Urgent Repair Requests Opened in November 2003 (11) | School | Description | Open Date |
| Patricia R Harris Ed Center | FM-200339817 11/3/03 (Harris, P.R./W.B. Patterson) !!!URGENT!!! 3rd Floor/Stairwell #4: Replace flush valve in teachers bathroom. | November 3, 2003 |
| Shaw JHS | FM-200339916 11/5/03 Shaw Basement Hall and Cafeteria Safety Reinsoluate 3 valves, (2) valves in basement hall and (1) valve in cafeteria. Asbestos Code A - Clear for repairs on 11/05/03. DCPS Safety - Richard Gibson (RG) Asbestos Code A - Abated and cleared for repairs on 08/14/06 by Leroy Mniton Jr per Goel Construction Safety Office 202-576-8962. Note: This work order was extended due to a re-occurance of condensation leaks. | November 5, 2003 |
| Patricia R Harris Ed Center | FM-200339985 11/5/03 (Harris, P.R./W.B. Patterson) Parking lot lights: Repair lights on parking lot that is very dark when the after/care is dismissed. (Safety Hazard) | November 5, 2003 |
| Turner Elementary School | FM-200340155 11/10/03 (Turner) !!!URGENT!!! Cafeteria: Repair outlet on wall where internet outlet was connected. | November 10, 2003 |
| Ferebee-Hope Elementary School | FM-200340282 11/14/03 (Ferebee-Hope) !!!VERY URGENT!!! D-Building 2nd Floor/Exit Stairwell: There is no glazing compound around window to secure frame; window pane attempting to fall out due to strong winds. | November 14, 2003 |
| Johnson JHS | FM-200340293 11/14/03 (Johnson Jr.) !!!VERY URGENT!!! 2nd Floor/Room #233: Window pulled away from the frame, attempting to fall; due to heavy winds. | November 14, 2003 |
| Green Elementary School | FM-200340626 11/21/03 (Green) Exterior of Building: Repair concrete walk-way near main entrance Asbestos Code A - Clear for repairs on 11/21/03. DCPS Safety - Richard Gibson (RG) | November 21, 2003 |
| Cook J.F. Elementary School | FM-200340728 11/25/03 (Cook, J.F.) !!!VERY URGENT!!! 1st Floor/Room #101: Live steam coming from radiator. | November 25, 2003 |
| Patricia R Harris Ed Center | FM-200340737 11/25/03 (Harris, P.R.) Asbestos Assessment Required. Roof Top: Install roof top security lights over small gym; children exit after 6:00 p.m. Southeast side of the building. (Safety Hazard) Asbestos Code A - Clear for repairs on 11/26/03. Horne Engineering - Bjarne Smith (RG 12/01/03) | November 25, 2003 |
| Stanton Elementary School | FM-200340725 11/25/03 (Stanton) !!!VERY URGENT!!! Through-Out Building: Live steam coming from radiators in the following: Rooms #A-4, A-8, A-9, A-13, 106 107, & 109. (Univents blowing cold air) | November 25, 2003 |
| Marshall Educational Center | FM-200340794 11/28/03 Marshall Outside Lights Repair or replace outside lights on Pool Patio, Light are not working properly. Repair or replace lights on step area leaking to pool. Safety hazard " See Mr. Beckett for more information." | November 28, 2003 |
Routine Repair Requests Opened in November 2003 (50) | School | Description | Open Date |
| Smothers ES | FM-200339812 11/3/03 (Smothers) Asbestos Assessment Required. 1st Floor/Auditorium: Repair or replace wood flooring buckled up, and wood planks coming up from the auditorium back door leading to playground, and parking area. Asbestos Code A - Clear for repairs on 11/04/03. Horne Engineering - Troy Wilcome (RG 11/17/03) | November 3, 2003 |
| Hine JHS | FM-200339967 11/5/03 Hine Boiler Room Unstop floor drain behind Boiler #3 | November 5, 2003 |
| Amidon Elementary School | FM-200339915 11/5/03 Amindon Boiler room Repair leaking return pump for the # 3 boiler. | November 5, 2003 |
| Duke Ellington School | FM-200339936 11/5/03 (Ellington) North & South Stairs: Repair or replace hand rails, mount to stairwell walls. Asbestos Code A - Clear for repairs on 11/12/03. Horne Engineering - Troy Wilcome (RG 11/14/03) | November 5, 2003 |
| Patricia R Harris Ed Center | FM-200339986 11/5/03 (Harris, P.R./W.B. Patterson) Asbestos Assessment Required. Ground Floor Main Entrance/Playground: Repair exterior door that will not open on stairwell #5. Unable to secure door while open on stairwell #4. | November 5, 2003 |
| Raymond Elementary School | FM-200339974 4 11/5/03 (Raymond) !!!EMERGENCY!!! Asbestos Assessment Required. 1st Floor/Cafeteria: Ceiling has fallen; plaster ceiling is on the floor in cafeteria where students have lunch. Asbestos Code A - Clear for repairs on 09/05/03. Horne Engineering - Troy Wilcome (RG 11/07/03) | November 5, 2003 |
| Shaw JHS | FM-200339941 11/5/03 Shaw First floor gym Preparation for basketball season: install lights and covers in gym (no lights). Asbestos Code A - Clear for repairs on 11/05/03. Horne Engineering - Troy Wilcome (RG 11/12/03) | November 5, 2003 |
| Horace Mann Elementary School | FM-200340044 11/6/03 (Mann) Asbestos Assessment Required. Cafeteria: Need repair to floor, water damage, carpet mildew, and floor coming away from the walls. Asbestos Code A - Clear for repairs on 11/07/03. Horne Engineering - Bipin Nanavaty (RG 02/03/04) | November 6, 2003 |
| Cardozo High School | FM-200340012 11/6/03 (Cardozo) Asbestos Assessment Required. Dugout home team Repair ceiling to stop rain water from leaking into light fixture. | November 6, 2003 |
| Walker-Jones EC | FM-200340009 11/6/03 Walker - Jones Boiler Room Boiler #2 Flame failure. | November 6, 2003 |
| Shaed Elementary School | FM-200340050 11/6/03 (Shaed) 3rd Floor/Hallway: Newly installed metal door needs window cut in it. | November 6, 2003 |
| Wilson High School | FM-200340041 11/6/03 (Wilson, W.) Asbestos Assessment Required. 2nd Floor/Room #215: Repair or replace classroom door that will not close properly. Asbestos Code A - Clear for repairs on 11/07/03. Horne Engineering - Bipin Nanavaty (RG 11/14/03) | November 6, 2003 |
| Meyer Elementary School | FM-200340007 11/6/03 Meyer First floor room 102 A broken window need to be replaced. | November 6, 2003 |
| Reed LC | FM-200340068 11/7/03 Reed Boiler Room A mechanic from the heat shop needs to come and adjust the burners on Boiler #2 and #3. Boiler #2 will cut off if it is put into high fire. Boiler #3 has incomplete combustion. Work order for Boiler #3 was put in during Summer cleaning. | November 7, 2003 |
| Powell Elementary School | FM-200340083 11/7/03 Powell Second floor room 211 and hallway outside room 211 Repair roof leak in room 211 and outside room 211. Asbestos Code A - Clear for repairs on 11/10/03. Horne Engineering - Bipin Nanavaty (RG 11/12/03) | November 7, 2003 |
| Bancroft Elementary School | FM-200340089 89 11/7/03 Bancroft First floor Open space Replace light fixture in the bathroom (girls) near franklin room. Asbestos Code A - Clear for repairs on 11/12/03. Horne Engineering - Tony Marcolin (RG 11/14/03) | November 7, 2003 |
| Takoma Educational Center | FM-200340054 11/7/03 Takoma Boiler Room Replace locking bar circulating pump and B&G pump on storage tank. | November 7, 2003 |
| Shepherd ES | FM-200340094 11/7/03 Sheperd Second floor room 210 Asbestos check requested for walls to be painted. Lead & Asbestos Code A - Clear for repairs on 11/10/03. Horne Engineering - Edward Rodriguez (RG 11/12/03) | November 7, 2003 |
| River Terrace ES | FM-200340123 11/10/03 River Terrace Boiler room NO HEAT Repair # 2 burner ,will not start. # 1 burner is down also ( contractors) | November 10, 2003 |
| Meyer Elementary School | FM-200340213 11/12/03 (Meyer) 2nd Floor/Room #216: Roofing tar is penetrating through the ceiling. Asbestos Code A - Clear for repairs on 11/13/03. Horne Engineering -Tony Marcolin (RG 11/14/03) | November 12, 2003 |
| Moten Elementary School | FM-200340185 11/12/03 Moten Fourth Floor - 418,419,420 and 421. 1) All outlets are out in the above rooms and in room 421 the lights are out also. | November 12, 2003 |
| Ferebee-Hope Elementary School | FM-200340252 11/13/03 (Ferebee-Hope) Outside Field/Ball Field: Replace 120 lights and covers | November 13, 2003 |
| Hine JHS | FM-200340490 11/13/03 (Hine) 1st Floor-Lobby Replace two broken windows | November 13, 2003 |
| Langdon Elementary School | FM-200340235 11/13/03 Langdon Boiler Room Replace 3/4" gate valves located on the hot and cold water supply to service sink in Boiler, At present time there is no water in Boiler Room. | November 13, 2003 |
| Park View ES | FM-200340256 11/13/03 (Parkview) Pre-K Classroom: Due to very high winds, window blown out. | November 13, 2003 |
| Raymond Elementary School | FM-200340223 3 11/13/03 Raymond Boiler Room Furnish materials to repair Boilers. Fireye combustion control and Programmer E P 160 and Display E D 510 | November 13, 2003 |
| Walker-Jones EC | FM-200340243 11/13/03 (Walker Jones) 1st Floor/Main Office: Repair or replace ceiling tile due to water damage; staff will replace ceiling tile needed on-site. Staff will replace ceiling tile needed Asbestos Code A - Clear for repairs on 11/14/03. Horne Engineering - Tony Marcolin (RG 11/17/03) | November 13, 2003 |
| Marshall Educational Center | FM-200340276 11/14/03 Marshall Pool Entrance Pool entrance to filter room, chemical room not well lite. Causing a hazard for staff walking through area. | November 14, 2003 |
| Cardozo High School | FM-200340362 11/17/03 Cardozo Repair plumbing in stadium. | November 17, 2003 |
| Draper Elementary School | FM-200340433 11/18/03 (Draper) 1st Floor Hallway Stairwell/Parking Lot Side: Weld leaking pipe coming from univent in hallway. Asbestos Code A - Clear for repairs on 11/19/03. Horne Engineering - Bipin Nanavaty (RG 11/20/03) | November 18, 2003 |
| Stanton Elementary School | FM-200340507 11/19/03 Stanton Tunnel, cafeteria and kitchen The place is flooding need someone to come and unstop drain. | November 19, 2003 |
| Reed LC | FM-200340494 11/19/03 (Reed) Drains are stopped up in the following area's: 18th Street, UPO Playground, and Early Childhood Playground. | November 19, 2003 |
| Deal Junior High School | FM-200340481 11/19/03 Deal First floor room 105 Replace damage wooden door to storage class room with metal door and new lock in. Unable to secure wooden door. Code A-clear for repair by DCPS Charles Buchanan on 11-20-03 | November 19, 2003 |
| Aiton Elementary School | FM-200340514 11/20/03 Aiton Boiler roomm Replace 1" leaking relief valve on the dometic hot water tank. | November 20, 2003 |
| Wilson High School | FM-200340575 11/20/03 Wilson, W. Third floor rooms 307 and 318 Repair loose wood in the floors in rooms 307 and 318. Asbestos Code A - Clear for repairs on 11/21/03. Horne Engineering - Tony Marcolin ) (RG 12/01/03. | November 20, 2003 |
| Meyer Elementary School | FM-200340517 11/20/03 Meyer 1) Inspect the entire building including the roof for water leaks. Initiate repair. Poc - Eric Dreher - 202-438-3339 | November 20, 2003 |
| Green Elementary School | FM-200340644 11/21/03 (Green) 1st Floor/Multipurpose Room: Replace light bulbs; ceiling is very high. | November 21, 2003 |
| Wilson High School | FM-200340609 11/21/03 (Wilson, W.) 1st Floor/Auditorium Hallway: Water coming down the wall, below is an electrical box. Please repair now. | November 21, 2003 |
| Hine JHS | FM-200340635 11/21/03 Hine Boiler Room Replace (1) 2 1/2" gas manifold pressure gauge 0 - 15 in H2O on Boiler #3. | November 21, 2003 |
| Slowe Elementary School | FM-200340627 11/21/03 Slowe 2nd Floor Room #201 Replace bearing in univent on shaft size one set # BRG00115A | November 21, 2003 |
| Eastern High School | FM-200340632 11/21/03 (Eastern) Grounds/ Stadium Storage Room: Repair newly installed space heater, this would protect irrigation pipes inside this room from the cold. (This repair will support the Turkey Bowl (Football Game) to take place on November 27, 2003. | November 21, 2003 |
| Green Elementary School | FM-200340645 11/21/03 (Green) 1st Floor/3rd Floor Stairwell: Replace tread plates on steps. Asbestos Code A - Clear for repairs on 11/24/03. Horne Engineering - Philp Connolly (RG 11/26/03) | November 21, 2003 |
| West Elementary School | FM-200340616 11/21/03 West Boiler Room Air Handle Unit #2 Replace inline circulating pump coupling is busted and motor will not run. Name - Taco No. 1610CININO Amp 4.75 Pump will not run. | November 21, 2003 |
| Green Elementary School | FM-200340624 11/21/03 (Green) Exterior of Building: Paint handrails leading to front entrance door. Asbestos Code A - Clear for repairs on 11/24/03. Horne Engineering - Philp Connolly (RG 11/25/03 ) | November 21, 2003 |
| Bunker Hill Elementary School | FM-200340649 11/24/03 Bunker Hill Boiler Room Repair or replace domestic hot water heater, water heater is leaking very bad. | November 24, 2003 |
| Takoma Educational Center | FM-200340680 11/24/03 (Takoma) 3rd Floor/Room #210: At the time of heavy rain storms, the roof leaks in the classroom area, coming through the ceiling. Asbestos Code A - Clear for repairs on 11/25/03. Horne Engineering - Sophia Kapranos (RG 12/01/03) | November 24, 2003 |
| Shaed Elementary School | FM-200340727 11/25/03 Shaed Boiler room Repair the air compressor, the does not have any current. | November 25, 2003 |
| Patricia R Harris Ed Center | FM-200340739 11/25/03 (Harris, P.R.) Asbestos Assessment Required. Roof Top: Check light fixtures on the roof top, around the building; new bulbs were replaced and the lights did not come on. Some light fixtures have water in them. Asbestos Code A - Clear for repairs on 11/26/03. Horne Engineering - Bjarne Smith (RG 12/01/03) | November 25, 2003 |
| Amidon Elementary School | FM-200340749 11/25/03 (Amidon0 1st Floor/Gym: Exit lights in the ceiling need to be replaced. | November 25, 2003 |
| Whittier Elementary School | FM-200340764 11/26/03 Whittier Boiler room Repair or replace air compressor ,motor is locked up Nat Bd # 6003 WP 160 HD 120 year built 1960 | November 26, 2003 |