| Ferebee-Hope Elementary School | FM-200208837 6/3/02 Ferebee-Hope 1. Asbestos Assessment Reqd. 1st Floor Family Service (D Bldg. Room 20] 2. Replace wooden door frame---existing door frame is beyond repair [file room holding sensitive records]. Asbestos Code A - Clear for repairs on 06/06/02. DCPS Safety - Leroy Minton Jr. (RG 06/06/02) | June 3, 2002 |
| Macfarland Middle School | FM-200209223 09223 6/7/02 MacFarland ****Urgent**** 1. Asbestos Assessment Reqd. 1st Floor Auditorium 2. Survey for installation of electrical outlets in auditorium to support 6 to 8 a/c units which will be installed in time for graduation exercise next week---[Mrs. Colin Powell is the guest speaker]. Asbestos Code A - Clear for repairs on 06/07/02. Horne Engineering - Bipin Nanavaty (RG 06/10/02) | June 7, 2002 |
| Ferebee-Hope Elementary School | FM-200209242 6/7/02 Ferebee-Hope ****Urgent**** 2nd Floor D Bldg. computer Room Experienced burning ballasts that need replacement. Have isolated the area. | June 7, 2002 |
| Eastern High School | FM-200209285 6/11/02 Eastern Sub-basement Mechanical Room Furnish safety relief valves for domestic hot water tank. | June 11, 2002 |
| Cook J.F. Elementary School | FM-200209395 6/12/02 Cook, J.F. !!! Emergency !!! Second (2nd) Floor - Classroom #202 Air Conditioner Unit is Tripping the Electricity on and off. Safety Hazard. | June 12, 2002 |
| Eastern High School | FM-200209378 6/12/02 (Eastern) !!!!!!!!Urgent!!!!!!!! 1st Floor/Room #148: Replace faucets not holding on sink; leaking on down in-to the book room. Mr. Dickerson did not indicate leak causing any flooding. Asbestos Code A - Clear for repairs on 06/13/02. DCPS Safety - Leroy Minton Jr. (RG 06/14/02) | June 12, 2002 |
| Stevens Elementary School | FM-200209639 9 6/14/02 Stevens 1. Asbestos Assessment Reqd. 1st Floor Room #3 2. Need new wood replacement door and door jamb---old wooden door is rotted & dangerous. Code A-clear for repair by Horne Engineer ( Stephen Caldwell )on 07/09/02 DCPS CE Buchanan | June 14, 2002 |
| Johnson JHS | FM-200209667 7 6/17/02 (Johnson Jr.) ***Emergency*** 4th Floor Stairwell: Due to break-in, skylight broke and hanging from the ceiling; staff concerned with skylight falling to the floor. (Safety hazard) | June 17, 2002 |
| Turner Elementary School | FM-200210148 6/24/02 (Turner) !!Urgent!! Asbestos Assessment Required. New side/Old side: Service window units through-out buildings. Asbestos Code A- Cleared for repairs on 01-15-04 by Leroy Minton Jr (LM/01-15-04) Safety Office. 202-576-8962. | June 24, 2002 |
| Johnson JHS | FM-200210230 6/25/02 Johnson ****Urgent**** 1. Asbestos Assessment Reqd. 1st, 3rd & 4th Floors 2. Repair or install dedicated breakers to support the a/c units, because breakers are tripping in the following rooms, when the a/c is on: 1st floor library, room 154, nursing office, 102, 103, counselor's suite A100, principal's office & main office; 3rd floor rooms 302, 303 & 315; 4th floor rooms 401, 402 & 404. The high heat is affecting staff that is working in the above-listed areas. units are on: Code A-clear for repair by Horne Engineer ( Bipin Nanavaty ) on 06/26/02 | June 25, 2002 |
| Shepherd ES | FM-200210272 6/25/02 Shepherd 1. Asbestos Assessment Reqd. Areas Throughout the Building/Old & New Wings 2. All windows throughout old and new wings & windows facing the pre-K area on the 3rd floor. POC: Alfred Coleman (202)439-8276 Roofing/Glazing Shop Code A-clear for repair by Horne Engineer ( Edward Edoriguez ) on 06/26/02 Special Note: The roofing Shop will be able to continue with their work as long as plastic is on the ground below the work area. The USACE Contractor well clean the area below each day after the glazing shop completes their work. This is the only way the work can proceed. Sheila R. Howard- DCPS Safety- 06/26/02 Tracking # 14072 # 1140 | June 25, 2002 |
| Takoma Educational Center | FM-200210531 6/27/02 Takoma 1. Asbestos Assessment Reqd. 2nd Floor Room 143 [Computer Lab] 2. Repair breaches in walls behind the entrance door. Code A-clear for repair by DCPS Safety Leroy Minton on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
| Hine JHS | FM-200210535 6/27/02 (Hine) ***Very Very Urgent*** 1. Asbestos assessment required. Recreation Stairwell: Repair or replace floor and broken steps; a metal piece is missing from steps. A parent/visitor fell on the stairs this morning. Code A-clear for repair by Leroy Minton of DCPS Safety on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
| Hine JHS | FM-200210537 6/27/02 (Hine) ***Very Very Urgent*** 1. Asbestos assessment required. Recreation Stairwell: Lights has short from electrical panel box; unable to see in this area. A parent/visitor fell on these stairs this morning, as there is very little light to see. Code A-clear for repair by Leroy Minton of DCPS Safety on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
| Eliot Junior High School | FM-200210488 6/27/02 Eliot ****Urgent**** 2nd Floor Library The roof-top a/c unit is not cooling the library area. The library area will be in used during the summer-school session. | June 27, 2002 |
| Turner Elementary School | FM-200210530 6/27/02 (Turner) ***Very Very Urgent*** 1. Asbestos assessment required. Ground Floor/Cafeteria: Repair or replace exit door; The repairmen says there should be a new door installed, as this door is beyond repair. Code A-clear for repair by Leroy Minton of DCPS Safety on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
Routine Repair Requests Opened in June 2002 (30) | School | Description | Open Date |
| Orr Elementary School | FM-200208895 6/4/02 Orr Boiler Room Check and replace sump pump, #1 pump will not work. Flooding boiler room. | June 4, 2002 |
| Deal Junior High School | FM-200208957 6/4/02 Deal 1. Asbestos Assessment Reqd. 2nd Floor Room 213 2. Replaster and paint the ceiling which was damaged by a water leak---the leak has been resolved. Asbestos & Lead Code A - Clear for repairs on 06/05/02. Horne Engineering - Donald Maglienti \ Stephen Caldwell (RG 06/0502) | June 4, 2002 |
| Turner Elementary School | FM-200208878 6/4/02 Turner 1. Asbestos Assessment Required. Throughout Building 2. Survey, service & install window a/c and portable a/c units in the classrooms and areas listed on two attached sheets. [Classroom 215 for provision & installation of an a/c unit has already been cleared per FM-200205923] Asbestos Code A - Clear for repairs on 06/05/02. Horne Engineering - Troy Wilcome (RG 06/05/02) | June 4, 2002 |
| Wilkinson ES | FM-200208995 995 6/5/02 Wilkinson 1st Floor Gym Area [#66 Passageway] Replace two damaged flourescent light fixtures. Damage was the result of water. | June 5, 2002 |
| Turner Elementary School | FM-200209225 6/7/02 (Turner) ****Emergency**** 1. Asbestos assessment required. 1st Floor/Room #100: Ceiling badly damaged from a previous leak. Staff is concerned of the conditions and the possibility of falling. (Pending carpet cleaning) Asbestos Code A - Clear for repairs on 06/07/02. Horne Engineering - Stephen Caldwell (RG 06/10/02) | June 7, 2002 |
| Ballou Senior High School | FM-200209298 6/11/02 Ballou All Corridors 1) Remove the old ballast lights that were left installed and live behind the new acoustical drop ceiling and lights in the cooridors. Poc: Donna Ellis - 202-497-1527 Asbestos Code A - Clear for repairs on 06/11/02. Horne Engineering - Troy Wilcome (RG 06/12/02) | June 11, 2002 |
| Watkins Elementary School | FM-200209292 2 6/11/02 Watkins Boiler room 1. Asbestos assessment required. 2. Replace insulation on the inside of the front of the #2 boiler door. Asbestos Code A - Clear for repairs on 06/20/02. Horne Engineering - Bipin Nanavaty ( RG 06/21/02 ) | June 11, 2002 |
| Draper Elementary School | FM-200209293 6/11/02 Draper Rooms- 104,111,112,103 and auditorium. 1) Install braces for all a/c units. 2) Install (1) air conditioner in each room and (4) in the auditorium. ** Air Conditioners are on site. | June 11, 2002 |
| Rudolph Elementary School | FM-200209545 5 6/13/02 Rudolph Grd. fl. Special Ed. Repair or replace Westinghouse a/c unit. Fan does not run, compressor overheats and then cuts off. Model #AH157H2A1, BTU 14,800, volts 230/280, amps 11.5/12.2. | June 13, 2002 |
| Ketcham Elementary School | FM-200209700 6/17/02 Ketcham 1) TSI removal nad repair AMP room 93 K-94. Ceiling tile removal AMP room 194. Hot method FI tile removal AMP rooms 99,39, TSI repair AMP room 93,136,181,194,30,39. Envirobate - Charles Crenshaw - 571-436-1150 Code A-clear for repair asbestos abatement on 06/20/02 confirmed by R Edwards. CE Buchanan 06/25/02 | June 17, 2002 |
| Eastern High School | FM-200209695 6/17/02 (Eastern) 1. Asbestos assessment required. 3rd Floor/Hallway ceiling: Roof leak coming through ceiling; area located across from room #330 and 337. Code A-clear for repair by Horne Engineer ( Bipin Nanavaty ) on 06/20/02 | June 17, 2002 |
| Smothers ES | FM-200209707 07 6/18/02 Smothers 1. Asbestos Assessment Reqd. 3rd Floor boys' Restroom 2. Need assessment of wall behind urinal in the 3rd-floor boys' restroom. POC: M. Mack 576-8046 Pager: 996-6294 Code A-clear for repair by Horne Engineer ( Troy Wilcome ) on 6/19/02 | June 18, 2002 |
| Shaw JHS | FM-200210334 6/19/02 Shaw Room 9-268 Wall outlet R st side needs to be replaced. | June 19, 2002 |
| Browne Junior High School | FM-200209876 6/20/02 Browne 1. Asbestos Assessment Reqd. 1st Floor Room 114 2. Repair classroom door---the door hits the frame when being closed. Code A-clear for repair by DCPS CE Buchanan on 06/21/02 | June 20, 2002 |
| Turner Elementary School | FM-200209932 6/20/02 (Turner) 1. Asbestos assessment required. 2nd Floor/Room #200: Ceiling needs to be repaired and painted, wall peeling, plaster and paint is fallen. Code A-clear for repair by Horne Engineer ( Edward Rodrigez ) on 6/25/02 Lead Code A-clear for repair by Horne Engineer ( Edward Rodrigez ) on 6/25/02 | June 20, 2002 |
| Stanton Elementary School | FM-200209936 6/20/02 Stanton Annex 1st-floor Hallway Electrical Box The electric panel box on the 1st floor needs to be checked---- there is a sizzling noise when you turn on the exit light---needs checking/servicing. | June 20, 2002 |
| Browne Junior High School | FM-200209882 6/20/02 Browne 2nd Floor Room 211 Repair/restore power--there is no electricity coming into three side of room 211. | June 20, 2002 |
| Benning Elementary School | FM-200209994 4 6/21/02 Benning Outside of Building Water is running out of the side of the building in the area of the sprinkler system and a pipe is located--needs repair. The water has been shut down. | June 21, 2002 |
| Terrell Mc ES | FM-200209993 0209993 6/21/02 (Terrell, M.C.) !!!!Emergency!!!! Music Room/Hallway: Replace two (2) skylights; damaged due to attempted break-in. | June 21, 2002 |
| Ballou Senior High School | FM-200210089 6/24/02 Ballou/Stay North Stairwell The window-frame & foundation at the top of the window leaks when it rains. Code A-clear for repair by Horne Engineer ( Philip Connilly ) on 06/26/02 | June 24, 2002 |
| Beers Elementary School | FM-200210090 6/24/02 Beers Boiler Room Repair or replace sump pump, is no longer working. (No data plate information. | June 24, 2002 |
| Stuart-Hobson Middle School | FM-200210277 0210277 6/25/02 Stuart-Hobson 1. Asbestos Assessment Reqd. 2nd & 3rd Floors/Areas as Listed 2. Scrape away badly peeling, flaking paint off ceiling & walls in 2nd floor rooms 200, 202, 208 and 214, repaint affected ceilings & walls. 3. Scrape away badly peeling, flaking paint off ceiling & walls in 3rd floor rooms, 300, 302, 304 and repaint affected ceilings & walls. POC: Linda Magazine 202 439-7844 cell phone Tracking: #14075 & # 1139 Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) on 06/26/02 Code a for asbestos and Code A for lead based paint DCPS CE Buchanan | June 25, 2002 |
| Browne Junior High School | FM-200210392 6/26/02 Browne 1. Asbestos Assessment Reqd. Library 2. Replace broken door. Code A-clear for repair by Horne Engineer ( Philip Connolly ) on 07/01/02 DCPS CE Buchanan | June 26, 2002 |
| Browne Junior High School | FM-200210397 6/26/02 Browne 1. Asbestos Assessment Reqd. Rooms124 & 130 2. The electrical outlets in room 124 do not work. 2. Room 130 needs to be wired for more electrical outlets. Code A-clear for repair by Horne Engineer ( Philip Connolly ) on 07/01/02 DCPS CE Buchanan | June 26, 2002 |
| Browne Junior High School | FM-200210390 6/26/02 Browne 1. Asbestos Assessment Reqd. Room 104 2. Replaster ceiling and replace ceiling tiles. Asbestos Code A - Clear for repairs, 6/27/02 Horne Engineering - Edward Rodriguez, (RE- 6/28/02) Lead Based Paint, Code A - Clear for repairs, 6/27/02 Horne Engineering - Edward Rodriguez, (RE- 6/28/02) | June 26, 2002 |
| Takoma Educational Center | FM-200210529 6/27/02 Takoma 1. Asbestos Assessment Reqd. 2nd Floor Room 169 [Old Library] 2. Repair water-damaged walls & paint area. Asbestos/Lead Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
| Takoma Educational Center | FM-200210487 6/27/02 Takoma 1. Asbestos Assessment Reqd. 2nd Floor Corridor [#167] 2. Repair/replace joints that are loose & popping out of the ceiling. 3. Plaster & paint where the joints were loose. Asbestos/Lead Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
| Ballou Senior High School | FM-200210534 6/27/02 Ballou 1. Asbestos Assessment Reqd. Sub-basement Boys' Restroom 2. There is a door in the ceiling that will not close and there are pipes behind the door that leak and have old decaying insulation. Code A-clear for repair by Horne Engineer ( Sam Ebrahim ) on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
| Takoma Educational Center | FM-200210528 6/27/02 Takoma 1. Asbestos Assessment Reqd. 3rd Floor Conference Room [216] 2. Repair breach in the wall & paint. The asst. principal uses the room for conferences with parents. Asbestos/Lead Code A-clear for repair by Horne Engineer ( Edward Rodriguez ) on 07/01/02 DCPS CE Buchanan | June 27, 2002 |
| Cook J.F. Elementary School | FM-200210587 6/28/02 Cook,J.F. 1. Asbestos Assessment Reqd. 1st Floor Auditorium 2. Plaster is falling from the ceiling---needs to be replastered and painted. Asbestos/Lead Code A-clear for repair by Horne Engineer ( Edward Ridriguez )on 07/02/02 DCPS CE Buchanan | June 28, 2002 |