL 9812U. POC: MR. JONATHAN EMERSON CELL PHONE# (202)438-7308 February 8, 2001 March 4, 2002 389 days
Maury Elementary School FM-200201320 02 3/4/02 MAURY BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2.BOILER #2, REPLACE LEAKING TUBES. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/30/02 DONALD MAGLIENTI - HORNE ENGINEERING (RE) January 18, 2002 March 4, 2002 45 days
Brent Elementary School FM-200124961 /01 3/4/02 BRENT BOILER ROOM REPAIR BOILER #1 BURNER, IT CUT OFF ON FLAME FAILURE. (NEW BURNERS) Contractor: A.C.I. December 12, 2001 March 4, 2002 82 days
Truesdell Elementary FM-200121625 /01 3/4/02 TRUESDELL BOILER ROOM REPAIR BURNER ON BOILER #1. October 15, 2001 March 4, 2002 140 days
Wilson J. O. ES FM-200202963 02 3/4/02 Wilson J.O. (boiler Room) "HOT" Repair/replace oil pump on burner pump. Pump is leaking oil. February 13, 2002 March 4, 2002 19 days
Wilson J. O. ES FM-200202725 02 3/4/02 WILSON, J.O. BOILER ROOM REPAIR BOILER #2 BURNER, BURNER NEEDS ADJUSTMENTS. WORK IS COMPLETED February 11, 2002 March 4, 2002 21 days
Smothers ES FM-200122832 01 3/4/02 SMOTHER BOILER ROOM REPLACE 2 MOTORS ON RETURN TANK PUMP #1 & #4. MOTORS ARE BAD. BALDOR MOTOR, CAT. - CJL1301A, SER. W191, SPEC. 34F305599, VOLT. 115-208-230, FR. 56J, HP. .33, AMP. 3/3.2.3, RPM 1725, HZ 60, PH 1, CLASS B. November 2, 2001 March 4, 2002 122 days
Orr Elementary School FM-200203834 02 3/5/02 ORR SCHOOL (boiler room) Ck operation of AHU, unit continuously trips out on low limit (freeze stat). March 5, 2002 March 5, 2002 0 days
Deal Junior High School FM-200202351 02 3/5/02 DEAL JHS BOILER ROOM "EMERGENCY NO HEAT" BOILER # 2 BURNER OUT ON FLAME FAILURE # 3 WILL NOT IGNITE. February 4, 2002 March 5, 2002 29 days
Roosevelt High School FM-200126451 /01 3/5/02 ROOSEVELT BOILER ROOM FURNISH THE FOLLOWING ITEMS,SO THAT HOT WATER HEATER CAN BE INSTALLED IN BOILER ROOM. December 31, 2001 March 5, 2002 64 days
Davis Elementary School FM-200203290 02 3/5/02 Davis Boiler Room Survey and make necessary repairs to boiler #2. Boiler is off on flame failure. February 22, 2002 March 5, 2002 11 days
John Burroughs ES FM-200101228 13/01 3/5/02 Burroughs Boiler Room, Basement Level Replace mechanical seal on condensate return pump #2, seals are leaking causing loss of water in the system. Pump: Magnetek Century Electric, 2.0hp, Cat. No. #H733, Part No. #8-135804-02, Amps: 6.0-5/2.75, Volts: 200-230/460, RPM: 3450/2850, Type:SC January 13, 2001 March 5, 2002 416 days
Lincoln Middle School FM-200203441 02 3/5/02 Lincoln ***Emergency*** 1st Floor Kitchen Sewage is coming into the kitchen & boiler room areas from a drain backup. The problem has been ongoing---was repaired two weeks ago. February 26, 2002 March 5, 2002 7 days
West Elementary School FM-200203884 02 3/7/02 West Boiler room Repair or replace 1/8" copper line at the burner that is leaking oil. This line has a hole in it and oil is leaking from it. Engineer had to valve off oil at the burner. March 5, 2002 March 7, 2002 2 days
Deal Junior High School FM-200203769 02 3/7/02 DEAL BOILER ROOM BOILER #2 AND #3 KEEP GOING OUT ON FLAME FAILURE March 4, 2002 March 7, 2002 3 days
Eliot Junior High School FM-200117167 01 3/11/02 ELIOT BASEMENT BOILER ROOM BOILER #3 WILL NOT START OUT ON AUX. LIMIT LOCKOUT. WP-200108854 August 13, 2001 March 11, 2002 210 days
Walker-Jones EC FM-200122924 01 3/11/02 WALKER-JONES BOILER ROOM UNSTOP DRAINS IN BOILER ROOM. THREE DRAIN STOP UP. (3). WP-200107610 November 6, 2001 March 11, 2002 125 days
Cleveland Elementary School FM-200204030 02 3/11/02 (Cleveland) ****Urgent**** Basement Boiler Room Exit Door Boiler room exit door needs a panic bar installed on it. A padlock now used cannot be left off because the door can be pulled open from the outside and this poses a safety hazard to both students and staff. March 7, 2002 March 11, 2002 4 days
Jefferson JHS FM-200204194 02 3/11/02 Jefferson Boiler room Unstop drains in boiler room (in rear of boiler #3, beside condensate tank). March 11, 2002 March 11, 2002 0 days
Ronald H. Brown MS FM-200203799 02 3/11/02 Ron Brown exterior boiler room door Replace/rekey existing lock cylinders for newly installed doors for boiler room entrance - lock cylinders should be keyed to master and bldg. key code. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/04/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG 03/04/02) March 4, 2002 March 11, 2002 7 days
Shaed Elementary School FM-200204182 02 3/12/02 Shaed Boiler room Furnish materials to repair or replace sump pump. Will not operate, boiler room flooded. Emergency March 11, 2002 March 12, 2002 1 day
Slowe Elementary School FM-200122915 01 3/13/02 SLOWE BOILER ROOM REPAIR NATURAL GAS LEAK IN BIOLER ROOM. November 6, 2001 March 13, 2002 127 days
Roosevelt High School FM-200204356 02 3/13/02 Roosevelt Boiler room Install hot water heater thats located in basement mechanical room. March 13, 2002 March 13, 2002 0 days
Stuart-Hobson Middle School FM-200204197 02 3/13/02 Stuart-Hobson Boiler Room Repair #3 burner, burner cuts off on flaime failure. March 11, 2002 March 13, 2002 2 days
Francis Junior High School FM-200203946 02 3/14/02 Francis/Brookland Boiler room doors Repin new lock to DCPS master key and pass key. March 6, 2002 March 14, 2002 8 days
Cook J.F. Elementary School FM-200118872 01 3/14/02 COOK, J.F. BOILER ROOM 1) RESTORE OPERATION OF HVAC EQUIPMENT DAMAGED BY FLOODING CAUSED BY, HEAVY RAIN. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/01/01 HORNE ENGINEER: ROGER KAGER August 30, 2001 March 14, 2002 196 days
Langdon Elementary School FM-200122762 01 3/14/02 LANGDON BOILER ROOM REPLACE DOUBLE SHAFT MOTOR TO UNIVENT. NO INFORMATION ON MOTOR. WP-200108825 November 1, 2001 March 14, 2002 133 days
Roosevelt High School FM-200204447 02 3/15/02 Roosevelt Boiler room Install hot water heater thats located in basement mechanical room. March 13, 2002 March 15, 2002 2 days
Young Elementary School FM-200203692 02 3/15/02 Young Boiler room PM a/c chiller. February 28, 2002 March 15, 2002 15 days
Malcolm X ES FM-200203693 02 3/15/02 MalcolmX Boiler room PM a/c chiller. February 28, 2002 March 15, 2002 15 days
Beers Elementary School FM-200203614 02 3/15/02 Beers Boiler room PM a/c chiller. February 27, 2002 March 15, 2002 16 days
Benjamin Banneker Academic HS FM-200204358 02 3/15/02 Banneker Boiler room Repair or replace h/w circulating pump on return line on domestic hot water tank. Pump is leaking badly. March 13, 2002 March 15, 2002 2 days
Orr Elementary School FM-200203417 02 3/15/02 Orr ES Boiler room 1. Asbestos assestment required 2. Replace leaking 2" tubes in boiler #1 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/01/02. HORNE ENGINEEERING - SAM EBRAHIM (RG 03/04/02) February 25, 2002 March 15, 2002 18 days
Duke Ellington School FM-200204508 02 3/17/02 Ellington Boiler room PM a/c chiller. March 15, 2002 March 17, 2002 2 days
Coolidge High School FM-200201753 02 3/18/02 COOLIDGE BOILER ROOM FURNISH REPLACEMENT FOR LEAKING THRUSH BEARING ASSEMLY ON #2 DOMESTIC HOT WATER PUMP IN BOILER ROOM. TYPE AB-210, SER.#8288N, MOD.#TCB, PART#B15 FLANGED PUMP END. January 25, 2002 March 18, 2002 52 days
Roosevelt High School FM-200204497 02 3/18/02 Roosevelt Boiler room Repair lock to boiler room egress door. March 15, 2002 March 18, 2002 3 days
Shepherd ES FM-200204503 02 3/18/02 Shepherd Boiler Room and Pump Rm. 1st fl. Mech. Rm. 2nd fl. Provide keys and or repair or replace locking mechanism (key and knob type). Total of three (3) interior doors. Key alike (5). Note: No keys and these areas must be secured daily. March 15, 2002 March 18, 2002 3 days
Tyler Elementary School FM-200203084 02 3/18/02 Tyler Boiler room Repair or replace air compressor, unit is tripping circuit breaker. February 19, 2002 March 18, 2002 27 days
Cardozo High School FM-200202731 02 3/18/02 CARDOZO BOILER ROOM FURNISH MATERIALS TO REPLACE CORRODED 3" GALVINIZED DOMESTIC WATER MAIN. HOT ITEM!!!!! February 11, 2002 March 18, 2002 35 days
School WW High School FM-200123144 01 3/18/02 SCHOOL WITHOUT WALLS BOILER ROOM REPLACE PROGRAM BOX ON #1 BOILER, IT GOES OFF ON PRESSURE, WILL NOT COME BACK ON. HONEY/WELL RA890F-1270-F1270-83300- 120V -29 November 9, 2001 March 18, 2002 129 days
Coolidge High School FM-200120742 01 3/18/02 COOLIDGE URGENT!!!! BOILER ROOM ENTRANCE DOOR 1) DOOR WILL NOT LOCK PROPERLY. THIS IS A SECURITY BREECH!! October 1, 2001 March 18, 2002 168 days
Payne Elementary School FM-200204559 02 3/19/02 Payne Boiler room Replace 2" discharge line on the sump pump with copper pipe. March 18, 2002 March 19, 2002 1 day
Davis Elementary School FM-200203654 02 3/20/02 (Davis) Fire code violation: 1. Asbestos assessment required. Basement/Boiler room: Exposed wires next to pump in the boiler room. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/06/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG 03/06/02) February 28, 2002 March 20, 2002 20 days
Eastern High School FM-200106912 01 3/20/02 EASTERN BOILER ROOM UNSTOP 2" DISCHARGE LINE FOR PUMPS March 29, 2001 March 20, 2002 356 days
Bancroft Elementary School FM-200116965 01 3/20/02 BANCROFT BASEMENT - BOILER ROOM ASBESTOS ASSESSMENT REQUIRED. TSI, REMOVAL IN TUNNEL. BURST PIPE AND WATER IS RUNNING OUT HEAVILY FROM THE PIPE. (4") WATER IS FLOWING ALL OVER THE AREA. LOCATION IS IN TUNNEL. ISOLATE EMERGENCY!!! ENVIROBATE (IT GROUP)/7461-6848 CODE A - ASBESTOS ABATED ON 12/19/01 (SG) PER RONALD EDWARDS CONFIRMATION. August 8, 2001 March 20, 2002 224 days
Stuart-Hobson Middle School FM-200126631 02 3/20/02 STUART-HOBSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR LEAKING 3" RETURN LINE AT CONDENSATION TANK. ADBESTOS CODE A - CLEAR FOR REPAIRS ON 01/04/02. HORNE ENGINEERING - PHILP CONNOLLY January 3, 2002 March 20, 2002 76 days
Davis Elementary School FM-200203653 02 3/20/02 (Davis) Fire code violation: 1. Asbestos assessment required. Basement/Boiler room: Expose wires on junction box in boiler room. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/06/02. RICHARD GIBSON - SAFETY (202)576-5584 (RG 03/06/02) February 28, 2002 March 20, 2002 20 days
Ronald H. Brown MS FM-200204742 02 3/21/02 BROWN, RON Boiler Room 1. Rekey - 3 newly installed doors to master - bldgs keys as has been previosly performed by DCPS locksmith. Asbestos Code A - Clear For Repairs On 03/20/02. DCPS-Safety - Richard Gibson 576-5584 (RG 03/20/02) 2. Rekey/replace key and knob lock for entrance door leading to mech. room. No key is available. Security/safety concerns exist due to students having access to the area. March 20, 2002 March 21, 2002 1 day
Brent Elementary School FM-200104191 01 3/21/02 BRENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED ON #1 & 2 BOILERS FEEDWATER AND BY-PASS WATER LINES. 2. REPLACE 6 GATE VALVES ON BOILER FEEDWATER SUPPLY LINE, 2-3/4" THREADED BALL VALVES, 4-3/4" THREADED GATE VALVES. CODE A - ASBESTOS ABATED ON 3/31/01. ASBESTOS CODE A-CLAIR FOR REPAIR ON 9/25/01 BY HORNE ENGINEER STEPHEN CALDWELL February 23, 2001 March 21, 2002 391 days
Brent Elementary School FM-200120889 01 3/22/02 BRENT BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE (4) APPROX. 4" VIBRATOR ELOMINATOR ON HOUSE PUMPS (1) ONE VIBRATOR ELOMININATOR IS RUPTURED. HOT ASBESTOS CODE A-CLEAR FOR REPAIRS BY 10/13/01 HORNE ENGINEER TROY WILCOME October 3, 2001 March 22, 2002 170 days
Brent Elementary School FM-200202035 02 3/22/02 BRENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. 8" PNEUMATIC VALVE ON SUPPLY LINE NEEDS REPAIR/REPLACE (LEAKING). SHERYLL JAMES January 29, 2002 March 22, 2002 52 days
Plummer Elementary School FM-200117164 01 3/22/02 PLUMMER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR LEAKING TUBES IN BOILER #2. ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/23/01 HORNE ENGINEER : EDWARD RODRIGUEZ August 13, 2001 March 22, 2002 221 days
Smothers ES FM-200115680 01 3/22/02 SMOTHERS BOILER ROOM REPLACE FEEDWATER REGULATOR ON BOILER #1, 2. COMPLETE ASST. MODEL N-51-2, MAX BOILER PRESS. 35 PSI ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/04/01. HORNE ENGINEERING - EDWARD RODRIGUEZ July 23, 2001 March 22, 2002 242 days
Kimball Elementary School FM-200113495 01 3/22/02 KIMBALL BOILER ROOM (1) ASBESTOS ASSESSMENT IS REQUIRED (2) REPLACE LEAKING TUBES IN BOILER #2. ASBESTOS CODE A- CLEAR FOR REPAIRS ON 06/22/01. June 18, 2001 March 22, 2002 277 days
Tubman Elementary School FM-200118061 01 3/22/02 TUBMAN BOILER ROOM 1. ASSBESTOS ASSESSMENT REQUIRED. 2. RE-THREAD WATER LEG ON BOILER #2, SIZE 2, THREAD IS BAD. ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER TROY WILCOME August 22, 2001 March 22, 2002 212 days
Wilson J. O. ES FM-200201799 02 3/22/02 J.O. WILSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE 4" LEAKING RETURN LINE IN BOILER ROOM (HEATING HOT WATER). ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/29/02 BY HORNE ENGINEER: PHELP CONNALL January 25, 2002 March 22, 2002 56 days
Cardozo High School FM-200203739 02 3/25/02 Cardozo Boiler room Replace program contacts for boiler #3 - burner will not start- Mainflame failure. Boiler #1 -burner repairs/parts needed. Boiler #2 - tubes replacement needed. (Down) Building has no heat as of 3/18/02 March 1, 2002 March 25, 2002 24 days
Woodson High School FM-200204979 02 3/27/02 H.D. Woodson Boiler room Repair burner #2 off on flame failure. March 27, 2002 March 27, 2002 0 days
Deal Junior High School FM-200205004 02 3/27/02 Deal Boiler room Repair hartford loop on boiler #2. March 27, 2002 March 27, 2002 0 days
Woodson High School FM-200204996 02 3/28/02 H.D. Woodson Boiler room 1. Asbestos assessment required. 2. Repair ruptured 1/2" hot water heating line. Asbestos Code A - Clear For Repairs On 03/27/02. Horne Engineering - Troy Wilcome (RG 03/27/02) March 27, 2002 March 28, 2002 1 day
Woodson High School FM-200204971 02 3/28/02 Woodson, H.D Boiler room 1.Asbestos assessment required. 2.Repair or replace port valve on #13 pump strainer. Asbestos Code A - Clear For Repairs On 03/27/02. Horne Engineering - Philp Connolly (RG 03/27/02) March 27, 2002 March 28, 2002 1 day
Ballou Senior High School FM-200125654 /01 3/28/02 BALLOU BOILER ROOM REPLACE (1) ONE MAGNETIC STARTER FOR THE DOMESTIC HOT WATER PUMP. INFO: MAGNETIC STARTER SQUARE D TYPE SBG2, CLASS 8536, COIL # 31041-400-60. December 18, 2001 March 28, 2002 100 days
Wilkinson ES FM-200204950 02 4/1/02 (Wilkinson) **Urgent** 1. Asbestos assessment required. Boiler room: Need key removed from cylinder in lock; staff unable to remove. (Need assistance from locksmith) Asbestos Code A - Clear For Repairs On 03/27/02. Horne Engineering - Sharon Voss (RG 03/27/02) March 26, 2002 April 1, 2002 6 days
Patricia R Harris Ed Center FM-200202950 02 4/3/02 P.R. Harris Boiler room 1. Repair or replace entrance doors to Boiler room from outside stairwell. Doors drag and is hard to open. 2. Replace damage key knob lock on same door as request above locks. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/14/02 HORNE ENGINEER: STEPHEN CALDWELL February 13, 2002 April 3, 2002 49 days
Backus Middle School FM-200204297 02 4/4/02 BACKUS BOILER ROOM Furnish materials to replace broken sewer ejector pump. NOTE: Urgent, flooding boiler room. March 12, 2002 April 4, 2002 23 days
Cook J.F. Elementary School FM-200204298 02 4/4/02 COOK, J.F. BOILER ROOM Furnish materials to replace broken sewer ejector pump. NOTE: Urgent, flooding boiler room. March 12, 2002 April 4, 2002 23 days
Wilson J. O. ES FM-200203140 02 4/4/02 WILSON,J.O. BOILER ROOM FURNISH MATERIALS TO REPLACE DOMESTIC HOT WATER HEATER TANK. TANK IS LEAKING AT THE BOTTOM WHERE THEY ARE RUSTED OUT. HOT!!!!! February 20, 2002 April 4, 2002 43 days
Watkins Elementary School FM-200205481 02 4/5/02 Watkins Boiler Room Unstop drain in airway of stairs. April 5, 2002 April 5, 2002 0 days
Tubman Elementary School FM-200108452 01 4/8/02 TUBMAN BOILER ROOM 1. ASBESTOS ASSESSSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. REPAIR OR REPLACE GATE VALVE ON COLD WATER SUPPLY LINE OVEN TO OF BOILER #2 (3/4" VALVE) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/20/01. NEED ANOTHER ASSESSMENT PER C. BRADLEY 5/21/01 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/19/01. ROGER KAGER - HORNE ENGINEERING April 16, 2001 April 8, 2002 357 days
Backus Middle School FM-200126862 02 4/8/02 BACKUS BOILER ROOM FURNISH MATERIALS TO REPLACE SEWAGE PUMP IN BOILER ROOM. EXISTING PUMP IS BURNED OUT. January 7, 2002 April 8, 2002 91 days
Davis Elementary School FM-200116633 01 4/9/02 DAVIS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REMOVE AND REPLACE (2) 2" NIPPLES ON BOILERS. CODE A-CLEAR FOR REPAIR BY HORME ENG. 8/14/01. (CEB) August 3, 2001 April 9, 2002 249 days
Woodson High School FM-200104342 01 4/9/02 WOODSON, H.D. BASEMENT - BOILER ROOM 1) ASBESTOS ASSESSMENT REQUIRED 2) INSTALL NEW HAND-WASH SINK WITH NEW FAUCET AND ALL CONTROL. VALUES FOR HOT AND COLD WATER. REPLACING OLD SINK NOT WORKING. Asbestos Code A - Clear for Repair February 26, 2001 April 9, 2002 407 days
Watkins Elementary School FM-200202353 02 4/9/02 WATKINS SCHOOL BOILER ROOM REPAIR BOILER #2 OUT ON FLAME FAILURE. BOILER # 1 DOWN DUE TO RELEIF VALVE. February 4, 2002 April 9, 2002 64 days
Amidon Elementary School FM-200122557 /01 4/9/02 AMIDON BOILER ROOM 1) REPAIR BURNER #1,CUT OUT ON AIR/COM NO HEAT October 30, 2001 April 9, 2002 161 days
Francis Junior High School FM-200123320 /01 4/9/02 FRANCIS BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE 15 FT. OF 1/2 " RETURN LINE THAT LEAKING STEAM ,ALSO REPLACE 1 1/4" CAP ON THE SUPPLY LINE IN SAME AREA. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/15/01. HORNE ENGINEERING - TROY WILCOME (RG) November 14, 2001 April 9, 2002 146 days
Eaton Elementary School FM-200124422 01 4/10/02 EATON BOILER ROOM REPAIR REFRIGERANT LEAK IN CHILLER. December 4, 2001 April 10, 2002 127 days
Barnard Elementary School FM-200127398 02 4/10/02 BARNARD BOILER ROOM PUMP ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE FAULTY WATER PRESSURE REGULATOR. 3. REGULATOR IS OVER FILLING SYSTEM. WATTS SET 8TD, MODELL #5 MR, RANGE 10-35, MAX. TEMP. 180 DEGREES F, SIZE 3/4, MAX PRESSURE 200 LBS, U5BLP, ASSF 100.3 ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 BY HORNE ENGINEER: STEPHEN CALSWELL January 14, 2002 April 10, 2002 86 days
Rudolph Elementary School FM-200124162 /01 4/10/02 RUDOLPH BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 April 10, 2002 131 days
Barnard Elementary School FM-200205575 02 4/10/02 Barnard Boiler room Fix leak on feed to condensate tank and restrapped line. April 8, 2002 April 10, 2002 2 days
Eaton Elementary School FM-200119663 01 4/10/02 EATON BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE BROKEN IN-LINE CIRCULATING PUMP. 3.FURNISH MATERIAL AS INDICATED ON ATTACHED SHEET. September 12, 2001 April 10, 2002 210 days
Watkins Elementary School FM-200205635 02 4/10/02 Watkins Basement boiler room entrance Outside drain at boiler room door needs to be unstopped. April 9, 2002 April 10, 2002 1 day
Shepherd ES FM-200205655 02 4/11/02 Shepherd Basement boiler room Unstop boiler room drains April 9, 2002 April 11, 2002 2 days
Payne Elementary School FM-200203191 02 4/11/02 PAYNE BOILER ROOM FURNISH MATERIALS TO REPAIR SUMP PUMP IN BOILER ROOM. BOILER ROOM IN FLOODED. PUMP IS NOT WORKING. February 21, 2002 April 11, 2002 49 days
Stuart-Hobson Middle School FM-200203116 02 4/11/02 STUART-HOBSON Boiler room Repair leak from boys toilet in boys locker room. Emergency health hazard. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/21/02 HORNE ENGINEER:PHILIP CONNOLLY February 19, 2002 April 11, 2002 51 days
Ferebee-Hope Elementary School FM-200122348 /01 4/11/02 FEREBEE-HOPE BOILER RM. EXIT (STEPS) WELDER: INSTALL AND REPAIR MISSING METAL STEPS. (FIRE CODE VIOLATION) Requester Phone: 645-3094 October 19, 2001 April 11, 2002 174 days
Ferebee-Hope Elementary School FM-200124130 /01 4/11/02 FEREBEE HOPE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 April 11, 2002 132 days
Ferebee-Hope Elementary School FM-200126499 02 4/11/02 FEREBEE HOPE BOILER ROOM #1 & #2 BOILERS CONTINUOUSLY SHUT-OFF IN FLAME FAILURE. NEEDS SERVICE. January 2, 2002 April 11, 2002 99 days
Ferebee-Hope Elementary School FM-200205693 02 4/11/02 Ferebee-Hope Boiler room Unclog drain behind #1 and #3 boiler. April 10, 2002 April 11, 2002 1 day
Barnard Elementary School FM-200205656 02 4/11/02 Barnard Boiler room Replace or repair 1/2 copper tee on domestic cold water line. tee has a leak. April 9, 2002 April 11, 2002 2 days
Gage-Eckington ES FM-200205745 02 4/12/02 Gage-Eckington Boiler Room Repair or replace (service) leak on multi stack A/C unit in the boiler room. April 12, 2002 April 12, 2002 0 days
Seaton Elementary School FM-200202032 02 4/12/02 SEATON BOILER ROOM REPLACE L.W.C.O ON #2 BOILER (#630. January 29, 2002 April 12, 2002 73 days
Woodson High School FM-200205633 02 4/15/02 H.D. Woodson Boiler room Unstop floor drain blockage in boiler room. Floor is flooding. April 9, 2002 April 15, 2002 6 days
Thomas Elementary School FM-200205735 02 4/15/02 Thomas Boiler room Repair corroded 1 1/4" discharge line for sump pump #1. April 11, 2002 April 15, 2002 4 days
River Terrace ES FM-200205734 02 4/15/02 River Terrace Boiler room Replace amplifier for burner #1. Burner will not ignite - low purge lock out. April 11, 2002 April 15, 2002 4 days
Hart Middle School FM-200202434 02 4/16/02 HART BOILER ROOM BOILER#1 REPAIR BUNER - GOES OUT ON LOW GAS PRESSURE February 5, 2002 April 16, 2002 70 days
Shaw JHS FM-200203691 02 4/16/02 Shaw Boiler room PM a/c chiller. February 28, 2002 April 16, 2002 47 days
Hart Middle School FM-200205711 02 4/16/02 Hart Boiler room Blower starter on boiler #3 keeps tripping, causing boiler to go into flame failure. A.) Blower starter trips multiple times during course of a work day. April 11, 2002 April 16, 2002 5 days
Simon Elementary School FM-200124166 /01 4/17/02 SIMON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 April 17, 2002 138 days
Stoddert ES FM-200124170 /01 4/17/02 STODDERT BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 April 17, 2002 138 days
Shaw JHS FM-200205937 02 4/17/02 Shaw Boiler Room Replace rupture disc on the chill, vaccum system down, and recharge system. April 17, 2002 April 17, 2002 0 days
Orr Elementary School FM-200206054 02 4/18/02 Orr (Boiler room) Ck operation of chiller, will not run April 18, 2002 April 18, 2002 0 days
Ballou Senior High School FM-200115390 01 4/18/02 BALLOU BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE TWO (2) 8" CHECK VALVES ON THE CHILL WATER LINES THAT CONNECT TO TWO (2) CHILL WATER CIRCULATING PUMPS. NOTE: CHECK VALVES ARE NEEDED FOR HEATING AND COOLING PURPOSE. CODE A - CLEAR FOR REPAIR AS OF 7/25/01 (SG). July 19, 2001 April 18, 2002 273 days
Payne Elementary School FM-200205939 02 4/19/02 (Payne) ****Very Urgent**** Boiler room: Engineer discovered boiler room door open with key broke off in the door on arrival in the a.m. It appeared to him that the door was left open on the night before. April 17, 2002 April 19, 2002 2 days
Eaton Elementary School FM-200206140 02 4/19/02 Eaton Boiler room #1 & 2 chiller compressors need repair/replacement. #2 will not start and #1 needs charging with freon. Type Trane a/c units. Page 2 has information on chiller compressors. April 19, 2002 April 19, 2002 0 days
Payne Elementary School FM-200205998 02 4/19/02 Payne Boiler room entrance door Repair lock on boiler room entrance door, lock does not work. April 18, 2002 April 19, 2002 1 day
Seaton Elementary School FM-200205953 02 4/19/02 Seaton Boiler room Repair or replace 1-1/2 gate valve from the cold water main line. Valve is leaking in a closed position. There is no cold water at this time. April 17, 2002 April 19, 2002 2 days
Webb Elementary School FM-200206009 02 4/22/02 Webb Boiler Room Check and repair or replace gas pressure regulator on #1 boiler. April 18, 2002 April 22, 2002 4 days
Wilson High School FM-200206199 02 4/22/02 Wilson, W. !!! Emergency !!! Outside - Boiler Room Lighting hit the Tree on Friday and it fell down in the Parking Lot. April 22, 2002 April 22, 2002 0 days
Jessie LaSalle Elementary FM-200206241 02 4/23/02 Lasalle Boiler room Repair or replace sump pump motor and shaft. Motor has burning smell and shafts frozen. Plate information missing. April 22, 2002 April 23, 2002 1 day
Backus Middle School FM-200206253 02 4/23/02 Backus Boiler room Repair or replace centrifugal motor. Pump isn't circulating properly. Marathon Electric - high efficient, cat. no. e721, rpm 1760/1466, model no. 6V215T11B4926ANX, ph 3, type 7DR, hp - 10/7.5, hz - 60/50. April 22, 2002 April 23, 2002 1 day
Garfield ES FM-200202775 02 4/25/02 Garfield School (boiler Room) Repair # 2 boiler burner will not modulate from low to high fire. February 11, 2002 April 25, 2002 73 days
Stuart-Hobson Middle School FM-200206681 02 4/26/02 Stuart-Hopson Boiler room Repair or replace sump pump in boiler room. April 26, 2002 April 26, 2002 0 days
Clark Elementary School FM-200206097 02 4/26/02 Clarke School (Boiler room) Ck operation of air compressor, will not maintain pressure for chiller operation April 19, 2002 April 26, 2002 7 days
Eaton Elementary School FM-200206691 02 4/28/02 Eaton Boiler room Repair or replace broken city water supply line for the boiler room service area. 1 inch galvanized pipe 20 feet long broken off. Needs repair or replace. April 26, 2002 April 28, 2002 2 days
Malcolm X ES FM-200205736 02 4/28/02 Malcolm X Boiler room Snake out and clear four floor drains as marked for proper drainage of water when clearing floor. April 11, 2002 April 28, 2002 17 days
Wilson J. O. ES FM-200205109 02 4/29/02 J.O. Wilson Boiler room 1. Asbestos assessment required. Install electrical service to hot water heater electronic ignition. Asbestos code A - Clear for repairs on 04/05/02. DCPS Safety - Ronald Edwards (202) 576-6693 (RG 04/08/02 ) March 26, 2002 April 29, 2002 34 days
Stuart-Hobson Middle School FM-200206683 02 4/29/02 Stuart-Hopson Boiler room Repair Lochinvar domestic hot water heater. Heater will not start. April 26, 2002 April 29, 2002 3 days
Bell High School FM-200205959 02 4/29/02 Bell Boiler room Repair inoperable air conditioning unit in boiler room. Appears to be a flow control problem. April 17, 2002 April 29, 2002 12 days
Bell High School FM-200206789 02 4/30/02 Bell Boiler room Chiller appears to need refrigerant added to system. R-11 is refrigerant type. Re-charge as needed. April 29, 2002 April 30, 2002 1 day
Hine JHS FM-200205934 02 5/1/02 Hine Boiler room Service and start chillers, can not get unit on line. 1.Low Suction 2.Motor current 3.Leak on chiller (water) April 17, 2002 May 1, 2002 14 days
Ferebee-Hope Elementary School FM-200206990 02 5/7/02 Ferebee-Hope Boiler room Repair #2 chiller, chiller will not start. May 2, 2002 May 7, 2002 5 days
Ferebee-Hope Elementary School FM-200206987 02 5/7/02 Ferebee-Hope Basement boiler room Repair inoperable condensor pump #2. May 2, 2002 May 7, 2002 5 days
Shaw JHS FM-200207389 02 5/9/02 Shaw Boiler room Charge A/C chiller with refrigerant that on job sit. Unit will surge at 60%. May 8, 2002 May 9, 2002 1 day
Walker-Jones EC FM-200205826 02 5/10/02 Walker-Jones Boiler room Replace 6" vibrator eliminator on chill water in inlet line on the chiller. Eliminator has pin hole leaks in it. No asessment needed. April 15, 2002 May 10, 2002 25 days
Garnet-Patterson MS FM-200207024 02 5/13/02 Garnet-Patterson Boiler room Drain pipe from roof to boiler room has a leak. Water is flooding boiler room office. May 2, 2002 May 13, 2002 11 days
Cleveland Elementary School FM-200203401 02 5/14/02 (Cleveland) Basement Boiler Room Exit Door Need a panic bar installed on the basement boiler room exit door. Unable to leave padlock off because the door can be pulled open from the outside. This situation poses a safety hazzard for both staff and students. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/26/02 HORNE ENGINEER: STEPHEN CALDWELL February 25, 2002 May 14, 2002 78 days
Johnson JHS FM-200207443 02 5/14/02 Johnson JHS (boiler room) Ck charge on chiller may need to be recharge. Ck for refrigerant leak on same. May 9, 2002 May 14, 2002 5 days
Ronald H. Brown MS FM-200207183 02 5/15/02 Ron Brown (Boiler room) Replace purge unit discharge line vent line to atomsphere on chiller unit. Line was removed during boiler room renovation. May 6, 2002 May 15, 2002 9 days
Bell High School FM-200207643 02 5/15/02 Bell Boiler Room Check and repair a/c unit. A/C keep cutting off on high head. A/C is down. May 14, 2002 May 15, 2002 1 day
Tubman Elementary School FM-200207630 02 5/16/02 (Tubman) Fire code violation: Boiler room: Exit light out. May 13, 2002 May 16, 2002 3 days
Clark Elementary School FM-200207661 02 5/16/02 Clark Boiler room Repair chiller - cutting on low oil flow. May 14, 2002 May 16, 2002 2 days
Shaw JHS FM-200207925 02 5/20/02 Shaw Boiler Room Charge A/C unit with additional refrigerent, unit will surge at 60%, water temperature will only drop to 52%. May 17, 2002 May 20, 2002 3 days
Shaw JHS FM-200207853 02 5/20/02 Shaw Boiler room Fabricate rod for tube brush (3/8") 2 - 6 ft. lengths. May 16, 2002 May 20, 2002 4 days
Brightwood Elementary School FM-200205289 02 5/22/02 (Brightwood) 1. Asbestos assessment required. 1st floor/boys restroom: Repair 3" PVC trap on 3rd urinal; water leaking into boiler room. Code A-clear for repair by Honre Engineer ( Stephen Caldwell ) on 4/04/02 April 2, 2002 May 22, 2002 50 days
Bowen Elementary School FM-200207733 02 5/22/02 Bowen First Floor - Custodial Office 1) Ruptured line in custodial office bathroom. Engineer can not isolate line, water is running in to Boiler Room. May 15, 2002 May 22, 2002 7 days
Bancroft Elementary School FM-200208077 02 5/22/02 Bancroft ****Urgent**** Basement Boiler Room #4447 The outlet in the basement boiler room sparked, tripped the circuit breaker and the electric power in the room will not come on---needs immediate attention. May 20, 2002 May 22, 2002 2 days
Clark Elementary School FM-200118814 01 5/23/02 CLARK BOILER ROOM TROUBLESHOOT ELECTRICAL SERVICE TO HOT WATER HEATER. August 30, 2001 May 23, 2002 266 days
Brightwood Elementary School FM-200206945 02 5/24/02 Brightwood ****Emergency**** First Floor - Boys Bathroom 1) Urinal leaking down into Boiler Room. Leaking from 4 inch PCV trap. Reassigned/forwarded to BPO [Kramer] per James Vernon. May 1, 2002 May 24, 2002 23 days
Amidon Elementary School FM-200208568 02 5/29/02 Amidon (boiler room) R/R ruptured domestic water line over boiler. May 29, 2002 May 29, 2002 0 days
Clark Elementary School FM-200208720 02 5/31/02 Clark Boiler room Chiller is down with low refrigerant. May 31, 2002 May 31, 2002 0 days
Wilkinson ES FM-200113154 01 6/3/02 WILKINSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. FURNISH KEY TO BOILER ROOM EXTERIOR DOOR. ENGINEER CAN NOT ENTER TO PROVIDE HVAC SERVICES. Requester Phone: 698-1750 Requestor Phone: 698-1750 ASBESTOS CODE A-CLEAR FOR REPAIR BY L MINTON DCPS . ON 9/10/01. May 18, 2001 June 3, 2002 381 days
Duke Ellington School FM-200206094 02 6/3/02 Ellington Boiler Room Repair or replace or recharge #1 compressor on the chiller unit, will run but, must be reset each time the unit is satisfied. April 19, 2002 June 3, 2002 45 days
Leckie Elementary School FM-200208625 02 6/6/02 Leckie Boiler room Repair Air conditioning unit No air getting to receiver control. A/C unit is off line May 29, 2002 June 6, 2002 8 days
Hine JHS FM-200206621 02 6/6/02 Hine Boiler room 1. Asbestos assessment required. 2. Locate water leak on chillers chill water side under unit, unit jacket. Insulation must be removed to locate and repair. Code A-clear for repair by Horne Engineer by ( Bipin Nanavaty ) on 4/26/02 ( CEB ) April 25, 2002 June 6, 2002 42 days
Ludlow-Taylor ES FM-200209017 02 6/7/02 Ludlow-Taylor Boiler Room Check and restart a/c chiller. June 5, 2002 June 7, 2002 2 days
Harris, C.W. ES FM-200110043 01 6/7/02 C.W. HARRIS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED FOR WORK PERMIT. 2. REPAIR OR REPLACE 4" GATE VALVE OF CHILL WTER LINE, GATE VALVE LEAKING AND IS 25 FT,. HIGH FROM FLOOR. THIS WILL PROVIDE COOLING FOR THE BUILDING. Asbestos Code A - Clear For Repairs On 05/14/01. Horne Engineering - Bipin Nanavaty (RG 03/19/02) May 11, 2001 June 7, 2002 392 days
Reed LC FM-200209247 02 6/12/02 Reed Boiler room Replace rupture line on chill water pumps, cooling tower. June 10, 2002 June 12, 2002 2 days
Reed LC FM-200209268 02 6/12/02 Reed ****Emergency**** Basement Boiler Room Check all electrical power to chiller and electrical system in the boiler room. [Emergency phoned in on Sunday, June 9, 2002.] June 10, 2002 June 12, 2002 2 days
Roosevelt High School FM-200108112 01 6/13/02 (ROOSEVELT) (1) ASBESTOS ASSESSMENT REQUIRED. EXTERIOR OF BUILDING/NEAR BOILER ROOM: REMOVE GRAFFITI. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/11/01. April 11, 2001 June 13, 2002 428 days
Bancroft Elementary School FM-200204225 02 6/13/02 Boiler room Send electrician to disconnect electrical service from old domestic hot water heater and reconnect after new domestic hot water heater has been installed. March 11, 2002 June 13, 2002 94 days
Cooke H.D. Elementary School FM-200207378 02 6/13/02 (Cooke, H.D.) Fire Code Violation: Ground Floor/Boiler room: Exit light out. May 8, 2002 June 13, 2002 36 days
Reed LC FM-200209330 02 6/14/02 Reed boiler Room Check chiller, chiller not cooling. June 12, 2002 June 14, 2002 2 days
Clark Elementary School FM-200209384 02 6/14/02 (Clark) Fire code violation: Page 1 of 2 1Asbestos assessment required. 1st Floor/Exit behind boiler room: Defective doors. Code A-cleaar for repair by DCPS Safety Office Leroy Minton on 6/13/02 June 12, 2002 June 14, 2002 2 days
Watkins Elementary School FM-200201043 02 6/17/02 WATKINS BOILER ROOM BLOWDOWN VALVE (2") ON #2 CIRCULATING PUMP NOT HOLDING - R/R. ASBESTOS ASSESSMENT REQUIRED. CODE A -CLEAR FOR REPAIR BY HORNE ENG. SHERYLL JAMES 01-16-02 DCPS SAFETY SHEILA R. HOWARD 01-16-02 January 14, 2002 June 17, 2002 154 days
Coolidge High School FM-200208760 02 6/17/02 Coolidge Boiler room Water heater not working. Determine the problem to be electrical. Send electrician to correct problem. May 31, 2002 June 17, 2002 17 days
Bancroft Elementary School FM-200209329 02 6/19/02 Bancroft Boiler room office Survey breaker # 13 in Main Dist. Panel that keeps tripping. Breaker controls electric to primary wing of bldg. May be a faulty breaker or load problem (correct problem). Breaker only trips during cooling season. Panel board #AF-978261, 120/208 volt, cc/8-type, 120 amps, Plant-P, 3 ph & hw June 12, 2002 June 19, 2002 7 days
Clark Elementary School FM-200209387 02 6/19/02 (Clark) Fire code violation: Page 1 of 2 1Asbestos assessment required. 1st Floor/Exit behind boiler room: Defective Panic bar. Code A-cleaar for repair by DCPS Safety Office Leroy Minton on 6/13/02 June 12, 2002 June 19, 2002 7 days
Watkins Elementary School FM-200122865 01 6/20/02 WATKINS BOILER ROOM REPAIR BURNER #2 WILL NOT START- FLAME FAILURE. WP-200108661 November 5, 2001 June 20, 2002 227 days
Watkins Elementary School FM-200120867 01 6/20/02 WATKINS BOILER ROOM REPLACE SUMP PUMP AT PIT #2. WP-200108661 October 2, 2001 June 20, 2002 261 days
Watkins Elementary School FM-200124589 01 6/20/02 WATKINS BOILER ROOM REPAIR OR REPLACE #1 BURNER. BOILER #1 CUTTING OFF (ON) FLAME FAILURE. December 6, 2001 June 20, 2002 196 days
Garnet-Patterson MS FM-200209915 02 6/21/02 Garnet-Patterson ****Very Urgent**** Basement Boiler Room Replace the lock on the boiler room door. The lock has been damaged and the door opens to the outside of the building. June 20, 2002 June 21, 2002 1 day
Bell High School FM-200203775 02 6/24/02 BELL BOILER ROOM REPAIR BOILER #3. BOILER NEED NEW PROGRAMMER. March 4, 2002 June 24, 2002 112 days
Kenilworth ES FM-200203797 02 6/24/02 Kenilworth School (boiler room) Replace existing inoperable gas hot heater. Mfc. Teledyne Laars, Model N.K. - 400HN01B serial no. 8790319 Need electrican to hook up float switch on hot water heater. March 4, 2002 June 24, 2002 112 days
Bell High School FM-200203497 02 6/24/02 Bell Boiler Room Repair burner on boiler #1. Burner constantly shutting off on flame failure and low water. Note: This is the main boiler for the facility and is needed. February 27, 2002 June 24, 2002 117 days
Ferebee-Hope Elementary School FM-200122734 /01 6/27/02 FEREBEE-HOPE BASEMENT PUMP ROOM UNDER POOL REPAIR OR REPLACE TWO (2) CONDENSATE RETURN PUMPS. NEW CONVERTER INSTALLED AND RETURN (H20) CANNOT RETURN TO BOILER ROOM. WP-200108673 October 31, 2001 June 27, 2002 239 days
Ballou Senior High School FM-200206080 02 6/27/02 Ballou Boiler room Replace Trane Centravac Chiller electrical A/C contactor and coil assembly (for air conditioning). Info: Part : AC contactor - Westinghouse Mech style 2010A22G01 Max. Tl. amps 220, Max Lr amps 1320. Info: Part: Westinghouse size 43 s-1490647C 440v-60 350v-50 ct 220v-25cy April 18, 2002 June 27, 2002 70 days
Shaw JHS FM-200209655 02 6/27/02 Shaw Boiler room Hot water heater was checked by Industrial Equipment Mechanic and was determined that it was not a plumbing problem but an electrical problem. Project should be forwarded to electricians to make necessary repairs. June 17, 2002 June 27, 2002 10 days
Young Elementary School FM-200210585 02 6/28/02 Young Cooling Tower Replace 2" valve on copper line to cooling tower. Water is running from roof to boiler room, because of cracked valve. June 28, 2002 June 28, 2002 0 days
Benning Elementary School FM-200209973 02 7/3/02 Benning (Boiler Room) 1. Check chiller, unit starts making very loud noise while running, as if something is dragging. June 21, 2002 July 3, 2002 12 days
Marshall Educational Center FM-200210555 02 7/3/02 (Marshall) ***Emergency*** Boiler room: No power through-out the building. (Internal problem) Main circuit breaker will not reset at the electrical distribution panel. June 28, 2002 July 3, 2002 5 days
West Elementary School FM-200123482 /01 7/8/02 WEST BOILER ROOM Furnish materials to repair or replace sump pump. Boiler room flooded. November 16, 2001 July 8, 2002 234 days
Thomas Elementary School FM-200206734 02 7/9/02 Navel Thomas Boiler room 1. Asbestos assestment may be required. 2. Replace four(4) - 6" Dia pump isolation valves. two (2) each on cw pump and standby pump. Water appears to be seeping from cw side to chw side, valves are not holding. Code A-clear for repair by Horne Engineer by ( Sharon Voss ) on 4/26/02 ( CEB ) April 26, 2002 July 9, 2002 74 days
West Elementary School FM-200211068 02 7/13/02 West Boiler Room Repair /replace sewer ejector pump in boiler room. July 11, 2002 July 13, 2002 2 days
West Elementary School FM-200210525 02 7/16/02 (West) Fire code violation: Page 1 of 1 1. Asbestos assessment required. Next to boiler room door: Broken door return. Asbestos Code A - Clear for repairs, 6/28/02 DCPS Safety - L. Minton, (RE- 6/28/02) June 27, 2002 July 16, 2002 19 days
West Elementary School FM-200212178 02 7/16/02 (West) **Emergency** Boiler room door/Rear of building: Lock on door does not work, if you shake the door after locking, the door will come open again. July 16, 2002 July 16, 2002 0 days
Bruce-Monroe Elementary School FM-200211127 02 7/19/02 Bruce-Monroe Boiler Room Repair rusted air compressor tank. Welded crack in tank. Replace as needed. July 12, 2002 July 19, 2002 7 days
Bruce-Monroe Elementary School FM-200211128 02 7/19/02 Bruce-Monroe Boiler Room Repaired air filter on air compressor for pneumatic, filter is deteriorated. July 12, 2002 July 19, 2002 7 days
Orr Elementary School FM-200212479 02 7/22/02 ORR Boiler Room Check Chiller tripped out (oil differential switch). Engineer can not reset. July 22, 2002 July 22, 2002 0 days
Bell High School FM-200212679 02 7/23/02 Bell Boiler room Service house air compressor. Unit is not working properly. July 23, 2002 July 23, 2002 0 days
Raymond Elementary School FM-200210076 02 7/24/02 Raymond Boiler room Correct problem thats preventing chiller from going on line. Appears to be a problem with cooling tower fan motor. Name - Dayton model 3KW40B, FR 2137, TYPE FD, PH 3, HP 7.5, RPM 1765, VOLTS 208-230/460 (FL) AMPS 21.1 - 20/10, (SF) AMPS 22.6/11.3, SF 1.15, MODEL REF - DOL-AE-23A-H, CLASS F, SHAFT END BRG-6208-2ZJC3. June 24, 2002 July 24, 2002 30 days
Raymond Elementary School FM-200206777 02 7/24/02 Raymond Boiler room Correct circulating problem from condensor pump to cooling tower. Engineer is unable to get the water flow from pump to tower. April 29, 2002 July 24, 2002 86 days
Woodson High School FM-200213253 02 7/29/02 Woodson Boiler Room Check and make the necessary repairs to #1 and #2 compressors on chiller #1 the compressors will not activate after going through the timing cycle, both chillers are needed during extremly HOT temperature. EMERGENCY!!!!! July 29, 2002 July 29, 2002 0 days
Kimball Elementary School FM-200204740 02 7/30/02 KIMBALL SCHOOL Boiler Room Ck boiler 1 and 2 burners will not ignite or start cycle. since to have power lock out at starter contacts. March 20, 2002 July 30, 2002 132 days
Bell High School FM-200208868 02 8/2/02 Bell Boiler Room 1. Abestos assessment required 2.Check and repair chiller. Chiller keep shutting off, oil switch not coming on within 5 second. Contractor: Boland Service (Trane) POC: Curtis Emerson 438-7434 Asbestos Code A - Clear for repairs on 07/15/02. Horne Engineering - Troy Wilcome (RG 07/15/02) June 4, 2002 August 2, 2002 59 days
Bell High School FM-200213535 02 8/6/02 Bell Boiler Room Replace refrigerant dryer on air compressnr. Is not working properly. August 5, 2002 August 6, 2002 1 day
Kimball Elementary School FM-200213164 02 8/7/02 (Kimball) !!!Emergency!!! Tunnel/Boiler room: Ruptured water line; contractors working in tunnel where there was a minor leak from yesterday, today the leak became a ruptured pipe. July 26, 2002 August 7, 2002 12 days
Hart Middle School FM-200125297 /01 8/9/02 HART BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR RUPTURED EXPANSION TANK BEHIND BOILER #1. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/17/01. HORNE ENGINEERING - Z MAHOOD (RG) December 14, 2001 August 9, 2002 238 days
Johnson JHS FM-200213838 02 8/9/02 Johnson JHS Boiler Room 1. Replace aquastat control, compressor motor inoperable RPM 1725, V 115-230 , Hp 1/3 August 8, 2002 August 9, 2002 1 day
Johnson JHS FM-200213818 02 8/9/02 Johnson JHS Boiler Room 1. Check operation of purge unit motor on chiller. RPM 1725, V 115-230 , Hp 1/3 August 8, 2002 August 9, 2002 1 day
Burrville Elementary School FM-200201905 02 8/12/02 BURRVILLE BOILER ROOM 1. ASBESTOS ASSESTMENT MAY BE REQUIRED. 2. REMOVE FOUR (4) PLUGS ON BOILER # 2. PLUGS ARE SIEZED ON AND CAN NOT BE REMOVED. BOILER NEEDS TO WASHED OUT THROUGHLY. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/30/02 BY HORNE ENGINEER: BIPIN NANAVATY January 28, 2002 August 12, 2002 196 days
Stuart-Hobson Middle School FM-200202789 02 8/12/02 Stuart-Hobson Boiler room 1. Asbestos assessment required. 2. Repair or replace leaking water leg on #2 boiler. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/14/02 HORNE ENGINEER:BIPIN NANAVATY February 11, 2002 August 12, 2002 182 days
Hart Middle School FM-200204289 02 8/13/02 HART BOILER ROOM 1.Asbestos assessment required 2. Repair or replace two (2) gate valves on supply line size (1) 4" valve and (1) 1/2" valve, also (2) gate valves on return line, size (1) 2 1/2" valve and (1) 3" valve, to isolate valves for current leaking valves. DCB (IT Group)/703-461-6848 Code A - Asbestos abated on 03/27-28/02 PER Leroy Minton Jr. confirmation 04/04/02.(RG) March 12, 2002 August 13, 2002 154 days
Shaw JHS FM-200208066 02 8/14/02 Shaw Boiler room Repair or replace ignitor module on hot water heater - Lochinar. May 20, 2002 August 14, 2002 86 days
Johnson JHS FM-200124709 01 8/15/02 JOHNSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE (1) 6" OS&Y VALVE THAT IS LEAKING FROM PACING GLAND ON CWS/HWS LINE. 3. REPLACE PRESSURE RELIEF VALVE ON #2 BOILER, VALVE IS NOT HOLDING. ASBESTOS CODE A-CLEAR FOR REPAIR ON 12-10-01 BY HORNE ENGINEER : EDWARD RODRIGUEZ December 7, 2001 August 15, 2002 251 days
Dunbar High School FM-200213821 02 8/16/02 Repair air conditioner unit in the boiler room ,readout on unit is EX4 interlock. August 8, 2002 August 16, 2002 8 days
Brookland Elementary FM-200214446 02 8/16/02 Brookland Boiler room Adjust float on sump pumps so that water can drain off floor of boiler room August 14, 2002 August 16, 2002 2 days
Maury Elementary School FM-200202034 02 8/18/02 MAURY BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR THE HAND HOLD FRAME AREA (SMOOTH OUT). ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/30/02 BY HORNE ENGINEER: DONALD MAGLIENTI January 29, 2002 August 18, 2002 201 days
Eastern High School FM-200127096 02 8/18/02 EASTERN BOILER ROOM SUB-BASMENT REPIPE COPPER LINES - INLET AND OUTLET OF WATER SOFTNER BACK TO THE EXISTING OILY WATER LINE. THE LINES NEED TO BE 2" OR 2-1/2" IN SIZE AND SOFTNER HEAD TOO. THE SIZE OF IT NOW IS 1"... NOT ENOUGH WATER FLOW. RECOMMENDED VENDOR: TRI-CON ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 BY HORNE ENGINEER: EDWARD RODRIGUEZ January 9, 2002 August 18, 2002 221 days
Green Elementary School FM-200208869 02 8/19/02 Green Boiler Room Chiller keep cutting off. June 4, 2002 August 19, 2002 76 days
Stuart-Hobson Middle School FM-200100886 1/11/01 8/19/02 STUART-HOBSON BOILER ROOM REPAIR OR REPLACE DEFECTIVE BURNED OUT SUMP PUMP. WORK IS NEEDED TO REMOVE SEWER WATER FROM BUILDING (PUMP IS UNDER WATER). HC-20000127 January 11, 2001 August 19, 2002 585 days
Randle-Highlands ES FM-200123431 /01 8/19/02 RANDLE HIGHLAND BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPAIR 3" OR 2" RETURN LINE TO CONDENSATE STORAGE TANK. PIPE IS COVER BY INSULATION ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/27/01 HORNE ENGINEERING - RAYMOND AGNANT (RG) November 15, 2001 August 19, 2002 277 days
Beers Elementary School FM-200212917 02 8/19/02 Beers Boiler Room Check and unstop floor drain in boiler room. Water is on floor. July 25, 2002 August 19, 2002 25 days
Leckie Elementary School FM-200127194 02 8/19/02 LECKIE SCHOOL BOILER ROOM 1. ASBESTOS ASSESTMENT REQUIRED. 2. REPAIR/REPLACE 3 INCH NIPPLE LEAKING FROM THREADS ON RIGHT FRONT MUD LEG. POC - MR. LEONARD SLEDGE 202-438-7454 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 01/10/02. HORNE ENGINEERING - PHILP CONNOLLY (RG) January 10, 2002 August 19, 2002 221 days
Harris, C.W. ES FM-200207140 02 8/19/02 C. W. Harris (boiler room) Check problem with chiller, will not start May 6, 2002 August 19, 2002 105 days
Smothers ES FM-200214469 02 8/19/02 Smothers F-303.4 Fire Code Violation Boiler Room Need key for padlock. August 14, 2002 August 19, 2002 5 days
Thomas Elementary School FM-200201047 02 8/20/02 THOMAS BOILER ROOM CHECK BOILER #2, KEEP GOING OFF ON FLAME FAILURE. January 15, 2002 August 20, 2002 217 days
Shaw JHS FM-200209018 02 8/20/02 Shaw Boiler Room Repair or change chiller unit. Chiller will not load up on hot days. June 5, 2002 August 20, 2002 76 days
Amidon Elementary School FM-200119353 01 8/20/02 AMIDON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. TSI, REMOVAL FROM BOILER #1. REPLACE ONE 6 INCH VALVE ON #2 BOILER MAIN HEADER VALVE. VALVE SIZE 6 INCH WITH EIGHTEEN BOLTS HOLES AND HARDWARE. VALVE NOT HOLDING. CAPE (IT GROUP) 703-461-6848 CODE A - ASBESTOS ABATED ON 11/19/01 (SG) PER SHEILA HOWARDS CONFIRMATION PRIORITY LIST. September 7, 2001 August 20, 2002 347 days
Coolidge High School FM-200214824 02 8/20/02 (Coolidge) !!!Emergency!!! Ground floor/Entrance to boiler room: Unstop drain with two feet of stagnant water where mosquitos and other insects will breed. August 16, 2002 August 20, 2002 4 days
Houston Elementary School FM-200213736 02 8/21/02 (Houston) Fire code violation: 1st Floor/Boiler room: Exit sign out. August 7, 2002 August 21, 2002 14 days
Burrville Elementary School FM-200215154 02 8/22/02 Burrville Boiler Room Check and repair burner. Properly calibrate burner #1 to insure complete combustion. Burner is causing boiler room to fill up with fumes. August 20, 2002 August 22, 2002 2 days
Shaed Elementary School FM-200205337 02 8/22/02 Shaed Boiler Room 1. Asbestos assessment required. 2. Repair boiler #2 rear right water leg. Boiler is leaking from the right rear water leg. Code A-clear for repair by Honre Engineer ( Troy Wilcome ) on 4/04/02 April 3, 2002 August 22, 2002 141 days
School WW High School FM-200206067 02 8/22/02 (School Without Walls) ***Very Very Urgent*** 1. Asbestos assessment required. Boiler room: Continued power loss caused by main elect. panel box. Need to be upgraded from 150 volts to 175 volts; not enough voltage to support current. (The 2nd and 3rd floor is without power) Asbestos Code A - Clear for repairs on 04/26/02. DCPS Safety - Richard Gibson (RG 04/26/02) April 18, 2002 August 22, 2002 126 days
Lincoln Middle School FM-200120464 01 8/23/02 LINCOLN BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE OR REPAIR LEAKING 8 INCH OS&Y VALVES. (TOTAL OF (6) SIX VALVES). SUPPLY AND RETURN LINE TO (3) THREE BOILERS. THREE SUPPLY VALVES ARE APPROXIMATELY 26 INCH HIGH IN THE CEILING. POC CARNAL BRADLEY 202 438 7437 CELL PHONE ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/28/01. HORNE ENGINEERING - ROGER KAGER (RG) September 25, 2001 August 23, 2002 332 days
Thomas Elementary School FM-200202296 02 8/24/02 THOMAS NEVAL BOILER ROOM 1. ASBESTOS ASSESTMENT MAY BE REQUIRED. 2. REPLACE TWO (2) 3/4" DIA- 5 LINEAR FT CHEMICAL FEED LINES LOCATED ON CONDENSATE RETURN LINES. 3. REPLACE APPROX 28" OF 4" DIA. CONDENSOR WATER SUPPLY LINE TO COOLING TOWER. SECTION OF LINE SHOWS SIGN OF CORROSION. ASBESTOS CODE A-CLEAR FOR REPAIR ON 2/05/02 BY HORNE ENGINEER: ROGER KAGER February 1, 2002 August 24, 2002 204 days
Thomas Elementary School FM-200203774 02 8/26/02 THOMAS BOILER ROOM REPAIR BOILER #2. BOILER KEEP GOING OUT ON FLAME FAILURE. March 4, 2002 August 26, 2002 175 days
West Elementary School FM-200212286 02 8/26/02 West 1. Asbestos Assessment Reqd. Boiler Room Door The boiler room door is rusted out at the bottom and will not lock-- need new exit/entrance door [metal]. door. The door is rusted out at the bottom. Asbestos Code A, Clear for repairs on 7/23/02 DCPS Safety, R. Edwards (RE - 7/23/02) July 16, 2002 August 26, 2002 41 days
Anacostia Senior High School FM-200213995 02 8/26/02 Anacostia Boiler room 1. Asbestos assessment required. 2. Patch crack in boiler doors, one and two before putting back online (per boiler inspector). Asbestos/Lead Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) Charles Buchanan on 8/15/02 August 9, 2002 August 26, 2002 17 days
Draper Elementary School FM-200117681 01 8/27/02 DRAPER BOILER ROOM 1) ASBESTOS ASSESSMENT REQUIRED. 2) BASEMENT HALLWAY LEADING TO THE BOILER ROOM - 2" LEAKING GALVANIZED PIPE NEED TO REPLACE PIPE POC :PRESTON MAY 202 345-1542 ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/14/01 RICHARD BYRD OF HORNE ENGINEER August 16, 2001 August 27, 2002 376 days
Orr Elementary School FM-200215687 02 8/29/02 ORR boiler room Repair Trane chiller unit August 27, 2002 August 29, 2002 2 days
Patricia R Harris Ed Center FM-200213819 02 8/29/02 1. Asbestos assessment required 2. Replace leaking tube in # 1 boiler (steem boiler for the kitchen) as per A.Colvin request. Asbeastos Code A-clear for repair by Horne Engineer ( Philip Connolly ) 8/09/02 DCPS Charles Buchanan August 8, 2002 August 29, 2002 21 days
Johnson JHS FM-200214392 02 8/29/02 Johnson - F610.2 Basement - boiler room 1. Exit light out. August 14, 2002 August 29, 2002 15 days
Thomas Elementary School FM-200216083 02 8/29/02 Thomas Boiler room Check boiler room flooding sump pumps inoperable. August 29, 2002 August 29, 2002 0 days
Leckie Elementary School FM-200211124 02 8/30/02 Leckie Boiler Room 1. Asbestos assessment required 2. Check and repair chiller, low on pressure. July 12, 2002 August 30, 2002 49 days
Smothers ES FM-200214466 02 8/30/02 Smothers F-303.4 Fire Code Violation Basement Exit Door Exit door needs adjusting from boiler room. August 14, 2002 August 30, 2002 16 days
Garfield ES FM-200122216 /01 8/30/02 GARFIELD BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPAIR OR REPLACE LEAKING TUBES ON BOILER #2 Code A-clear for repair by Horne Engineer ( Z Mahmood ) on 3/25/02 (CEB) October 24, 2001 August 30, 2002 310 days
Eaton Elementary School FM-200209679 02 9/1/02 Eaton Boiler room Replace water heater in boiler room, existing water heater has to be replace. June 17, 2002 September 1, 2002 76 days
Wilson High School FM-200216158 02 9/1/02 Wilson,W Boiler Room Replace 1 1/2" blow down line on low water cut out. August 30, 2002 September 1, 2002 2 days
Bowen Elementary School FM-200216311 02 9/3/02 Bowen Boiler room Respond to emergency call - flooded boiler room. September 3, 2002 September 3, 2002 0 days
Hart Middle School FM-200204495 02 9/3/02 Hart Boiler room Replace (4) unknown existing safety relief valves on boilers #1 & 3 with 60 lb. each, (2) of 2" x 2 1/2" BTU/HR 6,751,000 & (2) 1" x 1 1/4" March 15, 2002 September 3, 2002 172 days
Gibbs Elementary School FM-200208696 02 9/4/02 Gibbs ****Urgent**** Outside Drain Near Boiler Room Exit Door Drain is backed up and harboring mosquitos [health hazard]. May 30, 2002 September 4, 2002 97 days
Wilson High School FM-200116252 01 9/4/02 W. WILSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE TWO (2) DEFECTIVE SAFETY VALVES TO #1 BOILER. MFR-LONERGAN, CODE-MD, NASVL 2.N.-7878, SIZE 2-1/2", TYPE-41W204, SET-135PSI. B.P.-6, SEAT DIA. 2-1/2", CAP.-8934, BY-MELENEY AND LIFT.-.320 IN.. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/23/01 HORNE ENGINEERS- TROY WILCOME July 31, 2001 September 4, 2002 400 days
Young Elementary School FM-200206170 02 9/5/02 Young Basement boiler room Repair or replace Summer-Winter switch-over valve. Chiller operating but not cooling building. Valves may be partially closed. April 22, 2002 September 5, 2002 136 days
Shaw JHS FM-200216655 02 9/5/02 Repair # 4 boiler ,boiler will not ignite. this boiler is the used for the steamer in the kitchen September 5, 2002 September 5, 2002 0 days
Roosevelt High School FM-200119582 01 9/9/02 ROOSEVELT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 1" SCREW TYPE GATE VALVE TO WAER COLUMN ON BOILER #3. SCHEDULE 80 PIPE HAS TO BE CUT FOR INSTALLATION OF VALVE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 09/19/01. HORNE ENGINEER ROGER KAGER September 10, 2001 September 9, 2002 364 days
Dunbar High School FM-200215562 02 9/9/02 Dunbar Boiler Room/Rooftop Replace leaking tubes in Boilers #1,#2 and #3. Boilers can not be inspected until work is done. August 26, 2002 September 9, 2002 14 days
Harris, C.W. ES FM-200216714 02 9/9/02 Harris,C.W. Boiler Room Entrance Door The door to the boiler does not lock--cannot secure the area. September 5, 2002 September 9, 2002 4 days
Tyler Elementary School FM-200209295 02 9/9/02 Tyler Boiler room 1. Asbestos assessment required. 2. Cut plug out of #2 boiler located under firebox. Asbestos Code A - Clear for repairs on 06/11/02. Horne Engineering - Troy Wilcome (RG 06/12/02) June 11, 2002 September 9, 2002 90 days
Brookland Elementary FM-200215577 02 9/10/02 Brookland Boiler room Check and repair sump pump in boiler room. Water is on boiler room floor. August 26, 2002 September 10, 2002 15 days
Brookland Elementary FM-200217198 02 9/10/02 Brookland Boiler Room Outside Stairway Boiler Room Outside Stairway Pump water from outside stairway September 10, 2002 September 10, 2002 0 days
Brookland Elementary FM-200206093 02 9/11/02 Brookland Boiler Room Service multi stack unit, unit will not start. (Read out states awaiting chill water flow.) April 19, 2002 September 11, 2002 145 days
Thomson Elementary School FM-200208825 02 9/11/02 Thomson Boiler room 1. Asbestos assessment required. 2. Replace leaking 1-1/2" copper cold water line. Asbestos Code A - Clear for repairs on 06/07/02. Horne Engineering - Sharon Voss (RG 06/11/02) June 3, 2002 September 11, 2002 100 days
Stevens Elementary School FM-200208823 02 9/11/02 Thomson Boiler room 1. Asbestos assessment required. 2. Replace 3/4 inch T pipe on Boiler #1 and 2. The two T pipe are galvanized pipes. Asbestos Code A - Clear for repairs on 06/04/02. Horne Engineering - Sharon Voss (RG 06/05/02) June 3, 2002 September 11, 2002 100 days
Thomson Elementary School FM-200208762 02 9/11/02 Thomson Boiler room 1. Asbestos assessment required. 2. Replace leaking 1- 1/2" copper domestic cold water line. May 31, 2002 September 11, 2002 103 days
Dunbar High School FM-200217241 02 9/11/02 Repair domestic hot water heaters in the boiler room they will not ignite. September 11, 2002 September 11, 2002 0 days
Thomson Elementary School FM-200208821 02 9/11/02 Thomson Boiler room 1. Asbestos assessment required. 2. R/R 1" ruptured line leaking hot water tank near #1 boiler. Asbestos Code A - Clear for repairs on 06/04/02. Horne Engineering - Sharon Voss (RG 06/05/02) June 3, 2002 September 11, 2002 100 days
River Terrace ES FM-200216689 02 9/12/02 River Terrace Boiler Room Boiler Room Asjust burner #1 flame September 5, 2002 September 12, 2002 7 days
Shaed Elementary School FM-200217112 02 9/13/02 Asbestos assessment required Replace 2 1/2" gate valve on domestic hot water storage tank in the boiler room.Valve will not close. Asbestos Code A - Clear for repairs on 09/11/02. Horne Engineering - Troy Wilcome (RG 09/11/02) September 10, 2002 September 13, 2002 3 days
Maury Elementary School FM-200213965 02 9/16/02 Asbestos assessment required. Replace approximately 10 leaking tubes in #2 boiler and reface the surface of the inner hand hole at the bottom hand hole cover will not seat properly. Asbestos Cose A-clear for repair by Horne Engineer Philip Connolly on 8/22/02 DCPS Charles E. Buchanan August 9, 2002 September 16, 2002 38 days
Kenilworth ES FM-200215340 02 9/20/02 Kenilworth Boiler Room Replace weil-let on water leg on Boiler #2. Size 1-1/2" August 22, 2002 September 20, 2002 29 days
Shaed Elementary School FM-200213968 02 9/23/02 Shaed TSI Removal in the Boiler Room. 1.Asbestos assessment and abatement required on the back of #2 boiler the area is marked 2.Replace leaking tubes in # 2 boiler 3.Replace two leaking tubes in #1 boiler. August 9, 2002 September 23, 2002 45 days
School WW High School FM-200218004 02 9/24/02 Unstop floor drain to boiler # 1, drain is stopped up September 20, 2002 September 24, 2002 4 days
Meyer Elementary School FM-200209574 02 9/24/02 Meyer Basement Floor Asbestos Assessment Required. The entrance door near the boiler room needs to be replaced. The door is beginning to deteriorate at the bottom and hard to shut. May 15, 2002 September 24, 2002 132 days
Woodson High School FM-200217255 02 9/24/02 H.D Woodson Basement Physical Heating Plant/ B.R Make the necessary repairs to the refactories in the combustion chamber of #1 and #2 boiler repairs are needed for boilers to pass inspection September 11, 2002 September 24, 2002 13 days
Wilkinson ES FM-200216059 02 9/26/02 Wilkinson F-608.1 Fire code violation Garage level - Exit door need adjustment in stairwell to garage and boiler room. August 28, 2002 September 26, 2002 29 days
Hyde Elementary School FM-200216703 02 9/26/02 Hyde E.S Boiler Room Boiler Room Remopve plugs from boilers 1 and 2 for inspection and replacement plugs size are 3/4 " inch. Note: Plugs are badly deteriorated September 5, 2002 September 26, 2002 21 days
River Terrace ES FM-200126443 /01 9/26/02 RIVER TERRACE BOILER ROOM 1. ASBESTOS ASSESTMENT REQUIRED 2. REPAIR LEAKING TEE ON CHEMICAL FEED LINE 3. REPAIR LEAKING 2 INCH NIPPLE ON RETURN LINE BY STOP CONTROL VALVE ASBESTOS CODE A-CEAR FOR REPAIR ON 1/03/01 BY HORNE ENGINEER: SHARON VOSS December 31, 2001 September 26, 2002 269 days
Miner Elementary FM-200217435 02 9/26/02 Rethread 1 1/2" water leg nipples on #1 boiler. September 13, 2002 September 26, 2002 13 days
Adams Elementary FM-200123681 /01 9/26/02 J.Q.ADAMS BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE 2" LINE LOCATED ON THE HART-FORD LOOP LINE. LINE IS BUSTED AND LEAKING. A PIPE FITTER IS NEEDED. CODE A- CLEAR FOR REPAIR BY HORNE ENGINEERING ROGER KAGER 11-21-01 (DCPS SAFETY S.R.HOWARD 11-21-01) November 21, 2001 September 26, 2002 309 days
Ballou Senior High School FM-200201274 02 9/27/02 BALLOU SUB-BASEMENT BOILER ROOM/ BOILER #1 REFACTORY THE ENTIRE INTERIOR OF THE BURNER HUB AND SURROUNDING FRONT STURCTURE TO #1 BOILER. INFO BOILER #1 PACIFIC STEEL HOT-WATER MOD. #122039. ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/23/02 HORNE ENGINEERING - EDWARD RODRIGUEZ (RG)-01/24/02 January 17, 2002 September 27, 2002 253 days
Backus Middle School FM-200122911 01 9/27/02 BACKUS BOILER ROOM REPLACE RELIEF VALVE ON BOILER #3. RELIEF VALVE IS BAD. CODE A - ASBESTOS ABATED ON 11/20/01 (SG) PER LEROY MINTONS CONFIRMATION. November 6, 2001 September 27, 2002 325 days
Smothers ES FM-200217614 02 9/28/02 Smother 1. Asbestos assestment may be required 2. Remove 7 plugs from boilers # 1 - (3) plugs #2 boiler (4) plugs . Plugs need to be cut out. Asbesstos Code A-clear for repair by Horne Engineer Troy Wilcome DCPS Charles E. Buchanan on 9/18/02 September 17, 2002 September 28, 2002 11 days
Cardozo High School FM-200218536 02 9/30/02 Repair ruptured safety valve nipple on the top of the storage tank in the boilerroom . September 30, 2002 September 30, 2002 0 days
Ballou Senior High School FM-200201814 02 9/30/02 BALLOU BOILER ROOM REFRACTORY WORK NEEDED ON THE ENTIRE INTERIOR OF THE BURNER HUB AND SURROUNDING FRONT STRUCTURE TO #2 BOILER. INFO: BOILER #2 HOT WATER PACIFIC STEEL. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/29/02 BY HORNE ENGINEER:EDWARD RODRIGUEZ January 25, 2002 September 30, 2002 248 days
Hart Middle School FM-200121974 /01 9/30/02 HART BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. REMOVE INSULATION FROM 4 OIL LINES IN FRONT OF BOILER #3. 40 FT. OF PIPING. 2. REPAIR 4 OIL LINES. ASBESTOS CODE-C BY HORNE ENGINEER : SHARON VOSS 10/24/01 (CEB) CODE A- ASBESTOS ABATED ON 11/19/01 (SG) PER SHEILA HOWARD CONFIRMATION BY PRIORITY LIST. October 19, 2001 September 30, 2002 346 days
Ballou Senior High School FM-200218458 02 10/1/02 Ballou Boiler room Repair trane centravac chiller oil sump system. NOTE: No oil pressure INFO: Trane centravac chiller; Ser# 11057 September 27, 2002 October 1, 2002 4 days
Malcolm X ES FM-200126788 02 10/1/02 MALCOLM X BOILER ROOM RENOVATIONS ONGOING, CIRCULATING PUMPS SCHEDULED TO BE REPLACED. DISTRIBUTION PIPING IN POOR CONDITION, SERVERAL UNITARY UNITS INOP. January 4, 2002 October 1, 2002 270 days
Gage-Eckington ES FM-200217720 02 10/1/02 Repair floor refractory in boiler #1 and #2 firebox. September 18, 2002 October 1, 2002 13 days
Malcolm X ES FM-200218549 02 10/1/02 MALCOM X Boiler room REPAIR/REPLACE AIR CONDITIONING UNIT September 30, 2002 October 1, 2002 1 day
Garrison ES FM-200218585 02 10/2/02 Repair # 2 boiler , no ignition on cycle. October 1, 2002 October 2, 2002 1 day
Benjamin Banneker Academic HS FM-200218446 02 10/2/02 Banneker Boiler Room Replace blow down valve on boiler #1 September 27, 2002 October 2, 2002 5 days
Benjamin Banneker Academic HS FM-200218529 02 10/2/02 Replace 2" gate valve on the blow down of # 1 boiler,as per A.Colvin Boiler Inspector. September 30, 2002 October 2, 2002 2 days
Malcolm X ES FM-200214623 02 10/2/02 Malcolm X ****Urgent**** Boiler Room Install security guards on windows to avoid break-ins [this was the point of entry for the break-in occurring on 8/14/02]. August 15, 2002 October 2, 2002 48 days
Gage-Eckington ES FM-200218534 02 10/2/02 Repair the refractory on the floor of # 1 and #2 boilers as per A. Colvin the Boiler Inspector. September 30, 2002 October 2, 2002 2 days
Benjamin Banneker Academic HS FM-200218528 02 10/3/02 Banneker Unstop floor drains behind the boilers as per A.Colvin,Boiler Inspector. (1) Exploratory required ,Asbestos assessment required. (2) Replace collapsed floor drain pipes. September 30, 2002 October 3, 2002 3 days
Cardozo High School FM-200218811 02 10/4/02 Cardozo S.H.S Boiler Room Start up burners and test safety controls on specified boilers. October 3, 2002 October 4, 2002 1 day
Ludlow-Taylor ES FM-200211971 02 10/4/02 Repair or Replace air compressor in the boiler room, unit will not start , possible cause the magnetic startor July 16, 2002 October 4, 2002 80 days
Smothers ES FM-200218716 02 10/4/02 Replace 1 " 1/2 blow down valve on boilers # 1 and #2 . On each boiler repalce one gate and one ball valve. Valves are not holding. October 2, 2002 October 4, 2002 2 days
Aiton Elementary School FM-200218874 02 10/4/02 Aiton Boiler Room Remove defective hand hole plate from Boiler #2 October 4, 2002 October 4, 2002 0 days
Terrell Mc ES FM-200218814 02 10/4/02 M.C Terrelll E.S Boiler Room Start up burners and test safety controls on specified boilers. October 3, 2002 October 4, 2002 1 day
Smothers ES FM-200122780 01 10/4/02 SMOTHERS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPLACE SAFETY VALVE ON BOILER #1 & 2. VALVE LEAKING 2 X 2, SET AT 15 PSI. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER : ROGER KAGER November 1, 2001 October 4, 2002 337 days
Truesdell Elementary FM-200218816 02 10/4/02 Truesdell E.S Basement Boiler Room Repair # 1 & 2 boilers will not start once switch is turn on (burner) October 3, 2002 October 4, 2002 1 day
Jefferson JHS FM-200218806 02 10/5/02 Jefferson J.H.S Boiler Room Start up burners and test safety controls on specified boilers. October 3, 2002 October 5, 2002 2 days
Backus Middle School FM-200218813 02 10/5/02 Backus M.S Boiler Room Start up burners and test safety controls on specified boilers. October 3, 2002 October 5, 2002 2 days
Cleveland Elementary School FM-200218699 02 10/7/02 Cleveland Basement - Boiler room Abatement on boiler room door. So locksmith can drill holes to place deadbolt lock on door. October 2, 2002 October 7, 2002 5 days
Coolidge High School FM-200218903 02 10/7/02 Coolidge Boiler Room Boiler #1 will not start. Has NO HEAT.Other 2 Boilers is down. October 7, 2002 October 7, 2002 0 days
Ross Elementary School FM-200218648 02 10/7/02 Make adjustments on # 2 Boiler, it smokes. October 2, 2002 October 7, 2002 5 days
Clark Elementary School FM-200218137 02 10/7/02 Clark Boiler Room Boiler #1 water leg needs retread. Front left side of boiler will be marked. September 23, 2002 October 7, 2002 14 days
Smothers ES FM-200218876 02 10/7/02 Smothers Boiler Room Replace 1 1/2" blow down valve on boiler 1 & 2. October 4, 2002 October 7, 2002 3 days
Bell High School FM-200214823 02 10/8/02 Bell Boiler Room Furnish the following belts for HVAC euipment motors.Size of belts: B-75; B-79; 5L540; 4L440; B-76; B-85 7/8; 5862; 4L620X1/2;B-8076; AP-76; 8-4580 (3 Each). August 16, 2002 October 8, 2002 53 days
Green Elementary School FM-200219016 02 10/9/02 Repair or replace B&G pump on # 4 boiler . October 8, 2002 October 9, 2002 1 day
Jessie LaSalle Elementary FM-200202352 02 10/9/02 LASALLE SCHOOL BOILER ROOM 1. ASBESTOS ASSESSMENT MAY BE REQUIRED. 2. REPAIR 1 1/2 " RUPTURE IN SUPPLY LINE TO EXPANSION TANK . Envirobate (IT Group)/703-461-6848 Code A - Asbestos was abated on 05/20/02 PER Leroy Minton confirmation. (RG 05/22/02) February 4, 2002 October 9, 2002 247 days
Ludlow-Taylor ES FM-200206622 02 10/9/02 Ludlow-Taylor Boiler room Repair or replace chiller. It will not start. April 25, 2002 October 9, 2002 167 days
Eastern High School FM-200208815 02 10/9/02 Eastern Boiler room Retap holes in low water cut-off on #3 boiler. Bolts poke off and need retapping. Task must be complete prior to DC Inspection June 3, 2002 October 9, 2002 128 days
Nalle Elementary School FM-200219030 02 10/10/02 NALLE J. C. Boiler room Boiler # 2 check operation of modulator will not ignite. October 8, 2002 October 10, 2002 2 days
Aiton Elementary School FM-200219044 02 10/10/02 Repair refractory in # 1 boiler fire box. October 8, 2002 October 10, 2002 2 days
Thomas Elementary School FM-200208650 02 10/10/02 Thomas boiler room Ck operation of chill water flow switch. Chiller will not run. No Air. May 30, 2002 October 10, 2002 133 days
Emery Elementary School FM-200124119 /01 10/10/02 EMERY BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 October 10, 2002 314 days
Spingarn High School FM-200212628 02 10/10/02 Spingarn Boiler room Check and unstop clogged drain in boiler room. Boiler room has water on floor. July 23, 2002 October 10, 2002 79 days
Payne Elementary School FM-200216123 02 10/10/02 Payne Boiler Room Asbestos assessment required Replace 1" leaking supply line on expansion tank in boiler room. Asbestos Code A-clear for repair by Horne Engineer ( Sam Ebrahim) on 8/30/02 DCPS Charles E. Buchanan August 29, 2002 October 10, 2002 42 days
Jessie LaSalle Elementary FM-200206631 02 10/10/02 Lasalle Boiler room 1. Replace or repair sump pump in boiler room. Water backs up on floor. 2. Pump was replacrd and new lines were ran from pump from the ejector pit. Pump is now working with heat at this time. Drains are also clear. April 25, 2002 October 10, 2002 168 days
Benning Elementary School FM-200219183 /02 10/11/02 Benning Boiler Room Boiler #2 will not start. Please check. October 10, 2002 October 11, 2002 1 day
Coolidge High School FM-200217375 02 10/15/02 Coolidge Boiler room Repair broken refactory floor inside boiler #3. Boiler failed inspection by Boiler Inspector. September 12, 2002 October 15, 2002 33 days
Sousa Middle School FM-200219390 /02 10/15/02 SOUSA JHS Boiler room Restore service to oil transfer pumps to operate boilers for heating. October 15, 2002 October 15, 2002 0 days
Jefferson JHS FM-200219467 /02 10/17/02 Jefferson JHS Boiler Room Basement Unstop floor drain at the blow down of boiler #2 and #3 ( Probably Related) October 16, 2002 October 17, 2002 1 day
Hart Middle School FM-200219441 /02 10/17/02 Hart Boiler Room EMERGENCY !!!!!! Boiler #1 will not start up, out on flame failure. Gas switch has been reset and other devices has been reset. Have a infant care center are in the building. October 16, 2002 October 17, 2002 1 day
Ferebee-Hope Elementary School FM-200219492 /02 10/17/02 Ferebee-Hope Pool Mechanical Room 1. Condensate pumps not pumping returns back to boiler converter holding condensaye at steam trap. 2. Returns are being dumped on floor October 16, 2002 October 17, 2002 1 day
Montgomery ES FM-200219469 /02 10/17/02 Scott Montgomery Boiler Room Basement Unstop floor drain between boiler #1 and #2 ( At Rear) October 16, 2002 October 17, 2002 1 day
Hart Middle School FM-200206300 02 10/17/02 Hart Basement Boiler room Replace leaking tube. Boiler #3 has a leaking tube. Tube is leaking water down the rear wall inside the combustion chamber area. April 23, 2002 October 17, 2002 177 days
Hart Middle School FM-200219146 02 10/18/02 Hart. M.S Boiler Room Roiler #2. Will not start-up (Nothing Happens) The programmer & blower motor starter does not run. There are no reset buttons on the aquastats. October 9, 2002 October 18, 2002 9 days
Brookland Elementary FM-200219437 /02 10/18/02 Brookland boiler room Repair/repalce ruptured line behind boiler October 16, 2002 October 18, 2002 2 days
Stanton Elementary School FM-200219480 /02 10/18/02 Stanton Boiler Room Basement Repair leak in city water supply line to domestic hot water heater October 16, 2002 October 18, 2002 2 days
Brookland Elementary FM-200207736 02 10/20/02 Brookland (boiler room) 1. Asbestos assessment required. 2. Replace leaking eight inch OS & Y valve on switch over line. Code A-clear for repair by Horne Engineer ( Sharon Voss ) on 5/16/02 3. Electricians will disconnect light fixture/s in boiler room and reconnect on completion of work. May 15, 2002 October 20, 2002 158 days
Thomas Elementary School FM-200219624 /02 10/20/02 Navel Thomas Boiler room Adjust burner #2 gas valve linkage. October 18, 2002 October 20, 2002 2 days
Sousa Middle School FM-200217690 02 10/21/02 (Sousa) Fire code violation: Page 1 of 6 Boiler room: Exposed wiring. September 17, 2002 October 21, 2002 34 days
Garfield ES FM-200218786 02 10/21/02 Garfield Boiler Room Replace leaking tubes boiler # 1 October 3, 2002 October 21, 2002 18 days
Woodson High School FM-200219818 /02 10/22/02 H.D Woodson Pool Boiler Pool 1. Adjust aquastat to bring up water temp. 2. Clean filter add chemical October 22, 2002 October 22, 2002 0 days
Whittier Elementary School FM-200219637 /02 10/22/02 Whitter Tunnel Area- Boiler room Check 3/4" steam line leaking ,black iron pipe. Steam is going to girls bathroom. EMERGENCY!!!!! October 18, 2002 October 22, 2002 4 days
Deal Junior High School FM-200219789 /02 10/23/02 Deal Boiler Room Repair burner to Boiler #2 and #3,Boilers will not light off. Boiler #1 has been condenm. NO HEAT IN BUILDING. October 22, 2002 October 23, 2002 1 day
Benjamin Banneker Academic HS FM-200219842 /02 10/23/02 Banneker Boiler Room R/R High limit switch on boiler #2 boiler is not firing off. October 22, 2002 October 23, 2002 1 day
Deal Junior High School FM-200219597 /02 10/23/02 Deal Boiler Room Send burner technician with calibration instruments to properly claibrate burners at all modulation levels on boiler #2 and #3. When burners are calibrated properly they burnt more efficiently and cleaner. * Alot of soot in boilers during cleaning. October 17, 2002 October 23, 2002 6 days
Browne Junior High School FM-200219901 /02 10/23/02 Browne Boiler Room P.M Chiller October 23, 2002 October 23, 2002 0 days
Randle-Highlands ES FM-200219839 /02 10/23/02 Randle Highland Boiler Room Check CO/2 fumes in building from boiler room. October 22, 2002 October 23, 2002 1 day
Draper Elementary School FM-200219854 /02 10/24/02 DRAPER boiler room Repair boiler # 1 out on flame failure. October 23, 2002 October 24, 2002 1 day
Houston Elementary School FM-200219767 /02 10/24/02 Houston Boiler Room Replace (2) sump pump motors. Motors are not working. October 22, 2002 October 24, 2002 2 days
Houston Elementary School FM-200219850 /02 10/24/02 Houston Boiler Room Boiler #2 needs flame adjustest October 22, 2002 October 24, 2002 2 days
Hart Middle School FM-200220007 /02 10/25/02 Hart Boiler room Repair or replace the burner motor on # 1 boiler. October 25, 2002 October 25, 2002 0 days
Hart Middle School FM-200220003 /02 10/25/02 Hart Boiler Room Repair Gas dump valve on # 2 boiler gas train. October 25, 2002 October 25, 2002 0 days
Burrville Elementary School FM-200219857 /02 10/25/02 BURRVILLE Boiler room Repair Condensate return pump continuously runs, overfilling boiler. October 23, 2002 October 25, 2002 2 days
Eliot Junior High School FM-200219284 /02 10/28/02 Eliot Repair fence on southeast side of building leading to playground and boiler room entrance. October 11, 2002 October 28, 2002 17 days
Brent Elementary School FM-200205340 02 10/28/02 Brent Boiler Room 1.Asbestos assessment required 2.Replace leaking tubes in boiler #1. Code A-clear for repair by Honre Engineer ( Stephen Caldwell ) on 4/04/02 April 3, 2002 October 28, 2002 208 days
Deal Junior High School FM-200217303 02 10/29/02 Deal JHS Basement Boiler Room Repair or replace fire bricks and refactory (Broken or Missing) in boiler No. 3 Request to be repaired Note: Needed so that boiler can be inspected (Annual) September 11, 2002 October 29, 2002 48 days
Montgomery ES FM-200220090 /02 10/30/02 Montgomery Boiler Room Replace 2" nipple on gas trane to boiler. October 28, 2002 October 30, 2002 2 days
Spingarn High School FM-200123716 /01 10/30/02 SPINGARN BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR LEAK IN 2" LINE IN NORTH TUNNEL. 3. REPAIR LEAK IN 3" LINE IN WEST TUNNEL. POC: CARNAL BRADLEY 202-438-7437 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/26/01 HORNE ENGINEERING - SHARON VOSS (RG) November 21, 2001 October 30, 2002 343 days
Woodson High School FM-200219868 /02 10/31/02 Woodson,H.D. Boiler room Repair # 1 boiler ,will not start October 23, 2002 October 31, 2002 8 days
Brookland Elementary FM-200220037 /02 10/31/02 Check and correct temperture control on heating system , boiler will not reach correct water temperture. October 25, 2002 October 31, 2002 6 days
Moten Elementary School FM-200220287 /02 11/1/02 Moten Boiler Room Replace rupture hot waterheat lineon 3rd floor hallway. October 30, 2002 November 1, 2002 2 days
Moten Elementary School FM-200220291 /02 11/1/02 Moten Boiler Room Repair rupture line to side arm heater. October 30, 2002 November 1, 2002 2 days
Shepherd ES FM-200220166 /02 11/1/02 Shepherd Boiler Room Replace low water cut off valve on boilers #1 and #2. October 28, 2002 November 1, 2002 4 days
Raymond Elementary School FM-200219605 /02 11/1/02 Raymond Boiler Room Basement Send burner technician with calibration instruments to properly claibrate burners at all modulation levels on boiler #1 and #2. When burners are calibrated properly they burnt more efficiently and cleaner. * Buners are overfiring. October 17, 2002 November 1, 2002 15 days
Shaed Elementary School FM-200219769 /02 11/4/02 Shaed E.S. Boiler room Asbestos assessment required Replace leaking tubes in # 2 boiler , engineer will identify. Asbestos Code A - Clear for repairs on 10/24/02. Horne Engineering - Troy Wilcome (RG 10/25/02) October 22, 2002 November 4, 2002 13 days
Patricia R Harris Ed Center FM-200219945 /02 11/4/02 HARRIS P. R. Boiler room Repair/replace leaking tubes on boiler # one. October 24, 2002 November 4, 2002 11 days
Kramer Middle School FM-200219732 /02 11/5/02 Kramer Boiler Room Replace 1" busted pipe in tunnel of Boiler room. Pipe is rusty and leaking. Asbestos Code A - Clear for repairs on 10/22/02. Horne Engineering - Troy Wilcom (RG 10/23/02) October 21, 2002 November 5, 2002 15 days
Burrville Elementary School FM-200220046 /02 11/5/02 BURRVILLE Boiler room Replace pressure reducing valve for air compressor. Size: Honeywell PP901B-1002-5-9912 150 psi max 2 pressure October 25, 2002 November 5, 2002 11 days
School WW High School FM-200219040 02 11/6/02 Repair all gas leaks on the gas train of boiler # 1 and boiler #2 , boilers were red tagged by Wash. Gas Co. until the leaks are repaired. October 8, 2002 November 6, 2002 29 days
Takoma Educational Center FM-200217437 02 11/7/02 Takoma ****Urgent**** 1st Floor Level Boiler Room 2 Rekey grates at windows so there will be ventilation in the area. The contractors are punching tubes into the boiler room and the exhaust is blowing back into the area causing the hallway to be smoked up. September 13, 2002 November 7, 2002 55 days
Ballou Senior High School FM-200205975 02 11/12/02 Ballou ****Urgent**** Boiler room Check and repair magnetic starter for chiller. It does not have any current leaving the starter to power unit. April 17, 2002 November 12, 2002 209 days
Shepherd ES FM-200219604 /02 11/12/02 Shepherd Boiler Room Send burner technician with calibration instruments to properly claibrate burners at all modulation levels on boiler #1. When burners are calibrated properly they burnt more efficiently and cleaner. * Alot of soot in boilers during cleaning. October 17, 2002 November 12, 2002 26 days
Hyde Elementary School FM-200218373 02 11/12/02 Hyde Boiler Room Repair boiler #2, boiler will noy ignite September 26, 2002 November 12, 2002 47 days
Tyler Elementary School FM-200220176 /02 11/12/02 Repair or replace feed water regulator on the #1 boiler ,it does not respond to low water condition, October 29, 2002 November 12, 2002 14 days
Ballou Senior High School FM-200218260 02 11/12/02 BALLOU Boiler room Repair/ Check operation of chiller. Having problems with chiller staying on line September 25, 2002 November 12, 2002 48 days
Aiton Elementary School FM-200218873 02 11/13/02 Aiton Boiler Room Boiler #1 will not start off on flame failure October 4, 2002 November 13, 2002 40 days
West Elementary School FM-200220902 /02 11/13/02 West (Boiler Room) 1. Repair leak on city water line (branch) coming off the main 2" elbow (no insulation is on the line) November 13, 2002 November 13, 2002 0 days
Backus Middle School FM-200205478 02 11/13/02 Backus Boiler Room Repair burner #2. Burner goes off on flame failure. April 5, 2002 November 13, 2002 222 days
Amidon Elementary School FM-200201786 02 11/13/02 AMIDON BOILER ROOM REPAIR #1 BURNER #1 BOILER WILL NOT START. January 25, 2002 November 13, 2002 292 days
Spingarn High School FM-200220747 /02 11/14/02 Spingarn Boiler Room Replace old steam pipe in the west tunnel on steam sice November 12, 2002 November 14, 2002 2 days
Barnard Elementary School FM-200219608 /02 11/14/02 Barnard Boiler Room Replace rusted 3/4" joint nipple located on main header leg. October 17, 2002 November 14, 2002 28 days
Kramer Middle School FM-200220413 /02 11/14/02 Kramer Boiler Room Repair #3 Boiler keeps going off on flame failure, this is am emergency. October 31, 2002 November 14, 2002 14 days
Brookland Elementary FM-200219349 /02 11/14/02 Repair or replace sump pump, and sewer injector pump in the boiler room. October 15, 2002 November 14, 2002 30 days
West Elementary School FM-200221029 /02 11/14/02 West Boilerroom Trouble shoot hot water heater November 14, 2002 November 14, 2002 0 days
River Terrace ES FM-200219860 /02 11/14/02 RIVER TERRACE Boiler room Correct pnuematic controls for reset schedule. Heating H/W temps are excessive. October 23, 2002 November 14, 2002 22 days
Benjamin Banneker Academic HS FM-200220499 02 11/14/02 Banneker Boiler Room Repair burner on Boiler #2. Boiler will not start up. (Will not prepurge). November 1, 2002 November 14, 2002 13 days
Kramer Middle School FM-200218875 02 11/15/02 Kramer Boiler Room Boiler #1,#2 and #3 will not start. Please check. October 4, 2002 November 15, 2002 42 days
Amidon Elementary School FM-200220625 /02 11/15/02 Amidon Boiler Room 1) Assess and abate doors,door frames, windows and louvers associated with the boiler room. Asbestos Code B by Horne Engineer Sheryll James on 11/13/02 DCPS Charles E Buchanan November 12, 2002 November 15, 2002 3 days
Tyler Elementary School FM-200220175 /02 11/15/02 Repair automatic condensate pump control on the condensate tank,it will not pump water back to the boiler properly. October 29, 2002 November 15, 2002 17 days
Bruce-Monroe Elementary School FM-200220559 02 11/15/02 Bruce-Monroe Boiler Room Boiler #1 temperature control need to be replace. Boiler would not shut off on temperature, need new aquastat. November 1, 2002 November 15, 2002 14 days
Eaton Elementary School FM-200221172 /02 11/19/02 Eaton Boiler room URGENT NO HEAT Repair broken pneumatic main control switch for heating and cooling ,need switch replaced to heat all class rooms and open space area. November 18, 2002 November 19, 2002 1 day
Benning Elementary School FM-200221244 /02 11/20/02 BENNING Boiler room Check air compressor for air leak near bleeder valve. November 19, 2002 November 20, 2002 1 day
Beers Elementary School FM-200221161 /02 11/20/02 BEERS BOILER ROOM Make repairs to air compress/pneumatic controls, no air supplies to control valves in classrooms of new wing. Weekending 11/4 - 11/8 - FM-200220945 November 18, 2002 November 20, 2002 2 days
Burrville Elementary School FM-200221335 /02 11/21/02 Burrville Boiler Room Boilers #1 and #2, replace McDonnell-Miller Automatic water feeders November 19, 2002 November 21, 2002 2 days
Deal Junior High School FM-200221359 /02 11/21/02 Deal Boiler Room Restore electrical service to burners November 19, 2002 November 21, 2002 2 days
Deal Junior High School FM-200221254 /02 11/21/02 Deal Boiler Room No heat in building made necessary repairs to #2 and #3 boilers November 19, 2002 November 21, 2002 2 days
Leckie Elementary School FM-200220773 02 11/21/02 LECKIE BOILER ROOM Check # 1 boiler. Burner continuously going out on insufficient air alarm. weekending 11/4 - 11/8 - FM-200220944 November 7, 2002 November 21, 2002 14 days
King M L ES FM-200221087 /02 11/22/02 (King) !!!URGENT!!! Boiler room: Replace lock on boiler room door; engineer dropped key in storm drain. November 15, 2002 November 22, 2002 7 days
Burrville Elementary School FM-200221114 /02 11/22/02 Burrville boiler room Replace McDonnell-Miller automatic water feeder on boiler # 1 and 2 model 52 H.D.-2 November 18, 2002 November 22, 2002 4 days
Meyer Elementary School FM-200221120 /02 11/22/02 Meyer Boiler room Repair burner # 2 cuts off on flame failure.( Flame amperfier.) November 18, 2002 November 22, 2002 4 days
Burrville Elementary School FM-200221460 /02 11/23/02 BURRVILLE BOILER ROOM Repair/replace rupture hot water supply line in boiler room November 21, 2002 November 23, 2002 2 days
Kramer Middle School FM-200221553 /02 11/24/02 Kramer Boiler Room Boiler #2, has leaking tubes. November 22, 2002 November 24, 2002 2 days
Nalle Elementary School FM-200221264 /02 11/25/02 Nalle J.C. 1. Asbestos assessment may be required 2. Install security lock on boiler room interior door to prevent unauthorized personnel from entering boiler room. Asbestos Code A - Cleared for repairs on 12-02-02 (LM / 12-04-02 ) Leroy Minton Jr. Safety Office 202-576-8962. November 19, 2002 November 25, 2002 6 days
Woodson High School FM-200220601 02 11/25/02 "Emergency Second Service Order" H.D Woodson Physican Heating Plant, Boiler Room Boiler Room Please make the necessary repairs to #1, #2, #3 and #4 boiler feed water pumps and feed water controls for #1 and #2 boilers, all pumps are leaking badly #1 and #2 boilers are constantly loosing water, pump motor controls are not working on automatic and have to constantly be hand feed. (A.S.A.P Before critical and inclement weathr begins) November 1, 2002 November 25, 2002 24 days
Orr Elementary School FM-200219889 /02 11/25/02 Orr Boiler Room P.M Chiller October 23, 2002 November 25, 2002 33 days
Gage-Eckington ES FM-200221518 /02 11/25/02 Gage Eckington Boiler Room Replace Mcdonnell Miller #150 -S Low water cut on the # 1 boiler ,will not cut the burner off when blown down. November 22, 2002 November 25, 2002 3 days
Meyer Elementary School FM-200221519 /02 11/25/02 Meyer Boiler Room Replace Mcdonnell Miller Low water cut # 63 on the # 1 boiler,will not cut the boiler off when blown down. November 22, 2002 November 25, 2002 3 days
Stuart-Hobson Middle School FM-200220468 02 11/26/02 Stuart-Hobson Tunnel in Boiler Room Replace all leaking steam line in tunnel of boiler room. Steam line is 3/4". There is no insulation on pipes. Emergency!!!!!!! Asbestos Code A-clear for repair by Horne Engineer Troy Wilcome on 11/15/02 DCPS Charles E. Buchanan November 1, 2002 November 26, 2002 25 days
Maury Elementary School FM-200221764 /02 12/1/02 Maury Boiler Room Replace Mcdonnell Miller #51 HD automatic water feeder on #2 boiler, engineer will install November 29, 2002 December 1, 2002 2 days
Burrville Elementary School FM-200221752 /02 12/1/02 BURRVILLE Boiler room Replace defective cond. return motor and pump end # 1. Motor draws too high an amperage. Note: B. Davis P. Jeter, Jr. have surveyed and rec'd info for motor / pump end replacement. November 29, 2002 December 1, 2002 2 days
River Terrace ES FM-200221137 /02 12/2/02 RIVER TERRACE SCHOOL BOILER ROOM 1. Replace leaking mechanical seals on condensate return pump # 1 . 2. Check and make necessary repairs to condensate return pump # 2 controls. Pump constantly runs while in "auto" mode. November 18, 2002 December 2, 2002 14 days
Backus Middle School FM-200221767 02 12/2/02 Backus Boiler room Repair #2 boiler off on flame failure December 2, 2002 December 2, 2002 0 days
Green Elementary School FM-200221692 /02 12/2/02 GREEN boiler room Check boiler operation sequence. Only 1 of 5 boilers continue to operate. November 26, 2002 December 2, 2002 6 days
Tubman Elementary School FM-200207814 02 12/2/02 Tubman 1st Floor South Corridor Electric Panel Box Circuit breaker switch No. 6 will not switch the lights on and off in the stairwell near the interior east-side of building, or the stairwell going down to the boiler room. May 15, 2002 December 2, 2002 201 days
Woodson High School FM-200221883 02 12/3/02 WOODSON, H.D. BOILER ROOM Check # 2 boiler burner continuously going out on flame failure. December 3, 2002 December 3, 2002 0 days
Brent Elementary School FM-200204129 02 12/3/02 Brent Boiler Room 1. Asbestos assessment required. 2. Repair or replace 1-3/4" pipe coming off expansion tank leaking. Asbestos Code A - Clear For Repairs On 03/12/02. Horne Engineering - Stephen Caldwell (RG 03/12/02) March 8, 2002 December 3, 2002 270 days
Emery Elementary School FM-200222007 02 12/3/02 Emery Boiler Room Basement Start boiler for heating of school building Boiler were locking out . December 3, 2002 December 3, 2002 0 days
Slowe Elementary School FM-200126813 02 12/4/02 SLOWE SCHEDULED FOR CHILLER REPLACEMENT. BOILER ROOM BEING RENOVATED. CLASSROOM UNIVENTS NEED OVERHAULING. January 4, 2002 December 4, 2002 334 days
West Elementary School FM-200221904 02 12/5/02 West Boiler Room Ground Floor Provide assistance with hot water heater.Kitchen is not getting hot water December 3, 2002 December 5, 2002 2 days
Bunker Hill Elementary School FM-200220136 /02 12/5/02 Bunker-Hill Boiler Room Repair or replace condensate return pumps and controls. October 28, 2002 December 5, 2002 38 days
West Elementary School FM-200221905 02 12/5/02 West Boiler Room Ground Floor Provide assistance with hot water heater (domestic) December 3, 2002 December 5, 2002 2 days
Thomas Elementary School FM-200222144 02 12/9/02 Thomas Boiler Room Respond to electrical power outage to ensure facility heating to prevent freeze up of mechanical equipment due to cold weather. December 7, 2002 December 9, 2002 2 days
Stevens Elementary School FM-200222128 02 12/9/02 Stevens Boiler Room Boiler #1 Replace low water cut off will not cut off. EMERGENCY!!!!!! December 5, 2002 December 9, 2002 4 days
Stuart-Hobson Middle School FM-200218645 02 12/9/02 Replace manhole ring and cover on #3 boiler. (1) Asbestos assessment may be required. Asbestos Code A - Clear for repairs on 10/02/02. Horne Engineering - Roger Kager (RG 10/02/02) October 2, 2002 December 9, 2002 68 days
Bruce-Monroe Elementary School FM-200222145 02 12/9/02 Bruce-Monroe Boiler Room Repair burner on Boiler #1 and adjusts aquastats and high limit controls December 7, 2002 December 9, 2002 2 days
Ludlow-Taylor ES FM-200222146 02 12/9/02 Ludlow-Taylor Boiler Room Repair sump pumps in Boiler room. December 7, 2002 December 9, 2002 2 days
Ballou Senior High School FM-200219887 /02 12/9/02 Ballou SHS Boiler Room P.M Chiller October 23, 2002 December 9, 2002 47 days
River Terrace ES FM-200220050 /02 12/10/02 RIVER TERRACE Boiler room Repair program controls for burner # 1 flame failure - "replace amplifier" - Note: Programmer was "warm to Touch" October 25, 2002 December 10, 2002 46 days
River Terrace ES FM-200221647 /02 12/10/02 RIVER TERRACE Boiler room Repair burner # 2 - flame failure - run interlock - open November 26, 2002 December 10, 2002 14 days
Johnson JHS FM-200221111 /02 12/10/02 Johnson JHS Boiler room Check boiler burner # 3, constantly goes out on flame failure. WEEKENDING 11/4-11/8 FM-20020667 November 18, 2002 December 10, 2002 22 days
Bunker Hill Elementary School FM-200204974 02 12/10/02 Bunker Hill Boiler Room Repair magnetic starters on house pumps #1 and #2. Starter will not pull in. NO HEAT ON ONE SIDE OF BUILDING. URGENT!! March 27, 2002 December 10, 2002 258 days
Jefferson JHS FM-200222156 02 12/11/02 Jefferson Boiler Room Respond to power outage. No heat. December 9, 2002 December 11, 2002 2 days
Green Elementary School FM-200219888 /02 12/11/02 Green Boiler Room P.M Chiller October 23, 2002 December 11, 2002 49 days
River Terrace ES FM-200222170 02 12/11/02 River Terrance Boiler Room 1. Repair leaking seal on condensate return pump #1. 2. Repair condensate return pump #2 controls, Pump/motor runs continuosly. December 9, 2002 December 11, 2002 2 days
Jessie LaSalle Elementary FM-200222345 /02 12/11/02 (Lasalle) !!!Emergency!!! Basement Level: Lock jammed on inner door leading to boiler room. December 10, 2002 December 11, 2002 1 day
Winston EC FM-200219885 /02 12/12/02 Winston Boiler Room P.M Chiller October 23, 2002 December 12, 2002 50 days
Clark Elementary School FM-200222378 /02 12/12/02 Clark Boiler Room Check domestic hot water heater in Boiler Room. Polit not coming on. December 11, 2002 December 12, 2002 1 day
Terrell Mc ES FM-200222515 /02 12/13/02 Terrell, M.C. Boiler Room Replace 1 1/2" valve on city water line going to Boiler #1 and 1 1/2" valve on by pass for Boiler #1. One (1) valve is sweated and one (1) valve is threaded. December 13, 2002 December 13, 2002 0 days
Shaed Elementary School FM-200222399 /02 12/14/02 Shead Boiler Room Boiler #2 replace leaking tubes December 12, 2002 December 14, 2002 2 days
Bunker Hill Elementary School FM-200222514 /02 12/16/02 Bunker Hill boiler room Repair water column system on boilers one and two. December 13, 2002 December 16, 2002 3 days
Smothers ES FM-200222672 /02 12/17/02 Smothers Boiler Room Boiler #2 flame failure. December 17, 2002 December 17, 2002 0 days
Orr Elementary School FM-200222687 /02 12/18/02 ORR Boiler room Pneumatic air leak. Compressor continuously running. Replace 2 foot leaking section of copper air supply line to the compressor. December 17, 2002 December 18, 2002 1 day
Ronald H. Brown MS FM-200219900 /02 12/18/02 Ron Brown Boiler Room P.M Chiller October 23, 2002 December 18, 2002 56 days
Deal Junior High School FM-200220937 /02 12/18/02 Deal Boiler Room Asbestos assessment is needed. Repair a 3" leaking steam return line, black iron pipe. Engineer is hand feeding boiler Asbestos Code A-clear for repair by Horne Engineer Philip Connolly on 11/15/02 DCPS Charles E. Buchanan November 14, 2002 December 18, 2002 34 days
Stuart-Hobson Middle School FM-200222893 /02 12/19/02 Stuart-Hobson Boiler room Repair gas leak on # 3 boiler December 19, 2002 December 19, 2002 0 days
Beers Elementary School FM-200222892 /02 12/19/02 BEERS Boiler room Repair # 1 & 2 boilers off on flame failure. December 19, 2002 December 19, 2002 0 days
Ketcham Elementary School FM-200222890 /02 12/20/02 Ketcham Boiler Room Boiler #1 down on flame failure. December 20, 2002 December 20, 2002 0 days
Slowe Elementary School FM-200223009 /02 12/23/02 SLOWE boiler room Check feed chemical pumps - not allowing returns back into boiler December 23, 2002 December 23, 2002 0 days
Slowe Elementary School FM-200222535 /02 12/23/02 SLOWE Boiler room Repair # 2 boiler low water alarm, it can only be reset by cutting the power off to the boiler, the reset button will not respond. December 13, 2002 December 23, 2002 10 days
Shepherd ES FM-200222529 /02 12/23/02 Shepherd Boiler Room Correct problems with pump controls on boiler #1 and #2. Control are not working properly, causing alarm problems. December 13, 2002 December 23, 2002 10 days
Shepherd ES FM-200222894 /02 12/23/02 Shepherd Boiler room Repair or replace # 2 condensate pump,must reset pump each day. December 19, 2002 December 23, 2002 4 days
John Burroughs ES FM-200223091 /02 12/24/02 BURROUGHS Boiler room # 2 boiler off on flame failure. December 24, 2002 December 24, 2002 0 days
Woodson High School FM-200220478 02 12/24/02 Woodson,H.D Boiler Room Boilers #1 and #2 will not feed on automatic. Please connect. November 1, 2002 December 24, 2002 53 days
Stoddert ES FM-200208803 02 12/26/02 Stoodert Boiler Room Replace domestic hot water heater in boiler room. Hot water heater is leaking very bad. June 3, 2002 December 26, 2002 206 days
Stoddert ES FM-200222809 /02 12/27/02 Stoddert Boiler Room Replace rupture domestic hot water heater. December 19, 2002 December 27, 2002 8 days
Bancroft Elementary School FM-200217890 02 12/31/02 Bancroft Basement Boiler Room Replace domestic hot water heater that is leaking water at the bottom and extinguishing the pilot. A.O Smith Hot Water Heater Model# BT 251A 830 Cap- 84 Gals BTU/HT 251000 Rec. RTG (100' Rise) 2130 gals Maximum Working Pressure 160 PSI. September 19, 2002 December 31, 2002 103 days
Bunker Hill Elementary School FM-200222385 /02 1/2/03 Bunker Hill Boiler Room Repair Condensate pumps December 11, 2002 January 2, 2003 22 days
Jefferson JHS FM-200223385 /02 1/2/03 Jefferson Old Boiler Room Ground Floor Provide assistance with injactor pumps. Pumps are not removing water from well. Temp pump are in place December 31, 2002 January 2, 2003 2 days
Bunker Hill Elementary School FM-200223357 /02 1/2/03 Bunker Hill Boiler Room Repair/Replace burnt out motor starter for condensate pumps December 30, 2002 January 2, 2003 3 days
Takoma Educational Center FM-200221696 /02 1/2/03 Takoma Boiler Room Replace aquastat on hot water tank Note: Is not controlling temp. properly (to high) Unsafe November 26, 2002 January 2, 2003 37 days
Drew Elementary School FM-200223380 /02 1/2/03 Drew Boiler Room Boiler #1 keep going off on flame failure. December 31, 2002 January 2, 2003 2 days
Stuart-Hobson Middle School FM-200223466 03 1/3/03 Stuart-Hobson Boiler room Locate and repair gas leak in the boiler room ,may be on the boiler gas train. January 3, 2003 January 3, 2003 0 days
King M L ES FM-200223532 03 1/6/03 KING boiler room Repair/replace sump pump will not operating on auto. January 6, 2003 January 6, 2003 0 days
Orr Elementary School FM-200222024 02 1/6/03 ORR Boiler room "No Heat" Check air compressor inoperable. December 4, 2002 January 6, 2003 33 days
Cardozo High School FM-200219981 /02 1/6/03 CARDOZO BOILER ROOM "URGENT NO HEAT" REPAIR/REPLACE BURNER PILOT FLAME FAILURE. October 24, 2002 January 6, 2003 74 days
Bunker Hill Elementary School FM-200223528 03 1/6/03 Bunker Hill Parking lot Temp.Boiler Reconnect small oil tank to oil pump, and restart boiler January 6, 2003 January 6, 2003 0 days
Payne Elementary School FM-200223527 03 1/6/03 Payne Boiler Room Boiler room flooded, repair or replace sump pump, pump not working. January 6, 2003 January 6, 2003 0 days
Brent Elementary School FM-200201856 02 1/7/03 BRENT BOILER ROOM BOILER #1 GOING OUT ON FLAME FAILURE (UNDER CONTRACT). A.C.I. January 25, 2002 January 7, 2003 347 days
Savoy Elementary School FM-200223490 03 1/7/03 Savoy Boiler room Repair #2 burners, off on lock out January 3, 2003 January 7, 2003 4 days
Benning Elementary School FM-200219891 /02 1/7/03 Benning Boiler Room P.M Chiller October 23, 2002 January 7, 2003 76 days
Reed LC FM-200220948 /02 1/7/03 Reed Boiler Room Asbestos assessment required Replace leaking pipe in ceiling of Boiler room over Boiler #3. Insulation on pipe. EMERGENCY!!!!! Asbestos Code A- clear for repairs as of 11/18/02 by Horne Engineers Troy Wilcome. November 14, 2002 January 7, 2003 54 days
Burrville Elementary School FM-200219898 /02 1/7/03 Burrville Boiler Room P.M Chiller October 23, 2002 January 7, 2003 76 days
John Burroughs ES FM-200223569 03 1/8/03 Burroughs Basement hall by boiler room entrance door Asbestos assessment required Repair or replace ruptured 1 1/4" low pressure reture line ,basement hall by boiler room door. Asbestos Code A-clear for repair by Horne Engineer Bipin Nanavaty on 01/08/03 DCPS Charles Buchanan January 7, 2003 January 8, 2003 1 day
Ferebee-Hope Elementary School FM-200219879 /02 1/8/03 Ferebee-Hope Boiler Room P.M Chiller October 23, 2002 January 8, 2003 77 days
Terrell Mc ES FM-200223454 03 1/8/03 Terrell, M.C. Boiler Room Boiler #2 off on flame failure. January 3, 2003 January 8, 2003 5 days
Stoddert ES FM-200223659 03 1/9/03 Stoddert Boiler Room Check hot water domestic heater, fire code,may need electric work.Check electric out let for hard wiring. January 9, 2003 January 9, 2003 0 days
Ketcham Elementary School FM-200223489 03 1/10/03 Ketcham Boiler room Repair boilers #1,2,3,and 4 off on lock out January 3, 2003 January 10, 2003 7 days
Stuart-Hobson Middle School FM-200223399 03 1/10/03 Stuart-Hobson Boiler Room Boiler #1 Repair or replace low water cut off. January 2, 2003 January 10, 2003 8 days
Leckie Elementary School FM-200219882 /02 1/10/03 Leckie Boiler Room P.M Chiller October 23, 2002 January 10, 2003 79 days
Davis Elementary School FM-200223707 03 1/10/03 Davis Coal shoot Repair axcess door (coal shoot) to boiler room from outside, parking area. Security risk this is a direct entrance to the boiler room that is open. January 10, 2003 January 10, 2003 0 days
Terrell Mc ES FM-200223432 03 1/10/03 M.C. Terrell Boiler Room Check both boilers keep going off on flame failure. January 2, 2003 January 10, 2003 8 days
Bunker Hill Elementary School FM-200223624 03 1/10/03 Bunker Hill Boiler room Adjust contacts on burner control on the wall behind # 1 bolier it has a loud hum. January 8, 2003 January 10, 2003 2 days
Sousa Middle School FM-200223571 03 1/10/03 SOUSA boiler room Check boiler feed pumps #3 will not run. January 7, 2003 January 10, 2003 3 days
Bell High School FM-200217370 02 1/10/03 Bell Boiler room Replace badly deteriorated flue pipe on hot water heater. NOTE: Fumes are escaping from flue pipe when in operation. HOT!!! September 12, 2002 January 10, 2003 120 days
Roosevelt High School FM-200204756 02 1/10/03 Roosevelt Swimming pool filtration room Boiler will not light off. March 20, 2002 January 10, 2003 296 days
Sousa Middle School FM-200223572 03 1/10/03 SOUSA Boiler Check vacuum pumps will not operate. Pull condensate return and vacuum pumps for repair. Replace floats and city water make up device. Check all electrical components such as motor starters, alternating relays, service disconnects etc. Install new pumps. Check system for proper operation. Clean debris from job site. Contact Facilities Maintenance and Operation upon completion of work. Poc - David P. Grimard - 301-440-6751 ACI Inc January 7, 2003 January 10, 2003 3 days
Bunker Hill Elementary School FM-200223623 03 1/11/03 Bunker Hill Boiler room Make adjustments on pump control,to increase the the amount of returns going to the boiler. January 8, 2003 January 11, 2003 3 days
Slowe Elementary School FM-200223010 /02 1/13/03 SLOWE boiler room Repair/replace ruptured 3/4 inch city water feed line on boiler control panel. December 23, 2002 January 13, 2003 21 days
Roosevelt High School FM-200223574 03 1/13/03 ROOSEVELT SHS boiler room Check and restore power to boiler. Generator not engaging. January 7, 2003 January 13, 2003 6 days
Wilson J. O. ES FM-200219185 /02 1/14/03 Wilson,J.O Boiler Room Furnish feed water regulator for Boilers #1 and #2. October 10, 2002 January 14, 2003 96 days
Kramer Middle School FM-200210794 02 1/14/03 Kramer Basement Boiler Room #4 Water is running into the sink--there is no shut-off valve. Repair or replace fixture parts. July 8, 2002 January 14, 2003 190 days
Bell High School FM-200223453 03 1/14/03 Bell Boiler room (EMERGENCY) Repair # 2 and #3 will not start,reading lock out January 3, 2003 January 14, 2003 11 days
Burrville Elementary School FM-200223732 03 1/14/03 BURRVILLE Boiler room Resolve problem with burner out on flame failure on boiler #2 January 13, 2003 January 14, 2003 1 day
Wilson J. O. ES FM-200219768 /02 1/14/03 J.O. Wilson Boiler room Trouble shoot and start boilers # 1 and # 2 , L1-13 lockout. October 22, 2002 January 14, 2003 84 days
Brent Elementary School FM-200210056 02 1/15/03 Brent Boiler Room Check and repair A/C chiller, unit must be reset each day. ( Cooling tower fans not running.) 6/24/02 June 24, 2002 January 15, 2003 205 days
Shaw JHS FM-200223877 03 1/15/03 Shaw Boiler Room Repair and replace McDonell no. 157. Pump control and low water cut-off on #2 boiler. Cut off in low water January 13, 2003 January 15, 2003 2 days
Johnson JHS FM-200219884 /02 1/15/03 Johnson JHS Boiler Room P.M Chiller October 23, 2002 January 15, 2003 84 days
Bancroft Elementary School FM-200223388 /02 1/16/03 Bancroft Boiler Room Hot water heater need to be electircally wired. December 31, 2002 January 16, 2003 16 days
Cardozo High School FM-200223989 03 1/16/03 Cardozo Boiler room (URGENT) Replace leaking pit cock valve on the the domestic hot water boiler, unit was shut down by the gas co.1/14/03 January 15, 2003 January 16, 2003 1 day
Spingarn High School FM-200213264 02 1/17/03 (Spingarn) !!!Very Very Urgent!!! Outside/Boiler room used for greenhouse: Due to attempted break-in wire mesh glass broke, and metal frame damaged, needs welding. July 29, 2002 January 17, 2003 172 days
Leckie Elementary School FM-200222813 /02 1/17/03 Leckie Boiler Room Boiler #2 Replace one 2" leaking tube in bottom section December 19, 2002 January 17, 2003 29 days
Spingarn High School FM-200213263 02 1/17/03 (Spingarn) !!!Very Very Urgent!!! Outside/Boiler room used for greenhouse: Due to attempted break-in, wire mesh glass broke and metal frame was damaged. July 29, 2002 January 17, 2003 172 days
Bowen Elementary School FM-200223682 03 1/21/03 A.Bowen Boiler room Repair burner # 1 ,no power to control box January 10, 2003 January 21, 2003 11 days
Davis Elementary School FM-200125557 /01 1/21/03 DAVIS BOILER ROOM REPAIR OR REPLACE SUMP PUMPS. December 18, 2001 January 21, 2003 399 days
Ludlow-Taylor ES FM-200219903 /02 1/21/03 Ludlow-Taylor Boiler Room P.M Chiller October 23, 2002 January 21, 2003 90 days
Langdon Elementary School FM-200113346 01 1/22/03 LANGDON E.S BOILER ROOM AND TUNNEL ASBESTOS ASSESSMENT REQUIRED SURVEY AND MAKE NECESSARY REPLACEMENT OF 21/4 INCH CONDENSATE RETURN LINE COMING OUT OF THE WALL TO THE CONDENSATE TANK. RETURN LINE IS LEAKING ONTO THE BOILER ROOM FLOOR. CODE A - NO ABATEMENT REQUIRED PER LEROY MINTON 12/04/01. (RG) June 14, 2001 January 22, 2003 587 days
John Burroughs ES FM-200223617 03 1/22/03 (Burroughs) Asbestos Assestment Required Lower level/Outside of boiler room: Ruptured pipe near custodians office; hot water pouring out. Asbestos Code A-clean for repair by Horne Engineer Sharon Voss on 01/10/03 Charles Buchanan January 7, 2003 January 22, 2003 15 days
Kimball Elementary School FM-200221451 /02 1/22/03 Kimball Basement - boiler room Replace water closet Replace flush valves for new boiler room. November 20, 2002 January 22, 2003 63 days
Woodson High School FM-200219899 /02 1/22/03 H.D Woodson Boiler Room P.M Chiller October 23, 2002 January 22, 2003 91 days
Montgomery ES FM-200223683 03 1/22/03 Montgomery Boiler Room Repair condensate pump #1 (on condensate tank). Boiler #1 is inoperative due to pump failure. BFS Industries, model:F12559- 1/2 SERIAL: 00624-1 Motor marathon electric part no. 2771RA; Model #5vn56t34d5991AP; HP-1/2; Volt 208/230; RPM 3450 January 10, 2003 January 22, 2003 12 days
Plummer Elementary School FM-200223912 03 1/23/03 Plummer Boiler Room Boiler #2 off on flame failure, also check # 1 boiler it must be reset serveral times aday. January 14, 2003 January 23, 2003 9 days
Plummer Elementary School FM-200217253 02 1/23/03 Repair gas leak on gas train of boilers, gas odor is detected when boilers are started. September 11, 2002 January 23, 2003 134 days
Dunbar High School FM-200222405 /02 1/23/03 Dunbar Boiler Room/Rooftop Boiler #2 Replace leaking tubes. Asbestos Code A - Clear for repairs on 12/20/02. Horne Engineering - Troy Wilcome (RG 12/23/02) December 12, 2002 January 23, 2003 42 days
Woodson High School FM-200224196 03 1/23/03 Woodson Boiler Room Asbestos assessment required Please make the necessary repairs to the ruptured 2" nipple on the condensate return line by the domestic hot water tank, line ruptureed, causing loss of condensate returns to condensate tank for Boiler feed. Asbestos Code A - Clear for repairs on 01/21/03. Horne Engineering - Troy Wilcome (RG 01/22/03) January 21, 2003 January 23, 2003 2 days
Brent Elementary School FM-200219902 /02 1/23/03 Brent Boiler Room P.M Chiller October 23, 2002 January 23, 2003 92 days
Reed LC FM-200224463 03 1/23/03 Marie H. Reed Boiler Room Check domestic hot water system. January 23, 2003 January 23, 2003 0 days
Gage-Eckington ES FM-200224139 03 1/24/03 Gage Eckington Boiler room Repair or replace B&G domestic hot water pump in the boiler in the boiler room , pump does not work. January 17, 2003 January 24, 2003 7 days
Roosevelt High School FM-200201746 02 1/25/03 ROOSEVELT BOILER ROOM FURNISH FLOAT SWITCH TO REPLACE LEAKING SWITCH ON SURGE TANK. SWITCH CONTROLS MAKE-UP WATER SOLENOID VALVE. FLOAT SWITCH CLOSED TANK MAKE- SQUARE-D CLASS-9037 TYPE- HG36 January 25, 2002 January 25, 2003 365 days
Raymond Elementary School FM-200224418 03 1/26/03 Raymond Boiler room Three windows need repairing, to keep squirrels and etc. out. January 23, 2003 January 26, 2003 3 days
Ludlow-Taylor ES FM-200224476 03 1/27/03 LUDLOW-TAYLOR boiler room Repair inoperable sump pump. Will not pump water down, boiler room will flood. January 24, 2003 January 27, 2003 3 days
Takoma Educational Center FM-200224624 03 1/27/03 Takoma E.S Boiler Room Repair BMG Heating Hot Water Inline Circulating Pump January 27, 2003 January 27, 2003 0 days
Tubman Elementary School FM-200223464 03 1/27/03 Tubman Boiler Room Repair or replace burner to domestic hot water heater, burner will not light off due to boiler room flooding. January 3, 2003 January 27, 2003 24 days
Eliot Junior High School FM-200223887 03 1/28/03 Eliot Boiler room Asbestos assessment maybe required Repair or replace ruptured 2" condensate return line in the tunnel by the electrical box same as work order FM-200340775 Sylvia Grimes 12/8/03. January 14, 2003 January 28, 2003 14 days
West Elementary School FM-200202025 02 1/28/03 WEST BOILER ROOM REPAIR OR REPLACE OIL CIRCULATOR PUMP #1. NAME: KRAISSL DRIVE, CLASS 60, DIVISION SER. #59541, PUMP IS FROZEN AND WILL NOT TURN. January 29, 2002 January 28, 2003 364 days
Benning Elementary School FM-200224426 03 1/28/03 Benning Boiler Room Repair or replace aquastat on hot water storage tank, will not maintain set temp. January 23, 2003 January 28, 2003 5 days
Takoma Educational Center FM-200224626 03 1/28/03 Takoma E.S Boiler Room Repair BMG Hot Water House Pump January 27, 2003 January 28, 2003 1 day
Woodson High School FM-200223402 03 1/28/03 H.D.Woodson Boiler room Asbestos assessment may be required Repace ruptured 2" tee on return line to boiler to # 1 boiler Asbestos Code A - Clear for repairs 01/06/03. Horne Engineering - Tony Marcolin (RG 01/07/03) January 2, 2003 January 28, 2003 26 days
Hyde Elementary School FM-200220551 02 1/29/03 Hyde Boiler Room Boiler #1 Replace McDonnel Miller water control 2 switch.Model N47-2 November 1, 2002 January 29, 2003 89 days
Rudolph Elementary School FM-200209570 02 1/29/03 Rudolph Boiler room Water heater won't stay lit. The problem is electrical. Send electrician to correct problem. May 15, 2002 January 29, 2003 259 days
Shaed Elementary School FM-200224581 03 1/29/03 Shaed Boiler room URGENT Replace cut away section on # 2 boiler breeching area that was removed for tube replacement. January 26, 2003 January 29, 2003 3 days
Hyde Elementary School FM-200224669 03 1/29/03 Hyde Boiler Room Repair Boiler #2, need to trouble shoot . January 28, 2003 January 29, 2003 1 day
Stanton Elementary School FM-200219988 /02 1/29/03 (Stanton) 1. Asbestos assessment required. Ground floor Annex/Boiler room: Wooden door has rotted out all around door frame. Door will soon fall if not repaired. Asbestos Code-A clear for repair on 10/28/02 DCPS Charles E. Buchanan October 24, 2002 January 29, 2003 97 days
Bruce-Monroe Elementary School FM-200224642 03 1/29/03 (Bruce-Monroe) Through-out the building: Electrical problems in the following area's: Family center, 1st floor, Kitchen, 1st floor, Boiler room, basement. January 27, 2003 January 29, 2003 2 days
Kimball Elementary School FM-200223654 03 1/30/03 KIMBALL Old boiler room Replace inoperable sump pumps to prevent old boiler room from flooding. January 9, 2003 January 30, 2003 21 days
Tubman Elementary School FM-200223313 /02 1/30/03 Tubman (Boiler Room) 1. Boiler room flooded due to a defective sump pump. Note: School is without heat due to water level being at the burners. December 30, 2002 January 30, 2003 31 days
Tubman Elementary School FM-200224103 03 1/30/03 Tubman Boiler Room #2 boiler burner will not fire off January 16, 2003 January 30, 2003 14 days
Tubman Elementary School FM-200224591 03 1/30/03 Tubman Boiler Room Boiler #1 will not start, off on flame failure. Need both Boilers to heat Building. January 27, 2003 January 30, 2003 3 days
Roosevelt High School FM-200224935 03 2/1/03 Roosevelt Boiler Room Flooded Boiler Room Flooded Pit January 30, 2003 February 1, 2003 2 days
Orr Elementary School FM-200224946 03 2/2/03 Repair explosion doors on boilers Hinges are broken and need to be repair. January 31, 2003 February 2, 2003 2 days
Truesdell Elementary FM-200223972 03 2/3/03 Truesdell Boiler Room Basement Repair leaking return line size 3/4" in front of boilers and leaking 2" nipple at condensation tank. Asbestos Code A - Clear for repairs on 01/15/03. Horne Engineering - Tony Marcolin (RG 01/17/03) January 14, 2003 February 3, 2003 20 days
Brookland Elementary FM-200225048 03 2/3/03 Brookland Boiler room Check low gas pressure condition to boilers # 2. the flame is not burning correct. February 3, 2003 February 3, 2003 0 days
Brent Elementary School FM-200219905 /02 2/3/03 Brent Boiler Room P.M Chiller October 23, 2002 February 3, 2003 103 days
Green Elementary School FM-200225130 03 2/4/03 GREEN boiler room "URGENT" BOILER ROOM WILL FLOOD Repair/replace ruptured (2) two inch nipple on discharge line from sump pump. Replace (2) two cracked floor plugs to drains that are no longer used due to boiler room reconstruction. Plugs needed to prevent boiler room from flooding. February 4, 2003 February 4, 2003 0 days
Bruce-Monroe Elementary School FM-200224408 03 2/5/03 Bruce-Monroe Boiler Room Boiler Room Boiler #1 won't restart after shuting down it goes out on flame failure burner needs to be adjusted January 23, 2003 February 5, 2003 13 days
Orr Elementary School FM-200225047 03 2/5/03 ORR boiler room Check operation of boiler # 2 continuously going out in flame failure. February 2, 2003 February 5, 2003 3 days
Raymond Elementary School FM-200220109 /02 2/5/03 Raymond Boiler Room P.M Chiller October 28, 2002 February 5, 2003 100 days
Whittier Elementary School FM-200223549 03 2/5/03 Whittier Boiler Room Exterior Unstop drains outside boiler room back door. Approx (2) 3" Engineer attempted t unstop with negative results. Note: Flooding boiler room January 6, 2003 February 5, 2003 30 days
Thomas Elementary School FM-200221128 /02 2/5/03 THOMAS SCHOOL BOILER ROOM Replace leaking mechanical seals on condensate return pump # 3. NOTE: THIS IS THE ONLY OPERABLE CONDENSATE RETURN PUMP November 18, 2002 February 5, 2003 79 days
Ronald H. Brown MS FM-200126874 02 2/5/03 BROWN RON BOILER ROOM TSI, Exploratory Demolition. 1. ASBESTOS ASSESTMENT REQUIRED 2. REPAIR LEAKING 3/4 INCH SUPPLY LINE FOR ENGINEERS OFFICE UNIVENT. DCB (IT Group) / 703-461-6848 CODE A - ASBESTOS ABATED ON 02/18/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/20/02) January 7, 2002 February 5, 2003 394 days
Payne Elementary School FM-200225180 03 2/5/03 Payne Boiler Room Boilers off line -lock out status February 4, 2003 February 5, 2003 1 day
Barnard Elementary School FM-200224420 03 2/5/03 Barnard Boiler Room-Pump Room R/R faculity float on condensate return. Float is stick, either in open or close position. This float operaties the solenoid valve of the city water make up to tank January 23, 2003 February 5, 2003 13 days
Eaton Elementary School FM-200224855 03 2/5/03 Eaton E.S Boiler Room Basement Replace burn out motor on air handler unit B-1 Trane Unit, Motor Century Type 5C Volt 200-208, FR-M145T HP-1.5, AMP 6.0, PH-3, RPM-1745 January 29, 2003 February 5, 2003 7 days
Nalle Elementary School FM-200225344 03 2/6/03 NALLE J.C. boiler room Correct problem with down boiler # 2, burner continuously goes out on flame failure. 1 of 2 boiler operates February 6, 2003 February 6, 2003 0 days
Sousa Middle School FM-200225285 03 2/6/03 SOUSA JHS boiler room " URGENT URGENT NO HEAT TO BUILDING" Correct problem with boiler # 3 out on flame failure. One of three boiler operate. February 6, 2003 February 6, 2003 0 days
Eliot Junior High School FM-200225230 03 2/6/03 Eliot Boiler room Asbestos assessment required Repair or replace 2 1/2" blow down lines and or valve ,front and back of # 1 boiler , lines and or valves appears to have a restriction in them, can not blow boiler down. February 5, 2003 February 6, 2003 1 day
West Elementary School FM-200219912 /02 2/6/03 West Boiler Room P.M Chiller October 23, 2002 February 6, 2003 106 days
Orr Elementary School FM-200225376 03 2/6/03 ORR BOILER ROOM Thomas/Wilson responded to call, the building was cold. Boiler #2 was off on flame failure, reset boiler #2 it ran for five minutes then went back out on flame failure. February 6, 2003 February 6, 2003 0 days
Park View ES FM-200225146 03 2/6/03 "URGENT" Parkview Boiler Room Pump out flooded boilerroom February 4, 2003 February 6, 2003 2 days
Roosevelt High School FM-200103380 01 2/9/03 ROOSEVELT BOILER ROOM PROVIDE (9) NINE 1/2" BRONZE HAND WHEEL TRY COCKS WITH STAINLESS STEEL BALL TO REPLACE LEAKING TRY COCKS ON HIGH PRESS. BOILERS TRY COCKS MUST BE RATE FOR PRESSURES UP TO 250 PSI. February 9, 2001 February 9, 2003 730 days
Smothers ES FM-200223655 03 2/10/03 SMOTHERS pipe tunnel Replace (2 ) two inoperable sump pumps to prevent tunnel and boiler room from flooding. URGENT URGENT - boiler room will flood 2/10/03 - boiler room sump pump non-operable January 9, 2003 February 10, 2003 32 days
Nalle Elementary School FM-200225431 03 2/10/03 Nalle Boiler Room Boiler #2 down on lock out February 10, 2003 February 10, 2003 0 days
Woodson High School FM-200225425 03 2/10/03 Woodson, H.D. Boiler room Repair # 1 and # 2 Burners ,they cut in flame failure and be reset February 10, 2003 February 10, 2003 0 days
Spingarn High School FM-200224182 03 2/10/03 Spingarn Boiler Room Asbestos assessment required Replace 1/2" stud to refractory door to Boiler #4 Asbestos Code A - Clear for repairs on 01/22/03. Horne Engineering - Troy Wilcome (RG 01/23/03) January 21, 2003 February 10, 2003 20 days
Hart Middle School FM-200223603 03 2/11/03 HART boiler room Check boiler burners # 2 will not start this is the only operating boiler. January 7, 2003 February 11, 2003 35 days
Ballou Senior High School FM-200108406 01 2/11/03 BALLOU BOILER ROOM SUB-BASEMENT 1. ASBESTOS ASSESSMENT REQUIRED IN ORDER TO RECEIVE WORK PERMIT. 2. CLEAVERY BROOKS PACKAGED BOILER #4. REFACTORY ENTIRE INTERIOR OF THE BOILER INCLUDING THE MORRISON TUBE AREA. BOILER INFO: MOD #760-125A SER#L47171 Tracking #10087 EEC (Envirobate)/301-436-1150 Code A - Asbestos abated on 06/07/02 PER Leroy Minton confirmation.(RG 06/18/02) April 13, 2001 February 11, 2003 669 days
Hart Middle School FM-200225510 03 2/11/03 Hart Boiler Room Replace inoperable High/Low limit control and operator limit control on Boiler #1 and #2. Note: Amount two (2) High / Low Limit and two (2) Operator Limit February 11, 2003 February 11, 2003 0 days
Hine JHS FM-200219904 /02 2/11/03 Hine Boiler Room P.M Chiller October 23, 2002 February 11, 2003 111 days
Shaed Elementary School FM-200219909 /02 2/11/03 Shaed Boiler Room P.M Chiller October 23, 2002 February 11, 2003 111 days
Shaed Elementary School FM-200203408 02 2/12/03 Shaed School (Boiler Room ) 1. Asbestos assestment required 2. Replace 4" Multi gate valves on chill water condenser line. Valve is not holding causing hot water to be carried over to chiller. EEC/Envirobate/301-742-0330 Code A Clear for Repair asbestos abatement date was 06-26-02 confirmed by Leroy Minton DCPS Safety Sheila R. Howard DCPS Safety 06-28-02. February 25, 2002 February 12, 2003 352 days
Amidon Elementary School FM-200201801 02 2/12/03 AMIDON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 3/4 BYPASS VALVE ON #1 BOILER. January 25, 2002 February 12, 2003 383 days
Wilson J. O. ES FM-200225649 03 2/12/03 Wilson, J.O. Boiler Room Repair domestic hot water circulating pump has broken coupling February 12, 2003 February 12, 2003 0 days
Ludlow-Taylor ES FM-200225179 03 2/12/03 Ludlow-Taylor Boiler Room Boilers off line-lock out status February 4, 2003 February 12, 2003 8 days
Bunker Hill Elementary School FM-200222133 02 2/12/03 Bunker Hill Nurse's Restroom Asbestos assessment required Boiler #1 repair and replace crack section. Asbestos Code A - Clear for repairs on 12/09/02. Horne Engineering - Sheryll James (RG 12/12/02) December 6, 2002 February 12, 2003 68 days
Raymond Elementary School FM-200225552 03 2/13/03 Raymond Boiler Room P.M Chiller February 11, 2003 February 13, 2003 2 days
Winston EC FM-200225535 03 2/13/03 Winston Boiler Room P.M Chiller February 11, 2003 February 13, 2003 2 days
Woodson High School FM-200225538 03 2/13/03 H. D Woodson Boiler Room P.M Chiller February 11, 2003 February 13, 2003 2 days
Clark Elementary School FM-200224993 03 2/13/03 Clark Boiler Room Asbestos assessment required Replace leaking tubes in Boiler #1. Asbestos Code A - Clear for repairs on 02/03/03. Horne Engineering - Troy Wilcome (RG 02/04/03) January 31, 2003 February 13, 2003 13 days
Gibbs Elementary School FM-200225545 03 2/13/03 Gibbs Boiler Room P.M Chiller February 11, 2003 February 13, 2003 2 days
Hine JHS FM-200225546 03 2/13/03 Hines Boiler Room P.M Chiller February 11, 2003 February 13, 2003 2 days
Benjamin Banneker Academic HS FM-200225737 03 2/13/03 Banneker Boiler room Repair or replace sump pumps # 1 and # 2, boiler room is flooded,problem appears to be with the pumps and not the motors February 13, 2003 February 13, 2003 0 days
Roosevelt High School FM-200225461 03 2/13/03 (Roosevelt) Boiler room: Repairs on Thursday: Supply materials to make necessary repairs to cables, to supply power to boiler room. February 10, 2003 February 13, 2003 3 days
Johnson JHS FM-200225543 03 2/13/03 Johnson Boiler Room P.M Chiller February 11, 2003 February 13, 2003 2 days
Terrell Mc ES FM-200223314 /02 2/13/03 Terrell, M.C. Boiler Room Replace relief valve: model #M, serial # 740, size 1 1/2, set 40-LBS, vavle keep popping> December 30, 2002 February 13, 2003 45 days
West Elementary School FM-200224690 03 2/13/03 West Boiler Room Basement Asbestos Assestment Required Replace 1 1/2" gate valve on back of #1 and #2 boilers blow down lines. Valves will not hold (leaking) Asbestos Code A - Clear for repairs on 01/29/03. Horne Engineering - Sharon Voss ( RG 01/30/03) January 28, 2003 February 13, 2003 16 days
Brightwood Elementary School FM-200203776 02 2/13/03 BRIGHTWOOD BOILER ROOM REPAIR BOILER #3. BOILER IN LOCK OUT, STAND BY MODE. (CONTRACTOR) March 4, 2002 February 13, 2003 346 days
Ronald H. Brown MS FM-200225542 03 2/13/03 Ron Brown Boiler Room P.M Chiller February 11, 2003 February 13, 2003 2 days
Tubman Elementary School FM-200225732 03 2/13/03 Tubman Boiler room "URGENT" Repair burner #1 , cuts off on flame failure, one boiler will not carry the building on cold days. Repair boiler burner # 2 continuously going out on flame failure. February 13, 2003 February 13, 2003 0 days
School WW High School FM-200225831 03 2/14/03 School W/O Walls Boiler room Repair or replace leaking pilot line and or valve on the # 1 boiler ,line has a tag on it, also cover exposed wires on the boiler. February 14, 2003 February 14, 2003 0 days
Spingarn High School FM-200225868 03 2/14/03 Spingarn Boiler Room Boiler #4 Replace refractory to door. February 14, 2003 February 14, 2003 0 days
Janney Elementary School FM-200225596 03 2/14/03 Janney Boiler Room Exterior R/R exterior lock on boiler room door key will not fully engage in key way to enable or disable lock February 11, 2003 February 14, 2003 3 days
Walker-Jones EC FM-200225533 03 2/14/03 Walker Jones Boiler Room P.M Chiller February 11, 2003 February 14, 2003 3 days
Emery Elementary School FM-200219596 /02 2/15/03 Emery Boiler Room Send burner technician with calibration instruments to properly claibrate burners at all modulation levels on boiler #1 and #2. When burners are calibrated properly they burnt more efficiently and cleaner * Alot of soot in boilers during cleaning. October 17, 2002 February 15, 2003 121 days
Emery Elementary School FM-200218751 02 2/15/03 Emery Boiler Room 1. Boiler# 2 - Down on flame failure October 3, 2002 February 15, 2003 135 days
Ballou Senior High School FM-200225558 03 2/18/03 Ballou Boiler Room P.M Chiller February 11, 2003 February 18, 2003 7 days
Stevens Elementary School FM-200225917 03 2/18/03 STEVENS URGENT!!!! BOILERROOM 1) THE SKY LIGHT GLASS IS BROKEN, AND GLASS IS HANGING ON THE PIPE AND FROM THE SKYLIGHT. PLEASE REPAIR. February 18, 2003 February 18, 2003 0 days
Anacostia Senior High School FM-200225925 03 2/19/03 Anacostia Boiler Room Busted 2" black nipple on supply line feeding all boilers. Continuously loosing water. NO HEAT February 19, 2003 February 19, 2003 0 days
Bruce-Monroe Elementary School FM-200225946 03 2/21/03 Bruce-Monroe Boiler Room Repair/Replace rupture 1" domestic hot water line in the boiler room. February 20, 2003 February 21, 2003 1 day
Plummer Elementary School FM-200225927 03 2/21/03 Plummer Boiler Room Replace a leaking 3" inch. circulating line and replace the blow down on the storage tank February 19, 2003 February 21, 2003 2 days
Bunker Hill Elementary School FM-200225947 03 2/22/03 Bunker Hill Boiler Room Made necessary repairs to back flow preventor valve February 20, 2003 February 22, 2003 2 days
Meyer Elementary School FM-200225343 03 2/22/03 Meyer Boiler room floor Unstop floor drains between Boilers #1 and #2 . February 6, 2003 February 22, 2003 16 days
Payne Elementary School FM-200226011 03 2/23/03 PAYNE BOILER ROOM Repair/Replace rupture line in the boiler room. February 21, 2003 February 23, 2003 2 days
Jefferson JHS FM-200225924 03 2/24/03 Jefferson Boiler Room Replace 1 1/2" black pipe (approx 8" long) at the top of Hartford Loop. Pipe leaking is the supply line from the condensate pump. Boiler is now inoperable. No insulation on pipe. February 19, 2003 February 24, 2003 5 days
Kimball Elementary School FM-200226081 03 2/25/03 Old Boiler Room in flooded north wing. February 24, 2003 February 25, 2003 1 day
Seaton Elementary School FM-200225550 03 2/25/03 Seaton Boiler Room P.M Chiller February 11, 2003 February 25, 2003 14 days
Clark Elementary School FM-200225117 03 2/26/03 Clark Basement/Boiler Room Repair/Repair boiler #1 has leaking tubes. Note: One tube, 2 1/2 " Only (2) boilers in plant Asbestos Code A - Clear for repairs on 02/14/03. Horne Engineering - Sharon Voss (RG 02/19/03) February 3, 2003 February 26, 2003 23 days
Woodson High School FM-200225856 03 2/27/03 Woodson,H.D Boiler room Asbestos assessment required Repair or replace 1 1/2" leaking return condensate return line on #2 boiler Asbestos Code A - Clear for repairs on 02/19/03. Horne Engineering - Bipin Nanavaty (RG 02/20/03) February 14, 2003 February 27, 2003 13 days
Jessie LaSalle Elementary FM-200226316 03 2/27/03 LaSalle Boiler room Repair modulating control on # 1 boiler boiler only runs in low fire ,#2 boiler down also Flame failure,FM-200221236 February 27, 2003 February 27, 2003 0 days
Randle-Highlands ES FM-200226340 03 3/1/03 Randle-Highland Boiler Room First Floor Work with water works,trying to get water cut off and also waited on Pepco to cut electricity off. Help remove snow from parking lot to find main water shut-off February 27, 2003 March 1, 2003 2 days
Randle-Highlands ES FM-200226333 03 3/1/03 Randle-Highland Boiler Room Basement Check on flooded boiler for Mr. Tony Law Informed him that contractor is pumping water out February 27, 2003 March 1, 2003 2 days
Thomson Elementary School FM-200207912 02 3/3/03 Thomson E.S. (boiler room) 1. asbestos assessment required. 2. R/R one (1") domestic hot water line over top boilers, line is reuptured in two places. Retro (IT Group) /703-461-6848 Code A - Asbestos was abated on 05/17/02 PER Leroy Minton confirmation. (RG 05/22/02) May 17, 2002 March 3, 2003 290 days
Emery Elementary School FM-200226385 03 3/3/03 Emery Boiler Room Repair electrical wiring on domestic hot water tank. Wire has come loose from electronic ignition. School has no hot water. February 28, 2003 March 3, 2003 3 days
Malcolm X ES FM-200225869 03 3/3/03 Malcolm X Exterior of building Repair / Replace locks on shed and the boiler room door. February 14, 2003 March 3, 2003 17 days
Aiton Elementary School FM-200226476 03 3/4/03 Aiton Boiler Room Boiler #1 Flame failure March 4, 2003 March 4, 2003 0 days
Clark Elementary School FM-200225573 03 3/4/03 Clark Boiler Room P.M Chiller February 11, 2003 March 4, 2003 21 days
Gage-Eckington ES FM-200225190 03 3/4/03 Gage-Eckington Boiler Room Asbestos assessment required Boiler #1 water in fire box. Asbestos Code A - Clear for repairs on 02/06/03. Horne Engineering - Bipin Nanavaty (RG 02/11/03) February 5, 2003 March 4, 2003 27 days
Clark Elementary School FM-200219911 /02 3/4/03 Clark Boiler Room P.M Chiller October 23, 2002 March 4, 2003 132 days
Bunker Hill Elementary School FM-200226456 03 3/5/03 Bunkerhill E.S Boiler Room Repair burner on #1 boiler March 3, 2003 March 5, 2003 2 days
Kramer Middle School FM-200226058 03 3/5/03 Kramer Boiler Room Boiler #1 out on flame failure. February 24, 2003 March 5, 2003 9 days
Miner Elementary FM-200226423 03 3/7/03 Miner Boiler Room Asbestos Assessment Required Assess and abate piping on condensate return line receiver tank located in boiler room. Asbestos Code A - Clear for repairs on 02/28/03. Horne Engineering - Sharon Voss (RG 03/04/03) February 28, 2003 March 7, 2003 7 days
Maury Elementary School FM-200226425 03 3/7/03 Maury Boiler Room Asbestos Assessment Required Assess and abate piping on condensate return line receiver tank located in boiler room. Asbestos Code A clear for repairs 03/03/03 DCPS Safety R. Edwards (RE) February 28, 2003 March 7, 2003 7 days
Roosevelt High School FM-200226598 03 3/7/03 Roosevelt Boiler Room Basement Flooded boiler room March 5, 2003 March 7, 2003 2 days
Takoma Educational Center FM-200226615 03 3/7/03 Takoma Boiler Room Repair seal in circulating convector pump Note: Leaking badly March 5, 2003 March 7, 2003 2 days
Kimball Elementary School FM-200226624 03 3/8/03 Kimball Boiler Room Pump water from boiler room 2 1/2 feet. March 6, 2003 March 8, 2003 2 days
Bunker Hill Elementary School FM-200226625 03 3/8/03 Bunker Hill Boiler Room Replace blow down valve on boiler. March 6, 2003 March 8, 2003 2 days
Jessie LaSalle Elementary FM-200226760 03 3/9/03 LaSalle E.S Boiler Room First Floor Disassemble B & G pump for hot water. Hot water working now March 7, 2003 March 9, 2003 2 days
Spingarn High School FM-200226762 03 3/9/03 Spingarn SHS Boiler Room Provide pump and holes for flood in tunnel. (Used my vehicle personal to transport equipment) March 7, 2003 March 9, 2003 2 days
Nalle Elementary School FM-200226619 03 3/10/03 Nalle Boiler Room Repair or replace air compressor making noises (loud) March 6, 2003 March 10, 2003 4 days
Duke Ellington School FM-200219915 /02 3/11/03 Duke Ellington Boiler Room P.M Chiller October 23, 2002 March 11, 2003 139 days
Payne Elementary School FM-200226676 03 3/12/03 Payne Boiler Room Repair/Replace 1" steam leak in incinerator room. March 6, 2003 March 12, 2003 6 days
Maury Elementary School FM-200223082 /02 3/12/03 Maury Boiler #1 low water cut out will not shut off the boiler in low water. December 23, 2002 March 12, 2003 79 days
Bunker Hill Elementary School FM-200226775 03 3/12/03 BUNKER HILL boiler room Repair/replace condensate return pump March 10, 2003 March 12, 2003 2 days
Maury Elementary School FM-200223533 03 3/12/03 Maury Boiler room Repair # 2 boiler,modulator motor or controls is not responding ,boiler stuck in the purge cycle. January 6, 2003 March 12, 2003 65 days
Shaw JHS FM-200226892 03 3/12/03 Shaw Boiler Room P.M Chiller March 12, 2003 March 12, 2003 0 days
Payne Elementary School FM-200226943 03 3/13/03 Payne Boiler Room Repair/Replace rupture discharge line to sump pump. March 12, 2003 March 13, 2003 1 day
Kramer Middle School FM-200220613 /02 3/13/03 Kramer Boiler Romm Tunnel Repair or replace busted 3/4" steam supply line in tunnel. No insulation on pipes. Asbestos Code A - Clear for repairs on 12/12/02. Horne Engineering - Tony Marcolin (RG 12/13/02) November 12, 2002 March 13, 2003 121 days
Garfield ES FM-200225950 03 3/13/03 GARFIELD boiler room Repair/replace leaking tubes in boiler # 1 (two ) February 20, 2003 March 13, 2003 21 days
Ferebee-Hope Elementary School FM-200125124 /01 3/13/03 (FEREBEE-HOPE) EXTERIOR/ HATCH TO BOILER ROOM FENCE CREW: SURVEY TO INSTALL CAGE TYPE FENCE AROUND HATCH DOORS (15" x 6") WITH LOCKING GATE. December 13, 2001 March 13, 2003 455 days
Benjamin Banneker Academic HS FM-200226315 03 3/13/03 Banneker Boiler Room Asbestos assessment require Boiler #1 replace leaking tubes. Asbestos Code A - Clear for repairs on 02/28/03. Horne Engineering - Roger Kager (RG 03/05/03) February 27, 2003 March 13, 2003 14 days
Orr Elementary School FM-200225398 03 3/13/03 Orr Boiler Room Asbestos assessment required Circulating pump #2 is leaking return water. Gage nipple needs to be replaced (1/4 inch) Asbestos Code A - Clear for repairs on 02/07/03. Horne Engineering - Troy Wilcome (RG 02/11/03) February 7, 2003 March 13, 2003 34 days
Thomas Elementary School FM-200118928 01 3/13/03 (THOMAS) OUTSIDE GROUNDS INSTALL GATE AROUND STAIRWELL LEADING TO CUSTODIANS OFFICE AND BOILER ROOM. August 31, 2001 March 13, 2003 559 days
Cook J.F. Elementary School FM-200226777 03 3/14/03 Cook, JF Boiler Room Check sump pump in boiler room and unstop drain. Need to change status to URGENT BOILER ROOM IS FLOODING 2" OF WATER ON FLOOR. (3/11/03) March 10, 2003 March 14, 2003 4 days
Cook J.F. Elementary School FM-200226759 03 3/14/03 J.F.Cook Boiler Room Repair sump pump in boiler room. Boiler Room has flooded. March 7, 2003 March 14, 2003 7 days
Clark Elementary School FM-200217352 02 3/14/03 Clark Boiler room Repair or replace circulating pumps #1 and 2 that are leaking. Need mechanical seals repaired or replaced. Ser. #: 197088-1 (Weinman), Date: 8/2/92, max W/P: 175, Model: 4L3-100PN-14-G-U. September 12, 2002 March 14, 2003 183 days
John Burroughs ES FM-200102680 /1/01 3/14/03 BURROUGHS BASEMENT BOILER ROOM R/R MOTOR AND/OR PUMP ON #2 CIRCULATING PUMP. THE PUMP BLOWS OUT THE FUSE WHEN WE TRY TO REPLACE THE FUSES. US ELECTRICAL MOTOR HPB 5.0, PH 3, HZ 60, RPM 1715, FRAME 184T, SF 1.15, VOLTS 200, FL AMPS 15.8, TYPE DDP, 6206-2Z-J/C3 END BRG, SHIFT OPP 6202-2Z-J/C3 ITT AC PUMPS 2000 SERVES PUMP H.T.P. 2000 AVS CHALMERS. PUMP. TYPE 2000 SIZE 2-1/2 X 2 X 9L, FRAME 330, GPM 90, HD FT 75 RPM 1250 IMP. DIA. 8.80. February 1, 2001 March 14, 2003 771 days
Clark Elementary School FM-200201709 02 3/14/03 CLARK BOILER ROOM REPAIR OR REPLACE BROKEN UNIVENTS IN CLASSROOM, THERE IS NO HEAT AT THIS TIME, ALSO PUT IN OSY VALVE. REPAIR SUPPLY LINE ON AHU IN CAFETERIA. THE LINE ATTACH TO THE COIL IS SPLIT AND LEAKING CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER ( STEPNEN CALDWELL ) ON 3/04/02 (CEB) January 25, 2002 March 14, 2003 413 days
Maury Elementary School FM-200226907 03 3/14/03 Maury E.S Boiler Room Perform electrical rewire of condensate return pumps March 12, 2003 March 14, 2003 2 days
Davis Elementary School FM-200103979 01 3/14/03 Davis Boiler Room Repair badly leaking seals on (2) pumps. Pump #1 Marathon, Pump #2 Lincoln February 21, 2001 March 14, 2003 751 days
Clark Elementary School FM-200122814 01 3/14/03 CLARK BOILER ROOM PERFORM PNEUMATIC REPAIRS TO HEAT SYSTEM. November 2, 2001 March 14, 2003 497 days
Draper Elementary School FM-200120211 01 3/14/03 DRAPER BOILER ROOM FURNISH MATERIAL TO INSTALL GAS BURNER FOR BOILER. September 20, 2001 March 14, 2003 540 days
Young Elementary School FM-200209727 02 3/17/03 Young Boiler room Unclog drain at boiler room rear door. Drain is stopped up and will not take water. June 18, 2002 March 17, 2003 272 days
Miner Elementary FM-200220198 /02 3/17/03 Asbestos assessment required. Repair possible leak in the rear of #2 boiler. Asbestos Code -C 10/31/02 DCPS Charles E. Buchanan October 29, 2002 March 17, 2003 139 days
Reed LC FM-200203749 02 3/17/03 Reed Boiler room Unstop floor drain located between boilers #2 and 3. March 1, 2002 March 17, 2003 381 days
Reed LC FM-200205855 02 3/17/03 Reed Boiler Room 1. Asbestos assessA plumber is needed to replace the mixing valve for domestic hot water heater. There is no hot water in pool area and Learning center #2 which is right over the pool. These areas are the farthest from the hot water tank. Other areas in the building have warm water and some areas have hot water. April 16, 2002 March 17, 2003 335 days
Hine JHS FM-200120493 01 3/17/03 HINES BOILER ROOM REPAIR OR REPLACE A 3X3X1 INCH COUPLING AT BOTTOM OF STORAGE TANK. WP-200108863 September 25, 2001 March 17, 2003 538 days
Thomson Elementary School FM-200204412 02 3/17/03 (Thomson) ****Emergency**** Basement Boiler Room There is a leak in the ceiling [coming from the cold water supply line {3/4-inch galvanized copper pipe}] near boiler #1. The leak is between the T and the elbow & the water runoff is collecting in the restroom above. POC: Mr. Oneill Asbestos Code A - Clear For Repairs On 03/14/02. Richard Gibson - DCPS-Safety (RG 03/14/02) March 14, 2002 March 17, 2003 368 days
Garrison ES FM-200116550 01 3/17/03 GARRISON BOILER ROOM R/R LEAKING DOMESTIC HOT WATER TANK. WP-200107644 August 2, 2001 March 17, 2003 592 days
Wilson J. O. ES FM-200114561 01 3/17/03 J.O. WILSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE THREE 1/4 " GATE VALVES ON FEED WATER REGULATOR SUPPLY AND BYPASS VALVES NOT HOLDING ON BOTH BOILERS. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: STEPHEN CALDWELL July 2, 2001 March 17, 2003 623 days
Takoma Educational Center FM-200102215 01 3/17/03 TAKOMA BOILER ROOM REPLACE DEFECTIVE MAGNETIC STARTER AQUASTAT ON HOT WATER STORAGE TAN (NO HOT WATER). STARTER: FURNAS SZ 14CF3BC71 January 26, 2001 March 17, 2003 780 days
Miner Elementary FM-200212602 02 3/17/03 Cut loose metal from water leg of 1 boiler front side,so boiler will pass inspection July 23, 2002 March 17, 2003 237 days
Woodson High School FM-200100149 1/7/01 3/17/03 WOODSON, H.D. THE HEATING PLANT MAKETHE NECESSARY REPAIRS TO # 1 & 2 BOILER FEED PUMPS. CONTROLS TO BOILER FEED PUMPS. BOILER FEED PUMPS LEAKING AND HAVE TO CONSTANTLY HAND FEED # 1 & 2 BOILERS. January 7, 2001 March 17, 2003 799 days
Miner Elementary FM-200209546 02 3/17/03 Miner Basement Boiler Room 1. Asbestos assessment required. 2. Boiler #1 repair brick and refractory in boiler. Code A-clear for repair by Horne Engineer ( Sam Ebrahim ) on 6/17/02 June 13, 2002 March 17, 2003 277 days
Jefferson JHS FM-200226124 03 3/17/03 Jefferson Boiler Room Boiler #2 will not start,has pilot, and main flame for a few seconds and shuts off. February 24, 2003 March 17, 2003 21 days
Takoma Educational Center FM-200218833 02 3/17/03 TAKOMA SCHOOL Boiler room ] Check operation of domestic hot water heater. Water is not reaching set temperatures. October 4, 2002 March 17, 2003 164 days
Stuart-Hobson Middle School FM-200100876 1/11/01 3/17/03 STUART-HOBSON BOILER ROOM REPAIR OR REPLACE BURNED OUT VACUUM PUMP MOTOR. RETRAP ENTIRE BUILDING. January 11, 2001 March 17, 2003 795 days
Barnard Elementary School FM-200214643 02 3/17/03 Basement Boiler Room Remove on approximate 6" clean out plug at bottom right side of boiler #2 Was n't able to remove it out selves. Note: Preparing boilers for inspection (Annual) August 15, 2002 March 17, 2003 214 days
Kramer Middle School FM-200102698 01 3/17/03 KRAMER BOILER ROOM KRAMER MS BOILER ROOM (1) ASBESTOS ASSESSMENT IS REQUIRED (2)TWO PIPES OVER HOT WATER TANK ARE LEAKING - ONE 1-1/2" AND ONE 2". DOMESTIC HOT WATER TANK. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/06/01. HORNE ENGINEERING - SHERYLL GAMES (RG) February 1, 2001 March 17, 2003 774 days
Kramer Middle School FM-200100758 01 3/17/03 KRAMER BOILER ROOM REPAIR BURNER ON BOILER #1 DOWN ON MAIN FLAME FAILURE. ONLY (1) BOILER IS IN OPERATION. HC-20001081 January 10, 2001 March 17, 2003 796 days
Turner Elementary School FM-200104457 01 3/17/03 TURNER GROUND - BOILER ROOM PLEASE SNAKE OUT INSIDE, BOILER ROOM; WAS INSTRUCTED THAT NO WATER SHOULD BE ON FLOOR IN THAT ROOM TO SHORT OUT EMERGENCY GENERATOR. RIGHT NOW THE DRAIN VERY, VERY SLOW. NEED DONE. ASAP February 27, 2001 March 17, 2003 748 days
Barnard Elementary School FM-200203069 02 3/17/03 BARNARD BOILER ROOM/TUNNEL 1. ASBESTOS ASSESSMENT REQUIRED 2.REPAIR LEAKING 3/4" NIPPLE ON CONDENSATE RETURN LINE ON 1 3/4" TEE COMING OFF MAIN STEAM LINE IN TUNNEL. LINE IS RUSTY. ASBESTOS CODE A-CLEAR FOR REPAIR NO 2/21/02 HORNE ENGINEER: STEPHEN CALDWELL February 19, 2002 March 17, 2003 391 days
Randle-Highlands ES FM-200218866 02 3/17/03 Randle-Highlands boiler room Repair/replace leaking tubes boiler # 2. October 4, 2002 March 17, 2003 164 days
Randle-Highlands ES FM-200213466 02 3/17/03 Randle Highland Boiler Room Check domestic hot water heater, will not light. August 2, 2002 March 17, 2003 227 days
Backus Middle School FM-200213738 02 3/17/03 Backus boiler room Replace (2) two 2 1/2" check valves coming off of the cold water main. Cold water side on sinks Hot water circulating though cold side of sink and flush valve on toilet. Furnish materials for repairs. August 7, 2002 March 17, 2003 222 days
Eaton Elementary School FM-200219914 /02 3/17/03 Eaton Boiler Room P.M Chiller October 23, 2002 March 17, 2003 145 days
Randle-Highlands ES FM-200126464 /01 3/17/03 RANDLE HIGHLANDS ASBESTOS ASSESSMENT REQUIRED BOILER ROOM TUNNEL REPAIR/REPLACE CONDENSATE RETURN PUMPS. NO. 1 PUMP MECHANICAL SEALS LEAKING. NO. 2 WILL NOT START. CONDENSATE IS FLOODING TUNNEL AREA. POC MR. GAUSE @ 202-438-7543 MR. RUTHERFORD @ 202-345-1546 CODE A -CLEAR FOR REPAIR BY HORNE ENGINEERING EDWARD RODRIGUEZ 12-31-01 (S.R. HOWARD 12-31-01) December 31, 2001 March 17, 2003 441 days
Turner Elementary School FM-200112714 01 3/17/03 TURNER BOILER ROOM REPAIR 4 " DRAIN THAT IS BUSTED AND KEEPS BACKING UP WHEN IT RAINS AND FLOODS. BOILER ROOM AND STORAGE ROOM ARE AFFECTED. WP-200108659 June 7, 2001 March 17, 2003 648 days
Seaton Elementary School FM-200205747 02 3/17/03 Seaton Boiler Room Replace 1 1/4" valve in the boiler room that feeds bathroom above. Sited by health inspector. April 12, 2002 March 17, 2003 339 days
Seaton Elementary School FM-200215444 02 3/17/03 Seaton Boiler Room Repair A O Smith hot water heater. Piolet will not lignite. August 23, 2002 March 17, 2003 206 days
Stuart-Hobson Middle School FM-200100881 1/11/01 3/17/03 STUART-HOBSON BOILER ROOM REPLACE 2 MOTORS ON RETURN PUMPS. (MAGNELEK JET PUMP DUTY). BOTH MOTORS ARE BURNED OUT. HC020000918 January 11, 2001 March 17, 2003 795 days
Barnard Elementary School FM-200124101 /01 3/17/03 BARNARD BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 17, 2003 472 days
Shaed Elementary School FM-200125270 /01 3/17/03 SHEAD BOILER ROOM 1.FURNISH MATERIALS TO REPLACE BELL AND GOSSETT DOMESTIC HOT WATER CIRCULATING PUMP, ON HOT WATER STORAGE TANK SERIES #100-BNFI/669. 2.REPAIR 1" SUPPLY LINE IN SAME AREA. December 14, 2001 March 17, 2003 458 days
Randle-Highlands ES FM-200124128 /01 3/17/03 RANDLE HIGHLAND BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 17, 2003 472 days
Emery Elementary School FM-200219825 /02 3/17/03 Emery E.S Boiler Room Unstop (4) floor drains in boiler room, Engineer attempted to unstop with negative results. October 22, 2002 March 17, 2003 146 days
Langdon Elementary School FM-200202476 02 3/17/03 LANGDON BOILER ROOM REPAIR LOCHINVAR DOMESTIC HOT WATER HEATER OFF ON MAIN FLAME FAILURE. February 5, 2002 March 17, 2003 405 days
Lafayette Elementary School FM-200109487 01 3/17/03 LAFAYETTE BOILER ROOM UNSTOP DRAINS IN BOILER ROOM WP-200108809 May 2, 2001 March 17, 2003 684 days
West Elementary School FM-200221174 /02 3/17/03 West (Boiler Room) 1. Replace 1 1/4 inch gate valve. Valve is brken in the seated position, causing building to be without domstic hot water. November 18, 2002 March 17, 2003 119 days
Raymond Elementary School FM-200219830 /02 3/17/03 Raymond Old Boiler Room Basement Unstop floor drain in old boiler room water is standing on the floor drawinng flying insects. *Roving Engineer attempted to unstop with negative results* October 22, 2002 March 17, 2003 146 days
Bruce-Monroe Elementary School FM-200104355 01 3/17/03 Bruce Monroe Boiler Room Survey and make necessary repairs to leaking city water meter. February 26, 2001 March 17, 2003 749 days
Coolidge High School FM-200119645 01 3/17/03 COOLIDGE BOILER ROOM BOILER #1 WILL NOT LIGHT OFF. ALL ELECTRONICS HAVE ALREADY BEEN CHECKED BY ENGINEER ON SITE. September 11, 2001 March 17, 2003 552 days
Randle-Highlands ES FM-200109914 01 3/17/03 RANDLE HIGHLANDS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR SEWER EJECTOR PUMPS #1 & 2. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/10/01. MR. RICHARD GIBSON - SAFETY (202)437-5937 May 10, 2001 March 17, 2003 676 days
Randle-Highlands ES FM-200103576 6 2/13/01 3/17/03 RANDLE HIGHLAND BOILER ROOM REPAIR FLOAT CONTROL SWITCH ON SUMP PUMPS AND DISCHARGE LINE PIT. NO NAME PLATE. WP-200108657 February 13, 2001 March 17, 2003 762 days
Kenilworth ES FM-200126493 02 3/17/03 KENILWORTH BOILER ROOM REPLACE COUPLING ON D.H.W. CIRCULATING PUMP (BELL & GOSSETT). January 2, 2002 March 17, 2003 439 days
Takoma Educational Center FM-200226592 03 3/17/03 Takoma Boiler Room First Floor Replace (burn out motor) Hot water circulate pump and motor. Name: Bell Gosset ITT Industries Information On Motor: RPM 1750 Volts 115 208,231 H.P 1/4 Modle 70B56A17 D57E Part # 403 576 PH1 Note: In-Line pump/supply hot water to gymnasium March 5, 2003 March 17, 2003 12 days
Bruce-Monroe Elementary School FM-200120857 01 3/17/03 BRUCE-MONROE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE FLOW SWITCH ON HOT WATER HEATER. EXISTING SWITCH HAS DETERIORATED. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/10/01. HORNE ENGINEERING - STEPHEN CALDWELL (RG) October 2, 2001 March 17, 2003 531 days
Aiton Elementary School FM-200204455 02 3/17/03 (Aiton) Jacobsen tractor lawn mower [located in the boiler room] needs repair, a complete tune-up, oil change, tires repair and the broken seat needs repair. POC: Myers Mariel March 14, 2002 March 17, 2003 368 days
Park View ES FM-200226177 03 3/17/03 Parkview Boiler Room Basement Drain need to be unstop Drain behind boiler #1 Note: This area has flooding problems. February 25, 2003 March 17, 2003 20 days
Bruce-Monroe Elementary School FM-200214839 02 3/17/03 Bruce-Monroe Boiler room Unclog stopped up floor drains in boiler room . Two (2) drain in boiler room A.S.A.P. August 16, 2002 March 17, 2003 213 days
Reed LC FM-200117558 01 3/17/03 REED BOILER ROOM REPAIR/REPLACE TWO (2) SUMP PUMPS FOR BOILER ROOM DRAINS. WP-200107655 August 15, 2001 March 17, 2003 579 days
Park View ES FM-200221108 /02 3/17/03 Parkview Boiler room Check flooded boiler room , sump pump,and drains. 8" inches of water on the floor. November 18, 2002 March 17, 2003 119 days
Miner Elementary FM-200124148 /01 3/17/03 MINER BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 17, 2003 472 days
Duke Ellington School FM-200126872 02 3/17/03 ELLINGTON BOILER ROOM FURNISH MATERIALS TO REPLACE LEAKING DOMESTIC HOT WATER HEATER TANK 85 GAL. A.O. SMITH MODEL-BTC 365 A 962; SEARIAL #LL96-0598710-962. TANK HAS RUSTED OUT ON THE BOTTOM. January 7, 2002 March 17, 2003 434 days
Sousa Middle School FM-200103884 01 3/17/03 Sousa Boiler Room Repair/Replace defective oil pumps #1 and #2. February 20, 2001 March 17, 2003 755 days
Backus Middle School FM-200205482 02 3/17/03 Backus Boiler Room Repipe injector pump discharge line to sewer. Existing line dumps into a mop sink that floods the 1st floor when it discharges. April 5, 2002 March 17, 2003 346 days
Spingarn High School FM-200203725 02 3/17/03 Spingarn Boiler room Install sump pump in west corner of boiler room. Water is coming in boiler room from outside through wall and floor causing flood February 28, 2002 March 17, 2003 382 days
Miner Elementary FM-200117768 01 3/17/03 MINER BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR THREADED FLANGE FOR WATER LEG NIPPLE 1-1/2" OPENING STRIPPED THREADS. BOILER #2. ASBESTOS CODE A-CLEAR FOR REPAIR ON 12/14/01 BY HORNE ENGINEER: SHERYLL JAMES August 17, 2001 March 17, 2003 577 days
Powell Elementary School FM-200105454 01 3/17/03 POWELL BOILER ROOM REPAIR DAMAGED DOMESTIC WATER PIPE IN BOILER ROOM CONNECTED TO HOSE BIB. LEAKING IN FLOOR. March 9, 2001 March 17, 2003 738 days
Barnard Elementary School FM-200215268 02 3/17/03 Basement Boiler Room Remove approximately 3" to 4" water side clean out plug. Located bottom right side of boiler # 2. We were unable t remove it ourselves Note: Needed for annual boiler inspection. August 21, 2002 March 17, 2003 208 days
Bunker Hill Elementary School FM-200104633 01 3/17/03 Bunker Hill Boiler Room Install hot water gauge on domestic hot water tanks #1 and #2. March 1, 2001 March 17, 2003 746 days
Miner Elementary FM-200226714 03 3/17/03 Miner Boiler Room Check Boilers, No power going to Boilers. March 7, 2003 March 17, 2003 10 days
Miner Elementary FM-200220732 /02 3/17/03 Miner Boiler room Repair oe replace 4" cross tee that's leaking on the return line behind # 2 boiler. Weeks of 11/4/02-11/8/02 FM-200220821 Asbestos Code A-clear for repair by Horne Engineer Sharon Voss on 11/13/02 DCPS Charles E Buchanan November 12, 2002 March 17, 2003 125 days
Miner Elementary FM-200220731 /02 3/17/03 Miner Boiler room Replace missing metal baffsl plate on the last pass before the breeching on # 2 boiler. Weeks of 11/4/02-11/8/02 FM-200220822 Asbestos Code A-clear for repair by Horne Engineer Sharon Voss on 11/13/02 DCPS Charles E Buchanan November 12, 2002 March 17, 2003 125 days
Cardozo High School FM-200103235 /01 3/18/03 CARDOZO BASEMENT BOILER ROOM REPLACE 2 (TWO) 2" BOILER WATER TUBES IN #2 BOILER THAT ARE LEAKING. CODE A-CLEAR FOR REPAIR BY HORNE ENG 8/15/01 (CEB) February 8, 2001 March 18, 2003 768 days
Spingarn High School FM-200221275 /02 3/18/03 Spingarn Boiler Room Working on heat related problerms at Spingarn Assisting one licensed engineer on site with running a high pressure plant November 19, 2002 March 18, 2003 119 days
Anacostia Senior High School FM-200102667 /1/01 3/18/03 ANACOSTIA BOILER ROOM REPLACEMENT OF BLDG. CIRCULATION HOT WATER PUMP. NAME MARATHON, MOD K#PV856T34D-1004AW, FR 560-10, PH 3, VOLT 208 230/460, DUTY - CONT., 4 DEGREE AMR, RPM 3450, HP 2, AMPS 7. February 1, 2001 March 18, 2003 775 days
Leckie Elementary School FM-200114571 01 3/18/03 LECKIE BOILER ROOM GROUND FL. 1. ASBESTOS ASSESSMENT REQUIRED. 2. REMOVE ONE (1) 2" PLUG FROM OUTSIDE FRONT TUBE SHEET AT BOTTOM FOR PROPER CLEANING OF WATER SIDE AND MUD LEGS. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: EDWARD RODRIGUEZ July 2, 2001 March 18, 2003 624 days
Eastern High School FM-200101986 01 3/18/03 EASTERN SUB-BASEMENT BOILER ROOM ACID CLEAN #1 & 2 BOILERS. January 24, 2001 March 18, 2003 783 days
Meyer Elementary School FM-200113468 01 3/18/03 MEYER BASEMENT BOILER ROOM 1.ASSESSMENT REQUIRED 2.REPAIR FIRE BOX REFACTORY IN BOILERS #1 AND #2. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER SHERYLL JAMES June 18, 2001 March 18, 2003 638 days
Browne Junior High School FM-200226638 03 3/18/03 Browne Boiler Room Survey and correct problem with (10 ) air condition system for main office. System have not work since power outage at Brown JHS on 8/18/02 March 6, 2003 March 18, 2003 12 days
Kimball Elementary School FM-200113494 01 3/18/03 KIMBALL BOILER ROOM (1) ASBESTOS ASSESSMENT IS REQUIRED (2) REMOVE CAP OFF OF BOILER #1 WATER LEG. Code A-clear for repair by Horne Engineer ( Troy Wilcme ) 0n 3/20/02 (CEB) June 18, 2001 March 18, 2003 638 days
Wilkinson ES FM-200225585 03 3/18/03 Wilkinson Boiler Room P.M Chiller February 11, 2003 March 18, 2003 35 days
Eastern High School FM-200101479 01 3/18/03 EASTERN BOILER ROOM (1) ASBESTOS ASSESSMENT IS NEEDED ON INSIDE OF COMBUSTION CHAMBER WALLS & FLOOR (2) BOILER # 2 - DCPS CONTRACTOR REPLACE BOILER TUBES (3) ASBESTOS CODE A - CLEAR FOR REPAIRS ON 03/06/01. January 17, 2001 March 18, 2003 790 days
Maury Elementary School FM-200108784 01 3/19/03 MAURY BOILER ROOM Refurbish condensate system. April 20, 2001 March 19, 2003 698 days
Adams Elementary FM-200103989 01 3/19/03 Adams Boiler Room Roll or replace leaking boiler tubes in boiler #2. February 21, 2001 March 19, 2003 756 days
Jefferson JHS FM-200227154 03 3/19/03 Jefferson Boiler Room Pump water out of the tunnel in boiler roo, March 17, 2003 March 19, 2003 2 days
Duke Ellington School FM-200111077 01 3/19/03 ELLINGTON BOILER ROOM 1. ASSESSMENT NEEDED ON #1 AND #2 BOILER HAND HOLD COVER PLATES, CUT AND REMOVE APPROX. 6" OF INSULATION FROM AROUND COVER PLATES. Requester Phone: 698-1750 POC: C BRADLY (202)438-7437 MR. RICE (202)345-1541 ASBESTOS CODE A-CLEAR FOR REPAIR 12/05/01 BY HORNE ENGINEER: BILL CAMPION May 17, 2001 March 19, 2003 671 days
Terrell Mc ES FM-200106258 3/21/01 3/19/03 M.C. TERRELL BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. INSPECT - REPAIR OR REPLACE WATER LEGS ON BOILER #2. THE FIRE BOX IS CONTINUOUSLY FILLING UP WITH WATER. ASBESTOS CODE A - CLEAR FOR REPAIRS ON MAR.23, 2001 ROGER KAGER - HORNE ENGINEER March 21, 2001 March 19, 2003 728 days
Duke Ellington School FM-200109588 01 3/19/03 ELLINGTON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR LEAKING SHELL ON #2 BOILER, WATER IS LEAKING INTO FIREBOX. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 05/15/01. May 4, 2001 March 19, 2003 684 days
Anacostia Senior High School FM-200225568 03 3/19/03 Anacostia Boiler Room P.M Chiller February 11, 2003 March 19, 2003 36 days
Payne Elementary School FM-200226036 03 3/19/03 Payne Boiler Room Replace blow down valves on Boiler #1 and #2. See Rutherford the engineer. February 23, 2003 March 19, 2003 24 days
Dunbar High School FM-200109045 01 3/19/03 (DUNBAR) ROOF/AIR HANDLER UNIT: B-5. BUSTED COOLING COIL LOCATED IN BOILER ROOM ON THE 6TH FLOOR. WATER FLOODING ALL FLOORS. ASBESTOS CODE - A CLEAR FOR REPAIRS ON 04/24/01. April 24, 2001 March 19, 2003 694 days
Coolidge High School FM-200104061 01 3/19/03 COOLIDGE GROUND FL. GREENHOUSE BLDG. SURVEY SERVICE/REPAIR GREENHOUSE BOILER & PIPE SYSTEM. BOILER HAS BEEN IDLE FOR A PROLONGED PERIOD. February 21, 2001 March 19, 2003 756 days
Terrell Mc ES FM-200106233 3/21/01 3/19/03 M.C. TERRELL BOILER ROOM REPLACE MUDLEG IN BOILER #1 & BOILER#2. ASBESTOS CODE A-CLEAR FOR REPAIR ON 9/14/01 ROGER KAGER OF HORNE ENGINEER March 21, 2001 March 19, 2003 728 days
Randle-Highlands ES FM-200227155 03 3/19/03 Randle-Highlands E.S Boiler Room Pump water out of the tunnel in boiler room. March 17, 2003 March 19, 2003 2 days
Ronald H. Brown MS FM-200202649 02 3/19/03 (BROWN,RON) 1ST LEVEL PARKING LOT THERE IS A POT-HOLE ON THE PARKING LOT OUTSIDE THE BOILER BLOW DOWN & NEEDS TO BE REPAIRED. February 8, 2002 March 19, 2003 404 days
Anacostia Senior High School FM-200109939 01 3/19/03 ANACOSTA BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. NEED 8" TEE AND 8" VALVE ON HOT WATER LINE. HOT WATER DETERIORATING COLD WATER STRAINER. ASBESTOS CODE A -CLEAR FOR REPAIRS ON 05/25/01. May 10, 2001 March 19, 2003 678 days
Reed LC FM-200220570 02 3/19/03 Reed, Marie Asbestos assessment required. First floor hallway Repair leaking convertor .Convector is lecking down into the boiler room Asbestos Code A - Clear for repairs on 03/06/03. Horne Engineering - Tony Marcolin (RG 03/07/03) November 1, 2002 March 19, 2003 138 days
Janney Elementary School FM-200124132 /01 3/20/03 JANNEY BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Roosevelt High School FM-200124160 /01 3/20/03 ROOSEVELT BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Leckie Elementary School FM-200124140 /01 3/20/03 LECKIE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Terrell Mc ES FM-200124143 /01 3/20/03 TERRELL,M.C. BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Stanton Elementary School FM-200124169 /01 3/20/03 STANTON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
River Terrace ES FM-200124175 /01 3/20/03 RIVER TERRACE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Bruce-Monroe Elementary School FM-200124149 /01 3/20/03 BRUCE MONROE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Woodson High School FM-200124190 /01 3/20/03 WOODSON,H.D. BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Beers Elementary School FM-200124102 /01 3/20/03 BEERS BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Sousa Middle School FM-200124168 /01 3/20/03 SOUSA BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Ballou Senior High School FM-200124098 /01 3/20/03 BALLOU BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Clark Elementary School FM-200124109 /01 3/20/03 CLARK BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Gage-Eckington ES FM-200124117 /01 3/20/03 ECKINGTON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Raymond Elementary School FM-200124159 /01 3/20/03 RAYMOND BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Reed LC FM-200124144 /01 3/20/03 MARIR REED BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Cook J.F. Elementary School FM-200124110 /01 3/20/03 COOK, J.F. BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
West Elementary School FM-200124185 /01 3/20/03 WEST BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Hearst Elementary School FM-200124126 /01 3/20/03 HEARST BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Johnson JHS FM-200124134 /01 3/20/03 JOHNSON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Cardozo High School FM-200124108 /01 3/20/03 CARDOZO BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Bell High School FM-200124103 /01 3/20/03 BELL BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Smothers ES FM-200124167 /01 3/20/03 SMOTHERS BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Langdon Elementary School FM-200215180 02 3/20/03 Repair domestic hot water boiler in the boiler room , must reset boiler constantly for proper operations. (lochinvar hot water boiler) August 21, 2002 March 20, 2003 211 days
Langdon Elementary School FM-200124139 /01 3/20/03 LANGDON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Garfield ES FM-200124121 /01 3/20/03 GARFIELD BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Stuart-Hobson Middle School FM-200124171 /01 3/20/03 STUART HOBSON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Lafayette Elementary School FM-200124138 /01 3/20/03 LAFAYETTE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
King M L ES FM-200124136 /01 3/20/03 KING, ML BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Truesdell Elementary FM-200124178 /01 3/20/03 TRUESDELL BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Payne Elementary School FM-200124155 /01 3/20/03 PAYNE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Thomas Elementary School FM-200124177 /01 3/20/03 THOMAS BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Ross Elementary School FM-200124161 /01 3/20/03 ROSS BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Wilson High School FM-200105732 01 3/20/03 WILSON, W. 1ST FLOOR BETWEEN AUDITORIUM & BOILER ROOM REPAIR OR REPLACE SLATE PAVED AREA WHICH IS CAUSING WATER DAMAGE TO WALL IN AUDITORIUM STAIRWAY AND DAMAGE TO WALLS ON GROUND FLOOR LEVEL IN BOILER ROOM. March 14, 2001 March 20, 2003 736 days
Tubman Elementary School FM-200124179 /01 3/20/03 TUBMAN BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Bancroft Elementary School FM-200124099 /01 3/20/03 BANCROFT BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Coolidge High School FM-200124111 /01 3/20/03 COOLIDGE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Young Elementary School FM-200124191 /01 3/20/03 YOUNG BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
West Elementary School FM-200107405 01 3/20/03 WEST BASEMENT BOILER ROOM 1. ASSESSMENT REQUIRED FOR WORK PERMIT. 2. REPAIR OR REPLACE CONDENSOR CIRCULATOR PUMP AND MOTOR. MOTOR AND PUMP ARE DISASSEMBLED. PUMP: BELL & GOSSETT MOD: V5C9-1/2 B2HR PUMP # 6X6X12 - INDENT # 751494MT. MOTOR NAME UNICLOSED HP - 20, PH 3, FRAME 256T, VOLTS 230/1460, AMPS 54/27. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/18/01. April 5, 2001 March 20, 2003 714 days
Montgomery ES FM-200124150 /01 3/20/03 MONTGOMERY BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Duke Ellington School FM-200124118 /01 3/20/03 ELLINGTON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Lincoln Middle School FM-200124142 /01 3/20/03 LINCOLN BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Benjamin Banneker Academic HS FM-200124100 /01 3/20/03 BANNEKER BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Anacostia Senior High School FM-200124097 /01 3/20/03 ANACOSTIA BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Kimball Elementary School FM-200124135 /01 3/20/03 KIMBALL BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Hendley Elementary School FM-200124127 /01 3/20/03 HENDLEY BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Ludlow-Taylor ES FM-200124174 /01 3/20/03 LUDLOW TAYLOR BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Adams Elementary FM-200124096 /01 3/20/03 ADAMS BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Kimball Elementary School FM-200227195 03 3/20/03 Kimball Boiler Room Old boiler room flooded,pump water out to parking lot draing half way finish March 18, 2003 March 20, 2003 2 days
Whittier Elementary School FM-200124187 /01 3/20/03 WHITTIER BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Nalle Elementary School FM-200124152 /01 3/20/03 NALLE,J.C. BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Wilkinson ES FM-200124188 /01 3/20/03 WILKINSON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Burrville Elementary School FM-200124107 /01 3/20/03 BURRVILLE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Garrison ES FM-200124122 /01 3/20/03 GARRISON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Patricia R Harris Ed Center FM-200124124 /01 3/20/03 HARRIS, P.R. BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Webb Elementary School FM-200124184 /01 3/20/03 WEBB BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Gibbs Elementary School FM-200124123 /01 3/20/03 GIBBS BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Hine JHS FM-200124129 /01 3/20/03 HINE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Orr Elementary School FM-200124153 /01 3/20/03 ORR BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Takoma Educational Center FM-200124173 /01 3/20/03 TAKOMA BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Jefferson JHS FM-200124133 /01 3/20/03 JEFFERSON BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Kramer Middle School FM-200124137 /01 3/20/03 KRAMER BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Deal Junior High School FM-200124112 /01 3/20/03 DEAL BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Eastern High School FM-200124116 /01 3/20/03 EASTERN BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Dunbar High School FM-200124115 /01 3/20/03 DUNBAR BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Bowen Elementary School FM-200124105 /01 3/20/03 BOWEN BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Walker-Jones EC FM-200124181 /01 3/20/03 WALKER JONES BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Marshall Educational Center FM-200124145 /01 3/20/03 MARSHALL BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Shaw JHS FM-200124164 /01 3/20/03 SHAW BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Hyde Elementary School FM-200124131 /01 3/20/03 HYDE BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Maury Elementary School FM-200124146 /01 3/20/03 MAURY BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Wilson High School FM-200124189 /01 3/20/03 WILSON,W BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Brent Elementary School FM-200124106 /01 3/20/03 BRENT BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Birney Elementary School FM-200124104 /01 3/20/03 BIRNEY BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Shaw JHS FM-200227338 03 3/20/03 Shaw Boiler Room Repair or replace sump pump motor and ball float. Make Westinghouse; serial # 31P162A, SERFM 73; Type F5; INSA; HP-1/2; Fr-B566; SF-1.25; AMB 40 degrees C; V-240/460; AMP-2.8; HZ-60. March 20, 2003 March 20, 2003 0 days
Turner Elementary School FM-200124180 /01 3/20/03 TURNER BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Draper Elementary School FM-200124114 /01 3/20/03 DRAPER BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Shepherd ES FM-200124165 /01 3/20/03 SHEPHERD BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Eastern High School FM-200219476 /02 3/20/03 Eastern Sub-basement - Boiler room Water proof and resurface driveways outside boiler room, rain is damaging wall and running on electrical conduits and electrical control panels. Fire code voilation October 16, 2002 March 20, 2003 155 days
Watkins Elementary School FM-200124183 /01 3/20/03 WATKINS BOILER MAINTENANCE 1) BOILER WATER TREATMENT SERVICES TRICON OF WASHINGTON INC. POC: THOMAS PICKETT - 698-1750 November 30, 2001 March 20, 2003 475 days
Kimball Elementary School FM-200227278 03 3/21/03 Kimball E.S Boiler Room Pumping water out of old boiler room Work is completed March 19, 2003 March 21, 2003 2 days
Kimball Elementary School FM-200227355 03 3/22/03 Kimball Old Boiler Room First Floor Wired up pump for pit to remove water. Also help install surmerible pump March 20, 2003 March 22, 2003 2 days
Meyer Elementary School FM-200113467 01 3/24/03 MEYER BASEMENT BOILER ROOM (1) ASBESTOS ASSESSMENT IS NEEDED REPAI AND REPLACE TEMPERATURE AND PRESSURE RELIEF VALVE, WATTS -SET POINT 150 PSI 210 F. TEMPERATURE RATINGS 210 F, 1,000, 000 BTUS. RELIEF VALVE LOOSING WATER, WILL NOT RE-SEAT AND WATER LEAKING OUT OF BLOW DOWN PIPE. APPROX. 3/4 INCH PIPE CONNECTION ON HOT WATER STORAGE TANK. CODE A - ASBESTOS ABATED ON 8/21/01 (SG) PER LEROY MINTONS CONFIRAMTION. June 18, 2001 March 24, 2003 644 days
Dunbar High School FM-200225579 03 3/24/03 Dunbar Boiler Room P.M Chiller February 11, 2003 March 24, 2003 41 days
Stanton Elementary School FM-200227559 03 3/24/03 Stanton E.S Boiler Room Ground Survey pit pumps. Electric control switch needs replacing or bad fuse. Inform Joe of the problem March 24, 2003 March 24, 2003 0 days
Anacostia Senior High School FM-200114610 01 3/24/03 ANACOSTIA BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE 3/4" CHECK VALVE FOR CITY MAKE UP WATER LINE (BOILER #1). ASBESTOS CODE A - CLEAR FOR REPAIRS ON 07/19/01. July 2, 2001 March 24, 2003 630 days
Payne Elementary School FM-200226992 03 3/24/03 Payne Boiler Room Replace lock on Boiler room from hall door. March 13, 2003 March 24, 2003 11 days
Nalle Elementary School FM-200114618 01 3/24/03 NALLE BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. SURVEY LEAK IN BOILER ROOM TUNNEL, LEAK SEEMS TO BE COMING FROM AREA ABOVE TUNNEL. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER: RAY AGNANT July 2, 2001 March 24, 2003 630 days
Leckie Elementary School FM-200126457 /01 3/25/03 LECKIE BOILER ROOM SURVEY AND MAKE REPAIRS TO AIR COMPRESSOR MOTOR. NUMBER 2 MOTOR CONTINUOUSLY TRIPPING OUT ON OVERLOAD. MOTOR: GE 3-PHASE, HP-3, VOLTS-208, AMPS-10.2 RPM -1755, FRAME 182T, MODEL NO. 5K182AL213A December 31, 2001 March 25, 2003 449 days
Bruce-Monroe Elementary School FM-200120838 01 3/25/03 BRUCE-MONROE BOILER/MECH. ROOM REPLACE RELIEF VALVE ON BOILER #2. WATER IS COMING FROM VALVE ON #2 BOILER. RE: LOST OF HEAT/WATER. SERIAL-00250 MODEL-M NO. 740 SZ. 2" (2X2 1/2 ) SET 30 LBS BTU 5,250,000 October 2, 2001 March 25, 2003 539 days
Bruce-Monroe Elementary School FM-200104372 01 3/25/03 Bruce Monroe Boiler Room Install chemical treatment to HVAC water system, chemicals are needed to protect system metal. February 27, 2001 March 25, 2003 756 days
Bruce-Monroe Elementary School FM-200104368 01 3/25/03 Bruce Monroe Boiler Room Install ventilation louvers for rear door at airway for boiler combustion. Existing metal is badly damaged and there are no windows in boiler room. February 27, 2001 March 25, 2003 756 days
Terrell Mc ES FM-200122420 /01 3/25/03 M.C. TERRELL BOILER ROOM BOILER#2 REPAIR/REPLACE FIRE DOORS ON BOILER. SPENCER THREE PASS FULL WET BOILER, MODEL# 4F563WSPL, SERIAL#8963, GROSSOUT 91 HP, MPH 3063, MPH IN PUT 4083, SQ. FT. FIRESIDE SURFACE 563, MAWP 30LBS, LS HR STEAM 4540 MBH WATER, ASME# FIRE BOX CAN BE PRESSURE TESTED. THIS IS REQUIRED DUE TO NEW BURNER INSTALLATION. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-14-01 HORNE ENGINEER: TROY WILCOME October 26, 2001 March 25, 2003 515 days
Terrell Mc ES FM-200124897 01 3/25/03 MC TERRELL BOILER ROOM REPAIR LEAKS IN # 2 BOILER MUD LEAKS ARE LEAKING December 7, 2001 March 25, 2003 473 days
Terrell Mc ES FM-200126683 02 3/25/03 M.C. TERRELL BOILER ROOM REPLACE CONTROL BOX ON PUMP #6. CONTROL BOX HAD A SHORT IN IT (ELECTRICAL SHORT). IT CIRCULATES IN OFFICE AND KINDERGARTEN. January 4, 2002 March 25, 2003 445 days
Bunker Hill Elementary School FM-200100882 1/11/01 3/25/03 BUNKER HILL BOILER ROOM REPLACE BURNED OUT MOTOR ON #1 & 2 CONDENSATION STORAGE TANK (CONDENSATE PUMPS). BALDOR RPM 1725, HP . 5, VOLTS 208-230/460, AMPS 2.1 2.0. HC-20000346 January 11, 2001 March 25, 2003 803 days
Bunker Hill Elementary School FM-200104637 01 3/25/03 Bunker Hill Boiler Room Survey and make necessary repairs or replacement to vacuum pump motor. Motor is not working. March 1, 2001 March 25, 2003 754 days
King M L ES FM-200122142 /01 3/25/03 KING,M.L. BOILER ROOM REPAIR I.D.FAN ON BOILER#2 October 23, 2001 March 25, 2003 518 days
Bunker Hill Elementary School FM-200122736 /01 3/25/03 BUNKER HILL BOILER ROOM REPLACE HEATER COIL FOR HOT WATER CIRCULATING PUMP #1. October 31, 2001 March 25, 2003 510 days
Bunker Hill Elementary School FM-200122737 /01 3/25/03 BUNKER HILL BOILER ROOM REPLACE BURNED OUT MOTORS #1 & 2 CONDENSATE TANK. BALDOOR, F S6, FRAMER 56J, SERIAL W6-90, HP 5, VOLTS 208-230, RPM 1725, HZ 6.0). MOTORS REMOVED BY PEARSON & BARKSDALE. October 31, 2001 March 25, 2003 510 days
Kramer Middle School FM-200100789 01 3/25/03 KRAMER BOILER ROOM SURVEY AND MAKE NECESSARY REPAIRS TO BOILER #1. BOILER WILL NOT LIGHT OFF. HC-20001062 January 10, 2001 March 25, 2003 804 days
Kramer Middle School FM-200122493 /01 3/25/03 KRAMER ANNEX BOILER ROOM REPLACEMENT OF FOUR (4) BOILER FEEDWATER PUMPS. MARATHON MODEL #DM-0-101, PH 3 TYPE, VOLT 208 230/460, DUTY CONT.L, RPM 1735, HP-2. WP-200107422 October 26, 2001 March 25, 2003 515 days
Kramer Middle School FM-200123746 /01 3/25/03 KRAMER BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPAIR LEAKING COLD WATER LINE IN MOTOR ROOM. 1 INCH LINE IS LEAKING. WATER IS LEAKING ON BOLIER ROOM FLOOR CODE A CLEAR FOR REPAIR BY HORNE ENG. TROY WILCOME 11-23-01. DCPS SAFETY S.R. HOWARD 11-23-01. November 23, 2001 March 25, 2003 487 days
Takoma Educational Center FM-200104387 01 3/25/03 Takoma Boiler Room Install chemical treatment tank for closed loop heating/cooling system. Chemical treatment is needed to protect system metals. February 27, 2001 March 25, 2003 756 days
Burrville Elementary School FM-200123736 /01 3/25/03 BURRVILLE BOILER ROOM REPLACE PUMP COUPLING ON CONDENSATE RETURN PUMP #1 November 23, 2001 March 25, 2003 487 days
Browne Junior High School FM-200124990 /01 3/25/03 BROWNE BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE 2" RETURN LINE IN BOILER ROOM. RETURN LINE IS LEAKING. ASBESTOS CODE A-CLEAR FOR REPAIR ON 12/12/01 BY HORNE ENGINEER: STEPHEN CALDWELL December 12, 2001 March 25, 2003 468 days
Montgomery ES FM-200123566 /01 3/25/03 MONTGOMERY,S BOILER ROOM REPAIR #1 AND #2 BURNERS CUT OFF IN FLAME FAILURE NO HEAT. November 19, 2001 March 25, 2003 491 days
Thomas Elementary School FM-200117121 01 3/25/03 THOMAS BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPAIR PVC CONDESOR WATER SUPPLY LINE TO CHEMICAL TREATMENT TANK FOR COOLING TOWER AND MULTI-STACK CHILLER. LINE HAS BECOME DISLODGED FROM ELBOW ON LINE BEFORE ENTERING TANK, TRICONS EQUIPMENT. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER RAY AGNANT August 10, 2001 March 25, 2003 592 days
Young Elementary School FM-200121365 /01 3/25/03 YOUNG BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.ASSESS AND REPAIR ELECTRIC VALVES. VALVES NOT OPENING. CAUSING BOILERS TO CUT OFF ON STAND BY. October 11, 2001 March 25, 2003 530 days
Lafayette Elementary School FM-200104400 01 3/25/03 Lafayette Boiler Room Install chemical system to system water for heating/cooling. Chemical system is needed to protect metals on heating/cooling equipment. February 27, 2001 March 25, 2003 756 days
Key Elementary School FM-200121599 /01 3/25/03 KEY BOILER ROOM CHECK BURNERS ON BOILER #1 AND #2. BURNERS MUST BE CALIBRATED October 15, 2001 March 25, 2003 526 days
Key Elementary School FM-200120642 01 3/25/03 KEY BASEMENT BOILER ROOM REPAIR OR REPLACE SUMP PUMP. APPEARS TO BE A PROBLEM WITH FLOW ROD. WP-200108647 September 27, 2001 March 25, 2003 544 days
Thomas Elementary School FM-200121401 /01 3/25/03 N. THOMAS BOILER ROOM ADJUST FUEL AND AIR SUPPLY ON BOILER #2. BURNER NOT FIRING OFF PROPERLY October 11, 2001 March 25, 2003 530 days
Thomas Elementary School FM-200125704 /01 3/25/03 THOMAS BOILER ROOM 1.REPAIR BOILER#2 PUMP,ADJUST PUMP CONTROL TO CONDENSATE RETURN PUMP, PUMP CONTINUING TO RUN. December 19, 2001 March 25, 2003 461 days
Thomas Elementary School FM-200126447 /01 3/25/03 N. THOMAS BOILER ROOM REPLACE DEFECTIVE AUTOMATIC WATER FEEDER ON BOILER NUMBER ONE FLOAT APPEARS TO BE STICKING AND NOT RELEASING ALLOWING ADEQUATE WATER FLOW- MAKE MCDONNELL-MILLER- S-51 December 31, 2001 March 25, 2003 449 days
Key Elementary School FM-200104177 01 3/25/03 KEY BOILER ROOM CHECK ALL BOILER ROOM EQUIPMENT GAS COMPANY RED TAGGED ATMOSPHERIC BOILER. February 22, 2001 March 25, 2003 761 days
Thomson Elementary School FM-200123301 /01 3/25/03 THOMSON BOILER ROOM REPAIR OR REPLACE POLIT 0N GAS SUPPLY LINE 1/4" ON BOILER #2 BOILER GAS TRANE, LINE IS BROKEN WP#200108658 November 14, 2001 March 25, 2003 496 days
Lincoln Middle School FM-200105895 01 3/25/03 LINCOLN BOILER ROOM R/R HOT WATER CIRCULATING PUMPS #1 & 2 ON HEATING SIDE. BEARING APPEARS TO BE GOING BAD ON MECHANICAL END. MAKE OF PUMPS IS FEDERAL. March 15, 2001 March 25, 2003 740 days
Sousa Middle School FM-200123830 /01 3/25/03 SOUSA BOILER ROOM REPLACE BOILER FEED WATER FLOAT ON VACUUM TANK. MOTORS WILL NOT COME ON BOILER #1,#2 AND #3. November 27, 2001 March 25, 2003 483 days
Truesdell Elementary FM-200105083 01 3/25/03 TRUESDELL BOILER ROOM REPLACE SOLENOID VALVE ON CITY WATER SUPPLY LINE LEADING TO CONDENSATION TANK LOCATED ON A 1/4" LINE. SER. #A669468 VALVE STAYS OPEN ALL THE TIME FILLING UP AND OVER FLOWING TANK. March 7, 2001 March 25, 2003 748 days
Lincoln Middle School FM-200119631 01 3/25/03 LINCOLN BOILER ROOM FURNISH 1 EA. SUBMERSIBLE SUMP PUMP FOR BOILER ROOM. September 11, 2001 March 25, 2003 560 days
Sousa Middle School FM-200103880 01 3/25/03 Sousa Boiler Room Replace city water float switch on condensate tank. February 20, 2001 March 25, 2003 763 days
Cook J.F. Elementary School FM-200117552 01 3/25/03 J.F. COOK BOILER ROOM REPAIR SUMP PUMP DAMAGED BY FLOOD. WP-200108641 August 15, 2001 March 25, 2003 587 days
Brookland Elementary FM-200225581 03 3/25/03 Brookland Boiler Room P.M Chiller February 11, 2003 March 25, 2003 42 days
Johnson JHS FM-200124419 01 3/25/03 JOHNSON BOILER ROOM OVERHAUL CHILLER, RECOMMEND 10 YEARS. December 4, 2001 March 25, 2003 476 days
Brookland Elementary FM-200124424 01 3/25/03 BROOKLAND BOILER ROOM P.M. MULTISTACK CHILLER. December 4, 2001 March 25, 2003 476 days
Anacostia Senior High School FM-200107427 /5/01 3/25/03 ANACOSTIA BOILER ROOM 1. ASSESSMENT REQUIRED FOR WORK PERMIT. 2. .REPLACEMENT OF BOILER FEEDWATER PUMP, NAME MARATHON MOD. #PV856T34D-1004AW, FR560-10, PH 3, VOLT 208 230/460, DUTY-CONT., 4 DEGREES AMR, RPM 3450, HP 2, AMPS 7. CODE A -CLEAR FOR REPAIR AS OF 4/17/01 April 5, 2001 March 25, 2003 719 days
Lincoln Middle School FM-200120229 01 3/25/03 LINCOLN BOILER ROOM R/R INOPERABLE PUMPS #1 / #2 IN SUMP WELL. NO NOMENCLATURE ON PUMPS. URGENT WP-200108873 September 20, 2001 March 25, 2003 551 days
Coolidge High School FM-200120670 01 3/25/03 COOLIDGE TUNNEL AREA BY BOILER ROOM REPLACE LEAKING 2 1/2 INCH RETURN LINE LOCATION IN TUNNEL AREA BY BOILER ROOM. ABOUT 20 FEET NEEDS TO BE REMOVED AND REPLACED September 28, 2001 March 25, 2003 543 days
Coolidge High School FM-200121267 /01 3/25/03 COOLIDGE BOILER ROOM ASSESS AND REPAIR TUBES LEAKING IN BOILER #2 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 10/24/01. HORNE ENGINEERING - BIPIN NANAVATY (RG) October 10, 2001 March 25, 2003 531 days
Coolidge High School FM-200124655 01 3/25/03 COOLIDGE BOILER ROOM REPAIR BOILER #3. BOILER WILL NOT START. December 7, 2001 March 25, 2003 473 days
Lincoln Middle School FM-200120500 01 3/25/03 LINCOLN BOILER ROOM INSTALL (7) CHAIRS AND BRACKET TO (7) OS&Y VALVES. VALVES ARE APPROXIMATELY 24 INCH FROM FLOOR TO VALVES. MAKE IT EASIER TO OPEN/CLOSE VALVES. September 25, 2001 March 25, 2003 546 days
Anacostia Senior High School FM-200112254 01 3/25/03 ANACOSTIA BOILER ROOM REPLACE SOLENOID VALVE ON CONDENSATE TANK. VALVE NOT HOLDING. GOULD VALVE (AW) 14 WATTS. SIZE 11/4 MAX. PSI 125, VOLTS 120, CYCLES 60, TYPE "M", SERIAL # 513148. WP-200108897 June 4, 2001 March 25, 2003 659 days
Anacostia Senior High School FM-200124421 01 3/25/03 ANACOSTIA BOILER ROOM PERFORM P.M. ON MULTISTACK CHILLER 2 EA. December 4, 2001 March 25, 2003 476 days
Draper Elementary School FM-200117460 01 3/25/03 DRAPER BASEMENT BOILER ROOM 1. ASBESTOS ASSESSMENT IS REQUIRED ON BOILER #1 FOR THE REMOVAL OF THE BURNER ASSEMBLY. 2. REMOVE BURNER ASSEMBLY FOR TUBE REPLACEMENT. Code A-clear for repair by Horne Engineer ( Stephen Caldwell ) 0n 3/22/02 (CEB August 14, 2001 March 25, 2003 588 days
Shaw JHS FM-200227580 03 3/25/03 Shaw Boiler Room Repair lochinvar hot water heater. Will not start. Make: Lochinvar Model: CWN0985PM Ser.: M003835 Control #: F-9 March 25, 2003 March 25, 2003 0 days
Brent Elementary School FM-200123824 /01 3/25/03 BRENT BOILER ROOM REPLACE FEEDWATER REGULATOR ON #1 BOILER. November 27, 2001 March 25, 2003 483 days
Brent Elementary School FM-200122417 /01 3/25/03 BRENT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 1. REPAIR/REPLACE PNEUMATIC VALVE ON SUPPLY LINE - LEAKING. ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/30/01 HORNE ENGINEER: BILL CAMPION October 25, 2001 March 25, 2003 516 days
Brent Elementary School FM-200120306 01 3/25/03 BRENT BOILER ROOM FABRICATE METAL MOUNTING PLATE FOR HEATING/CHILL WATER PUMP. ASBESTOS ASSESSMENT REQUIRED. ASBEATOS CODE A - CLEAR FOR REPAIRS ON 9/24/01. STEPHEN CALDWELL - HORNE ENGINEERS (RG) September 21, 2001 March 25, 2003 550 days
Tyler Elementary School FM-200119170 01 3/25/03 TYLER BOILER ROOM SURVEY AND RESTORE ELECTRICAL POWER TO SUMP PUMP NEAR HOT WATER STORAGE TANK. WP-200108810 September 5, 2001 March 25, 2003 566 days
Marshall Educational Center FM-200103771 01 3/25/03 MARSHALL GROUND FL. BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE 3 WAY PNEUMATIC VALVE LOCATED ON MAIN HEADER FOR HEATING SYSTEM. POC: CURTIS EMERSON CELL#438-7434 ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/20/01. ROGER KAGER - HORNE ENGINEERING February 16, 2001 March 25, 2003 767 days
Dunbar High School FM-200122723 /01 3/25/03 DUNBAR BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. PLEASE REPLACE ONE RELIEF VALVE THAT IS LEAKING ON #2 BOILER. SERIAL #98260, MODEL M #740, SIZE 2" X 2-1/2", SET 30 LB. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/09/01 HORNE ENGINEER : BIPIN NANAVATY October 31, 2001 March 25, 2003 510 days
Maury Elementary School FM-200104049 01 3/25/03 Maury Boiler Room Replace existing defective condensate tank and return pumps. February 21, 2001 March 25, 2003 762 days
Shaw JHS FM-200103601 01 3/25/03 SHAW KITCHEN R/R CONDENSATE RETURN PUMPS TO BOILER #4. February 13, 2001 March 25, 2003 770 days
Shaw JHS FM-200103570 01 3/25/03 SHAW BOILER ROOM REPLACE LEAKING GAS VALVE ON TRAIN TO #2 BOILER. DAMAGED BY CONTRACTOR. February 13, 2001 March 25, 2003 770 days
Watkins Elementary School FM-200227296 03 3/25/03 Watkins Boiler room Repair gas leak on the # 1 boiler gas train. March 19, 2003 March 25, 2003 6 days
Houston Elementary School FM-200105224 /01 3/25/03 HOUSTON BOILER ROOM REPLACE 2 EA. SETS OF SUMP PUMPS. TEMPORARY PUMPS ARE IN PLACE. EXISTING PUMPS ARE BEYOND REPAIR. March 7, 2001 March 25, 2003 748 days
Meyer Elementary School FM-200122757 01 3/25/03 MEYER BOILER ROOM REPAIR OR REPLACE BOILER #2 GOING INTO ALARM WHEN BOILER IS NOT WORKING. WP-200108652 November 1, 2001 March 25, 2003 509 days
Hine JHS FM-200125707 /01 3/25/03 HINE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2.REPAIR OR REPLACE 2" BLOW DOWN VALVE AND PIPE ON PUMP HEADER. LEAKING AND CORRODED. HEATING SYSTEM PUMPS. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/19/01. HORNE ENGINEERING - SHERYLL JAMES (RG) December 19, 2001 March 25, 2003 461 days
Benning Elementary School FM-200122136 /01 3/25/03 BENNING BOILER ROOM REPAIR EMERGENCY CUTOFF SWITCH FOR BOILERS, SWITCH CUTS OFF BOILERS BUD DOES NOT RESET CONTROL SWITCH. ASCO - 920 REMOTE CONTROL SWITCH. October 22, 2001 March 25, 2003 519 days
Eliot Junior High School FM-200126478 02 3/25/03 ELIOT BOILER ROOM REPAIR CONDENSATE---VACUUM PUMPS WILL NOT SHUT OFF IN AUTOMATIC January 2, 2002 March 25, 2003 447 days
Duke Ellington School FM-200106372 01 3/25/03 ELLINGTON BOILER ROOM REPLACE QUINCY AIR COMPRESSOR (NO LONGER OPERATING). MOD. 0C0070603, SER. 5038038 March 22, 2001 March 25, 2003 733 days
Duke Ellington School FM-200118284 01 3/25/03 ELLINGTON BOILER ROOM REPAIR AUTOMATIC WATER FEEDER ON #1 BOILER. BUILDING ONLY HAS ONE BOILER MODEL # 51S-2, 35 PSI. WP-200108907 August 23, 2001 March 25, 2003 579 days
Duke Ellington School FM-200120960 01 3/25/03 ELLINGTON BOILER ROOM REPAIR OR REPLACE FEED WATER PUMP #1. MOTOR:G.E MODEL: 5K47KG748A HP:1.5 VOLT: 208/230 PH:3 RPM: 3450 FR: 56J WP-200108907 HOT October 3, 2001 March 25, 2003 538 days
West Elementary School FM-200104588 01 3/25/03 WEST BOILER ROOM REPLACE PACKING GLAND AND STUDS ON HOT WATER CIRCULATOR PUMPS #1, 2 AND 3. NAME - TACO, MOD - SB40108:526PZF27LO, GPM - 226, HP 2-1/2, RPM - 1750, FRAME - C6. PUMPS ARE LEAKING AND STUDS ARE BROKEN. March 1, 2001 March 25, 2003 754 days
West Elementary School FM-200107407 01 3/25/03 WEST BASEMENT BOILER ROOM 1. ASSESSMENT REQUIRED FOR WORK PERMIT. 2. R/R MOTOR TO #1 HOT WATER HEATING CIRCULATOR PUMP. MOTOR RUNS OVER HEAT AND CUT OFF. NAME - DOERR, PH3, VOLT 460, AMPS 11.0/22.0, HP 7.5, RPM 1740. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 04/18/01. April 5, 2001 March 25, 2003 719 days
Emery Elementary School FM-200122418 /01 3/25/03 EMERY BOILER ROOM CONNECT GAS TRAINS TO BURNERS ON BOILERS #1 & #2. AFTER GAS TRAINS HAVE BEEN CONNECTED, CALIBRATE BURNERS. BURNER PROBABLY WILL BE MORE EFFICENT AND BURN CLEANER IF CONNECTION WAS MADE. October 25, 2001 March 25, 2003 516 days
Bell High School FM-200125614 /01 3/25/03 BELL BOILER ROOM DISCONNECT ALL PNEUMATIC LINE ON EXISTING HOUSE AIR COMPRESSOR AND CONNECT THEM TO SHOP AIR COMPRESSOR. NOT: HOUSE AIR COMRESSOR IS NOT WORKING. December 18, 2001 March 25, 2003 462 days
Woodson High School FM-200218531 02 3/25/03 Replace the refractory on the doors of # 1 and # 2 boilers as per A. Colvin , Boiler Inspector. (1) Asbestos assessment required on door insulation. Asbestos Code A-clear for repair by Horne Engineer Sheryll James on 10/09/02 DCPS Charles E. Buchanan September 30, 2002 March 25, 2003 176 days
Backus Middle School FM-200227611 03 3/25/03 Backus Boiler room (URGENT) Unstop floor drain in the boiler room area,this needed in order to drain the boilers for repairs March 25, 2003 March 25, 2003 0 days
Moten Elementary School FM-200123018 01 3/25/03 MOTEN BOILER ROOM PUMP#2 - REPAIR HOT WATER HEATING CIRCULAING PUMP MECHANICAL SEAL IS BUSTED (BUILDING HAS NO HEAT) PUMP#1 IS DOWN DUE TO WIRING PROBLEM November 7, 2001 March 25, 2003 503 days
Bruce-Monroe Elementary School FM-200125580 /01 3/25/03 BRUCE MONROE BOILER ROOM 1. NO ASBESTOS REMOVAL REQUIRED. 2. REPLACE LEAKING TUBES IN BOILER #1. 7 TUBES LEAKING. TUBES HAVE BEEN IDENTIFIED AND MARKED. December 18, 2001 March 25, 2003 462 days
Bruce-Monroe Elementary School FM-200122115 /01 3/25/03 BRUCE-MONROE BOILER ROOM REPLACE SIX (6) FAULTY GAT VALVES ON CITY WATER LINE TO BOILERS. SIZE 3/4". BOILER CONSTANTLY FILLING WITH WATER AND CAUSING A LOSS OF HEAT AND ENERGY. WP-2008640 CODE A - ASBESTOS ABATED ON 01/29/02 PER RONALD EDWARDS CONFIRMATION.(RG 02/05/02) October 22, 2001 March 25, 2003 519 days
Roosevelt High School FM-200123365 /01 3/25/03 ROOSEVELT BOILER ROOM REPLACE CRACKED MCDONNELL 193-7B SERIES ELECTRIC PROPORTIONING CONTROL ON BOILERS #1 & #2. November 15, 2001 March 25, 2003 495 days
Roosevelt High School FM-200120669 01 3/25/03 ROOSEVELT BOILER ROOM INSTALL THREE (3) 2" SCHEDULE 80 CHECK VALVES FOR BOILER #1,#2 AND #3 BOTTOM BLOW DOWN LINES. ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER TROY WILCOME September 28, 2001 March 25, 2003 543 days
River Terrace ES FM-200104809 3/2/01 3/25/03 RIVER TERRACE BOILER ROOM REPAIR CONDENSATE PUMP #2 NOT WORKING DUE TO ELECTRIC PROBLEM IN CONTROL BOX. March 2, 2001 March 25, 2003 753 days
Hart Middle School FM-200123724 /01 3/25/03 HART BOILER ROOM INSTALL AN EMERGENCY BURNER SWITCH AT EACH E/BOILER ROOM EXIT. November 21, 2001 March 25, 2003 489 days
Woodson High School FM-200122772 01 3/25/03 H.D. WOODSON HEATING PLANT SUB-BASEMENT 1. ASBESTOS ASSESSMENT REQUIRED. 2. EXTEND THE BLOW DOWN LINES OF #1 AND #2 BOILERS FROM FLOOR DRAINS TO SUMP PUMP PIT. FLOOR DRAINS CANNOT HANDLE WATER WHEN BLOWING DOWN OR DRAING DOWN FOR SUMMER CLEANING CAUSES PLANT FLOOR TO FLOOD. ASBESTOS CODE A-CLEAR FOR REPAIR BY 11/02/01 HRONE ENGINEER: EDWARD RODRIGUEZ November 1, 2001 March 25, 2003 509 days
Woodson High School FM-200117548 01 3/25/03 H.D. WOODSON BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. R/R DOOR REFRACTORY ON #1 & 2 BOILERS. 3. R/R AROUND CONES OF BURNER. ASBESTOS CODE A-CLEAR FOR REPAIR BY ROY AGNANT HORNE ENG. ON 9/10/01. August 15, 2001 March 25, 2003 587 days
Ballou Senior High School FM-200115291 01 3/25/03 BALLOU BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. BOILER #4 CLEAVER BROOKS PACKAGED: TUPE REPLACEMENT. REPLACE ENTIRE INTERIOR FIRE TUBES ON #4 BOILER (79 FIRE TUBES) BOILER INFO: CLEAVER BROOKS MOD. #760-125A, SER. #L47171. ASBESTOS CODE A - CLEAR FOR REPAIR ON 07/20/01. July 16, 2001 March 25, 2003 617 days
Ballou Senior High School FM-200120675 01 3/25/03 BALLOU 1 ST FLOOR REGESTRA ROOM REPLACE (1) ONE SAFETY RELIEF VALVE ON BOILER #1 INFO: 2" RELIEF VALVE MOD# 174A 30 LBS. ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER STEPHEN CALDWELL September 28, 2001 March 25, 2003 543 days
Ballou Senior High School FM-200121007 01 3/25/03 BALLOU BOILER ROOM SPOT WELD (2) TWO 5 INCH METAL PLATES ON THE SUPPLY AND RETURN CONDENSER A/C LINES. NOTE: NO INSTALLATION ON ALL THE PIPING, PLATES ARE NEEDED TO COVER EXITING HOLES. CODE A- CLEAR FOR REPAIRS AS OF 10/24/01 (SG) FOR CEB. October 4, 2001 March 25, 2003 537 days
Ballou Senior High School FM-200121008 01 3/25/03 BALLOU BOILER ROOM REPLACE (1) ONE HOT WATER CIRCULATING PUMP THAT SUPPLIES THE HEATING TO AUTO SHOP. INFO: WORTHINGTON PUMP: SER#AZ10869 IMP. DIA. 6 3/4 A PUMP-1 1/2 LLR7 NOTE: REPLACEMENT NEEDED - WEAR AND TEAR. October 4, 2001 March 25, 2003 537 days
Ballou Senior High School FM-200124425 01 3/25/03 BALLOU BOILER ROOM REPLACE COOLING TOWER. TOWER IS DETERIORATED AND LEAKS BADLY. December 4, 2001 March 25, 2003 476 days
Ballou Senior High School FM-200125642 /01 3/25/03 BALLOU BOILER ROOM REPLACE #1 HOT WATER (MAIN) CIRCULATING PUMP. INFO: BELL & GOSSETT SIZE 185011, SERIAL # 1664615 I.D. #L19. NOTE: THIS PUMP SUPPLIES HEAT TO THE MAIN BUILDING (FOR HEATING ONLY). December 18, 2001 March 25, 2003 462 days
Ballou Senior High School FM-200125785 /01 3/25/03 BALLOU BOILER ROOM PM A/C CHILLER. December 19, 2001 March 25, 2003 461 days
Reed LC FM-200126794 02 3/25/03 REED BOILER ROOM SCHEDULED FOR CHILLER REPLACEMENT. January 4, 2002 March 25, 2003 445 days
Plummer Elementary School FM-200126446 /01 3/25/03 PLUMMER BOILER ROOM REPLACE SERVICE DISSCONECT FOR BURNER ON BOILER #2. December 31, 2001 March 25, 2003 449 days
Garnet-Patterson MS FM-200122923 01 3/25/03 GARNET-PATTERSON BOILER ROON REPAIR/REPLACE STICKING GAS VALVE ON #2. wp-200108858 November 6, 2001 March 25, 2003 504 days
Nalle Elementary School FM-200125373 /01 3/25/03 J.C. NALLE BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE CHEMICAL TANK THAT IS LEAKING WATER. TANK CAN NOT BE ISOLATED. SYSTEM IS LOSING WATER PRESSURE. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 12/17/01. HORNE ENGINEERING - ROGER KAGER (RG) December 14, 2001 March 25, 2003 466 days
Nalle Elementary School FM-200125609 /01 3/25/03 NALLE BOILER ROOM REPLACE FEEDWATER REGULATOR. REGULATOR NOT FEEDING WATER BACK INTO BOILER. December 18, 2001 March 25, 2003 462 days
Peabody Elementary School FM-200124959 /01 3/25/03 PEABODY BOILER ROOM REPAIR BOILER #2 BURNER, IT CUTS OFF ON FLAME FAILURE. December 12, 2001 March 25, 2003 468 days
Peabody Elementary School FM-200124284 01 3/25/03 (PEABODY) BOILER# 2 FLAME FAILURE December 3, 2001 March 25, 2003 477 days
Peabody Elementary School FM-200123933 /01 3/25/03 PEABODY BOILER ROOM REPLACE #1 RETURN PUMP MOTOR. MAGNETEK MODEL #BJ6-252, PH 3, AMPS. 2.5.18.9, RPM 3450/2850. November 28, 2001 March 25, 2003 482 days
Peabody Elementary School FM-200123826 /01 3/25/03 PEABODY BOILER ROOM REPAIR OR REPLACE MCDONNELL & MILLER LOW WATER CUT OFF ON BOILER #2. NEW FEEDER November 27, 2001 March 25, 2003 483 days
Patricia R Harris Ed Center FM-200124935 /01 3/25/03 P.R. HARRIS BOILER ROOM RELOCATE GAS VENT LINES FROM DISCHARGING ONTO LOADING DOCK AREA AND RAISE TO ROOF TOP AIRA. * SAFETY HAZARD GAS FUNES FROM VENT LINES ENTERING KITCHEN AREA. Code-A clear for repiar by Horne Engineer ( Sam Ebrahim ) 3/07/02 CEB December 11, 2001 March 25, 2003 469 days
Patricia R Harris Ed Center FM-200124447 01 3/25/03 P.R. HARRS BOILER ROOM GRD. FL. 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE LEAKING 2" BLACK PIPE CITY WATER MAKE-UP LINES TO CHILL WATER EXPANSION TANK AND HOT WATER EXPANSION TANK. ALSO, ISOLATE LINES WHEN WORK IS COMPLETE. ASBESTOS CODE A-CLEAR FOR REPAIR 12/05/01 BY HORNE ENGINEER: TROY WILCOME December 4, 2001 March 25, 2003 476 days
Wilson J. O. ES FM-200121685 /01 3/25/03 WILSON, J.O. BOILER ROOM 1.ASBESTOS ASSESSMENT REQUIRED 2.REPLACE 2 FEED WATER REGULATOR ON 1/4" LINE GOING TO BOILER. 3.REPLACE 3 1/4" GATE VALVE BY PASS 1/4 AND 1 1/4"GOING TO #1 BOILER AND 2 819; A3; 225F;30LBS.;125PSI VALVES ARE NOT HOLDING ASBESTOS CODE A-CLEAR FOR REPAIR BY 10/31/01 HORNE ENGINEER: BIPIN NANAVANT October 16, 2001 March 25, 2003 525 days
Patricia R Harris Ed Center FM-200104709 01 3/25/03 HARRIS, P.R. GROUND FL. BOILER ROOM REPLACE BOTH CONDENSATE RETURN PUMPS TO STEAM BOILER #4 DUE TO IMPROPER FLOW OF RETURN WATER TO BOILER. PUMPS - TAIT MANUFACTURING CO. DAYTON OHIO. MODEL #SJF2, SERIAL #C74. BOTH PUMPS HAVE BEEN REBUILT TWO TIMES EACH. March 2, 2001 March 25, 2003 753 days
Winston EC FM-200125787 /01 3/25/03 WINSTON BOILER ROOM PM A/C CHILLER. December 19, 2001 March 25, 2003 461 days
Orr Elementary School FM-200123392 /01 3/25/03 ORR SCHOOL BOILER ROOM 1. ASBESTOS ABATEMENT REQUIRED 2. REPLACE 3/4 INCH DRAIN LINE AND GATE VALVE ON AIR SEPARATOR. ASBESTOS CODE A-CLAER FOR REPAIR 11/30/01 BY HORNE ENGINEER: RAY AGNANT November 15, 2001 March 25, 2003 495 days
Orr Elementary School FM-200125788 /01 3/25/03 ORR BOILER ROOM PM A/C CHILLER. December 19, 2001 March 25, 2003 461 days
Harris, C.W. ES FM-200120451 01 3/25/03 C.W. HARRIS BOILER ROOM REPLACE EXISTING SUMP PUMP MOTORS WHICH ARE NON-FUNCTIONAL,CAUSING BOILER ROOM TO FLOOD. September 25, 2001 March 25, 2003 546 days
Wilson High School FM-200121937 /01 3/25/03 WILSON SHS BOILER ROOM BOILER # 3 BURNER WILL NOT IGNITE (PURGE INTERLOCK) October 19, 2001 March 25, 2003 522 days
Wilson High School FM-200104026 01 3/25/03 WILSON, W. BOILER ROOM/PUMP ROOM REPAIR STEAM OPERATED WORTHINGTON RECIPROCATING FEED WATER PUMP, SIZE 10 X 6 X 10 & TYPE-VC. February 21, 2001 March 25, 2003 762 days
Wilson High School FM-200103497 01 3/25/03 WILSON, W BOILER ROOM REPLACE AIR FUEL MODULATING CONTROL MOTOR TO #1 & 2 BURNERS; PART NO. M8OJAC-3, MFG - PENN. February 12, 2001 March 25, 2003 771 days
Harris, C.W. ES FM-200102658 2/1/01 3/25/03 HARRIS, C.W. BOILER ROOM REPAIR CIRCULATING PUMP #2 ( ELECTRICAL PROBLEM - CHECK SWITCH #21 IN CONTROL BOX) PUMP NOT WORKING. February 1, 2001 March 25, 2003 782 days
Bancroft Elementary School FM-200117941 01 3/25/03 BANCROFT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE FAULTY 1-1/4" BYPASS GATE VALVE ON DOMESTIC HOT WATER CIRCULATING PUMP LINE. BONNET IS BROKEN. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 08/22/01 HORNE ENGINEERS- BIPIN NANAVATY August 21, 2001 March 25, 2003 581 days
Bancroft Elementary School FM-200117939 01 3/25/03 BANCROFT BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE FAULTY 1-1/4" BYPASS GATE VALVE ON DOMESTIC HOT WATER CIRCULATING PUMP LINE. BONNET IS BROKEN. ASBESTOS CODE A-CLEAR FOR REPAIR BY HORNE ENGINEER DONALD MAGLIENTI August 21, 2001 March 25, 2003 581 days
Bancroft Elementary School FM-200110649 01 3/25/03 BANCROFT MAIN BLDG. BOILER ROOM REPLACE #1 HOT WATER CIRCULATING PUMP. THE PUMP HAS A CRACK IN THE HOUSING NEAR THE REAR PACKING GLANDS EYE BOLT. AURORA PUMP, SIZE 28 X 2-1/2, NO. 6220978-2, RPM 1750, HEAD FEET 65, GPM 96. WP-200108636 May 21, 2001 March 25, 2003 673 days
Bell High School FM-200206791 02 3/26/03 Bell Boiler room 1. Asbestos assessment required. 2. Electronic valve over top of chiller needs to be replaced or repaired. Valve is leaking. Asbestos Code A - Clear for repairs on 04/29/02. Horne Engineering - Stephen Caldwell (RG 04/30/02) April 29, 2002 March 26, 2003 331 days
Bruce-Monroe Elementary School FM-200220196 /02 3/26/03 Bruce-Monroe Boiler Room Repair burner to Boiler #1. Will not start inoperable. October 29, 2002 March 26, 2003 148 days
Eastern High School FM-200208816 02 3/26/03 Eastern Boiler room Asbestos assessment required Brick work is needed in firebox of #1 boiler. 1) the bridge wall 2) the side wall by opening. Task must be complete before boilers are inspected. Asbesstos Code A-clear for repair by Horne Engineer Roger Kager DCPS Charles E. Buchanan on 9/18/02 June 3, 2002 March 26, 2003 296 days
Draper Elementary School FM-200204258 02 3/26/03 Draper School Boiler room Repair boiler #2, will not start, out on flame failure. March 11, 2002 March 26, 2003 380 days
Eastern High School FM-200222273 /02 3/26/03 Eastern Boiler Room Boiler #1 replace feed water line. Asbestos Code A - Clear for repairs on 12/23/02. Horne Engineering - Troy Wilcome (RG 12/24/02) December 10, 2002 March 26, 2003 106 days
Eastern High School FM-200222395 /02 3/26/03 Eastern Mechanical Room Sub Basement Furnish and install (3) low pressure condensate retunr tanks in gym in order to bring condensate back to boiler room. Info: HOFFMAN Type:WC SIMPLES Watchman WC8-208 Asbestos Code A - Clear for repairs on 12/11/02. Horne Engineering - Philp Connolly (RG 12/13/02) December 11, 2002 March 26, 2003 105 days
Shaed Elementary School FM-200214054 02 3/26/03 1. Asbestos assessment required. 2. Repair or replace refractory in the combustion chambers of boilers #1 and #2 Asbestos Code A-clear for repair by Horne Engineer Philip Connolly on 8/23/02 DCPS Charles E. Buchanan August 12, 2002 March 26, 2003 226 days
Shepherd ES FM-200202430 02 3/26/03 SHEPHERD BOILER ROOM PERFORM REPAIRS TO CONDENSATE SYSTEM AND BALANCE RETURN WATER February 5, 2002 March 26, 2003 414 days
Seaton Elementary School FM-200219450 /02 3/26/03 repair gas leak on # 1 boiler . October 16, 2002 March 26, 2003 161 days
Deal Junior High School FM-200226039 03 3/26/03 Deal Boiler Room Repair linkages on Boiler #2. Boiler off. February 23, 2003 March 26, 2003 31 days
Benning Elementary School FM-200224131 03 3/26/03 Benning Boiler room Repair # 1 boiler ,burner will not start. January 17, 2003 March 26, 2003 68 days
Deal Junior High School FM-200225915 03 3/26/03 Deal Boiler Room Repair condensate return pumps February 18, 2003 March 26, 2003 36 days
Eaton Elementary School FM-200220554 02 3/26/03 Eaton Boiler Room Remove old demestic hot water heater from boiler room. Old heater was never remove once the new one was install. November 1, 2002 March 26, 2003 145 days
Eaton Elementary School FM-200223660 03 3/26/03 Eaton Boiler Room Check hot water domestic heater, fire code volation, may need electric work. Check electric out let for hard wiring. January 9, 2003 March 26, 2003 76 days
Deal Junior High School FM-200204037 02 3/26/03 Deal Basement/ Boiler Room Repair or replace 3" steam line with hole in it. Leaking very badly. No insulation in this area. Code A-clear for repair by DCPS Safety Charles Buchanan ( ) on 3/15/02 (CEB) March 7, 2002 March 26, 2003 384 days
Jefferson JHS FM-200105364 01 3/26/03 Jefferson Boiler Room Replace two (2) float assemblies on vacuum return tank. Assemblies are leaking onto floor causing the floor to be constantly wet and creating slippery condition. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 06/19/01. March 9, 2001 March 26, 2003 747 days
School WW High School FM-200218714 02 3/26/03 Replace program box on # 1 boiler , unit must be reset each time building calls for heat. Honeywell #RA890F1346 9113 Asbestos Code A-clear for repair by Horne Engineer Troy Wilcome on 10/07/02 DCPS Charles E. Buchanan October 2, 2002 March 26, 2003 175 days
Jefferson JHS FM-200202998 02 3/26/03 JEFFERSON BOILER ROOM SURVEY AND MAKE NECESSARY REPAIRS TO BOILER #2. BOILER WILL NOT START. February 14, 2002 March 26, 2003 405 days
School WW High School FM-200203730 02 3/26/03 School Without Walls Boiler room Repair or replace condensate pump #1 in boiler room leaking water on floor. You have to make it run sometime. February 28, 2002 March 26, 2003 391 days
Jefferson JHS FM-200224653 03 3/26/03 JEFFERSON JHS Boiler room "URGENT" Repair or replace damaged flue stack on hot water heater in old boiler. Fumes are escaping into building causing a potential health hazard. January 27, 2003 March 26, 2003 58 days
Hine JHS FM-200209896 02 3/26/03 Hine Boiler Room Replace blowdown valve on pump header line. Valve will not holding. June 20, 2002 March 26, 2003 279 days
Woodson High School FM-200225424 03 3/26/03 Woodson ,H.D. Boiler room Repair or replace sump pumps ,will not run in automatic Boler room Flooded February 10, 2003 March 26, 2003 44 days
Payne Elementary School FM-200219059 02 3/26/03 Check circuit breaker for boilers # 1 and # 2, breaker will not reset October 8, 2002 March 26, 2003 169 days
Davis Elementary School FM-200222268 /02 3/26/03 Davis Boiler Room Boiler #2 out on flame failure. December 10, 2002 March 26, 2003 106 days
Ludlow-Taylor ES FM-200222271 /02 3/26/03 Ludlow-Taylor Boiler Room Boiler #2 replace bad check valve on feed water line. December 10, 2002 March 26, 2003 106 days
Ludlow-Taylor ES FM-200218870 02 3/26/03 Repair or replace Honeywell air compressor in the boiler room, Model: czt-156HP3 :Ser.# 119-85073 : MAWP 200 psi 450 degree F SH.154,HD 124 ,MDMT 200F @200 psi HD,RAD Part# 38788 D TNk HSD,S CRWE 7399 2C October 4, 2002 March 26, 2003 173 days
Terrell Mc ES FM-200207162 02 3/26/03 Terrell M.C. (boiler room) Repair/replace refactory insulation on fire door (front) on boiler #1. insulations is cracked and broken. May 6, 2002 March 26, 2003 324 days
Ludlow-Taylor ES FM-200212605 02 3/26/03 Cut loose metal from water leg of #2 boiler rear side, so that the boiler will pass inspection July 23, 2002 March 26, 2003 246 days
Savoy Elementary School FM-200225964 03 3/26/03 Savoy Boiler Room Check and repair Boilers #1 and #3, Boilers in flame failure. Only (1) one Boilers working. February 21, 2003 March 26, 2003 33 days
Eliot Junior High School FM-200209805 02 3/26/03 Eliot Boiler room 1. Asbestos assessment required. 2. Replace (2) 2" quick opening valves on #3 boiler. Code A-clear for repair by Horne Engineer ( Bipin Nanavaty ) on 06/20/02 June 19, 2002 March 26, 2003 280 days
Savoy Elementary School FM-200224141 03 3/26/03 Savoy Boiler room Repair Boiler # 1 ,off on lockout. January 17, 2003 March 26, 2003 68 days
Meyer Elementary School FM-200222407 /02 3/26/03 MEYER Boiler room URGENT ON HEAT IN BUILDING Check boiler burner and all auxiliary equipment. As a result of unscheduled power outage on yesterday (12/11/02). Burner are off on safety fault. Electricians are need to check also. December 12, 2002 March 26, 2003 104 days
Webb Elementary School FM-200219435 /02 3/26/03 Repace low water cut out on # 1 boiler, McDonnell Miller #63. The Engineer will install. October 16, 2002 March 26, 2003 161 days
Webb Elementary School FM-200225049 03 3/26/03 Webb Boiler room Replace coupling insert on the circulaing pump , the coupling is broken into small pieces. February 3, 2003 March 26, 2003 51 days
Anacostia Senior High School FM-200207626 02 3/26/03 Anacostia Boiler room Replace gasket on 4" line condenser side of chiller. May 13, 2002 March 26, 2003 317 days
Terrell Mc ES FM-200202294 02 3/26/03 TERRELL M.C. BOILER ROOM REPAIR BURNER ON BOILER # 1 OUT ON FLAME FAILURE. February 1, 2002 March 26, 2003 418 days
Tubman Elementary School FM-200226593 03 3/26/03 Tubman Boiler Room Basement Repair burner on boiler #2 Boiler keep cutting off on flame failure March 5, 2003 March 26, 2003 21 days
Coolidge High School FM-200220679 /02 3/26/03 Coolidge Mechanical Room Replace leaking mechanical seal on shipco vacuum pump motor in boiler room. Model #D vertical JM Frame three phase. November 12, 2002 March 26, 2003 134 days
Coolidge High School FM-200220602 02 3/26/03 Coolidge Boiler Room Boiler #1 will not start, bad solenoid valve. Pilot gas solenoid valve ASCO Watts 10 Cat. K3A432T PSI Max 1/2 Date 9/94 Volts 120/60 Ser. # 160978 Volts 110/50 Pipe size 1/2'' Amps 15 November 1, 2002 March 26, 2003 145 days
Bancroft Elementary School FM-200221950 02 3/26/03 Bancroft Boiler Room Replace faulty McDonnell boiler control, model #51 SFHD. This safety device is not seating (closing) and opening properly. December 3, 2002 March 26, 2003 113 days
Duke Ellington School FM-200213517 02 3/26/03 Recharge compressor # 1 on Air conditioning unit in the boiler room August 5, 2002 March 26, 2003 233 days
Coolidge High School FM-200220595 02 3/26/03 Coolidge Boiler Room Provide McDonnell & Miller modulating pneumatic liquid level control valves needed to operate boiler feed water system Model # PFC-1-GR November 1, 2002 March 26, 2003 145 days
Coolidge High School FM-200220594 02 3/26/03 Coolidge Boiler Room Replace quick open and slow open valves on both bottom and surfaca blow down lines on boilers #1 and #3 . Valves Leaking Asbestos Code A - Clear for repairs on 11/14/02. Horne Engineering - Bipin Nanavaty (RG 11/15/02) November 1, 2002 March 26, 2003 145 days
Coolidge High School FM-200208763 02 3/26/03 Coolidge Boiler room Replace (4) 4 inch flanged steam stop valves, 2 one north side, 2 on side stations in tunnel entrance. May 31, 2002 March 26, 2003 299 days
Coolidge High School FM-200207598 02 3/26/03 Coolidge Boiler room Replace two non-return valves and two steam stop valves to #2 boiler as requested by DC Boiler Inspector. May 13, 2002 March 26, 2003 317 days
Bancroft Elementary School FM-200219827 /02 3/26/03 Bancroft Open Space Boiler Room Roof Top Replace bearing on fan in air handle #1 bearing are bad and fan is making very loud noise October 22, 2002 March 26, 2003 155 days
Bell High School FM-200218911 02 3/26/03 Bell S.H.S Boiler Room Repair burner on # 1 Boiler Burner going out on flame failure when burner comes on lockout. October 7, 2002 March 26, 2003 170 days
Coolidge High School FM-200203717 02 3/26/03 Coolidge Cafeteria 1. Asbestos assessment required. 2. Repair leaking 2" steam supply line broken in cafeteria floor at floor level. Boiler plant is off line due to steam leak. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/28/01. HORNE ENGINEERING - SHERYLL JAMES (RG 02/2802) February 28, 2002 March 26, 2003 391 days
Anacostia Senior High School FM-200107424 /5/01 3/26/03 ANACOSTIA BOILER ROOM REPLACE FEEDWATER REGULATOR ON BOILER #3. BOILER - ORR & SEMBOWER, MODEL #6791, YEAR BUILT 1974, MAX. WP 15 LBS PS., HEATING SURFACE 1323 SQ. FT. April 5, 2001 March 26, 2003 720 days
Watkins Elementary School FM-200209294 02 3/26/03 Watkins Boiler room Boiler #2 burner need recalibrating, it smokes on hard fire. June 11, 2002 March 26, 2003 288 days
Bancroft Elementary School FM-200219599 /02 3/26/03 Bancroft Boiler Room Send burner technician with calibration instruments to properly claibrate burners at all modulation levels on boiler #1. When burners are calibrated properly they burn more efficiently and cleaner . * Alot of soot in boilers during cleaning. October 17, 2002 March 26, 2003 160 days
King M L ES FM-200224594 03 3/26/03 King,M.L. Boiler Room Boiler #1 will not start, off on flame failure. January 27, 2003 March 26, 2003 58 days
Emery Elementary School FM-200223374 /02 3/26/03 EMERY boiler room Repair boilers to start. Out on flame failure December 31, 2002 March 26, 2003 85 days
Smothers ES FM-200219644 /02 3/26/03 SMOTHERS BOILER ROOM 1. Asbestos assesment may be required. 2. Repair pin hole leak on condensate receiver Asbestos Code A - Clear for repairs on 10/18/02. Horne Engineering - Edward Rodrigue (RG 10/21/02) October 18, 2002 March 26, 2003 159 days
Smothers ES FM-200219657 /02 3/26/03 SMOTHERS TUNNEL in BOILER ROOM 1. Asbestos assessment required. 2. Replace ruptured approximately 16 ' section of 2" black pipe on condensate return line. 3. Replace ruptured 1 inch condensate return on boiler # 1. Asbestos Code A - Clear for repairs on 10/22/02. Horne Engineering - Troy Wilcome (RG 10/23/02) October 18, 2002 March 26, 2003 159 days
Bancroft Elementary School FM-200201040 02 3/26/03 BANCROFT BASEMENT MAIN BLDG. BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR LEAKING 2" CONDENSATE RETURN LINE ON BOILER ROOM FLOOR. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 HORNE ENGINEER: EDWARD RODRIZUEZ January 14, 2002 March 26, 2003 436 days
Woodson High School FM-200217259 02 3/26/03 H.D. Woodson Basement Physical Heating Plant/ B.R Make the necessary repairs to (2) leaking fire tubes in boiler # (1) also (2) leaking fire tubes in boiler #2, leaking tubes need to be replaced before the heating season starts October 15, 2002. Also for D.C Insepction September 11, 2002 March 26, 2003 196 days
Bancroft Elementary School FM-200127421 02 3/26/03 BANCROFT MAIN BLDG. BOILER ROOM 1. ASBESTOS ASSESSMENT NEEDED. 2. ADJUSTMENT NEEDED ON FLOAT CONTROL TO CIT WATER MAKEUP ON CONDENSATE RETURN TANK. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 BY HORNE ENGINEER: STEPHEN CALSWELL January 14, 2002 March 26, 2003 436 days
Johnson JHS FM-200127232 02 3/26/03 JOHNSON JHS BOILER ROOM 1. ASBESTOS ASSESTMENT REQUIRED. 2. REPLACE LEAKING PRESSURE RELIEF VALVE ON NUMBER ONE (1) BOILER. VALVE IS NOT HOLDING. POC MR. ROY DANIELS @ 202-996-2795 ASBESTOS CODE - A - CLEAR FOR REPAIRS ON 01/10/02 HORNE ENGINEERING - TROY WILCOME (RE) January 10, 2002 March 26, 2003 440 days
West Elementary School FM-200214721 02 3/26/03 West Boiler room Repair or replace header valve on #2 boiler size 8" valve is leaking will not hold the water in the system. Repair needed for annual boiler inspection. August 16, 2002 March 26, 2003 222 days
Moten Elementary School FM-200216365 02 3/26/03 Moton boiler room Repair refactory in firebox in one and two boiler. Asbestos Code A - Clear for repairs on 09/04/02. Horne Engineering - Troy Wilcome (RG 09/11/02) September 3, 2002 March 26, 2003 204 days
Johnson JHS FM-200218807 02 3/26/03 Johnson J.H.S Boiler Room Start up burners and test safety controls on specified boilers. October 3, 2002 March 26, 2003 174 days
Johnson JHS FM-200220612 /02 3/26/03 Johnson Boiler Room Check building for heating problem. Relief valve need to be replace. Asbestos Code A - Clear for repairs on 12/12/02. Horne Engineering - Tony Marcolin (RG 12/13/02) November 12, 2002 March 26, 2003 134 days
Ferebee-Hope Elementary School FM-200205692 02 3/26/03 Ferebee-Hope Boiler room Repair ID fans #1 and #2. Fans run constantly when power to boilers is on. April 10, 2002 March 26, 2003 350 days
Johnson JHS FM-200220667 /02 3/26/03 Johnson JHS boiler room Check boiler burner # 3, constantly goes out on flame failure. November 12, 2002 March 26, 2003 134 days
Sousa Middle School FM-200202082 02 3/26/03 SOUSA JHS BOILER ROOM TROUBLESHOOT AND MAKE NECESSARY CORRECTIONS TO BURNERS ON BOILERS # 1 AND 2. BOTH BURNERS ARE OUT ON FLAME FAILURE. January 30, 2002 March 26, 2003 420 days
Sousa Middle School FM-200217758 02 3/26/03 SOUSA Boiler room Repair or repalce existing oil transfer pump. first pump is inoperable, second pump makes excessive noise. Pumps needed to operate boilers for heating. September 18, 2002 March 26, 2003 189 days
Moten Elementary School FM-200223403 03 3/26/03 Moten Boiler Room Repair or replace circulating pumps #1 and #2, pumps down. January 2, 2003 March 26, 2003 83 days
Moten Elementary School FM-200224713 03 3/26/03 MOTEN boiler room " Urgent" Recontruction concrete pading/base is deterioting. January 28, 2003 March 26, 2003 57 days
Ferebee-Hope Elementary School FM-200224756 03 3/26/03 Ferebee- Hope Boiler Room Electrical Department Need To Check Power Box ,Motor and make sure its pulling the right amperage HVAC Shop Repair or replace ejector pump, pump not working. January 29, 2003 March 26, 2003 56 days
Roosevelt High School FM-200226781 03 3/26/03 Roosevelt Boiler Room Replace (1) one inch threaded gate valve (150S) on Boiler #3. Gate valve needs to be rated for 150 PIS steam pressure. March 10, 2003 March 26, 2003 16 days
Hart Middle School FM-200220067 /02 3/26/03 Hart M.S Boiler Room Boiler #1 (Burner) blower motor is pulling high amps and causing the blower starter motr to trip (Shutting down the boiler in main flame failure) October 25, 2002 March 26, 2003 152 days
Lincoln Middle School FM-200105153 01 3/26/03 LINCOLN BOILER ROOM BOILER #2 REPLACE MOTOR ID FAN ON BOILER. INFO: DELCO 3 PHASE, MOD # 2J2224R1Z, SER. F-87, INS #1 , AM B:40, HP 3/4, RPM 1745, V 208-220/440 - 230/460, A - 2.8 - 2.8/1.4, HZ 60, CODE L, SE 1.25, DUTY CONT. BRGS - ND-77503-LR1RV. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 11/06/01 LEROY MINTON - SAFETY (202)576-6691(RG) March 7, 2001 March 26, 2003 749 days
Roosevelt High School FM-200224665 03 3/26/03 Roosevelt Boiler room Investigate and determine why the boilers will not maintain steam pressure January 28, 2003 March 26, 2003 57 days
Thomson Elementary School FM-200202703 02 3/26/03 THOMSON BOILER ROOM REPAIR #1 BOILER BURNER CUT OFF ON FLAMER FAILURE. February 8, 2002 March 26, 2003 411 days
Spingarn High School FM-200202951 02 3/26/03 Spingarn 3rd fl. Room 325 Do survey on a/c leaks in tunnel and why compensate will not return to boiler room. ASBESTOS CODE A - CLEAR FOR REPAIRS ON 02/21/02. HORNE ENGINEERING - SHERYLL JAMES (RG 02/22/02) February 13, 2002 March 26, 2003 406 days
Spingarn High School FM-200203709 02 3/26/03 Spingarn West Tunnel 1. Asbestos assessment required. 2. Repair leak in 4" line in west tunnel near boiler room. CODE A- CLEAR FOR REPAIR BY HORNE ENGINEER( STEPHEN CALDWELL ) ON3/01/02 (CEB) February 28, 2002 March 26, 2003 391 days
Spingarn High School FM-200223116 /02 3/26/03 SPINGARN BOILER RM 1. Asbestos assessment required on insulation. 2. Repair/replace leak on eight inch OS & Y valve on main steam header. HP steam leaking. Asbestos code A-clead for repair by Horne Engineer Sheryll James DCPS on 12/31/02 Charles E Buchanan December 26, 2002 March 26, 2003 90 days
Wilson J. O. ES FM-200222404 /02 3/26/03 Wilson, J.O. Boiler Room Pumps down, Heating problem for Principal's Office,main office and 1st floor new side of Building. Manually resetting by hand. Little / no heat in these area. Marathen electric: Motor model - AJ145TTD7926ABN; Frame-145T; Type-TRR-BE; AMP-5.5; Max Amb-40; PH-3;Code-J; Class-of ins B; Duty-Cont; S.F.-1.15; Res - B; Shaft and Bearing; Volt-200; Amp-5.5 December 12, 2002 March 26, 2003 104 days
Hart Middle School FM-200218817 02 3/26/03 Hart M.S Boiler Room Boiler # 2 Replace (Missing) burner linkage that controls inlet damper. * Can 't test fire or operate boiler without missing part. October 3, 2002 March 26, 2003 174 days
Hart Middle School FM-200204496 02 3/26/03 Hart Boiler room Replace (3) 1" feed water reg. range 25-75 lbs, adjust to minimum 40 lb. set. Install with regulators (8) 1" gate valves not holding on boilers. Boiler No. 1 required (4) 1" valves, No. 2 required (2) and No. 3 requires (2) system must be filled to properly adjust pounds and feet of water. March 15, 2002 March 26, 2003 376 days
Hart Middle School FM-200204304 02 3/26/03 Hart Boiler room Replace safety valve in #1 boiler. Specs: 60 PSI, 2" diameter. March 12, 2002 March 26, 2003 379 days
Leckie Elementary School FM-200217540 02 3/26/03 Leckie Repair chiller in boiler room, unit making loud noise, control pressure @ 3 psi chiller subject to shut down. September 16, 2002 March 26, 2003 191 days
Leckie Elementary School FM-200210850 02 3/26/03 Leckie Boiler room Replace weld-o-let on mud legs on boilers #1 and #2. July 9, 2002 March 26, 2003 260 days
Stanton Elementary School FM-200201321 02 3/26/03 STANTON SCHOOL BOILER ROOM TROUBLESHOOT PROBLEM WITH BOILER ONE FLAME FAILURE. January 18, 2002 March 26, 2003 432 days
River Terrace ES FM-200218428 02 3/26/03 RIVER TERRACE BOILER ROOM Retube boilers #1 and #2 September 27, 2002 March 26, 2003 180 days
Stanton Elementary School FM-200204064 02 3/26/03 Stanton School Boiler room Ck starter contorl switch on the condensate return for # 2 boiler March 7, 2002 March 26, 2003 384 days
Kenilworth ES FM-200215339 02 3/26/03 Kenilworth Boiler Room Check burner #1 will not start, flame failure. August 22, 2002 March 26, 2003 216 days
Kenilworth ES FM-200218073 02 3/26/03 Kenilworth Boiler room Check boiler #2 , burner continues to go out on flame failure. September 23, 2002 March 26, 2003 184 days
Woodson High School FM-200204878 02 3/26/03 H. D. Woodson Boiler room ceiling 1. Asbestos assessment required. 2. Repair 6" hot water supply line to dual circulating pumps #12 & 13. Line is approximate 10 ft. high in ceiling. Line is leaking rapidly through insulation and can not be isolated. POC: Mr. Parker Asbestos Code A - Clear For Repairs On 03/25/02. Horne Engineering - Troy Wilcome (RG 03/25/02) March 25, 2002 March 26, 2003 366 days
Woodson High School FM-200204167 02 3/26/03 Woodson Boiler Room Boilers #1 and # 2 down on flame failure. March 11, 2002 March 26, 2003 380 days
Jessie LaSalle Elementary FM-200226052 03 3/26/03 LaSalle Boiler room Replace Low water cut off on the # 2 boiler ,unit is rusted out on one side February 24, 2003 March 26, 2003 30 days
Jessie LaSalle Elementary FM-200226050 03 3/26/03 LaSalle Boiler room Repair # 2 boiler ,boiler is off on lock-out February 24, 2003 March 26, 2003 30 days
Park View ES FM-200225184 03 3/26/03 Parkview Boiler room Investigate problems with sump pumps February 5, 2003 March 26, 2003 49 days
Clark Elementary School FM-200221675 /02 3/26/03 Clark Boiler Room Replace relief valve on boiler #1.Relief valve is discharging with no pressure. Model-M #740; size 1 1/2" ; setting 30 ; BTU rating 29000 ASME Boiler #2 has been red tag by gas company. November 26, 2002 March 26, 2003 120 days
Park View ES FM-200223218 /02 3/26/03 Parkview Boiler Room Correct problem that causing boiler room to flood. Boiler Room was flooded a couple of weeks ago without problem being resuleted(It's about a 1 1/2" on floor at present) Note: Sump pump appears to be working December 26, 2002 March 26, 2003 90 days
Raymond Elementary School FM-200207067 02 3/26/03 Raymond Boiler room Repair leak in #1 boiler that appears to be leaking around the weld inside the fire box were the fire door open and close fire box is full with water. Assessment does not apply. May 3, 2002 March 26, 2003 327 days
Gage-Eckington ES FM-200205936 02 3/26/03 G. Eckington Boiler room Service multi stack units, they cut off on fault. April 17, 2002 March 26, 2003 343 days
Gage-Eckington ES FM-200207854 02 3/26/03 Gage-Eckington Boiler room Troubleshoot and repair 7 of 12 compressors that are off in fault units goes in to fault after you reset them. 5 compressors running continuously. May 16, 2002 March 26, 2003 314 days
Gage-Eckington ES FM-200219104 02 3/26/03 Gage-Eckington Boiler Room Replace circuit breaker to Boiler #1 and #2. Boiler will not start. October 9, 2002 March 26, 2003 168 days
Raymond Elementary School FM-200202788 02 3/26/03 Raymond Boiler room Repair leak in shell around the clean out door in back of the boiler. Water is leaking from the seam of the shell around the clean out door. Asbestos assessment does not apply. February 11, 2002 March 26, 2003 408 days
Gage-Eckington ES FM-200220757 /02 3/26/03 Gage Eckington Boiler room Asbestos assessment required Repair leaking water leg on the # 1 boiler in the rear. Asbestos Code A-clear for repair by Horne Engineer Sharon Voss on 11/19/02 DCPS Charles E. Buchanan November 13, 2002 March 26, 2003 133 days
Ketcham Elementary School FM-200224130 03 3/26/03 Ketcham Boiler Room Boiler #1 and #2 out on flame failure. January 17, 2003 March 26, 2003 68 days
Gage-Eckington ES FM-200225191 03 3/26/03 Gage-Eckington Boiler room Re pair or replace leaking mud leg on the # 1 boiler Asbestos Code A - Clear for repairs on 02/13/03. Horne Engineering - Bipin Nanavaty (RG 02/19/03) February 5, 2003 March 26, 2003 49 days
Gage-Eckington ES FM-200225580 03 3/26/03 Gage Eckington Boiler Room P.M Chiller February 11, 2003 March 26, 2003 43 days
Orr Elementary School FM-200217872 02 3/26/03 ORR Boiler room Repair # 1 Boiler , will not start flame failure. September 19, 2002 March 26, 2003 188 days
Reed LC FM-200208189 02 3/26/03 Reed Boiler room Condensate builds up on AHU unit causing floods in units and also on Mech rm. floor. Trays do not server purpose, trays need to be re-arranged. AHU #10 & 11. Also condensate leaks from the bottom seams caused by corrosion to AHU #3, 4, 5 & 6 causing flooding on mech room floor and gauge area. May 22, 2002 March 26, 2003 308 days
Ballou Senior High School FM-200201815 02 3/26/03 BALLOU BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. RE-INSULATE AND RESET FIRE DOORS ON BOILER S #1, #2 & #3. INFO: BOILERS HOT WATER PACIFIC STEEL. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/29/02 BY HORNE ENGINEER: EDWARD RODRIGUEZ January 25, 2002 March 26, 2003 425 days
Reed LC FM-200209248 02 3/26/03 Reed Boiler Room 1.Asbestos assessment required 2. Asbestos assessment require need on standing water in boiler room floor. 3.Pump 7' of standing water from boiler room. Asbestos Code A - Clear for repairs on 06/10/02. DCPS Safety - Leroy Minton Jr. (RG 06/10/02) June 10, 2002 March 26, 2003 289 days
Ballou Senior High School FM-200210463 02 3/26/03 Ballou Boiler Room Replacing condenser line on cooling system. June 27, 2002 March 26, 2003 272 days
Cardozo High School FM-200202928 02 3/26/03 Cardozo SHS (Boiler Room) (NO HEAT) Repair/Replace Boiler Burner #3 will not ignite. February 13, 2002 March 26, 2003 406 days
Thomas Elementary School FM-200226049 03 3/26/03 THOMAS boiler room "URGENT BOILER ROOM WILL FLOOD" Repair/replace inoperable sump pump # 1 Urgent boiler room will flood due to inoperable condensate return pumps, return are being dump into drain. February 24, 2003 March 26, 2003 30 days
Cardozo High School FM-200202571 02 3/26/03 Cardozo (Boiler room) 1. Asbestos assessment is required for the replacement of the burner ring for #1 boiler. 2. Investigate problem with boiler burner#1. Contact person: C. Emerson office: 202 698-1752 cell: 202 438-7434. Fiber Release Clean-up in AMP 165,19,19a,D1 and gasket removal from Boilers 1 and 3. CODE C ABATEMENT REQUIRED February 7, 2002 March 26, 2003 412 days
Thomas Elementary School FM-200215338 02 3/26/03 Thomas Boiler Room Check and resolve control problem with Boiler #1 will not start. August 22, 2002 March 26, 2003 216 days
Benjamin Banneker Academic HS FM-200220640 /02 3/26/03 Banneker Boiler Room R/R 2" blow down valve on boiler #2 valve is not holding water in boiler. "No water showing in sight glass" Note: Rear of boiler #2. Asbestos Code A - Clear for repairs on 12/12/02. Horne Engineering - Troy Wilcome (RG 12/13/02) November 12, 2002 March 26, 2003 134 days
Thomas Elementary School FM-200209669 02 3/26/03 Thomas Boiler room 1. Asbestos assessment required. 2. Cap off line to former oil storage tank. Tank was removed by contractor. Line leaks rain water into boiler room. Asbestos code A - clears for repairs, on 6/18/02 DCPS Safety - R. Edwards (RE-6/18/02) June 17, 2002 March 26, 2003 282 days
Garfield ES FM-200209670 02 3/26/03 Garfield Basement boiler room Refurish condensate system. June 17, 2002 March 26, 2003 282 days
Garfield ES FM-200217661 02 3/26/03 Garfield Boiler Room Repair steam boiler # 2, boiler light off main gas valve not opening. Also will not modulate from low to high fire. September 17, 2002 March 26, 2003 190 days
Thomas Elementary School FM-200206400 02 3/26/03 Thomas Boiler room Furnish six (6) Gould Cartridge fuses - TR 70R - 70A 250v or less Time delay. Fuses are needed for chill water pumps. April 24, 2002 March 26, 2003 336 days
Stuart-Hobson Middle School FM-200220618 /02 3/26/03 Stuart-Hobson Boiler Room Repair steam leaks in tunnel on westside and eastside of building. Size of line 3/4" and 4" nipple. Asbestos Code A - Clear for repairs on 12/12/02. Horne Engineering - Sharon Voss (RG 12/13/02) November 12, 2002 March 26, 2003 134 days
Stuart-Hobson Middle School FM-200221357 /02 3/26/03 Stuart-Hobson Boiler room Asbestos assessment required Repair or replace leaking water leg inside of the fire box of # 2 boiler,(view from front back right side. only one of (3) boiler are operational. Asbestos Code A - Clear for repairs on 11/20/02. Horne Engineering - Sharon Voss (RG 11/21/02) November 19, 2002 March 26, 2003 127 days
Stuart-Hobson Middle School FM-200222481 /02 3/26/03 Stuart-Hobsos Boiler room URGENT Asbestos assessment may be required. Replace 4" stop valve ont the domestic hot water storage tank line, so contractor can replace new temerture regulator valve. Asbestos Code A - Clear For Repairs On 12/13/02. Horne Engineering - Roger Kager (RG 12/13/02) December 13, 2002 March 26, 2003 103 days
Stuart-Hobson Middle School FM-200223373 /02 3/26/03 Stuart-Hobson Boiler Room Repair or replace 3" return lines leaking on floor. No insulation on line. December 31, 2002 March 26, 2003 85 days
Stuart-Hobson Middle School FM-200224186 03 3/26/03 Stuart-Hobson Boiler Room Replace low water cut out on Boiler #1 URGENT!!!!! January 21, 2003 March 26, 2003 64 days
Powell Elementary School FM-200220527 02 3/26/03 Powell Boiler Room Repair or replace starter control to air compressor General electric- name; AMP-30; Model-7; PH-3; Type-3B; 240-Vac/250-Vac; Cat #TG4321R November 1, 2002 March 26, 2003 145 days
Powell Elementary School FM-200214714 02 3/26/03 Powell Boiler room Repair or replace starter control to air compressor Name - Square-D, Nema size-0, 2-ph, class - 8536, type - bg-2, volts - 110, 120, 440/550, series - A, class 8536, form - 4252-55, compress runs for about 5 mins. The reset kicks out. August 16, 2002 March 26, 2003 222 days
Montgomery ES FM-200210730 02 3/26/03 Montgomery Boiler Room Repair cooling unit on roof. Unit will not run. Note: Services Day Care Center. July 3, 2002 March 26, 2003 266 days
Montgomery ES FM-200219484 /02 3/26/03 Montgomery Boiler Room Basement Repair gas leak on boiler #1 pilot, 3/8" compling to thread October 16, 2002 March 26, 2003 161 days
Plummer Elementary School FM-200224180 03 3/26/03 Plummer Boiler Room Boilers #1 and #2 keep going off on flame failure. January 20, 2003 March 26, 2003 65 days
Plummer Elementary School FM-200218752 02 3/26/03 PLUMMER Boiler room Replace Water regulator Ser. 9246 No. 25 Aub ASSE_1003 1B. 25-75 October 3, 2002 March 26, 2003 174 days
Montgomery ES FM-200223529 03 3/26/03 S.Montgomery Boiler room Repair # 1 boiler off on flame failure, January 6, 2003 March 26, 2003 79 days
Orr Elementary School FM-200218808 02 3/26/03 Orr E.S Boiler Room Start up burners and test safety controls on specified boilers. October 3, 2002 March 26, 2003 174 days
Burrville Elementary School FM-200221754 /02 3/26/03 BURRVILLE boiler room Check compressor # 1 operation excessive amount of oil is being consumed and entering tank, main and branch lines. Repair defective pressure relief valve on pnuematic system. November 29, 2002 March 26, 2003 117 days
Burrville Elementary School FM-200217748 02 3/26/03 BURRVILLE Boiler room Calibrate boiler burner #1 fuel and air distribution. September 18, 2002 March 26, 2003 189 days
Browne Junior High School FM-200218138 02 3/26/03 Browne Boiler Room Replace 1- 1/4" leaking copper line approximately 4 ft. Needs to be replaced. September 23, 2002 March 26, 2003 184 days
Nalle Elementary School FM-200215691 02 3/26/03 Nalle Boiler room 1. Asbestos assessment required. 2. Replace air separator per Alex Colvin. School will be without heat prior to completion of task. Asbestos Code A - Clear for repairs on 08/28/02. Horne Engineering - Philp Connolly (RG 08/28/02) August 27, 2002 March 26, 2003 211 days
Browne Junior High School FM-200219468 /02 3/26/03 !! Emergency !! Browne Boiler Room Repair ruptured waste line in boiler room. 4' cast iron October 16, 2002 March 26, 2003 161 days
Oyster Elementary School FM-200224836 03 3/26/03 Oyster E.S Boiler Room First Floor Motor and pump for boiler #1 need replacing. Bell Gossett Part # 903583, Model-7VA48T1701 64D-P, FR-48Y,PH-3,Type-T.S Hz-60,HP-3/4,RPM-1725 Volts 208-230/460 January 29, 2003 March 26, 2003 56 days
Oyster Elementary School FM-200224179 03 3/26/03 OYSTER SCHOOL boiler room " NO HEAT" Correct existing computerized problems relating to Boiler # 1 will not respond properly, preventing # 2 boiler from engage/heatiing/starting. January 19, 2003 March 26, 2003 66 days
Browne Junior High School FM-200224643 03 3/26/03 Browne Boiler Room Repair leaking circulating pump #2, Pump is leaking at mechanical seal. January 27, 2003 March 26, 2003 58 days
Kramer Middle School FM-200222166 02 3/26/03 Kramer Boiler #2 and # 3 Boiler #2 and #3 flame failure. December 9, 2002 March 26, 2003 107 days
Orr Elementary School FM-200220178 /02 3/26/03 Asbestos assessment mayby required. Repair leaking tubes or leaking mud leg on # 1 boiler . This 2 of 2 boiler that are down, building has no heat. Asbestos Code A - Clear for repairs on 10/29/02. Horne Engineering - Sheryll James (RG 10/30/02) October 29, 2002 March 26, 2003 148 days
Kramer Middle School FM-200220364 /02 3/26/03 Kramer Boiler Room Replace leaking tubes in Boiler #2 October 31, 2002 March 26, 2003 146 days
Nalle Elementary School FM-200226774 03 3/26/03 Nalle Boiler Room Survey feed tank vent pipe in area, vent pipe need to be vented outside of boiler room steaing boiler and area were tank at. March 9, 2003 March 26, 2003 17 days
Kramer Middle School FM-200220098 /02 3/26/03 Kramer Boiler Room 1-Asbestos assessment required 2-Replace 2" copper pipe on domestic hot water tank. (1) 2'X1" pipe; (2) 3" pipe, both pipes are corrsion and leaking. EMGERENCY!!!! October 28, 2002 March 26, 2003 149 days
Orr Elementary School FM-200223731 03 3/26/03 ORR boiler room "URGENT" "NO HEAT THE ONLY ONE OF TWO BOILERS OPERATE" Resolve problem with boiler # 2 will not start out on flame failure. January 13, 2003 March 26, 2003 72 days
Harris, C.W. ES FM-200225940 03 3/26/03 C.W.Harris Boiler room Repair # 3 boiler it off on safety (P3 open) February 20, 2003 March 26, 2003 34 days
Takoma Educational Center FM-200126630 02 3/26/03 TAKOMA BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE RELIEF VALVES ON BOILERS #1 & 2. CAN NOT RECEIVE CHEMICALS UNTIL VALVES ARE REPLACED. MODEL # "M" 98170, SIZE 2, INLET 2-1/2" OUTLET, SET 30 LBS., 5,250,000 BTU, MAKE WATTS ASBESTOS CODE A-CEAR FOR REPAIR ON 1/04/01 BY HORNE ENGINEER: SAM EBRAHIM January 3, 2002 March 26, 2003 447 days
Terrell Mc ES FM-200222482 /02 3/26/03 Terrell,M.C. Boiler Room Check boiler #2 burner keep cutting off on flame failure. Will run but cut off after complete cycle. December 13, 2002 March 26, 2003 103 days
Payne Elementary School FM-200225677 03 3/26/03 Payne Boiler Room Check on Boiler 1 and 2, when starting up both boilers they are making loud noises. February 12, 2003 March 26, 2003 42 days
Green Elementary School FM-200205338 02 3/26/03 Green School Boiler Room Repair AC unit, Unit has to be reset when it goes off in temperature. Unit was previously checked and service AWP for repairs. See Re: service order number FM-200110492 service order was closed out work was not completed. April 3, 2002 March 26, 2003 357 days
Takoma Educational Center FM-200218809 02 3/26/03 Takoma E.S Boiler Room Start up burners and test safety controls on specified boilers. October 3, 2002 March 26, 2003 174 days
Takoma Educational Center FM-200220759 /02 3/26/03 TAKOMA SCHOOL BOILER ROOM CHECK OPERATION OF DOMESTIC H/W CIRCULATING PUMP (BURNT OUT). November 13, 2002 March 26, 2003 133 days
Takoma Educational Center FM-200222517 /02 3/26/03 Takoma Boiler Room In line circulating pump (heating) AHU #4 pump missing (No information) Note: Pump was removed by HVAC Shop December 13, 2002 March 26, 2003 103 days
Kramer Middle School FM-200219728 /02 3/26/03 Kramer Boiler Room Repair/Replace city water make up tank float. Float is sticking,must hand feed water into Boilers. October 21, 2002 March 26, 2003 156 days
Bunker Hill Elementary School FM-200224185 03 3/26/03 Bunker Hill Boiler Room Boiler #1 Repair or replace condensate return pump. January 21, 2003 March 26, 2003 64 days
Bunker Hill Elementary School FM-200219993 /02 3/26/03 Bunker Hill Boiler Room Asbestos assessment required Replace crack section in # 2 boiler ,# 1 awaiting inpsection from D.C. inspector. Asbestos Code A - Clear for repairs on 10/25/02. Horne Engineering - Philp Connolly (RG 10/28/02) October 25, 2002 March 26, 2003 152 days
Wilson High School FM-200219436 /02 3/26/03 Wilson,W Boiler Room Replace mudulating motor on burner #1 Boiler. October 16, 2002 March 26, 2003 161 days
Dunbar High School FM-200202367 02 3/26/03 DUNBAR BOILER ROOM REPAIR OR REPLACE COMPRESSOR #1. COMPRESS LEAKS OIL BADLY AND TRIPS BREAKER WHEN IN USE. WORTHINGTON, MG. #JBEENH1A9, SER. #EE 299, SIZE 4-7/8 X 14-7/8 X 2-1/8. February 4, 2002 March 26, 2003 415 days
Bowen Elementary School FM-200220409 /02 3/26/03 Bowen Boiler Room Asbestos assessment required Repair leaks in tunnel losing steam pressure thoughout system. Asbestos Code A - Clear For Repair on 11/04/02. Horne Engineering - Phillip Connolly ( RG 11/05/02 ) October 31, 2002 March 26, 2003 146 days
Bowen Elementary School FM-200219350 /02 3/26/03 Asbestos assessment required Locate and repair leak in # 2 boiler. Asbestos Code A-clear for repair by Horne Engineer phillip Connolly on 11/12/02 DCPS Charles E Buchanan October 15, 2002 March 26, 2003 162 days
Tyler Elementary School FM-200207629 02 3/26/03 Tyler Boiler room Cut broken nipple out of #2 boiler. May 13, 2002 March 26, 2003 317 days
Dunbar High School FM-200225234 03 3/26/03 Dunbar Roof top Retube boilers#1,#2 and #3 February 5, 2003 March 26, 2003 49 days
Shaw JHS FM-200127290 02 3/26/03 SHAW BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPLACE (8) SAFETY VALVES ON BOILER #1 & #2. 2 EA - 3 X 3 SIZE; 15 PSI; 6843 LB/HR 4 EA - 2-1/2 X 2-1/2; 15 PSI; 4676 LB/HR. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 BY HORNE ENGINEER: STEPHEN CALSWELL January 11, 2002 March 26, 2003 439 days
Hyde Elementary School FM-200221286 /02 3/26/03 Hyde Boiler Room Repair or Replace #2 feed water pump for #2 boiler. The seal are leaking Model # J # 05 A Ser. 0010040381 Hp-1-3 RPM 3450 November 19, 2002 March 26, 2003 127 days
Shaw JHS FM-200203721 02 3/26/03 Shaw Boiler room 1. Asbestos assessment required. 2. Replace 10" butterfly valve on hot/chill water line located over chiller. Valve leaks on light fixture and chiller creating fire hazard. CODE A- CLEAR FOR REPAIR BY HORNE ENGINEER( SHARON VOSS ) ON3/01/02 (CEB) February 28, 2002 March 26, 2003 391 days
Brent Elementary School FM-200208813 02 3/26/03 Brent Boiler room Boiler #2 has nine (9) leaking tubes, need replacing. Asbestos Code A - Clear for repairs on 06/04/02. Horne Engineering - Donald Maglienti (RG) June 3, 2002 March 26, 2003 296 days
Wilson High School FM-200201760 02 3/26/03 W. WILSON BOILER ROOM 2ND LEVEL MAKE NECESSARY REPAIRS TO BRUNER CORPORATION WATER CONDITIONING EQUIPMENT; MODEL NO. BD-120, SERIAL NO. B-0791000-E AND B-0791000-I. NO ASBESTOS IN THIS AREA. January 25, 2002 March 26, 2003 425 days
Bunker Hill Elementary School FM-200127252 02 3/26/03 BUNKER-HILL BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. 2. REPAIR OR REPLACE WHAT APPEARS TO BE A LEAKING SECTION IN BOILER #1. ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 BY HORNE ENGINEER: PHILIP CONNOLY January 10, 2002 March 26, 2003 440 days
Bruce-Monroe Elementary School FM-200227591 03 3/27/03 Bruce-Monroe Boiler Room P.M Chiller March 25, 2003 March 27, 2003 2 days
Dunbar High School FM-200227589 03 3/27/03 Dunbar Boiler Room P.M Chiller March 25, 2003 March 27, 2003 2 days
Eastern High School FM-200226744 03 3/27/03 Eastern Female locker room / boiler room Repair roof leak, water coming from roof above boiler room. Leaking badly into locker room. March 7, 2003 March 27, 2003 20 days
Langdon Elementary School FM-200227582 03 3/27/03 Langdon E.S Boiler Room 1. Invistigate problem with burner being down on flame failure (School is without heat) March 25, 2003 March 27, 2003 2 days
Clark Elementary School FM-200227416 03 3/28/03 CLARK Boiler room 1. Asbestos assessment needed. Areas for assessment are marked by HVAC shop 2. Replace two (2) 5" O S & Y valves and (2) two 5" butterfly valves on chill water and condenser lines. Asbestos Code A - Clear for repairs on 03/24/03. Horne Engineering - Troy Wilcome (RG 03/25/03) March 21, 2003 March 28, 2003 7 days
Thomas Elementary School FM-200225564 03 3/30/03 Nevel Thomas Boiler Room P.M Chiller February 11, 2003 March 30, 2003 47 days
Turner Elementary School FM-200227981 03 4/2/03 Turner Groung floor old bldg. Change lock on storage room doorin boiler room. April 1, 2003 April 2, 2003 1 day
Patricia R Harris Ed Center FM-200227829 03 4/2/03 HARRIS, P. R. boiler room Replace one (1) 3" tube leaking in hot water boiler # 1. March 28, 2003 April 2, 2003 5 days
Hart Middle School FM-200120953 01 4/3/03 HART ENGINEER OFFICE/STORAGE 1.REPLACE EXISTING MORTIS CYL. LOCK ON ENGINEER OFFICE DOOR TO PRIMUS OR NONDUPLICATED KEY WAY. 2. INSTALL DEAD BOLT OR MORTIS CYL. LOCK ON STORAGE ROOM. 3. REKEY PRIMUS RIM CYLINDER WITH PANIC DEVICE ON BOILER ROOMS EXIT DOOR. ACTION REQUIRED TO SECURE OPERATING EQUIPMENT, SUPPLIES AND TO STOP UNAUTORIZED PERSONNEL DUPLICATION WITH SCHLAGE KEY TRAVEL IN RESTRICTED AREA. October 3, 2001 April 3, 2003 547 days
Ferebee-Hope Elementary School FM-200205689 02 4/3/03 Ferebee-Hope Boiler room Replace two: 2" ft -75 and ft - 125 Sarco Therostatic steam trap 125 psi, for man converters. April 10, 2002 April 3, 2003 358 days
Patricia R Harris Ed Center FM-200223495 03 4/3/03 P. R. HARRIS BOILER ROOM ASBESTOS ASSESTMENT REQUIRED REPLACE VENT VALVE ON CHILLEDWATER AIR SEPARATOR Asbestos Code A - Clear for repairs 01/06/03. Horne Engineering - Bipin Nanavaty (RG 01/07/03) January 3, 2003 April 3, 2003 90 days
Woodson High School FM-200228099 03 4/3/03 W.D Woodson Boiler room Replace B&G domestic hot water circulating pump in the boiler room , the pump is frozen and there is no hot water to the kitchen. April 2, 2003 April 3, 2003 1 day
Emery Elementary School FM-200223398 03 4/4/03 Emery Boiler room Correct problem with # 2 boiler burner electrical problem will not start. January 1, 2003 April 4, 2003 93 days
Eastern High School FM-200221227 /02 4/7/03 Eastern Sub-basement - boiler room Two (2) sets of keys need to be made for new staff members. approx. thiry (30) keys November 18, 2002 April 7, 2003 140 days
Maury Elementary School FM-200226779 03 4/7/03 Maury - Boiler Room 1. Asbestos assessment required 2. Hard wire newly installed condensate return tank POC: Curtis Emerson (202) 438-7434 Asbestos Code A - Clear for repairs on 03/10/03. Horne Engineering - Donald Maglienti (RG 03/11/03) March 10, 2003 April 7, 2003 28 days
Wilson High School FM-200226491 03 4/7/03 Wilson, W. Tunnel by the boiler pump room Electrical domestic hot water tank is not working. March 4, 2003 April 7, 2003 34 days
Shepherd ES FM-200228438 03 4/8/03 Shepherd Boiler Room Check Boiler #1 and #2, cut off on low water when in operation. April 8, 2003 April 8, 2003 0 days
Spingarn High School FM-200227051 03 4/8/03 Spingran Boiler Room Replace 1 1/2" line to return tank line is leaking in Boiler room March 14, 2003 April 8, 2003 25 days
Payne Elementary School FM-200227447 03 4/8/03 PAYNE boiler room Replace existing exterior boiler room boiler lock wiith New one Asbestos Code A-clear for repair by DCPS on 04/07/03 Charles Buchanan March 21, 2003 April 8, 2003 18 days
Deal Junior High School FM-200228329 03 4/8/03 Deal JHS Boiler Room Basement Repair condensater return pump #2 condensate pump #2 will not cut off ater condensate tank is empty. Pump keeps running April 4, 2003 April 8, 2003 4 days
Randle-Highlands ES FM-200223998 03 4/9/03 Randle Highland Furnish keys to engineer for new addition boiler room for access to check building for heat. NOTE: Coil rupture this morning. Engineer could not enter building until custodian arrived. Asbestos Code A - Clear for repairs on 01/15/03. DCPS Safety - Richard Gibson (RG) January 15, 2003 April 9, 2003 84 days
Smothers ES FM-200228432 03 4/9/03 Smothers Boiler Room Check condensate pumps, pumps not working. Have to hand feed water into Boilers. April 8, 2003 April 9, 2003 1 day
Brookland Elementary FM-200224765 03 4/9/03 Brookland Boiler room door Cut 2 pass key for the boiler room door. Asbestos Code A-clear for repair by DCPS on 03/05/03 Charles Buchanan January 29, 2003 April 9, 2003 70 days
Benjamin Banneker Academic HS FM-200226132 03 4/10/03 Banneker Boiler Room Repair or replace domestic hot water heater. No hot water in Building. February 25, 2003 April 10, 2003 44 days
Cook J.F. Elementary School FM-200227736 03 4/10/03 Cook, J.F. 1st Floor Hallway Furnish and install security cage over thermostat, so building staff can not control operation of boilers March 27, 2003 April 10, 2003 14 days
Browne Junior High School FM-200226637 03 4/10/03 Browne Boiler Room Repair multi-stack air condition uniit in browne boiler room, unit will not come on after power failure on 8-18-02 March 6, 2003 April 10, 2003 35 days
School WW High School FM-200227968 03 4/10/03 School W/O Walls Boiler room Repair or replace Ruptured 1 1/2" line (pin hole on the hartford loop) on the # 1 boiler April 1, 2003 April 10, 2003 9 days
Woodson High School FM-200227967 03 4/10/03 H.D. Woodson Boiler room Repair or replace # 4 sump pump in the boiler room unit is not pumping. April 1, 2003 April 10, 2003 9 days
Stevens Elementary School FM-200227966 03 4/10/03 Stevens Boiler room Unstop floor drain between # 1 and # 2 boilers . April 1, 2003 April 10, 2003 9 days
Brookland Elementary FM-200228272 03 4/10/03 Brookland Boiler room Repair electrical short on # 1 boiler,circuit breaker tripps when boiler is tured on. April 4, 2003 April 10, 2003 6 days
Garfield ES FM-200227576 03 4/11/03 Garfield Boiler Room Check domestic hot water heater, No hot water in Building. March 25, 2003 April 11, 2003 17 days
Brent Elementary School FM-200227964 03 4/14/03 Brent Boiler room area Replace 3/4" gate valve that feeds water to the cooling tower, the valve is broke in the closed position, and is needed to fill the cooling tower. April 1, 2003 April 14, 2003 13 days
Kramer Middle School FM-200228665 03 4/16/03 Kramer Boiler room Repair # 1 burner , burner starts up and runs for two minutes then cuts off .can not build up any steam pressure, fire eye has been cleaned. #2 and #3 boiler down also. April 11, 2003 April 16, 2003 5 days
Shaw JHS FM-200222136 02 4/21/03 Shaw JHS Basement !!! EMERGENCY !!! Asbestos Assestment Required Repair ruptured condensation 3"inch. line located above boiler #1. Asbestos Code A - Clear for repairs on 12/06/02. Horne Engineering - Bipin Nanavaty (RG 12/09/02) December 6, 2002 April 21, 2003 136 days
Bruce-Monroe Elementary School FM-200228080 03 4/23/03 Bruce - Monroe Boiler room Replace (2) two 8" vibrator eleminator on the condenser pump. April 2, 2003 April 23, 2003 21 days
Patricia R Harris Ed Center FM-200228558 03 4/23/03 Harris,P.R. Boiler Room-Ground Floor Repair or replace refractory material inside of fire box of Boilers #1, #2 and #3. April 10, 2003 April 23, 2003 13 days
Shaw JHS FM-200328997 03 4/24/03 Shaw Boiler Room Repair carrier A/C chiller will not start. "High motor temperature". April 24, 2003 April 24, 2003 0 days
Ferebee-Hope Elementary School FM-200328970 03 4/25/03 Ferebee Hope Pool Room First Floor Working on heating problem with Mr. Lancaster Boiler will not stary on. April 23, 2003 April 25, 2003 2 days
Janney Elementary School FM-200227737 03 4/29/03 Janney Boiler Room Replace leaking steam gasket on main steam header valve. Leaking very bad. 8 inch header valve gasket. March 27, 2003 April 29, 2003 33 days
Woodson High School FM-200226613 03 4/29/03 H.D. Woodson Boiler Room Replace /Repair bad alternating float control switch for sump pump. March 5, 2003 April 29, 2003 55 days
Park View ES FM-200201037 02 4/30/03 PARK VIEW TUNNEL LEADING FROM BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED 2. REPAIR BUSTED STEAM LINE. EMERGENCY POC: JOHN AGNEW (PVT-202 438-7456) ASBESTOS CODE A-CLEAR FOR REPAIR ON 1/15/02 BY HORNE ENGINEER: RAY AGNANT January 14, 2002 April 30, 2003 471 days
Orr Elementary School FM-200329100 03 4/30/03 Orr Boiler Room Welder needed to spot weld supoabeara and casing on A.H.U. #1 in Boiler Room April 28, 2003 April 30, 2003 2 days
Benning Elementary School FM-200329234 03 4/30/03 Benning Boiler Room Replace 2" check valve on domestic hot water storage tank, valve is not holding allowing hot water to enter comodes and cooling tower. April 30, 2003 April 30, 2003 0 days
Garfield ES FM-200227372 03 4/30/03 GARFIELD Boiler room Weld relief valves pull chains bracket on top of boiler # 1 (No insulation to be remove) March 20, 2003 April 30, 2003 41 days
Eliot Junior High School FM-200228560 03 4/30/03 Eliot Boiler room Repair #3 burner will not start, off on Lockout #29 April 10, 2003 April 30, 2003 20 days
Shaed Elementary School FM-200329101 03 5/1/03 Shaed Boiler room (URGENT) Pump Water out of flooded boiler room (cause failed sump pumps) April 28, 2003 May 1, 2003 3 days
West Elementary School FM-200329129 03 5/1/03 West Boiler Room Check air condition, oil pressure light is on. April 28, 2003 May 1, 2003 3 days
Ronald H. Brown MS FM-200225966 03 5/4/03 BROWN, RON boiler room Repair burner # 5 out on flame failure - "false flame" will not come on line after numerous resetting attempts. February 21, 2003 May 4, 2003 72 days
Peabody Elementary School FM-200203114 02 5/5/03 PEABODY BOILER ROOM Close two holes in boiler room. Hole size 5 x 5. Needs to be closed up as soon as possible. Bricklayer needed. February 19, 2002 May 5, 2003 440 days
Orr Elementary School FM-200202494 02 5/6/03 ORR SCHOOL BOILER ROOM REPLACE BEARING ON AIR HANDLER UNIT #2 NAME-TRANE CLIMATE, TYPE M63, SERIAL-K3A229416, OPERATIONAL BALANCE A-6 February 5, 2002 May 6, 2003 455 days
Woodson High School FM-200329459 03 5/7/03 H.D.Woodson Boiler room Replace Leaking tubes is the # 2 boiler,the firebox is filled with water, this boiler was used to heat domestic hot water. May 5, 2003 May 7, 2003 2 days
Terrell Mc ES FM-200123651 /01 5/8/03 M.C. TERRELL BOILER ROOM FURNISH HVAC STOP WITH (4) 8" 8 BOLT OS&Y VALVE FOR CONDENSER AND CHILL WATER LINE ON CHILLER. VALVES ARE NOT HOLDING. November 20, 2001 May 8, 2003 534 days
Orr Elementary School FM-200329402 03 5/8/03 ORR boiler room EMERGENCY SAFETY HEALTH Problem Replace existing exhaust pipe on generator with 40 - 50 ft of additional piping to directing fumes away from inside of school. Or relocated existing generator to outside location. May 2, 2003 May 8, 2003 6 days
Smothers ES FM-200214468 02 5/9/03 Smothers F-603.1 Fire Code Violation Boiler Room Replace missing stairs on outside. August 14, 2002 May 9, 2003 268 days
Shaed Elementary School FM-200329833 03 5/9/03 Shaed Boiler room Replace 3/8" pressure gauge that broken off in the pipe well on the condenser pump,this is needed for operation of A/C unit. May 9, 2003 May 9, 2003 0 days
Whittier Elementary School FM-200204025 02 5/12/03 Whittier Tunnel near boiler room 1. Asbestos assessment required. 2. Repair 1" steam line in tunnel west end of tunnel/outside of boiler room. Code-A clear for repiar by Horne Engineer ( Edward Rodriguez ) 3/08/02 CEB March 7, 2002 May 12, 2003 431 days
Eliot Junior High School FM-200104099 01 5/12/03 Eliot Boiler Room Replace condensate pump #2. February 21, 2001 May 12, 2003 810 days
Bancroft Elementary School FM-200225593 03 5/12/03 Bancroft Boiler Room Basement Make proper adjustment to float control that regulates solenoid valve on city water make up line to condensate return tank. The make up water is needed when the condensate does nit return fast enough to supply boiler operation. Tryed to make adjustments, but with little success February 11, 2003 May 12, 2003 90 days
Hart Middle School FM-200123186 01 5/13/03 HART BOILER ROOM REPLACE I.D. FAN MOTOR ON #2 BOILER. November 9, 2001 May 13, 2003 550 days
Woodson High School FM-200330222 03 5/15/03 H.D Woodson Boiler Room Basement Replace hot water circulating pump and adjust aquastat higher May 15, 2003 May 15, 2003 0 days
Stoddert ES FM-200330045 03 5/15/03 (Stoddert) Boiler room/Tunnel: Repair busted cold water pipe in the tunnel. May 12, 2003 May 15, 2003 3 days
Hardy Middle School FM-200329032 03 5/15/03 Hardy Basement - boiler room Outside of boiler room drain is stopped up. Drain needs to be re-open. April 24, 2003 May 15, 2003 21 days
Hardy Middle School FM-200330259 03 5/16/03 Rosario (Hardy) Boiler Room Repair or replace sump pumps. Pump #1 in hand position and Pump #2 will not come on. EMERGENCY : If not repair may cause Boiler Room to flood. May 16, 2003 May 16, 2003 0 days
Eaton Elementary School FM-200330079 03 5/19/03 Eaton Boiler room #1 chiller compressors need repair/replacement. #1 will not start , needs charging with freon. Type Trane a/c units. EMERGENCY!!!!!!!! May 13, 2003 May 19, 2003 6 days
Ballou Senior High School FM-200330301 03 5/19/03 Ballou Boiler Room Replace (1) one Honeywell Programeron #2 Boiler. Information: Honeywell Microcomputer Burner control system BC 7000L1000 120V 60HZ. May 19, 2003 May 19, 2003 0 days
Benning Elementary School FM-200214522 02 5/19/03 Benning Boiler room Repair a/c chiller. Down due to power outage August 15, 2002 May 19, 2003 277 days
Hyde Elementary School FM-200226599 03 5/22/03 Hyde Boiler Room Asbestos Survey Is Required Replace two faulty 3/4" gate valve city water valve and by pass valve to boiler #1 they aren't holding . Water is seeping through and filling up boiler. Asbestos Code A - Clear for repairs on 03/07/03. Horne Engineering - Troy Wilcome (RG 03/10/03) March 5, 2003 May 22, 2003 78 days
Deal Junior High School FM-200330414 03 5/23/03 Deal Boiler Room Tunnel Repair or replace busted 1 inch nipple on blow down connecting back on 3 inch return condensate line. 1 inch nipple was connected on the 3 inch line. For blowing down condensate and air out. May 20, 2003 May 23, 2003 3 days
Woodson High School FM-200225859 03 5/26/03 Woodson,H.D. Boiler room Asbestos assessment required Replace leaking tubes in the # 1 boiler (engineer will identify) Asbestos Code A - Clear for repairs on 02/19/03. Horne Engineering - Bipin Nanavaty (RG 02/20/03) February 14, 2003 May 26, 2003 101 days
Coolidge High School FM-200330325 03 5/27/03 (Coolidge) !!!VERY URGENT!!! Outside boiler room/Window well: Stopped up drains, causing water to come in-to the building, at the the window well, flooding the area: May 19, 2003 May 27, 2003 8 days
Whittier Elementary School FM-200330258 03 5/28/03 Whittier Outside boiler room steps Large overhead metal grate leading to boiler room need to be reattached. May 16, 2003 May 28, 2003 12 days
Raymond Elementary School FM-200330638 03 5/28/03 Raymond Boiler Room Furnish (1) cutler hammer motor starter for condenser pump to chiller. May 23, 2003 May 28, 2003 5 days
Browne Junior High School FM-200330798 03 5/28/03 Browne Jr.High Boiler room and electric room (URGENT) Pump water out of flooded boiler room and electric room. May 28, 2003 May 28, 2003 0 days
Shaw JHS FM-200228920 03 5/30/03 Shaw Boiler Room Boiler #3 need leaking tubes replace April 22, 2003 May 30, 2003 38 days
Walker-Jones EC FM-200330881 03 5/31/03 Walker-Jones Boiler Room First Floor Repairecd hot water heater for kitchen May 29, 2003 May 31, 2003 2 days
Ronald H. Brown MS FM-200220420 /02 6/2/03 Brown,Ron Boiler Room Furnish key to outside boiler room door October 31, 2002 June 2, 2003 214 days
Kenilworth ES FM-200331086 03 6/4/03 Kenilworth Boiler Room Replace sump pump in Boiler room, pump is not working and boiler room will be flooded if pump not replace. June 3, 2003 June 4, 2003 1 day
Brookland Elementary FM-200331166 03 6/4/03 Brookland Boiler room Start Multistack unit off on awaiting for External interlock #4 June 4, 2003 June 4, 2003 0 days
Davis Elementary School FM-200225075 03 6/5/03 Davis Auditorium and boiler room Change the two lobby auditorium doors and two boiler room doors to master keys locks. Need to keep childred out of maintenance staff office and out of auditorium doing special cleaning projects. February 3, 2003 June 5, 2003 122 days
Leckie Elementary School FM-200330785 03 6/5/03 REPAIR/REPLACE TUBE(S)/SHELL Replace two (2) leaking tubes in boiler # 1 and one (1) leaking tube in boiler # 2 . both lare leaking inside of firebox size: 3 inch tube. May 28, 2003 June 5, 2003 8 days
Bancroft Elementary School FM-200331407 03 6/6/03 (Bancroft) Third floor Room 322, health suite and boiler room near grates Replace doors. June 6, 2003 June 6, 2003 0 days
Coolidge High School FM-200331294 03 6/7/03 Coolidge SHS Boiler Room Ground Floor Survey tunnel for possible leaks on city water line, outside air ways and window seals. June 5, 2003 June 7, 2003 2 days
Montgomery ES FM-200228901 03 6/10/03 Montgomery Boiler Room Furnish relief valve, Serial # 97170; No.740; Size 1 inch; Set 30 lbs. BTU,HR Rating 1,300,000 April 21, 2003 June 10, 2003 50 days
Raymond Elementary School FM-200330893 03 6/10/03 Raymond Boiler Room Correct flow problem on condenser side of cooling system May 29, 2003 June 10, 2003 12 days
Bruce-Monroe Elementary School FM-200224835 03 6/11/03 Bruce-Monroe Old Building Boiler Room Electric panel that supply lights and electric for #3 boiler. No power corrective action needed. January 29, 2003 June 11, 2003 133 days
Thomas Elementary School FM-200330784 03 6/11/03 REPAIR/REPLACE TUBE(S)/SHELL Leaking tube/s in boiler # 2 tube is marked May 28, 2003 June 11, 2003 14 days
Reed LC FM-200330244 03 6/11/03 Reed Boiler Room Repair turbo power gas hot/water heater. Model #500 Phe 75 ATP; Serial # 109896081 EMERGENCY!!!! May 16, 2003 June 11, 2003 26 days
Clark Elementary School FM-200331645 03 6/12/03 Clark Boiler Room Check A/C for Low refrigerant temperature, keep cutting. June 12, 2003 June 12, 2003 0 days
West Elementary School FM-200331646 03 6/12/03 West Boiler Room Check A/C unit will not load up. June 12, 2003 June 12, 2003 0 days
Patricia R Harris Ed Center FM-200331534 03 6/12/03 Harris, P.R. Boiler Room Check expansion tank in Boiler Room. June 10, 2003 June 12, 2003 2 days
Brent Elementary School FM-200331709 03 6/13/03 Brent Boiler / Playground Check the motor on the cooling tower,motor seems to have lost a phase June 13, 2003 June 13, 2003 0 days
Young Elementary School FM-200331337 03 6/13/03 Young Boiler room roof Install guard rail around smoke stack near cooling tower on roof for safety. June 5, 2003 June 13, 2003 8 days
West Elementary School FM-200330892 03 6/13/03 West Boiler Room Basement Replace 1/4" x 4" nipple on chill water pump at pressure gage nipple is leaking very bad May 29, 2003 June 13, 2003 15 days
Brookland Elementary FM-200331815 03 6/16/03 Brookland Boiler Room Check and repair fan motors on chiller. June 16, 2003 June 16, 2003 0 days
Wilkinson ES FM-200331813 03 6/16/03 Wilkinson Boiler Room Repair rupture chill water line at bottom of chiller, line is about 3'' to 4''. Line has insulation. June 16, 2003 June 16, 2003 0 days
Wilson J. O. ES FM-200222984 /02 6/16/03 Wilson, J.O. Boiler, chair and storage rooms Replace cylinders to doors for security reasons. NOTE: Request that cylinders be keyed to new key system. December 20, 2002 June 16, 2003 178 days
Murch Elementary School FM-200331200 03 6/16/03 Murch Boiler Room (Tunnel) Repair or replace busted steam pipe, 3/4 X 40" long, Leaking very bad. Damaging walls and stairwell areas. Emergency!!!!!! June 4, 2003 June 16, 2003 12 days
Payne Elementary School FM-200331389 03 6/17/03 Payne Boiler Room Remove 2" nipples from in front of boiler #1 and #2. Engineers has try all source to remove nipples. June 6, 2003 June 17, 2003 11 days
Birney Elementary School FM-200331362 03 6/17/03 Birney Repair or replace manhole cover on boiler (size 11 x 15) Plate has a hole on side of it June 6, 2003 June 17, 2003 11 days
Gibbs Elementary School FM-200331830 03 6/17/03 Gibbs Boiler Room Check cooling tower fan, fan is not working. June 16, 2003 June 17, 2003 1 day
Benjamin Banneker Academic HS FM-200331363 03 6/17/03 Banneker Boiler room flooded. Repair inoperable sump pumps June 6, 2003 June 17, 2003 11 days
Ballou Senior High School FM-200225379 03 6/18/03 Ballou Boiler Room Asbestos assessment required Replace 2" X 3 ft. leaking feed water supply line to the expansion tank. Note: Expansion tank has to be drained to repair pipe. Asbestos Code A, clear for repairs on 02/14/03 DCPS Safety, R Edwards (RE) Abatement was conducted 02/13/03 by CATI Re-insulation will begin after pipeline iis repaired. February 7, 2003 June 18, 2003 131 days
Spingarn High School FM-200331827 03 6/18/03 Spingarn Tunnel Check tunnel flooded, water running into cafeteria area. Possible drain stopage in boiler room. No asbestos in tunnel. June 16, 2003 June 18, 2003 2 days
Gage-Eckington ES FM-200331931 03 6/19/03 Gage-Eckington Boiler room Spot well pin holes on 1 1/2" Condenser line for the Multistack unit. June 17, 2003 June 19, 2003 2 days
Gage-Eckington ES FM-200332188 03 6/20/03 Gage-Eckington Boiler Room Check chiller, chiller not working. June 20, 2003 June 20, 2003 0 days
Orr Elementary School FM-200331466 03 6/20/03 Orr Boiler Room Check and repair air compressor, will not build up pressure. June 9, 2003 June 20, 2003 11 days
Garfield ES FM-200226963 03 6/20/03 Garfield Boiler Room Asbestos assessment required, Remove asbestos from Boiler #1 and #2 door lining around tube sheet. Replace with appropriate lining. Asbestos Code A - Clear for repairs on 03/13/03. Horne Engineering - Sheryll James (RG 03/18/03) March 13, 2003 June 20, 2003 99 days
Shepherd ES FM-200332240 03 6/20/03 Shepherd Boiler Room Send burner technician with calibration instruments to properly calibrate burner (S) at all modulation levels on Boiler (S) No. #1. Note: When burner are not modulating properly, it creates big problem when cleaning boilers and reduce efficiency. June 20, 2003 June 20, 2003 0 days
Bell High School FM-200331930 03 6/20/03 Bell Boiler Room Check chiller, not working. June 17, 2003 June 20, 2003 3 days
Marshall Educational Center FM-200221983 02 6/23/03 Thurgood Marshall Boiler Room Repair the flow meter leaking in the boiler room Code A - clear for repairs as of 6/20/03, abatement completed verified by Ron Edwards. DCPS Sylvia Grimes. December 3, 2002 June 23, 2003 202 days
Terrell Mc ES FM-200332017 03 6/23/03 Terrell. M.C. Boiler Room Check air compressor motor, motor not during. No a/c on 3rd floor. June 18, 2003 June 23, 2003 5 days
Stuart-Hobson Middle School FM-200331295 03 6/23/03 Stuart Hobson Emergency !!! Third Floor, Second Floor, First Floor and Basement 1) Leaking down from the third floor bathroom. All the urnials are stopped up, can not use any of the boys bathrooms. Leak has flooded the storage room in the basement. When the toilet is flushed in the Boys Gym the water goes into the Boiler Room. Asbestos Code A - Clear for repairs on 06/05/03. Horne Engineering - Bipin Nanavaty (RG 06/05/03) June 5, 2003 June 23, 2003 18 days
Ferebee-Hope Elementary School FM-200329970 03 6/23/03 Ferebee-Hope Boiler Room Unclog (4) four floor drains, sewage backing up thur drains. Flood going into computer room. EMERGENCY!!!!!!!! May 9, 2003 June 23, 2003 45 days
Browne Junior High School FM-200227053 03 6/24/03 BROWNE Boiler Room Repair # 1 circulation pump will not start. May be caused from scheduled power outage. March 14, 2003 June 24, 2003 102 days
Benjamin Banneker Academic HS FM-200332405 03 6/25/03 Banneker Boiler Room Unstop (4") - 2" Floor drains. Water is going down slowly. Engineers,attempted to unstop with negative results. Boiler #3, water side needs to be drained for cleaning. HOT!!!!!! June 24, 2003 June 25, 2003 1 day
Johnson JHS FM-200332435 03 6/26/03 Johnson Jr. Boiler room Repair or replace condenser unit on the purge of the A/C unit June 25, 2003 June 26, 2003 1 day
Garfield ES FM-200330349 03 6/27/03 Garfield Boiler Room Replace five (5) leaking tubes in Boiler #2. Two (2) tubes leaking inside fire box. May 20, 2003 June 27, 2003 38 days
Johnson JHS FM-200332717 03 6/30/03 Johnson Boiler Room Check and unstop drains in boiler room to stop boiler room from flooding. June 30, 2003 June 30, 2003 0 days
Ballou Senior High School FM-200332656 03 6/30/03 "EMERGENCY" Ballou SHS Boiler Room Boiler Room Stopped up drain, backing up in boiler room *Need immediate attention* June 27, 2003 June 30, 2003 3 days
Thomas Elementary School FM-200332666 03 6/30/03 Thomas Boiler Room Resolve electrical problem with chill water circulating pump. June 30, 2003 June 30, 2003 0 days
Shepherd ES FM-200332487 03 7/1/03 Shepherd Boiler Room Check and unstop drain in Boiler Room. Boiler Room has water on floor, had to stop draining Boilers down. June 25, 2003 July 1, 2003 6 days
Winston EC FM-200332284 03 7/1/03 Winston Boiler Room Check and repair A/C unit. Reading low on refrigerate. Replace motor on cooling tower. June 23, 2003 July 1, 2003 8 days
Bancroft Elementary School FM-200331433 03 7/1/03 (Bancroft) 1st Floor/leading to outside near grates. Door will not close in the boiler room. Asbestos Code A - Clear for repairs on 06/09/03. Horne Engineering - Philp Connolly (RG 06/10/03) June 6, 2003 July 1, 2003 25 days
Green Elementary School FM-200332719 03 7/3/03 Green Boiler Room Repair or replace flow switch on condenser line, no condenser flow. June 30, 2003 July 3, 2003 3 days
Dunbar High School FM-200332443 03 7/7/03 Dunbar Boiler room \ Asbestos assessment required R/R ruptured 1 1/2" nipple and valve on DWH storage tank. Asbestos Code A - Clear for repairs on 06/25/03. Horne Engineering - Edward Rodriguez ( RG 06/27/03) June 25, 2003 July 7, 2003 12 days
Ronald H. Brown MS FM-200332510 03 7/8/03 Brown, Ron Boiler Room Replace ruptured disc on chiller. Recharge chiller. June 25, 2003 July 8, 2003 13 days
Burrville Elementary School FM-200330633 03 7/8/03 Burrville Replace (1) one leaking tube in boiler # 2. May 23, 2003 July 8, 2003 46 days
Tubman Elementary School FM-200332034 03 7/8/03 Tubman Boiler Room Remove hot water cap at top left side of #1 Boiler. We were unable to remove the cap ourselves. Also remove 1" plug on how water cut off water column to Boilers #1 & #2 June 18, 2003 July 8, 2003 20 days
Garfield ES FM-200330350 03 7/8/03 Garfield Boiler Room Replace one (1) leaking tubes in Boiler #1. May 20, 2003 July 8, 2003 49 days
Dunbar High School FM-200329209 03 7/8/03 Dunbar 5-East,Science Lab Water leaking from boiler down to classroom. Drain from Boiler need to be replace. April 29, 2003 July 8, 2003 70 days
Janney Elementary School FM-200332039 03 7/8/03 Janney Boiler Room Remove tow caps to two 3/4" check valves, They are located on the right top side of boiler #2 water column.We were unable to remove the caps ourselves. June 18, 2003 July 8, 2003 20 days
Seaton Elementary School FM-200222774 /02 7/10/03 Seaton Boiler Room Repair or rethread left side rear bottom blow down, retap. Asbestos Code A - Clear for repairs on 12/20/02. Horne Engineering - Edward Rodriguez (RG 12/20/02) December 18, 2002 July 10, 2003 204 days
Shaed Elementary School FM-200332396 03 7/10/03 Shaed Boiler Room Replace rupture line on house pump. June 24, 2003 July 10, 2003 16 days
Johnson JHS FM-200332652 03 7/10/03 Johnson Boiler room Replace Chiller oil pump and purge ,and ruptured 1/2 " line and valve .( ruptured line is located from chill water line cooling system) June 27, 2003 July 10, 2003 13 days
Woodson High School FM-200225731 03 7/11/03 H.D.Woodson boiler room Asbestos assessment required Repair leaking 1 1/2" return line on the # 1 boiler Asbestos Code A - Clear for repairs on 02/14/03. Horne Engineering - Philp Connolly (RG 02/19/03) February 13, 2003 July 11, 2003 148 days
Brookland Elementary FM-200332792 03 7/12/03 Brookland Boiler Room Furnish magnetic starter for cooling tower. Magnetic starter; CT3-32 Specher Schuh coil voltage: 110 Volt 50HZ, setting 22-32A,120 Volt, 60 HZ, IEC 947, EN 63947 IEC, Concond Tip 2" 5"PA. July 1, 2003 July 12, 2003 11 days
Malcolm X ES FM-200331990 03 7/14/03 MALCOLM X meter room near boiler room Restore electrical service to distribution panel for # 2 RTU June 17, 2003 July 14, 2003 27 days
West Elementary School FM-200221437 /02 7/14/03 West Boiler Room Basement Repair 1 1/4" copper gate valve restricted flow of domestic hot water, for kitchen area. Plumbers:French & Beckett working on problem November 20, 2002 July 14, 2003 236 days
Sousa Middle School FM-200333199 03 7/15/03 (Sousa) !!!VERY URGENT!!! 1.Boiler room door and Basement service entrance next to parking lot , Two (2) drains need to be unclogged. July 11, 2003 July 15, 2003 4 days
Brookland Elementary FM-200331444 03 7/16/03 Brookland Boiler room Restore electrical service to Multistack control pannel. June 9, 2003 July 16, 2003 37 days
Ferebee-Hope Elementary School FM-200332256 03 7/17/03 Ferebee-Hope Boiler Room Basement Unstop clogged floor drains (6) in all. June 20, 2003 July 17, 2003 27 days
Raymond Elementary School FM-200332497 03 7/17/03 Raymond Old Boiler Room Check and unstop drain in Old Boiler Room, water is on the floor because sump pumps not working properly. Asbestos Code A - Clear for repairs on 07/17/03. Horne Engineering - Sharon Voss (RG 07/17/03) June 25, 2003 July 17, 2003 22 days
Woodson High School FM-200331533 03 7/18/03 Woodson Boiler Room Repair or replace sump pumps #3 and #4, not working. Emergency !!!!! June 10, 2003 July 18, 2003 38 days
Ronald H. Brown MS FM-200333371 03 7/18/03 Brown,Ron Boiler Room Remove 1" Brass plug from cross-"T" on Boiler #2 AWF blow down line. Plug rounded off. Requested removal for Boiler inspection. July 17, 2003 July 18, 2003 1 day
Hine JHS FM-200331391 03 7/18/03 Hine Boiler Room Asbestos Assestment Required Repair or replace 2" chill water line above Boiler #2 right hand side. Asbestos maybe located on the line it is leaking very badly . Code A -clear for repairs as of 6/11/03 by DCPS Sylvia Grimes. Girls restroom above boiler room need toilet remove and valve is not holding. Re-Opened Exploratory Needed for Girls Bath Room on 1st Floor along with water line above Boiler #2. See Attached Map POC: Kingwood / Sylvia Grimes Asbestos Code A - Clear for repairs on 06/12/03. Horne Engineering - Philp Connolly (RG 06/16/03) Repairs were made by the Steamfitting Shop and it was cleared by Asbestos Assestment Management See information above. 1. Pipe has to be insulated 12" of 1 1/2 pipe (Safety) 2. Repair black wall in bathoom. 1st fl. girls bathroom (Grounds) 3. Replace toilet in 1st floor girls bathroom (Plumbers) June 6, 2003 July 18, 2003 42 days
Brookland Elementary FM-200331507 03 7/18/03 Brookland Boiler Room Check and restored electric to chiller, chiller does not has electric. June 9, 2003 July 18, 2003 39 days
Young Elementary School FM-200333445 03 7/21/03 Charles Young Boiler room Repair low oil condition on the chiller , the chiller is down. July 21, 2003 July 21, 2003 0 days
Payne Elementary School FM-200226395 03 7/21/03 Payne Boiler Room Connect 2" steam pipe line to condensate tank to well and steam line to pipe connect steam pipe to existence pipe in ceiling February 28, 2003 July 21, 2003 143 days
Green Elementary School FM-200333357 03 7/22/03 Green boiler room Remove 2 1/2" plug on # 1 boiler. July 17, 2003 July 22, 2003 5 days
Ballou Senior High School FM-200333404 03 7/22/03 Ballou Boiler Room Check A/C unit for refrigerant, low in refrigerant, need approximate. 100-Lbs. July 18, 2003 July 22, 2003 4 days
Shaw JHS FM-200333405 03 7/22/03 Shaw JHS Boilerroom Survey and repair central air condition unit. Unit cutting off due to low refrigerant temperature. July 18, 2003 July 22, 2003 4 days
Stanton Elementary School FM-200226721 03 7/22/03 Staton Annex Boiler Room Asbestos assessment required Demolation work in room A1 and A2 to carpet, glue,wood, concrete floor. To repair steam leak in crawl space under room A1 and A2 . Asbestos Code A - Clear for repairs on 03/07/03. Horne Engineering - Sharon Voss (RG 03/10/03) Note to Grounds : Repair concrete floor in room A2 March 7, 2003 July 22, 2003 137 days
Hine JHS FM-200330800 03 7/23/03 Hine Boiler room Repair # 1 York Chiller unit will not run, was worked on by boland trane 2002 and was said that the unit has a flow problem. Repair # 2 York Chiller, only 1 of 2 compressors will operate, unit cuts off on current. May 28, 2003 July 23, 2003 56 days
Browne Junior High School FM-200333229 03 7/24/03 Browne Boiler Room Repair 1 1/4" leaking line on feed water on cooling tower. July 14, 2003 July 24, 2003 10 days
Gibbs Elementary School FM-200333749 03 7/24/03 (Gibbs) !!!VERY URGENT!!! Boiler Room: Water building up; sump pump is not pumping water out; water has flooded the floor. July 24, 2003 July 24, 2003 0 days
Kenilworth ES FM-200331596 03 7/24/03 Kenilworth Repair/replace one (1) leaking tube in boiler # June 11, 2003 July 24, 2003 43 days
Gibbs Elementary School FM-200333745 03 7/25/03 "EMERGENCY" Gibbs Boiler Room Repair/Replace sump pumps boiler room is flooded. Structural Maintenance, Electrical Department Restore electrical service to sump pump in boiler room July 24, 2003 July 25, 2003 1 day
Bruce-Monroe Elementary School FM-200332354 03 7/28/03 Bruce- Monroe Boiler Room Send burner technician with calibration instruments to properly calibrate burner (s) at all modulation levels on boiler (s) No. #1 and No. #2. Note: When burning are not modulating properly it creates big problem when cleaning boilers and reduce efficiency. June 23, 2003 July 28, 2003 35 days
Gibbs Elementary School FM-200333821 03 7/28/03 Gibbs Boiler Room Repair domestic hot water heater. no hot water in Building. July 28, 2003 July 28, 2003 0 days
Bancroft Elementary School FM-200332353 03 7/28/03 Bancroft Boiler Room Send burner technician with calibration instruments to properly calibrate burner (s) at all modulation levels on boiler(s) No. #1 and No.#2 June 23, 2003 July 28, 2003 35 days
Beers Elementary School FM-200333729 03 7/28/03 Beers Boiler Room - Step Area 1) Contractors are working in the area and need light in order to work. July 24, 2003 July 28, 2003 4 days
Bell High School FM-200332246 03 7/29/03 Bell Boiler Room Boilers #1, #2 and #3 need burner technician with calibration instruments to properly calibrate burner (s) at all modulation levels. Note: When burner are not modulating properly, it creates bigs problem when cleaning boilers and reduce efficiency. June 20, 2003 July 29, 2003 39 days
Roosevelt High School FM-200225458 03 7/29/03 (Roosevelt) Boiler room: Repairs on thursday and friday - Trouble shoot loss of power to boiler room. February 10, 2003 July 29, 2003 169 days
Langdon Elementary School FM-200333244 03 7/29/03 Langdon Boiler room Recalibrate burner # 1 and # 2 , they are burning too rich, July 15, 2003 July 29, 2003 14 days
Benjamin Banneker Academic HS FM-200332244 03 7/29/03 Banneker Boiler Room Boilers #1, #2 and #3 need burners technican with calibration instruments to properly calibrate burner(s) at all modulating properly, it creates big problem when cleaning boilers and reduce efficiency. June 20, 2003 July 29, 2003 39 days
Benjamin Banneker Academic HS FM-200220522 02 7/29/03 Bannker Boiler Room Repair burner on Boiler #1. Boiler goes through its cycle, but will not start. Inoperable. November 1, 2002 July 29, 2003 270 days
Marshall Educational Center FM-200331458 03 7/29/03 T.Marshall Boiler Room Restore electricl service to chill water pump and pumps control pannel box , pannel box has water in it from the rain storm. ( This needed in order to operate the A/C unit) June 9, 2003 July 29, 2003 50 days
Johnson JHS FM-200333907 03 7/30/03 Johnson Boiler Room Check chiller, not power to unit. July 29, 2003 July 30, 2003 1 day
Spingarn High School FM-200331505 03 7/30/03 Spingran Boiler Room Install vacuum Return pumps to return condensate back from building to Boilers June 9, 2003 July 30, 2003 51 days
Ronald H. Brown MS FM-200333787 03 7/30/03 Brown, Ron Adjust controls (AWF & LWCO) for boilers # 4 burner controls will not make until make-up water is manually fed thur by pass. July 25, 2003 July 30, 2003 5 days
Spingarn High School FM-200331506 03 7/30/03 Spingran Boiler Room Install lckenvar hot water heater in boiler room to heat hot water tanks. So boilers will not need to be on to heat hot water. June 9, 2003 July 30, 2003 51 days
Montgomery ES FM-200218447 02 7/30/03 Montgomery Boiler Room Replace gas valve on gas train. Boiler #2 (Valve surveyed by B. Pearson) September 27, 2002 July 30, 2003 306 days
Anacostia Senior High School FM-200201743 02 7/31/03 ANACOSTIA BOILER ROOM REPLACE BALLAST IN BOILER ROOM WHERE NEEDED. UNIVERSAL-THERM-0-MATIC SERIES SLIMLINE BALLAST FOR TWO F96 OR F72/ & 12 SLIMELINE LAMPS 277 VOLTS 60 HERTZ. January 25, 2002 July 31, 2003 552 days
Burrville Elementary School FM-200333968 03 7/31/03 Burrville Boiler Room Cut-out 1 1/4" weldlet on Boiler #1 water leg and replace after metal scapes are removed from water leg per- request of Boiler Inspector. July 29, 2003 July 31, 2003 2 days
Burrville Elementary School FM-200333977 03 8/1/03 Burrville Boiler room Check chiller , it cuts off on low oil pressure. July 30, 2003 August 1, 2003 2 days
Ronald H. Brown MS FM-200334023 03 8/1/03 (Brown, Ron (Roper) !!!VERY URGENT!!! 1st Floor/Main Entry Door, and Boiler Room: Change locks on doors to the above area's due to change of staff; former personnel did not return keys on leaving. (Safety Issue) July 30, 2003 August 1, 2003 2 days
Turner Elementary School FM-200331889 03 8/1/03 Turner E.S. boiler room Replace relief valve on return line. Water constantly runs. WATTS, 50 #, #174-A, size 3/4" , 9,507,700 BTU, 965 in, June 16, 2003 August 1, 2003 46 days
King M L ES FM-200331814 03 8/4/03 KING boiler room Replace relief valve on # 1 boiler model - M 740 - 2 inch 30# BTU - 5,250,000 MFD - by WATTS June 16, 2003 August 4, 2003 49 days
Thomas Elementary School FM-200334197 03 8/4/03 Thomas Boiler Room No A/C, Summer School site. Check condenser pump, would not stay on line. August 4, 2003 August 4, 2003 0 days
Patricia R Harris Ed Center FM-200332392 03 8/4/03 Harris, P.R. Boiler Room Boiler #4 has 2 tubes leaking, tubes size is 7' 4" long by 3" diameter. June 24, 2003 August 4, 2003 41 days
Marshall Educational Center FM-200334338 03 8/5/03 Marshall parking lot/boiler room Check electrical service to chiller located on the parking lot, possible phase lost. August 5, 2003 August 5, 2003 0 days
Seaton Elementary School FM-200333832 03 8/5/03 Seaton Boiler Room Repair leak in 1" copper return line to hot water storage tank. July 28, 2003 August 5, 2003 8 days
Tubman Elementary School FM-200332657 03 8/6/03 Tubman Boiler Room Repair or replace(house air compressor). After unit has reached set pressure, it trips out causing roof top cooling unit that services multi-purpose area to shut down. June 27, 2003 August 6, 2003 40 days
Tubman Elementary School FM-200331699 03 8/6/03 Tubman Boiler Room Check air compressor, need air compressor to run A/C in cafeteria. June 12, 2003 August 6, 2003 55 days
Ballou Senior High School FM-200330304 03 8/8/03 Ballou Boiler Room Repair leaking rear water leg. Information: Boiler #2 Pacific Steel Hotwater Model #122040 Note: Loosing Hot-Water Daily. May 19, 2003 August 8, 2003 81 days
Takoma Educational Center FM-200332043 03 8/8/03 Takoma Boiler Room Repair or replace leaking tubes in boiler #2. Need to be done for inspection purposes. Tubes just need to be reroll three inch tubes. June 18, 2003 August 8, 2003 51 days
Woodson High School FM-200334735 03 8/10/03 H.D Woodon Boiler Room First Floor Installed temporary pump to pump water out of boiler room August 8, 2003 August 10, 2003 2 days
Anacostia Senior High School FM-200330652 03 8/12/03 Anacostia Boiler Room Refractory, brickwork need repaving, Boiler #2. May 23, 2003 August 12, 2003 81 days
Stoddert ES FM-200334979 03 8/13/03 Stoddert Boiler Room Boiler, replace main flame control switch. Failed D.C. Inspection. August 13, 2003 August 13, 2003 0 days
Anacostia Senior High School FM-200335112 03 8/14/03 Anacostia Boiler Room Check operation of Multi stack. Only 3 compressors responding. August 13, 2003 August 14, 2003 1 day
Anacostia Senior High School FM-200332621 03 8/15/03 Anacostia Boiler Room Basement Refractor, brick work need repaving boiler #1 June 27, 2003 August 15, 2003 49 days
Meyer Elementary School FM-200204483 02 8/18/03 Meyer Basement Boiler room Repair or replace circulating pump in back of boilers. 3/4 hp, 115/230 volt part #M80082 1.25 amp Bell & Gossett. March 15, 2002 August 18, 2003 521 days
Moten Elementary School FM-200335583 03 8/18/03 Moten Boiler room Replace Mcdonell-Miller Automatic water feeder on boiler #1 & #2, as per boiler inspector's request. August 18, 2003 August 18, 2003 0 days
Shaw JHS FM-200335598 03 8/18/03 Shaw J.H.S Boiler room Repair or replace sewage injector pumps infront of the boilers, motor is running but the pump is not discharging. August 18, 2003 August 18, 2003 0 days
Woodson High School FM-200332610 03 8/20/03 H.D. Woodson Boiler room Repair or replace (1) of (2) compressors needed for A/C operation. June 27, 2003 August 20, 2003 54 days
Woodson High School FM-200333433 03 8/20/03 Woodson Boiler Room Check #1 and #2 chiller, chiller keep cutting off. Had to reset approx. 10 times. Still having the same problem. July 18, 2003 August 20, 2003 33 days
Murch Elementary School FM-200334977 03 8/20/03 Murch Boiler Room Boiler #1,#2, #3, #4 & #5 replace automatic blow down, boilers failed D.C. Inspection. August 13, 2003 August 20, 2003 7 days
Woodson High School FM-200331882 03 8/20/03 Woodson Boiler Room Check compressor #1 and #2 on chiller, chiller down, no power. Dunhan Bush compressor. June 16, 2003 August 20, 2003 65 days
Payne Elementary School FM-200335975 03 8/21/03 Payne Boiler Room Boiler #2 need to be boiled out. August 21, 2003 August 21, 2003 0 days
Shaw JHS FM-200335798 03 8/21/03 Shaw J.H.S. Boiler room Check and recharge chiller. August 20, 2003 August 21, 2003 1 day
Woodson High School FM-200336034 03 8/21/03 Woodson Pool Pump/Boiler Room Added water to pool, work on pit pumos in boiler room with Booth. One pit pump is working now. Fuses were on site. August 21, 2003 August 21, 2003 0 days
Harris, C.W. ES FM-200335840 03 8/21/03 Harris,C.W. Boiler Room Replace automatic blow down valve. Fail D.C. Inspection. August 20, 2003 August 21, 2003 1 day
Leckie Elementary School FM-200332485 03 8/21/03 Leckie Boiler Room Requesting the remover of one 2" plug at botton of front tube sheet of boiler #1 and one 2" plug at bottom of front tube sheet of Boiler #2 for cleaning out purpose. June 25, 2003 August 21, 2003 57 days
Reed LC FM-200335807 03 8/21/03 Reed Boiler Room Check A/C unit, bad regulator. No chill water and no water in system. Serial # 92260 U5RLP Model #5M3 August 20, 2003 August 21, 2003 1 day
Savoy Elementary School FM-200335848 03 8/21/03 Savoy Boiler Room Replace automatic blow down valve. Fail D.C. Inspection. August 20, 2003 August 21, 2003 1 day
Browne Junior High School FM-200333425 03 8/21/03 Browne Boiler Room Replace twenty (20') ft of 2" leaking pipe in ceiling of Boiler Room. July 18, 2003 August 21, 2003 34 days
Webb Elementary School FM-200332858 03 8/21/03 Webb Boiler room Remove (2( two stripped galvinized inspection plugs on cross tee of the # 1 boiler. July 3, 2003 August 21, 2003 49 days
King M L ES FM-200333708 03 8/22/03 (King) FIRE CODE VIOLATION: 1st Floor/Exit Door: Exit light out near entrance to boiler room. July 23, 2003 August 22, 2003 30 days
Coolidge High School FM-200225932 03 8/22/03 Coolidge Ground Floor Boiler Room Office Asbestos assessment required Replace leaking 1 1/2" condensate return line embedded in ceiling in boiler room office. Asbestos Code A - Clear for repairs on 02/20/03. Horne Engineering - Bipin Nanavaty (RG 02/21/03) February 19, 2003 August 22, 2003 184 days
Simon Elementary School FM-200333641 03 8/22/03 (Simon) FIRE CODE VIOLATION: Ground Floor: Exit light out in hallway, near boiler room. July 22, 2003 August 22, 2003 31 days
Cooke H.D. Elementary School FM-200334993 03 8/25/03 Cooke, H.D. Boiler Room Boilers, replace automatic blow down. Failed D.C. Inspection. August 13, 2003 August 25, 2003 12 days
Takoma Educational Center FM-200336143 03 8/25/03 Takoma Boiler Room Boiler #1 and #2 Repair refractory around burner comb. August 25, 2003 August 25, 2003 0 days
Wilson High School FM-200334990 03 8/25/03 Wilson, W. Pump Room Repair or replace sump pump #1. Sump pump #2 was already down. Water in boiler room. Sump pump #2 work request number is FM-200227184 August 13, 2003 August 25, 2003 12 days
Slowe Elementary School FM-200335850 03 8/25/03 Slowe Boiler Room Replace automatic blow down valve. Fail D.C. Inspection. August 20, 2003 August 25, 2003 5 days
Cooke H.D. Elementary School FM-200335351 03 8/25/03 Cooke, H.D. Boiler Room Boilers #1, #2, and #3 replace automatic blow down valve on bottom blow down. August 15, 2003 August 25, 2003 10 days
Hardy Middle School FM-200335835 03 8/26/03 Hardy Boiler Room Replace automatic blow down valve. Fail D.C. Inspection. August 20, 2003 August 26, 2003 6 days
Malcolm X ES FM-200335856 03 8/26/03 Malcolm X Boiler Room Replace automatic blow down valve. Fail D.C. Inspection. August 20, 2003 August 26, 2003 6 days
Horace Mann Elementary School FM-200334980 03 8/26/03 Mann Boiler Room Boilers #1, #2 & #3 replace auto blow down. Boilers failed D.C.Inspection. August 13, 2003 August 26, 2003 13 days
Slowe Elementary School FM-200336253 03 8/27/03 Slowe Boiler Room Replace 1" feed water line to all 5 Boilers. August 26, 2003 August 27, 2003 1 day
Davis Elementary School FM-200335492 03 8/27/03 Davis First floor back boilerroom door Replace back boilerroom door locl cylinder to master key, we do not have key to old cylinder, ASAP. August 18, 2003 August 27, 2003 9 days
Ketcham Elementary School FM-200335842 03 8/28/03 Ketcham Boiler Room Replace automatic blow down valve. Fail D.C. Inspection. August 20, 2003 August 28, 2003 8 days
Browne Junior High School FM-200333927 03 8/29/03 Browne Exterior 1) Weld screen over top of air vents to tunnels. Cats have crawled into the tunnel and fleas are in Engineer office, Custodial office, Boiler room and tunnels. July 29, 2003 August 29, 2003 31 days
Benning Elementary School FM-200335374 03 8/30/03 Benning Boiler Room Correct problem with purge unit going off in fault on chiller. August 15, 2003 August 30, 2003 15 days
Whittier Elementary School FM-200335882 03 9/2/03 Whittier Boiler Room Remove 2" plugs from Boilers #1 and #2, at the bottom in front. Engineers can not remove plugs. One each needed before annual inspection. (Cleaning). August 20, 2003 September 2, 2003 13 days
Park View ES FM-200335844 03 9/2/03 Park View Boiler Room Replace automatic blow down valve. Fail D.C. Inspection. August 20, 2003 September 2, 2003 13 days
Clark Elementary School FM-200334976 03 9/2/03 Clark Boiler Room Boiler #1 Replace 1" gate valve on city feed water line, failed D.C. Inspection. August 13, 2003 September 2, 2003 20 days
Turner Elementary School FM-200336007 03 9/2/03 Turner Boiler Room Replace relief valve on return line, co. watts, 50 Lb. set, #174-A, Size 3/4" 9507700 BTU 965 in. Boiler Inspector. August 21, 2003 September 2, 2003 12 days
Watkins Elementary School FM-200335548 03 9/2/03 Watkins F-343.5 FIRE CODE VIOLATION Boiler room boiler room exit door defective. August 18, 2003 September 2, 2003 15 days
Seaton Elementary School FM-200330810 03 9/2/03 REPAIR/REPLACE TUBE(S)/SHELL Replace leaking tubes in boiler # 2. May 28, 2003 September 2, 2003 97 days
Ferebee-Hope Elementary School FM-200334675 03 9/2/03 Ferebee-Hope Boiler Room Check domestic hot water heater,seal on pump is leaking bad. August 8, 2003 September 2, 2003 25 days
Woodson High School FM-200336491 03 9/2/03 Woodson Boiler Room Repair or replace #3 and #4 sump pump, not working. August 28, 2003 September 2, 2003 5 days
Francis Junior High School FM-200335857 03 9/2/03 Francis Boiler Room Repair or replace header piping.Fail D.C.Inspection August 20, 2003 September 2, 2003 13 days
Cook J.F. Elementary School FM-200335886 03 9/3/03 Cook, J.F. Boiler Room Boiler #1 and #2 remove (3) 2" plugs at the bottom front. Engineers can not remove needed before D.C. Boiler Inspector, inspect. August 20, 2003 September 3, 2003 14 days
Hearst Elementary School FM-200334978 03 9/3/03 Hearst Boiler Room Boiler, replace safety valve. Boiler failed D.C. Inspection. August 13, 2003 September 3, 2003 21 days
West Elementary School FM-200334974 03 9/4/03 West Boiler Room Boiler #1 & #2 needs refractory work. Boilers failed D.C. inspection. August 13, 2003 September 4, 2003 22 days
Kimball Elementary School FM-200336747 03 9/4/03 Kimball Boiler Room Need electrician to check power to circulating pumps and boilers in Boiler Room, has no power to circulating pumps to pump water throughout Building. No hot water for the kitchen. EMERGENCY !!!!!! September 3, 2003 September 4, 2003 1 day
West Elementary School FM-200334975 03 9/5/03 West Boiler Room Boiler #1 & #2 replace (4) four 3/4" check valves , valves sticking. Boilers failed D.C. inspection. August 13, 2003 September 5, 2003 23 days
Brent Elementary School FM-200336252 03 9/5/03 Brent Boiler room Repair chiller , unit will not start. August 26, 2003 September 5, 2003 10 days
King M L ES FM-200336877 03 9/7/03 King, M.L. Boiler Room 1. Investigate gas leak September 5, 2003 September 7, 2003 2 days
Woodson High School FM-200335869 03 9/9/03 Woodson,H.D. Boiler Room Repair or replace #3 and #4 sump pump, pumps not working. August 20, 2003 September 9, 2003 20 days
Leckie Elementary School FM-200336622 03 9/9/03 Leckie Boiler room Repair A/C unit in the boiler , will not start, August 30, 2003 September 9, 2003 10 days
Walker-Jones EC FM-200337069 03 9/9/03 Walker-Jones Boiler Room Check A/C unit, No flow. September 9, 2003 September 9, 2003 0 days
Woodson High School FM-200228116 03 9/10/03 (Woodson, H.D.) !!!VERY URGENT!!! Outside grounds/Near Boiler room/Driveway: Metal cage hanging from the structure of the wall. Re-anchor cage to wall, as this cage is swaying back and forth, making it very dangerous for staff and students. April 2, 2003 September 10, 2003 161 days
Montgomery ES FM-200330553 03 9/10/03 (Montgomery) !!!EMERGENCY!!! Asbestos Assessment Required. Basement/Boiler Room: Busted pipe rusty, corroded, and possible asbestos. A very lound noise is coming from the boiler room. Asbestos Code A - Clear for repairs on 05/22/03. Horne Engineering - Sharon Voss (RG 05/23/03) May 21, 2003 September 10, 2003 112 days
Brent Elementary School FM-200336784 03 9/10/03 Brent Boiler room Repair chiller, unit will not start. September 3, 2003 September 10, 2003 7 days
Leckie Elementary School FM-200336133 03 9/11/03 Leckie Boiler Room (Air- Condition) Repair Trane Air - Condition in boiler room, go off on low temp, First stage - freon drop 1/2 glass Second stage - freon drop out of sight in glass August 25, 2003 September 11, 2003 17 days
Wilson High School FM-200333827 03 9/11/03 Wilson, W. Boiler Room Replace two (2) leaking safety valves on Boiler #3 in order to pass Boiler Inspection. Safety valves: Kundle Valve Co., Fort Wayne, Indiana N.B, FIG. No-250, 1 1/2- In , Seat-J, 135-LB-Set, 8936 & Pat. No. 2414794. No abestos in this area. July 28, 2003 September 11, 2003 45 days
Benning Elementary School FM-200336615 03 9/11/03 Benning Boiler room Recharge Trane A/C unit , low Refrigerant level,unit goes out on surging.(da-code) August 30, 2003 September 11, 2003 12 days
Malcolm X ES FM-200336788 02 9/12/03 (Malcolm X) The lock on the boiler room door needs to be repaired or replaced. The key pad for the new security system is housed in that area and there is some difficulty getting the door open and locking it back. Requester Phone: 202 645 3409 August 15, 2002 September 12, 2003 393 days
Payne Elementary School FM-200335853 03 9/12/03 Payne F-519.0 Fire Code Violation Basement Boiler room emergency light defective. August 20, 2003 September 12, 2003 23 days
Leckie Elementary School FM-200337039 03 9/12/03 Leckie Boiler Room Check A/C unit, not working. September 8, 2003 September 12, 2003 4 days
Patricia R Harris Ed Center FM-200333654 03 9/12/03 (Harris, P.R.) FIRE CODE VIOLATION: Basement/Boiler Room: Exit light missing. July 23, 2003 September 12, 2003 51 days
Shaw JHS FM-200336957 03 9/15/03 Shaw Boiler room Repair chiller,will not start ,flow switch on the chill water side. September 8, 2003 September 15, 2003 7 days
Brent Elementary School FM-200336623 03 9/16/03 Brent Boiler room Repair flow problem with the chiller, strainer were cleaned by engineers 8/29/03 August 31, 2003 September 16, 2003 16 days
Key Elementary School FM-200337650 03 9/16/03 Key Boiler Room AHU units for the Library Computer Lab; main office areas; open space is not supplying air or heat to these areas, unit and dampers controls need repair or replace. September 16, 2003 September 16, 2003 0 days
Benning Elementary School FM-200333248 03 9/16/03 Benning Boiler Room Check chiller, making loud noise. July 15, 2003 September 16, 2003 63 days
Emery Elementary School FM-200335899 03 9/17/03 Emery Boiler Room Perform hydrostatic test on tube sheeet and/or tubes in boiler #2. Take corrective action as needed. Note: Calcium build up in about (5) tubes. August 20, 2003 September 17, 2003 28 days
Woodson High School FM-200336958 03 9/17/03 Woodson H.D. Boiler room Repair chiller, will not start ,off on high motor temp. September 8, 2003 September 17, 2003 9 days
Bruce-Monroe Elementary School FM-200334985 03 9/18/03 Bruce-Monroe Boiler Room Boilers need hydro test, failed D.C. Inspection. August 13, 2003 September 18, 2003 36 days
Stevens Elementary School FM-200335983 03 9/18/03 Stevens Boiler Room Boilers #1 and #2 need 3/4" vent valves installed or replace. August 21, 2003 September 18, 2003 28 days
Green Elementary School FM-200217877 02 9/20/03 Green Boiler Room Repair drain line for outside sump pump. Pipe is disconnect from discharge line. September 19, 2002 September 20, 2003 366 days
Dunbar High School FM-200336749 03 9/22/03 Dunbar Boiler Room Repair loose insulation in (Fire box) combustion chamber of #2 Boiler. September 3, 2003 September 22, 2003 19 days
Cook J.F. Elementary School FM-200335888 03 9/23/03 Cook, J.F. Boiler Room Remove three approx. 3" front water leg plugs that we were unable to remove. Boiler #1 has two plugs and Boiler #2 has one plugs. Replace the three plugs with nipples (3) and (3) caps. Needed before D.C. Boiler Inspector, inspect. August 20, 2003 September 23, 2003 34 days
West Elementary School FM-200337896 03 9/23/03 West Boiler Room Repair or replace condenser pump. Pumps not working properly. September 23, 2003 September 23, 2003 0 days
Moten Elementary School FM-200336369 03 9/23/03 Moten Boiler Room Check domestic hot water heater, unit is not heating. August 27, 2003 September 23, 2003 27 days
Spingarn High School FM-200337763 03 9/23/03 (Spingarn) Boiler Room: Make keys to roof door. September 18, 2003 September 23, 2003 5 days
Burrville Elementary School FM-200337860 03 9/23/03 Burrville Boiler Room Check chiller, reading low oil pressure. September 23, 2003 September 23, 2003 0 days
Woodson High School FM-200337857 03 9/23/03 Woodson, H.D. Boiler Room Boiler Room flooded. Pump water from flooded Boiler Room. September 23, 2003 September 23, 2003 0 days
Stoddert ES FM-200337655 03 9/23/03 Stoddert Basement Drain outside of boiler room need snaking, water keeps backing up into boiler room. September 16, 2003 September 23, 2003 7 days
Stuart-Hobson Middle School FM-200335057 03 9/23/03 Stuart Hubson Boiler Room Boilers #2 and #3 remove plugs on top. August 13, 2003 September 23, 2003 41 days
Wilson High School FM-200334221 03 9/24/03 Wilson,W Boiler Room Boiler #2 repair or replace crack and missing refactory around burner cone inside of fire box. No asbestos in area. August 4, 2003 September 24, 2003 51 days
Eastern High School FM-200218252 02 9/25/03 Eastern Boiler Room Repair air compressor in Boiler Room to maximize an air pressure thur system. Need 92 psi out and 20 psi feed September 25, 2002 September 25, 2003 365 days
Shaed Elementary School FM-200338027 03 9/25/03 Shead Boiler Room Check and or repair sump pumps in the Boiler Room, Boiler Room is flooded. September 25, 2003 September 25, 2003 0 days
Green Elementary School FM-200337858 03 9/25/03 Green Boiler Room Boiler Room flooded. Pump water from flooded Boiler Room. September 23, 2003 September 25, 2003 2 days
Shaed Elementary School FM-200337856 03 9/25/03 Shead Boiler Room Flooded Boiler Room. Pump water from flooded Boiler Room. September 23, 2003 September 25, 2003 2 days
Francis Junior High School FM-200224360 03 9/25/03 Francis Boiler Room Asbestos assessment required Repair 3" condensate return line in boiler room this line severely leaking. Asbestos A-clear for repair by Horne Engineer Sharon Voss on 01-24-03 Charles Buchanan January 22, 2003 September 25, 2003 246 days
Brookland Elementary FM-200337859 03 9/25/03 Brookland Boiler Room Boiler Room flooded. Pump water from flooded Boiler Room. September 23, 2003 September 25, 2003 2 days
Bancroft Elementary School FM-200337217 03 9/26/03 Bancroft Boiler Room A hydrostatic test is needed on boiler #1. This was requested by the D.C. Boiler Inspector. Code A - clear for repairs as of 9/24/03 by Sylvia Grimes DCPS safety. September 10, 2003 September 26, 2003 16 days
Watkins Elementary School FM-200336535 03 9/26/03 (Watkins) !!!VERY URGENT!!! Boiler Room: Elevator stopped on basement floor; need key to open door leading to elevator. August 28, 2003 September 26, 2003 29 days
Dunbar High School FM-200336750 03 9/26/03 Dunbar Boiler Room Repair leaking tube in Boiler #1. September 3, 2003 September 26, 2003 23 days
Orr Elementary School FM-200338026 03 9/27/03 Orr Boiler Room Check and or repair sump pumps in the Boiler Room, Boiler Room is flooded. September 25, 2003 September 27, 2003 2 days
Brookland Elementary FM-200338023 03 9/27/03 Brookland Boiler Room Check and or repair sump pumps in the Boiler Room, Boiler Room is flooded. September 25, 2003 September 27, 2003 2 days
Green Elementary School FM-200338024 03 9/27/03 Green Boiler Room Check and or repair sump pumps in the Boiler Room, Boiler Room is flooded. September 25, 2003 September 27, 2003 2 days
Woodson High School FM-200338077 03 9/30/03 Woodson Boiler Room Check chiller, will not come on. Both down. September 26, 2003 September 30, 2003 4 days
Shaw JHS FM-200338031 03 9/30/03 Shaw Boiler Room Check A/C unit, Unit is not working properly. September 25, 2003 September 30, 2003 5 days
Thomas Elementary School FM-200337702 03 10/1/03 Thomas Boiler Room Repair stand by pump on chiller HVAC and condenser pump also need to be check. September 17, 2003 October 1, 2003 14 days
Burrville Elementary School FM-200334090 03 10/1/03 Burrville Boiler Room Boiler # 1 replace (1) brass tee, 1 inch on blow down line. July 31, 2003 October 1, 2003 62 days
Clark Elementary School FM-200338288 03 10/1/03 Clark Boiler Room Repair chiller. Unit will not start. September 30, 2003 October 1, 2003 1 day
Meyer Elementary School FM-200337073 03 10/2/03 Meyer Boiler Room Boiler #2 replace 3/4" gate stop valve on city water line. September 9, 2003 October 2, 2003 23 days
Stuart-Hobson Middle School FM-200334728 03 10/3/03 Stuart-Hobson Boiler Room Repair busted water leg on Boiler #2 left side. August 8, 2003 October 3, 2003 56 days
Benjamin Banneker Academic HS FM-200336341 03 10/3/03 Banneker Boiler Room Repair or replace domestic hot water heater. Heater will not lite off. August 27, 2003 October 3, 2003 37 days
Aiton Elementary School FM-200338019 03 10/4/03 Aiton Boiler Room Check domestic hot water heater, no hot water. September 25, 2003 October 4, 2003 9 days
Watkins Elementary School FM-200338498 03 10/5/03 Watkins Boiler Room Check Boilers #1 and #2, not firing off. October 5, 2003 October 5, 2003 0 days
Smothers ES FM-200336196 03 10/5/03 Smother Boiler Room Boiler #1 city water feeder inner chamber need badly to be clean. Boiler #2 replace bad city water feeder. To pass inspection. Boilers failed inspection. Per D.C. Inspector. August 25, 2003 October 5, 2003 41 days
Patricia R Harris Ed Center FM-200334672 03 10/7/03 Harris, P.R. Boiler Room Boilers #1, #2, #3 and #4 needs to replace 1" check valves to pass Boiler Inspection. Per requested by Boiler Inspector August 8, 2003 October 7, 2003 60 days
Wilson High School FM-200334679 03 10/7/03 Wilson, W Boiler Room Furnish Yarway type B Balanced Seatless Valve, 2"-250 psi, 8- bolt, 6 1/2"- flanges. August 8, 2003 October 7, 2003 60 days
Patricia R Harris Ed Center FM-200336642 03 10/7/03 HARRIS P.R. REPAIR/REPLACE VALVE (STOP/SAFETY) PERFORM HYDRO TEST # 4 BOILER Asbestos Code A - Clear for repairs on 09/02/03. DCPS Safety - Charles Buchanan ( RG 09/02/03) September 2, 2003 October 7, 2003 35 days
John Burroughs ES FM-200338386 03 10/7/03 Burroughs Boiler room Re-Tap threads on 11/2" right rear water leg of # 2 boiler. October 2, 2003 October 7, 2003 5 days
Burrville Elementary School FM-200338531 03 10/8/03 Burrville Boiler Room Repair leaking tubes in Boiler #1 October 6, 2003 October 8, 2003 2 days
Garfield ES FM-200338528 03 10/8/03 Garfield Boiler Room Boiler #1 and #2 repair breaching or back to Boilers by welding breaching up. October 6, 2003 October 8, 2003 2 days
Benning Elementary School FM-200332842 03 10/8/03 Benning Boiler Room Boiler #1 has water in fire box. Check for leaking tubes. July 2, 2003 October 8, 2003 98 days
Bancroft Elementary School FM-200338527 03 10/8/03 Bancroft Boiler Room Replace leaking tubes in Boiler #2. October 6, 2003 October 8, 2003 2 days
Watkins Elementary School FM-200338611 03 10/8/03 Watkins Boiler Room Gas company tag domestic hot water heater, Leaking gas. School has no hot water. Gas company cut off heater. October 7, 2003 October 8, 2003 1 day
Bruce-Monroe Elementary School FM-200338272 03 10/9/03 Bruce-Monroe Boiler room Boilers #1 and #2 Replace 2" gate valves on blow down lines. Bad valves. Boilers need work done to pass annual inspection. September 30, 2003 October 9, 2003 9 days
Park View ES FM-200338612 03 10/9/03 Park View Boiler room Door lock need to be replace. Door will not lock. October 7, 2003 October 9, 2003 2 days
Park View ES FM-200338744 03 10/9/03 Parkview Boiler Room Repair burners on boiler #4 thru #5. Something is preventing burners from liting off. There are the only units ready to test fire. October 9, 2003 October 9, 2003 0 days
Emery Elementary School FM-200338221 03 10/9/03 Emery Boiler Room Replace 3" gate valve on hot water storage tank,valve is not holding. September 30, 2003 October 9, 2003 9 days
Roosevelt High School FM-200338692 03 10/9/03 Roosevelt Boiler Room Replace started control on condensation tank in boiler room. NEMA Size-1 HP-Max - 36 200/230 V- HP-7 1/2 V-380/460/575 October 9, 2003 October 9, 2003 0 days
Hearst Elementary School FM-200338635 03 10/10/03 Hearst Boiler Room Repair broken line in tunnel and repair circulating pump to hot water heater. October 8, 2003 October 10, 2003 2 days
Reed LC FM-200338341 03 10/10/03 Reed Boiler Room/Tank Room Replace 2" ell and 1 1/4" nipple on rupture supply line to domestic hot water heater. October 1, 2003 October 10, 2003 9 days
Slowe Elementary School FM-200338743 03 10/10/03 Slowe Boiler Room Repair burners on boiler #1 thru #5. Something is preventing burners from liting off. There are the only units ready to test fire. October 9, 2003 October 10, 2003 1 day
Ballou Senior High School FM-200338819 /03 10/11/03 Ballou Boiler Room Boiler #3 replace programmer. October 11, 2003 October 11, 2003 0 days
Houston Elementary School FM-200338817 /03 10/11/03 Houston Boiler Room Boiler #1 replace control box. October 11, 2003 October 11, 2003 0 days
Janney Elementary School FM-200338832 /03 10/12/03 Janney Boiler Room Repair or replace sump pump, float sticking. October 12, 2003 October 12, 2003 0 days
Orr Elementary School FM-200338820 /03 10/14/03 Orr Boiler Room Boilers #1 and #2 needs refractory work. October 11, 2003 October 14, 2003 3 days
Hardy Middle School FM-200338742 03 10/14/03 Hardy (Filmore) Boiler Room Repair burner on Boilers #1 and #2. Something is preventing burners from liting off. There are the only units ready to test fire October 9, 2003 October 14, 2003 5 days
Bell High School FM-200338811 /03 10/14/03 Bell Boiler Room Boilers #1 and #2 flame failure. October 11, 2003 October 14, 2003 3 days
Patricia R Harris Ed Center FM-200338844 /03 10/14/03 Harris P.R. Boiler room Repair # 4 steam boiler , continuously cuts off on flame failure at start up October 14, 2003 October 14, 2003 0 days
Houston Elementary School FM-200338957 /03 10/15/03 Houston Boiler Room Check burners to Boilers, Boilers will not start. October 15, 2003 October 15, 2003 0 days
Dunbar High School FM-200338976 /03 10/15/03 Dunbar Boiler Room Boiler #1 will not start up. Flame failure. October 15, 2003 October 15, 2003 0 days
Shaw JHS FM-200338829 /03 10/15/03 Shaw Boiler Room Boilers #1 and #3 down. Boiler #3 programmer read hold D-8 high purge open. October 12, 2003 October 15, 2003 3 days
Bell High School FM-200338840 /03 10/15/03 Bell Boiler room Repair # 3 boiler , it will not ignite October 14, 2003 October 15, 2003 1 day
Harris, C.W. ES FM-200338825 /03 10/15/03 Harris, C.W. Boiler Room Boiler #3 replace valve on city water supply line. October 12, 2003 October 15, 2003 3 days
Clark Elementary School FM-200332044 03 10/16/03 Clark Basement/Boiler Room Repair/replace needed: Boiler #2 have a leaking tube. Tube size is 2 1/2" (N) Tube will be Mark. June 18, 2003 October 16, 2003 120 days
Janney Elementary School FM-200338504 03 10/16/03 Janney Boiler Room Repair or replace McDonnell Miller #51-2 feed water control that leaks water at connection of basket strainer chamber and linkage chamber to float on boiler #1. Emergency !!! October 5, 2003 October 16, 2003 11 days
Stoddert ES FM-200338746 03 10/16/03 Stoddert Boiler Room Repair or replace McDonnell Miller Auto. water feeder. Make-up water continuously runs. Note: Model #51HD (only boiler). October 9, 2003 October 16, 2003 7 days
Janney Elementary School FM-200339035 /03 10/16/03 Janney Boiler Room Repair Boiler #1 that goes into (Lockout Purge -3-P, High pressure after about 6-10 seconds and doesn't complete the ignition cycle. Emergency!!!! October 16, 2003 October 16, 2003 0 days
Roosevelt High School FM-200338993 /03 10/16/03 Roosevelt Boiler Room Boiler #1 down will not come on, but power is to Boiler. October 16, 2003 October 16, 2003 0 days
Eastern High School FM-200339039 /03 10/17/03 Eastern Boiler Room Replace innerfeed water line on Boilers #1, #2 and #3, 80 Gage; 2" pipe, approximatelly 15' (FT.) needs to be replace. Emergency!!!!! October 16, 2003 October 17, 2003 1 day
Meyer Elementary School FM-200338982 /03 10/17/03 Meyer Boiler Room Water coming through wall near electric panel box. May cause electric problem. Send electrician as soon as possible to investigate situation. EMERGENCY !!!!! October 15, 2003 October 17, 2003 2 days
Moten Elementary School FM-200335552 03 10/20/03 Moten Boiler room Repair leaking shell in the rear of the fire boxes of #1, and # 2 boilers as per boiler inspector's request.+ August 18, 2003 October 20, 2003 63 days
Plummer Elementary School FM-200339070 /03 10/20/03 Plummer Boiler Room Boiler #1Repair or replace modulator. October 17, 2003 October 20, 2003 3 days
Gibbs Elementary School FM-200339133 /03 10/20/03 Gibbs Boiler Room Pump out Boiler Room. Boiler Room flooded. October 20, 2003 October 20, 2003 0 days
Moten Elementary School FM-200339182 /03 10/21/03 Moten Boiler Room Boiler #1 out on flame failure. October 21, 2003 October 21, 2003 0 days
Moten Elementary School FM-200335555 03 10/21/03 Moten Boiler room Repair or replace refractory in the fire box of # 1 boiler as per boiler inspector's request. Boilers failed inspection. August 18, 2003 October 21, 2003 64 days
Thomas Elementary School FM-200338980 /03 10/21/03 Thomas, N Boiler Room Boiler #2 Replace leaking MM-S-51 auto water feeder, leaking thru needle valve and float control housing October 15, 2003 October 21, 2003 6 days
Moten Elementary School FM-200338868 /03 10/21/03 Moten Boiler Room Repair refractory work in fire box of boiler #1. October 14, 2003 October 21, 2003 7 days
Emery Elementary School FM-200339174 /03 10/21/03 Emery Boiler room Repair # 1 burner Must reset each time boiler reach set pressure. October 21, 2003 October 21, 2003 0 days
Beers Elementary School FM-200339175 /03 10/22/03 Beers Boiler room Repair # 1 and # 2 burner will not start, off on lock out October 21, 2003 October 22, 2003 1 day
Kimball Elementary School FM-200337692 03 10/22/03 Kimball Basement 1. Key Boiler room exit and entry door to master key. September 17, 2003 October 22, 2003 35 days
Gibbs Elementary School FM-200339176 /03 10/22/03 Gibbs Boiler room Relite Domestis Hot water heater , unit was under water . October 21, 2003 October 22, 2003 1 day
Roosevelt High School FM-200339040 /03 10/22/03 Roosevelt Boiler Room Correct problem with control to boilers, will not come on, some types of lock out. Emergency!!! October 16, 2003 October 22, 2003 6 days
Emery Elementary School FM-200338275 03 10/22/03 Emery Boiler Room Area Boilers #1 and #2 install (2) 3/4" gate valves on supply lines. September 30, 2003 October 22, 2003 22 days
Cook J.F. Elementary School FM-200337317 03 10/22/03 Cook,J.F. Boiler Room Repair 1 1/2" elbow on domestic hot water tank (Leaking badly). September 11, 2003 October 22, 2003 41 days
Webb Elementary School FM-200339169 /03 10/23/03 Webb Boiler room Repair or replace # 4 house pump, pump will not run. Lincoln Motor: Model # 9VB- CCF4P5461- L Product: LM26253AB Frame: 2154 PH - 3 Hz.- 60 Hp- 5.0 RPM 1765 Volts 230/460 Fla. 6.3/6.5 October 21, 2003 October 23, 2003 2 days
Watkins Elementary School FM-200339253 /03 10/23/03 Watkins Boiler Room Unstop floor drains in Boiler Room, (between the two pumps) October 22, 2003 October 23, 2003 1 day
Hardy Middle School FM-200339322 /03 10/23/03 Rossario Boiler room Correct condensate return and steam generating problem with boilers 1 thru 5, boiler will run ok until the header valve is open , the boilers will shut down in low water condition. October 23, 2003 October 23, 2003 0 days
Orr Elementary School FM-200338830 /03 10/23/03 ORR Boiler room Repair # 1 and # 2 oil pumps , (1) one has a bad seal , and the other pump needs a #5 woods coupling. October 12, 2003 October 23, 2003 11 days
Kimball Elementary School FM-200339327 /03 10/23/03 Kimball Boiler Room Repair single phase pumps #1 and #2 on condensate, pumps not working properly. October 23, 2003 October 23, 2003 0 days
Thomas Elementary School FM-200338536 03 10/23/03 Thomas Boiler Room Reweld broken yoke for condensate return tank strainer. Bradley has yoke. October 6, 2003 October 23, 2003 17 days
Anacostia Senior High School FM-200330592 03 10/24/03 Anacostia Boilerroom Replace flow switch on condenser line May 22, 2003 October 24, 2003 155 days
Green Elementary School FM-200339404 /03 10/24/03 Green Boiler Room Boiler #4 Replace or repair circulating pump. Boiler burnt out. October 24, 2003 October 24, 2003 0 days
Kimball Elementary School FM-200339359 /03 10/24/03 Kimball Boiler Room Repair Boilers #1, #2, #3 and #4, not working. Emergency!!!!! No heat. October 23, 2003 October 24, 2003 1 day
Sousa Middle School FM-200339183 /03 10/24/03 Sousa Boiler Room Boiler #3 off on flame failure. October 21, 2003 October 24, 2003 3 days
Hine JHS FM-200339386 /03 10/24/03 Hine Boiler Room Boilers #1, #2 and #3 will not come on. Burner switch open. No heat in Building. October 24, 2003 October 24, 2003 0 days
Moten Elementary School FM-200339408 /03 10/24/03 Moten Boiler Room Boiler room flooded. October 24, 2003 October 24, 2003 0 days
Plummer Elementary School FM-200339033 /03 10/24/03 Plummer Boiler Room Replace regulator valve on Boiler #1. Building will has no heat. URGENT October 16, 2003 October 24, 2003 8 days
Woodson High School FM-200339331 /03 10/24/03 Woodson Boiler room Boiler #1 Replace hand hole. Work completed. October 23, 2003 October 24, 2003 1 day
Young Elementary School FM-200337004 03 10/24/03 Charles Young Boiler room Repair chiller, off on low oil pressure. September 8, 2003 October 24, 2003 46 days
Meyer Elementary School FM-200337961 03 10/25/03 Meyer Boiler Room Check Boiler #1 metal shell, water coming through metal in front of Boiler around hand hole gasket. Emergency!!!! Same as work orders FM-200337070 and FM-200337076. September 24, 2003 October 25, 2003 31 days
Sousa Middle School FM-200339379 /03 10/26/03 Sousa Boiler Room Boiler #3 Start Boiler and repair condensate pump. October 24, 2003 October 26, 2003 2 days
Eaton Elementary School FM-200338922 /03 10/27/03 Eaton Boiler Room Check domestic hot water in Building , no hot water in building. October 15, 2003 October 27, 2003 12 days
Eaton Elementary School FM-200339527 /03 10/27/03 Eaton Boiler Room Repair or replace leaking 1" copper line to domestic hot water tank. Losing a lot of hot water because of leak. Emergency!!!!! October 27, 2003 October 27, 2003 0 days
Brightwood Elementary School FM-200339466 /03 10/27/03 Brightwood Boiler Room Check domestic hot water. No hot water in building. October 27, 2003 October 27, 2003 0 days
King M L ES FM-200334652 03 10/27/03 King,M.L. Boiler Room Boiler #1 and #2 need hydra test, Boilers failed inspection. Asbestos assessment on the Header valve on boilers 1 & 2 , remove foot of TSI off both sides of valve and the TSI on the valve. Assess city water and bypass on both boilers. Area's are marked in red marker. POC: Sylvia Grimes 202 345-1527. August 7, 2003 October 27, 2003 81 days
Shepherd ES FM-200339524 /03 10/27/03 Shepherd Boiler Room Unstop floor drains in boiler room and outside entrances to this area (approximate. 2 inches) Engineer attempted to unstop with negative results. October 27, 2003 October 27, 2003 0 days
Malcolm X ES FM-200339366 /03 10/27/03 Malcolm X Boiler Room Repair or replace return pumps and motor (Blend pumps) not circulating water to main circulating pumps that heats the building. (Back of Boiler #1) Marathon Electric; HP- 1/3; Cat. No. G5/3 Volts: 115/208-230 Mod #GVM5GC17F2042B FLA-6/3-3 FR. S6C SF-1.15 PH-1 Type-SCS Hertz- 60 Code-M October 23, 2003 October 27, 2003 4 days
Kimball Elementary School FM-200338937 /03 10/28/03 Kimball Boiler Room Recut keys to entry to Boiler Room door. October 15, 2003 October 28, 2003 13 days
Kimball Elementary School FM-200339559 /03 10/28/03 Kimball Boiler room Restore operating service to the boilers , there is no electrical service to the control pannel October 28, 2003 October 28, 2003 0 days
Orr Elementary School FM-200339068 /03 10/28/03 Orr Boiler Room Recut keys to entry to Boiler Room door. October 17, 2003 October 28, 2003 11 days
Ronald H. Brown MS FM-200338938 /03 10/28/03 Brown, Ron (Roper) Boiler Room Recut keys to entry to Boiler Room door. October 15, 2003 October 28, 2003 13 days
Benjamin Banneker Academic HS FM-200339585 /03 10/28/03 Banneker Boiler Room Repair or replace domestic hot water circulating pump. Pump not working and leaking no Data tag on pump. October 28, 2003 October 28, 2003 0 days
Gibbs Elementary School FM-200339471 /03 10/28/03 Gibbs Boiler Room Check domestic hot water. No hot water in building. October 27, 2003 October 28, 2003 1 day
Beers Elementary School FM-200339388 /03 10/28/03 Beers URGENT Front door boiler room Front door entrance of building lock is not keching alson the boiler roon entrance door lock is not keching. October 24, 2003 October 28, 2003 4 days
Cardozo High School FM-200339426 /03 10/28/03 Cardozo Boiler Room Survey Boilers gas train on all 3 Boilers- strong gas smell from gas vents, also check outside gas meter for boiler room gas supply. October 24, 2003 October 28, 2003 4 days
Amidon Elementary School FM-200339067 /03 10/28/03 Amidon Boiler Room Recut keys to entry to Boiler Room door. October 17, 2003 October 28, 2003 11 days
Houston Elementary School FM-200338936 /03 10/28/03 Houston Boiler Room Recut keys to entry to Boiler Room door. October 15, 2003 October 28, 2003 13 days
Barnard Elementary School FM-200339644 /03 10/29/03 Barnard Boiler Room Check H.V.A.C. Equipment, unit continuously indicating re-boot. can not access. Hot!!!! Also repair or replace computer that control H,V.A.C.equipment. October 29, 2003 October 29, 2003 0 days
Randle-Highlands ES FM-200339633 /03 10/29/03 Randle-Highland Sub-Basement - Across from tennis courts - Panic bar won't lock door. Stairwell sub basement - Toward boiler room - Door won't unlock. October 29, 2003 October 29, 2003 0 days
Drew Elementary School FM-200339638 /03 10/29/03 Drew Boiler room Repair # 1 burner will not start , cuts off on flame failure. October 29, 2003 October 29, 2003 0 days
Randle-Highlands ES FM-200339628 /03 10/29/03 Randle-Highland Sub-Basement - Across from tennis courts - Panic bar won't lock door. Stairwell sub basement - Toward boiler room - Door won't unlock. October 29, 2003 October 29, 2003 0 days
Nalle Elementary School FM-200339319 /03 10/30/03 Nalle J.C. boiler room Make adjustment the low water cut off on the # 1 boiler ,level in the site glass is to low ,boiler cuts off before the feeder comes on. October 23, 2003 October 30, 2003 7 days
Walker-Jones EC FM-200339626 /03 10/31/03 Walker-Jones Boiler Room Boiler #2 Replace relief valve,draining. Per D.C.Boiler Inspector October 29, 2003 October 31, 2003 2 days
Kimball Elementary School FM-200339784 /03 10/31/03 Kimball Boiler Room Electrican needed to repair electric line on condensate pump for Boiler start up. Pump 112 is single phasing. (Please rush this) October 31, 2003 October 31, 2003 0 days
West Elementary School FM-200339702 /03 11/1/03 West Boiler Room Check domestic hot water, No domestic hot water in Building.. October 30, 2003 November 1, 2003 2 days
Roosevelt High School FM-200339707 /03 11/1/03 Roosevelt Boiler Room Installed sub pump motor and clean pump that was in pit re-install pump and motor. October 30, 2003 November 1, 2003 2 days
Roosevelt High School FM-200339693 /03 11/1/03 Roosevelt Boiler Room Install one sub- pump motor. Remove. Two bad motor from pit. October 30, 2003 November 1, 2003 2 days
Peabody Elementary School FM-200226075 03 11/4/03 Peabody Outside driveway boiler-room steps Replace metal rail, snow removal truck ran into rail plowing driveway and rail was dis-engaged. February 24, 2003 November 4, 2003 253 days
Lincoln Middle School FM-200120941 01 11/4/03 LINCOLN BOILER ROOM 1. ASBESTOS ASSESSMENT REQUIRED. FURNISH AND INSTALL (11) FOUR TUABE FLUORESCENT LAMP FIXTURES. CAN NOT SEE GAUGES OR INSTRUMENTS TO TAKE PROPER READING BECAUSE BOILER ROOM IS TOO DARK. Requester Phone: 576-5316 Requestor Phone: 576-5316 ASBESTOS CODE A-CLEAR FOR REPAIR BY 11-06-01 HORNE ENGINEER : SHARON VOSS September 25, 2001 November 4, 2003 770 days
Lincoln Middle School FM-200204221 02 11/4/03 Lincoln Boiler room Sewer Main needs to be checked for possible belly or collapsed line. March 11, 2002 November 4, 2003 603 days
Harris, C.W. ES FM-200339745 /03 11/4/03 Harris, C.W. Boiler Room Repair Boilers #1 and #3. October 31, 2003 November 4, 2003 4 days
Nalle Elementary School FM-200339747 /03 11/5/03 Nalle Boiler Room Repair condensate return pump. October 31, 2003 November 5, 2003 5 days
Savoy Elementary School FM-200339954 03 11/5/03 Savoy Boiler Room Boiler #3 need gas regulator valve replace. November 5, 2003 November 5, 2003 0 days
Park View ES FM-200339975 03 11/5/03 Pakview Basement / Boiler Room Replacement needed: Boiler #4 need electrode,electrode missing. November 5, 2003 November 5, 2003 0 days
Montgomery ES FM-200338876 /03 11/6/03 Scott Montgomery Boiler room Repair Locnivar Gas Water Heater October 14, 2003 November 6, 2003 23 days
Backus Middle School FM-200340006 03 11/6/03 Backus Boiler Room Boiler #3 Flame failure. November 6, 2003 November 6, 2003 0 days
Jefferson JHS FM-200340008 03 11/6/03 Jefferson Boiler Room Boiler #2 Flame failure. November 6, 2003 November 6, 2003 0 days
Watkins Elementary School FM-200338763 /03 11/6/03 Watkins Boiler Room Boiler #2 need 2 1/2" gate valve replace on blow down line. October 10, 2003 November 6, 2003 27 days
Oyster Elementary School FM-200339951 03 11/7/03 Oyster Boiler Room Check two (2) heat pumps, pumps not working may need motors. November 5, 2003 November 7, 2003 2 days
Ferebee-Hope Elementary School FM-200340062 03 11/8/03 Ferebee - Hope Boiler Room Unclog two floor drains in Boiler Room. November 7, 2003 November 8, 2003 1 day
Bancroft Elementary School FM-200226468 03 11/10/03 Bancroft Open Space Area of Building Roof Boiler #3 elec. will not start Note: This is the only boiler for open space area March 3, 2003 November 10, 2003 252 days
Randle-Highlands ES FM-200338992 /03 11/11/03 Randle-Highland Boiler Room Furnish (5) five 1 1/2" X 10" nipples and caps. October 16, 2003 November 11, 2003 26 days
Eaton Elementary School FM-200339103 /03 11/12/03 Eaton Boiler Room Replace crack McDonnell & Miller feeder water regulator, model #N-51-2M. Leaking very bad can not use Boiler #2. Large crack. URGENCY!!!!! October 17, 2003 November 12, 2003 26 days
Montgomery ES FM-200340814 /03 11/12/03 Montgomery Boiler Room Install controller and power supply for operation of hot water heater. November 12, 2003 November 12, 2003 0 days
Moten Elementary School FM-200338560 03 11/12/03 Moten Bioler Room Furnish for repairs low water cut off on boilers #1 and #2. Model #205015-202030 205490 McDowell boiler control Need tow feeder with #2 switch. October 7, 2003 November 12, 2003 36 days
Houston Elementary School FM-200340219 /03 11/13/03 Houston Boiler room (No Heat) Repair Boiler # 1 and #2 both boilers down on lockout. November 13, 2003 November 13, 2003 0 days
Backus Middle School FM-200338818 /03 11/13/03 Backus Boiler Room Boiler #1 and #2 replace programmer. October 11, 2003 November 13, 2003 33 days
Bruce-Monroe Elementary School FM-200339026 /03 11/13/03 Bruce-Monroe Old Wing (Boiler #3) Repair or replace automatic feeder. Damaged float ball (McDonnell/ Miller No.) and adjust pump control. Per D.C. Boiler Inspected, request. October 16, 2003 November 13, 2003 28 days
Eliot Junior High School FM-200338823 /03 11/13/03 Eliot Boiler Room Boilers #1 and #3 out on flame failure. October 12, 2003 November 13, 2003 32 days
Hine JHS FM-200334037 03 11/14/03 (Hine) FIRE CODE VIOLATION: Basement/Boiler Room: Adjust door. Asbestos Code A - Clear for repairs on 08/04/03. Horne Engineering - Bipin Nanavaty (RG 08/05/03) July 30, 2003 November 14, 2003 107 days
Walker-Jones EC FM-200340297 /03 11/14/03 Walker-Jones Boiler Room Repair Boiler #2. November 14, 2003 November 14, 2003 0 days
Backus Middle School FM-200340294 /03 11/14/03 Backus Boiler Room Repair Burners on all Boilers. November 14, 2003 November 14, 2003 0 days
Terrell Mc ES FM-200340295 /03 11/14/03 Terrell, M.C. Boiler Room Repair Burner #1. November 14, 2003 November 14, 2003 0 days
Green Elementary School FM-200340205 /03 11/14/03 GREEN boiler room Repair # 1 boiler , will not start. November 12, 2003 November 14, 2003 2 days
Brightwood Elementary School FM-200340126 /03 11/14/03 Brightwood Boiler room NO HEAT Repair # 1 and # 2 burner ,will not start. November 10, 2003 November 14, 2003 4 days
Malcolm X ES FM-200339948 03 11/14/03 Malcolm X Boiler Room Check heat timer on Boilers #1, #2 ,#3, #4 and #5 timer needs to be check so Boilers can run automatic. November 5, 2003 November 14, 2003 9 days
Eliot Junior High School FM-200337418 03 11/15/03 Eloit Boiler room Repair or replace # 1 and # 2 condensate return pumps ,they will not run. September 12, 2003 November 15, 2003 64 days
Drew Elementary School FM-200340269 /03 11/16/03 Drew Boiler room NO HEAT Restart boilers ,will not start readout on pannel awaitinting cycle. November 14, 2003 November 16, 2003 2 days
Montgomery ES FM-200340361 /03 11/17/03 Montgomery Boiler Room Boiler #1 will not start. November 17, 2003 November 17, 2003 0 days
Green Elementary School FM-200336009 03 11/19/03 Green Boiler Room Remove automatic blow down from in front of Boilers. D.C. Boiler Inspector. August 21, 2003 November 19, 2003 90 days
Houston Elementary School FM-200331460 03 11/19/03 Houston Boiler Room Unstop 4" drain in Boiler Room. Drain is stop up and water is on the floor. June 9, 2003 November 19, 2003 163 days
Kenilworth ES FM-200338468 03 11/20/03 Kenilworth Boiler room Replace leaking tube in Boilers #1 and #2. October 3, 2003 November 20, 2003 48 days
Kramer Middle School FM-200340399 /03 11/20/03 Kramer M.S Entrance door ,boiler room office Cut (3) three keys for engineer ,engineer has key that is be cut. November 18, 2003 November 20, 2003 2 days
Simon Elementary School FM-200335559 03 11/21/03 (Simon) FIRE CODE VIOLATION: Ground floor: Exit light in hallway near boiler room. August 18, 2003 November 21, 2003 95 days
Whittier Elementary School FM-200335792 03 11/21/03 (Whittier) FIRE CODE VIOLATION: Boiler Room: Need exit sign. August 19, 2003 November 21, 2003 94 days
Backus Middle School FM-200340580 /03 11/21/03 Backus Boiler Room Boiler #2 has electric problem. Boiler will not come on. November 21, 2003 November 21, 2003 0 days
Watkins Elementary School FM-200335550 03 11/21/03 Watkins F-110.0 FIRE CODE VIOLATION Exit light missing in boiler room. August 18, 2003 November 21, 2003 95 days
Eastern High School FM-200336432 03 11/21/03 (Eastern) FIRE CODE VIOLATION: Basement/Near Boiler Room: Exit light out. August 27, 2003 November 21, 2003 86 days
Slowe Elementary School FM-200340311 /03 11/21/03 Slowe Boiler Room Repair or replace busted city water make- up line to Boilers, 3/4". Line is located over treatment tank. Boiler shutting down on low water. Note: Can be isolated. this effect boiler operation. November 14, 2003 November 21, 2003 7 days
Watkins Elementary School FM-200337748 03 11/21/03 (Watkins) FIRE CODE VIOLATION: Boiler Room: Exit sign must be illuminated, or violation notice will be submitted as soon as possible. September 17, 2003 November 21, 2003 65 days
Emery Elementary School FM-200340621 /03 11/21/03 Emery Boiler Room Repair air condition system (multi-stack). A/C Electrical system on cooling tower area has shortage. November 21, 2003 November 21, 2003 0 days
Green Elementary School FM-200340582 /03 11/21/03 GREEN boiler room Check boilers # 3 and 4 went out on flame failure after attempting to start. Check boiler # 2 (fves gas valve) will not operate. November 21, 2003 November 21, 2003 0 days
Coolidge High School FM-200340562 /03 11/24/03 Coolidge Boiler Room Repair and replace 2" leaking steam line in Boiler Room. November 20, 2003 November 24, 2003 4 days
Stanton Elementary School FM-200339957 03 11/24/03 Stanton Boiler Room-Annex Boiler #1 Annex need LWCO replace. November 5, 2003 November 24, 2003 19 days
Ketcham Elementary School FM-200339945 03 11/24/03 Ketcham Boiler Room Boiler #4 LWCO float need to be replace. November 5, 2003 November 24, 2003 19 days
Roosevelt High School FM-200340704 /03 11/25/03 Roosevelt Boiler room Repair or replace main circuit breaker in the boiler room will not reset. (No Heat) November 25, 2003 November 25, 2003 0 days
Whittier Elementary School FM-200340564 /03 11/25/03 Whittier Tunnel Repair or replace 3" leaking steam line in tunnel of Boiler Room. November 20, 2003 November 25, 2003 5 days
Green Elementary School FM-200340694 /03 11/25/03 Green Boiler room Replace manual reset aquastat on # 3 boiler ,120 volts- 240 volts; fullload 8.0 5.1 locked rotor 48.0 30.6; 0.25 amps at 0.25- 12 vdc Honeywell November 25, 2003 November 25, 2003 0 days
Green Elementary School FM-200340696 /03 11/25/03 Green Boiler room Repair # 5 burner off on flame failure ( PIFF) November 25, 2003 November 25, 2003 0 days
Whittier Elementary School FM-200340770 /03 11/26/03 Whittier Boiler Room Boilers #1 and #2 down, will not start. November 26, 2003 November 26, 2003 0 days
Malcolm X ES FM-200340651 03 11/26/03 (Malcolm X) A lock and door knob needs to be put on the boiler room door. The lock had to be removed in order to get in the door because the lock was jammed. The alarm system is also in that room. This is an urgent request. November 7, 2003 November 26, 2003 19 days
Cook J.F. Elementary School FM-200340718 /03 11/26/03 J.F. COOKE boiler room Boiler # 2 will not fire off. November 25, 2003 November 26, 2003 1 day
Green Elementary School FM-200340836 03 12/1/03 Green Boiler room Repair # 3 ,4,5 , burners cut of on flame failure.only 1 boiler in operation December 1, 2003 December 1, 2003 0 days
Gibbs Elementary School FM-200340798 /03 12/1/03 Gibbs Boiler Room Repair or replace sump pump, pump will not work on automatic. November 28, 2003 December 1, 2003 3 days
Moten Elementary School FM-200340511 /03 12/1/03 Moten Boiler room Supply engineer with the following: (3) feed water regulators Nd.V58 : Model# 5ME: Set STd: Reg.25-75 November 20, 2003 December 1, 2003 11 days
Green Elementary School FM-200339608 /03 12/2/03 Green Boiler Room Repair or replace Bell & Gossett motor on Boiler #4.HP-1/4, RMP-1725, PH-1, Volts 115, AMPS 3.0, HZ-60. October 28, 2003 December 2, 2003 35 days
Gibbs Elementary School FM-200340835 03 12/2/03 Gibbs boiler room Repair or replace sump pump problem in th e boiler room . December 1, 2003 December 2, 2003 1 day
Whittier Elementary School FM-200340889 03 12/3/03 Whittier Boiler Room Remove all bolts from all pumps and replace with new pumps. December 1, 2003 December 3, 2003 2 days
Kramer Middle School FM-200340822 /03 12/3/03 Kramer Middle School Boiler Room Install deadbolt or rim lock, on wooden boiler room door. November 28, 2003 December 3, 2003 5 days
Slowe Elementary School FM-200340996 03 12/3/03 Slowe Boiler Room Replace busted section of 1" copper pipe over treatment tank. This line is continuously being repaired. Line is isolated at this time. December 3, 2003 December 3, 2003 0 days
Ronald H. Brown MS FM-200228685 03 12/3/03 Brown Ron Boiler room - Bldg 1 Repair leaking cond. return line. Leak occurs at bldg chase from bldg #2. Note: Insulation is present asbestos assessment required newly insulated. Asbestos Code A - Clear for repairs on 04/14/03. Horne Engineering - Bipin Nanavaty (RG 04/15/03) April 11, 2003 December 3, 2003 236 days
Green Elementary School FM-200341084 03 12/4/03 Green Boiler room Install new air seperator for heating hot water system. December 4, 2003 December 4, 2003 0 days
Maury Elementary School FM-200340987 03 12/5/03 Maury Boiler room Repair or replace Ruptured 2" condensate return line behind the boilers. December 3, 2003 December 5, 2003 2 days
Slowe Elementary School FM-200341118 03 12/5/03 Slowe Boiler Room Check float switch on condensate return tank. Switch is sticking. See Engineer. December 5, 2003 December 5, 2003 0 days
Bancroft Elementary School FM-200341105 03 12/5/03 Bancroft Boiler Room Boiler #3 Down will not come on (Electric), no heat in open space area. December 5, 2003 December 5, 2003 0 days
Woodson High School FM-200341119 03 12/5/03 Woodson Boiler Room Repair 3" PVC line to sump pump Emergency!!!!! December 5, 2003 December 5, 2003 0 days
Thomas Elementary School FM-200341153 03 12/7/03 N.Thomas Boiler room Repair condensate pumps in the boiler room. December 7, 2003 December 7, 2003 0 days
Sousa Middle School FM-200341158 03 12/7/03 Sousa Boiler room Repair or replace condensate pumps in the boiler room. December 7, 2003 December 7, 2003 0 days
Jefferson JHS FM-200341154 03 12/7/03 Jefferson Boiler room Repair #3 burner ,it will not start December 7, 2003 December 7, 2003 0 days
Gibbs Elementary School FM-200341233 03 12/9/03 Gibbs Boiler Room Boiler #1 Need programmer. December 9, 2003 December 9, 2003 0 days
Anacostia Senior High School FM-200335750 03 12/9/03 Anacostia Boiler Room Boiler #1 Repair or replace leaking tubes in row #6 and 2 tubes. August 19, 2003 December 9, 2003 112 days
Tubman Elementary School FM-200338500 03 12/11/03 Tubman Boiler Room Repalced faulty 2" dia. nipple at rear of boiler #2. Bottom threads have rusted away. tried to remove nipple, but it began collaping. October 5, 2003 December 11, 2003 67 days
Aiton Elementary School FM-200331387 03 12/11/03 Aiton Boiler Room Check leaking tubes in boiler #1 and #2. Boiler #1 leaking tubes in back and Boiler #2 leaking tubes in front and back. P.S. Need rounding again. June 6, 2003 December 11, 2003 188 days
Ronald H. Brown MS FM-200341328 /03 12/12/03 Ron Brown Boiler room Repair 6" steam line in the boiler room behind the chillwater pump December 10, 2003 December 12, 2003 2 days
Slowe Elementary School FM-200341295 03 12/12/03 Slowe Boiler Room Repair or replacetemperature control device on domestic hot water heater #1 ( water get too hot) Note: Unit is off at this time and H/W heater #2 is on line. December 9, 2003 December 12, 2003 3 days
Marshall Educational Center FM-200339470 /03 12/12/03 Marshall Bolier #2 Boiler #2 Replace LWCO, leaking very bad. October 27, 2003 December 12, 2003 46 days
Janney Elementary School FM-200341537 /03 12/13/03 Janney Boiler Room Repair or replace domestic hot water heater. Water is dropping into the flame causing it to go out. A O Smith Capacity 75 Gal Electonic Inition Replaced circulating pump and motor on 12/03, but didn't solve the problem. December 13, 2003 December 13, 2003 0 days
Horace Mann Elementary School FM-200341787 /03 12/18/03 Mann Boiler Room Check Boilers will not come on, no heat December 18, 2003 December 18, 2003 0 days
West Elementary School FM-200341776 /03 12/18/03 West Boiler Room Check domestic hot water is not working, will not light off. No hot water. December 18, 2003 December 18, 2003 0 days
Stuart-Hobson Middle School FM-200339242 /03 12/19/03 Stuart-Hobson Boiler room 1)Repair 2" steam line in the boiler room , 2) Repair 1 1/2" steam leak in the ceiling behind boiler # 3 3) Repair all steam leaks in the tunnels. October 22, 2003 December 19, 2003 58 days
Gibbs Elementary School FM-200341900 /03 12/22/03 Gibbs Boiler room Replace leaking tubes in th e # 2 boiler ,and # 1 Boiler December 20, 2003 December 22, 2003 2 days
Wilkinson ES FM-200339484 /03 12/22/03 Wilkinson Boiler Room Boiler #1 ,Replace leaking tube. October 27, 2003 December 22, 2003 56 days
Ferebee-Hope Elementary School FM-200339944 03 12/23/03 Ferebee-Hope Boiler Room Boiler #1 has leaking tubes November 5, 2003 December 23, 2003 48 days
Reed LC FM-200342020 /03 12/23/03 Reed Hot water storage tank room Repair 1 1/2" Domestic hot water line in the tank room above the boiler room December 23, 2003 December 23, 2003 0 days
Kramer Middle School FM-200342071 /03 12/29/03 Kramer Boiler Room Domestic hot water heater leaking, from tank and union. December 29, 2003 December 29, 2003 0 days
Nalle Elementary School FM-200339384 /03 12/31/03 Nalle Boiler Room Steam Tunnel Replace 2" black pipe on steam line. Steam line to condensate is leaking. October 24, 2003 December 31, 2003 68 days
Woodson High School FM-200339255 /03 12/31/03 Woodson Boiler Room Boiler #2 condensate return line to feed water line to boiler is leaking, 2" line October 22, 2003 December 31, 2003 70 days
Gibbs Elementary School FM-200342164 04 1/2/04 Gibbs Boiler Room Boiler Room flooded, pumps not working. January 2, 2004 January 2, 2004 0 days
Nalle Elementary School FM-200342165 04 1/4/04 Nalle Boiler Room Boilers will not start. January 2, 2004 January 4, 2004 2 days
Backus Middle School FM-200442225 04 1/5/04 Backus School Boiler room Repair gas leak on boiler # 2. Boiler has been isolated. January 5, 2004 January 5, 2004 0 days
Gibbs Elementary School FM-200342199 04 1/5/04 Gibbs Boiler Room Domestic hot water heater need to be relight. No hot water in Building. January 5, 2004 January 5, 2004 0 days
Shepherd ES FM-200342096 /03 1/5/04 Sherpherd Boiler Room Unstop drain in Boiler Room and outside of Boiler Room door. December 29, 2003 January 5, 2004 7 days
Kramer Middle School FM-200442201 04 1/5/04 Kramer Boiler Room Check hot water circulating pump, pump not working properly, Emergency!!!!! January 5, 2004 January 5, 2004 0 days
Whittier Elementary School FM-200227744 03 1/5/04 Whittier Boiler Room Repair or replace feed water (condensate pump #1 & 2 The pumps seal is leakign for #1 boiler. This pump keeps water on the floor of the boiler room None of the condensate pumps are operational . Note: The school is without HEAT. Note: Create slipping hazzard March 27, 2003 January 5, 2004 284 days
Shaed Elementary School FM-200340581 /03 1/5/04 Shead Boiler Room Boiler #2 leaking leg. November 21, 2003 January 5, 2004 45 days
Moten Elementary School FM-200442238 04 1/5/04 Moten Boiler Room Boiler #1Replace 2" safety valve. Valve leaking January 5, 2004 January 5, 2004 0 days
Gage-Eckington ES FM-200340610 /03 1/5/04 Gage- Eckington Boiler Room SAFETY Need safety to check water in Boiler Room Sub-pump not working. Drains in Boiler Room (Raw sewage backing up in this area). HOT!!!! Code A-clear for repair by DCPS Charles Buchanan on 12/01/03 November 21, 2003 January 5, 2004 45 days
Tyler Elementary School FM-200342196 04 1/5/04 Tyler Boiler room Restore power to boilers, no read out on panel January 4, 2004 January 5, 2004 1 day
Tubman Elementary School FM-200442285 04 1/6/04 Tubman Boiler Room Replace faulty McDonnell & Miller #63 low water cut off. Tested it & it failed to shut off Boiler #2. (This is a Hot water boiler) HOT !!!!!!! January 6, 2004 January 6, 2004 0 days
Roosevelt High School FM-200336726 03 1/7/04 Roosevelt Boiler Room Repair Boiler used for heating pool. Repairs due to flood. September 3, 2003 January 7, 2004 126 days
Green Elementary School FM-200339407 /03 1/7/04 Green Boiler Room Boiler #5 out on flame failure. October 24, 2003 January 7, 2004 75 days
Jessie LaSalle Elementary FM-200341232 03 1/7/04 LaSalle Boiler Room Boiler #1 Down on lockout. December 9, 2003 January 7, 2004 29 days
Wilson High School FM-200338974 /03 1/7/04 Wilson, W. Boiler Room Boiler #1 will not start up. Flame failure. October 15, 2003 January 7, 2004 84 days
Shaw JHS FM-200442312 04 1/7/04 Shaw Boiler room 1) make adjustment on pump control for #2 boiler, boiler cuts off on low water constantly. 2) Replace the burner linkage on the # 3 boiler . January 7, 2004 January 7, 2004 0 days
Miner Elementary FM-200339488 /03 1/7/04 Miner Building and Boiler Room Recut keys to entry to Building and Boiler Room door. October 27, 2003 January 7, 2004 72 days
Thomas Elementary School FM-200339958 03 1/7/04 Thomas Boiler Room Boiler #1 has defective air damper. November 5, 2003 January 7, 2004 63 days
Brightwood Elementary School FM-200342066 /03 1/8/04 Brightwood boiler room Replace/ repair nonoperational LWCO on # 2 boiler. December 24, 2003 January 8, 2004 15 days
Coolidge High School FM-200338507 03 1/8/04 Coolidge Boiler Room Supply 3 liquid level controls types PFCIGR AND 12 Ametek pressure gauges 2" center back connections 0 to 30 range. October 5, 2003 January 8, 2004 95 days
Shepherd ES FM-200332407 03 1/8/04 Shepherd Boiler Room Boiler #2 repair or replace burners. Problem appears to be with ignition transformer. Note: Problem, existed since the close of last heating season. June 24, 2003 January 8, 2004 198 days
Bancroft Elementary School FM-200442383 04 1/8/04 Bancroft boiler room Correct problem with electric boiler, circulating hot water temperature is not being heated high enough to adequately heat new wing (120 degrees) January 8, 2004 January 8, 2004 0 days
Beers Elementary School FM-200442370 04 1/8/04 Beers Boiler room Repair #1 burner, cut off on flame failure. January 8, 2004 January 8, 2004 0 days
Shepherd ES FM-200340125 /03 1/8/04 Shepherd Boiler room NO HEAT Repair # 1 burner ,will not start. # 2 down ,gas valve. November 10, 2003 January 8, 2004 59 days
Burrville Elementary School FM-200442374 04 1/8/04 Burrville Boiler room Repair # 1 boiler ,cuts off on flame failure. January 8, 2004 January 8, 2004 0 days
Janney Elementary School FM-200442286 04 1/8/04 Janney Boiler Room Repair or replace faulty domestic Hot water heater, that keeps going out. Problem maybe the damper control. When you move the damper the heater starts up until it reaches set temperature (140) A O Smith 75 Gallons Capacity Electronic Ignition Hot Water Heater. January 6, 2004 January 8, 2004 2 days
Smothers ES FM-200442376 04 1/8/04 Smothers Boiler room Replace condensate return tank assembly and controls for boilers # 1 and # 2.( boilers must be hand fed.) January 8, 2004 January 8, 2004 0 days
Nalle Elementary School FM-200442379 04 1/8/04 J.C.Nalle Boiler room Asbestos asssessment required Repair ruptured line above the # 1 boiler. Asbestos Code A - Clear for repairs on 01/08/04. Horne Engineering - Philp Connolly (RG 01/09/04) January 8, 2004 January 8, 2004 0 days
Woodson High School FM-200340793 /03 1/8/04 Woodson Boiler Room Boiler #1 Tubes leaking. November 28, 2003 January 8, 2004 41 days
Ferebee-Hope Elementary School FM-200342101 /03 1/8/04 Ferebee-Hope Boiler Room-A.H.U. C-1 Mechanical Maint. Unit unable to supply heat to kitchen area. Motor operable coil hot. December 29, 2003 January 8, 2004 10 days
Leckie Elementary School FM-200442206 04 1/9/04 Leckie Boiler Room Boiler #1 (Hot water) replace leaking tube, Size 3". January 5, 2004 January 9, 2004 4 days
Roosevelt High School FM-200442430 04 1/9/04 Roosevelt Boiler Room Boiler #1 and #2 Adjust burner proportioning control. (Very little flame in Boiler and smoking,) January 9, 2004 January 9, 2004 0 days
Backus Middle School FM-200442311 04 1/9/04 Backus Boiler room Repair # 3 buner ,will not start ,cuts off on flame failure.( # 2 boiler is down also,only 1 boiler operational) January 7, 2004 January 9, 2004 2 days
Ludlow-Taylor ES FM-200339993 03 1/9/04 Ludlow-Taylor Boiler room Repair hair line crack in the rear of the #1 boiler,left side Asbestos Code A - Clear for repairs on 01/06/04. Horne Engineering - Bipin Nanavaty (RG 01/08/04) November 6, 2003 January 9, 2004 64 days
Tubman Elementary School FM-200442322 04 1/9/04 Tubman Boiler Room Replace sump pump, flooded Boiler Room. January 7, 2004 January 9, 2004 2 days
Gibbs Elementary School FM-200342198 04 1/9/04 Gibbs Boiler Room Boilers #1 and #2 Leaking tubes. January 5, 2004 January 9, 2004 4 days
Ludlow-Taylor ES FM-200342200 04 1/10/04 Ludlow-Taylor Boiler Room Check sump pump, not working properly. 2" Water on Boiler room floor. January 5, 2004 January 10, 2004 5 days
Bunker Hill Elementary School FM-200442473 04 1/11/04 Bunker Hill Boiler Room Condensate pumps not putting water back into Boilers, Had to keep hitting reset. January 11, 2004 January 11, 2004 0 days
Randle-Highlands ES FM-200442472 04 1/11/04 Randle-Highland Boiler room #2 Air handler Repair or replace ruptured heating coil on Air handler #2 in the boiler room ( coil is isolated) a number of class room will be without heat . January 11, 2004 January 11, 2004 0 days
Shepherd ES FM-200442492 04 1/12/04 Shepherd Boiler Room Boiler #1 Down flame failure (purge, low fire switch) Boiler #2 Has to hand feed water do to condensate pumps not working. Emergency !!!!! January 12, 2004 January 12, 2004 0 days
Hine JHS FM-200340636 /03 1/13/04 Hine Boiler Room Repair or replace domestic hot water motor and / or pump. Make: B&G HP- 1/4 RPM: 1725 PH 1 HZ: 60 Volts: 115 Amp: 3.0 SF: 1.35 Thermal Prot: M74799 Part # M10534-M89 Cont Rating: 40 C Pump B&G 185332 AOO Note:Circuit breaker kicks out motor hot. November 21, 2003 January 13, 2004 53 days
Gibbs Elementary School FM-200442577 04 1/13/04 Gibbs Boiler room Replace amplifier on boiler #1. January 13, 2004 January 13, 2004 0 days
Kramer Middle School FM-200442251 04 1/14/04 Kramer Boiler room Repair or replace domestic water circulating pump. January 6, 2004 January 14, 2004 8 days
Benjamin Banneker Academic HS FM-200339939 03 1/14/04 Banneker Boiler Room Boiler #1 tubes leaking. November 5, 2003 January 14, 2004 70 days
Gibbs Elementary School FM-200442677 04 1/14/04 GIBBS Boiler room Replace leaking tubes in # 1 and # 2 boilers. January 14, 2004 January 14, 2004 0 days
Rudolph Elementary School FM-200442604 04 1/14/04 Rudolph Boiler Room Furnish HVAC Shop with regulator valves to control heat on new side of building. January 13, 2004 January 14, 2004 1 day
Smothers ES FM-200442787 04 1/15/04 Smothers Boiler Room Boiler #1 out on flame failure. January 15, 2004 January 15, 2004 0 days
Kramer Middle School FM-200442250 04 1/15/04 Kramer Boiler room Repair leaking man hole ring on the domestic hot water storage tank. January 6, 2004 January 15, 2004 9 days
Rudolph Elementary School FM-200341670 /03 1/15/04 Rudolph Boiler Room Check circulating pumps in Boiler Room that heats new wing of Building. Both pumps are not working. Area is cold. December 16, 2003 January 15, 2004 30 days
Raymond Elementary School FM-200339467 /03 1/16/04 Raymond Boiler Room Check domestic hot water. No hot water in building. October 27, 2003 January 16, 2004 81 days
Dunbar High School FM-200339510 /03 1/16/04 Dunbar Penthouse (Boiler Room) Boiler #1tubes over heated casing damage to exterior of boiler. October 27, 2003 January 16, 2004 81 days
Malcolm X ES FM-200338845 /03 1/16/04 Malcolm X Boiler room Install larger horse power motor for sump pumps ,Pumps are not sending water out of the well properly,Drains are full , can not blow boilers down. October 14, 2003 January 16, 2004 94 days
Kimball Elementary School FM-200442770 04 1/18/04 Kimball Boiler Room Boiler #1 in lock out. January 15, 2004 January 18, 2004 3 days
Meyer Elementary School FM-200442832 04 1/20/04 Meyer Boiler room Repair # 1 burner ,it will not start., building has no heat. ,both boiler down. January 16, 2004 January 20, 2004 4 days
Gage-Eckington ES FM-200442973 04 1/20/04 Gage-Eckington Boiler Room Check domestic hot water heater circulating pump. No hot water cause of circulating pump. January 20, 2004 January 20, 2004 0 days
Kramer Middle School FM-200442991 04 1/21/04 Kramer Boiler room Repair burner #1 cuts off in flame failure. Only (1) one of (3) three boilers will operate. January 21, 2004 January 21, 2004 0 days
Bunker Hill Elementary School FM-200443027 04 1/21/04 Bunker Hill Boiler Room Repair or replace 3/4" rupture nipple on steam line in Boiler Room, behind trap over hot water tank. Urgent!!!! January 21, 2004 January 21, 2004 0 days
Burrville Elementary School FM-200341902 /03 1/21/04 Burrville Boiler room Replace 2" X 4" nipple on condensate line of pump # 2 December 21, 2003 January 21, 2004 31 days
Burrville Elementary School FM-200443003 04 1/21/04 Burrville Boiler room Repair ruptured return lines on the condensate return tank. January 21, 2004 January 21, 2004 0 days
Whittier Elementary School FM-200442287 04 1/21/04 Whittier Tunnel Enter Boiler Room Repair or replace leaking steam line. 2" condensate line. HOT !!!!! January 6, 2004 January 21, 2004 15 days
John Burroughs ES FM-200443088 04 1/22/04 Burroughs Boiler room Cap off 3/4" steam vent line above convertor. The steam loss is droppng the heating water temperture to the new wing of the building heating water temperture is now 160 deg. down from 180 deg. There is no insulation on the area that is to be repaired. January 22, 2004 January 22, 2004 0 days
Shepherd ES FM-200442490 04 1/22/04 Shepherd Boiler Room Check condensate return pumps #1 and #2, try to reset but nothing happen. Pumps are not pumping returns to Boilers. Possible bad pumps. Note: Hand feeding boilers. URGENT January 12, 2004 January 22, 2004 10 days
Tubman Elementary School FM-200443158 04 1/23/04 Tubman Boiler Room Check domestic hot water heater, heater will not stay on. No hot water in Building. January 23, 2004 January 23, 2004 0 days
Gibbs Elementary School FM-200442929 04 1/24/04 Gibbs Boiler room Replace lecking tubes in the # 1 boiler January 20, 2004 January 24, 2004 4 days
Gibbs Elementary School FM-200443091 04 1/24/04 Gibbs Boiler room Replace leaking tubes in the # 2 boiler . January 22, 2004 January 24, 2004 2 days
Bunker Hill Elementary School FM-200443092 04 1/24/04 Bunker- Hill Boiler room Repair leaking steam line room next to the boiler room office. January 22, 2004 January 24, 2004 2 days
Backus Middle School FM-200340933 03 1/24/04 Backus Boiler Room Boiler #2 Repair or replace burner blow fuse in control box when unit comes back on line. December 2, 2003 January 24, 2004 53 days
Garrison ES FM-200443218 04 1/26/04 Garrison Boiler room Boilers 1,2,3, and 4 will not start , phase lost January 26, 2004 January 26, 2004 0 days
Jefferson JHS FM-200341951 /03 1/27/04 Jefferson Old boiler room Repair ruptured 1 1/2" water line in the old boiler room . Repair dometic hot heater in the same area. Gas was shut off by Washington Gas co. no hot water or heat to the building. December 22, 2003 January 27, 2004 36 days
Ludlow-Taylor ES FM-200442897 04 1/27/04 Ludlow-Taylor Boiler room Replace high limit control switch for #1 boiler . January 17, 2004 January 27, 2004 10 days
Hart Middle School FM-200443412 04 1/30/04 Hart Boiler Room Boiler #3 Replace broken inlet damper draft control rod and linkage. Also check for blower motor vibration. January 30, 2004 January 30, 2004 0 days
Bruce-Monroe Elementary School FM-200443390 04 1/30/04 Bruce-Monroe Boiler Room Repair or replace air compressor tank. (Hole in bottom of tank). Model #A5150-4 Serial #AG17 Urgent !!! January 30, 2004 January 30, 2004 0 days
Payne Elementary School FM-200213824 02 1/30/04 Repair or replace sump pump in the boiler room , August 8, 2002 January 30, 2004 540 days
Bunker Hill Elementary School FM-200443417 04 1/30/04 Bunker Hill Boiler Room Repair or replace new condensate return pumps. Pumps are continuously being reset during late evening hours (Contractor). Urgent !!!! January 30, 2004 January 30, 2004 0 days
Woodson High School FM-200443452 04 1/31/04 Woodson,H D Boiler Room Boiler #1 tubes leaking. January 31, 2004 January 31, 2004 0 days
Tubman Elementary School FM-200443355 04 2/2/04 Tubman Basement exit door Exit door lock to be keyed as same as entrance door to enter buildind. Easy access to boiler room. Principal's Office: Replace entrance door lock too the office, door will not open. January 29, 2004 February 2, 2004 4 days
Garfield ES FM-200442930 04 2/2/04 Garfield Boiler Room Boiler #2 Flame failure. January 20, 2004 February 2, 2004 13 days
Woodson High School FM-200443738 04 2/6/04 Woodson Boiler Room Repair leaking condensate return tank. Need work to supply water back in boilers. February 6, 2004 February 6, 2004 0 days
Kramer Middle School FM-200442319 04 2/7/04 Kramer Boiler Room Boiler #2 need repair. January 7, 2004 February 7, 2004 31 days
Gibbs Elementary School FM-200443655 04 2/7/04 Gibbs Boiler Room Repair circulating pump supply return line on cooling and heating system. February 4, 2004 February 7, 2004 3 days
Gibbs Elementary School FM-200443605 04 2/7/04 GIBBS Boiler room Replace leaking tubes in boilers # 1 , and # 2 February 2, 2004 February 7, 2004 5 days
Maury Elementary School FM-200442931 04 2/9/04 Maury Boiler room Replace the pressure control and modulating control on the # 2 boiler , both units are leaking steam. January 20, 2004 February 9, 2004 20 days
Cook J.F. Elementary School FM-200340625 /03 2/9/04 Cook, J.F. Boiler Room Pipe blow down lines on automatic water and low water cut out on boiler #1 and #2 to drains. Approximate line size 1 1/2 November 21, 2003 February 9, 2004 80 days
Maury Elementary School FM-200443807 04 2/9/04 Maury Boiler Room Repair or replace controls,electric motor and McDonnell and Miller Automatic water feeder for heating unit.. February 9, 2004 February 9, 2004 0 days
Walker-Jones EC FM-200443654 04 2/11/04 Walker/ Jones Boiler room Asbestos assessment maybe requireed, Line has insulation on it. Replace 3/4" feed water regulator valve ,and 3/4 stop valves . Asbestos Code A - Clear for repairs on 02/04/04. Horne Engineering - Edward Rodriguez (RG 02/05/04) February 4, 2004 February 11, 2004 7 days
Rudolph Elementary School FM-200443928 04 2/13/04 Rudolph Boiler Room Install pneumatic valve to steam convertor for new side of building. February 11, 2004 February 13, 2004 2 days
Brent Elementary School FM-200444087 04 2/16/04 Brent Boiler room Replace leaking tubes in the # 1 boiler , # 2 boiler is down also to be retubed, NO heat Asbestos Code A - Clear for repairs on 02/18/04. Horne Engineering - Edward Rodriguez (RG 02/19/04) February 16, 2004 February 16, 2004 0 days
King M L ES FM-200443279 04 2/17/04 M.L. King Boiler Room Repair Electrical problem with circuit breeker for boiler, it tripps after 15 minites.operation. January 28, 2004 February 17, 2004 20 days
Ronald H. Brown MS FM-200444070 04 2/17/04 (Brown, Ron (Roper) !!!VERY URGENT!!! 1st Floor/Door leading to Boiler Room: Broken panic bar. 1st Floor/Incinerator Room: Key broke off in lock. February 13, 2004 February 17, 2004 4 days
Kramer Middle School FM-200443580 04 2/17/04 Kramer Boiler Room Boiler #3 out on flame failure. Boiler #2 need to be fixed before calibration 1 out of 3 Boilers working. February 2, 2004 February 17, 2004 15 days
Benning Elementary School FM-200334080 03 2/18/04 Benning Boiler Room Replace commpressor on Quenicy Air Compressor. Model 216 - 103; SN - 161 - 995; Size - 3 X 2 - 5 July 31, 2003 February 18, 2004 202 days
Turner Elementary School FM-200443941 04 2/18/04 Turner Boiler Room Repair or replace #1 condensate pump, pump keep blowing fuses. February 11, 2004 February 18, 2004 7 days
Turner Elementary School FM-200442520 04 2/18/04 (Turner) !!!VERY URGENT!!! Outside Grounds: Unstop drain outside exit door of boiler room; water is spilling over in-to the boiler room with a foul odor. January 12, 2004 February 18, 2004 37 days
Ludlow-Taylor ES FM-200444143 04 2/19/04 (Ludlow-Taylor) School Security Problem: The main entrance door to Ludlow Taylor cannot be secured. This problem is associated with the installation of the ADT camera, several years ago. Since the door cannot be secured, the door is locked in a way that the school system cannot use the master key for this building to enter after duty hours. The building engineer uses the boiler roon key to enter the building. REQUEST IMMEDIATE ACTION TO CORRECT THIS PROBLEM. THE SCHOOL STAFF HAD TO WORK A MODIFIED SCHEDULE TO ACCOMMODATE THE "LEAD IN WATER" INSPECTORS THIS PASS WEEKEND. February 17, 2004 February 19, 2004 2 days
Benning Elementary School FM-200224751 03 2/19/04 Benning Boiler Room Repair or replace Quewcy Air Compressor, unit will not pump air. January 29, 2003 February 19, 2004 386 days
Ronald H. Brown MS FM-200443632 04 2/20/04 Brown, Ron Entrance by the Boiler Room Window guard need repairing. February 3, 2004 February 20, 2004 17 days
West Elementary School FM-200340618 /03 2/23/04 West Boiler Room Repair or replace starter coil to Air Handler Unit #8, Name Westington House Cat. A200M2CACV 200 - 230, 460/575 PH- 3 HP - 10 -15 Starter will not pull in to start unit. November 21, 2003 February 23, 2004 94 days
Roosevelt High School FM-200443586 04 2/23/04 Roosevelt Boiler Room Repair sump pumps in Boiler Room. February 2, 2004 February 23, 2004 21 days
Roosevelt High School FM-200444168 04 2/23/04 Roosevelt Boiler Room Repair or replace locks on Boiler Room door. Locks jammed sometime and door won't open. Security and safety hazard. Key knob and Dead bolt lock. February 18, 2004 February 23, 2004 5 days
Roosevelt High School FM-200342099 /03 2/24/04 Roosevelt Boiler Room Survey and correct electric short problem, causing power failure to entire Boiler Room. (Main O.P. circuit to trip open). December 29, 2003 February 24, 2004 57 days
Leckie Elementary School FM-200337925 03 2/24/04 Leckie boiler room Repair chiller, no vaine pressure reading. September 24, 2003 February 24, 2004 153 days
Brookland Elementary FM-200219917 /02 2/24/04 Brookland Boiler Room P.M Multi Stack October 23, 2002 February 24, 2004 489 days
Browne Junior High School FM-200225572 03 2/25/04 Browne Boiler Room P.M Chiller February 11, 2003 February 25, 2004 379 days
King M L ES FM-200444409 04 2/25/04 ML Kiing Boiler room Check and repair # 1 burner motor or electrical circuit ,burner will trip main breaker for the boiler room February 25, 2004 February 25, 2004 0 days
Shaed Elementary School FM-200443233 04 2/26/04 Shead Boiler Room Boiler #1 has crack shell or tubes leaking. Fire box is wet. January 26, 2004 February 26, 2004 31 days
Spingarn High School FM-200109654 01 2/26/04 SPINGARN N. PARKING LOT - OUTSIDE RAMP REPLACE GUARD RAIL TO RAMP LEADING TO PARKING LOT NEAR BOILER ROOM (8 INCHES DROPOFF) SAFETY HAZARD. May 7, 2001 February 26, 2004 1,025 days
West Elementary School FM-200443932 04 2/26/04 West Boiler Room Repair or replace domestic hot water heater, problem with unit liting off. Urgent !!! February 11, 2004 February 26, 2004 15 days
Roosevelt High School FM-200339965 03 2/27/04 Roosevelt Boiler Room Survey and repair leak to chiller, feon 123. November 5, 2003 February 27, 2004 114 days
Ferebee-Hope Elementary School FM-200122338 /01 2/27/04 FEREBEE-HOPE BOILER RM. EXIT (EXTERIOR) WELDER: FABRICATE DOORS (METAL) DOUBLE DOORS TO OPEN AND LOCK FROM THE INSIDE. (FIRE CODE VIOLATION) Requester Phone: 645-3094 ASBESTOS CODE A - CLEAR FOR REPAIRS 10/30/01. HORNE ENGINEERING - BILL CAMPION (RG) October 19, 2001 February 27, 2004 861 days
Leckie Elementary School FM-200444268 04 2/27/04 Leckie Boiler Room Repair or replace leaking tubes in Boiler #1.Size no. 3" February 20, 2004 February 27, 2004 7 days
Garnet-Patterson MS FM-200207055 02 3/1/04 Garnet-Patterson ****Urgent**** Boiler Room The drain pipe is leaking from the roof to the boiler room allowing water to flood the boiler room office. May 3, 2002 March 1, 2004 668 days
Harris, C.W. ES FM-200219205 /02 3/2/04 HARRIS C. W. Boiler room Weld stairs leading to boiler room back to frame per boiler inspector A. Colvin. Asbestos Code A-clear for repair on 10/11/02 DCPS Charles E. Buchanan October 10, 2002 March 2, 2004 509 days
Meyer Elementary School FM-200443653 04 3/3/04 Meyer Boiler room Repair # 2 burner it will not start. February 4, 2004 March 3, 2004 28 days
Patricia R Harris Ed Center FM-200340172 /03 3/4/04 HARRIS P. R. boiler room Replace 1 " draft gauge nipple on side of boiler # 1, nipple is leaking inside firebox. November 12, 2003 March 4, 2004 113 days
Rudolph Elementary School FM-200443064 04 3/4/04 RUDOLPH boiler room Boiler # 2 continuously shuts down on lock out. January 21, 2004 March 4, 2004 43 days
Patricia R Harris Ed Center FM-200444876 04 3/4/04 Harris, P.R. Boiler Room Engineers assist welding shop while working on tube replacement or rolling tubes and inside plate on boiler #1. March 4, 2004 March 4, 2004 0 days
Kimball Elementary School FM-200442928 04 3/4/04 Kimball Boiler room Repair # 4 burner ,cuts off on high purge. January 20, 2004 March 4, 2004 44 days
Young Elementary School FM-200444745 04 3/4/04 Young Boiler Room Repair or replace domestic hot water heater, will not stay on. Need hot water for kitchen. Urgent !!!! March 3, 2004 March 4, 2004 1 day
Eliot Junior High School FM-200444812 04 3/4/04 Eliot Boiler room Repair dometic hot heater in the boiler room , it cuts off on flame failure. March 4, 2004 March 4, 2004 0 days
Clark Elementary School FM-200444605 04 3/5/04 (Clark) Boiler Room Boiler #2 repair or replace leaking tubes. March 1, 2004 March 5, 2004 4 days
Watkins Elementary School FM-200444868 04 3/5/04 Watkins Boiler Room Repair or replace domestic hot water heater, no hot water in Building. March 5, 2004 March 5, 2004 0 days
Ferebee-Hope Elementary School FM-200444854 04 3/6/04 Ferbee-hope Boiler rrom Replace packing on the # 1 hot water circulating pump. March 5, 2004 March 6, 2004 1 day
Patricia R Harris Ed Center FM-200444914 04 3/7/04 Harris, P.R. Boiler Room Boiler #1 Roll front and back end of five (5) Tube preverious installed (small locks). March 5, 2004 March 7, 2004 2 days
Key Elementary School FM-200446530 04 3/8/04 Key ES, Boiler Room. Pick up filters at Penn Center's Warehouse and deliver them to Key School. March 8, 2004 March 8, 2004 0 days
Savoy Elementary School FM-200126808 02 3/9/04 SAVOY BOILER ROOM Repair A/C chiller. Chiller will not start. January 4, 2002 March 9, 2004 795 days
Ludlow-Taylor ES FM-200444866 04 3/9/04 Ludlow-Taylor boiler room Sump pump / submergible pump inoperable boiler room is flooding. Replace 1 1/2" check valve on sump pump. March 5, 2004 March 9, 2004 4 days
Savoy Elementary School FM-200219886 /02 3/9/04 Savoy Boiler Room P.M Chiller October 23, 2002 March 9, 2004 503 days
Hearst Elementary School FM-200444925 04 3/9/04 Hearst Tunnel Area (Boiler Room) Repair or replace busted 3/4" domestic hot water line in tunnel of Boiler Room. March 7, 2004 March 9, 2004 2 days
Hearst Elementary School FM-200446531 04 3/9/04 Hearst ES, boiler room (tunnel) . Assisting the Steam Shop with repair of leaking line in tunnel on domestic water line. March 9, 2004 March 9, 2004 0 days
Ludlow-Taylor ES FM-200444865 04 3/9/04 Ludlow-Talyor Boiler room Repair or replace sump pumps in the boiler room , the drop-in pump is not working and the floor has 1" of water on it. March 5, 2004 March 9, 2004 4 days
West Elementary School FM-200339911 03 3/9/04 West Boiler Room Repair or replace stand by pump starter, will not pull in. November 5, 2003 March 9, 2004 125 days
Savoy Elementary School FM-200225574 03 3/9/04 Savoy Boiler Room P.M Chiller February 11, 2003 March 9, 2004 392 days
Walker-Jones EC FM-200445171 04 3/10/04 Walker-Jones boiler room Make repairs to HW circulation pumps. Both pumps trip out and are unable to reset. March 10, 2004 March 10, 2004 0 days
Jessie LaSalle Elementary FM-200443144 04 3/10/04 La Salle Boilers #1 & #2 Boilers #1 and #2 Blow down are leaking. January 23, 2004 March 10, 2004 47 days
Benjamin Banneker Academic HS FM-200340792 /03 3/10/04 Banneker Boiler Room Check domestic hot water heater in Boiler Room, not working. November 28, 2003 March 10, 2004 103 days
Ferebee-Hope Elementary School FM-200444857 04 3/11/04 Ferbee-Hope Boiler room Replace (6) six , 2" check valves on Boiler # 1,#2, and #3 blow down lines, March 5, 2004 March 11, 2004 6 days
Gibbs Elementary School FM-200445137 04 3/11/04 GIBBS repair leaking tubes #1 boiler March 10, 2004 March 11, 2004 1 day
Whittier Elementary School FM-200226997 03 3/11/04 Whittier Boiler Room Area Asbestos Assestment Required Send electrician to repair or replace approx. (10) fluorescent lamps. Area is getting dark especially pump room Asbestos Code A - Clear for repairs on 03/13/03. DCPS-Safety - Richard Gibson (RG) March 13, 2003 March 11, 2004 364 days
Amidon Elementary School FM-200127183 02 3/12/04 AMIDON ASBESTOS ASSESSMENT REQ. EXTERIOR OF BOILER ROOM FABRICATE WINDOW GUARDS FOR BOILER ROOM. GUARDS ARE NEEDED TO PREVENT SEVERAL ATTEMPTED BREAK-INS. 3 WINDOWS EA. CODE FOR STRUCTURAL ASBESTOS CODE A - CLEAR FOR REPAIRS ON 01/10/02. HORNE ENGINEERING - PHILP CONNOLLY (RG) January 4, 2002 March 12, 2004 798 days
Roosevelt High School FM-200445253 04 3/12/04 Roosevelt Boiler room Restore electrical service to boilers. March 12, 2004 March 12, 2004 0 days
Gibbs Elementary School FM-200442895 04 3/12/04 Gibbs Boiler room Repair or replace mechanical seals on circulation pumps # 1 and # 2 for the all purpose room. January 17, 2004 March 12, 2004 55 days
Cardozo High School FM-200224571 03 3/15/04 CARDOZO boiler room No insulation - Can not be isolated. Repair ruptured 2 1/2" nipple on return line boiler # 2 (no insulation) "CAN NOT BE ISOLATED." January 25, 2003 March 15, 2004 415 days
Cardozo High School FM-200204684 02 3/15/04 Cardozo Boiler room Repair or replace domestic hot water heater. Domestic hot water pipes have water hammer when heater starts up with main flame and immediately shuts down. No domestic hot water lochinvar. March 19, 2002 March 15, 2004 727 days
Cardozo High School FM-200124555 01 3/15/04 CARDOZO BOILER ROOM INSTALL ELECTRICAL SERVICE FOR BOILER PUMP CONTROLS TO RETURN PUMPS AND TANK. MCDONNEL MILLER - 150, BOILERS #1, 2, & 3. December 5, 2001 March 15, 2004 831 days
Cardozo High School FM-200124034 /01 3/15/04 (CARDDOZO) ASBESTOS ASSESSMENT REQUIRED SUB-BASEMENT/BOILER ROOM ASSESS BOILER ROOM WALLS & FLOOR PAINT FOR SCRAPING AND RE-PAINTING. ASBESTOS CODE A-CLAER FOR REPAIR 11/30/01 BY HORNE ENGINEER: BILL CAMPION November 29, 2001 March 15, 2004 837 days
Cardozo High School FM-200104711 01 3/15/04 CARDOZO BASEMENT ROOM 19 REPLACE 2 - 1" VALVES ON LOW WATER CUT OFF/AUTOMATIC WATER FEEDER AND PUMP CONTROL BLOW DOWN PIPES ON BOILER #3. VALVES NOT HOLDING. March 2, 2001 March 15, 2004 1,109 days
Tubman Elementary School FM-200443652 04 3/15/04 Tubman Boiler room Repair # 1 boiler off on flame failure. Repair # 2 boiler ,it hard restart when it cuts off. February 4, 2004 March 15, 2004 40 days
Gibbs Elementary School FM-200444315 04 3/15/04 GIBBS Boiler room Repair leaking tubes in boilers # 1 , and boiler # 2 February 23, 2004 March 15, 2004 21 days
Kramer Middle School FM-200340797 /03 3/15/04 Kramer Middle School Boiler Room Repair/Replace low water cut off and pump controls on all boilers. November 28, 2003 March 15, 2004 108 days
Lafayette Elementary School FM-200446538 04 3/16/04 Lafayette ES., POOL MAINTENANCE Isolated two city water regulators (pressure) to hot water heating circulting system. Also, turned off city water feed to condensate return tank and both boilers (#1&2), This was done as part of the process to determie the damage caused by the fire and to make repairs accordingly. March 16, 2004 March 16, 2004 0 days
Leckie Elementary School FM-200105922 01 3/16/04 LECKIE BOILER ROOM REPAIR #1 WELL PUMP, NOT MOVING WATER FROM WELL. SERIAL # 19028, TYPE F2, SIZE 2". SUMP PUMP OPERATIONAL. March 15, 2001 March 16, 2004 1,097 days
Garfield ES FM-200443625 04 3/16/04 Garfield Boiler room-Auditorium Survay and repair or replace Bell & Gossett motor with pump. HP-1/2 RPM-1725 PH-1 HZ-60 Volt -115/230 AMP -5.2/2.5 Alternatins current motor No-M80067 B69 Pump #B69 8 Hole Bolt to motor February 3, 2004 March 16, 2004 42 days
Dunbar High School FM-200226396 03 3/17/04 Dunbar Boiler Room Penthouse Repair pneumatic controller and contols that operate the automaic temperature for the domestic hot water tank. No Hot Water February 28, 2003 March 17, 2004 383 days
Shepherd ES FM-200445306 04 3/17/04 Shepherd Boiler Room Repair time clock for outside light on side and back of play ground, light only work on manual dial on clock does not operate our side light. Note: This creates a safety issue for roving engineer entering site during early morning. Urgent !!!! March 12, 2004 March 17, 2004 5 days
Montgomery ES FM-200201291 02 3/17/04 MONTGOMERY BOILER ROOJ REPLACE FLOAT IN CONDENSATE TANK, FLOAT IS CONSTANTLY FILLING TANK AND BACKING UP RETURN LINES. January 17, 2002 March 17, 2004 790 days
Dunbar High School FM-200339943 03 3/17/04 Dunbar Penthouse Boiler #3 has leak in back, when boiler not running. November 5, 2003 March 17, 2004 133 days
Woodson High School FM-200341540 /03 3/17/04 Woodson Boiler Room Please make the necessary repair to circulation pump #9 expansion joint is leaking. December 13, 2003 March 17, 2004 95 days
Sousa Middle School FM-200444971 04 3/17/04 Sousa Boiler room Start # 3 boiler ,boiler programmer has no power March 8, 2004 March 17, 2004 9 days
Dunbar High School FM-200226397 03 3/17/04 Dunbar Boiler Room Penthouse Repair two (2) A.O Smith Hot water heaters Model BL 670 Serial D 85 54468 24 Volts A.O Smith Ser. 932A 97 36226 Model HW 670 932 February 28, 2003 March 17, 2004 383 days
Dunbar High School FM-200228781 03 3/17/04 Dunbar Boiler Room Replace motor on Air Handlers number B-7, motor has burnt out. April 15, 2003 March 17, 2004 337 days
Dunbar High School FM-200328989 03 3/17/04 Dunbar Boiler Room Replace motor on air handlers number B-7. Motor has burn out. April 23, 2003 March 17, 2004 329 days
Montgomery ES FM-200227134 03 3/18/04 MONTGOMERY boiler room "URGENT BOILER ROOM WILL FLOOD" Check float control for sump pump, control have to be activated manually to pump water down in sump pit. Boiler room was flooded this morning 3/17/03 4" of water on floor. March 17, 2003 March 18, 2004 367 days
Benjamin Banneker Academic HS FM-200443850 04 3/18/04 Banneker Boiler Room Repair or replace lower/upper float control on condensate return tank. Control is not working properly, sometime. Urgent !!!! February 9, 2004 March 18, 2004 38 days
Ferebee-Hope Elementary School FM-200335540 03 3/18/04 Ferebee Hope Boilerroom Repair or replace air compressor it is needed to operate the chiller August 18, 2003 March 18, 2004 213 days
Shaed Elementary School FM-200337803 03 3/22/04 (Shaed) Boiler Room: Assess, and make repairs to electrical conduit leading to pump in the Boiler room. Electrical conduit is under ground, and shorted out due to flood. Asbestos Code A - Clear for repairs on 09/29/03. Horne Engineering - Sheryll James (RG 10/01/03) September 22, 2003 March 22, 2004 182 days
Garnet-Patterson MS FM-200445638 04 3/23/04 Garnet-Patterson boiler room Repair leak on boiler # 3 Replace leaking brass 1" nipple on LWCO. March 22, 2004 March 23, 2004 1 day
River Terrace ES FM-200340508 /03 3/23/04 River Terrace Boiler room 1) Replace Defective temperature transmitter on heating supply line from the convertor. 2) Calibrate pnuematics -excessive heat temperatures. November 20, 2003 March 23, 2004 124 days
Roosevelt High School FM-200445738 04 3/24/04 Roosevelt Boiler Room P.M Chiller Asbestos Code A - Clear for repairs on 03/24/04. DCPS Safety - Richard Gibson (RG) March 24, 2004 March 24, 2004 0 days
Woodson High School FM-200444813 04 3/25/04 Woodson Boiler Room Repairs perimeter control valve zone 5, Pneumatic valve is leaking. Zone control heat and cooling of Auditorium and Gym. March 4, 2004 March 25, 2004 21 days
Savoy Elementary School FM-200338568 03 3/25/04 Savoy Boiler Room Boiler #1 repair or replace burner #1. October 7, 2003 March 25, 2004 170 days
West Elementary School FM-200445451 04 3/25/04 West Boiler Room Boiler #1 replace leaking tubes. March 16, 2004 March 25, 2004 9 days
Bunker Hill Elementary School FM-200443250 04 3/25/04 Bunker-Hill Boiler Room Re-connect 2" return line (condensate) with bucket trap to return system. Building has bad trap. This will prevent live steam from entering has new return tank. Urgent !!! January 27, 2004 March 25, 2004 58 days
Savoy Elementary School FM-200443138 04 3/25/04 Savoy Boiler room Replace Temperture control on the # 1 boiler, it sticks on 170 deg. ,run for 5 minutes then cuts off on temperture .( only (1) one of (3) three boilers operate. January 23, 2004 March 25, 2004 62 days
Brent Elementary School FM-200444995 04 3/29/04 Brent Boiler Room Repair or replace domestic hot water heater, no heat in building. March 9, 2004 March 29, 2004 20 days
Tubman Elementary School FM-200445750 04 3/29/04 Tubman Boiler Room Repair or replace domestic hot water heater, will not stay lit. There is no domestic hot water in Building. March 24, 2004 March 29, 2004 5 days
Stuart-Hobson Middle School FM-200445964 04 3/29/04 Stuart-Hobson Boiler Room URGENT URGENT URGENT!!!!!!!!!! Boiler #1 Replace safety valve, Valve keep popping. School will be without heat if repairs are not made today 3/29/04. boilers 2 and 3 are down March 29, 2004 March 29, 2004 0 days
Montgomery ES FM-200202795 02 3/29/04 Montgomery Boiler room Replace float assembly on condensate tank. Tank is overflowing, backing up in return lines, causing heat problems in classrooms. February 11, 2002 March 29, 2004 777 days
Beers Elementary School FM-200222891 /02 3/30/04 BEERS Boiler room Responed to no domestic hot water call December 19, 2002 March 30, 2004 467 days
Hine JHS FM-200446046 04 3/30/04 Hine Boiloer room Repair # 1 boiler , unit cut off in flame failure after it reaches temperture. March 30, 2004 March 30, 2004 0 days
Anacostia Senior High School FM-200341170 03 3/31/04 Anacostia Boiler Room Boiler #2 keep going off on purge, Boiler #1 has tubes replacement. No heat in Building. December 8, 2003 March 31, 2004 114 days
Anacostia Senior High School FM-200443812 04 3/31/04 Anacostia Boiler Room Boiler #1 need to be repair, out on flame failure. February 9, 2004 March 31, 2004 51 days
Garfield ES FM-200444811 04 3/31/04 Garfield Boiler room Replace Defective Automatic water feeder on steam boiler #1 , it will not shut the burner off doing the safety test blow down, Model # 51 HD March 4, 2004 March 31, 2004 27 days
Anacostia Senior High School FM-200444085 04 3/31/04 Anacostia Boiler room Repair # 1 and # 2 Boiler ,will not start, no heat. February 16, 2004 March 31, 2004 44 days
Anacostia Senior High School FM-200342158 /03 3/31/04 Anacostia Boiler Room Need Steamfitting Shop and HVAC Shop To put Boiler #3 back on line. See Requisition Form December 31, 2003 March 31, 2004 91 days
Savoy Elementary School FM-200445530 04 4/1/04 Savoy Boiler room Check and restore electrical service to mechanical equipment,service was down during the night. March 18, 2004 April 1, 2004 14 days
Hart Middle School FM-200124500 /01 4/3/04 (HART) ASBESTOS ASSESSMENT REQUIRED BOILER ROOM REPLACE EXISTING LIGHT FIXTURES WITH VAPOR PROOF FIXTURES DUE TO POOR LIGHTING & NO OPERABLE LIGHT FIXTURES IN THE MECH. RM. B26. ASBESTOS CODE A-CLEAR FOR REPAIR 12/11/01 BY HORNE ENGINEER: Z MAHMOOD November 20, 2001 April 3, 2004 865 days
Anacostia Senior High School FM-200446228 04 4/4/04 Anacostia Boiler Room Multi-Stack #2 control not working. April 1, 2004 April 4, 2004 3 days
Reed LC FM-200446314 04 4/5/04 Marie Reed L. C. BOILER ROOM Burners on boiler # 2 and 3 need to be adjusted. # 3 boiler request was submitted during the summer for repairs. April 5, 2004 April 5, 2004 0 days
Wilson High School FM-200442986 04 4/6/04 Wilson,W On Top of Boiler #3 Replace leaking Tee to main steam header drip leg. Top of tee 2" , bottom of Tee 1 1/2" and side of Tee 3/4" . 3/4" 2" __l__ 1 1/2" January 20, 2004 April 6, 2004 77 days
Ferebee-Hope Elementary School FM-200446321 04 4/6/04 (Ferebee-Hope) !!!VANDALISM!!! C-Building/1st Floor: Replace broken window near boiler room. April 5, 2004 April 6, 2004 1 day
Montgomery ES FM-200446313 04 4/6/04 Scoot Montgomery boiler room Asbestos assessment may be required on pipe insulation Repair 2" nipple on steam header April 5, 2004 April 6, 2004 1 day
Montgomery ES FM-200446257 04 4/6/04 (Montgomery) Asbestos Assessment Required. Boiler Room: Steam leak on boiler #1. Code A - clear for repairs as of 4/1/04 by Horne Eng. April 1, 2004 April 6, 2004 5 days
Woodson High School FM-200446493 04 4/8/04 Woodson Boiler Room Boiler #2 Repair or replace busted feed water line. Approximately 2" pipe. Pipe has no insulation. 04/08/2004 08:35 BLK - April 8, 2004 April 8, 2004 0 days
Bancroft Elementary School FM-200446302 04 4/8/04 Bancroft Boiler Room Boiler #3 Electric need repair, Boiler will not come on. April 5, 2004 April 8, 2004 3 days
Dunbar High School FM-200337378 03 4/8/04 Dunbar Staduim football stadium near first St. Have a large hole in the football field. It is 3ft. deep hole. , near the goal post. This area is where the old dunbar boiler room use to stand. Need to have this hole filled ASAP. September 12, 2003 April 8, 2004 209 days
Dunbar High School FM-200338456 03 4/8/04 Dunbar Garage Area Check Boiler for kitchen, Boiler will not reset. Off on high limit. October 3, 2003 April 8, 2004 188 days
Dunbar High School FM-200338508 03 4/8/04 Dunbar Boiler Room/Penthouse Repair damaged breaching on Boiler #2. October 5, 2003 April 8, 2004 186 days
Jessie LaSalle Elementary FM-200446578 04 4/12/04 LASALLE boiler room #2 boiler will not start. April 12, 2004 April 12, 2004 0 days
Wilson High School FM-200446597 04 4/12/04 Wilson, W. Boiler Room Repair 1/4" busted line on drip leg in Boiler Room. April 12, 2004 April 12, 2004 0 days
Deal Junior High School FM-200444688 04 4/12/04 Deal Boiler Room Repair or replace broken supply city water feed line for Boiler #1 and #2. Leaking very bad. 1" copper pipe, no insulation on pipe. Ok Hot !!!! March 2, 2004 April 12, 2004 41 days
Bunker Hill Elementary School FM-200446602 04 4/13/04 Bunker Hill Boiler Room Boiler #1 will not come on, boiler will not do anything. April 12, 2004 April 13, 2004 1 day
Gibbs Elementary School FM-200446619 04 4/13/04 GIBBS boiler room URGENT ATTENTION is needed Repair/replace inoperable sump pumps boiler room will flood. April 13, 2004 April 13, 2004 0 days
Lafayette Elementary School FM-200446556 04 4/13/04 (Lafayette) Repair 2" inch copper 45 in ceiling, outside of boiler room door. April 9, 2004 April 13, 2004 4 days
Cardozo High School FM-200442294 04 4/13/04 (Cardozo) Through-Out Building: Furnish boiler room staff with safety wire mesh glass. January 6, 2004 April 13, 2004 98 days
Malcolm X ES FM-200331695 03 4/14/04 Malcolm X Boiler Room (Dryer) Repair/replace leaking condensate bowl on pnuematic equipment dryer. June 12, 2003 April 14, 2004 307 days
Sousa Middle School FM-200446787 04 4/14/04 Sousa Temp Boiler , Trailer Restart temp. Boiler, unit will not start. April 14, 2004 April 14, 2004 0 days
Sousa Middle School FM-200446785 04 4/14/04 Sousa Boiler room Restore Prime to oil pumps, and lines. April 14, 2004 April 14, 2004 0 days
Reed LC FM-200446605 04 4/14/04 Marie Reed L.C. boiler room Repair leak on 1/2 inch copper line @ shut off valve on domestic hot water . Line has a pin hole size leak. April 12, 2004 April 14, 2004 2 days
Francis Junior High School FM-200442773 04 4/15/04 Francis Boiler Room Boiler #4 out on flame failure. Repair gas burner unit. This Boiler not operating. January 15, 2004 April 15, 2004 91 days
Ferebee-Hope Elementary School FM-200444861 04 4/15/04 Ferbee-Hope Boiler room Repair leak on 2" copper supply line to the domestic hot water tank from the gas fired boiler. March 5, 2004 April 15, 2004 41 days
Emery Elementary School FM-200446753 04 4/15/04 EMERY boiler room Troubleshoot boilers, will not start. No power to panel. April 15, 2004 April 15, 2004 0 days
Woodson High School FM-200443846 04 4/19/04 Woodson Front of Boiler Room by storage room Repair busted air handle unit coil in front of Boiler Room February 9, 2004 April 19, 2004 70 days
Raymond Elementary School FM-200446834 04 4/19/04 Raymond Boiler Room Pump water from Boiler room floor. Approximated 3' of water on floor. April 19, 2004 April 19, 2004 0 days
Drew Elementary School FM-200446810 04 4/21/04 Drew Boiler room Replace leaking Domestic hot water heater in the boiler room ,NO DOMESTIC HOT WATER April 19, 2004 April 21, 2004 2 days
Kimball Elementary School FM-200446994 04 4/23/04 Kimball Basement boiler room office Re-key door lock, need to secure door at sll time. Safety concern. Entry for staff only. Put the building master on entry door. April 22, 2004 April 23, 2004 1 day
Burrville Elementary School FM-200447032 04 4/28/04 BURRVILLE boiler room start chiller / low oil pressure April 23, 2004 April 28, 2004 5 days
Ludlow-Taylor ES FM-200447251 04 4/28/04 Lulow Taylor boiler room Correct problem with magnetic starter on chiller. Preventing chiller from starting. April 28, 2004 April 28, 2004 0 days
Reed LC FM-200445663 04 4/29/04 Reed Boiler Room Boiler #3 has leaking tubes. March 22, 2004 April 29, 2004 38 days
Gage-Eckington ES FM-200447287 04 5/1/04 GAGE-ECKINGTON Boiler room Check / correction problem with multi-stack unit continuously shut down on fault " Waiting for EX 2 external interlock" April 28, 2004 May 1, 2004 3 days
Orr Elementary School FM-200447097 04 5/3/04 ORR Boiler room Check and service A/C Chiller unit is surging during operation. April 25, 2004 May 3, 2004 8 days
Terrell Mc ES FM-200447489 04 5/5/04 Terrell, M.C. Boiler Room Repair or replace domestic hot water heater gas polit. No hot water. May 5, 2004 May 5, 2004 0 days
Walker-Jones EC FM-200447098 04 5/5/04 Walker Jones Boiler room Replace leaking vibrator eliminator on the condenser line of the chiller 6" April 25, 2004 May 5, 2004 10 days
Clark Elementary School FM-200447631 04 5/7/04 Clark Boiler room Service the chiller ,unit will not run ,cuts off on transmission failure May 7, 2004 May 7, 2004 0 days
Spingarn High School FM-200447131 04 5/7/04 Spingarn Outside back parking lot by boiler room Requesting fence be fixed on the back side. April 26, 2004 May 7, 2004 11 days
Woodson High School FM-200447619 04 5/8/04 Woodson,H D Boiler Room Boiler #1 tubes leaking. May 6, 2004 May 8, 2004 2 days
Beers Elementary School FM-200446885 04 5/10/04 Beers Tunnel by the old boiler room Asbestos assessment required. Repair 3' ruptured supply line in the tunnel by the old boiler room,and reinsulate pipe after the repairs are made, this line is part of the A/C system and will sweat when the A/C is on line. Asbestos Code A - Clear for repairs on 04/20/04. Horne Engineering - Bipin Nanavaty (RG 04/21/04) April 20, 2004 May 10, 2004 20 days
Stuart-Hobson Middle School FM-200341477 /03 5/11/04 Stuart-Hobson Basement boys shower room area Repair urinal leaking in boiler room. December 12, 2003 May 11, 2004 151 days
Winston EC FM-200447529 04 5/11/04 Winston Boiler room top floor Repair A/C unit , unit is surging. May 5, 2004 May 11, 2004 6 days
Montgomery ES FM-200338093 03 5/12/04 Montgomery Boiler Room Repair roof top Trane Air Condition unit. Unit not working. September 26, 2003 May 12, 2004 229 days
Benning Elementary School FM-200447815 04 5/12/04 Benning Boiler room Service Trane chiller located in the boiler room, unit is low on oil. ( Building has no windows) May 12, 2004 May 12, 2004 0 days
Ronald H. Brown MS FM-200447818 04 5/12/04 Ron Brown Boiler room Service chiller, unit is off on low oil pressure May 12, 2004 May 12, 2004 0 days
Patricia R Harris Ed Center FM-200447665 04 5/13/04 Harris P.R. Boiler room Check A/C chiller #1 on line and running, (noise like it pulling hard, will not load up above 60% , Strainers and checked. May 10, 2004 May 13, 2004 3 days
Emery Elementary School FM-200447756 04 5/13/04 EMERY BOILER ROOM Modular chiller will not start. May 11, 2004 May 13, 2004 2 days
Young Elementary School FM-200447689 04 5/18/04 Young C. boiler room Repair problem with chiller, will not stay read out indicating excessive purge and half phase. May 10, 2004 May 18, 2004 8 days
Brookland Elementary FM-200448026 04 5/19/04 Brookland Boiler Room Remove bolts from chill water strainer located above stand by pump in Boiler Room engineer was unable to remove bolts May 17, 2004 May 19, 2004 2 days
Sousa Middle School FM-200448202 04 5/22/04 Cleaning and removing of trash in boiler and oil pump room areas. Cleaned and removed trash in boiler room and pump areas. May 20, 2004 May 22, 2004 2 days
Ferebee-Hope Elementary School FM-200448035 04 5/24/04 Ferbee-hope Boiler room Replace 3' of 3/4" line in the rear of boiler # 3, chemical feed by-pass line. May 18, 2004 May 24, 2004 6 days
Leckie Elementary School FM-200448117 04 5/25/04 Leckie Boiler Room Boiler #1 and #2 has (1) one leaking tubes each. May 19, 2004 May 25, 2004 6 days
Wilkinson ES FM-200448420 04 5/26/04 Boiler room-Clean strainers and replace strainers so multi stack cooling unit could go bck on lie to chill the building. May 24, 2004 May 26, 2004 2 days
Slowe Elementary School FM-200448167 04 5/28/04 SLOWE BOILER ROOM Replace 6" leaking OS & Y valve on chill water line. leak can not be secure with securing the central A/C unit. May 20, 2004 May 28, 2004 8 days
Meyer Elementary School FM-200448060 04 6/1/04 MEYER boiler room Repair floor and wall cap refactory in boilers # 1 and 2 May 18, 2004 June 1, 2004 14 days
West Elementary School FM-200448377 04 6/2/04 West First floor by boiler room Maintenance room drain is stopped up. We have no way to pur dirty water and we do not have a snake. May 24, 2004 June 2, 2004 9 days
Brookland Elementary FM-200448616 04 6/3/04 Brookland Boiler room Repair or replace sump pump # 1 and #2 by the boiler room door June 1, 2004 June 3, 2004 2 days
Green Elementary School FM-200448518 04 6/3/04 GREEN ES boiler room Engineer stated that chiller display is indicating problem with starter transition switch and chiller will not stay on line. May 26, 2004 June 3, 2004 8 days
Brookland Elementary FM-200447052 04 6/3/04 Brookland Boiler Room Repair or replace condenser pump #3 motor in Boiler Room. HP-30 RPM-1770 PH-3 PF-82.0 Frame- 286T Amps.-73.6/36.8 Part #- F-391990-60 April 23, 2004 June 3, 2004 41 days
Meyer Elementary School FM-200448059 04 6/4/04 MEYER boiler room Pipe down safety valve on boiler # 2 May 18, 2004 June 4, 2004 17 days
Young Elementary School FM-200448916 04 6/4/04 (Young) Unstop airway drain out side of Boiler Room. June 4, 2004 June 4, 2004 0 days
Benning Elementary School FM-200448966 04 6/7/04 Benning boiler room Repair or replace purge control unit on the chiller, unit will not work auto or manual. June 7, 2004 June 7, 2004 0 days
Anacostia Senior High School FM-200448767 04 6/7/04 Anacostia Boiler Room Boiler #2 need repaving around burner. June 2, 2004 June 7, 2004 5 days
Kramer Middle School FM-200448700 04 6/8/04 Kramer Boiler Room Boiler #3 need refractory on front door repaving. June 2, 2004 June 8, 2004 6 days
Stevens Elementary School FM-200339427 /03 6/8/04 (Stevens) Asbestos Assessment Required. Boiler Room: Fabricate, and install new metal step on stairwell as you enter the boiler room from the inside of the building. The temporary step is loose. (Safety Hazard) Asbestos Code A - Clear for repairs on 10/18/03. Horne Engineering - Sheryll James (RG 10/29/03) October 24, 2003 June 8, 2004 228 days
Wilson High School FM-200447264 04 6/9/04 Wilson, W. Boiler Room-Pump Room Furnish 2" in line 150 PSI high pressure float thermostatic steam trap to high pressure condensate tank. April 28, 2004 June 9, 2004 42 days
Anacostia Senior High School FM-200448877 04 6/9/04 Anacostia Boiler Room Boiler #2 needs (1) 2 1/2" nipple 5" long replace on rear of Boiler. Need heat to remove nipple. June 4, 2004 June 9, 2004 5 days
Ronald H. Brown MS FM-200448968 04 6/10/04 Brown, Ron Break-In !!! Boiler Room 1) Repair or replace lock on Boiler Room Door. June 7, 2004 June 10, 2004 3 days
Eaton Elementary School FM-200449259 04 6/14/04 Eaton Boiler room Charge A/C unit, located in the boiler room June 13, 2004 June 14, 2004 1 day
Woodson High School FM-200449269 04 6/15/04 Woodson Boiler Room Repair or replace compressor in boiler room not working properly. June 14, 2004 June 15, 2004 1 day
Harris, C.W. ES FM-200448779 04 6/16/04 Harris C.W. Boiler room 1) Correct cause of Mod # 1 - compressor # 1 & # 2 Chiller- circuit breaker trips constantly ,units out on fault. 2) Correct cause of Mod # 4 compressor # 1 & # 2 freezestat has to be constantly reset. Units goes out in fault. June 3, 2004 June 16, 2004 13 days
Burrville Elementary School FM-200449354 04 6/16/04 Burrville Roof cooling tower / boiler room Check and correct cooling tower fan motor or controls , chiller is running high head pressure of 10 lbs,condenser leaving at 98 degrees, and returning at 98 degrees. Adjust control for cooling towere and check for proper operation. June 16, 2004 June 16, 2004 0 days
Benning Elementary School FM-200449001 04 6/17/04 Benning Boiler room Repair the purge control unit on the chiller, the unit does not work in auto, and engineer can not bleed it manual ,unit is surging. June 7, 2004 June 17, 2004 10 days
School WW High School FM-200447511 04 6/17/04 School Without Walls Boiler Room Replace blow down valve on Boiler #1. Pipe size3/4" and 3/4" valve. Pipe and Valve are corrosive. May 5, 2004 June 17, 2004 43 days
Woodson High School FM-200448959 04 6/17/04 Woodson Boiler Room Check cooling system, lose phase in system. June 6, 2004 June 17, 2004 11 days
Beers Elementary School FM-200447643 04 6/18/04 Beers Boiler room correct cause of inoperable compressor on the modular chiller #2 and #3 out on fault, onlyindication. May 7, 2004 June 18, 2004 42 days
Amidon Elementary School FM-200449378 04 6/18/04 Amidon First floor boiler room door Need locksmith to fix boiler room door, it will not lock properly. June 16, 2004 June 18, 2004 2 days
Roosevelt High School FM-200448479 04 6/21/04 Roosevelt Boiler Room Remove caps and plugs from water side of Boiler #1. Engineer unable to remove. May 25, 2004 June 21, 2004 27 days
Stevens Elementary School FM-200447515 04 6/23/04 Stevens Boiler Room Replace Blow Down Valve and pipe on Boiler #1 and #2. Pipes and valves size 3/4". Pipes and valves are corrosive. May 5, 2004 June 23, 2004 49 days
Coolidge High School FM-200228089 03 6/25/04 Coolidge Boiler Room Replace section of 4 inch pipe leaking in threads on condensate return line to D.A. tank in Boiler Room. Code A - clear for repairs as of 4/3/03 by Sylvia Grimes DCPS Safety. April 2, 2003 June 25, 2004 450 days
Coolidge High School FM-200444795 04 6/25/04 COOLIDGE SHS Install (1) one 3 " isolation valve on gas line in boiler room (low psi gas line) to isolate domestic hot water heater from line going to main bldg. March 3, 2004 June 25, 2004 114 days
John Burroughs ES FM-200338424 03 6/28/04 Burroughs Basement - Boiler Room 1) Re-hang exterior entrance door to Boiler Room. Asbestos Code A - Clear for repairs on 10/03/03. Horne Engineering - Troy Wicome (RG 10/08/03) October 2, 2003 June 28, 2004 270 days
Payne Elementary School FM-200449631 04 6/29/04 Payne Boiler Room Take off (4) four 2" nippers (3) on Boiler #1 and (1) off Boiler #2 If you facing Boiler #1 nippers on right Boiler #2 located on right hand side of Boiler June 22, 2004 June 29, 2004 7 days
Roosevelt High School FM-200448576 04 6/29/04 Roosevelt Boiler room Repair chiller , unit will not start. May 28, 2004 June 29, 2004 32 days
Clark Elementary School FM-200449525 04 6/29/04 Clark Boiler Room Remove 2" water leg on top of Boiler #1 and #2. Also, reomve plugs in cross tee's for Boiler #1 and #2. One plug per Boiler. June 20, 2004 June 29, 2004 9 days
Ronald H. Brown MS FM-200448682 04 6/30/04 Brown, Ron Boiler Room Check A/C unit in Boiler Room. Unit is leaking oil and goes out on manual reset. Unit is down. June 2, 2004 June 30, 2004 28 days
Brent Elementary School FM-200449663 04 7/6/04 Brent Boiler Room Boiler #1 replace refractory work June 23, 2004 July 6, 2004 13 days
Ballou Senior High School FM-200443411 04 7/6/04 Ballou Boiler Room Boiler #3 Repair leaking right rear water leg. Information: Boiler #3 Pacific Steel Hot Water #122037 January 30, 2004 July 6, 2004 158 days
Leckie Elementary School FM-200449778 04 7/8/04 Leckie Boiler Room Replace leaking tube Boiler #1 and #2 in fire box. June 25, 2004 July 8, 2004 13 days
Hardy Middle School FM-200450103 04 7/12/04 Rosario (Hardy) Boiler Room Remove hard to remove plugs (2) at tees. One at front of Boiler #1 and one at front of Boiler #3. This is needed to complete Boiler Readiness for inspection. July 10, 2004 July 12, 2004 2 days
Lafayette Elementary School FM-200450072 04 7/14/04 Lafatyette Basement Repair pipe in tunnel before entering boiler room leaking bad. July 9, 2004 July 14, 2004 5 days
Walker-Jones EC FM-200450116 04 7/14/04 Walker Jones Boiler Room Repair cooling system in building, Not working properly. July 12, 2004 July 14, 2004 2 days
Cardozo High School FM-200450193 04 7/15/04 Cardozo Boiler Room Repair or replace shaft on domestic hot water circulating pump and motor. Pump can not be turned on because of heavy water leaks- shaft is smaller and in between packing sizes which causes pump to leak. July 13, 2004 July 15, 2004 2 days
Webb Elementary School FM-200449547 04 7/15/04 Webb Boiler Room Replace 3" tubes in boiler #1Tubes are leaking. Boilers failed D.C. Inspection. June 21, 2004 July 15, 2004 24 days
Ronald H. Brown MS FM-200450432 04 7/19/04 Brown, Ron Boiler Room Repair oil leak on chiller. Vibrator leaking. Urgent !!!!! July 19, 2004 July 19, 2004 0 days
Cooke H.D. Elementary School FM-200449811 04 7/19/04 Cooke,H.D. Boiler Room Boilers #1,#2 and #3 failed D.C.Boiler Inspection because need to entend blow down pipe to drain. June 25, 2004 July 19, 2004 24 days
Plummer Elementary School FM-200450560 04 7/19/04 Plummer Boiler Room Boilers #2 Replace door refractory. Boiler Failed D. C. Inspection. July 19, 2004 July 19, 2004 0 days
Duke Ellington School FM-200450409 04 7/19/04 Remove all automatic blowdown valves on all boilers July 17, 2004 July 19, 2004 2 days
Gibbs Elementary School FM-200450528 04 7/20/04 Gibbs Boiler Room Replace wires from panel box to sump pump in Boiler Room. Wire shorted out. URGENT !!!!!! Boiler Room will be flooded if work not done soon. July 20, 2004 July 20, 2004 0 days
Malcolm X ES FM-200449777 04 7/21/04 Malcolm X Boiler Room Remove automatic blow down from Boilers Job completed. June 25, 2004 July 21, 2004 26 days
Ronald H. Brown MS FM-200449776 04 7/21/04 Brown, Ron Boiler Room Remove automatic blow down from Boilers Job completed. June 25, 2004 July 21, 2004 26 days
Francis Junior High School FM-200449813 04 7/22/04 Francis Boiler Room Boilers #1,#2, #3 ,#4,#5 and #6 remove automatic blow down and extend blow down pipe to drain. Boilers failed D.C. Inspection. June 25, 2004 July 22, 2004 27 days
Raymond Elementary School FM-200450317 04 7/22/04 Raymond Boiler Room Repair or replace Hi temp. senser on motor will not reset. Chiller down. July 15, 2004 July 22, 2004 7 days
Ludlow-Taylor ES FM-200450605 04 7/22/04 Ludlow-Taylor Boiler Room Boiler #2 remove large pieces of metal from water leg right rear of boiler,when facing boiler. July 22, 2004 July 22, 2004 0 days
Meyer Elementary School FM-200450563 04 7/23/04 Meyer Boiler Room Boilers #1 & #2 Replace refractory missing from tube doors. Boiler Failed D. C. Inspection. July 21, 2004 July 23, 2004 2 days
Brightwood Elementary School FM-200450403 04 7/26/04 Remove automatic blowdown valves on all 3 boilers, Job completed. July 17, 2004 July 26, 2004 9 days
Burrville Elementary School FM-200448993 04 7/26/04 Burrville Boiler Room Replace (3) leaking tubes in Boiler #1 Replace (1) leaking tubes in Boiler #2 June 7, 2004 July 26, 2004 49 days
Coolidge High School FM-200450830 04 7/28/04 Collidge Front and back door Need the doors fix because you can not in them. Need to go in the boiler room door to open the building. July 27, 2004 July 28, 2004 1 day
Francis Junior High School FM-200450849 04 7/29/04 Francis Boiler Room Remove automatic blow downs on Boilers #1 thru #6. Boilers failed D.C. Inspection. Duplicate Work Request July 27, 2004 July 29, 2004 2 days
Francis Junior High School FM-200450850 04 7/29/04 Francis Boiler Room Install extend blow downs on Boilers #1 thru #6. Boilers failed D.C. Inspection. Duplicate Work Request July 27, 2004 July 29, 2004 2 days
Jessie LaSalle Elementary FM-200451082 04 7/29/04 LaSalle ES - Boiler Room Boiler #1 Replace refractory in comustion chamber July 28, 2004 July 29, 2004 1 day
Bunker Hill Elementary School FM-200451080 04 7/29/04 Bunker Hill ES - Boiler Room Pump-Heating hot water, leaking July 28, 2004 July 29, 2004 1 day
Bunker Hill Elementary School FM-200451078 04 7/29/04 Bunker Hill ES - Boiler Room Boiler #2 Replace casing insulating July 28, 2004 July 29, 2004 1 day
River Terrace ES FM-200450213 04 7/30/04 1. Remove (8) eight 1- inch plugs from cross tees on boiler 1. 2. Remove (2) two 3 - inch caps from waterwalls on boiler 1 Removal requested to prepare boiler for annual inspection July 14, 2004 July 30, 2004 16 days
Amidon Elementary School FM-200450929 04 7/30/04 Amidon Need locksmith to fix boilerroom door, will not lock properly. July 28, 2004 July 30, 2004 2 days
Hardy Middle School FM-200451073 04 7/30/04 Hardy/ Filmore Boiler room Boilers # 1-5 , Remove automatic blowdown valves Job completed. July 29, 2004 July 30, 2004 1 day
Adams Elementary FM-200444932 04 7/30/04 ADAMS ES boiler room Provide one key for front door and boiler room entrance. March 8, 2004 July 30, 2004 144 days
Roosevelt High School FM-200226711 03 7/30/04 Roosevelt Boiler room office door Repair locking hardware on this door. Office should be secured. Asbestos Code A - Clear for repairs on 04/09/03. Horne Engineering - Roger Kager (RG 04/10/03) March 7, 2003 July 30, 2004 511 days
Browne Junior High School FM-200451090 04 7/31/04 Browne JHS - Boiler Room Boiler #1-5 failed - remove all automatic blowdown valves. Job completed. July 29, 2004 July 31, 2004 2 days
Deal Junior High School FM-200450561 04 8/2/04 Deal Boiler Room Boilers #1 & #2 Replace door refractory. Boiler Failed D. C. Inspection. July 21, 2004 August 2, 2004 12 days
Horace Mann Elementary School FM-200451221 04 8/2/04 Remove all automatic blowdown valves on all boilers Job completed. July 31, 2004 August 2, 2004 2 days
Patterson ES FM-200451223 04 8/2/04 Remove all automatic blowdown valves on all boilers Remove all blowdown. July 31, 2004 August 2, 2004 2 days
Murch Elementary School FM-200451222 04 8/2/04 Remove all automatic blowdown valves on all boilers Job completed. July 31, 2004 August 2, 2004 2 days
Truesdell Elementary FM-200449021 04 8/3/04 Truesdell Basement stairwell going to the boiler room The pipe is leaking water and it is about to bust. June 7, 2004 August 3, 2004 57 days
Whittier Elementary School FM-200119740 01 8/4/04 (WHITTIER) WHITTIER BOILER ROOM REPAIR OR REPLACE LIGHT FIXTURES. ROOM IS TOO DAR TO SEE OR READ GAUGES FOR PROPER OPERATION. TWO FIXUTRES ARE MISSING BALANES. Requestor Phone: 698-1750 ASBESTOS CODE A-CLEAR FOR REPAIR 10/12/01 BY HORNE ENGINEER SHARON VOSS August 30, 2001 August 4, 2004 1,070 days
Plummer Elementary School FM-200450972 04 8/6/04 Plumer Boiler room Need Hydro Test on #1 bolier to check for leaking tubes July 28, 2004 August 6, 2004 9 days
Stanton Elementary School FM-200451021 04 8/6/04 Stanton First grate near the boiler room The grate need welding before a kid fall in. July 28, 2004 August 6, 2004 9 days
Takoma Educational Center FM-200450856 04 8/9/04 Takoma Boiler Room Replace refactory in fire box on Boilers #1 and #2. Boilers failed D.C. Inspection. July 27, 2004 August 9, 2004 13 days
Shaed Elementary School FM-200450624 04 8/9/04 Shead Boiler Room Boilers #1 and #2 repair or replace refactory in fire boxes. Boilers failed D.C. Inspection. July 22, 2004 August 9, 2004 18 days
Brookland Elementary FM-200450632 04 8/10/04 Brookland Boiler Room Boilers #1 and #2 replace refactory in fire boxes. Boilers failed D.C. Inspection. July 22, 2004 August 10, 2004 19 days
Bruce-Monroe Elementary School FM-200450671 04 8/10/04 Bruce-Monroe Boiler Room Replace refractory in fire box boiler #2. Boiler failed D.C. Inspection. July 23, 2004 August 10, 2004 18 days
Ronald H. Brown MS FM-200450404 04 8/11/04 Replace all safety valves on boilers 1-6 valves were incorrectly installed. Extend blowdown piping from safety valves, and water column to floor drains July 17, 2004 August 11, 2004 25 days
School WW High School FM-200450608 04 8/12/04 School Without Walls Boiler Room Boilers #1 and #2 Install air vent on each boiler Boilers failed D.C. Inspection July 22, 2004 August 12, 2004 21 days
Garrison ES FM-200449814 04 8/16/04 Garrison Boiler Room Boilers #1,#2, #3 and #4 failed D.C.Boiler Inspection because burners need to be calibrated. June 25, 2004 August 16, 2004 52 days
Shepherd ES FM-200450855 04 8/17/04 Shepherd Boiler Room Calibrate burner on Boilers #1 and #2. Boilers failed D.C. Inspection. July 27, 2004 August 17, 2004 21 days
Anacostia Senior High School FM-200452784 04 8/18/04 Anacostia Boilere room Replace programmer for #1 boiler , boiler will light off when test fired . August 17, 2004 August 18, 2004 1 day
Tubman Elementary School FM-200341492 /03 8/19/04 Tubman Space 36 - boys restroom Repair water leak in restroom causing water to leak into boiler room over top of boiler # 2. December 12, 2003 August 19, 2004 251 days
Orr Elementary School FM-200452430 04 8/19/04 Orr Boiler room Repair chiller will not run cut off on (F6) High condenser refrigerant pressure. August 12, 2004 August 19, 2004 7 days
Anacostia Senior High School FM-200452871 04 8/19/04 Anacostia Boiler Room Check cooling tower,breaker keep tripping. It has a 100 Amp circuit breaker for the cooling tower. Breaker trips at least once a day. Recommend replace breaker with 150 Amp August 18, 2004 August 19, 2004 1 day
Roosevelt High School FM-200452946 04 8/25/04 Roosevelt Pool area Restored electrical service to lights and pool heating boiler. August 19, 2004 August 25, 2004 6 days
Aiton Elementary School FM-200453293 04 8/25/04 Aiton Boiler room Repace leaking Domestic hot water tank. Need electrician to hook up domestic hot water heater, heater is on site. Name: Smith Burkey Model # BC300760-Gas Ser# 760HA773024 BTU- HR300,000 252 US Gals August 25, 2004 August 25, 2004 0 days
Bowen Elementary School FM-200453369 04 8/26/04 Bowen Boiler room Check and correct fault problem with modular chillers. Strainers have been pulled and clean. August 26, 2004 August 26, 2004 0 days
Birney Elementary School FM-200450547 04 8/27/04 (Birney) FIRE CODE VIOLATION: 2nd Floor/Boiler Room: Repair emergency light. July 20, 2004 August 27, 2004 38 days
Bunker Hill Elementary School FM-200450329 04 8/27/04 (Bunker-Hill) FIRE CODE VIOLATION: Basement/Boiler Room: Defective emergency back-up lights. July 15, 2004 August 27, 2004 43 days
Drew Elementary School FM-200451876 04 8/27/04 Drew Boiler room Repair refractory around burner as per boiler inspector's request August 9, 2004 August 27, 2004 18 days
Roosevelt High School FM-200453549 04 8/27/04 Roosevelt Boiler Room Furnish 2 deaerator gaskets for Cleaver Brooks Spraymaster Deaerator. Model SMP-45 Serial DG-8244 Capacity 45,000 Date 1999 19" across 1/4" thick 08/27/2004 13:37 BLK - August 27, 2004 August 27, 2004 0 days
Gage-Eckington ES FM-200451050 04 8/31/04 Gage Eckington Boiler room R/R Refractory in the firebox of boiler #1 & 2 July 29, 2004 August 31, 2004 33 days
Jefferson JHS FM-200452339 04 8/31/04 Jefferson Boiler room Replace leaking relief valve on the hot water storage tank. as per the boiler inspector's request August 12, 2004 August 31, 2004 19 days
School WW High School FM-200337208 03 8/31/04 School W/O Walls Boiler room Replace 2" Gas cock valve on the # 2 boiler gas train, valve will not close.( per boiler inspector's request) September 10, 2003 August 31, 2004 356 days
King M L ES FM-200451335 04 8/31/04 KING Boiler # 1 Replace leaking flange gasket on safety valve discharge line on boiler # 1 August 3, 2004 August 31, 2004 28 days
Backus Middle School FM-200450859 04 9/1/04 (Backus) FIRE CODE VIOLATION: 1st Floor/Boiler Room: Replace exit light over exit door from incinerator room. July 27, 2004 September 1, 2004 36 days
Clark Elementary School FM-200452159 04 9/1/04 Clark Boiler room Boiler # 1 Repair refractory in combustion chamber August 11, 2004 September 1, 2004 21 days
Takoma Educational Center FM-200450863 04 9/1/04 Takoma Boiler Room Boilers #1 and #2 need Hydro test. Boilers failed D.C. Inspection. July 27, 2004 September 1, 2004 36 days
Langdon Elementary School FM-200452279 04 9/1/04 Landgon Fire Code Violation Basement Replace electrical panel cover in boiler room. Asbestos Code A - Clear for repairs on 08/12/04. DCPS Safety - Richard Gibson (RG) August 11, 2004 September 1, 2004 21 days
Langdon Elementary School FM-200452280 04 9/1/04 Landgon Fire Code Violation Basement Replace electrical panel cover in boiler room. Asbestos Code A - Clear for repairs on 08/12/04. DCPS Safety - Richard Gibson (RG) August 11, 2004 September 1, 2004 21 days
Langdon Elementary School FM-200452284 04 9/1/04 Landgon Fire Code Violation Basement Replace light switch cover at top of stairs in boiler room. Asbestos Code A - Clear for repairs on 08/12/04. DCPS Safety - Richard Gibson (RG) August 11, 2004 September 1, 2004 21 days
Hine JHS FM-200447315 04 9/1/04 Hine Boiler Room Repair chiller A/C unit that runs for 5 mins. and goes out on low suction. April 29, 2004 September 1, 2004 125 days
Kenilworth ES FM-200452297 04 9/1/04 Kenilworth FIRE CODE VIOLATION: First floor Emergency light not working in boiler room. August 11, 2004 September 1, 2004 21 days
Ludlow-Taylor ES FM-200451432 04 9/1/04 Ludlow-Taylor Fire Code Violation 603.1605.6 First Floor - Boiler Room 1) Electrical panel inaccessible. August 4, 2004 September 1, 2004 28 days
Jessie LaSalle Elementary FM-200451063 04 9/2/04 LaSalle ES - Boiler #2 Repair leak in combustion chamber July 28, 2004 September 2, 2004 36 days
Moten Elementary School FM-200453912 04 9/3/04 Moten Boiler Room Furnish the following materials for pumps: 6-pcs of tub size: 4X4 3ft.X3 inch X 20 inch wide 12 inch long 2 pcs plate 18" X 36" September 3, 2004 September 3, 2004 0 days
Burrville Elementary School FM-200453950 04 9/7/04 Burrville Boiler room Replace 8" rubber vibrator eliminator on the condenser suction side. September 4, 2004 September 7, 2004 3 days
Hine JHS FM-200454017 04 9/8/04 Hine Boiler room Repair # 2 chiller ,unit will not start off on motor current. September 8, 2004 September 8, 2004 0 days
Oyster Elementary School FM-200453894 04 9/9/04 Oyster First floor hall and boiler room Water is leaking from the ceiling near maintenance office also in boiler room. September 3, 2004 September 9, 2004 6 days
Woodson High School FM-200454780 04 9/13/04 Woodson Boiler Room Repair or replace B&G circulating pump, series 60 pump. Pump not working. September 13, 2004 September 13, 2004 0 days
Savoy Elementary School FM-200454819 04 9/16/04 Savoy Boiler room Boiler #3 flame failure. September 16, 2004 September 16, 2004 0 days
Adams Elementary FM-200454321 04 9/16/04 ADAMS ES Pipe all blowdowns to drains boilers 1, 2, 3, & 4 September 10, 2004 September 16, 2004 6 days
Webb Elementary School FM-200454826 04 9/16/04 Webb Boiler Room Boilers #2 out on flame failure. September 16, 2004 September 16, 2004 0 days
John Burroughs ES FM-200454807 04 9/17/04 Burroughs Boiler room Tap out mud leg on boilers September 15, 2004 September 17, 2004 2 days
Kramer Middle School FM-200454092 04 9/17/04 Kramer Boiler Room Check and repair Boiler #3, out on P3. Will not come on. Need to boil out boiler for reinspection. September 9, 2004 September 17, 2004 8 days
Moten Elementary School FM-200340413 /03 9/17/04 Moten Boiler Room Replace rusted 2" X 4" line on circulating pump1. November 18, 2003 September 17, 2004 304 days
Houston Elementary School FM-200454818 04 9/20/04 Houston Boiler Room Check Boiler #2, will not come on. September 16, 2004 September 20, 2004 4 days
Eliot Junior High School FM-200454822 04 9/20/04 Eliot Boiler Room Boilers #3 out on flame failure. September 16, 2004 September 20, 2004 4 days
Orr Elementary School FM-200454016 04 9/21/04 ORR Boiler room Repair # 1& # 2 boilers ,flame failure September 8, 2004 September 21, 2004 13 days
Moten Elementary School FM-200339333 /03 9/21/04 Moten Boiler room Replace vibration eliminator and about 2 feet of piping leading to vibration eliminator, both are rusted out. Pipe and pump #3 are leaking. Code A - clear for repairs as of 12/11/03 By Sylvia Grimes October 23, 2003 September 21, 2004 334 days
Spingarn High School FM-200455229 04 9/21/04 Spingarn Boiler Room Boiler #1 & #4 Replace 1/2" stud on door. Boiler #1 has (1) stud and Boiler #4 has (2) stud. September 21, 2004 September 21, 2004 0 days
Benjamin Banneker Academic HS FM-200455072 04 9/21/04 Banneker Boiler Room Remove plugs from water leg Boiler #2 and #3 September 19, 2004 September 21, 2004 2 days
Burrville Elementary School FM-200455241 04 9/23/04 Burrville Boiler room Replace tube in # 1 boiler ,tube was cut too short on one end, September 21, 2004 September 23, 2004 2 days
Woodson High School FM-200449809 04 9/23/04 Woodson Boiler Room Boiler #1and #2 refractory work needed. June 25, 2004 September 23, 2004 90 days
Brightwood Elementary School FM-200455660 04 9/24/04 Brightwood Boiler Room Repair or replace, Check Boilers #1 & #2 will not fire off. September 24, 2004 September 24, 2004 0 days
Cardozo High School FM-200455617 04 9/24/04 Cardozo Boiler Room Repair emergency shut off switch for boiler room, push button switch will not turn off burners and accessories. September 24, 2004 September 24, 2004 0 days
Sousa Middle School FM-200455521 04 9/25/04 Sousa Boiler Room Boiler # 3 Replace relief valve September 23, 2004 September 25, 2004 2 days
Tyler Elementary School FM-200448331 04 9/27/04 Tyler Boiler room Repair sump pump in the pit by # 1 boiler , pump discharges slow. May 24, 2004 September 27, 2004 126 days
Peabody Elementary School FM-200451865 04 9/27/04 Peabody Boiler room Remove automatic heat timers for boilers as oer boiler inspector request. Duplicate w/o cancelled 9/27/04 per B. Shaw August 9, 2004 September 27, 2004 49 days
Davis Elementary School FM-200454821 04 9/27/04 Davis Boiler Room Boilers #3 & 4 out on flame failure. September 16, 2004 September 27, 2004 11 days
Peabody Elementary School FM-200454824 04 9/27/04 Peabody Boiler Room Boilers #3 out on flame failure. Cancelled duplicated W/O per B. Shaw September 16, 2004 September 27, 2004 11 days
Moten Elementary School FM-200454305 04 9/28/04 MOTON ES Boilers # 2 repair damaged and missing refractory September 10, 2004 September 28, 2004 18 days
Spingarn High School FM-200454465 04 9/28/04 Spingran Boiler Room Repair 6" leaking steam line in Boiler Room. No insulation on pipe. September 13, 2004 September 28, 2004 15 days
Cardozo High School FM-200456020 04 9/29/04 CARDOZO SHS Remove automatic heat timers per DCMR boiler inspector to pass annual inspection September 29, 2004 September 29, 2004 0 days
Cooke H.D. Elementary School FM-200454820 04 9/29/04 Cooke, H.D. Boiler Room Boilers #1,2,3,4,5 & 6 out on flame failure. September 16, 2004 September 29, 2004 13 days
Maury Elementary School FM-200455513 04 9/30/04 Maury Boiler Room 1. Boilers 1 & 2 perform hydrostatic test September 23, 2004 September 30, 2004 7 days
Bancroft Elementary School FM-200450400 04 10/1/04 Replace leaking tubes in boiler # 2 July 17, 2004 October 1, 2004 76 days
Burrville Elementary School FM-200455242 04 10/1/04 Burrville Boiler room Boilers # 1& 2 need hydro test , as per boiler Inspector request September 21, 2004 October 1, 2004 10 days
Woodson High School FM-200456017 04 10/4/04 Woodson H.D. Boiler room Check chiller , unit will not start. September 29, 2004 October 4, 2004 5 days
Shaed Elementary School FM-200450625 04 10/4/04 Shead Boiler Room Boilers #1 and #2 replace leaking tubes. Boilers failed D.C. Inspection. July 22, 2004 October 4, 2004 74 days
Thomas Elementary School FM-200454828 04 10/4/04 Thomas Boiler room Replace 3/4" Nibco threaded brass gate valve for by pass on the chill water make-up line to boiler # 2 , valve is not holding. September 16, 2004 October 4, 2004 18 days
Moten Elementary School FM-200456429 04 10/5/04 Moten Boiler room Repair or replace varbirate eliminator on pump #2 October 4, 2004 October 5, 2004 1 day
West Elementary School FM-200450910 04 10/5/04 West Boiler Room Boiler #1 replace refactory in combustion chamber and on fire door. Boiler failed inspection. July 28, 2004 October 5, 2004 69 days
West Elementary School FM-200454421 04 10/6/04 West Boiler room HOT!!!!!!!!! Service the chiller , unit will surge at 45 percent with aload and must be set at 50 percent,unit has been purged , and strainer have been cleaned. September 12, 2004 October 6, 2004 24 days
Kimball Elementary School FM-200456557 04 10/6/04 KIMBALL ES Boiler # 1,2 ,3 & 4 replace blow down October 6, 2004 October 6, 2004 0 days
Reed LC FM-200454827 04 10/7/04 Reed Boiler Room Remove hand hole plate from Boiler #1. September 16, 2004 October 7, 2004 21 days
Watkins Elementary School FM-200450614 04 10/7/04 Watkins Boiler Room Boilers #1 and #2 repair refractory work needed around morrison tube. Boilers failed D.C. Inspection. July 22, 2004 October 7, 2004 77 days
Langdon Elementary School FM-200454830 04 10/8/04 Langdon Boiler Room Boiler #2 tube replacement. September 16, 2004 October 8, 2004 22 days
Thomas Elementary School FM-200456564 04 10/8/04 Thomas Boiler Room Correct cause of improper operation of LWCO and Pump Controller on Boiler #2 October 7, 2004 October 8, 2004 1 day
Johnson JHS FM-200454803 04 10/11/04 Johnson Boiler room Boilers # 1 &3 Repair refractory. September 15, 2004 October 11, 2004 26 days
Moten Elementary School FM-200456493 04 10/13/04 Moten Boiler Room Boiler #1 & #2 off on flame failure. October 5, 2004 October 13, 2004 8 days
Patricia R Harris Ed Center FM-200456744 /04 10/15/04 Harris, P.R. Boiler Room Check and survey faulty purge unit- on chiller #1 unit surging continuously. October 13, 2004 October 15, 2004 2 days
Woodson High School FM-200456850 /04 10/17/04 WOODSON, H.D. boiler room Remove tubes from waterside of boilers # 1 and 2 October 15, 2004 October 17, 2004 2 days
Maury Elementary School FM-200454304 04 10/18/04 MAURY ES Boilers 1 & 2 repair refractory in combustion chamber September 10, 2004 October 18, 2004 38 days
West Elementary School FM-200445729 04 10/19/04 (West) 1st Floor/Learning Center, and Main Office:s Need three (3) key entry lock for vault, boiler room, and main office restroom. March 23, 2004 October 19, 2004 210 days
Bruce-Monroe Elementary School FM-200457185 /04 10/20/04 Bruce-Monroe Boiler Room Repair or replace burner on Boiler #2. Burner shutting of on flame failure. Note: Chemical are in boiler for Boil-out. Hot !!!!! October 20, 2004 October 20, 2004 0 days
Terrell Mc ES FM-200450155 04 10/20/04 Terrell, M.C. Boiler Room Furnish motor for air handler unit for cooling. July 13, 2004 October 20, 2004 99 days
Patricia R Harris Ed Center FM-200457023 /04 10/20/04 Harris P.R. Boiler room Replace cutler hammer control for hot water standby pump Ser.# Al # A10DG0: Size 2: PH:3; Amps 45: HP: 15: Volts: 230 HVAC Shop requested that electrician to check pumps, pump has lost L3, single phasing pump. October 19, 2004 October 20, 2004 1 day
Orr Elementary School FM-200457132 /04 10/20/04 ORR Boiler room Repair air compressor in the boiler room . October 20, 2004 October 20, 2004 0 days
Truesdell Elementary FM-200457135 /04 10/20/04 Truesdell Boiler Room Boiler #2 Flame failure. October 20, 2004 October 20, 2004 0 days
Sousa Middle School FM-200456739 /04 10/21/04 Sousa Boiler Room Boiler #3 flame failure on L-13 open. October 13, 2004 October 21, 2004 8 days
Payne Elementary School FM-200457209 /04 10/21/04 Payne Boiler Room Remove emergency switch box from boiler room to outside of hall by boiler room door. Emergency switch box is loose. See Engineer. October 21, 2004 October 21, 2004 0 days
King M L ES FM-200457104 /04 10/21/04 King Boiler Room Boiler #1 and #2 repair refractory. October 19, 2004 October 21, 2004 2 days
King M L ES FM-200457106 /04 10/21/04 King Boiler Room Boiler #1 and #2 Perform hydrostatic test October 19, 2004 October 21, 2004 2 days
Tubman Elementary School FM-200450610 04 10/22/04 Tubman Boiler Room Boilers #1 and #2 repair or replace buckled doors both overfiring. Boilers failed D.C. Inspection. July 22, 2004 October 22, 2004 92 days
Montgomery ES FM-200457184 /04 10/22/04 Montgomery Boiler Room Replace missing nipple and cap on header. Steam come out of header when boilers are in operation. October 20, 2004 October 22, 2004 2 days
Tubman Elementary School FM-200457141 /04 10/22/04 Tubman Boiler Room Fabricate bracket for pull chains for safety valve on all Boilers October 20, 2004 October 22, 2004 2 days
Kramer Middle School FM-200457045 /04 10/22/04 Kramer Basement A key or some object is broken off in lock to boiler / custodial office. Vandalism October 19, 2004 October 22, 2004 3 days
Aiton Elementary School FM-200456852 /04 10/22/04 AITON ES boiler room Replace leaking tubes boiler # 1 and 2 1. Boiler # 1 tubes leaking in rear. 2. Boiler # 2 tubes leaking in front. Tubes are marked on boiler # 2. October 15, 2004 October 22, 2004 7 days
Webb Elementary School FM-200450615 04 10/22/04 Webb Boiler Room Bioler #1 and #2 repair or replace corroded rear right hand hole and buckled d