Routine Repair Requests Opened in September 2006 (386)
| School |
Description |
Open Date |
| Johnson JHS |
FM-200628707 9/1/06 Rear Exterior of Cafeteria. Unstop storm drain outside of exterior cafeteria door, water is on the verge of backing up into the building. |
September 1, 2006 |
| Malcolm X ES |
FM-200628709 9/1/06 2nd & 4th Floors- Repair/replace water fountains. |
September 1, 2006 |
| Eastern High School |
FM-200628677 9/1/06 Sub-Basement - Cafeteria/Kitchen - A/C unit for the Main Office needs to be diagnosed to determine the problem of 3 amp fuse blowing everyday. Keeping unit off. |
September 1, 2006 |
| Roosevelt High School |
FM-200628724 9/1/06 Room 204- Repair roof leak. |
September 1, 2006 |
| Lafayette Elementary School |
FM-200628715 9/1/06 Library- Repair leaking ceiling. Repair leak between old wing and new wing. |
September 1, 2006 |
| Dunbar High School |
FM-200628696 9/1/06 Upper Garage- 213 Level Replace drywall; breach in the ceiling. Lead & Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Roger Small (RG 09/07/06) SEE ASSESSMENTS |
September 1, 2006 |
| Merritt Middle School |
FM-200628718 9/1/06 Second floor, Gynasium. Repair roof leak in gymnasium. Asbestos Code A - Clear for repairs on 11/10/06. Tidewater - Kenny Belton (RG 11/16/06) |
September 1, 2006 |
| Kimball Elementary School |
FM-200628708 9/1/06 Playground Side Exit Door/Door handle is broken and hard to open, the lock may also be damaged. Note: This is the door the custodians use to enter the building. Asbestos Code A - Clear for repairs on 09/05/06. Tidewater - Kenny Long (RG 09/06/06) |
September 1, 2006 |
| Powell Elementary School |
FM-200628766 M-200628766 9/1/06 In the storage room on the 2nd floor near rm 219 plaster is falling from the ceiling need to have check for abestos so that I can get up the louse plaster. Asbestos Code A - Clear for repairs on 10/03/06. Tidewater - Shamika Parker (RG 10/24/06) |
September 1, 2006 |
| Merritt Middle School |
FM-200628720 9/1/06 Second floor, Room 204. Unclog 3rd exterior drain water is backing up into the classroom. |
September 1, 2006 |
| Powell Elementary School |
FM-200628716 M-200628716 9/1/06 1) On the 2nd floor restroom near room 213 the faucet has a pen hole in it and water is coming out. (2)Also on that same floor in the teachers lounge the washer under neath the sink is no good causing water to leak out. |
September 1, 2006 |
| Garrison ES |
FM-200628695 9/1/06 Supply independent line for portable a/c unit. Asbestos Code A - Clear for repairs on 09/05/06. Tidewater - Thomas Johnson (RG 09/08/06) |
September 1, 2006 |
| Benning Elementary School |
FM-200628686 9/1/06 Benning Chiller Check and repair chiller, reading low evaporator Refrigerate. Not working |
September 1, 2006 |
| Birney Elementary School |
FM-200628705 9/1/06 First, Second & Third floors. Repair or Replace broken window panes in the following areas: First floor-Assembly Hall (5) Second floor-Room 213 (6), Room 208 (2) Third floor-Hallway (2), Room 302 (2), Room 304 (2), Room 308 (5) and Replace (2) broken windows in Girls' restroom on the old side. Asbestos Code A - Clear for repairs on 09/05/06. Tidewater - Kenny Long (RG 09/06/06) SEE ASSESSMENTS |
September 1, 2006 |
| Harris, C.W. ES |
FM-200628725 9/1/06 2nd Floor- Room 231 Computer Lab Caulk around windows; there is water coming in. |
September 1, 2006 |
| Brent Elementary School |
FM-200628711 9/1/06 Repair roof leak. New ceiling tile in the library are being damaged. |
September 1, 2006 |
| Takoma Educational Center |
FM-200628692 0628692 9/1/06 Rm./200 the sink is off the wall, remount. |
September 1, 2006 |
| Coolidge High School |
FM-200628679 9/1/06 Ground Floor - Boiler Room - Repair and make operable (2) hot water circulating pumps for the new Gym heating system.Pumps located in Boiler Room. Both needs magnetic starters to be replaced. Type - Klockweiz - Moeller D1/2-22/22 Na Ph 3 amp 60 Max fuse 200 size fuse - 80 amp. |
September 1, 2006 |
| Noyes Elementary School |
FM-200628680 9/1/06 Basement - Boiler Room - # 2 chiller is low on it's refrigerant charge and it needs to be serviced . ASAP. - 134-A refrigerant. |
September 1, 2006 |
| Garfield ES |
FM-200628726 9/2/06 Garfield Boiler Room Check sump pump #4motor and shaft not working. Engineer replace (3) three fuses for #3 sump pump now working. Mod# SVB56T17D890A Frame 56C-6 PH-3 HZ 60 Type TS RPM 1725 HP 1/2 208/230 CRN-R 15 Class RK-5 AMPS 200,000 Volts or Less 250 |
September 2, 2006 |
| Cardozo High School |
FM-200629560 9/5/06 CARDOZO- CLASSROOMS - 3,5,309,316,113- MAKE NEW KEYS AND SPARES FOR CLASSROOMS, OLD KEYS ARE NOT IN BUILDING. |
September 5, 2006 |
| Park View ES |
FM-200628772 9/5/06 2nd Floor- Room 228 Repair bad roof leak. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Tony Marcolin (RG 09/11/06 |
September 5, 2006 |
| Bruce-Monroe Elementary School |
FM-200628803 9/5/06 Roof in Old Gymnasium near roof drain area). Repair leaking roof. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Tony Marcolin (RG 09/11/06 |
September 5, 2006 |
| Gibbs Elementary School |
FM-200628794 9/5/06 1st Floor- Main Office Troubleshoot and repair electrical problem; the power keeps going out. |
September 5, 2006 |
| Cook J.F. Elementary School |
FM-200629553 29553 9/5/06 There is a leak in the ceiling on the first floor corridor near room 101 Asbestos Code A - Clear for repairs on 10/02/06 Tidewater - Shamika Parker (RG 10/03/06) |
September 5, 2006 |
| Cook J.F. Elementary School |
FM-200628779 9/5/06 Repair roof leaks in the following locations: - 1st Floor- Room 102 - 3rd Floor- Room 306 - Cafeteria Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Carlos Vera (RG 09/07/06) |
September 5, 2006 |
| Young Elementary School |
FM-200628760 9/5/06 2nd Floor- Multiple Rooms Repair roof leaks. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Shamika Parker (RG 09/13/06) SEE ASSESSSMENTS |
September 5, 2006 |
| Ballou Senior High School |
FM-200628740 9/5/06 BALLOU room 104 Repair AAF heating and cooling ventilator (split system) also exhaust fume hood Note: Both systems work together. |
September 5, 2006 |
| Eastern High School |
FM-200628764 9/5/06 Unstop roof drains; it is causing the roof to leak in the following locations: Auditorium, cafeteria, west side, lower roof, 3rd Floor Room 330. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Shamika Parker (RG 09/11/06) |
September 5, 2006 |
| Cardozo High School |
FM-200629561 9/5/06 CARDOZO- 3RD FLOOR 320-A,FURNISH AND INSTALL WINDOW AIR CONDITIONER,BRACKET FOR A/C. |
September 5, 2006 |
| Cardozo High School |
FM-200629567 9/5/06 CARDOZO- 3RD FLOOR 320-A, INSTALL ELECTRICAL SERVICE FOR WINDOW AIR CONDITIONER . Asbestos Code A - Clear for repairs on 10/02/06 Tidewater - Shamika Parker (RG 10/03/06) |
September 5, 2006 |
| Eliot Junior High School |
FM-200628765 9/5/06 Repair leaking roof in the following locations: Room 307, 1st Floor- Boys Gymnasium. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Shamika Parker (RG 09/08/06) |
September 5, 2006 |
| Stuart-Hobson Middle School |
FM-200628776 9/5/06 Basement- Cafeteria Unstop floor drain. |
September 5, 2006 |
| Gage-Eckington ES |
FM-200628800 9/5/06 Second floor, Cafeteria & Hall near elevator. Repair leaking roof. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Carlos Vera (RG 09/07/06) |
September 5, 2006 |
| Powell Elementary School |
FM-200629542 M-200629542 9/5/06 In the girls restroom on the 1st floor the faucet needs to be replace because the hot & cold water handles are broken. Also the sink near the window bracket that holes it up is broke and the sink is about to fall down. (2) On the 2nd floor girls restroom on both sinks the faucets need to be replace. |
September 5, 2006 |
| Wilson J. O. ES |
FM-200628806 9/5/06 Rooms 302 on North & South side/Second floor library . Repair leaking roof. Note: Water is leking from the roof down through the light fixtures in rooms 302. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Shamika Parker (RG 09/08/06) |
September 5, 2006 |
| Patterson ES |
FM-200628788 9/5/06 First floor/Main Lobby front entrance, Room 235 & Stairwell closes to the right side of main entrance. Repair leaking roof. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Cornell Parks (RG 09/13/06) |
September 5, 2006 |
| Webb Elementary School |
FM-200628759 9/5/06 2nd Floor- Room 207 Repair broken window; water is coming into classroom. |
September 5, 2006 |
| Webb Elementary School |
FM-200628754 9/5/06 1st Floor- Room 141B Repair broken toilet in Kindergarten classroom; it cannot be flushed. |
September 5, 2006 |
| Barnard Elementary School |
FM-200628780 9/5/06 First floor/Gymnasium & Second/Library. Repair leaking roof. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Tony Marcolin (RG 09/11/06 |
September 5, 2006 |
| Ballou Senior High School |
FM-200628756 9/5/06 1st Floor- Hallway Repair water fountains between 115 & 116; water is leaking and cannot be shut off. |
September 5, 2006 |
| Walker-Jones EC |
FM-200628767 9/5/06 Repair multiple roof leaks: - 2nd floor/open space area - 1st Floor/Main Lobby - 2nd Floor/Hallway near 216. Asbestos Code A - Clear for repairs on 09/08/06. Tidewater - Carlos Vera (RG 03/07/07) |
September 5, 2006 |
| Murch Elementary School |
FM-200628757 9/5/06 2nd Floor- Room 212 Repair leaking ceiling; it is leaking badly. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Tony Marcolin (RG 09/07/06) |
September 5, 2006 |
| Terrell Mc ES |
FM-200628795 9/5/06 School Grounds- Cut large tree limbs. |
September 5, 2006 |
| Ballou Senior High School |
FM-200628753 9/5/06 BALLOU Mechanical Rm. # 1 Tech Area A32 Repair heat pump uit WSHP B- 1 (split system) Note: Unit will not cool, |
September 5, 2006 |
| Garfield ES |
FM-200628859 9/6/06 Lower Level, Main Bldg. Repair leaking roof. Roofs are leaking in all the demountables Asbestos Code A - Clear for repaors on 09/13/06. Tidewater - Shamika Parker (RG 09/18/06) |
September 6, 2006 |
| Shaw JHS |
FM-200628867 9/6/06 Top floor, Blue,Yellow and Orange Houses. Repair leaking roof, water is pouring into the building. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Thomas Johnson (RG 09/11/06) |
September 6, 2006 |
| Seaton Elementary School |
FM-200628883 9/6/06 First Floor/Pre School Area Coat Closets + Supply Closet - Water leaking from behind the wall, may be a busted pipe. Investigate and make repairs. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Roger Small (RG 09/07/06) |
September 6, 2006 |
| Savoy Elementary School |
FM-200628829 0628829 9/6/06 Rm. 127/Roof Leak, water leaking on electrical panel box. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Cornell Parks (RG 09/11/06 |
September 6, 2006 |
| Malcolm X ES |
FM-200628862 9/6/06 First floor, Principal's Office. Repair leaking roof. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Carlos Vera (RG 09/15/06) |
September 6, 2006 |
| Kramer Middle School |
FM-200628851 9/6/06 Rm. 300/Repair or replace A/C unit |
September 6, 2006 |
| Kramer Middle School |
FM-200628850 9/6/06 Rm. 205/Air conditioner has been installed, need outlet installed to run it. Asbestos Code A - Clear for repairs on 09/08/06. Tidewater - Carlos Vera (RG 09/12/06) |
September 6, 2006 |
| Walker-Jones EC |
FM-200628880 9/6/06 Install playground equipment parts |
September 6, 2006 |
| Marshall Educational Center |
FM-200628810 9/6/06 Marshall Boiler Room Repair or replace breaker panel which has water coming throw it fromroof drain line when it rains. 480 volts. |
September 6, 2006 |
| Meyer Elementary School |
FM-200628881 9/6/06 Second floor, Boys' Restroom. Repair leaking roof, water is pouring through the ceiling causing it to collaspe. Lead & Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Roger Small/Thomas Johnson (RG 09/11/06) SEE ASSESSMENTS |
September 6, 2006 |
| Macfarland Middle School |
FM-200628828 9/6/06 ALL Stairwells. Repair leaking roof. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Tony Marcolin (RG 09/07/06) |
September 6, 2006 |
| Nalle Elementary School |
FM-200628861 9/6/06 Second floor, Boys' Restroom/Main Bldg. Repair leaking roof, this leak is causing the entire restroom to flood. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Carlos Vera (RG 09/11/06 |
September 6, 2006 |
| Turner Elementary School |
FM-200628844 9/6/06 First floor, Rooms 103, 105, 107 & Second floor, Rooms 203 & 207. Water is pouring in around the window wells. Also the exterior drain is backing up into the building. |
September 6, 2006 |
| Draper Elementary School |
FM-200628878 9/6/06 First floor, Exterior Window. Replace Exterior window asap! Note: There is no way to secure building. |
September 6, 2006 |
| Stuart-Hobson Middle School |
FM-200628852 9/6/06 Rm. 306 - Burning Smell, smells like wires burning. Note: don't know where its coming from in the room. |
September 6, 2006 |
| Aiton Elementary School |
FM-200628860 9/6/06 Fourth floor, Rooms 406 & 407. Repair leaking roof, water is pouring into classroom. Asbestos Code A - Clear for repairs on 09/06/06. Tidewater - Shamika Parker (RG 09/08/06) |
September 6, 2006 |
| Spingarn High School |
FM-200628879 9/6/06 Basement/ROTC Store Rm.-Survey outlets, a tester was used and there is no power coming from the outlets. |
September 6, 2006 |
| Ross Elementary School |
FM-200628869 9 9/6/06 First floor, Room 107 (Lockerroom) Repair leaking roof, water is pouring through the ceiling wall. Asbestos Code A - Clear for repairs on 09/07/06. Tidewater - Thomas Johnson (RG 09/11/06) |
September 6, 2006 |
| Anacostia Senior High School |
FM-200629565 9/6/06 Re-key principal office and entrance doors to building. |
September 6, 2006 |
| Eaton Elementary School |
FM-200628892 9/7/06 Third Floor - Classroom 306 - Repair or replace drip pan on HVAC unit. Drip pan has a large hole in it. Unit is off untill it is repaired or replaced. |
September 7, 2006 |
| Browne Junior High School |
FM-200628981 9/7/06 Auditorium- Replace light bulbs and ballasts. |
September 7, 2006 |
| Walker-Jones EC |
FM-200628916 9/7/06 3rd Floor- Room 311 Re-align classroom door. |
September 7, 2006 |
| Walker-Jones EC |
FM-200628921 9/7/06 1st Floor- Room 103 Repair ceiling. Asbestos Code A - Clear for repairs on 09/08/06. Tidewater - Shamika Parker (RG 09/13/06) |
September 7, 2006 |
| Young Elementary School |
FM-200628926 9/7/06 1st & 2nd Floors- Bathrooms Repair/replace doors on both Boys & Girl's bathrooms. Asbestos Code A - Clear for repairs on 09/08/06. Tidewater - Thomas Johnson (RG 09/13/06) |
September 7, 2006 |
| Kenilworth ES |
FM-200628888 9/7/06 First Floor/Kitchen - Repair slop sink, when water is run in it; it leaks from the bottom onto the floor. |
September 7, 2006 |
| Woodson High School |
FM-200628944 9/7/06 Woodson Boiler Room Replace condensate system for Boiler #1 and #2 |
September 7, 2006 |
| Turner Elementary School |
FM-200628966 9/7/06 Cafeteria/Kitchen - Repair ceiling from water damage Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Thomas Johnson (RG 09/28/06) |
September 7, 2006 |
| Montgomery ES |
FM-200628953 9/7/06 Learning Center 1/Storage Room 10C - Repair Lock, the door will not open |
September 7, 2006 |
| Key Elementary School |
FM-200628893 9/7/06 Attic - AHU #2 - Attic Area - Repair or replace # 2 AHU. Computer is broken. Classrooms 108 and 109 units will no longer come on. Also on the computer. |
September 7, 2006 |
| Cardozo High School |
FM-200629682 9/7/06 CARDOZO - AUDITORIUM 1ST FLOOR AND BALCONY/ATTIC,REPAIR LIGHTS. LIGHT FIXTURES HAVE A SHORT IN WIRING,TRIPS BREAKER . |
September 7, 2006 |
| Eaton Elementary School |
FM-200628891 9/7/06 First Floor - Main Office 100 - Repair or replace drip pan on HVAC unit. Unit is leaking very bad. Unit is off untill repair or replace in Principal's Office. |
September 7, 2006 |
| Malcolm X ES |
FM-200628913 9/7/06 4th Floor- Hallway Repair 4 holes in the wall. Asbestos Code A - Clear for repairs on 09/08/06. Tidewater - Carlos Vera (RG 09/12/06) |
September 7, 2006 |
| Dunbar High School |
FM-200628934 9/7/06 Lower Garage/Mechanical Rm. On 2B Level - Snake out the drain |
September 7, 2006 |
| Wilson High School |
FM-200628910 9/7/06 Third Floor - Main Building - Room 327 - Replace 115 volt air conditioning. Compressor inoperable. |
September 7, 2006 |
| Hart Middle School |
FM-200628941 9/7/06 Repair exterior lights on parking lot. Note: All lights are out. |
September 7, 2006 |
| Malcolm X ES |
FM-200628911 9/7/06 2nd Floor- Boys Bathroom Repair urinal. |
September 7, 2006 |
| Shaw JHS |
FM-200628949 9/7/06 Shaw Boiler Room Replace boiler feed pumps #1 and #2 Located in pump pit. Asbestos Code A - Clear for repairs on 03/20/07. Tidewater - Kenny Belton (RG 03/21/07) |
September 7, 2006 |
| Tubman Elementary School |
FM-200628895 9/7/06 Lower Level - Engineer Office Bathroom - Supply hot and cold water to Bathroom, Repair or replace any inoperable fixtures in Bathroom. Note - This unhealthy condition has existed for years and must be corrected.ASAP. |
September 7, 2006 |
| Eastern High School |
FM-200628919 9/7/06 Sub B - Cafeteria-Kitchen - Replace both water softners systems in Boiler room. Both softners are leaking and float assemblys need replacing. System is vital to the operation of the plant. Info - Bruner Corperation |
September 7, 2006 |
| Coolidge High School |
FM-200628912 9/7/06 First Floor - 128 Office - Furnish ( 1 ) window a/c unit 115 volts, 8 to 10,000 btu. Office has computers. |
September 7, 2006 |
| Coolidge High School |
FM-200628915 9/7/06 Ground Floor - P.E. Classroom - Main Gym - Replace leaking heating hot water system pneumatic actuator valve in P.E. Classroom located in the Main Gym. Johnson Control - v-3754-1020,G-17-311-472,1/2 val 3-6 PSI 8523. |
September 7, 2006 |
| Burrville Elementary School |
FM-200628972 9/7/06 Repair lights in staff parking lot. |
September 7, 2006 |
| Burrville Elementary School |
FM-200628973 9/7/06 Properly cover exposed wires and those that are covered by a cone. |
September 7, 2006 |
| Burrville Elementary School |
FM-200628974 9/7/06 Repair water leak behind the hall in Ms. Brown-Walker's classroom. Note: This is in an open space; there are not any classroom numbers. Asbestos Code A - Clear for repairs on 09/08/06. Tidewater - Thomas Johnson (RG 09/13/06) |
September 7, 2006 |
| Burrville Elementary School |
FM-200628976 9/7/06 Remove graffiti from school grounds and re-paint parking lot lines. |
September 7, 2006 |
| Burrville Elementary School |
FM-200628977 9/7/06 Repair windows to prevent leaks when it rains. |
September 7, 2006 |
| Bancroft Elementary School |
FM-200628951 9/7/06 3rd Floor- Room 323 Primary Wing Replace light switch; it is sparking. |
September 7, 2006 |
| Leckie Elementary School |
FM-200628988 9/8/06 LECKIE Survey and make corrections to window ac units that continuously trips out breakers. |
September 8, 2006 |
| Ballou Senior High School |
FM-200629707 9/8/06 Plumber need.to relocate one the hot water lines to the cold water side,culanary art has no running cold water. Asbestos Code A - Clear for repairs on 10/04/06 Tidewater - Kenneth Belton (RG 10/12/06) |
September 8, 2006 |
| Francis Junior High School |
FM-200629014 9/8/06 Auditorium- Survey and repair ceiling. A very large piece of the ceiling fell. Lead & Asbestos Code A - Clear for repairs on 09/11/06. Tidewater - Roger Small/Shamika Parker (RG 09/13/06) SEE ASSESSMENTS |
September 8, 2006 |
| Ronald H. Brown MS |
FM-200628990 9/8/06 They are smelling gas. |
September 8, 2006 |
| Ballou Senior High School |
FM-200629706 9/8/06 Replace window in sevice bay area,vandalized. |
September 8, 2006 |
| Bancroft Elementary School |
FM-200629005 9/8/06 Top Floor- Hallway (near girls bathroom) Repair leaking spigot and supply line on water fountain. |
September 8, 2006 |
| Key Elementary School |
FM-200629010 9/8/06 Replace the following windows: 202, 203, 204, 104, Hallway on ground floor (2). |
September 8, 2006 |
| Bancroft Elementary School |
FM-200628992 9/8/06 2nd Floor- Room 120 Main Building Repair leakey roof. Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Shamika Parker (RG 09/13/06) |
September 8, 2006 |
| Browne Junior High School |
FM-200629000 9/8/06 Basement- Kitchen Plaster and paint walls and ceilings. Lead & Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Roger Small (RG 09/13/06) SEE ASSESSMENTS |
September 8, 2006 |
| Bancroft Elementary School |
FM-200628991 9/8/06 2nd Floor- Room 124 Main Building Replace area of slate on roof. Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Shamika Parker (RG 09/13/06) |
September 8, 2006 |
| Browne Junior High School |
FM-200628999 9/8/06 Basement- New Gym/Boys Lockerroom Plaster and paint offices. Lead & Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Roger Small (RG 09/13/06) SEE ASSESSMENTS |
September 8, 2006 |
| Brent Elementary School |
FM-200628997 9/8/06 Rooms 307, 209, Teacher Lounge Repair univents. |
September 8, 2006 |
| Benjamin Banneker Academic HS |
FM-200628998 9/8/06 1st Floor- Gym/Girls Lockerroom Repair light fixtures. There is no light in this room. |
September 8, 2006 |
| Shaw JHS |
FM-200629020 9/8/06 Child Care Center- R. Street Side Repair/modify door so that it cannot be opened from the outside. |
September 8, 2006 |
| Francis Junior High School |
FM-200629003 9/8/06 1st Floor- Auditorium Repair roof leak above the room. Asbestos Code A - Clear for repaors on 09/13/06. Tidewater - Shamika Parker (RG 09/18/06) |
September 8, 2006 |
| Merritt Middle School |
FM-200629021 9/8/06 4th Floor- Room 403 Repair roof above room; water leaks inside when it rains. Asbestos Code A - Clear for repaors on 09/13/06. Tidewater - Kenneth Belton (RG 09/18/06) |
September 8, 2006 |
| Miner Elementary |
FM-200629102 9/11/06 Second Floor - Large Group Construction Room - AHU #4 has a leaking chill water supply line. 3" line is leaking gylco. |
September 11, 2006 |
| Bunker Hill Elementary School |
FM-200629108 9/11/06 1st & 2nd Floors- Room 122 & 229 (West Wing) Plaster and paint over holes in the walls. Lead & Asbestos Code A - Clear for repaors on 09/14/06. Tidewater - Roger Small (RG 09/18/06) SEE ASSESSMENTS |
September 11, 2006 |
| Bunker Hill Elementary School |
FM-200629101 9/11/06 2nd Floor- Middle Wing Repair holes in the ceiling in the following classrooms: 220, 212, 211. Lead & Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Roger Small (RG 09/13/06) SEE ASSESSMENTS |
September 11, 2006 |
| Bunker Hill Elementary School |
FM-200629100 9/11/06 Replace exterior lights on school grounds. |
September 11, 2006 |
| Merritt Middle School |
FM-200629144 9/11/06 School Playground and Parking Lot- Repair large pot holes in the parking lot and large holes on the playground. |
September 11, 2006 |
| Merritt Middle School |
FM-200629143 9/11/06 Front of Building- Exterior Repair loose brackets on handrail. |
September 11, 2006 |
| Merritt Middle School |
FM-200629142 9/11/06 1st, 2nd, & 3rd Floors- Repair/replace faucets and valves in bathrooms. |
September 11, 2006 |
| Merritt Middle School |
FM-200629141 9/11/06 Ground Floor- All Entrance Doors Install/repair door hardware (kick plates, bolts, etc.) Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Thomas Johnson (RG 09/15/06) |
September 11, 2006 |
| Houston Elementary School |
FM-200629149 9/11/06 Kindergarten Area- Replace carpet (it was already removed). |
September 11, 2006 |
| Merritt Middle School |
FM-200629140 9/11/06 Ground Floor- All Entrance Doors Install/repair door locks, latches, and panic bars. |
September 11, 2006 |
| Takoma Educational Center |
FM-200629138 0629138 9/11/06 Install scuffle to drain water from roof. |
September 11, 2006 |
| Montgomery ES |
FM-200629056 9/11/06 Exterior Door Leading To Parking Lot Wont Close. |
September 11, 2006 |
| Stuart-Hobson Middle School |
FM-200629044 9/11/06 3rd Floor/Teachers Lounge - Hole In Ceiling Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Kenny Belton (RG 09/15/06) |
September 11, 2006 |
| Wilson J. O. ES |
FM-200629120 9/11/06 Wilson, J.O. Boiler room Replace B& G spring coupling on the DHW circulating pump. |
September 11, 2006 |
| Leckie Elementary School |
FM-200629029 9/11/06 Second Floor/Between Rms. 212 & 211A - Panel Box Door Need To Be Put Back Up. |
September 11, 2006 |
| Bancroft Elementary School |
FM-200629088 9/11/06 3rd Floor- Room 323 Primary Wing Replace circuit breaker. |
September 11, 2006 |
| Bancroft Elementary School |
FM-200629085 9/11/06 2nd Floor- Room 314 Primary Wing Supply and install replacement light fixture. |
September 11, 2006 |
| Roosevelt High School |
FM-200629123 9/11/06 Replace tile around wall mounted sink. Note: The plumber is on-site and cannot remount sink because of missing tile. Asbestos Code A - Clear for repairs on 09/12/06. Tidewater - Thomas Johnson (RG 09/15/06) |
September 11, 2006 |
| Bunker Hill Elementary School |
FM-200629112 9/11/06 2nd Floor- Middle Wing Room 220 Repair leaking ceiling. Asbestos Code A - Clear for repaors on 09/14/06. Tidewater - Roger Small (RG 09/18/06) |
September 11, 2006 |
| Bunker Hill Elementary School |
FM-200629113 9/11/06 1st Floor- Auditorium Repair leakey ceiling. Asbestos Code A - Clear for repaors on 09/14/06. Tidewater - Roger Small (RG 09/18/06) |
September 11, 2006 |
| Bunker Hill Elementary School |
FM-200629110 9/11/06 2nd Floor- Rooms 211, 212, 220 Troubleshoot electrical problem; there are no lights in these rooms. |
September 11, 2006 |
| Bunker Hill Elementary School |
FM-200629109 9/11/06 2nd Floor- West Wing Library Plaster and paint room. Lead & Asbestos Code A - Clear for repaors on 09/14/06. Tidewater - Roger Small (RG 09/18/06) SEE ASSESSMENTS |
September 11, 2006 |
| Bancroft Elementary School |
FM-200629219 9/12/06 Top Floor- Girls Bathroom Replace water fountain with a water cooler. |
September 12, 2006 |
| Bancroft Elementary School |
FM-200629203 9/12/06 1st & 2nd Floors- Rooms 121 & 110 Repair leaking ceilings. Asbestos Code A - Clear for repaors on 09/14/06. Tidewater - Kenny Belton (RG 09/18/06) |
September 12, 2006 |
| Bancroft Elementary School |
FM-200629223 9/12/06 1st Floor- Girls & Teacher's Bathroom Replace water damaged ceiling. Asbestos Code A - Clear for repaors on 09/14/06. Tidewater - Kenneth Belton (RG 09/18/06) |
September 12, 2006 |
| Young Elementary School |
FM-200629720 9/12/06 There is no heating system in office. I am told that this office is extremely cold in the fall/winter months. A heating pump/unit is needed ASAP. |
September 12, 2006 |
| Turner Elementary School |
FM-200629154 9/12/06 Second Floor (new side) - Repair broken door closer on the exit door. |
September 12, 2006 |
| Dunbar High School |
FM-200629174 9/12/06 Dunbar Boiler Room Repair or replace exhaust fan on roof near Boiler Room |
September 12, 2006 |
| Wilson High School |
FM-200629212 9/12/06 3rd Floor- Room 313 Main Building Restore 220V power supply to window a/c unit. |
September 12, 2006 |
| Eaton Elementary School |
FM-200629224 9/12/06 3rd Floor- Room 305 Boys Restroom Repair/replace slop sink. |
September 12, 2006 |
| Eliot Junior High School |
FM-200629199 9/12/06 Outside rm. 212 - Breach in ceiling Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Shamika Parker (RG 09/21/06) |
September 12, 2006 |
| Ferebee-Hope Elementary School |
FM-200629179 9/12/06 Troubleshoot and possibly repair plumbing problem. There is a bad odor coming from all bathrooms. |
September 12, 2006 |
| Ferebee-Hope Elementary School |
FM-200629190 9/12/06 Un-Clog 4 inch sewage line. |
September 12, 2006 |
| Roosevelt High School |
FM-200629188 9/12/06 Exterior of Building 13th St., side. Install marquis in front of the school. Also need electricians to assess and connect electrical service. |
September 12, 2006 |
| Gibbs Elementary School |
FM-200629155 9/12/06 First Floor/Cafeteria - Repair or replace broken windows |
September 12, 2006 |
| Gibbs Elementary School |
FM-200629156 9/12/06 First Floor/103 - Repair water cooler |
September 12, 2006 |
| Gibbs Elementary School |
FM-200629157 9/12/06 First Floor/Health Suite - Replace water fountain |
September 12, 2006 |
| Gibbs Elementary School |
FM-200629158 9/12/06 First Floor/Rosedale side of the bldg. - Water cooler pressure is low |
September 12, 2006 |
| Payne Elementary School |
FM-200629161 9/12/06 First Floor/Hallway (new wing) - Ceiling is leaking near lobby when it rains. |
September 12, 2006 |
| Payne Elementary School |
FM-200629160 9/12/06 St. John - Roof is leaking in back rm. when it rains. |
September 12, 2006 |
| Key Elementary School |
FM-200629181 9/12/06 Install stair light covers. |
September 12, 2006 |
| Benjamin Banneker Academic HS |
FM-200629312 9/13/06 305/Roof Leak from upper ceiling-middle window, room floods when raining. |
September 13, 2006 |
| Kelly Miller MS |
FM-200629252 9/13/06 Boiler # 1 perform hydro. test |
September 13, 2006 |
| Benjamin Banneker Academic HS |
FM-200629309 9/13/06 308/Replace black board, it's cracked and coming out from the wall. Asbestos Code A - Clear for repaors on 09/14/06. Tidewater - Carlos Vera (RG 09/18/06) |
September 13, 2006 |
| West Elementary School |
FM-200629229 9/13/06 West Boiler Room Boilers #1,#2 & #3 Repair damage sheet metal jacket Per DC Boiler Inspector |
September 13, 2006 |
| Turner Elementary School |
FM-200629288 9/13/06 Third Floor/Boy's Restroom - Replace Toilet, Its Broken, A Flush Valve Is Also Needed. |
September 13, 2006 |
| Kelly Miller MS |
FM-200629226 9/13/06 Boiler # 1 & 3 perform hydro. test |
September 13, 2006 |
| Kimball Elementary School |
FM-200629355 9/13/06 Exterior Doors- Playground Area Repair/install panic bars. |
September 13, 2006 |
| Turner Elementary School |
FM-200629349 9/13/06 1st Floor- Girl's Bathroom (old side) Install stall partitions. Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Thomas Johnson (RG 09/28/06) |
September 13, 2006 |
| Barnard Elementary School |
FM-200629327 9/13/06 Troubleshoot and repair electrical problem that is causing the network to be down. |
September 13, 2006 |
| Deal Junior High School |
FM-200629315 9/13/06 Basement- Cafeteria Repair ceiling. Water damaged plaster is falling in chunks. Asbestos Code A - Clear for repaors on 09/13/06. Tidewater - Kenneth Belton (RG 09/18/06) |
September 13, 2006 |
| Eastern High School |
FM-200629319 9/13/06 Unstop down spout hub outside Kitchen, entry from parking lot. |
September 13, 2006 |
| Eastern High School |
FM-200629314 9/13/06 Unstop 5 drains on the building roof - 1-on armory roof, SE corner - 2 on woodshop roof, west side - 2 Auditorium roof, left side |
September 13, 2006 |
| Barnard Elementary School |
FM-200629284 9/13/06 First Floor/Lobby - Women's Bathroom - The First Stall Has A Heavy Constant Leak From The Fush Valve, Repair or Replace. |
September 13, 2006 |
| Bowen Elementary School |
FM-200629237 9/13/06 Boiler # 2 burner calibration. |
September 13, 2006 |
| Harris, C.W. ES |
FM-200629362 9/13/06 1st Floor- Roomos 143, 144, 146, 149, Near 111, and Hallway near Boiler Room Repair roof leaks above these areas. Asbestos Code A - Clear for repairs on 09/15/06. Tidewater - Thomas Johnson (RG 09/18/06) |
September 13, 2006 |
| Montgomery ES |
FM-200629358 9/13/06 LCI/Women's Restroom- Repair sink. |
September 13, 2006 |
| Patterson ES |
FM-200629481 9/14/06 1st Floor- Room 123 There is no water in this bathroom. |
September 14, 2006 |
| Wilkinson ES |
FM-200629478 9/14/06 2nd Floor- Bookroom/Room 187 Rekey lock so that it fits the master key. |
September 14, 2006 |
| Kelly Miller MS |
FM-200629453 9/14/06 Kelly Miller Replace backflow preventor |
September 14, 2006 |
| Jefferson JHS |
FM-200629484 9/14/06 Basement- Kitchen Restroom Repair/replace light fixture. |
September 14, 2006 |
| Takoma Educational Center |
FM-200629400 0629400 9/14/06 Takoma Mechanical #12 Repair busted coil in Air Handler Unit #13 |
September 14, 2006 |
| Thomas Elementary School |
FM-200629424 9/14/06 Thomas Cafeteria Replace 1" sweated check valve on condensate drain line from univents, drain line is tied into 6" roof drain, excessive raining water backs up thru the univent drain line causing flooding of the cafeteria. |
September 14, 2006 |
| Young Elementary School |
FM-200629379 9/14/06 First Floor/Outside - Unstop Drain (playground area) |
September 14, 2006 |
| Beers Elementary School |
FM-200629465 9/14/06 Rm. #210 has lots of paint peeling off the walls Lead Code A - Clear for repairs on 09/18/06. Tidewater - Roger Small (RG 09/19/06) SEE ASSESSMENTS |
September 14, 2006 |
| Beers Elementary School |
FM-200629423 9/14/06 2nd Floor- Teachers Lounge Repair cracked toilet and stop leaking water. |
September 14, 2006 |
| Beers Elementary School |
FM-200629416 9/14/06 First Floor/Bldg. 1 - Rm. #106 has lots of paint peeling off the walls Lead Code A - Clear for repaors on 09/14/06. Tidewater - Roger Small (RG 09/18/06) |
September 14, 2006 |
| Cardozo High School |
FM-200630073 9/14/06 CARDOZO -2ND FLOOR ROOM 207 SPECIAL EDUCATION ROOM .REPAIR OR REPLACE BROKEN FLOOR TILES,9X9,FLOOR SIZE IS APPOX. 12FEET BY 14 FEET.ASBESTOS CONCERNS. Asbestos Code A - Clear for repairs on 10/02/06 Tidewater - Shamika Parker (RG 10/03/06) |
September 14, 2006 |
| Rudolph Elementary School |
FM-200629449 9/14/06 Install window a/c units in rooms 100 & 208. Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Thomas Johnson (RG 09/21/06) |
September 14, 2006 |
| Eastern High School |
FM-200629389 9/14/06 Unclog Roof Drains, Roof Leaks In The Stairwell Near B78 Leading To Cafeteria, Armory, And Auditorium. |
September 14, 2006 |
| Eastern High School |
FM-200629387 9/14/06 Second Fl/Custodial Closet Sink Is Clogged. |
September 14, 2006 |
| Spingarn High School |
FM-200629479 9/14/06 Basement- Kitchen Replace knobs on sinks. |
September 14, 2006 |
| Dunbar High School |
FM-200629421 9/14/06 Ground Floor- Child Care Center Repair broken door. Asbestos Code A - Clear for repairs on 09/18/06. Tidewater - Shamika Parker (RG 09/19/06) |
September 14, 2006 |
| Wilkinson ES |
FM-200629475 9/14/06 2nd Floor- Water Fountain (near girls restroom) Replace cut-off valve. |
September 14, 2006 |
| Wilkinson ES |
FM-200629476 9/14/06 1st Floor- Room 122 Replace door closer. Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Roger Small (RG 09/21/06) |
September 14, 2006 |
| Wilkinson ES |
FM-200629477 9/14/06 1st Floor- Kitchen Restroom/Room 126 Replace door closer. Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Roger Small (RG 09/21/06) |
September 14, 2006 |
| Burrville Elementary School |
FM-200629415 9/14/06 Remove 2 walls. Note: These are new walls that were just erected over the summer. |
September 14, 2006 |
| Bruce-Monroe Elementary School |
FM-200629485 9/14/06 1st Floor- Main Office Staff Restroom Sink needs to be snaked out. |
September 14, 2006 |
| Patterson ES |
FM-200629480 9/14/06 2nd Floor- Boys Bathroom Repair 2 sinks that are leaking. |
September 14, 2006 |
| Francis Junior High School |
FM-200629576 9/15/06 1st Floor- Outside of Room 114 Supply master key to get into 40 lockers. |
September 15, 2006 |
| Montgomery ES |
FM-200629585 9/15/06 1st Floor- LC 1 Repair sink in boys bathroom. |
September 15, 2006 |
| Payne Elementary School |
FM-200629541 9/15/06 First Floor (old wing) - Breaches in ceiling in Janitor's Closet. Asbestos Code A - Clear for repairs on 09/18/06. Tidewater - Kenny Long (RG 09/19/06) |
September 15, 2006 |
| Montgomery ES |
FM-200629587 9/15/06 1st Floor- LC 1/Women's Bathroom Repair leaking toilet. |
September 15, 2006 |
| Montgomery ES |
FM-200629588 9/15/06 1st Floor- LC 1/Men's Bathroom Repair lock. |
September 15, 2006 |
| Gibbs Elementary School |
FM-200629545 9/15/06 1st Floor- Boys & Girls Restrooms Unlock doors. |
September 15, 2006 |
| Tyler Elementary School |
FM-200629564 9/15/06 Basement- Cafeteria Replace lock on metal doors. |
September 15, 2006 |
| Tyler Elementary School |
FM-200629566 9/15/06 Basement- Cafeteria Install 2 window a/c units. Asbestos Code A - Clear For Repairs On 09/20/06. Tidewater - Shamika Parker ( RG 09/25/06) |
September 15, 2006 |
| Burrville Elementary School |
FM-200629547 9/15/06 2nd Floor- Counselor's Office Change locks.l |
September 15, 2006 |
| Murch Elementary School |
FM-200629524 9/15/06 Murch Boiler Room Repair or replace burner on Boiler #5. Will not start. |
September 15, 2006 |
| Burrville Elementary School |
FM-200629546 9/15/06 Kitchen- Replace faucet on the sink. |
September 15, 2006 |
| Burrville Elementary School |
FM-200629514 9/15/06 2nd Floor- Open Space Paint Room. |
September 15, 2006 |
| Patterson ES |
FM-200629568 9/15/06 3rd Floor- Repair water fountain; it keeps shutting off. |
September 15, 2006 |
| Browne Junior High School |
FM-200629554 9/15/06 1st & 2nd Floor- New Wing & Old Wing Install new glass on the bulletin board. |
September 15, 2006 |
| Browne Junior High School |
FM-200629552 9/15/06 Basement- Cafeteria Put new hinges on doors leading to this area. Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Shamika Parker (RG 09/21/06) |
September 15, 2006 |
| Johnson JHS |
FM-200629582 9/15/06 Exterior Patio/Near Gymnasium. Repair or replace metal exterior door, it has been severely damaged leaving a breach in the door and frame work. Note: This door cannot be secured. |
September 15, 2006 |
| Beers Elementary School |
FM-200629581 9/15/06 Make a new key for Main Entry Door. |
September 15, 2006 |
| Barnard Elementary School |
FM-200629513 9/15/06 Cafeteria/Kitchen - Garbage Disposal Leaking. |
September 15, 2006 |
| Stanton Elementary School |
FM-200629503 9/15/06 Replace filters on all water coolers throughtout the school. |
September 15, 2006 |
| Bancroft Elementary School |
FM-200629558 9/15/06 Ground Floor- Hallway (near boiler room) Furnish and install 4 light fixtures. |
September 15, 2006 |
| Adams Elementary School |
FM-200629627 9/18/06 Repair electrical problem. Cafeteria/Kitchen- The lights are blinking on and off. Middle Stairwell- No lights at all. |
September 18, 2006 |
| Beers Elementary School |
FM-200629638 9/18/06 Bldg. 2 - Old Boiler Rm. - Sub pump is not working, causing outside drain to be stopped up. Lots of standing water and mosquitoes are growing. |
September 18, 2006 |
| Dunbar High School |
FM-200629642 9/18/06 Ground Level- Boys Locker room Replace door. Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Thomas Johnson (RG 09/21/06) |
September 18, 2006 |
| Dunbar High School |
FM-200629644 9/18/06 Ground Level- Boys Locker room Repair/replace floor; it is buckling. Asbestos Code A - Clear for repairs on 09/19/06. Tidewater - Thomas Johnson (RG 09/26/06) |
September 18, 2006 |
| Eaton Elementary School |
FM-200629635 9/18/06 1st Floor- Room 104 Supply key. |
September 18, 2006 |
| Payne Elementary School |
FM-200629618 9/18/06 Girl's Restroom (Lobby Area) - Repair the ceiling due to a condensation leak that was repaired, plaster is falling light fixture needs to be replaced. Asbestos Code A - Clear for repairs on 09/18/06. Tidewater - Kenny Long (RG 09/19/06) |
September 18, 2006 |
| Seaton Elementary School |
FM-200629633 9/18/06 1st Floor- Room 113 Repair/replace faucet and repair leaking water line under the sink. |
September 18, 2006 |
| Tubman Elementary School |
FM-200629591 9/18/06 Basement - Boiler Room - Replace missing wall mounted sink, need to wash up when in the Boiler Room. Asbestos Code A - Clear For Repairs On 09/21/06. Tidewater - Thomas Johnson ( RG 09/25/06) |
September 18, 2006 |
| Woodson High School |
FM-200629632 9/18/06 Unclog grease trap; kitchen area is flooding. |
September 18, 2006 |
| Gibbs Elementary School |
FM-200629689 9/19/06 1st- Hallway No lights. |
September 19, 2006 |
| Kenilworth ES |
FM-200629673 9/19/06 Second Floor/Girl's Restroom - Sink is hanging off the wall, the water was cut off. |
September 19, 2006 |
| Kramer Middle School |
FM-200629653 9/19/06 Third Floor/307 - Repair or replace wood floor, it's damaged Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Roger Small (RG 09/21/06) |
September 19, 2006 |
| Kramer Middle School |
FM-200629651 9/19/06 Second Floor/207 - Repair or replace wood floor, it's damaged Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Roger Small (RG 09/21/06) |
September 19, 2006 |
| Merritt Middle School |
FM-200629674 9/19/06 3rd Floor- Room 304 Replace wire mesh glass in door. Asbestos Code A - Clear For Repairs On 09/21/06. Tidewater - Shamika Parker ( RG 09/25/06) |
September 19, 2006 |
| King M L ES |
FM-200629671 9/19/06 Flush valves are needed in the following locations: - 1st Floor/Boys & Girls Restrooms - 3rd Floor/Boys Restrooms |
September 19, 2006 |
| Hendley Elementary School |
FM-200629691 9/19/06 2nd & 3rd Floor- Rooms 204 & 306 Repair/replace light switch. |
September 19, 2006 |
| Bancroft Elementary School |
FM-200629667 9/19/06 1st Floor- Teacher's Bathroom Repair leaking ceiling; when it rains, the ceiling leaks. Asbestos Code A - Clear For Repairs On 09/19/06 Tidewater - Shamika Parker (RG 09/21/06) |
September 19, 2006 |
| Ronald H. Brown MS |
FM-200629686 9/19/06 Repair security lights around the building. |
September 19, 2006 |
| Gibbs Elementary School |
FM-200629694 9/19/06 3rd Floor- Room 300 Repair outlets; none are working. |
September 19, 2006 |
| Gibbs Elementary School |
FM-200629693 9/19/06 3rd Floor- Hallway No lights. |
September 19, 2006 |
| Cleveland Elementary School |
FM-200629685 9/19/06 Ground- G39 Computer Room Repair water damaged wall. Lead & Asbestos Code A - Clear For Repairs On 09/20/06. Tidewater - Roger Small ( RG 09/25/06) SEE ASSESSMENTS |
September 19, 2006 |
| Gibbs Elementary School |
FM-200629688 9/19/06 1st- Boys Bathroom No lights. |
September 19, 2006 |
| Gibbs Elementary School |
FM-200629687 9/19/06 Trash Closets- 1st, 2nd, 3rd Hallways Install 15 and 20 amp grounded outlets. Asbestos Code A - Clear For Repairs On 09/21/06. Tidewater - Roger Small ( RG 09/25/06) |
September 19, 2006 |
| Cleveland Elementary School |
FM-200629683 9/19/06 Ground- Front Entrance Move sensor to a different location. |
September 19, 2006 |
| School WW High School |
FM-200629726 9/20/06 Repair Stairway Ladder That Leads To Roof Access Door. Asbestos Code A - Clear For Repairs On 09/21/06. Tidewater - Thomas Johnson ( RG 09/25/06) |
September 20, 2006 |
| Ferebee-Hope Elementary School |
FM-200629713 9/20/06 First Floor/Book Room - Exposed Pipe leaking in ceiling with a bad smell. Asbestos Code A - Clear for repairs on 09/25/06. Tidewater - Tony Marcolin (RG 09/26/06) |
September 20, 2006 |
| Cardozo High School |
FM-200629736 9/20/06 Basement floor, Kitchen Area. Repair or Replace faucets on (2) sinks in kitchen, sinks are none operational. Note: This is a health code violation. |
September 20, 2006 |
| McKinley Technology High |
FM-200629742 9/20/06 Chiller Room, Boiler Room. 1.) Repair or replace leaking mechanical seal chillwater secondary pumps#2 and #3. 2.) Repair or Replace leaking boiler hotwater secondary pump mechanical seal #2. |
September 20, 2006 |
| Nalle Elementary School |
FM-200629739 9/20/06 First Floor-Hallway - Unit vent Smoking Note: The Fire Department Was Called. Motor replacement. |
September 20, 2006 |
| Dunbar High School |
FM-200629717 9/20/06 Boy's locker Room - Repair the shower |
September 20, 2006 |
| Spingarn High School |
FM-200629699 9/20/06 Boiler Room - Repair refactory to boiler # 4 firebox cleanout opening and square cleanout plug. |
September 20, 2006 |
| Anacostia Senior High School |
FM-200630083 9/20/06 Re-key 5 counselor offices |
September 20, 2006 |
| Eastern High School |
FM-200629697 9/20/06 Rm. 326 - Breaches in ceiling & walls Asbestos Code A - Clear For Repairs On 06/27/06. Tidewater - Roger Small (RG 09/28/06) |
September 20, 2006 |
| Woodson High School |
FM-200629740 9/20/06 Kitchen - Electrical Outlet - Shooting Sparks. |
September 20, 2006 |
| Eastern High School |
FM-200629700 9/20/06 Rm. 324 - Breaches in wall Asbestos Code A - Clear For Repairs On 09/20/06 Tidewater - Roger Small (RG 09/21/06) |
September 20, 2006 |
| Oyster Elementary School |
FM-200629730 730 9/20/06 Red Stairwell - Replace 8 Rubber Treds. Asbestos Code A - Clear For Repairs On 09/21/06. Tidewater - Thomas Johnson ( RG 09/25/06) |
September 20, 2006 |
| Takoma Educational Center |
FM-200629809 0629809 9/21/06 Kitchen. Repair or replace leaking sink faucet. |
September 21, 2006 |
| Kelly Miller MS |
FM-200629746 9/21/06 Kelly Miller Roof Check and repair air handler unit # 14 , low limit switch line voltage 130 v. each leg, needs 277 volts, could not locate main circuit breaker. |
September 21, 2006 |
| Cardozo High School |
FM-200629824 9/21/06 1st Floor & Basement- Girl's Gym & Kitchen Replace damaged flooring in the Kitchen (clay tile), and Girl's Gym (wood floor). Asbestos Code A - Clear for repairs on 09/25/06. Tidewater - Kenneth Belton (RG 09/26/06) |
September 21, 2006 |
| Kelly Miller MS |
FM-200629748 9/21/06 Kelly Miller 2nd Flor Mechanical room Replace motor sheave on air handler unit # 1, ( VP62 x 1-3/8 ) belts are on order for unit. |
September 21, 2006 |
| Anacostia Senior High School |
FM-200630087 9/21/06 Line teachers parking lot. |
September 21, 2006 |
| Wilkinson ES |
FM-200629797 9/21/06 1st Floor- Room 45 Custodian Closet Unclog drain. |
September 21, 2006 |
| Plummer Elementary School |
FM-200629750 9/21/06 Second Floor and Third Floor - Replace or repair window a/c units. (2) units in 127 and () units in 129. 115v.15.amp 24,000 btu. Replace or repair window a/c units (1) unit in 209 and (1) unit in 213. 115v.15.amp 24,000 btu. |
September 21, 2006 |
| Plummer Elementary School |
FM-200629749 9/21/06 Second Floor - Room 209 and 213 - Modify outlet to accommodate a/c window unit. 115v.15.amp 15,000 btu. |
September 21, 2006 |
| Turner Elementary School |
FM-200629864 9/22/06 TURNER Boiler room Repair or re-direct existing collapse floor drain line in boiler room, cause boiler room to flood. |
September 22, 2006 |
| Woodson High School |
FM-200629875 9/22/06 Classroom #506 Home Economics Lab Unstop clogged sink. Double sink located on the inside hall wall. Building staff is not able to unstop drain and is requested assistance. Note: Classroom has been placed off limits until repairs are complete. Contact Pedro Macins, Building Engineer |
September 22, 2006 |
| Orr Elementary School |
FM-200629858 9/22/06 Library Area. Shut off and secure water supply lines in library. |
September 22, 2006 |
| Kelly Miller MS |
FM-200629837 9/22/06 Replace several broken windows throughout the building. 1. Broken window above the exterior door (rear parking lot). 2. Two broken windows on second level rear of building (view from the parking lot). 3. Room A101 (window currently taped up) 4. Broken windows (Front stairwell near office) Note: These repairs are to be completed before Dr. Janey's and US Department of Education's site visit on September 25,2006. Asbestos Code A - Clear for repairs on 09/22/06. Tidewater - Meneka Rodrigo (RG 09/22/06) |
September 22, 2006 |
| Dunbar High School |
FM-200629856 9/22/06 Replace or Repair back up pool pump in the filtration room on 2b level upper garage. |
September 22, 2006 |
| Cardozo High School |
FM-200629880 9/22/06 Ground Floor/Stairwell Near Construct. Academy - Repair panic bars on exterior door. |
September 22, 2006 |
| Reed LC |
FM-200629876 9/22/06 Boiler Room - Repair or Replace boiler # 1. Parts removed from boiler to repair # 2 and # 3. |
September 22, 2006 |
| McKinley Technology High |
FM-200629895 9/24/06 McKinley Boiler Room Boiler #1 Failed need mechanical seals on pumps Boiler #4 Failed need actuator DC Boiler Inspector |
September 24, 2006 |
| Simon Elementary School |
FM-200629902 9/24/06 Simon Boiler Room Boiler #2 leaking tubes DC Boiler Inspection |
September 24, 2006 |
| Shaw JHS |
FM-200629911 9/24/06 Shaw Boiler Room Boiler #2 Need refractory work with combustion chamber DC Boiler Inspector |
September 24, 2006 |
| Houston Elementary School |
FM-200629906 9/24/06 Houston Boiler Room Boiler #1 Need refractory work in fire box DC Boiler Inspector |
September 24, 2006 |
| Hine JHS |
FM-200629958 9/25/06 3rd Floor- Gym Corridor Repair dry wall ceiling. Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Tony Marcolin (RG 09/28/06) |
September 25, 2006 |
| Leckie Elementary School |
FM-200629997 9/25/06 Re-culk around windows thru-out the building in order to stop water leaks. |
September 25, 2006 |
| King M L ES |
FM-200630009 9/25/06 Scope of Work: Survey electrical power supply in the following rooms and supply sufficient air conditioning/supply. Rooms: Counselor Ms. Nellie Cureton, 108, 109, 117, 118, 114, 115, 216, 219, 223, 123, 217, 220, 306, 313, 304, 324, 319/320, 321/322, 111, 128, 204, 212, 221, 318, 122, 218, 323, 222. |
September 25, 2006 |
| McKinley Technology High |
FM-200629940 9/25/06 Basement, Boiler Room. Repair or Replace leaking mechanical seal boiler # 1. |
September 25, 2006 |
| Hine JHS |
FM-200629970 9/25/06 4th Floor- Corridor Repair water coolers. |
September 25, 2006 |
| Hine JHS |
FM-200629969 9/25/06 4th Floor- Room 409 Repair lights/breaker. |
September 25, 2006 |
| Hine JHS |
FM-200629966 9/25/06 3rd Floor- Custodial Room Repair breech in wall. Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Tony Marcolin (RG 09/28/06) |
September 25, 2006 |
| Hine JHS |
FM-200629965 9/25/06 3rd Floor- Hallway near Men's Restroom Install water cooler. Asbestos Code A - Clear for repairs on 09/26/06. Tidewater - Tony Marcolin (RG 10/20/06) |
September 25, 2006 |
| Hine JHS |
FM-200629955 9/25/06 3rd Floor- Gym/Ladies Restroom Secure toilet to the floor. Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Tony Marcolin (RG 09/28/06) |
September 25, 2006 |
| Hine JHS |
FM-200629954 9/25/06 2nd Floor- Girls & Boys Bathrooms (B Wing) Repair urinals and toilets. |
September 25, 2006 |
| Orr Elementary School |
FM-200629967 9/25/06 First floor, Blue Stairwell. Repair or Replace lock on door, the right door cannot be secured on this stairwell. |
September 25, 2006 |
| Garfield ES |
FM-200630005 9/25/06 First Floor (new wing)/Custodial Closet (by Teachers Lounge entrance) - Snake out slop sink |
September 25, 2006 |
| Roosevelt High School |
FM-200629947 9/25/06 Remove pedistle pumps from the boiler room. |
September 25, 2006 |
| Duke Ellington School |
FM-200630012 9/25/06 Repair condensation leak from cooling tower on the roof. Note: The water is spilling over and leaking down into classrooms. |
September 25, 2006 |
| Woodson High School |
FM-200629945 9/25/06 Basement- Kitchen Repair/replace broken floor plug. It is out of the floor. |
September 25, 2006 |
| Eliot Junior High School |
FM-200629928 9/25/06 Eliot Roof drains over the boiler room Unstop roof drains over top of the boiler room |
September 25, 2006 |
| Shepherd ES |
FM-200629934 9/25/06 Outside - Pieces of wall and concrete falling to ground from around school (falling hazards) |
September 25, 2006 |
| Stanton Elementary School |
FM-200629949 9/25/06 Annex- A9 Music Room Replace door hinge. Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Thomas Johnson (RG 09/28/06) |
September 25, 2006 |
| Montgomery ES |
FM-200629951 9/25/06 Re-key all classroom locks to a new master system. * no keys to classrooms* |
September 25, 2006 |
| Coolidge High School |
FM-200630008 9/25/06 Survey leaky roof over class 317, 325 and 329, this leak is causing damage to plaster ceiling. Asbestos Code A - Clear for repairs on 01/17/07. Tidewater - Roger Small (RG 01/19/07) |
September 25, 2006 |
| Coolidge High School |
FM-200630007 9/25/06 1.) Survey damages plaster ceiling & wall for asbestos in classrooms 317, 325 and 328. 2.) Survey for lead paint on walls & ceiling, on pipe in class room 317, 325 and 329. Lead & Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Roger Small (RG 09/29/06) SEE ASSESSMENTS |
September 25, 2006 |
| Coolidge High School |
FM-200629938 9/25/06 Boiler Room/Leak - Cemical tank |
September 25, 2006 |
| Cardozo High School |
FM-200630016 9/25/06 Rear of School/ Near Stadium Re-align doors. They cannot secure the exit doors. |
September 25, 2006 |
| John Burroughs ES |
FM-200629989 9/25/06 Replace pieces of a cast iron grate. |
September 25, 2006 |
| Browne Junior High School |
FM-200629987 9/25/06 2nd Floor- Room 237 Replace door hinges on the door. Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Carlos Vera (RG 09/28/06) |
September 25, 2006 |
| Browne Junior High School |
FM-200629986 9/25/06 2nd Floor- Room 216 Repair leaking pipe under the sink. |
September 25, 2006 |
| Browne Junior High School |
FM-200629984 9/25/06 Cafeteria- Replace door hinges on the cafeteria door. Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Carlos Vera (RG 09/28/06) |
September 25, 2006 |
| Browne Junior High School |
FM-200629983 9/25/06 1st Floor- New Wing Install door check on the exit door near Room 119. |
September 25, 2006 |
| Browne Junior High School |
FM-200629976 9/25/06 Auditorium- Replace light bulbs. |
September 25, 2006 |
| Ronald H. Brown MS |
FM-200629964 9/25/06 First, floor/Near Strairwell # 8. Repair leaky water fountain, water is continuously leaking on the floor. |
September 25, 2006 |
| Walker-Jones EC |
FM-200629943 9/25/06 Second Floor/Boy's Restroom - Urinal cracked and leaking. |
September 25, 2006 |
| Walker-Jones EC |
FM-200629944 9/25/06 Third Floor/Rm. 303 - Lock broken, replace the lock. |
September 25, 2006 |
| Walker-Jones EC |
FM-200629946 9/25/06 First Floor/Boy's Restroom - Leaking toilet in the second stall. |
September 25, 2006 |
| Walker-Jones EC |
FM-200629948 9/25/06 First Floor/Rm. 103 - Repair ceiling Asbestos Code A - Clear for repairs on 09/27/06 Tidewater - Cornell Parks (RG 10/03/06) |
September 25, 2006 |
| Walker-Jones EC |
FM-200629952 9952 9/25/06 First Floor/Principal Office - Repair toilet, it keeps running. |
September 25, 2006 |
| Walker-Jones EC |
FM-200629956 9956 9/25/06 Third Floor/Rm. 311 - Door hardware - Door off hinge |
September 25, 2006 |
| Walker-Jones EC |
FM-200629960 9960 9/25/06 First Floor/Pre-Kindergarten Area - Toilet leaking around the bottom in the third stall. |
September 25, 2006 |
| Ballou Senior High School |
FM-200629988 9/25/06 Staff Bathroom- Repair cold water fixture; water leaks from the fixture. |
September 25, 2006 |
| Adams Elementary School |
FM-200630075 9/26/06 3rd Floor- Math Room Repair/replace water damaged ceiling. Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Thomas Johnson (RG 09/29/06) |
September 26, 2006 |
| Wilson High School |
FM-200630072 9/26/06 1st Floor- Room 108/College Bureau Install 3 electrical wall outlets. Asbestos Code A - Clear for repairs on 09/29/06. Tidewater - Shamika Parker (RG 10/02/06) |
September 26, 2006 |
| Adams Elementary School |
FM-200630074 9/26/06 3rd Floor- Math Room Repair/replace water damaged walls. Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Thomas Johnson (RG 09/29/06) |
September 26, 2006 |
| Deal Junior High School |
FM-200630035 9/26/06 Second Floor/Balcony - Replace missing door handle |
September 26, 2006 |
| Kelly Miller MS |
FM-200630024 9/26/06 Rm. 201 - Broken Window Asbestos Code A - Clear For Repairs On 06/26/06. Tidewater - Carlos Vera (RG 09/28/06) |
September 26, 2006 |
| Stanton Elementary School |
FM-200630050 9/26/06 Repair damage plaster ceiling that's coming from roof leak into room 106. HA 016 Plaster No Asbestos HA 716 Brown Coat with HA016 Code A-clear for repair by DCPS Charles Buchanan on 9-26-06 |
September 26, 2006 |
| Spingarn High School |
FM-200630061 9/26/06 Second floor, Room 204. Repair or replace floor outlet. Need a metal plate to cover exposed wires. |
September 26, 2006 |
| Francis Junior High School |
FM-200630081 9/26/06 2nd Floor- Hallway by Room 107 Supply electricity for water cooler. Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Thomas Johnson (RG 09/29/06) |
September 26, 2006 |
| Stanton Elementary School |
FM-200630051 9/26/06 Unclog roof drain over top of room 106, 105, & at Front Entrance. Code A-clear for repair by DCPS Charles Buchanan 9-26-06 |
September 26, 2006 |
| Francis Junior High School |
FM-200630080 9/26/06 3rd Floor- Room 312 Install cover plate around fan switch. Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Thomas Johnson (RG 09/29/06) |
September 26, 2006 |
| Francis Junior High School |
FM-200630077 9/26/06 1st Floor- Outside of Room 114 Replace light fixture. Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Thomas Johnson (RG 09/29/06) |
September 26, 2006 |
| Shaw JHS |
FM-200630148 9/26/06 R.I.ave side of school welder needed for outside gate leading to pool area. |
September 26, 2006 |
| Burrville Elementary School |
FM-200630021 9/26/06 Burrville Boiler Room Repair or replace burnt out starter coil to condenser pump |
September 26, 2006 |
| Eastern High School |
FM-200630041 9/26/06 Provide keys for the following areas: - 322, 226, 239, 167, Bathroom keys, Auditorium (key is broken off in the lock). |
September 26, 2006 |
| Marshall Educational Center |
FM-200630039 9/26/06 Basement/Gym - Interior and Exterior Doors Need Panic Bars Replaced. |
September 26, 2006 |
| Deal Junior High School |
FM-200630037 9/26/06 Second Floor/Rm. 200, 215, 213, 205A, 205B - Repair handle to classroom doors, handles are hanging down, unable to secure the classrooms. |
September 26, 2006 |
| Patterson ES |
FM-200630060 9/26/06 South Capitol St. - Cut + remove fallen tree branch |
September 26, 2006 |
| Wilson High School |
FM-200630071 9/26/06 Basement- Room B-19 Install 4 electrical wall outlets. Asbestos Code A - Clear for repairs on 09/29/06. Tidewater - Shamika Parker (RG 10/02/06) |
September 26, 2006 |
| Dunbar High School |
FM-200630159 9/27/06 Ground Floor- Home Economics Area Restore electrical power to the classroom. |
September 27, 2006 |
| Burrville Elementary School |
FM-200630125 9/27/06 Kitchen- Replace faucet on the sink. |
September 27, 2006 |
| Stanton Elementary School |
FM-200630109 9/27/06 Annex- A/2 Mrs. Forester Replace ballast |
September 27, 2006 |
| Stanton Elementary School |
FM-200630111 9/27/06 Annex- A/9 Music Room Replace ballast and repair lights. |
September 27, 2006 |
| Stanton Elementary School |
FM-200630115 9/27/06 Annex- A3 Art Class Replace hinge on the left side of the door. Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Kenny Long (RG 09/29/06) |
September 27, 2006 |
| Gage-Eckington ES |
FM-200630173 9/27/06 Install exterior lights around the school perimeter. |
September 27, 2006 |
| Wilkinson ES |
FM-200630195 9/27/06 1st Floor- Room 92 Replace door closer. Asbestos Code A - Clear for repairs on 09/29/06. Tidewater - Shamika Parker (RG 10/02/06) |
September 27, 2006 |
| Randle-Highlands ES |
FM-200630090 9/27/06 No Water In The Restrooms (Boy's + Girls) On All Floors. |
September 27, 2006 |
| Thomas Elementary School |
FM-200630144 9/27/06 THOMAS N. Boiler # 2 leaking draft port in firebox |
September 27, 2006 |
| Draper Elementary School |
FM-200630138 9/27/06 DRAPER boiler room Replace light fixtures in boiler room. Inadequate lighting to complete repairs to boilers SCHOOL WILL HAVE NO HEAT IF FIXTURES CAN NOT BE REPAIR. |
September 27, 2006 |
| Backus Middle School |
FM-200630119 9/27/06 2nd & 3rd Floors- Rooms 314, 304, 213, & 211 Repair concrete walls in the hall around the door frames. Note: Door frames are extremely loose. Asbestos Code A - Clear for repairs on 09/28/06. Tidewater - Kenny Long (RG 09/29/06) |
September 27, 2006 |
| Kimball Elementary School |
FM-200630116 9/27/06 1st Floor- Room 106 Repair heating unit. - Repair or replace leaking univent coil. |
September 27, 2006 |
| Kenilworth ES |
FM-200630137 9/27/06 Kenillworth Merchanical Room Boiler #1 repair or replace automatic make up feed switch, switch not working properly. Also Boiler #2 replace bulb on control panel for power on. |
September 27, 2006 |
| Wilkinson ES |
FM-200630194 9/27/06 2nd Floor- Room 180/Boys Restroom Repair/replace exhaust fan. |
September 27, 2006 |
| Gibbs Elementary School |
FM-200630176 9/27/06 1st Floor- Speech Room B Install a new lock and supply keys. |
September 27, 2006 |
| Stuart-Hobson Middle School |
FM-200630139 9/27/06 HOBSON S boiler room Retube boiler # 1 |
September 27, 2006 |
| Plummer Elementary School |
FM-200630175 9/27/06 1st Floor- Room 37 Remove floor check and install hinge and door check. Asbestos Code A - Clear for repairs on 09/29/06. Tidewater - Shamika Parker (RG 10/02/06) |
September 27, 2006 |
| Eaton Elementary School |
FM-200630091 9/27/06 2nd Floor- West Side/Room 206 Repair/replace plaster as needed inside and outside of this classroom. Lead & Asbestos Code A - Clear for repairs on 10/03/06. Tidewater - Roger Small\Shamika Parker (RG 10/24/06) |
September 27, 2006 |
| Kramer Middle School |
FM-200630132 9/27/06 KRAMER boiler room Boiler # 3 repair refractory around fire door per boiler inspector. |
September 27, 2006 |
| Plummer Elementary School |
FM-200630174 9/27/06 1st Floor- Boiler Room Re-align restroom door. |
September 27, 2006 |
| School WW High School |
FM-200630133 9/27/06 1st Floor- Hallway near Room 105 Repair/replace drinking fountain. |
September 27, 2006 |
| Plummer Elementary School |
FM-200630127 9/27/06 First Floor/Hallway By Rm. 38 - Button on water gets stuck, repair or replace. |
September 27, 2006 |
| Benjamin Banneker Academic HS |
FM-200630197 9/27/06 3rd Floor- Room 315 Open door and change the lock on the closet door. |
September 27, 2006 |
| Benjamin Banneker Academic HS |
FM-200630196 9/27/06 1st & 2nd Floors- Repair leaking water coolers. |
September 27, 2006 |
| Garrison ES |
FM-200630192 9/27/06 1st & 2nd Floors- Repair leaking water coolers. |
September 27, 2006 |
| Davis Elementary School |
FM-200630198 9/27/06 1st Floor- Room 101 Bathroom Repair bolts on toilets. |
September 27, 2006 |
| Spingarn High School |
FM-200630086 9/27/06 Thru-Out The Building - Key the bldg. to master key |
September 27, 2006 |
| Turner Elementary School |
FM-200630181 9/27/06 2nd Floor- Custodianal Closet Repair/replace light. |
September 27, 2006 |
| Turner Elementary School |
FM-200630190 9/27/06 1st Floor- Rooms 103, 105, 107 Scrape, plaster, and paint the ceilings. Lead & Asbestos Code A - Clear for repairs on 10/17/06. Tidewater - Roger Small/Shamika Parker (RG 10/19/06) SEE ASSESSMENTS |
September 27, 2006 |
| Dunbar High School |
FM-200630157 9/27/06 Restore electrical power to the stadium storage room. |
September 27, 2006 |
| Simon Elementary School |
FM-200630230 9/28/06 2nd Floor- Room 207 Counselor's Office Repair/replace locks on file cabinets. |
September 28, 2006 |
| Davis Elementary School |
FM-200630237 9/28/06 1st Floor- Install security screens for exterior doors in the following areas. Rooms: 115, 117, 119, and along the Hallway. Asbestos Code A - Clear for repairs on 09/29/06. Tidewater - Kenny Long (RG 10/02/06) |
September 28, 2006 |
| Anacostia Senior High School |
FM-200630605 9/28/06 Replace supply line on sink. |
September 28, 2006 |
| Coolidge High School |
FM-200630217 9/28/06 2nd Floor- Teachers Bathroom Repair sink; it is hanging off of the wall. |
September 28, 2006 |
| Coolidge High School |
FM-200630216 9/28/06 3rd Floor- Boys Bathroom Repair sink; it is hanging off of the wall. |
September 28, 2006 |
| Anacostia Senior High School |
FM-200630292 9/28/06 Replace 277 ballast in two lights in kitchen and install 4 recessed lights in cafeteria. |
September 28, 2006 |
| Garfield ES |
FM-200630245 9/28/06 GARFIELD Room D - 107 Repair heat pump in room 107 on off switch not operating Mod. FH884389 BTU -C- 14100 |
September 28, 2006 |
| Anacostia Senior High School |
FM-200630289 9/28/06 Frame and pour walk area 20'X 4'in rear ofd building. |
September 28, 2006 |
| Thomas Elementary School |
FM-200630218 9/28/06 Thomas Boiler Room Boiler #1 Replace leaking tube. Boiler #1 Replace defective 1-1/2" gate valve on Bottom Blowdown line. |
September 28, 2006 |
| Anacostia Senior High School |
FM-200630269 9/28/06 Unclog toliets,replace supply line on sinks in women's lavatory and replace wax ring in men's LAVATORY |
September 28, 2006 |
| Wilson High School |
FM-200630221 9/28/06 Wilson, W. Boiler Room Replace defective firerye programmer to burner #2 |
September 28, 2006 |
| Kramer Middle School |
FM-200630206 9/28/06 First Floor/Lobby Entrance - Fire mesh glass broken out. Asbestos Code A - Clear for repairs on 09/29/06. Tidewater - Kenny Long (RG 10/02 |